AGUSTUS 2017 SEPTEMBER 2017 OKTOBER 20
MINGGU KE
URAIAN PEKERJAAN % tase
1 2 3 4 5 6 7 8 9 10

A START / KONTRAK
B PEKERJAAN PERSIAPAN 2.199% 2.199
C PEKERJAAN PONDASI & TANAH 12.215% 6.107 6.107
D PEKERJAAN STRUKTUR 39.125% 9.781 9.781 9.781 9.781
E PEKERJAAN ATAP & PLAFOND 13.169% 6.585 6.585
F PEKERJAAN PASANGAN 14.724% 4.908 4.908 4.908
G PEKERJAAN KUSEN PINTU & JENDELA 7.441% 3.721 3.721
H PEKERJAAN PENGECATAN 4.410%
i PEKERJAAN PLUMBING & SANITAIR 1.952% 0.976
J PEKERJAAN LISTRIK 4.764% 1.588 1.588
M SERAH TERIMA - I

Bobot Rencana 100.000% 2.199 6.107 15.889 9.781 9.781 16.366 11.493 4.908 10.217 6.285
Bobot Realisasi
Akumulasi Rencana 2.199 8.307 24.195 33.977 43.758 60.123 71.616 76.524 86.741 93.026
Akumulasi Realisasi
OKTOBER 2017 KET
MINGGU KE
11 12

100

90

80

70

60

50

40

2.205 2.205 30

0.976 20

1.588 10

4.769 2.205

97.795 100.000

BANDUNG MAJALAYA 2017


REKAPITULASI RENCANA ANGGARAN BIAYA (RAB
Pekerjaan : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
Pemberi Tugas : KEMNAKER
Tahun Anggaran : 2017

NO ITEM PEKERJAAN

A PEKERJAAN PERSIAPAN
B PEKERJAAN PONDASI & TANAH
C PEKERJAAN STRUKTUR
D PEKERJAAN ATAP & PLAFOND
E PEKERJAAN PASANGAN
F PEKERJAAN KUSEN PINTU & JENDELA
G PEKERJAAN PENGECATAN
H PEKERJAAN PLUMBING & SANITAIR
I PEKERJAAN LISTRIK
J LAIN - LAIN

TOTAL
PEMBULATAN
TERBILANG : "LIMA RATUS JUTA RUPIAH
ANA ANGGARAN BIAYA (RAB)
AN BLK KOMUNITAS WAHDATUT TAUHID

TOTAL

10,905,932.00
60,570,986.63
194,010,903.97
65,302,597.00
73,015,290.23
36,900,000.00
21,867,253.88
9,680,243.20
23,625,000.00
4,000,000.00

499,878,206.91
500,000,000.00

BANDUNG MAJALAYA 2017


BILL OF QUANTITY

PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID


PEMBERI TUGAS : KEMNAKER
TAHUN : 2017

HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SAT.
( Rp. )

A PEKERJAAN PERSIAPAN
1 Papan Proyek 1.00 unt Rp 350,000.00
2 Pek. Pengukuran dan Bowplank 52.00 m' Rp 85,691.00
3 Pek. Listrik & Air Kerja 1.00 ls Rp 2,500,000.00
4 Pek. Laporan & Dokumentasi 1.00 ls Rp 3,600,000.00
B PEKERJAAN PONDASI & TANAH
1 Pek. Galian Tanah Pondasi 66.67 m3 Rp 44,106.25
2 Pek. Urug Tanah Kembali 22.22 m3 Rp 45,712.50
3 Pek. Urug Tanah Peninggian Peil Lantai (t = 10 cm) 10.70 m3 Rp 113,256.25
4 Pek. Cerucuk (L = 2m) 64.00 bh Rp 60,000.00
5 Pek. Pasir Urug
- Bawah Pondasi 11.59 m3 Rp 115,642.50
- Bawah Lantai 15.65 m3 Rp 115,642.50
5 Pek. Pondasi Tapak P1 (100x100x20-40)
- Beton K-225 6.05 m3 Rp 682,213.90
- Pembesian 841.58 kg Rp 6,536.00
- Bekisting 26.88 m2 Rp 272,182.00
6 Pek. Pondasi Aanstamping 16.01 m 3
Rp 222,487.00
7 Pek. Pondasi Batu Belah P2 58.70 m3 Rp 294,163.00
8 Pek. Sloof Beton (20/30)
- Beton K-225 3.51 m3 Rp 682,213.90
- Pembesian 736.62 kg Rp 6,536.00
- Bekisting 35.10 m2 Rp 97,831.88
C PEKERJAAN STRUKTUR
C.1 STRUKTUR BETON
1 Pek. Kolom Beton K1 (30/30)
- Beton K-225 6.48 m3 Rp 682,213.90
- Pembesian 1,071.50 kg Rp 6,536.00
- Bekisting 86.40 m2 Rp 180,643.00
2 Pek. Kolom Praktis KP (15/15)
HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SAT.
( Rp. )

- Beton K-225 0.54 m3 Rp 682,213.90


- Pembesian 138.40 kg Rp 6,536.00
- Bekisting 14.40 m2 Rp 180,643.00
3 Pek. Balok Beton B1 (20/30)
- Beton K-225 3.33 m3 Rp 682,213.90
- Pembesian 1,085.92 kg Rp 6,536.00
- Bekisting 44.40 m2 Rp 193,571.00
4 Pek. Balok Beton Lintel RB (15/15)
- Beton K-225 1.80 m3 Rp 682,213.90
- Pembesian 547.73 kg Rp 6,536.00
- Bekisting 31.20 m2 Rp 193,571.00
5 Pek. Ramp Beton T = 10 cm
- Beton K-175 0.35 m3 Rp 924,073.19
- Pembesian 42.24 kg Rp 6,536.00
- Bekisting 0.69 m 2
Rp 221,555.17
C.2 STRUKTUR BAJA
1 WF 200x100x6x9 + zinchromate 2,946.99 kg Rp 26,400.00
2 H 100x100x6x8 + zinchromate 459.76 kg Rp 26,400.00
3 CNP 125x50x20x2,3 + zinchromate 1,189.11 kg Rp 26,400.00
4 Base Plate t = 16 mm 186.50 kg Rp 26,400.00
5 Plat Buhul t = 12 mm 36.46 kg Rp 26,400.00
6 Stiffner Plate t = 8 mm 59.74 kg Rp 26,400.00
7 Ikatan Angin besi dia. 12 mm + asesories 42.80 kg Rp 26,400.00
8 Sagrod besi dia. 8 mm 8.53 kg Rp 6,536.00
9 Angkur D 19 64.00 bh Rp 20,000.00
10 Baut M16 152.00 bh Rp 15,000.00
D PEKERJAAN ATAP & PLAFOND
1 Atap Spandek t = 0.35 mm 252.06 m2 Rp 75,000.00
2 Atap Bubungan & Jurai 21.60 m' Rp 65,000.00
3 Pekerjaan Talang BJLS 6.84 m' Rp 46,500.00
4 Listplank GRC 60.62 m' Rp 60,000.00
5 Plafond Gipsum 9 mm + Rangka Hollow 4/4 ; t = 0.35 136.49 m 2
Rp 190,000.00
6 Plafond Calsiboard 4,5 mm + Rangka 59.51 m 2
Rp 214,000.00
7 Lis Gipsum 5 cm 94.85 m' Rp 25,000.00
E PEKERJAAN PASANGAN
1 Pasangan Dinding Bata 134.65 m2 Rp 89,073.00
2 Plester + Acian 269.30 m 3
Rp 62,500.00
3 Pasangan Rolaag Bata 19.80 m' Rp 60,000.00
HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SAT.
( Rp. )

4 Pekerjaan Rabat Beton t = 5 cm bawah lantai keramik 7.82 m3 Rp 761,134.80


5 Pekerjaan Rabat Beton t = 5 cm keliling bang lbr = 60 cm 2.04 m3 Rp 761,134.80
6 Pekerjaan Meja Beton Wastafel t = 8 cm 0.10 m3 Rp 2,600,000.00
7 Pasangan Keramik Lantai 40/40 Polished 136.40 m 2
Rp 93,267.00
8 Pasangan Keramik Lantai 30/30 Polished 52.00 m2 Rp 128,300.00
9 Pasangan Keramik Lantai 20/20 Unpolished 3.04 m 2
Rp 130,000.00
10 Pasangan Keramik Bak & Meja Wastafel 20/20 Polished 1.77 m2 Rp 130,000.00
11 Pasangan Keramik Dinding 30/60 Polished 5.29 m 2
Rp 150,000.00
12 Pas Dinding 2 Muka Partisi GRC + R. Hollow t = 0.50 50.59 m2 Rp 260,000.00
13 Pasangan Batu Alam Candi Kolom Entrace 5.60 m 2
Rp 50,000.00
14 Pek. Logo & Tulisan 1.00 ls Rp 1,000,000.00
F PEKERJAAN KUSEN PINTU & JENDELA
1 Kusen/Pintu type P1 1.00 unt Rp 5,250,000.00
2 Kusen/Pintu type P2 3.00 unt Rp 2,200,000.00
3 Kusen/Pintu type P3 (Spandrel) 1.00 unt Rp 1,500,000.00
4 Kusen/Jendela type J1 1.00 unt Rp 1,800,000.00
5 Kusen/Jendela type J2 8.00 unt Rp 2,400,000.00
6 Kusen/Jendela type J3 1.00 unt Rp 1,750,000.00
7 Kusen/Jendela type BV 1.00 unt Rp 800,000.00
G PEKERJAAN PENGECATAN
1 Pek. Pengecatan Dinding Interior 225.72 m2 Rp 35,000.00
2 Pek. Pengecatan Dinding Exterior 134.65 m 2
Rp 45,300.00
3 Pek. Pengecatan Plafond 196.00 m2 Rp 35,000.00
4 Pek. Pengecatan Listplank 18.19 m 2
Rp 55,400.00
H PEKERJAAN PLUMBING & SANITAIR
1 Instalasi Pipa PVC AW 4" 16.00 m' Rp 77,845.00
2 Instalasi Pipa PVC AW 2" 12.00 m' Rp 45,000.00
3 Instalasi Pipa PVC AW 3/4" 20.00 m' Rp 33,736.16
4 Instalasi Pipa PVC AW 1/2" 15.00 m' Rp 28,000.00
5 Septic Tank dan Rembesan 1.00 unt Rp 3,000,000.00
6 Pemasangan Closed Jongkok 1.00 bh Rp 350,000.00
7 Pemasangan Kran Air 2.00 bh Rp 25,000.00
8 Pemasangan Wastafel + Kran 2.00 bh Rp 1,500,000.00
9 Pemasangan Cermin Wastafel 100x200 1.00 unt Rp 400,000.00
I PEKERJAAN LISTRIK
1 Penyambungan Daya Listrik 3,500.00 VA Rp 3,500,000.00
2 Perijinan Sertifikat Layak Operasi (SLO) 3,500.00 VA Rp 1,500,000.00
3 Panel Listrik 1.00 unt Rp 500,000.00
HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SAT.
( Rp. )

