Anda di halaman 1dari 76

PROGRAM : PEMBANGUNAN TURAP/TALUD/BRONJONG

KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG


PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
LOKASI : KEC. MARISA KAB. POHUWATO
TAHUN ANGGARAN : 2009
KONTRAKTOR : CV. M - DUA

KONTRAKTOR : CV. M - DUA


KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009
NILAI KONTRAK : Rp 179,411,000.00

KONTRAK KONSULTAN 01/KONT/PPTK-PENGW/BM/DPU-PHWT/VII/2009


06 JULI 2009 02 Desember 2009
Rp 108,480,000.00

Marisa, November 2009


Dibuat Oleh :

Disetujui Oleh : Kontraktor Pelaksana : ,,,,, ,,,,,


Pejabat Pelaksana Teknis Kegiatan CV. M - DUA Direktur Pimpinan Tehnik
Dinas Pekerjaan Umum
Kab. Pohuwato Diperiksa :
Konsultan Pengawas : Ir. MISENAN IKHWANUL MUSLIMIN, ST
CV. MULTI CIPTA KONSULTAN Site Engineer Inspector
RINI MEILANI, ST
Nip. 19800511 200802 2 002 IGOR KARENGGA,ST
Inspector

Mengetahui, Pengawas Lapangan M.SADAT


Dinas PU Kab. POHUWATO Inspector

YUSTAM
Nip. 19770628200604 1 014

Asisten Teknik
Dinas PU Kab. POHUWATO

SUNU SUHANDOKO, ST
Nip. 19701123 200501 1 007
Pimpinan Tehnik

IKHWANUL MUSLIMIN, ST

IGOR KARENGGA,ST
DAFTAR KUANTITAS DAN HARGA

Kegiatan : Pembangunan / Peningkatan Jalan & Jembatan


Pekerjaan : Pembangunan Jalan Pohon Cinta Segmen 01
Lokasi : Kec. Marisa Kab. Pohuwato
Tahun Anggaran :2008
Kontraktor : CV. BERKAT MULIA

Mata Perkiraan Harga


Pemba- Uraian Satuan Kuantitas Satuan
yaran (Rp.)
a b c d e
DIVISI 1. MOBILISASI

1.2 Mobilisasi Ls 1.00 500,000.00

Jumlah Harga Pekerjaan Divisi 1 (masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DIVISI 2. DRAINASE
2.1 Galian untuk Selokan Drainase dan Saluran Air M' #REF! #REF!
2.2 Pasangan Batu dengan Mortar M3 1.00 500,000.00
2.3 (1) Gorong-Gorong Pipa Beton Bertulang Dia. Dalam 50 cm M' -
2.3 (2) Gorong-Gorong Pipa Beton Bertulang Dia. Dalam 50 -70 cm M' -
2.3 (3) Pipa Gorong-Gorong Beton Bertulang Dia. Dalam 70 - 100 Cm M' - -
2.3 (4) Pipa Gorong-Gorong Beton Bertulang Dia. Dalam 100 - 130 Cm M' -
2.3 (5) Pipa Gorong-Gorong Beton Bertulang Dia. Dalam 140 - 150 Cm M' -
2.3 (6) Gorong-Gorong Pipa Baja bergelombang Ton -
2.3 (7) Gorong-gorong pipa beton tanpa Tulang diameter Dalam 20 cm M' -
sampai 30 cm
2.4 (1) Timbunan Porous atau Bahan Penyering (Filter) M3 -
2.4 (2) Anyaman Filter Plastik M2 -
2.4 (3) Pipa bertulang banyak (Perforated Pipe) untuk Pek. Drainase M' #REF! #REF!
Bawah Permukaan

Jumlah Harga Pekerjaan Divisi 2 (masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DIVISI 3. PEKERJAAN TANAH
3.1 (1) Galian Biasa M3 - -
3.1 (2) Galian Batu M3 - -
3.1 (3) Galian Struktur Kedalaman 0 - 2 meter M3
3.1 (4) Galian Struktur Kedalaman 2 - 4 meter M3
3.1 (5) Galian Struktur Kedalaman 4 - 6 meter M3
3.1 (6) Coferdam, Penyokong, Pengaku dan Pekerjaan yg berkaitan Ls
3.1 (7) Galian Perkerasan Beraspal dengan Cold Milling Machine M3
3.1 (8) Galian Perkerasan Beraspal tanpa Cold Milling Machine M3
3.1 (9) Biaya Tambahan untuk Biaya Pengangkutan Bahan Galian
yang Melebihi 5 Km M3
3.2 (1) Timbunan Biasa dari Selain Galian Sumber Bahan M3 - -
3.2 (2) Timbunan Pilihan M3 138.60 3,064,446.00
3.2 (3) Timbunan Pilihan Atas Tanah Rawa (diukur diatas bak truck) M3
3.2 (4) Timbunan Batu dengan Manual M3
3.2 (5) Timbunan Batu dengan Derek M3
3.2 (6) Timbunan Batu dengan Derek Ton
3.3 Penyiapan Badan Jalan M2 340.50 60,019,197.95
3.4 Pengupasan Permukaan Aspal Lama dan Pencampuran
kembali (tebal 15 cm) M2

Jumlah Harga Pekerjaan Divisi 3 (masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DAFTAR KUANTITAS DAN HARGA

Kegiatan : Pembangunan / Peningkatan Jalan & Jembatan


Pekerjaan : Pembangunan Jalan Pohon Cinta Segmen 01
Lokasi : Kec. Marisa Kab. Pohuwato
Tahun Anggaran :2008
Kontraktor : CV. BERKAT MULIA

Mata Perkiraan Harga


Pemba- Uraian Satuan Kuantitas Satuan
yaran (Rp.)
a b c d e
DIVISI 4. PERBAIKAN TEPI PERKERASAN DAN
BAHU JALAN
4.2 (1) Lapis Pondasi Agregat Kelas A M3 -
4.2 (2) Lapis Pondasi Agregat Kelas B M3 1.00 0
4.2 (3) Lapis Pondasi Semen Tanah M3 -
4.2 (4) Semen untuk Lapis Pondasi Semen Tanah Ton -
4.2 (5) Laburan Aspal satu Lapis (BURTU) M2 -
4.2 (6) Bahan Aspal untuk Pekerjaan Laburan Liter -
4.2 (7) Lapis Resap Pengikat Liter -

Jumlah Harga Pekerjaan Devisi.4 (masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DIVISI 5. PERKERASAN BERBUTIR
5.1 (1) Lapis Pondasi Agregat Kelas A M3 #REF! #REF!
5.1 (2) Lapis Pondasi Agregat Kelas B M3 -
5.2 (1) Lapis Pondasi Agregat Kelas C M3 -
5.4 (1) Semua untuk Lapis Pondasi Semen Tanah Ton -
5.4 (2) Lapis Pondasi Semen Tanah M3 -

Jumlah Harga Pekerjaan Devisi.5 (masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DIVISI 6. PERKERASAN ASPAL
6.1 (1) Lapis Resap Pengikat Liter #REF! #REF!
6.1 (2) Lapis Perekat Liter - -
6.2 (1) Agregat Penutup BURTU M2
6.2 (2) Agregat Penutup BURDA M2
6.2 (3) Bahan Aspal untuk Pekerjaan Laburan Liter
6.3 (1) Latasir (SS) Kelas A M2
6.3 (2) Latasir (SS) Kelas B M2
6.3 (3) Lataston - Lapis Aus (HRS-WC) M2
6.3 (4) Lataston - Lapis Pondasi (HRS-Base) M3
6.3 (5a) Lataston - Lapis Aus (AC - WC) M2
6.3 (5c) Lataston - Lapis Pengikat (AC - BC) Leveling Ton
6.3 (6) Lapis Aus Aspal Beton (AC-BC) M3 #REF! #REF!
6.3 (6c) Lataston Lapis Antara (AC-BC) Leveling Ton
6.3 (7a) Lataston Lapis Pondasi (AC-WC) M3
6.3 (7c) Lataston Lapis Pondasi (AC-WC) Leveling Ton
Skh. 6.3.b (1a) Camp. Hangat Asbuton Lap. Aus (AC-WC AsbH) T 20/25 (t= 4 cm) M2 - -
Skh. 6.3.b (1b) Camp. Hangat Asbuton Lap. Aus (AC-WC AsbH) Leveling T 20/25 (t ≥ 3 cm) Ton -
Skh. 6.3.b (2a) Camp. Hangat Asbuton Lap. Permuk. Antara (AC-BC AsbH) T 20/25 (t= 5 cm) M3 - -
Skh. 6.3.b (2b) Camp. Hangat Asbuton Lap. Permuk. Antara (AC-BC AsbH) Leveling T 20/25 (t ≥ 5 cm) Ton
Skh. 6.3.b (3a) Camp. Hangat Asbuton Lap. Permuk. Antara (AC-BC AsbH) T 20/25 (t= 6 cm) M3
Skh. 6.3.b (3b) Camp. Hangat Asbuton Lap. Permuk. Antara (AC-BC AsbH) Leveling T 20/25 (t ≥ 6 cm) Ton
6.6 Lapis Penetrasi Macadam Perata (Leveling) M3

Jumlah Harga Penawaran Devisi.6 (masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DAFTAR KUANTITAS DAN HARGA

