Pekerjaan pondasi poer Plat ( P-1) Jumlah = 1 titik

Cor Beton Cor Beton dalam 1 titik 0.16 0.25 m3


Besi Beton Pondasi poer plat 14.78 43.57 Kg
Bekisting P = 1 m 0.8 1 m2
L = 1 m
T = 0.25 m
V = P x L x T x jumlah
= 0.25 m3

Besi Beton dalam 1 titik (Besi φ 12)


besi Jml p berat/m berat.ttl SAT
Horizontal 6 2.3 1.58 21.7856 Kg
Vertikal 6 2.3 1.58 21.7856 Kg
43.5712 Kg
V. Total = 1 x 43.5712
= 43.571 Kg

Bekisting
P = 4 m
L = 0.25 m
V = P x L x jumlah
= 1 m2

Pekerjaan kolom Pedestal

Kolom pedestal 40x40 cm Jumlah = 1 titik


Cor Beton Cor Beton dalam 1 kolom 0.128 m3
Besi Beton T = 0.8 m 18.12 Kg
Bekisting Luas = 0.16 m2 0.64 m2
V = Luas x T
= 0.128 m3
V total = V x jumlah
= 0.128 m3

berat besi 1 kolom tinggi 1m


besi Jml p berat/m berat.ttl SAT
B16 10 0.85 1.58 13.4187 Kg
Beugel *8 7 1.7 0.39 4.69653 Kg
18.1152 Kg
V. Total = 1 x 18.1152
= 18.115 Kg

Bekisting
V = PXL
V = 0.8 x 0.8
= 0.64 m2
Vt = 0.64 x 1
= 0.64 M2