4 Pek. Instalasi Kabel Feeder NYY 4x10 mm2 2.00 m' Rp -


5 Pek. Instalasi Penerangan & Power NYM 3x2,5 mm2 + conduit 59.00 ttk Rp 200,000.00
6 Pemasangan Lampu TKO 2x36W 16.00 bh Rp 125,000.00
7 Pemasangan lampu E27 ESS 8W + fitting 2.00 BH Rp 45,000.00
8 Pemasangan Lampu Baret Kotak 22W 7.00 bh Rp 95,000.00
9 Pemasangan Saklar Engkle 2.00 bh Rp 35,000.00
10 Pemasangan Saklar Double 4.00 bh Rp 35,000.00
11 Pemasangan Stop Kontak Single 4.00 bh Rp 35,000.00
12 Pemasangan Stop Kontak Ganda 16.00 bh Rp 45,000.00
13 Grounding (max 2 Ohm) 1.00 lot Rp 2,500,000.00
L LAIN - LAIN
1 IMB 1.00 dok Rp 3,000,000.00
2 Transport 2.00 paket Rp 500,000.00
JUMLAH TOTAL
DI BULATKAN
OF QUANTITY

JUMLAH HARGA
( Rp. )

Rp 10,905,932.00
Rp 350,000
Rp 4,455,932
Rp 2,500,000
Rp 3,600,000
Rp 60,570,986.63
Rp 2,940,387.26
Rp 1,015,823.18
Rp 1,211,841.88
Rp 3,840,000.00

Rp 1,340,065.29
Rp 1,809,226.91

Rp 4,126,029.67
Rp 5,500,570.75
Rp 7,316,252.16
Rp 3,561,571.90
Rp 17,266,191.45

Rp 2,394,570.79
Rp 4,814,556.41
Rp 3,433,898.99
Rp 194,010,903.97

Rp 4,420,746.07
Rp 7,003,351.48
Rp 15,607,555.20
JUMLAH HARGA
( Rp. )

Rp 368,395.51
Rp 904,587.75
Rp 2,601,259.20

Rp 2,271,772.29
Rp 7,097,542.10
Rp 8,594,552.40

Rp 1,227,985.02
Rp 3,579,971.98
Rp 6,039,415.20

Rp 325,273.76
Rp 276,080.64
Rp 153,138.93

Rp 77,800,485.31
Rp 12,137,558.40
Rp 31,392,414.24
Rp 4,923,600.00
Rp 962,500.00
Rp 1,577,033.33
Rp 1,129,920.00
Rp 55,765.15
Rp 1,280,000.00
Rp 2,280,000.00
Rp 65,302,597.00
Rp 18,904,275.00
Rp 1,404,000.00
Rp 318,060.00
Rp 3,637,200.00
Rp 25,933,100.00
Rp 12,734,712.00
Rp 2,371,250.00
Rp 73,015,290.23
Rp 11,993,821.97
Rp 16,831,450.00
Rp 1,188,000.00
JUMLAH HARGA
( Rp. )

Rp 5,953,976.97
Rp 1,552,714.99
Rp 249,600.00
Rp 12,721,618.80
Rp 6,671,600.00
Rp 394,875.00
Rp 229,612.50
Rp 794,100.00
Rp 13,153,920.00
Rp 280,000.00
Rp 1,000,000.00
Rp 36,900,000.00
Rp 5,250,000.00
Rp 6,600,000.00
Rp 1,500,000.00
Rp 1,800,000.00
Rp 19,200,000.00
Rp 1,750,000.00
Rp 800,000.00
Rp 21,867,253.88
Rp 7,900,102.00
Rp 6,099,717.48
Rp 6,859,930.00
Rp 1,007,504.40
Rp 9,680,243.20
Rp 1,245,520.00
Rp 540,000.00
Rp 674,723.20
Rp 420,000.00
Rp 3,000,000.00
Rp 350,000.00
Rp 50,000.00
Rp 3,000,000.00
Rp 400,000.00
Rp 23,625,000.00
Rp 3,500,000.00
Rp 1,500,000.00
Rp 500,000.00
JUMLAH HARGA
( Rp. )

Rp -
Rp 11,800,000.00
Rp 2,000,000.00
Rp 90,000.00
Rp 665,000.00
Rp 70,000.00
Rp 140,000.00
Rp 140,000.00
Rp 720,000.00
Rp 2,500,000.00
Rp 4,000,000.00
Rp 3,000,000.00
Rp 1,000,000.00
Rp 499,878,206.91
Rp 500,000,000.00
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

PEKERJAAN BONGKARAN

1 1 m2 Bongkaran penutup atap


Upah
0.0400 Oh Pekerja

2 1 Kg Bongkaran Rangka atap baja


Upah
0.0400 Oh Pekerja
0.0035 Oh Tukang besi

3 1 m2 Bongkaran Rangka Atap Kayu


Upah
0.0700 Oh Pekerja
0.1000 Oh Tukang kayu

4 1 m2 Bongkaran Talang Atap


ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

Upah
0.0500 Oh Pekerja
0.1000 Oh Tukang besi

lebar talang = 0.3 m


1 m' Bongkaran Talang Atap

5 1 m3 Bongkaran beton bertulang


Upah
6.6670 Oh Pekerja

6 1 m2 Bongkaran Partisi 2 muka gipsum (+ alumunium/kaca)


Upah
0.0600 Oh Pekerja
0.1200 Oh Tukang aluminum/kaca
0.0100 Oh Kepala tukang alumunium/kaca

6 1 m2 Bongkaran dinding bata


Upah
0.2000 Oh Pekerja
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

7 1 m2 Bongkaran plesteran
Upah
0.0500 Oh Pekerja

9 1 m2 Bongkaran plafond
Upah
0.1250 Oh Pekerja

10 1 m2 Bongkaran lantai keramik


Upah
0.1000 Oh Pekerja

11 1 m3 Bongkaran kusen
Upah
0.1000 Oh Pekerja
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

12 1 m2 Bongkaran daun pintu


Upah
0.1000 Oh Pekerja

13 1 m2 Bongkaran daun jendela kaca / kaca


Upah
0.0300 Oh Pekerja

PEKERJAAN GALIAN

1 1 m3 Galian Untuk Tanah Biasa sedalam MAX 1 m


Upah An. SNI ( Revisi ) 6.1.1
0.9500 Oh Pekerja

2 1 m3 Galian Untuk Tanah Biasa sedalam MAX 2 m


Upah An. SNI ( Revisi ) 6.2.1
1.2000 Oh Pekerja
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

3 1 m3 Galian Untuk Tanah Lumpur sedalam MAX 1 m


Upah An. SNI ( Revisi ) 6.3.1
1.5000 Oh Pekerja

4 1 m3 Urugan kembali
Bahan - m3 Tanah Urug

Upah An. SNI ( Revisi ) 6.9.1


0.2500 Oh Pekerja

5 1 m3 Urugan pasir dengan pasir urug.


Bahan An. SNI ( Revisi ) 6.11.1
1.1000 m3 Pasir urug

Upah An. SNI ( Revisi ) 6.11.2


0.5000 Oh Pekerja

6 1 m3 Urugan tanah pilihan


ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

Bahan An. SNI ( Revisi ) 6.11.1


1.2000 m3 Tanah campur

Upah An. SNI ( Revisi ) 6.11.2


0.2500 Oh Pekerja

7 1 m3 Pemadatan tanah
Upah An. SNI ( Revisi ) 6.11.2
0.2500 Oh Pekerja

Alat
0.0210 jam Sewa Stamper

1 m2 Pemadatan tanah

PEKERJAAN BETON

1 1 m3 beton mutu f'c = 7,4 Mpa (K100), slump (12 +/- 2), w/c = 0,87 sitemix
Bahan An. SNI DT-1-0009-2007
205.000 kg Portland Cement
0.621 m3 Pasir Beton
0.740 m3 Kerikil (maximum 30 mm)
215.000 ltr Air
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

Upah An. SNI DT-1-0009-2007


1.650 Oh Pekerja
0.275 Oh Tukang batu

2 1 m3 beton mutu f'c = 14.5 Mpa (K175), slump (12 +/- 2), w/c = 0.66 sitemix
Bahan
326.000 kg Portland Cement
0.543 m3 Pasir Beton
0.762 m3 Kerikil (maximum 30 mm)
215.000 ltr Air

Upah
1.650 Oh Pekerja
0.275 Oh Tukang batu

3 1 m3 beton mutu f'c = 19.3 Mpa (K225), slump (12 +/- 2), w/c = 0.58
Bahan
371.000 kg Portland Cement
0.499 m3 Pasir Beton
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

0.776 m3 Kerikil (maximum 30 mm)


215.000 ltr Air

Upah
1.650 Oh Pekerja
0.275 Oh Tukang batu

4 1 m3 beton mutu f'c = 21.7 Mpa (K250), slump (12 +/- 2), w/c = 0.56
Bahan
384.000 kg Portland Cement
0.494 m3 Pasir Beton
0.770 m3 Kerikil (maximum 30 mm)
215.000 ltr Air

Upah
1.650 Oh Pekerja
0.275 Oh Tukang batu

5 1 m3 beton Ready Mix mutu K-250


ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

Bahan
1.000 m3 Beton Ready Mix mutu K-250

Upah
0.800 Oh Pekerja
0.400 Oh Tukang batu

Alat
1.000 m3 Sewa Alat Concrete Pump

6 Pembesian 10 kg dengan besi ulir


Pembesian 1 kg
Bahan
10.500 kg Besi Ulir
0.150 kg Kawat Beton

Upah
0.070 Oh Pekerja
0.070 Oh Tukang besi
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

