DAFTAR HARGA ANALISA PEKERJAAN

1. 1m' Pasang Pagar Panel Beton 240 x 45 x 5 cm Setinggi 2 Meter


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja L.01 OH 0.375 110,000.00 41,250.00
Kepala Tukang L.02 OH 0.012 150,000.00 1,800.00
Tukang L.03 OH 0.125 120,000.00 15,000.00
Mandor L.04 OH 0.019 150,000.00 2,850.00
JUMLAH TENAGA KERJA 60,900.00

B BAHAN
Panel Beton Pracetak lbr 0.99 182,000.00 179,452.00
Kolom Beton Pracetak btg 0.53 480,000.00 252,000.00
PC kg 45.00 1,532.50 68,962.50
Pasir Beton m3 0.07 260,000.00 19,240.00
Batu Pecah 2/3 m3 0.15 272,000.00 39,712.00
JUMLAH HARGA BAHAN 559,366.50

C PERALATAN
JUMLAH HARGA ALAT

D Jumlah( A + B + C ) 620,266.50
10% 62,026.65
E Harga Satuan Pekerja (D + E ) 682,293.15

2. 1m' Pasang Pagar Kawat Duri Setinggi 2 Meter


Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja L.01 OH 0.300 110,000.00 33,000.00
Kepala Tukang L.02 OH 0.020 150,000.00 3,000.00
Tukang L.03 OH 0.200 120,000.00 24,000.00
Mandor L.04 OH 0.020 150,000.00 3,000.00
JUMLAH TENAGA KERJA 63,000.00

B BAHAN
Kolom Beton btg 0.53 480,000.00 252,000.00
PC kg 45.00 1,532.50 68,962.50
Pasir Beton m3 0.07 260,000.00 19,240.00
Kawat Duri kg 4.50 19,200.00 86,400.00
Koral Beton 2/3 m3 0.15 272,000.00 39,712.00
JUMLAH HARGA BAHAN 466,314.50

C PERALATAN
JUMLAH HARGA ALAT

D Jumlah( A + B + C ) 529,314.50
10% 52,931.45
E Harga Satuan Pekerja (D + E ) 582,245.95

3. 1m' Pasang Pagar Panel Beton 240 x 45 x 5 cm Setinggi 2 Meter Beserta Kawat Duri Setinggi 50 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
( Rp) ( Rp)
A TENAGA
Pekerja L.01 OH 0.375 110,000.00 41,250.00
Kepala Tukang L.02 OH 0.012 150,000.00 1,800.00
Tukang L.03 OH 0.125 120,000.00 15,000.00
Mandor L.04 OH 0.019 150,000.00 2,850.00
JUMLAH TENAGA KERJA 60,900.00

B BAHAN
Panel Beton Pracetak lbr 0.99 182,000.00 179,452.00
Kolom Beton Pracetak btg 0.53 480,000.00 252,000.00
PC kg 45.00 1,532.50 68,962.50
Pasir Beton m3 0.07 260,000.00 19,240.00
Batu Pecah 2/3 m3 0.15 272,000.00 39,712.00
Kawat Duri Tinggi 50 cm m' 1.00 90,000.00 90,000.00
JUMLAH HARGA BAHAN 649,366.50

C PERALATAN
JUMLAH HARGA ALAT

D Jumlah( A + B + C ) 710,266.50
10% 71,026.65
E Harga Satuan Pekerja (D + E ) 781,293.15
DAFTAR HARGA BAHAN BANGUNAN & UPAH KERJA

No. JENIS BAHAN Sat. Harga ( Rp ) Keterangan

A. BAHAN BANGUNAN
1 Tanah Urug m3 132,000.00
2 Pasir Urug pilihan m3 187,200.00
3 Pasir Pasang m3 260,000.00
4 Pasir Beton m3 260,000.00
5 Batu Belah 15/20 m3 466,000.00
6 Kerikil/Koral Beton m3 260,000.00
7 Agregat Kasar / Batu pecah 2/3 m3 272,000.00
8 Sirtu m3 169,800.00
9 Bata Merah bj 1,000.00
10 Portland Cement (PC) 40 Kg zak 61,300.00
11 Portland Cement (PC) 50 Kg zak 73,800.00
12 Portland Cement (PC) Putih kg 2,115.60
13 Floorhardener kg 32,000.00
14 Polimer Calbon kg 54,000.00
15 Besi Beton Polos kg 13,000.00
16 Besi Beton Ulir kg 13,000.00
17 Baja Profil WF & Kanal kg 23,900.00
18 Kawat Beton ( bendrat ) kg 22,000.00
19 Besi hollow 40.40.2 m' 8,433.33
20 Cheimcal Ramset tube 950,000.00
21 Zincalum colour m2 166,200.00
22 Paku Kait ( pancing ) bh 7,500.00
23 Minyak Cat ( B ) ltr 42,800.00
24 Cat Meni Besi kg 49,900.00
25 Cat besi kg 70,700.00
26 Cat Dinding luar (weather shield) kg 94,920.00
27 Cat Dinding dalam kg 60,320.00
28 Plamir Dinding kg 62,800.00
29 Dempul kg 35,800.00
30 Kuas 2" bh 15,800.00
31 Bambu (Dia 6 - 8 cm x 600cm) btg 11,000.00
32 Seng gelombang lbr 72,500.00
33 Kayu Bekisting m3 3,484,400.00
34 Paku Biasa 2" kg 17,983.00
35 Multiplek 9 mm, uk. 1,20 x 2,40 m lbr 210,000.00
36 Paku Biasa 4" kg 17,500.00
37 Balok kayu meranti m3 4,899,900.00
38 Dolken Kayu Gelam btg 11,900.00
39 Air Bersih/Tawar ltr 750.00
40 Minyak Bekisting ltr 30,100.00
41 Plat Besi 12 mm kg 40,200.00
42 Pelat Zincalume 0.4 mm m' 43,000.00
43 Mortar Utama (MU-830) zak 263,000.00
44 Angkur D 19 Panjang 70 cm bh 58,700.00
45 Angkur M-16 bh 36,600.00
46 Mur Baut M-16 bh 9,000.00
47 Paving Block Abu-Abu Tebal 6 cm m2 73,200.00
48 Sekrup bh 750.00

Harga Satuan: 2
No. JENIS BAHAN Sat. Harga ( Rp ) Keterangan

49 Sealant tube 65,000.00


50 Acrylic m2 175,000.00
51 Kertas Gosok lbr 20,900.00
52 Reng Baja Ringan m' 8,740.00
53 Mill kg 900.00
54 Epoxy kg 146,000.00
55 Soda Api ltr 29,100.00

B. UPAH TENAGA KERJA


1 Pekerja Org/Hr 110,000.00
2 Tukang Org/Hr 120,000.00
3 Kepala Tukang Org/Hr 150,000.00
4 Mandor Org/Hr 150,000.00
5 Operator Org/Hr 115,000.00

C. SEWA ALAT
1 Sewa Dump Truck 5 ton per jam 71,900.00
2 Sewa Alat Bor per jam 18,125.00
3 Sewa Alat Bantu ( set / 3 alat ) per jam 15,500.00
4 Compressor ls 10,000.00

Harga Satuan: 3