Kegiatan : Pembangunan / Peningkatan Jalan & Jembatan


Pekerjaan : Pembangunan Jalan Pohon Cinta Segmen 01
Lokasi : Kec. Marisa Kab. Pohuwato
Tahun Anggaran :2008
Kontraktor : CV. BERKAT MULIA

Mata Perkiraan Harga


Pemba- Uraian Satuan Kuantitas Satuan
yaran (Rp.)
a b c d e
DIVISI VII : STUKTUR
7.1 (1) Beton K500 M3 -
7.1 (2) Beton K400 M3 -
7.1 (3) Beton K350 M3 -
7.1 (4) Beton K300 M3 -
7.1 (5) Beton K250 M3 - -
7.1 (6) Beton K175 M3 -
7.1 (7) Beton Siklop K175 M3 #REF! #REF!
7.1 (8) Beton K125 M3 -
7.2 (1) Unit Pracetak Gelagar Type I Bentang 13.60 Meter Bh -
7.2 (2) Unit Pracetak Gelagar Type I Bentang 16.60 Meter Bh -
7.2 (3) Unit Pracetak Gelagar Type I Bentang 19.60 Meter Bh -
7.2 (4) Unit Pracetak Gelagar Type I Bentang 22.60 Meter Bh -
7.2 (5) Unit Pracetak Gelagar Type I Bentang 25.60 Meter Bh -
7.2 (6) Unit Pracetak Gelagar Type I Bentang 28.60 Meter Bh -
7.2 (7) Unit Pracetak Gelagar Type I Bentang 31.60 Meter Bh -
7.2 (8) Baja Prategang Kg -
7.2 (9) Plat Berongga (Hollow Slab) Pracetak Bentang 8.25 Meter Bh -
7.2 (10) Plat Berongga (Hollow Slab) Pracetak Bentang 10.25 Meter Bh -
7.2 (11) Beton Diafragma K350 termasuk Pekerjaan Pra Penegangan M3 -
7.2 (12) Plat Lantai / Dek Siap Pakai Mutu Beton K350 Bh -
7.3 (1) Baja Tulangan U-24 Polos Kg - -
7.3 (2) Baja Tulang U32 Polos Kg -
7.3 (3) Baja Tulang D32 Ulir Kg -
7.3 (4) Baja Tulangan D39 Ulir Kg -
7.3 (5) Baja Tulangan D48 Ulir Kg -
7.3 (6) Anyaman Kawat yang Dilas (Welded Wire Mesh) Kg -
7.4 (1) Baja Struktur Titik Leleh 2500 kg/cm2 Kg -
7.4 (2) Baja Struktur Titik Leleh 2800 kg/cm2 Kg -
7.4 (3) Baja Struktur Titik Leleh 3500 kg/cm2 Kg -
7.5 (1) Pemasangan Jembatan Rangka Baja Kg -
7.5 (2) Pengangkutan Material Jembatan Kg -
7.6. (1) Pondasi Cerucuk, Penyediaan dan Pemancangan M' -
7.6. (2) Dinding Turap Kayu Tanpa Pengawetan M2 -
7.6. (3) Dinding Turat Kayu dengan Pengawetan M2 -
7.6. (4) Dinding Turap baja M2 -
7.6. (5) Dinding Turap Beton M2 -
7.6 (6) Penyediaan Tiang Pancang Kayu Tanpa Pengawetan M3 -
7.6 (7) Penyediaan Tiang Pancang Kayu dengan Pengawetan M3 -
7.6 (8) Penyediaan Tiang Pancang Baja Kg -
7.6 (9) Penyediaan Tiang Pancang Beton Bertulang Pracetak M3 -
7.6 (10) Penyediaan Tiang Pancang Beton Pracetak M3 -
7.6 (11) Pemancangan Tiang Pancang Kayu M' -
7.6 (12) Pemancangan Tiang Pancang Pipa Baja : Diameter 400 mm M' -
7.6 (13) Pemancangan Tiang Pancang Pipa Baja : Diameter 500 mm M' -
7.6 (14) Pemancangan Tiang Pancang Pipa Baja : Diameter 600 mm M' -
7.6 (15) Penyediaan Tiang Pancang Beton Pracetak : M' -
30 cm x 30 cm atau diameter 300 mm
7.6 (16) Penyediaan Tiang Pancang Beton Pracetak : M' -
40 cm x 40 cm atau diameter 400 mm
7.6 (17) Penyediaan Tiang Pancang Beton Pracetak : M' -
50 cm x 50 cm atau diameter 500 mm -

Bersambung ke Halaman Berikut


DAFTAR KUANTITAS DAN HARGA

Kegiatan : Pembangunan / Peningkatan Jalan & Jembatan


Pekerjaan : Pembangunan Jalan Pohon Cinta Segmen 01
Lokasi : Kec. Marisa Kab. Pohuwato
Tahun Anggaran :2008
Kontraktor : CV. BERKAT MULIA

Mata Perkiraan Harga


Pemba- Uraian Satuan Kuantitas Satuan
yaran (Rp.)
a b c d e
7.6 (18) Tiang Bor Beton Diameter 600 mm M' -
7.6 (19) Tiang Bor Beton Diameter 800 mm M' -
7.6 (20) Tiang Bor Beton Diameter 1000 mm M' -
7.6 (21) Tiang Bor Beton Diameter 1200 mm M' -
7.6 (22) Tiang Bor Beton Diameter 1500 mm M' -
7.6 (23) Tambahan Biaya untuk nomor mata pembayaran 7.6 (11) s/d M' -
7.6 (17) Bila tiang pancang beton dikerjakan ditempat berair.
7.6 (24) Tambahan Biaya untuk nomor mata pembayaran 7.6 (18) s/d M' -
7.6 (22) Bila tiang Bor beton dikerjakan ditempat berair.
7.6 (25) Pengujian Pembebanan pada Tiang dengan Diameter sampai Buah -
600 mm
7.6 (26) Pengujian Pembebanan pada Tiang dengan Diameter diatas Buah -
600 mm
7.7 (1) Penyediaan Dinding Sumuran silinder, Diameter 250 cm M' -
7.7 (2) Penyediaan Dinding Sumuran silinder, Diameter 300 cm M' -
7.7 (3) Penyediaan Dinding Sumuran silinder, Diameter 350 cm M' -
7.7 (4) Penyediaan Dinding Sumuran silinder, Diameter 400 cm M' -
7.7 (5) Penurunan Dinding Sumuran silinder, Diameter 250 cm M' -
7.7 (6) Penurunan Dinding Sumuran silinder, Diameter 300 cm M' -
7.7 (7) Penurunan Dinding Sumuran silinder, Diameter 350 cm M' -
7.7 (8) Penurunan Dinding Sumuran silinder, Diameter 400 cm M' -
7.9 Pasangan Batu M3 - -
7.10 (1) Pasangan Batu Kosong Diisi Adukan M3 -
7.10 (2) Pasangan Batu Kosong M3 -
7.10 (3) Bronjong (Gabion) M3 -
7.11 (1) Expansion Joint Tipe Torma M' -
7.11 (2) Expansion Joint Tipe Rubber 1 M' -
7.11 (3) Expansion Joint Tipe Rubber 2 M' -
7.11 (4) Expansion Joint Tipe Rubber 3 M' -
7.11 (5) Joint Filler untuk Sambungan Konstruksi M' -
7.11 (6) Expansion Joint Tipe Baja Bersudut M' -
7.12 (1) Perletakan Logam Buah -
7.12 (2) Perletakan Elastometrik Jenis 1 Buah -
7.12 (5) Perletakan Strip M' -
7.13 Sandaran Jembatan M' -
7.14 Papan Nama Jembatan Buah -
7.15 (1) Pembongkaran Pasangan batu M3 -
7.15 (2) Pembongkaran Beton M3 -
7.15 (3) Pembongkaran Beton Pratekan M3 -
7.15 (4) Pembongkaran Bangunan Gedung M2 -
7.15 (5) Pembongkaran Rangka Baja M2 -
7.15 (6) Pembongkaran Balok Baja (Steel Stringers) M' -
7.15 (7) Pembongkaran Lantai Jembatan Kayu M2 -
7.15 (8) Pembongkaran Jembatan Kayu M2 -
7.15 (9) Pengangkutan Hasil Bongkaran yang melebihi 5 km M3/Km -

Jumlah Harga Pekerjaan Divisi 7 (Masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DAFTAR KUANTITAS DAN HARGA

Kegiatan : Pembangunan / Peningkatan Jalan & Jembatan


Pekerjaan : Pembangunan Jalan Pohon Cinta Segmen 01
Lokasi : Kec. Marisa Kab. Pohuwato
Tahun Anggaran :2008
Kontraktor : CV. BERKAT MULIA