7 Pembesian 10 kg dengan besi polos


Pembesian 1 kg
Bahan
10.500 kg Besi Polos
0.150 kg Kawat Beton

Upah
0.070 Oh Pekerja
0.070 Oh Tukang besi

8 1 M2 Pembesian Wiremesh M10-150 1 lapis


Bahan
0.088 Lbr Wiremesh M10
10.000 bh Beton decking

Upah
0.070 Oh Pekerja
0.070 Oh Tukang besi
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

9 1 M2 Pembesian Wiremesh M8-150 1 lapis


Bahan
0.088 Lbr Wiremesh M6
10.000 bh Beton decking

Upah
0.070 Oh Pekerja
0.070 Oh Tukang besi

10 1 M2 Pasangan Bondex
Bahan
1.050 m2 Bondex

Upah
0.050 Oh Pekerja
0.050 Oh Tukang besi

Alat
1.000 Ls Stootwerk (perancah)
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

11 1 M3 Perancah
Bahan
1.100 m3 Kayu kelas III
0.400 kg Paku 5 cm - 10 cm

Penggunaan Bekisting dipakai 2x

Upah
0.660 Oh Pekerja
0.330 Oh Tukang Kayu

12 Memasang 1 m2 bekisting untuk pondasi


Bahan
0.040 m3 Kayu kelas III
0.100 kg Paku 5 cm - 10 cm
0.100 ltr Minyak Bekisting

Penggunaan Bekisting dipakai 2x

Upah
0.520 Oh Pekerja
0.260 Oh Tukang Kayu
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

13 Memasang 1 m2 bekisting untuk Sloof


Bahan
0.045 m3 Kayu kelas III
0.300 kg Paku 5 cm - 10 cm
0.100 ltr Minyak Bekisting

Penggunaan Bekisting dipakai3x

Upah
0.520 Oh Pekerja
0.260 Oh Tukang Kayu

14 Memasang 1 m2 bekisting untuk Kolom


Bahan
0.040 m3 Kayu kelas III
0.400 kg Paku 5 cm - 10 cm
0.200 ltr Minyak Bekisting
0.015 m3 Balok Kayu Kelas II
0.350 lbr Plywood tebal 9 mm
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

2.000 btg Dolken kayu Galam, f (8-10), Panjang 4 m

Penggunaan Bekisting dipakai 2x

Upah
0.660 Oh Pekerja
0.330 Oh Tukang Kayu

15 Memasang 1 m2 bekisting untuk Balok


Bahan
0.040 m3 Kayu kelas III
0.400 kg Paku 5 cm - 10 cm
0.200 ltr Minyak Bekisting
0.018 m3 Balok Kayu Kelas II
0.350 lbr Plywood tebal 9 mm
2.000 btg Dolken kayu Galam, f (8-10), Panjang 4 m

Penggunaan Bekisting dipakai 2x

Upah
0.660 Oh Pekerja
0.330 Oh Tukang Kayu
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

16 Memasang 1 m2 bekisting untuk Lantai


Bahan
0.040 m3 Kayu kelas III
0.400 kg Paku 5 cm - 10 cm
0.200 ltr Minyak Bekisting
0.015 m3 Balok Kayu Kelas II
0.350 lbr Plywood tebal 9 mm
6.000 btg Dolken kayu Galam, f (8-10), Panjang 4 m

Penggunaan Bekisting dipakai 2x

Upah
0.660 Oh Pekerja
0.330 Oh Tukang Kayu

17 Memasang 1 m2 bekisting untuk Dinding / Lisplang


Bahan
0.030 m3 Kayu kelas III
0.400 kg Paku 5 cm - 10 cm
0.200 ltr Minyak Bekisting
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

0.020 m3 Balok Kayu Kelas II


0.350 lbr Plywood tebal 9 mm
3.000 btg Dolken kayu Galam, f (8-10), Panjang 4 m

Penggunaan Bekisting dipakai 3x

Upah
0.660 Oh Pekerja
0.330 Oh Tukang Kayu

18 Memasang 1 m2 bekisting untuk Tangga


Bahan
0.030 m3 Kayu kelas III
0.400 kg Paku 5 cm - 10 cm
0.150 ltr Minyak Bekisting
0.015 m3 Balok Kayu Kelas II
0.350 lbr Plywood tebal 9 mm
2.000 btg Dolken kayu Galam, f (8-10), Panjang 4 m

Penggunaan Bekisting dipakai 3x

Upah
0.660 Oh Pekerja
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

0.330 Oh Tukang Kayu

19 Memasang 1 m' Kolom Praktis Beton Bertulang (11x11) cm


Bahan
0.002 m3 Kayu kelas III
0.010 kg Paku 5 cm - 10 cm
3.000 kg Besi Beton Polos
0.450 kg Kawat Beton
4.000 kg Portland Cement
0.006 m3 Pasir Beton
0.009 m3 Kerikil

Upah
0.180 Oh Pekerja
0.020 Oh Tukang Kayu
0.020 Oh Tukang Batu
0.020 Oh Tukang Besi

PEKERJAAN BAJA
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

1 1 Kg Fabrikasi Baja Profil WF , H Beam


Bahan
1.000 kg Baja profil
0.050 m2 Pengecatan zincromate

Upah
0.060 Oh Pekerja
0.060 Oh Tukang Las

2 1 Kg Fabrikasi Baja Profil CNP, SIKU L


Bahan
1.000 kg Baja profil CNP, Siku L
0.050 m2 Pengecatan zincromate

Upah
0.060 Oh Pekerja
0.060 Oh Tukang Las
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

3 1 kg Base Plate/Stiffner
Bahan
1.000 kg Base Plate, Stiffner

Upah
0.060 Oh Pekerja
0.060 Oh Tukang Baja/Las

4 1 m2 Zincromate Baja
Pengecatan Zincromate /kg Baja
Bahan
0.150 kg Cat Zincromate
0.100 lt Thinner
0.400 lmb Amplas
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

Upah
0.080 Oh Pekerja
0.080 Oh Tukang besi

6 1 bh Angkur Besi 19 mm
Bahan
1.000 bh Angkur dia 19 mm L=80 cm

Upah
0.080 Oh Pekerja

7 1 bh Baut Baja dia 16 mm


Bahan
1.000 bh Baut HTB dia 16 mm

Upah
0.050 Oh Pekerja
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

8 1 bh Baut Baja dia 12 mm


Bahan
1.000 bh Baut HTB dia 12 mm

Upah
0.050 Oh Pekerja

9 1 m2 Rangka Atap Baja Ringan


Bahan
1.488 m' Z-75, 0.70
2.232 m' Z-75, 0.70
28.000 bh Baut (Screw Driver)
1.600 bh Dynabolt
5.400 m' Reng 0.4

Upah
0.200 Oh Pekerja
0.450 Oh Tukang besi

Alat
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

1.000 ls Sewa Alat Bor

PEKERJAAN ATAP

1 M^1 Nok Genteng Metal Zincalume


Bahan
1.05 m' Nok genteng zincalume
0.05 Kg Paku biasa 2" - 5"

Upah
0.2 Oh Pekerja
0.1 Oh Tukang Kayu

1 M Flashing Metal Zincalume


Bahan
1.05 m' Flashing genteng metal
0.05 Kg Paku biasa 2" - 5"
10.8 Kg Semen abu-abu
0.032 m3 Pasir pasang
0.25 Kg Semen warna
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

Upah
0.2 Oh Pekerja
0.1 Oh Tukang Kayu

1 M2 Atap Corrugated Metal


Bahan
1.05 m2 Atap corrugated metal
0.03 Kg Paku biasa 2" - 5"

Upah
0.2 Oh Pekerja
0.1 Oh Tukang Kayu

1 M^1 Papan Lisplang GRC


Bahan An. SNI ( Revisi ) 6.50.1
1.050 m Lisplank GRC
0.05 Kg Paku biasa 2" - 5"

Upah An. SNI ( Revisi ) 6.50.2


0.11 Oh Pekerja
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

0.22 Oh Tukang kayu

1 M^1 Nok Genteng Metal Berpasir


Bahan
1.05 m' Nok genteng metal berpasir
0.05 Kg Paku biasa 2" - 5"

Upah
0.2 Oh Pekerja
0.1 Oh Tukang Kayu

1 M2 Atap Genteng Berpasir


Bahan
1.05 m2 Atap Genteng Metal Berpasir
0.03 Kg Paku biasa 2" - 5"

Upah
0.2 Oh Pekerja
0.1 Oh Tukang Kayu
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

1 M2 Atap Genteng Keramik


Bahan
13.60 bh Atap Genteng Keramik
0.03 Kg Paku biasa 2" - 5"

Upah
0.20 Oh Pekerja
0.10 Oh Tukang Kayu

1 M' Atap Nok Genteng Keramik


Bahan
3.80 bh Nok Genteng Keramik
0.05 Kg Paku biasa 2" - 5"
10.80 Kg Semen abu-abu
0.03 m3 Pasir Pasang
0.02 Kg Paku biasa 2" - 5"

Upah
0.20 Oh Pekerja
0.10 Oh Tukang Kayu
ANALISA HARGA SATUAN
STRUKTUR
PEKERJAAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
PEMBERI TUGAS : KEMNAKER
Err:509 :
TAHUN : 2017

No Uraian

1 M2 Aluminium Foil
Bahan
0.0167 rol Aluminium Foil double side
0.0185 lbr Roof Mesh 7.5 x 7.5

Upah
0.2 Oh Pekerja
0.06 Oh Tukang Kayu
ATUAN

Harga Satuan Jumlah Harga

Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Sub total : Rp -

Rp - Rp -

Sub total : Rp -

Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Sub total : Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp - Rp -
Sub total : Rp -
20 cm Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -
Sub total : Rp -

Rp -
Rp -

Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp -
Rp -

Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp -

Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -

Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp - Rp -
Sub total : Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp -

Rp - Rp -
Rp - Rp -
Sub total : Rp -
Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -
Rp -

Rp - Rp -
Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -
Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Sub total : Rp -
Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -
Rp -

Rp - Rp -
Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -
Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -
Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -
Rp -

Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -

Sub total : Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp -

Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub total : Rp -

Rp -

Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -
0.05 Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Sub total : Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Sub total : Rp -

Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub total : Rp -

Rp -

Rp - Rp -
Sub total : Rp -

Rp - Rp -

Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub total : Rp -

Rp - Rp -
Rp - Rp -

Sub total : Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Sub total : Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub Total Rp -

Rp - Rp -
Rp - Rp -

Sub Total Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub Total Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -
Rp - Rp -

Sub Total Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub Total Rp -

Rp - Rp -
Rp - Rp -

Sub Total Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub Total Rp -

Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Rp - Rp -

Sub Total Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub Total Rp -

Rp - Rp -
Rp - Rp -

Sub Total Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub Total Rp -

Rp - Rp -
Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub Total Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub Total Rp -

