Anda di halaman 1dari 130

SMK N 7 SEMARANG

XI TKJIJ 2
TIME SCHEDULE
Pekerjaan : Pembuatan Pagar
Lokasi : Simpang Lima
T.A. : 2018

NO JENIS PEKERJAAN JUMLAH BOBOT (%) DURASI MINGGU 1 MINGGU 2 MINGGU 3 MINGGU 4 MINGGU 5 MINGGU 6 MINGGU 7 MINGGU 8 MINGGU 9 MINGGU 10 MINGGU 11 MINGGU 12
I Pekerjaan Persiapan 5,470,696.00 3.368 1 3.368
II Pekerjaan Tanah 4,283,657.13 2.637 2 1.319 1.319
III Pekerjaan Pondasi 17,423,404.63 10.727 3 3.576 3.576 3.576
IV Pekerjaan Beton 4,929,760.55 3.035 2 1.517 1.517
V Pekerjaan P.S. Dinding 8,076,790.11 4.972 3 1.657 1.657 1.657
VI Pekerjaan Plesteran 24,424,996.06 15.037 3 5.012 5.012 5.012
VII pekerjaan penutup lantai & dinding 7,644,800.55 4.706 2 2.353 2.353
VIII pekerjaan langit langit 3,605,822.55 2.220 2 1.110 1.110
IX pekerjaan penutup atap 7,172,500.67 4.416 2 2.208 2.208
X pekerjaan kayu 46,037,640.99 28.343 2 14.171 14.171
XI pekerjaan kunci dan kaca 2,644,519.35 1.628 1 1.628
XII pekerjaan pengecatan 6,293,508.76 3.875 1 3.875
XIII pekerjaan sanitasi dlm gedung 24,424,996.06 15.037 1 15.037
PROGRES MINGGU INI 3.368 4.894 4.894 6.750 3.175 6.670 7.366 8.475 3.318 16.379 14.171 20.540
162,433,093.39 100
PROGRES S/D MINGGU INI 0 3.368 8.262 13.156 19.907 23.082 29.751 37.117 45.592 48.910 65.289 79.460 100.000

Semarang, 13 Agustus 2018

henri rivalde
Estimator
SMK N 7 SEMARANG
XI TKJIJ 2
REKAPITULASI ANGGARAN BIAYA
Pekerjaan : RUMAH TINGGAL TYPE 36
Lokasi : Simpang Lima
T.A. : 2018

NO JENIS PEKERJAAN JUMLAH


I Pekerjaan Persiapan Rp 5,470,696
II Pekerjaan Tanah Rp 4,283,657
III Pekerjaan Pondasi Rp 17,423,405
IV Pekerjaan Beton Rp 4,929,761
V Pekerjaan P.S. Dinding Rp 8,076,790
VI Pekerjaan Plesteran Rp 24,424,996
VII pekerjaan penutup lantai & dinding Rp 7,644,801
VIII pekerjaan langit langit Rp 3,605,823
IX pekerjaan penutup atap Rp 7,172,501
X pekerjaan kayu Rp 46,037,641
XI pekerjaan kunci dan kaca Rp 2,644,519
XII pekerjaan pengecatan Rp 6,293,509
XIII pekerjaan sanitasi dlm gedung Rp 24,424,996
TOTAL Rp 162,433,093

Semarang, 13 Agustus 2018

henri rivalde
Estimator
-
SMK N 7 SEMARANG
XI TKJIJ 2
PERHITUNGAN KEBUTUHAN,UPAH DAN BAHAN
Pekerjaan : rumah tinggal type 36
Lokasi :graha sendangmulyo 2
T.A. : 2018