Mata Perkiraan Harga


Pemba- Uraian Satuan Kuantitas Satuan
yaran (Rp.)
a b c d e
DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR
8.1 (1) Lapis Pondasi Agregat Kelas A untuk Pekerjaan Minor M3 -
8.1 (2) Lapis Pondasi Agregat Kelas B untuk Pekerjaan Minor M3 -
8.1 (3) Agregat untuk Lapis Pondasi Jalan tanpa Penutup untuk M3 -
Pekerjaan Minor
8.1 (4) Waterbound Macadam untuk Pekerjaan Minor M3 -
8.1 (5) Campuran Aspal Panas untuk Pekerjaan Minor M3 -
8.1 (6) Lasbutag atau Latasbusir untuk Pekerjaan Minor M3 -
8.1 (7) Penetrasi Macadam untuk Pekerjaan Minor M3 -
8.1 (8) Campuran Aspal Dingin untuk Pekerjaan Minor M3 -
8.1 (9) Bitiumen Residual untuk Pekerjaan Minor Liter -
8.2 (1) Galian untuk Bahu Jalan dan Pekerjaan Minor Lainnya M3 -
8.2 (2) Pemotongan Pohon Diameter 15 - 30 cm Buah -
8.2 (3) Pemotongan Pohon Diameter 30 - 50 cm Buah -
8.2 (4) Pemotongan Pohon Diameter 50 - 75 cm Buah -
8.2 (5) Pemotongan Pohon Diameter > 75 cm Buah -
8.3 (1) Stabilisasi dengan Tanaman M2 #REF! #REF!
8.3 (2) Perdu M2 -
8.3 (3) Penanaman Pohon Buah #REF! #REF!
8.3 (4) Tanah Subur M3 #REF! #REF!
8.4 (1) Marka Jalan Bukan Thermoplastik M2 #REF! #REF!
8.4 (2) Marka Jalan Thermoplastik M2 - -
8.4 (5) Patok Pengarah Buah -
8.4 (6) Patok Kilometer Buah -
8.4 (6) Patok Kilometer Buah -
8.4 (7) Rel Pengaman M1 -
8.4 (8) Paku Jalan (Road Studs) Buah -
8.4 (9) Mata Kucing (cat eyes) Buah -
8.4 (10) Kerb Pracetak Buah #REF! #REF!
8.4 (11) Kerb yang Digunakan Kembali M' -
8.4 (12) Perkerasan Blok Beton pad Trotoar dan Median M2 #REF! #REF!
8.5 (1) Pengembalian Kondisi Lantai Jembatan Beton M2 -
8.5 (2) Pengembalian Kondisi Lantai Jembatan Kayu M2 -
8.5 (3) Pengembalian Kondisi Pelapisan Permukaan Baja Struktur M2 -
8.6 (1) Lampu Mercuri Bh #REF! #REF!
8.6 (2) Lampu Hias Bh #REF! #REF!

Jumlah Harga Pekerjaan Divisi 8 (Masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DAFTAR KUANTITAS DAN HARGA

Kegiatan : Pembangunan / Peningkatan Jalan & Jembatan


Pekerjaan : Pembangunan Jalan Pohon Cinta Segmen 01
Lokasi : Kec. Marisa Kab. Pohuwato
Tahun Anggaran :2008
Kontraktor : CV. BERKAT MULIA

Mata Perkiraan Harga


Pemba- Uraian Satuan Kuantitas Satuan
yaran (Rp.)
a b c d e
DIVISI 9. PEKERJAAN HARIAN
9.1 Mandor Jam -
9.2 Pekerja Biasa Jam -
9.3 Tukang Kayu, Tukang Batu, dsb Jam -
9.4 Dump Truck 3-4 M3 Jam -
9.5 Truck dengan Bak Terbuka Kapasistas 3-4 ton Jam -
9.6 Tangki Air 3000 - 4500 Liter Jam -
9.7 Bulldozer 100 - 150 HP Jam -
9.8 Motor Greader Min. 100 HP Jam -
9.9 Whell Loader 1,0 - 1,6 M3 Jam -
9.10 Treck Loader 75 - 100 HP Jam -
9.11 Excavator 80 - 140 HP Jam -
9.12 Crane 10 -15 Ton Jam -
9.13 Mesin Gilas Roda Besi 6 - 9 Ton Jam -
9.14 Mesin Gilas Bervibrasi 5 - 8 Ton Jam -
9.15 Pemadat dengan Bervibrasi 1.5 - 3.0 HP Jam -
9.16 Mesin Gilas Roda Karet 8 - 10 Ton Jam -
9.17 Kompressor 4000 - 6500 liter/menit Jam -
9.18 Mesin Pengaduk Beton 0.3 - 0.6 M3 Jam -
9.19 Pompa Air 70 - 100 mm Jam -

Jumlah Harga Pekerjaan Divisi 9 (Masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
DIVISI 10. PEKERJAAN PEMELIHARAAN RUTIN
10.1 (1) Pemeliharaan Rutin Perkerasan Ls - -
10.1 (2) Pemeliharaan Rutin Bahu Jalan Ls - -
10.1 (3) Pemeliharaan Rutin Selokan, Saluran Air, galian & Timbunan Ls - -
10.1 (4) Pemeliharaan Rutin Perlengkapan Jalan Ls -
10.1 (5) Pemeliharaan Rutin Jembatan Ls -

Jumlah Harga Pekerjaan Divisi 10 (Masuk pada Rekapitulasi Daftar Kuantitas dan Harga)
AFTAR KUANTITAS DAN HARGA

Jumlah
Harga
(Rp.)
f = (d x e)

500,000.00

500,000.00

#REF!
500,000.00

#REF!

#REF!

-
-

-
424,732,215.60

20,436,536,901.98

20,861,269,117.58
DAFTAR KUANTITAS DAN HARGA

Jumlah
Harga
(Rp.)
f = (d x e)

#REF!

#REF!

#REF!
-

#REF!

#REF!
DAFTAR KUANTITAS DAN HARGA

Jumlah
Harga
(Rp.)
f = (d x e)

#REF!

-
-
-
DAFTAR KUANTITAS DAN HARGA

Jumlah
Harga
(Rp.)
f = (d x e)

-
-

-
DAFTAR KUANTITAS DAN HARGA

Jumlah
Harga
(Rp.)
f = (d x e)

#REF!

#REF!
#REF!
#REF!
-

#REF!

#REF!

#REF!
#REF!

#REF!
DAFTAR KUANTITAS DAN HARGA

Jumlah
Harga
(Rp.)
f = (d x e)

-
-
-
-
-

-
REKAPITULASI
BULAN PERTAMA ( I ) 01 OKTOBER 2009 - 28 OKTOBER 2009

KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG


PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
LOKASI : KEC. MARISA KAB. POHUWATO
TAHUN ANGGARAN : 2009
KONTRAKTOR : CV. M - DUA

KONTRAK
No.
Uraian Jumlah Harga Bobot
Devisi
( Rp. ) (%)

1 BIAYA UMUM / PEKERJAAN PERSIAPAN Rp 2,550,000.00 1.563

2 PEKERJAAN BRONJONG Rp 158,551,459.80 97.210

3 PEKERJAAN FINISHING Rp 2,000,000.00 1.226

A Jumlah Harga Pekerjaan Rp 163,101,459.80 100.000


B PPN ( 10%) Rp. 16,310,145.98
C Jumlah total Harga Pekerjaan Rp. 179,411,605.78
D Dibulatkan 179,411,000.00

Terbilang :
" Empat Puluh Satu Juta Seratus Tujuh Puluh Lima Ribu Rupiah "
REKAPITULASI
RTAMA ( I ) 01 OKTOBER 2009 - 28 OKTOBER 2009

UATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH

REALISASI
Jumlah Harga Bobot
( Rp. ) (%)

Rp 2,050,000.00 1.26

Rp 65,963,078.20 40.44

Rp - 0.00

Rp 68,013,078.20 41.70

h Satu Juta Seratus Tujuh Puluh Lima Ribu Rupiah "


REKAPITULASI
BULAN KEDUA ( II ) 29 OKTOBER 2009 - 29 NOVEMBER 2009

KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG


PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
LOKASI : KEC. MARISA KAB. POHUWATO
TAHUN ANGGARAN : 2009
KONTRAKTOR : CV. M - DUA

KONTRAK
No.
Uraian Jumlah Harga Bobot
Devisi
( Rp. ) (%)

1 BIAYA UMUM / PEKERJAAN PERSIAPAN Rp 2,550,000.00 1.563

2 PEKERJAAN BRONJONG Rp 158,551,459.80 97.210

3 PEKERJAAN FINISHING Rp 2,000,000.00 1.226

A Jumlah Harga Pekerjaan Rp 163,101,459.80 100.000


B PPN ( 10%) Rp. 16,310,145.98
C Jumlah total Harga Pekerjaan Rp. 179,411,605.78
D Dibulatkan 179,411,000.00

Terbilang :
" Dua Puluh Juta Delapan Ratus Delapan Puluh Ribu Rupiah "
REKAPITULASI
DUA ( II ) 29 OKTOBER 2009 - 29 NOVEMBER 2009

UATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH

REALISASI
Jumlah Harga Bobot
( Rp. ) (%)

Rp 2,550,000.00 1.563

Rp 158,551,459.80 97.210

Rp 2,000,000.00 1.226

Rp 163,101,459.80 100.000

Juta Delapan Ratus Delapan Puluh Ribu Rupiah "


SERTIFIKAT BULANAN KONTRAK
MONTHLY CERTIFICATE (MC)

KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG


PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TE T. ANGGARAN : 2009
KONSULTAN : CV. MULTI CIPTA KONSULTAN MC. NOMOR : 01 (SATU )
KONTRAKTOR : CV. M - DUA BULAN : OKTOBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TANGGAL : 25 MEI 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009

HARGA KONTRAK TERCAPAI


No. URAIAN KEGIATAN
(Rp) BULAN INI (Rp)