Rp - Rp -
Rp - Rp -

Sub Total Rp -

Rp -

Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Rp - Rp -
Sub Total Rp -

Rp - Rp -
Rp - Rp -
ATUAN

Harga Satuan Jumlah Harga

Sub Total Rp -

Rp -

Rp - Rp -
Rp - Rp -
Sub Total Rp -

Rp - Rp -
Rp - Rp -

Sub Total Rp -
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

I. PEKERJAAN PERSIAPAN

LAND CLEARING/ PEMBERSIHAN LAHAN M2


pekerja 0.0700 org/hr

MEMASANG BOWPLANK M'


Kayu kaso 5x7x400 Meranti campur 0.0050 m3
Kayu papan 3x20x400 meranti 0.0050 m3
paku rata-rata 0.0350 kg
pekerja 0.1000 org/hr

II PEKERJAAN GALIAN & URUGAN

GALIAN TANAH (DALAM 1 METER) M3


pekerja 0.8000 org/hr

GALIAN PONDASI SUMURAN DIA.80CM M'


pekerja 2.0000 org/hr

0.5024 M3
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
1.0000 M3

GALIAN PONDASI SUMURAN DIA.100CM M'


pekerja 3.0000 org/hr

BUANG TANAH/ PERATAAN TANAH M3


pekerja 0.3000 org/hr

PEMADATAN TANAH MANUAL M2


pekerja 0.4000 org/hr

URUGAN PASIR URUG M3


pasir urug 1.2000 m3
pekerja 0.7500 org/hr

URUGAN PASIR BETON M3


pasir beton 1.2000 m3
pekerja 0.4000 org/hr
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

URUGAN SIRTU M3
sirtu 1.2000 m3
pekerja 0.5000 org/hr

URUGAN TANAH KEMBALI SISA GALIAN DIPADATKAN M3

pekerja 0.2500 org/hr

III PEKERJAAN PONDASI

CERUCUK DOLKEN TTK


dolken 0.5000 btg
pekerja 0.1000 org/hr

MEMASANG PONDASI AANSTAMPING M3


batu kali 1.1000 m3
pasir urug 0.4320 m3
tukang batu 0.3900 org/hr

pekerja 0.7800 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
MEMASANG PONDASI BATU KALI 1:4 M3
batu kali 1.1000 m3
semen PC ( 50 kg ) tiga roda 2.6056 zak
pasir pasang 0.5200 m3
tukang batu 0.6000 org/hr

pekerja 1.5000 org/hr

MEMASANG ROLAG BATA t=20 CM M'


batu bata merah (press) 0.0300 m3
semen PC ( 50 kg ) tiga roda 0.6000 zak
pasir pasang 0.1040 m3
tukang batu 0.1000 org/hr

pekerja 0.1000 org/hr

IV PEKERJAAN PASANGAN

DINDING 1/2 BATU BATA 1:2 M2


(BATA PRESS)
batu bata merah 70.0000 bh
semen PC ( 50 kg ) tiga roda 0.3790 zak
pasir pasang 0.0380 m3
tukang batu 0.1000 org/hr

pekerja 0.3200 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

DINDING 1/2 BATU BATA 1:4 M2


(bata press)
batu bata merah 70.0000 bh
semen PC ( 50 kg ) tiga roda 0.1936 zak
pasir pasang 0.0450 m3
tukang batu 0.1000 org/hr

pekerja 0.3200 org/hr

DINDING BATAKO M2
batako 13.0000 bh
semen PC ( 50 kg ) tiga roda 0.2650 zak
pasir pasang 0.0600 m3
tukang batu 0.1000 org/hr

pekerja 0.3200 org/hr

PLESTERAN DINDING 1:5 M2


tebal 15 mm
semen PC ( 50 kg ) tiga roda 0.2400 zak
pasir pasang 0.0190 m3
tukang batu 0.1500 org/hr

pekerja 0.2000 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
PLESTERAN BETON ad 1:3 M2
tebal 15 mm
semen PC ( 50 kg ) tiga roda 0.2400 zak
pasir pasang 0.0190 m3
tukang batu 0.2000 org/hr

pekerja 0.1500 org/hr

ACIAN M2
semen PC ( 50 kg ) tiga roda 0.1400 zak
tukang batu 0.1000 org/hr

pekerja 0.0500 org/hr

TALI AIR, SIKUAN, SKONENGAN, BENANGAN M'


semen PC ( 50 kg ) tiga roda 0.0300 zak
tukang batu 0.0800 org/hr

pekerja 0.0600 org/hr

DINDING BATA RINGAN (t=10 cm) M2


bata ringan t=10 cm 0.1000 m3
lem semen mortar 0.1000 zak
tukang batu 0.1000 org/hr

pekerja 0.3200 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

PLESTERAN DENGAN MORTAR M2


semen mortar untuk plesteran 0.5000 zak

pekerja 0.2000 org/hr

ACIAN DENGAN MORTAR M2


semen mortar untuk acian 0.2000 zak
tukang batu 0.1000 org/hr

pekerja 0.0500 org/hr

PLESTERAN + NAAD SESUAI EXISTING M2


plesteran dinding 1.0000 m2
tali air 5.5000 m'

ACIAN BETON DENGAN MORTAR PUTIH M2


semen mortar untuk acian beton 0.2500 zak
tukang batu 0.1000 org/hr

pekerja 0.0500 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

V PEKERJAAN BETON

MEMASANG KOLOM/BALOK/GEWEL PRAKTIS 13x13 M'


beton 1:2:3 1.0500 m3
besi 198.3760 kg
bekisting 16.6667 m2

Per m' (uk 13x13)

BETON SITE MIX ad 1:2:3 M3


semen PC ( 50 kg ) tiga roda 6.7000 zak
pasir beton 0.5400 m3
batu split 0.8700 m3
tukang batu 0.5000 org/hr

pekerja 0.5000 org/hr

MEMBUAT LANTAI KERJA ad 1:3:5 M3


semen PC ( 50 kg ) tiga roda 2.5000 zak
pasir beton 0.5200 m3
split 0.8700 m3
tukang batu 0.8000 org/hr

pekerja 0.8000 org/hr

Lantai kerja 1:3:5 , t 5 cm ; 1 M2 0.0500 m3


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

BETON SITE MIX CYCLOP (60% ad. 1:2:3 dan 40% batu be M3
semen PC ( 50 kg ) tiga roda 3.8800 zak
pasir beton 0.3120 m3
split 0.4680 m3
tukang batu 0.8500 org/hr

pekerja 2.5000 org/hr

MEMASANG LEVELING LANTAI t=3 CM M2


semen PC ( 50 kg ) tiga roda 0.1272 zak
pasir beton 0.0185 m3
tukang batu 0.0400 org/hr

pekerja 0.1100 org/hr

PEKERJAAN GELARAN PLASTIK COR M2


plastik cor 1.0500 m2

pekerja 0.0200 org/hr

BEKISTING

Bekesting beton sloof / tie beam & m2


pondasi plat
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
triplek 4x8 ft, 12 mm 0.2300 lbr
paku rata-rata 0.4000 kg
Kayu kaso 5x7x400 Meranti campur 0.0210 m3
kayu balok 8x12x400 Meranti campur 0.0040 m3
beton decking 4.0000 bh
tukang kayu 0.3000 org/hr

pekerja 0.2000 org/hr

BEKISTING BETON PRAKTIS M2


triplek 4x8 ft, 9 mm 0.2333 lbr
paku rata-rata 0.4000 kg
Kayu kaso 5x7x400 Meranti campur 0.0204 m3
kayu balok 8x12x400 Meranti campur 0.0300 m3
form tie type B 0.2500 bh
beton decking 4.0000 bh
tukang kayu 0.3000 org/hr

pekerja 0.2000 org/hr

BEKISTING KOLOM & BALOK PRAKTIS M2


triplek 4x8 ft, 9 mm 0.0875 lbr
paku rata-rata 0.2000 kg
Kayu kaso 5x7x400 Meranti campur 0.0060 m3
tukang kayu 0.5000 org/hr

pekerja 0.2000 org/hr

(untuk bongkar)
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

MEMASANG BALOK PRAKTIS M3


beton sitemix 1:2:3 1.0000 m3
besi 120.0000 kg
bekisting 8.3333 m2

MEMASANG KOLOM PRAKTIS M3


beton sitemix 1:3:5 1.0000 m3
besi 120.0000 kg
bekisting 8.3333 m2

VI PEKERJAAN PINTU DAN JENDELA

MEMASANG KUSEN ALUMUNIUM 3 INCH M'


alumunium profil 3" 1.0000 m'
sekrup fixer 2.0000 bh
sealant 0.0600 tube
pekerja 0.0430 org/hr
tukang alumunium 0.0430 org/hr

MEMASANG PINTU FRAME KACA ALUMUNIUM M2


alumunium profil 3" 3.5000 m'
profil alumunium 3.5000 m'
sealant 0.2700 tube
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
pekerja 0.0850 org/hr
tukang alumunium 0.0850 org/hr

MEMASANG ALUMUNIUM KISI KREPYAK M2


profil alumunium kisi /krepyak 1.0000 m'
pekerja 0.0150 org/hr
tukang kaca/alumunium 0.0150 org/hr

MEMASANG KACA CLEAR 5 MM M2


kaca clear 5 mm ; asahimas, mulia setara 1.0500 m2
sealant - tube
pekerja 0.0150 org/hr
tukang kaca/alumunium 0.1500 org/hr