NO JENIS PEKERJAAN
I Pekerjaan Persiapan
1 Pembersihan Lokasi
2 Pemasangan Bowplank
sub total I
II Pekerjaan Tanah
1 Galian Tanah
2 Urugan Pasir
3 Urugan Tanah Kembali
sub total II
III Pekerjaan Pondasi
1 Pondasi Batu Kosong
2 Pondasi Batu Kali 1:8
sub total III
IV Pekerjaan Beton
1 Sloof fc 21,7 Mpa(K250)
2 Kolom fc 21,7 Mpa(K250)
3 Ring Balok
sub total IV
VI Pekerjaan P.S. Dinding
Pasangan Bata Tebal 1/2 1:5
sub total VI
VII Pekerjaan Plesteran
P.S. Plesteran 1:5 tebal 15mm
Pemasangan acian
sub total VII
VIII pekerjaan penutup lantai & dinding
Pemasangan Lantai Keramik 30 x 30 cm
sub total VIII
IX pekerjaan langit langit
Pemasangan Langit-langit Akustik Ukuran (60x120) cm
sub total IX
X pekerjaan penutup atap
Pemasangan Atap Genteng Plentong Kecil
sub total X
XI pekerjaan kayu
Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III
Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Klas I atau II
Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau II
Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter
Pemasangan konstruksi Gording, Kayu Klas II
Pemasangan Rangka Atap Sirap, Kayu Klas II
Pemasangan Rangka Langit-langit (50x1,00) m, kayu Klas II atau III
sub total XI
XII pekerjaan kunci dan kaca
Pemasangan Kunci Tanam Biasa
Pemasangan Kunci Kamar Mandi
Pemasangan Engsel Pintu
Pemasangan Engsel Angin
Pemasangan Kunci Lemari
Pemasangan Kaca tebal 3 mm
sub total XIII
XIII pekerjaan pengecatan
Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup)
sub total XIII
XIV pekerjaan sanitasi dlm gedung
Pemasangan Closet Duduk / Mono Blok
Pemasangan Wastafel
Pemasangan Bak Fibreglass vol.1 m3
sub total XIV
sub total V
TOTAL
SATUAN VOLUME koef Kayu 5/7x 4m Kayu Kruing koef Paku Biasa 2" - 5" koef Kayu Papan 3/20 Kruing

m² 88.00
m 32.00 0.012 0.384 0.02 0.64 0.007

m³ 51.51
m³ 2.23
m³ 17.17

m³ 8.95
m³ 16.54

m³ 1.49 0.045 0.067


m³ 1.79 0.045 0.081
m³ 1.49 0.045 0.067

m² 82.18

m² 324.36
m² 280.04

m2 41.82

m2 41.22

m2 90.43

m3 0.51
m2 17.99
m' 21.00 0.10 2.1
m3 0.17 5.6 0.952
m3 0.51 3 1.53
m2 90.43 0.2 18.086
m2 41.82 0.2 8.364

Buah 4.00
Buah 1.00
Buah 15.00
Buah 16.00
Buah 2.00
m2 6.00

m2 164.36

1.00
1.00
1.00

Semarang, 13 Agustus 2018

HENRI RIVALDE
Estimator
Kayu Papan 3/20 Kruing koef Pasir Urug koef Batu Belah 15/20 koef Portland Sement koef Pasir Pasang

0.224

1.2 2.676

1.2 19.85 91 1,505.14 0.584

0.045

0.026

0.045
6 6.00 0.01
koef Pasir Pasang Portland Semen Pasir Beton Kerikil (maksimum 30 mm) Air

9.66

384 572.16 692 1031.08 1,039 1548.11 215


384 687.36 692 1238.68 1,039 1859.81 215
5.5 8.195 0.009 0.01341 0.015 0.02235

3.6981 9.68 795.5024

8.43336 5.184 1681.482


3.25 910.143

1.8819 10.00 418.2


0.01
Air Kayu Klas III (Terentang) Minyak Bekisting Balok Kayu Klas II Plywood tebal 9mm

320.35 0.045 0.07 0.1 0.15


384.85 0.045 0.08 0.1 0.18 0.015 0.03 0.35 0.63
0.003 0.00447
Dolken Kayu Galam diameter 8 - 10 cm / 4 m Besi Beton Polos Kawat Beton Bata Merah 5 x 11 x 22

2 3.58
3.6 5.364 0.05 0.0745

70
Bata Merah 5 x 11 x 22 Ubin Keramik 30 x 30 cm Semen Warna Profil Allumunium "T" Kawat Ø 4 mm

5752.6

11.87 496.4034 1.50 62.73

3.6 148.39 0.15


Kawat Ø 4 mm Ramset Akuatik 60 x 120 cm Genteng Plentong Kayu Klas II (Kamfer) , Balok

6.18 1.05 43.28 1.5 61.83

25 2260.75

1.2
Kayu Klas II (Kamfer) , Balok Paku Biasa 2" - 5 " Lem Kayu Kayu Klas II (Kamfer), papan

0.612 1.25 0.64 1 0.51


0.300 5.397 0.024 0.43176
Kayu klas I (Jati), papan Kayu Kamfer, balok Besi Strip Kayu Klas II (Kamfer), balok