1 BIAYA UMUM / PEKERJAAN PERSIAPAN Rp. 2,550,000.00 Rp. 2,050,000.00

2 PEKERJAAN BRONJONG Rp. 158,551,459.80 Rp. 65,963,078.20

3 PEKERJAAN FINISHING Rp. 2,000,000.00 Rp. -

A. SUB TOTAL Rp. 163,101,459.80 Rp. 68,013,078.20


B. PPN 10 % Rp. 16,310,145.98 Rp. 6,801,307.82
C. SUB TOTAL + PPN 10 % Rp. 179,411,605.78
D. TOTAL HARGA KONTRAK (DI BULATKAN) Rp. 179,411,600.00
E. TOTAL PEMBAYARAN S/D BULAN INI Rp. 74,814,386.02
F. MATERIAL ON SITE Rp. -
G. JUMLAH SERTIFIKAT BULANAN SEBELUM POTONGAN Rp. 74,814,386.02
POTONGAN - POTONGAN :
1. SERTIFIKAT BULANAN S/D BULAN LALU Rp. -
2. RETENSI 5 % SESUAI KONTRAK x G Rp. 3,740,719.30
3. PEMBAYARAN KEMBALI UANG MUKA 20 % x G Rp. 14,962,877.20
4. LAIN - LAIN Rp. -
H. JUMLAH POTONGAN Rp. 18,703,596.51
I. JUMLAH PEMBAYARAN SERTIFIKAT BULANAN (DI BULATKAN) Rp. 56,110,789.52
TERBILANG :
JUMLAH PEMBAYARAN :
FISIK (100/110 x I ) J Rp. 51,009,808.65
Terbilang :
PPN (DIPUNGUT) (10/110 x I ) K. Rp. 5,100,980.87
Terbilang :
TOTAL SERTIFIKAT BULANAN L. Rp. 56,110,789.52
Terbilang :

Sampai Dengan Bulan ini


KEMAJUAN YANG DICAPAI : Bulan Lalu
Bulan Ini
KAT BULANAN KONTRAK
NTHLY CERTIFICATE (MC)

01 (SATU )
OKTOBER 2009
25 MEI 2009

TERCAPAI BOBOT
BULAN INI (Rp) (%)

Rp. 2,050,000.00 1.26

Rp. 65,963,078.20 40.44

Rp. - 0.00

Rp. 68,013,078.20 41.70


Rp. 6,801,307.82

Rp. 74,814,386.02
Rp. -
Rp. 74,814,386.02

Rp. 18,703,596.51
Rp. 56,110,789.52

Rp. 51,009,808.65

Rp. 5,100,980.87

Rp. 56,110,789.52

41.70
0.00
41.70
SERTIFIKAT BULANAN KONTRAK
MONTHLY CERTIFICATE (MC)

KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG


PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TE T. ANGGARAN : 2009
KONSULTAN : CV. MULTI CIPTA KONSULTAN MC. NOMOR : 02 (DUA )
KONTRAKTOR : CV. M - DUA BULAN : NOVEMBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TANGGAL : 25 MEI 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009

HARGA KONTRAK TERCAPAI


No. URAIAN KEGIATAN
(Rp) BULAN INI (Rp)

1 BIAYA UMUM / PEKERJAAN PERSIAPAN Rp. 2,550,000.00 Rp. 2,550,000.00

2 PEKERJAAN BRONJONG Rp. 158,551,459.80 Rp. 158,551,459.80

3 PEKERJAAN FINISHING Rp. 2,000,000.00 Rp. 2,000,000.00

A. SUB TOTAL Rp. 163,101,459.80 Rp. 163,101,459.80


B. PPN 10 % Rp. 16,310,145.98 Rp. 16,310,145.98
C. SUB TOTAL + PPN 10 % Rp. 179,411,605.78
D. TOTAL HARGA KONTRAK (DI BULATKAN) Rp. 179,411,600.00
E. TOTAL PEMBAYARAN S/D BULAN INI Rp. 179,411,605.78
F. MATERIAL ON SITE Rp. -
G. JUMLAH SERTIFIKAT BULANAN SEBELUM POTONGAN Rp. 179,411,605.78
POTONGAN - POTONGAN :
1. SERTIFIKAT BULANAN S/D BULAN LALU Rp. -
2. RETENSI 5 % SESUAI KONTRAK x G Rp. 8,970,580.29
3. PEMBAYARAN KEMBALI UANG MUKA 20 % x G Rp. 35,882,321.16
4. LAIN - LAIN Rp. -
H. JUMLAH POTONGAN Rp. 44,852,901.45
I. JUMLAH PEMBAYARAN SERTIFIKAT BULANAN (DI BULATKAN) Rp. 134,558,704.34
TERBILANG :
JUMLAH PEMBAYARAN :
FISIK (100/110 x I ) J Rp. 122,326,094.85
Terbilang :
PPN (DIPUNGUT) (10/110 x I ) K. Rp. 12,232,609.49
Terbilang :
TOTAL SERTIFIKAT BULANAN L. Rp. 134,558,704.34
Terbilang :

Sampai Dengan Bulan ini


KEMAJUAN YANG DICAPAI : Bulan Lalu
Bulan Ini
KAT BULANAN KONTRAK
NTHLY CERTIFICATE (MC)

02 (DUA )
NOVEMBER 2009
25 MEI 2009

TERCAPAI BOBOT
BULAN INI (Rp) (%)

Rp. 2,550,000.00 1.56

Rp. 158,551,459.80 97.21

Rp. 2,000,000.00 1.23

Rp. 163,101,459.80 100.00


Rp. 16,310,145.98

Rp. 179,411,605.78
Rp. -
Rp. 179,411,605.78

Rp. 44,852,901.45
Rp. 134,558,704.34

Rp. 122,326,094.85

Rp. 12,232,609.49

Rp. 134,558,704.34

100.00
0.00
100.00
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM BULAN PERTAMA ( I ) 01 OKTOBER 2009 - 28 OKTOBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA BULAN LALU BULAN INI S/D BULAN INI
URAIAN PEKERJAAN SAT HARGA SATUAN JUMLAH HARGA BOBOT TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.00 0.00 0.50 0.31 0.50 0.31 50.00
2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 0.00 0.00 1.00 0.46 1.00 0.46 100.00
3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 1.00 0.31 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 0.00 0.00 1.00 0.18 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 0.00 0.00 138.60 1.88 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 0.00 0.00 135.35 36.80 135.35 36.80 39.75
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 0.00 0.00 7.25 0.07 7.25 0.07 21.58
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 0.00 0.00 36.50 1.70 36.50 1.70 69.52

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 0.00 41.70 41.70

15
KTOBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,050,000.00

0.31 500,000.00
0.46 750,000.00
0.31 500,000.00
0.18 300,000.00

65,963,078.20

1.88 3,064,446.00
36.80 60,019,197.95
0.07 111,091.75
1.70 2,768,342.50

0.00

0.00 0.00
0.00 0.00

41.70 68,013,078.20

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM BULAN KEDUA ( II ) 29 OKTOBER 2009 - 29 NOVEMBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA BULAN LALU BULAN INI S/D BULAN INI
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA BOBOT
TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT

1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.50 0.31 0.50 0.31 1.00 0.61 100.00
2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 1.00 0.46 0.00 0.00 1.00 0.46 100.00
3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 1.00 0.31 0.00 0.00 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 1.00 0.18 0.00 0.00 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 138.60 1.88 0.00 0.00 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 135.35 36.80 205.15 55.78 340.50 92.57 100.00
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 7.25 0.07 26.35 0.25 33.60 0.32 100.00
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 36.50 1.70 16.00 0.74 52.50 2.44 100.00

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 1.00 0.31 1.00 0.31 100.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 1.00 0.92 1.00 0.92 100.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 41.70 58.30 100.00

15
VEMBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,550,000.00

0.61 1,000,000.00
0.46 750,000.00
0.31 500,000.00
0.18 300,000.00

158,551,459.80

1.88 3,064,446.00
92.57 150,990,298.50
0.32 514,852.80
2.44 3,981,862.50

2,000,000.00

0.31 500,000.00
0.92 1,500,000.00

100.00 163,101,459.80

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM MINGGU PERTAMA ( I ) 01 OKTOBER 2009 - 07 OKTOBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA
URAIAN PEKERJAAN SAT MINGGU LALU MINGGU INI S/D MINGGU INI TERTIMBANG
PEMBAYARAN HARGA SATUAN JUMLAH HARGA BOBOT
VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.00 0.00 0.50 0.31 0.50 0.31 50.00
2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 0.00 0.00 1.00 0.46 1.00 0.46 100.00
3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 1.00 0.31 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 0.00 0.00 1.00 0.18 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 0.00 1.26 1.26

15
OKTOBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,050,000.00

0.31 500,000.00
0.46 750,000.00
0.31 500,000.00
0.18 300,000.00

0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00

0.00 0.00
0.00 0.00

1.26 2,050,000.00

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM MINGGU KEDUA ( II ) 08 OKTOBER 2009 - 14 OKTOBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA MINGGU LALU MINGGU INI S/D MINGGU INI
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA BOBOT
TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.50 0.31 0.00 0.00 0.50 0.31 50.00
2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 1.00 0.46 0.00 0.00 1.00 0.46 100.00