MEMASANG KUSEN DAN DAUN PINTU TYPE P1 BH


Daun pintu double teakwood finish HPL - unit
Kusen Alumunium 3" CA 9.1200 m'
Jalusi Alumunium Krepyak 1.2600 m2
Frame pintu aluminium 11.2000 m'
Kaca clear 6 mm 2.1808 m2
Sealant kaca 9.8400 m'
Sealant kusen 7.6400 m'
Lever Handle pintu ex.lokal 2.0000 psg
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
Engsel pintu 4" S/S 2BB ex.lokal 2.0000 psg
Kunci pintu ex.lokal 1.0000 bh
tukang kaca/aluminium 4.2500 org/hr

pekerja 6.3750 org/hr

MEMASANG KUSEN DAN DAUN PINTU TYPE P2 BH


Daun pintu double triplek 6mm finish duco - unit
Kusen Alumunium 3" CA 6.9200 m'
frame pintu allumunium 2.0640 m2
Kaca clear 5 mm 1.4448 m2
Sealant kaca 10.1200 m'
Sealant kusen 6.0400 m'
Lever Handle pintu ex.lokal 1.0000 psg
Engsel pintu 4" S/S 2BB ex.lokal 1.0000 psg
Engsel jendela 3" S/S 2BB ex.lokal 1.0000 psg
Kunci pintu ex.lokal 1.0000 bh
Rambuncis ex.dekson 1.0000 bh
tukang kaca 2.1250 org/hr

pekerja 3.1875 org/hr

MEMASANG KUSEN DAN DAUN PINTU TYPE P3 (Spandrel BH


Daun Pintu Alumunium Spandrel 1.0000 unit
Kusen Alumunium 3" CA 6.9200 m'
frame pintu allumunium - m2
Kaca clear 5 mm 0.2800 m2
Sealant kaca 2.2000 m'
Sealant kusen 6.0400 m'
Lever Handle pintu ex.lokal - psg
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
Engsel pintu 4" S/S 2BB ex.lokal 1.0000 psg
Engsel jendela 3" S/S 2BB ex.lokal - psg
Kunci pintu ex.lokal - bh
tukang kaca 0.5000 org/hr

pekerja 0.7500 org/hr

MEMASANG KUSEN DAN DAUN JENDELA TYPE J.1 BH


Kusen Alumunium 3" CA 11.0100 m'
frame jendela allumunium 2.2400 m2
Kaca clear 5 mm 2.3680 m2
Sealant kaca 11.4400 m'
Sealant kusen 5.8200 m'
Engsel Casement 24" 2.0000 set
rambuncis lokal 2.0000 bh
tukang kaca 0.5000 org/hr

pekerja 0.7500 org/hr

MEMASANG JENDELA BOVENLICH B1 1BH


alumunium 3" 2.1600 m'
kaca clear 4 mm 0.2176 m2
sealant kaca 2.1600 m'

MEMASANG KUSEN DAN DAUN JENDELA TYPE J.2 BH


Kusen Alumunium 3" CA 13.2300 m'
frame jendela allumunium 1.1200 m2
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
Kaca clear 5 mm 4.2194 m2
Sealant kaca 14.8720 m'
Sealant kusen 7.5660 m'
Engsel Casement 24" 1.0000 set
rambuncis lokal 1.0000 bh
tukang kaca 0.5000 org/hr

pekerja 0.7500 org/hr

MEMASANG KUSEN DAN DAUN JENDELA TYPE J.3 BH


Kusen Alumunium 3" CA 7.5400 m'
frame jendela allumunium - m2
Kaca clear 5 mm 2.3220 m2
Sealant kaca 8.6200 m'
Sealant kusen 6.4600 m'
Engsel Casement 24" - set
rambuncis lokal - bh
tukang kaca 0.5000 org/hr

pekerja 0.7500 org/hr

MEMASANG JENDELA KAWAT 1 M2


Kusen Besi Siku 50x50x5 1.0000 kg
Kawat Harmonika 1.0000 m2
Sealant kusen 0.5000 m'
tukang besi 0.0500 org/hr
kepala tukang besi 0.0500 org/hr
pekerja 0.0500 org/hr
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

MEMASANG JENDELA TYPE BV BH


Kusen Alumunium 3" CA 2.0000 m'
Kaca clear 5 mm 0.2000 m2
Sealant kaca 1.6000 m'
Sealant kusen 4.0000 m'
tukang kaca - org/hr

pekerja - org/hr

MEMASANG PINTU SHAFF TYPE PS BH


Kusen Alumunium 3" CA 2.0000 m'
Daun pintu double triplek 6 mm finish duco 1.0000 unit
Sealant kusen 3.2000 m'
tukang kaca - org/hr

pekerja - org/hr

MEMASANG JALUSI ALUMINIUM GALVALUME M2


Jalusi Aluminium Galvalume t : 0.5 1.0000 m2

MEMASANG PINTU TYPE P.1 M2


Folding Gate Galvalume tbl = 0.5 mm (termasuk kusen) 1.0000 m2
pekerja 0.4400 org/hr
tukang besi 0.4400 org/hr
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

MEMASANG PINTU TYPE P.D UNT


Daun pintu double triplek 6mm finish hpl 2.0000 unit
Kusen Alumunium 3" CA 5.9000 m'
Lever Handle pintu ex.lokal 2.0000 psg
Engsel pintu 4" S/S 2BB ex.lokal 2.0000 psg
Kunci pintu ex.lokal 1.0000 bh
tukang kayu 0.8800 org/hr

pekerja 0.0440 org/hr

MEMASANG PINTU TYPE PS UNT


Daun pintu double triplek 6mm finish hpl 1.0000 unit
Kusen Alumunium 3" CA 5.1000 m'
Lever Handle pintu ex.lokal 1.0000 psg
Engsel pintu 4" S/S 2BB ex.lokal 1.0000 psg
Kunci pintu ex.lokal 1.0000 bh
tukang kayu 0.4400 org/hr

pekerja 0.0440 org/hr

MEMASANG PINTU TYPE PJ.1 UNIT


Daun pintu double triplek 6mm finish hpl 1.0000 unit
Kusen Alumunium 3" CA 18.4000 m'
frame pintu allumunium 11.2000 m'
Kaca clear 6 mm 5.5513 m2
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
Sealant kaca 30.6080 m'
Sealant kusen 17.0000 m'
Lever Handle pintu ex.lokal 2.0000 psg
Engsel pintu 4" S/S 2BB ex.lokal 2.0000 psg
Kunci pintu ex.lokal 1.0000 bh
tukang kaca 4.2500 org/hr

pekerja 6.3750 org/hr

MEMASANG KUSEN PINTU JENDELA TYPE PJ3 UNIT


Kusen Alumunium 3" CA - m'
Kaca clear 6 mm 14.3700 m2
Sealant kaca 14.2600 m'
Sealant kusen 11.6000 m'
Daun Pintu Kaca Frame Alumunium - m'
Lever Handle pintu ex.lokal 1.0000 psg
Engsel pintu 4" S/S 2BB ex.lokal 2.0000 psg
Kunci pintu ex.lokal 1.0000 bh
tukang kaca 3.0000 org/hr

pekerja 3.0000 org/hr

MEMASANG KUSEN PINTU JENDELA TYPE PJ5 UNIT


Kusen Alumunium 3" CA 20.3000 m'
Kaca clear 6 mm 3.6650 m2
Sealant kaca 16.0000 m'
Sealant kusen 9.5500 m'
Daun Pintu Double Teakwood 2.0000 unt
Lever Handle pintu ex.lokal 1.0000 psg
Engsel pintu 4" S/S 2BB ex.lokal 2.0000 psg
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
Kunci pintu ex.lokal 1.0000 bh
tukang kaca 4.0000 org/hr

pekerja 3.0000 org/hr

MEMASANG JENDELA TYPE J.1 UNIT


Kusen Alumunium 3" CA 18.6400 m'
kawat Ayam 5.4912 m2
jendela allumunium 2.1216 m2
jalusi alumunium galvalume 5.4912 m2
Kaca clear 6 mm 4.1184 m2
Sealant kaca 24.8340 m'
Sealant kusen 9.1240 m'
Engsel Casement 12" 3.0000 set
rambuncis ex Deksson 3.0000 bh
tukang kaca 3.0000 org/hr

pekerja 4.0000 org/hr

MEMASANG JENDELA TYPE J.1a UNIT


Kusen Alumunium 3" CA 30.3000 m'
kawat Ayam 0.0000 m2
jendela allumunium 2.0579 m2
jalusi alumunium galvalume 5.4740 m2
Kaca clear 6 mm 2.0528 m2
Sealant kaca 27.2700 m'
Sealant kusen 14.7000 m'
Engsel Casement 12" 2.0000 set
rambuncis ex Deksson 2.0000 bh
tukang kaca 2.5000 org/hr
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

pekerja 4.0000 org/hr

MEMASANG JENDELA TYPE J.2 UNIT


Kusen Alumunium 3" CA 7.2000 m'
Kaca clear 6 mm 2.0800 m2
Sealant kaca 6.8000 m'
Sealant kusen 14.4000 m'
tukang kaca 1.2500 org/hr

pekerja 2.5000 org/hr

MEMASANG JENDELA TYPE J.3 UNIT


Kusen Alumunium 3" CA 39.9500 m'
jendela allumunium 2.6760 m2
Kaca clear 6 mm 12.0420 m2
Sealant kaca 45.9760 m'
Sealant kusen 32.6000 m'
Engsel Casement 12" 4.0000 set
rambuncis DEKKSON 4.0000 bh
tukang kaca 2.2500 org/hr

pekerja 4.5000 org/hr

MEMASANG JENDELA TYPE J.4 UNIT


Kusen Alumunium 3" CA 20.7000 m'
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
jendela allumunium 1.2630 m2
Kaca clear 6 mm 5.6835 m2
Sealant kaca 6.3680 m'
Sealant kusen 20.7000 m'
Engsel Casement 12" 4.0000 set
rambuncis DEKKSON 4.0000 bh
tukang kaca 2.2500 org/hr

pekerja 4.5000 org/hr

MEMASANG JENDELA TYPE J.4a UNIT


Kusen Alumunium 3" CA 14.7750 m'
jendela allumunium 1.5040 m2
Kaca clear 6 mm 4.2714 m2
Sealant kaca 20.4000 m'
Sealant kusen 8.7500 m'
Engsel Casement 12" 2.0000 set
rambuncis DEKKSON 2.0000 bh
tukang kaca 2.2500 org/hr

pekerja 4.5000 org/hr

MEMASANG JENDELA TYPE J.5 UNIT


Kusen Alumunium 3" CA 31.0440 m'
kawat Ayam 5.5000 m2
jendela allumunium 1.7033 m2
jalusi alumunium galvalume 5.1098 m2
Kaca clear 6 mm 3.4065 m2
Sealant kaca 9.0420 m'
Sealant kusen 26.1440 m'
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
Engsel Casement 12" 3.0000 set
rambuncis DEKKSON 3.0000 bh
tukang kaca 2.2500 org/hr

pekerja 4.5000 org/hr

MEMASANG JENDELA TYPE V.1 UNIT


Kusen Alumunium 3" CA 19.0000 m'
kawat Ayam 4.8000 m2
jalusi alumunium galvalume 5.4150 m2
Sealant kusen 26.6000 m'
tukang kaca 2.2500 org/hr

pekerja 4.5000 org/hr

MEMASANG JENDELA TYPE V.2 UNIT


Kusen Alumunium 3" CA 8.7420 m'
Kaca clear 6 mm 2.1575 m2
Sealant kaca 10.2420 m'
Sealant kusen 13.6840 m'
tukang kaca 2.2500 org/hr
kepala tukang alumunium 0.4500 org/hr
pekerja 4.5000 org/hr

MEMASANG JENDELA TYPE V.3 UNIT


Kusen Alumunium 3" CA 46.1180 m'
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
jalusi alumunium galvalume 17.3160 m2
Sealant kusen 92.2360 m'
tukang besi 4.5000 org/hr

pekerja 9.0000 org/hr

MEMASANG JENDELA TYPE V.4 UNIT


Kusen Alumunium 3" CA 9.3420 m'
kawat Ayam 2.3000 m2
jalusi alumunium galvalume 2.6325 m2
Sealant kusen 14.8840 m'
tukang kaca 1.5000 org/hr

pekerja 3.0000 org/hr

MEMASANG JENDELA TYPE V.5 UNIT


Kusen Alumunium 3" CA 13.8720 m'
kawat Ayam 5.0625 m2
jalusi alumunium galvalume 5.0625 m2
Sealant kusen 20.1440 m'
tukang kaca 1.5000 org/hr

pekerja 3.0000 org/hr

MEMASANG PINTU FOLDING GATE M2


pintu folding gate besi 1.0000 m2
dynabolt 1.5000 bh
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
pekerja 0.0850 org/hr
tukang alumunium 0.8500 org/hr

VII PEKERJAAN PLAFOND

MEMASANG PLAFOND GYPSUM TILE M2


gypsum board 4x8 ft , t = 9 mm 0.3472 lbr
hollow 20 x 40 x 0.35 mm 0.8000 btg
hollow 40 x 40 x 0.35 mm 0.5000 btg
penggantung plafond 1.0000 bh
compound 0.1000 sak
textile tape 0.2000 rol
skrup gypsum 15.0000 bh
tukang gypsum 0.1000 org/hr

pekerja 0.1000 org/hr

PLAFOND GRC + RANGKA HOLLOW GALVALUM M2


panel GRC 4x8 ft , t - 4.5 mm 0.3472 lbr
hollow 20 x 40 x 0.4 mm 0.8000 btg
hollow 40 x 40 x 0.4 mm 0.5000 btg
penggantung plafond 1.0000 bh
compound 0.1000 kg
textile tape 0.2000 rol
skrup gypsum 15.0000 bh
tukang gypsum 0.1000 org/hr

pekerja 0.1000 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

PARTISI GRC 2 MUKA 9 MM RANGKA HOLLOW M2


hollow galvanised 40 x 40 x 0.35 mm 1.0000 btg
hollow galvanised 20 x 40 x 0.35 mm 1.4000 btg
Calsiboard 0.7280 lmb
paku , sekrup, fisher 8.0000 bh
compound 0.2500 sak
textile tape 0.1440 rol
tukang gypsum 0.1000 org/hr

pekerja 0.2000 org/hr

LIST GYPSUM UK. 7x7 CM M'


List gypsum 7 x 7 1.0500 m'
compound 0.0250 kg
tukang gypsum 0.0600 org/hr

pekerja 0.0200 org/hr

LIST GYPSUM UK. 5x5 CM M'


List gypsum 5 x 5 1.0500 m'
compound 0.0250 kg
tukang gypsum 0.0600 org/hr

pekerja 0.0200 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

MEMASANG LIST KAYU KAMPER 5 x 5 CM M'


list profil kayu kamper 5 x 5 1.0500 m'
paku rata-rata 0.0500 kg
tukang kayu 0.0600 org/hr

pekerja 0.0200 org/hr

VIII PEKERJAAN PELAPIS LANTAI DAN DINDING

MEMASANG LANTAI KERAMIK 20x20 m2


adukan 1:5, tebal 5 cm
lantai keramik 20x20 1.1000 m2
pasir pasang 0.0300 m3
semen PC ( 50 kg ) tiga roda 0.2300 zak
semen isian naat 0.2000 kg
tukang batu 0.1350 org/hr

pekerja 0.2700 org/hr

MEMASANG LANTAI KERAMIK 30x30 m2


adukan 1:5, tebal 5 cm
lantai keramik 30x30 1.1000 m2
pasir pasang 0.0300 m3
semen PC ( 50 kg ) tiga roda 0.2300 zak
semen isian naat 0.2000 kg
tukang batu 0.1350 org/hr
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
pekerja 0.2700 org/hr

MEMASANG KERAMIK LANTAI UK. 40x40 M2


adukan 1:5, tebal 5 cm
lantai keramik 40x40 1.1000 m2
pasir pasang 0.0300 m3
semen PC ( 50 kg ) tiga roda 0.2300 zak
semen isian naat 0.2000 kg
tukang batu 0.1350 org/hr

pekerja 0.2700 org/hr

MEMASANG KERAMIK UK. 60x60 M2


adukan 1:5, tebal 5 cm
Lantai keramik , uk. 60x60 cm 1.1000 m2
pasir pasang 0.0300 m3
semen PC ( 50 kg ) tiga roda 0.2300 zak
semen isian naat 0.2000 kg
tukang batu 0.3800 org/hr

pekerja 0.1900 org/hr

MEMASANG DINDING KERAMIK 30 x 60 M2


adukan 1:5, tebal 5 cm
dinding keramik 20 x 40 1.0500 m2
pasir pasang 0.0180 m3
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
semen PC ( 50 kg ) tiga roda 0.1860 zak
semen isian naat 0.1000 kg
tukang batu 0.3200 org/hr

pekerja 0.5000 org/hr

MEMASANG PLINT KERAMIK UK. 10x40 M'


lantai keramik 10x40 2.5000 bh
pasir pasang 0.0020 m3
semen PC ( 50 kg ) tiga roda 0.0200 zak
tukang batu 0.0900 org/hr

pekerja 0.0900 org/hr

MEMASANG PLINT HOMOGENIOUS TILE UK. 10x60 M'


homogenious tile 10x60 1.6667 bh
pasir pasang 0.0020 m3
semen PC ( 50 kg ) tiga roda 0.0200 zak
tukang batu 0.2000 org/hr

pekerja 0.2000 org/hr

MEMASANG STEPNOZING TANGGA KERAMIK UK. 10x40 M'


stepnosing keramik tile 10x40 1.6667 bh
pasir pasang 0.0020 m3
semen PC ( 50 kg ) tiga roda 0.0200 zak
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
tukang batu 0.2000 org/hr

pekerja 0.2000 org/hr

MEMASANG BATU ALAM M2


adukan 1:5, tebal 5 cm
batu alam candi 1.0500 m2
pasir pasang 0.0180 m3
semen PC ( 50 kg ) tiga roda 0.1860 zak
tukang batu 0.3200 org/hr

pekerja 0.5000 org/hr

VIII PEKERJAAN PENGECATAN

CAT DINDING DALAM CATYLAC M2


(dinding baru , 3 lapis)
plamur tembok 0.3000 kg
amplas 0.5000 lbr
cat dasar alkali 0.1000 kg
cat tembok dalam Catylac 0.3000 kg
kuas roll 0.0250 bh
tukang cat 0.0800 org/hr

pekerja 0.0400 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
CAT DINDING DALAM MOWILEX M2
(dinding baru , 3 lapis)
plamur tembok 0.3000 kg
amplas 0.5000 lbr
cat dasar 0.1000 kg
cat tembok mowilex interior 0.3000 kg
kuas roll 0.0250 bh
tukang cat 0.0800 org/hr

pekerja 0.0400 org/hr

CAT DINDING LUAR MOWILEX M2


(dinding baru , 3 lapis)
plamur tembok 0.1905 kg
amplas 0.2500 lbr
cat dasar alkali 0.0952 kg
cat tembok mowilex 0.3000 kg
kuas roll 0.0238 bh
tukang cat 0.0800 org/hr

pekerja 0.0400 org/hr

CAT PLAFOND VINILEX M2


(dinding baru , 3 lapis)
amplas 0.5000 lbr
cat vililex putih 0.3000 kg
kuas roll 0.0250 bh
tukang cat 0.0800 org/hr

pekerja 0.0400 org/hr


ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

CAT LIST PLAFOND GYPSUM M'


amplas 0.0500 lbr
cat tembok 0.0600 kg
kuas roll 0.0025 bh
tukang cat 0.0080 org/hr

pekerja 0.0040 org/hr

CAT MINYAK M2
amplas 0.5000 lbr
cat besi Glotex 0.2500 kg
meni besi 0.1670 kg
thinner impala 0.1500 ltr
kuas besar 0.0476 bh
tukang cat 0.0667 org/hr

pekerja 0.0333 org/hr

CAT MELAMIK KAYU M'


ab dan mb cat plint kayu 1.0000 m'
plamur kayu 0.0100 kg
wood filler ultran 0.1000 kg
sending sealer ultran 0.1000 kg
amplas 0.1340 lbr
cat dasar 0.1000 kg
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
melamic ultran 0.1000 kg
thinner ND 0.1000 ltr
kuas 0.2000 bh
tukang cat 0.0500 org/hr

pekerja 0.0500 org/hr

PEK WATERPROFING COATING M2


Pre treatment/cleaning 1.0000 m2
waterproofing coating 0.2500 kg
kuas 0.5000 bh
tukang batu 0.0200 org/hr

pekerja 0.2000 org/hr

IX PEKERJAAN SANITAIR

WASTAFEL TANAM BH
wastafel gantung + accessories ex.lokal 1.0000 bh
sealant 0.5000 bh
tukang plambing 1.2500 org/hr

pekerja 0.2500 org/hr

CLOSED JONGKOK BH
closed jongkok 1.0000 bh
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN
semen putih ( 50 kg ) 0.0200 zak
pas bata 1.6000 m2
plesteran 1:2 1.0000 m2
tukang batu 0.3000 org/hr

pekerja 0.3000 org/hr

MEMASANG FLOOR DRAIN BH


floor drain 1.0000 bh
tukang plambing 0.1000 org/hr

pekerja 0.1000 org/hr

MEMASANG ROOF DRAIN 4" BH


roof drain 4" 1.0000 bh
semen PC ( 50 kg ) tiga roda 0.1600 zak
sealant 1.0000 tube
kalbon 0.1000 ltr
pasir pasang 0.0250 m3
tukang plambing 0.1000 org/hr