3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 1.00 0.31 0.00 0.00 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 1.00 0.18 0.00 0.00 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 0.00 0.00 138.60 1.88 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 0.00 0.00 0.00 0.00 0.00 0.00 0.00

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 1.26 1.88 3.14

15
KTOBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,050,000.00

0.31 500,000.00
0.46 750,000.00

0.31 500,000.00
0.18 300,000.00

3,064,446.00

1.88 3,064,446.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00

0.00 0.00
0.00 0.00

3.14 5,114,446.00

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM MINGGU KETIGA ( III ) 15 OKTOBER 2009 - 21 OKTOBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA BOBOT
MINGGU LALU MINGGU INI S/D MINGGU INI TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.50 0.31 0.00 0.00 0.50 0.31 50.00

2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 1.00 0.46 0.00 0.00 1.00 0.46 100.00

3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 1.00 0.31 0.00 0.00 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 1.00 0.18 0.00 0.00 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 138.60 1.88 0.00 0.00 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 0.00 0.00 68.10 18.51 68.10 18.51 20.00
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 0.00 0.00 0.00 0.00 0.00 0.00 0.00
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 0.00 0.00 15.00 0.70 15.00 0.70 28.57

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 3.14 19.21 22.35

15
OKTOBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,050,000.00

0.31 500,000.00

0.46 750,000.00

0.31 500,000.00
0.18 300,000.00

34,400,180.70

1.88 3,064,446.00
18.51 30,198,059.70
0.00 0.00
0.70 1,137,675.00

0.00

0.00 0.00
0.00 0.00

22.35 36,450,180.70

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM MINGGU KEEMPAT ( IV ) 22 OKTOBER 2009 - 28 OKTOBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA MINGGU LALU MINGGU INI S/D MINGGU INI
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA BOBOT
TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.50 0.31 0.00 0.00 0.50 0.31 50.00
2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 1.00 0.46 0.00 0.00 1.00 0.46 100.00
3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 1.00 0.31 0.00 0.00 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 1.00 0.18 0.00 0.00 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 138.60 1.88 0.00 0.00 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 68.10 18.51 67.25 18.28 135.35 36.80 39.75
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 0.00 0.00 7.25 0.07 7.25 0.07 21.58
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 15.00 0.70 21.50 1.00 36.50 1.70 69.52

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 22.35 19.35 41.70

15
OKTOBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,050,000.00

0.31 500,000.00
0.46 750,000.00
0.31 500,000.00
0.18 300,000.00

65,963,078.20

1.88 3,064,446.00
36.80 60,019,197.95
0.07 111,091.75
1.70 2,768,342.50

0.00

0.00 0.00
0.00 0.00

41.70 68,013,078.20

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM MINGGU KELIMA ( V ) 29 OKTOBER 2009 - 04 NOVEMBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA MINGGU LALU MINGGU INI S/D MINGGU INI
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA BOBOT
TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.50 0.31 0.00 0.00 0.50 0.31 50.00
2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 1.00 0.46 0.00 0.00 1.00 0.46 100.00
3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 1.00 0.31 0.00 0.00 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 1.00 0.18 0.00 0.00 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 138.60 1.88 0.00 0.00 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 135.35 36.80 63.55 17.28 198.90 54.08 58.41
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 7.25 0.07 8.15 0.08 15.40 0.14 45.83
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 36.50 1.70 16.00 0.74 52.50 2.44 100.00

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 41.70 18.10 59.80

15
OVEMBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,050,000.00

0.31 500,000.00
0.46 750,000.00
0.31 500,000.00
0.18 300,000.00

95,481,902.00

1.88 3,064,446.00
54.08 88,199,619.30
0.14 235,974.20
2.44 3,981,862.50

0.00

0.00 0.00
0.00 0.00

59.80 97,531,902.00

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM MINGGU KEENAM ( VI ) 05 NOVEMBER 2009 - 11 NOVEMBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA BOBOT
MINGGU LALU MINGGU INI S/D MINGGU INI TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.50 0.31 0.00 0.00 0.50 0.31 50.00
2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 1.00 0.46 0.00 0.00 1.00 0.46 100.00
3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 1.00 0.31 0.00 0.00 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 1.00 0.18 0.00 0.00 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 138.60 1.88 0.00 0.00 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 198.90 54.08 68.95 18.75 267.85 72.82 78.66
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 15.40 0.14 8.95 0.08 24.35 0.23 72.47
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 52.50 2.44 0.00 0.00 52.50 2.44 100.00

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 59.80 18.83 78.63

15
NOVEMBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,050,000.00

0.31 500,000.00
0.46 750,000.00
0.31 500,000.00
0.18 300,000.00

126,194,024.00

1.88 3,064,446.00
72.82 118,774,600.45
0.23 373,115.05
2.44 3,981,862.50

0.00

0.00 0.00
0.00 0.00

78.63 128,244,024.00

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM MINGGU KETUJUH ( VII ) 12 NOVEMBER 2009 - 18 NOVEMBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA BOBOT
MINGGU LALU MINGGU INI S/D MINGGU INI TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.50 0.31 0.00 0.00 0.50 0.31 50.00

2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 1.00 0.46 0.00 0.00 1.00 0.46 100.00
3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 1.00 0.31 0.00 0.00 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 1.00 0.18 0.00 0.00 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 138.60 1.88 0.00 0.00 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 267.85 72.82 72.65 19.75 340.50 92.57 100.00
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 24.35 0.23 9.25 0.09 33.60 0.32 100.00
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 52.50 2.44 0.00 0.00 52.50 2.44 100.00

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 78.63 19.84 98.47

15
NOVEMBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,050,000.00

0.31 500,000.00

0.46 750,000.00
0.31 500,000.00
0.18 300,000.00

158,551,459.80

1.88 3,064,446.00
92.57 150,990,298.50
0.32 514,852.80
2.44 3,981,862.50

0.00

0.00 0.00
0.00 0.00

98.47 160,601,459.80

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO PROGRESS REPORT


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM MINGGU KEDELAPAN ( VIII ) 19 NOVEMBER 2009 - 25 NOVEMBER 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
CV. MULTI CIPTA KONSULTAN
General Engineering Consultant
KONTRAK VOLUME YANG DIKERJAKAN
BOBOT
MATA MINGGU LALU MINGGU INI S/D MINGGU INI
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA BOBOT
TERTIMBANG
PEMBAYARAN VOLUME (%)
( Rp. ) ( Rp.) (%) VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14

BIAYA UMUM / PEKERJAAN PERSIAPAN 2,550,000.00

1 Mobilisasi dan Demobilisasi Alat Ls 1.00 1,000,000.00 1,000,000.00 0.61 0.50 0.31 0.50 0.31 1.00 0.61 100.00
2 Pengukuran / pemasangan patok Ls 1.00 750,000.00 750,000.00 0.46 1.00 0.46 0.00 0.00 1.00 0.46 100.00
3 Papan nama proyek Ls 1.00 500,000.00 500,000.00 0.31 1.00 0.31 0.00 0.00 1.00 0.31 100.00
4 Sewa bangsal kerja / gudang Ls 1.00 300,000.00 300,000.00 0.18 1.00 0.18 0.00 0.00 1.00 0.18 100.00

PEKERJAAN BRONJONG 158,551,459.80

1 Galian tanah M3 138.60 22,110.00 3,064,446.00 1.88 138.60 1.88 0.00 0.00 138.60 1.88 100.00
2 Pas. Bronjong Anyaman M3 340.50 443,437.00 150,990,298.50 92.57 340.50 92.57 0.00 0.00 340.50 92.57 100.00
3 Lapis Ijuk M2 33.60 15,323.00 514,852.80 0.32 33.60 0.32 0.00 0.00 33.60 0.32 100.00
4 Tiang Pancang Galpanis Dia. 2" M1 52.50 75,845.00 3,981,862.50 2.44 52.50 2.44 0.00 0.00 52.50 2.44 100.00

PEKERJAAN FINISHING 2,000,000.00

1 Pembersihan Akhir Ls 1.00 500,000.00 500,000.00 0.31 0.00 0.00 1.00 0.31 1.00 0.31 100.00
2 As. Built Drawing Ls 1.00 1,500,000.00 1,500,000.00 0.92 0.00 0.00 1.00 0.92 1.00 0.92 100.00

JUMLAH BOBOT PEKERJAAN 163,101,459.80 100.00 98.47 1.53 100.00

15
25 NOVEMBER 2009

LTAN
onsultant

BOBOT
TOTAL HARGA (Rp)
KEMAJUAN (%)

15 16

2,550,000.00

0.61 1,000,000.00
0.46 750,000.00
0.31 500,000.00
0.18 300,000.00

158,551,459.80

1.88 3,064,446.00
92.57 150,990,298.50
0.32 514,852.80
2.44 3,981,862.50

2,000,000.00

0.31 500,000.00
0.92 1,500,000.00

100.00 163,101,459.80

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM LAMPIRAN BERITA ACARA PEMERIKSAAN LAPANGAN
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :
NILAI KONTRAK : Rp 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH CV. MULTI CIPTA KONSULTAN
0 0 0 0
#VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! ### MINGGU LALU MINGGU INI S/D MINGGU INI #VALUE! #VALUE! #VALUE!
#VALUE! #VALUE! #VALUE! #VALUE!
VOLUME BOBOT VOLUME BOBOT VOLUME BOBOT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

BIAYA UMUM / PEKERJAAN PERSIAPAN #REF!