pekerja 0.1000 org/hr

MEMASANG KRAN AIR LOKAL BH


kran air lokal 1.0000 bh
seal tape 0.5000 bh
tukang plambing 0.0300 org/hr
ANALISA HARGA SATUAN
ARSITEKTUR
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI : 0.00
TAHUN : 2017
NO JENIS PEKERJAAN VOLUME SATUAN

pekerja 0.2500 org/hr


AN

HARGA JUMLAH

- -

jumlah -
dibulatkan -

-
-
-
- -

jumlah -
dibulatkan -

- -

jumlah -
dibulatkan -

###
- -

jumlah -
jumlah -
dibulatkan -
AN

HARGA JUMLAH
dibulatkan -

- -

jumlah -
dibulatkan -

- -

jumlah -
dibulatkan -

- -

jumlah -
dibulatkan -

-
- -

jumlah -
dibulatkan -

- -
- -

jumlah -
dibulatkan -
AN

HARGA JUMLAH

-
- -

jumlah -
dibulatkan -

- -

jumlah -
dibulatkan -

-
- -

jumlah -
dibulatkan -

- -
- -
- -

- -

jumlah -
dibulatkan -
AN

HARGA JUMLAH

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -
AN

HARGA JUMLAH

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -

- -

jumlah -
dibulatkan -
AN

HARGA JUMLAH

- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -

- -

jumlah -
dibulatkan -

- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -

- -
AN

HARGA JUMLAH

jumlah -
dibulatkan -

- -

- -

jumlah -
dibulatkan -

- -
- -

- -

jumlah -
dibulatkan -

- -
- -

jumlah -
dibulatkan -

- -
- -

- -
AN

HARGA JUMLAH
jumlah -
dibulatkan -

- -
- -
- -
jumlah/m3 -
-
jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
AN

HARGA JUMLAH
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -

- -

jumlah -
dibulatkan -

- -

- -

jumlah -
dibulatkan -
AN

HARGA JUMLAH
-
-
-
-
-
80,000 24,000

- -

jumlah 24,000
dibulatkan 24,000

- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -
AN

HARGA JUMLAH
jumlah -
dibulatkan -

###
- -
- -
- -

jumlah -
dibulatkan -

###
- -
- -
- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -

jumlah -
dibulatkan -

- -
- -
- -
AN

HARGA JUMLAH
- -
- -

jumlah -
dibulatkan -

- -
- -
- -

jumlah -
dibulatkan -

- -
- -
- -
- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -
AN

HARGA JUMLAH
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

-
- -
- -
- -
- -
- -
- -
AN

HARGA JUMLAH
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -

jumlah -
dibulatkan -

- -
- -
AN

HARGA JUMLAH
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -

jumlah -
AN

HARGA JUMLAH
dibulatkan -

- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -

jumlah -
dibulatkan -

- -
- -
- -
AN

HARGA JUMLAH

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
AN

HARGA JUMLAH
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
AN

HARGA JUMLAH
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -
- -
- -
AN

HARGA JUMLAH

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
AN

HARGA JUMLAH
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
AN

HARGA JUMLAH
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -

jumlah -
dibulatkan -

- -
AN

HARGA JUMLAH
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
AN

HARGA JUMLAH
- -
- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -
- -

- -
AN

HARGA JUMLAH

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -

- -
AN

HARGA JUMLAH
jumlah -
dibulatkan -

- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
AN

HARGA JUMLAH
- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
AN

HARGA JUMLAH
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
AN

HARGA JUMLAH
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -
AN

HARGA JUMLAH

- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -

- -
AN

HARGA JUMLAH

jumlah -
dibulatkan -

- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

-
-
-
-
-
-
AN

HARGA JUMLAH
-
-
-
-

jumlah -
dibulatkan -

5,000 5,000
- -
- -
- -

- -

jumlah 5,000
dibulatkan 5,000

- -
- -
- -

- -

jumlah -
dibulatkan -

- -
AN

HARGA JUMLAH
- -
- -
- -
- -

- -

jumlah -
dibulatkan -

- -
- -

- -

jumlah -
dibulatkan -

-
-
-
-
-
-

jumlah -
dibulatkan -

- -
- -
- -
AN

HARGA JUMLAH

- -

jumlah -
dibulatkan -
ANALISA HARGA PEK. PLUMBING

Pekerjaan : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID


Lokasi :
Pemberi Tugas : KEMNAKER
Tahun Anggaran : 2017

1 Memasang 1 m' Pipa HDPE dia 4" SDR-11 (PN 16)


Bahan An. SNI RSNIT-15-2002
1.200 m Pipa HDPE dia 4" SDR 11 (PN 16) @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
0.081 Oh Pekerja @ Rp. 0.00 = Rp
0.135 Oh Tukang Plumbing @ Rp. 0.00 = Rp

Sub total : = Rp
Total upah+bahan : = Rp

2 Memasang 1 unt Gate Valve dia 4"


Bahan An. SNI RSNIT-15-2002
1.000 bh Gate Valve dia 4" @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
1.300 Oh Pekerja @ Rp. 0.00 = Rp
1.300 Oh Tukang Plumbing @ Rp. 0.00 = Rp

Sub total : = Rp
Total upah+bahan : = Rp

4 Memasang 1 unt Pompa Jet Pump


Pengadaan Alat
1.000 bh Pompa VF 18-4 @ Rp. 0.00 = Rp
10.000 % Perlengkapan instalasi = Rp
1.000 ls Transportasi @ Rp. 0.00 = Rp
Sub total : = Rp
Upah & Commissioning
1.000 Oh Pekerja @ Rp. 0.00 = Rp
1.000 Oh Tukang Plumbing @ Rp. 0.00 = Rp

Sub total : = Rp
Total upah+bahan : = Rp

2 Memasang 1 m' Pipa PVC tipe AW dia 1/2"


Bahan An. SNI RSNIT-15-2002
1.200 m Pipa PVC AW 1/2" @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
0.036 Oh Pekerja @ Rp. 0.00 = Rp
0.060 Oh Tukang Plumbing @ Rp. 0.00 = Rp
ANALISA HARGA PEK. PLUMBING

Pekerjaan : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID


Lokasi :
Pemberi Tugas : KEMNAKER
Tahun Anggaran : 2017
Sub total : = Rp
Total upah+bahan : = Rp

2 Memasang 1 m' Pipa PVC tipe AW dia 3/4"


Bahan An. SNI RSNIT-15-2002
1.200 m Pipa PVC AW 3/4" @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
0.036 Oh Pekerja @ Rp. 0.00 = Rp
0.060 Oh Tukang Plumbing @ Rp. 0.00 = Rp

Sub total : = Rp
Total upah+bahan : = Rp

3 Memasang 1 m' Pipa PVC tipe AW dia 1"


Bahan An. SNI RSNIT-15-2002
1.200 m Pipa PVC AW 1" @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
0.036 Oh Pekerja @ Rp. 0.00 = Rp
0.060 Oh Tukang Plumbing @ Rp. 0.00 = Rp

Sub total : = Rp
Total upah+bahan : = Rp

4 Memasang 1 m' Pipa PVC tipe AW dia 1 1/2"


Bahan An. SNI RSNIT-15-2002
1.200 m Pipa PVC AW 1 1/2" @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
0.036 Oh Pekerja @ Rp. 0.00 = Rp
0.060 Oh Tukang Plumbing @ Rp. 0.00 = Rp

Sub total : = Rp
Total upah+bahan : = Rp

5 Memasang 1 m' Pipa PVC tipe AW dia 2"


Bahan An. SNI RSNIT-15-2002
1.200 m Pipa PVC AW 2" @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
0.054 Oh Pekerja @ Rp. 0.00 = Rp
0.090 Oh Tukang Plumbing @ Rp. 0.00 = Rp
ANALISA HARGA PEK. PLUMBING

Pekerjaan : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID


Lokasi :
Pemberi Tugas : KEMNAKER
Tahun Anggaran : 2017

Sub total : = Rp
Total upah+bahan : = Rp

6 Memasang 1 m' Pipa PVC tipe AW dia 3"


Bahan An. SNI RSNIT-15-2002
1.200 m Pipa PVC AW 3" @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
0.081 Oh Pekerja @ Rp. 0.00 = Rp
0.135 Oh Tukang Plumbing @ Rp. 0.00 = Rp

Sub total : = Rp
Total upah+bahan : = Rp

7 Memasang 1 m' Pipa PVC tipe AW dia 4"


Bahan An. SNI RSNIT-15-2002
1.200 m Pipa PVC AW 4" @ Rp. 0.00 = Rp
35.000 % Perlengkapan instalasi = Rp
Sub total : = Rp
Upah An. SNI RSNIT-15-2002
0.081 Oh Pekerja @ Rp. 0.00 = Rp
0.135 Oh Tukang Plumbing @ Rp. 0.00 = Rp

Sub total : = Rp
Total upah+bahan : = Rp
0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00
0.00
0.00

0.00
0.00
0.00

0.00
0.00

0.00
0.00

0.00
0.00
0.00

0.00
0.00

0.00
0.00
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

I. MATERIAL ALAM
batu bata merah bh
batako bh
batu kali m3
batu karang m3
koral beton m3
sirtu m3
split m3
beton decking bh
pasir beton m3
pasir pasang m3
pasir urug m3
tanah urug (lokal) m3

II. SEMEN
semen PC ( 50 kg ) kg
semen PC ( 50 kg ) zak
semen putih ( 50 kg ) zak
semen abu2 kg
semen isian naat / warna kg
lem semen mortar sak
semen mortar untuk plesteran sak
semen mortar untuk acian sak
semen mortar untuk acian beton sak
waterproofing coating ex aquaproof kg
waterproofing membran ex fosroc m2
plastik cor kedap air m2

III. READY MIX & BATA RINGAN


beton readymix K-250 m3
beton readymix K-300 m3
hebel / bata ringan tebal 10 cm m3
hebel / bata ringan tebal 10 cm bh
hebel / bata ringan tebal 8 cm m3
hebel / bata ringan tebal 8 cm bh
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