1 Mobilisasi dan Demobilisasi Alat Ls 1.000 1,000,000.000 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 41,760,000.000

### #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 28,007.900
3 Papan nama proyek Ls 1.000 500,000 #REF! #REF! #REF! 0.000 #REF! #REF! #REF! #REF! 0.000 0.000 -
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 43,772.720

PEKERJAAN BRONJONG #REF!


1 Galian tanah M3 138.600 22,110.000 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 88,237.860
2 Pas. Bronjong Anyaman M3 340.500 443,437.000 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 3,583.100

PEKERJAAN FINISHING #REF!

1 Pembersihan Akhir Ls 1.000 500,000.000 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 263,108.500

### #REF!

#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 311,220.260

### #REF!

#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 10,899.660
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 2,010,240.840

### #REF!

#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 755,171.63
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 17,710.00
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

### #REF!

#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 25,000.000
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 150,000.000
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 30,000.000
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 169,212.290
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 38,134.510
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 13,500.000
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 7,500,000.000
#REF! ### #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! 5,000,000.000

JUMLAH BOBOT PEKERJAAN #REF! #REF! #REF! #REF! #REF! #REF!

15
#VALUE!

17

41,760,000,000,000.000

#REF!
-
#REF!

1,950,939,084.600
1,588,879,114.700

131,554,250,000.000

#REF!

#REF!
#REF!

#REF!
#REF!
#REF!
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

#REF!

15
REALISASI PEKERJAAN FISIK

PEMERINTAH KABUPATEN POHUWATO MUTUAL CHECK AWAL ( MC-0 )


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM BULAN PERTAMA ( I ) 06 Juli 2009 - 02 Agustus 2009
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 Konsultan Pengawas :

NILAI KONTRAK : Rp. 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH CV. MULTI CIPTA KONSULTAN
General Engineering Consu
KONTRAK VOLUME YANG BERUBAH
MATA JUMLAH HARGA MC-0 PEK. TAMBAH PEK. KURANG
URAIAN PEKERJAAN SAT
HARGA SATUAN JUMLAH HARGA KONT BOBOT
PEMBAYARAN VOLUME VOLUME MC-0 ( Rp.)
( Rp. ) ( Rp.) (%) VOLUME JML HARGA VOLUME
1 2 3 4 4 5 6 6 7 8 9 10

DEVISI I. MOBILISASI 41,175,000.00 41,175,000.00 0.00

1.2. Mobilisasi Ls 1.00 1.00 41,175,000.00 41,175,000.00 41,175,000.00 4.65 0.00 0.00 0.00

DEVISI 3. PEKERJAAN TANAH 43,210,137.95 43,210,137.95 0.00

3.1.(7) Galian Struktur dengan Kedalaman 0 - 2 Meter M3


3.2.(1) Timbunan Biasa M2 297.30 181.09 82,153.07 24,424,107.71 24,424,107.71 2.76 0.00 0.00 116.21
3.3 Penyiapan Badan Jalan M2 5,946.00 4,000.00 3,159.44 18,786,030.24 18,786,030.24 2.12 0.00 0.00 1,946.00

DEVISI 4. PERBAIKAN TEPI PERKERASAN DAN BAHU JALAN 69,444,888.88 69,444,888.88 0.00

4.2 (2) Lapis Pondasi Agregat Kelas B M3 297.30 181.09 233,585.23 69,444,888.88 69,444,888.88 7.84 0.00 0.00 116.21

DEVISI 5. PERKERASAN BERBUTIR 280,097,326.14 280,097,326.14 2,543,769.86

5.1 (1) Lapis Pondasi Agregat Kelas A M3 396.40 400.00 306,995.63 121,693,067.73 121,693,067.73 13.73 3.60 1,105,184.27 0.00
5.1 (2) Lapis Pondasi Agregat Kelas B M3 594.60 600.00 266,404.74 158,404,258.40 158,404,258.40 17.88 5.40 1,438,585.60 0.00
5.2 (1) Lapis Pondasi Agregat Kelas C M3

DEVISI 6. PERKERASAN ASPAL 429,073,871.33 429,073,871.33 5,300,942.67

6.1 (1) Lapis Resap Pengikat M2 2,247.43 2,400.00 10,625.10 23,879,168.49 23,879,168.49 2.69 152.57 1,621,071.51 0.00
6.3 (6) Lapis Aus Aspal Beton ( AC - BC) M3 198.20 200.00 2,044,372.87 405,194,702.83 405,194,702.83 45.72 1.80 3,679,871.17 0.00

DEVISI 7. STRUKTUR 23,163,064.22 23,163,064.22 34,995,505.53

7,1(5) Beton K 250 M3 4.80 7.12 960,985.28 4,612,729.34 4,612,729.34 0.52 2.32 2,229,485.85 0.00
7,3 (1) Baja Tulangan U-24 Polos Kg 528.00 1,460.68 35,133.21 18,550,334.88 18,550,334.88 2.09 932.62 32,766,019.68 0.00
7,9, Pasangan Batu M3

JUMLAH 886,164,288.52 886,164,288.52 100.00 42,840,218.07


PPN 88,616,428.85 88,616,428.85 4,284,021.81
JUMLAH 974,780,717.37 974,780,717.37 47,124,239.88
DIBULATKAN 974,781,000.00 974,781,000.00 47,124,200.00

MENGETAHUI : DIPERIKSA OLEH, Marisa, November 2009


DIINAS PEKERJAAN UMUM KONSULTAN PENGAWAS DIAJUKAN OLEH :
CV. M - DUA
RINI MEILANI, ST
Nip. 19800511 200802 2 002 1. …………………………… 1. ……………………………….
Site Engineer 1. …………………………. ,,,,,
SUNU SUHANDOKO, ST Direktur 1. ……………………..
Nip. 19701123 200501 1 007 2. ………………………….. 2. ……………………………….
Quantity 2. ………………………… ,,,,,
YUSTAM Pimpinan Tehnik 2. …………………….
Nip. 19770628200604 1 014 3. …………………………..

15
WAL ( MC-0 )
09 - 02 Agustus 2009

awas :
KONSULTAN
eneral Engineering Consultant
RUBAH
PEK. KURANG

JML HARGA
11

0.00

0.00

15,695,278.50

9,547,008.26
6,148,270.24

27,144,939.58

27,144,939.58

0.00

0.00
0.00

0.00

0.00
0.00

0.00

0.00
0.00

42,840,218.08
4,284,021.81
47,124,239.89
47,124,200.00

……………..

…………….

15
PEMERINTAH KABUPATEN GORONTALO UTARA
DINAS PEKERJAAN UMUM
TAHUN ANGGARAN 2009
Kompleks Blok Plan Marisa Kec. Marisa Kab. Pohuwato

BRITA ACARA MUTUAL CHECK AWAL

Paket : Peningkatan Jalan Buntulia Selatan - Buntulia Barat (DAK)


Nom : ……………….

Pada Kamis tanggal 29 Bulan Juli Tahun 2009 Kami masing-masing Pihak Pimpinan Proyek, Jasa Konsultan Pengawas
dan pihak Kontraktor Pelaksana telah mengadakan Pengukuran Awal ( Mutual Check) Paket Peningkatan Jalan Buntulia
Selatan - Buntulia Barat Tahun Anggaran 2009

Dasar Pelaksanaan:
No./Tgl. DIP :
No./Tgl. Kontrak : 762/KONT/DPU-PPTK2-BM/01/VII/2009

Tujuan Pelaksanaan :

Mengecek kembali kondisi lapangan untuk memperoleh data-data aktual sebagai acuan pelaksanaan Kontrak
terutama Kuantitas setiap item pekerjaan. Dari data-data tersebut akan menghasilkan rekayasa lapangan sebagai
penyesuaian kuantitas untuk mempertahankan fungsi jalan agar tingkat pelayanan lalu lintas tetap maksimal sesuai
harapan bersama.

Kesimpulan :

Dari hasil pengukuran awal ( Mutual Check ) telah didapat data Rekayasa Lapangan untuk menjadi acuan
pelaksanaan Kontrak, agar fungsi jalan dan pelayanan lalu lintas tetap maksimal, adapun hasil yang telah kami
sepakati adalah Menyetujui Pelaksanaan Pekerjaan Tersebut sesuai dengan Kontrak yang ada.

Demikian Berita Acara ini dibuat untuk dipergunakan sebagai mana mestinya.

Pejabat Pelaksana Teknis Pengawas Konsultan : Kontraktor Pelaksana :


Kegiatan CV. KALATE KONSULTAN PT. SINAR NUSA GOLINDO

ANWAR SADAT, ST Ir. MISENAN HENDRA S. HEMETO, ST


Nip : 19731023 200501 1 Team Leader Direktur
KABUPATEN GORONTALO UTARA
PEKERJAAN UMUM
HUN ANGGARAN 2009
lan Marisa Kec. Marisa Kab. Pohuwato

A MUTUAL CHECK AWAL

Kami masing-masing Pihak Pimpinan Proyek, Jasa Konsultan Pengawas


akan Pengukuran Awal ( Mutual Check) Paket Peningkatan Jalan Buntulia

mperoleh data-data aktual sebagai acuan pelaksanaan Kontrak


i data-data tersebut akan menghasilkan rekayasa lapangan sebagai
n fungsi jalan agar tingkat pelayanan lalu lintas tetap maksimal sesuai

elah didapat data Rekayasa Lapangan untuk menjadi acuan


layanan lalu lintas tetap maksimal, adapun hasil yang telah kami
rjaan Tersebut sesuai dengan Kontrak yang ada.

HENDRA S. HEMETO, ST
Direktur
BERITA ACARA PEMERIKSAAN PRESTASI PEKERJAAN

Pada Hari Ini Jumat Tanggal Dua Belas Bulan Desember Tahun Dua Ribu Delapan yang bertanda tangan di bawah ini :

Nama : ANWAR SADAT, ST


Nip. : 940 003 422
Jabatan : Pejabat Pelaksana Teknis Kegiatan Kegiatan Pembangunan Jalan& Jembatan

Selanjutnya disebut sebagai Pihak I

Nama : YONGKIE LIMEN


Jabatan : DIREKTUR CV. BERKAT MULIA
Alamat : Jln. Sindulang I No. 11 Manado

Selanjutnya disebut sebagai Pihak II

Berdasarkan Surat Perjanjian Kontrak No.( Addendum) : 762-Add/KONT/DPU-PPTK-BM/28/XI/2008, Tanggal 12 November 2008 s/d 30 Desember 2008. telah melakukan Pemeriksaan bersama
atas kemajuan pekerjaan tersebut.

PEMERINTAH KABUPATEN POHUWATO


KONTRAKTOR : CV. M - DUA DINAS PEKERJAAN UMUM
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009 TAHUN ANGGARAN 2009 BERITA ACARA
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009 PEMERIKSAAN PRESTASI
PEKERJAAN
NILAI KONTRAK : Rp 179,411,000.00 PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
0 0 0 0
VOLUME BOBOT REALISASI FISIK
MATA PEMBAYARAN URAIAN PEKERJAAN SATUAN S/D MINGGU INI
CCO - 03 CCO - 03
VOLUME BOBOT
1 2 3 5 7 12 13

BIAYA UMUM / PEKERJAAN PERSIAPAN

1 Mobilisasi dan Demobilisasi Alat Ls 1,000,000.000 #REF! #REF! #REF!

###

#REF! ### #REF! #REF! #REF! #REF! #REF!


3 Papan nama proyek Ls 500,000.000 #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!

PEKERJAAN BRONJONG
1 Galian tanah M3 22,110.000 #REF! #REF! #REF!
2 Pas. Bronjong Anyaman M3 443,437.000 #REF! #REF! #REF!

PEKERJAAN FINISHING

1 Pembersihan Akhir Ls 500,000.000 #REF! #REF! #REF!

###

#REF! ### #REF! #REF! #REF! #REF! #REF!

###

#REF! ### #REF! #REF! #REF! #REF! #REF!


#REF! ### #REF! #REF! #REF! #REF! #REF!

###

#REF! ### #REF! #REF! #REF! #REF! #REF!


#REF! ### #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!

###

#REF! ### #REF! #REF! #REF! #REF! #REF!


#REF! ### #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!
#REF! ### #REF! #REF! #REF! #REF! #REF!

JUMLAH BOBOT PEKERJAAN #REF! #REF!

Tingkat Kemajuan Terhadap Seluruh Pekerjaan Adalah 89.968 % (Delapan Puluh Sembilan Koma Sembilan Enam Delapan
Persen )'

#REF!
#REF! #REF! #REF! Diajukan Oleh :
#REF! #REF! #REF! #REF!
#REF!

#REF! #REF! #REF! #REF!


#REF! #REF! #REF! #REF!

15
PEMERIKSAAN PRESTASI PEKERJAAN

U-PPTK-BM/28/XI/2008, Tanggal 12 November 2008 s/d 30 Desember 2008. telah melakukan Pemeriksaan bersama

BERITA ACARA
PEMERIKSAAN PRESTASI
PEKERJAAN

BOBOT
TERHADAP ITEM###
PEKERJAAN

14 ###

#REF!
###

#REF!
###
0.000
###
#REF!
###

#REF!
###
#REF!
###

#REF!
###

#REF!
###

#REF!
###
#REF!
###

#REF!
###
#REF!
###
#REF!
###
#REF!
###

#REF!
###
#REF!
###
#REF!
###
#REF!
###
#REF!
###
#REF!
###
#REF!
###
#REF!
###

###

Diajukan Oleh :

15
ALENDER
AKTU PELAKSANAAN 60 (ENAM PULUH) HARI
S C H E D D U L E ( KURVA 'S' )

KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG


PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
LOKASI : KEC. MARISA KAB. POHUWATO
TAHUN ANGGARAN : 2009

BOBOT OKTOBER NOVEMBER


NO. URAIAN PEKERJAAN (%)
(%) 1 2 3 4 5 6 7 8

BIAYA UMUM / PEKERJAAN PERSIAPAN


1 Mobilisasi dan Demobilisasi Alat 0.61 0.31 0.31
2 Pengukuran / pemasangan patok 0.46 0.46
3 Papan nama proyek 0.31 0.31 RENCANA
4 Sewa bangsal kerja / gudang 0.18 0.18

PEKERJAAN BRONJONG REALISASI


1 Galian tanah 1.88 1.88
2 Pas. Bronjong Anyaman 92.57 23.14 23.14 23.14 23.14
3 Lapis Ijuk 0.32 0.11 0.11 0.11
4 Tiang Pancang Galpanis Dia. 2" 2.44 0.61 0.61 0.61 0.61

PEKERJAAN FINISHING
1 Pembersihan Akhir 0.31 0.31
2 As. Built Drawing 0.92 0.92

RENCANA PERMINGGU ( % ) 100.00 1.26 1.88 23.75 23.86 23.86 23.86 0.31 1.23
RENCANA MINGGUAN KUMULATIF ( % ) 1.26 3.14 26.89 50.75 74.61 98.47 98.77 100.00
REALISASI PERMINGGU ( % ) 1.26 1.88 19.21 19.35 18.10 18.83 19.84 1.53
REALISASI MINGGUAN KUMULATIF ( % ) 1.26 3.14 22.35 41.70 59.80 78.63 98.47 100.00
DEVIASI ( % ) - - (4.54) (9.05) (14.81) (19.84) (0.31) -
KET
AKTU PELAKSANAAN 60 (ENAM PULUH) HARI

(%)
ALENDER
ALENDER
AKTU PELAKSANAAN 60 (ENAM PULUH) HARI
S C H E D D U L E ( KURVA 'S' )

KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG


PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
LOKASI : KEC. MARISA KAB. POHUWATO
TAHUN ANGGARAN : 2009

BOBOT OKTOBER NOVEMBER


NO. URAIAN PEKERJAAN (%)
(%) 1 2 3 4 5 6 7 8

BIAYA UMUM / PEKERJAAN PERSIAPAN


1 Mobilisasi dan Demobilisasi Alat 0.61 0.31 0.31
2 Pengukuran / pemasangan patok 0.46 0.46
RENCANA
3 Papan nama proyek 0.31 0.31
4 Sewa bangsal kerja / gudang 0.18 0.18
REALISASI
PEKERJAAN BRONJONG
1 Galian tanah 1.88 1.88
2 Pas. Bronjong Anyaman 92.57 23.14 23.14 23.14 23.14
3 Lapis Ijuk 0.32 0.11 0.11 0.11
4 Tiang Pancang Galpanis Dia. 2" 2.44 0.61 0.61 0.61 0.61

PEKERJAAN FINISHING
1 Pembersihan Akhir 0.31 0.31
2 As. Built Drawing 0.92 0.92

RENCANA PERMINGGU ( % ) 100.00 1.26 1.88 23.75 23.86 23.86 23.86 0.31 1.23
RENCANA MINGGUAN KUMULATIF ( % ) 1.26 3.14 26.89 50.75 74.61 98.47 98.77 100.00
REALISASI PERMINGGU ( % ) 1.26 1.88 19.21 19.35 18.10 18.83 19.84 1.53
REALISASI MINGGUAN KUMULATIF ( % ) 1.26 3.14 22.35 41.70 59.80 78.63 98.47 100.00
DEVIASI ( % ) - - (4.54) (9.05) (14.81) (19.84) (0.31) -
KET
AKTU PELAKSANAAN 60 (ENAM PULUH) HARI

(%)
ALENDER
SKEMA PENGGUNAAN ALAT
KEGIATAN : Konsultan Pengawas :
PEKERJAAN : CV. MULTI CIPTA KONSULTAN
LOKASI :
TAHUN ANGGARAN : KONTRAK : 16 JUNI 2008 - 12 NOPEMBER 2008
KONTRAKTOR :

JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOPEMBER


NO. URAIAN PEKERJAAN JUMLH. (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1. ASPHALT MIXING PLANE

2. ASPHALT FINISHER
100 %

3. ASPHALT SPRAYER

90 %
4. COMPRESSOR 4000-6500 L\M

5. CONCRETE MIXSER 0.3-0.6 M3

80 %
6. DUMP TRUCK 3-4 M3

7. DUMP TRUCK 70 %

8. EXCAVATOR 143 HP

9. GENERATOR SET 60 %

10. MOTOR GRADER > 100 HP

11. WHEEL LOADER 2.5 M3

12. TANDEM ROLLER 6-8 T


50 %

13. TIRE ROLLER 8-10 T

40 %
14. VIBRTORY ROLLER 5-8 T
30 %
15. CONCRETE VIBRATOR
20 %
16. STONE CRUSHER
10 %

17. WATER PUMP 70-100 mm

18. WATER TANKER 3000-4500 L.

19. TRAILER 20 TON 0%

DEVIASI ( % ) - - - - - - - - - - - - - - - - - - - -
SKEMA PENGGUNAAN TENAGA
KEGIATAN : Konsultan Pengawas :
PEKERJAAN : CV. MULTI CIPTA KONSULTAN
LOKASI :
TAHUN ANGGARAN : KONTRAK : 16 JUNI 2008 - 12 NOPEMBER 2008
KONTRAKTOR :

JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOPEMBER


NO. URAIAN PEKERJAAN JUMLH. (%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

1. GENERAL SUPERINTENDENT

2. PELAKSANA LAPANGAN
100 %

3. MATERIAL TECHNICIAN

4. 90 %
KEPALA LOGISTIK

5. SURVEYOR

6. KEPALA PERALATAN 80 %

7. OPERATOR & PEMBANTU 70 %

8. SOPIR

9. KEPALA TUKANG 60 %

10. TUKANG

11. MANDOR

12. PEKERJA
50 %
0%
REALISASI MINGGUAN KUMULATIF ADD ( % )
DEVIASI ( % ) #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
KET

WAKTU PELAKSANAAN 150 ERATUS LIMA PULUH) HARI KALENDER


SKEMA PENGGUNAAN ALAT
WAKTU PELAKSANAAN 150 ERATUS LIMA PULUH) HARI
KET

KALENDER
SKEMA PENGGUNAAN TENAGA
PERHITUNGAN WAKTU UNTUK MENYELESAIKAN ITEM PEKERJAAN TIMBUNAN PILIHAN (UNTUK
SEGMEN 01 )

ASUMSI :

Truk : 25.00 Buah

1 hari : 8.00 Jam Kerja

Truk/hari : 15.00 rate

1 Truk : 2.50 M3

Alat Yang dibutuhkan : - Escavator 2 Buah


- Buldozer 1 Buah

jadi :
= 25 x 15 x 2,5

= 937.50 M3/hari

Yang sudah di kerjakan : 4150.30

Volume RAB : #REF! M3

Waktu yang di butuhkan untuk menyelesaikan item pekerjaan timbunan pilihan :

Waktu dibutuhkan : #REF!


937.5

: #REF! hari
PERHITUNGAN WAKTU UNTUK MENYELESAIKAN ITEM PEKERJAAN PASANGAN TALUD (UNTUK
SEGMEN 01)

VOL. RAB : #REF! M3

ASUMSI :

1 grup : 1.00 Tukang


1.00 Pembantu

1 hari 8.00 Jam kerja

1 Grup : 1.75 M3 (Kuantitas Pekerjaan)

Asumsi :

Jika di pasang : Bahan dibutuhkan perhari

* 30 Grup/60 orang : 30 x 1,75 Asumsi :


1 M3 Pas. Batu
: 52.50 M3
* Waktu dibutuhkan Batu :
= #REF! hari Pasir :
Semen :
* 40 Grup/80 orang : 40 x 1,75
* untuk 30 Grup.
: 70.00 M3 Batu :
* Waktu dibutuhkan Pasir :
= #REF! hari Semen :
YELESAIKAN ITEM PEKERJAAN TIMBUNAN PILIHAN (UNTUK
SEGMEN 01 )
NYELESAIKAN ITEM PEKERJAAN PASANGAN TALUD (UNTUK
SEGMEN 01)

(Kuantitas Pekerjaan)

Bahan dibutuhkan perhari

1 M3 Pas. Batu

1.20 M3
0.52 M3
162.00 Kg

* untuk 30 Grup.
63.00 M3
27.30 M3
8,505.00 Kg
PEMERINTAH KABUPATEN GORONTALO UTARA
DINAS PEKERJAAN UMUM
TAHUN ANGGARAN 2009
Jl. Trans Sulewesi Desa Mootinelo ec. Kwandang

PEKERJAAN
Pekerjaan : :
Peningkatan Sarana & Prasarana
PENGAWASAN/SUPERVISI Aparatur
TEKNIS
REHAB/PEMELIHARAAN JALAN
LOKASI :
KABUPATEN GORONTALO UTARA

TAHUN ANGGARAN
2009

DIAJUKAN OLEH :
KONSULTAN PENGAWAS
KABUPATEN GORONTALO UTARA
PEKERJAAN UMUM
HUN ANGGARAN 2009
ewesi Desa Mootinelo ec. Kwandang

Pekerjaan :
ana & Prasarana
AN/SUPERVISI Aparatur
TEKNIS
MELIHARAAN JALAN
LOKASI :
TEN GORONTALO UTARA

UN ANGGARAN
2009

DIAJUKAN OLEH :
NSULTAN PENGAWAS
DATA PROYEK KONSULTAN

1 Kegiatan : PEMBANGUNAN TURAP/TALUD/BRONJONG


2 Pekerjaan : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA
3 Lokasi : KEC. MARISA KAB. POHUWATO
4 Nomor Kontrak Fisik : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009
5 Nomor Kontrak Pengawasan : 01/KONT/PPTK-PENGW/BM/DPU-PHWT/VII/2009
6 Sumber Dana : APBD
7 Total Kontrak Asli Pengawasan : Rp 108,480,000.00
8 Total Kontrak Revisi : -
9 Surat Perintah Mulai Kerja : 06 JULI 2009
10 Akhir Proyek : 02 Desember 2009
11 Jangka Waktu Pelaksanaan : 150 Hari Kalender
12 Waktu Kerja Sampai Saat ini :
13 Kemajuan Fisik :
14 Rencana Kemajuan Fisik : 70.25%
15 Selisih : 0.70
16 Konsultan : CV. MULTI CIPTA KONSULTAN
17 Kontraktor :
PROYEK KONSULTAN

PEMBANGUNAN TURAP/TALUD/BRONJONG
PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH

761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009
01/KONT/PPTK-PENGW/BM/DPU-PHWT/VII/2009
RINGKASAN KEMAJUAN FISIK
PERIODE : BULAN I (PERTAMA)

KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG


PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA TENGAH
LOKASI : KEC. MARISA KAB. POHUWATO
TAHUN ANGGARAN : 2009
KONTRAKTOR CV. M - DUA
KONTRAK NO. : 761.13/DPU-PSDA/KONT.PPTK-APBD-P/X/2009
TANGGAL : 01 OKTOBER 2009 S/D 29 NOVEMBER 2009
NILAI KONTRAK :

NILAI KONTRAK

1 Asal : Rp -
Komponen Lokal :
Komponen Asing :

2 Addendum :
Komponen Lokal :
Komponen Asing :

3 Total : Rp -
Komponen Lokal :
Komponen Asing :

4 Perkiraan Biaya Akhir : Rp -

WAKTU KONTRAK WAKTU TERPAKAI (HARI) KEMAJUAN KOMULATIF


Asal : 120 Hari Terpakai 28 Rencana :
Addendum : % Terpakai 23.33% Realisasi :
Total : Selisih :
SARAN/ INSTRUKSI DIREKSI

SARAN/ INSTRUKSI KONSULTAN SUPERVISI

SARAN/ INSTRUKSI PELAKSANA KEGIATAN


N KEMAJUAN FISIK
BULAN I (PERTAMA)

LAI KONTRAK

KEMAJUAN KOMULATIF

/ INSTRUKSI DIREKSI

UKSI KONSULTAN SUPERVISI

UKSI PELAKSANA KEGIATAN


DOKUMENTASI PROYEK
KEGIATAN : PEMBANGUNAN TURAP/TALUD/BRONJONG KONTRAKTOR PE
PEKERJAAN : PERKUATAN TEBING SUNGAI TALUDUYUNU DESA BUNTULIA CV. M - D
LOKASI : KEC. MARISA KAB. POHUWATO KONSULTAN PE
TAHUN ANGGARAN : 2009 CV. MULTI CIPTA
MENTASI PROYEK
KONTRAKTOR PELAKSANA :
CV. M - DUA
KONSULTAN PENGAWAS :
CV. MULTI CIPTA KONSULTAN

KETERANGAN :

KETERANGAN :
PEMERINTAH KABUPATEN POHUWATO
DINAS PEKERJAAN UMUM
TAHUN ANGGARAN 2009
Alamat : Kompleks Blok Plan Perkantoran Marisa

PEKERJAAN :

PENGAWASAN PEMBANGUNAN JALAN


PAKET IV

Marisa, Agustus 2009


Mengetahui, Konsultan Pengawas
CV. KALATE KONSULTAN CV. KALATE KONSULTAN

MUKTI ABDULLAH, ST Ir. MISENAN


Direktur Site Engineer

Menyetujui,

Pejabat Pelaksana Pejabat Pelaksana


Teknis Kegiatan (PPTK) Konsultan Teknis Kegiatan (PPTK) fisik
Kab. Pohuwato Kab. Pohuwato

JUFRI ARBIE, ST RISDIYANTO MOKODOMPIT, ST


NIP. 940 009 67086 NIP. 19770520 200604 1 024
H KABUPATEN POHUWATO
EKERJAAN UMUM
AHUN ANGGARAN 2009