IV. BESI , BAJA & ASESORIES


wiremesh M6 (2.1 x 5.4 m) lmbr
wiremesh M8 (2.1 x 5.4 m) lmbr
wiremesh M10 (2.1 x 5.4 m) lmbr
besi beton polos rata2 kg
besi beton ulir rata2 kg
form tie type B bh
baut HTB dia 12 mm bh
baut HTB dia.16 mm bh
ikatan gording dia.12 mm + turnbuckle kg
ikatan angin dia.16 mm kg
angkur dia. 19 mm L = 80 cm bh
bondex t = 0.75 m2
plat besi 8,10, 12, 16 mm kg
baja WF, H Beam kg
baja CNP, Siku kg
kawat ayam/ram 1/2" m2
kawat beton kg
kawat las harmonika kg
C - 75, 0.7 Truss baja ringan m'
C - 75, 0.7 Truss baja ringan m'
reng , 0.4 baja ringan m'
roofmesh 20x20 mm roll
paku seng kg
paku rata-rata kg
paku sekrup bh
baut (screw) baja ringan bh
dynabolt bh

VI. KAYU & MULTIPLEKS


dolken btg
kayu balok 5x10x400 Meranti klas II campur m3
kayu balok 8x12x400 Meranti klas II campur m3
kayu kaso 5x7x400 Meranti klas II campur m3
kayu papan 3x20x400 Meranti campur m3
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

kayu papan 3x30x400 Meranti campur m3


list profil kayu kamper 3 x 3 m'
triplek 122x244, 6 mm lbr
triplek 122x244, 9 mm lbr
triplek 122x244, 12 mm lbr

IV. PINTU DAN JENDELA


Pintu :
folding gate galvalume tbl 0.5 mm m2
folding gate besi m2
daun pintu keets/bedeng bh
daun pintu double teakwood, Finish HPL bh
kusen & daun Pintu PVC unit
Asesories :
engsel casement 24" psg
engsel casement 12" psg
engsel pintu 4" S/S 2BB ex.lokal psg
engsel jendela 3" S/S 2BB ex.lokal psg
hak angin lokal bh
lever handle pintu ex.lokal psg
kunci pintu ex.lokal set
kunci pintu keet bh
rambuncis lokal bh
rambuncis ex.dekson bh
Kaca :
bevel kaca m'
jendela nako 7 dn + kaca bening bh
jendela nako 7 dn + kaca bening bh
kaca clear 4 mm m2
kaca clear 5 mm m2
kaca clear 8 mm m2
kawat harmonika m2
U alumunium 2x3 cm m'
Alumunium / Frame :
jalusi galvalume m2
jalusi/kisi/krepyak m'
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

frame pintu alumunium m'


frame jendela allumunium m'
kusen alumunium 3" CA m'
daun jendela alumunium CA m2
profil alumunium kaca m'
sealant kusen m'
sealant kaca m'
sealant kusen/jendela tube
sekrup fixer bh

V. ATAP
nok genteng metal pasir m'
nok galvalum m'
nok genteng keramik bh
atap genteng metal pasir T=0.40 mm m2
atap spandek galvalum t=0.35 mm m2
atap genteng keramik bh
alumunium foil double side laminated (1,2 x 50) m roll
roof mesh 7.5 x 7.5 (1,8 x 30) m ; t : 1.2 mm lmbr
flashing ( S ) T = 0,40 TCT m'
seng gelombang 180x90x0.02 lbr
talang jurai m'

VI. PLAFOND
gypsum board 4x8 ft , t = 9 mm lbr
penggantung plafond bh
hollow 20 x 40 x 0.35 mm btg
hollow 40 x 40 x 0.35 mm btg
List gypsum 7 x 7 m'
List gypsum 5 x 5 m'
list profil kayu 3 x 3 m'
panel GRC 4x8 ft , t - 4.5 mm lbr
Lisplang GRC 20 cm m'
compound zak
skrup gypsum bh
textile tape roll
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

VII. MATERIAL LANTAI


dinding keramik 20 x 20 unpolished m2
dinding keramik 20 x 20 polished m2
dinding keramik 30 x 60, Asia Tile/KIA/Mulia m2
lantai keramik 30x30, Asia Tile/KIA/Mulia m2
lantai keramik 40x40, Asia Tile/KIA/Setara m2
lantai keramik 60x60 cm, Asia Tile/KIA/setara m2
plint keramik uk 10x60 cm bh
plint keramik uk.10x40 bh
stepnosing homogenious, uk 10x60 cm bh
stepnosing keramik, uk 10x40 cm bh
batu alam candi m2

VIII. CAT
cat dasar alkali Catylac kg
amplas lbr
cat dasar kg
cat besi Glotex kg
cat besi zinkromate kg
meni besi kg
cat tembok dalam Catylac kg
cat tembok mowilex (interior) kg
cat tembok catylac (luar) kg
cat tembok ICI dulux pentilite kg
cat plafond putih vinilex kg
plamur tembok kg
melamic ultran kg
sending sealer ultran kg
thinner impala ltr
thinner ND ltr
wood filler ultran ltr
kalbon ltr
plamur kayu kg
kuas bh
kuas besar bh
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

kuas roll bh
waterproofing (coating) kg
waterproofing (membran) m2

X. SANITAIR
bak fibre uk.60x60x60 untuk direksi keet bh
closet jongkok biasa untuk direksi keet bh
closet jongkok INA bh
closet duduk setara TOTO bh
wastafel tanam + accessories ex.lokal bh
floor drain bh
kalbon ltr
kran air lokal bh
kran shower bh
seal tape bh
sealant silicon tube
XI. JALAN & LANDSCAPE
buis beton ø 100 cm, panj.0.50 m bh
buis beton ø 80 cm, panj.0.50 m bh
saluran air U ditch 120x50x50 bh
saluran air U ditch 120x150x150 bh

XII. BBM
Bensin Premium ltr
Solar ltr
Oli / Pelumas ltr

XIII BAHAN KABEL


Kabel NYM 3 x 1,5 mm2 m'
Kabel NYM 3 x 4 mm2 m'
Kabel NYY 3 x 2,5 mm2 m'
Kabel NYY 4 x 6 mm2 m'
Kabel NYY 4 x 10 mm2 m'
Kabel BC 35 mm2 m'
Kabel BC 50 mm2 m'
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

XIV BAHAN LAMPU, SAKLAR & STOP KONTAK


Lampu TL 1 x 36 watt, Balk bh
Lampu TL 1 x 18 watt, Balk bh
Lampu TL Balk 1 x 18 watt c/w Battery bh
Lampu Pijar 25 watt + Fitting bh
Lampu Taman 80 watt type Bollard bh
Lampu TL TKO 2 x 36 watt + rumah bh
Lampu TL TKI 2 x 36 watt bh
Lampu Downlight DL LED 5 W Phillip bh
Lampu Baret 18W Philip bh
Lampu Bohlam 18W Philip bh
Stop kontak bh
Saklar Seri/Ganda bh
Stop Kontak bh

XVI ASESORIES
Flexible conduit 20 mm m'
Flexible conduit 32 mm m'
uPVC conduit 20 mm m'
Sock 20 mm bh
Tee dooz 20 mm bh
Inbouw Dooz bh
Klem 20 mm bh
Fisher bh
Isolasi bh
Splitzen 3/4" bh
Splitzen 1" bh
Klem Penyangga kabel BC bh
Klem Penyambung Kabel BC bh
Klem Kuku Macan bh
Tiang Arde 12 mm bh
Tiang Arde 16 mm bh

XVII BAHAN PIPA


Pipa PVC tipe AW diameter 1/2" @4m btg
Pipa PVC tipe AW diameter 3/4" @4m btg
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

Pipa PVC tipe AW diameter 1" @4m btg


Pipa PVC tipe AW diameter 1 1/2" @4m btg
Pipa PVC tipe AW diameter 2" @4m btg
Pipa PVC tipe AW diameter 2 1/2" @4m btg
Pipa PVC tipe AW diameter 3" @4m btg
Pipa PVC tipe AW diameter 4" @4m btg
Pipa PVC tipe AW diameter 6" @4m btg
Pipa PVC tipe D diameter 1 1/2" @4m btg
Pipa PVC tipe D diameter 2" @4m btg

Pipa GIP Medium diameter 1/2" @6m btg


Pipa GIP Medium diameter 3/4" @6m btg
Pipa GIP Medium diameter 1" @6m btg
Pipa GIP Medium diameter 1 1/2" @6m btg
Pipa GIP Medium diameter 2" @6m btg

Pipa HDPE 4" SDR 11 (PN 16) @6m btg


Pipa HDPE 2" SDR 11 (PN 16) @6m btg

Gate Valve Cast Iron FCL diameter 4" bh


BWRO Pump ex Groundfos unt
Centrifugal Pump ex KSB Movitech VF-18 unt

XVIII SEWA ALAT


Mobile Crane kap 5 ton jam
Dump Truck 3 ton jam
Dump Truck 9 ton jam
Truk Bak Terbuka Engkel jam
Truk Tanki Air jam
Bulldozer 100 - 150 hp jam
Motor Grader jam
Wheel Loader jam
Excavator jam
Crane 35 ton jam
Flat Bed Truck jam
Baby Roller / Pedestrian jam
HARGA SATUAN BAHAN & ALAT
KEGIATAN : PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI :
TAHUN : 2017

NO. JENIS BAHAN SATUAN

P.Tire Roller 8 - 10 ton jam


Baby Roller jam
Vibrator Roller self 7 ton jam
Pile Driver / Hammer jam
Water Pump jam
Asphalt Sprayer jam
Pick Up single cabin jam
AMP jam
Asphalt Finisher jam
Concrete Vibrator jam
Compressor jam
Concrete Mixer 0,125m3 jam
Concrete Cutter jam
Stamper jam
Genset 5-25kva+bbm jam
Alat Pengecat Marka jam
Mesin Las jam
Stone Crusher jam
Truck Trailer trip
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
HARGA SATUAN
(Rp.)
HARGA SATUAN UPAH
KEGIATAN PEMBANGUNAN BLK KOMUNITAS WAHDATUT TAUHID
LOKASI 0
TAHUN 2017

NO. PEKERJA SATUAN

1 Tukang Galian Org / hr


2 Tukang Batu Org / hr
3 Tukang Las Org / hr
4 Tukang Besi Org / hr
5 Tukang Kaca/Alumunium/Gipsum Org / hr
6 Tukang Kayu Org / hr
7 Tukang Cat Org / hr
8 Tukang Plumbing Org / hr
9 Pembantu Instalator / Tukang Listrik Org / hr
10 Tukang Babat Rumput Org / hr
11 Tukang Taman Org / hr
12 Operator Alat Berat Org / hr
13 Pembantu Operator Org / hr
14 Pekerja / Kenek Org / hr