0.0108 - 0.23
1.1 0.187 15 2.55
1.1 0.56 15 7.65
0.014 1.26602
0.0154 0.644028
Kunci Tanam Biasa Kunci Tanam Kamar Mandi Engsel pintu Engsel Angin Kunci Lemari

1 4.00
1 1.00
1 15
1 16
1
Kunci Lemari Kaca tebal 3mm Cat Menie Plamuur Cat Dasar
2
1.1 6.6

0.2000 32.872 0.1500 24.654 0.1700 27.9412


Cat Penutup Kuas Pengencer Amplas Kloset Duduk / Monoblok
0.2600 42.7336 0.0100 1.6436 0.0300 4.9308 0.2000 32.872

1
oset Duduk / Monoblok Kelengkapan 6% dari harga Kloset Wastafel Perlengkapan 30% Harga Wastafel
1 0.06 0.06
1 1 0.3
ngkapan 30% Harga Wastafel Bak Fibreglass Perlengkapan 12% Bak Fibreglass
0.3
1 1 0.12 0.12
SMK N 7 SEMARANG
XI TKJIJ 2
RENCANA ANGGARAN BIAYA RAB
Pekerjaan : rumah tinggal type 36
Lokasi
T.A. : 2018

NO JENIS PEKERJAAN
I Pekerjaan Persiapan
1 Pembersihan Lokasi
2 Pemasangan Bowplank
sub total I
II Pekerjaan Tanah
1 Galian Tanah
2 Urugan Pasir
3 Urugan Tanah Kembali
sub total II
III Pekerjaan Pondasi
1 Pondasi Batu Kosong
2 Pondasi Batu Kali 1:8
sub total III
IV Pekerjaan Beton
1 Sloof fc 21,7 Mpa(K250)
2 Kolom fc 21,7 Mpa(K250)
3 Ring Balok
sub total IV
VI Pekerjaan P.S. Dinding
Pasangan Bata Tebal 1/2 1:5
sub total VI
VII Pekerjaan Plesteran
P.S. Plesteran 1:5 tebal 15mm
Pemasangan acian
sub total VII
VIII pekerjaan penutup lantai & dinding
Pemasangan Lantai Keramik 30 x 30 cm
sub total VIII
IX pekerjaan langit langit
Pemasangan Langit-langit Akustik Ukuran (60x120) cm
sub total IX
X pekerjaan penutup atap
Pemasangan Atap Genteng Plentong Kecil
sub total X
XI pekerjaan kayu
Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III
Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Klas I atau II
Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau II
Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter
Pemasangan konstruksi Gording, Kayu Klas II
Pemasangan Rangka Atap Sirap, Kayu Klas II
Pemasangan Rangka Langit-langit (50x1,00) m, kayu Klas II atau III
sub total XI
XII pekerjaan kunci dan kaca
Pemasangan Kunci Tanam Biasa
Pemasangan Kunci Kamar Mandi
Pemasangan Engsel Pintu
Pemasangan Engsel Angin
Pemasangan Kunci Lemari
Pemasangan Kaca tebal 3 mm
sub total XIII
XIII pekerjaan pengecatan
Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup)
sub total XIII
XIV pekerjaan sanitasi dlm gedung
Pemasangan Closet Duduk / Mono Blok
Pemasangan Wastafel
Pemasangan Bak Fibreglass vol.1 m3
sub total XIV
sub total V
TOTAL
NG

AYA RAB

SATUAN VOLUME H. SATUAN JUMLAH

m² 88.00 11,825.00 1,040,600.00


m 32.00 138,440.50 4,430,096.00
5,470,696.00

m³ 51.51 68,557.50 3,531,396.83


m³ 2.23 233,585.00 520,894.55
m³ 17.17 13,475.00 231,365.75
4,283,657.13
-
m³ 8.95 503,629.50 4,507,484.03 ²
m³ 16.54 780,890.00 12,915,920.60 ³
17,423,404.63
-
m³ 1.49 1,033,492.78 1,539,904.24
m³ 1.79 1,033,492.78 1,849,952.07
m³ 1.49 1,033,492.78 1,539,904.24
4,929,760.55
-
m² 82.18 98,281.70 8,076,790.11
8,076,790.11
-
m² 324.36 50,532.46 16,390,708.73
m² 280.04 28,689.38 8,034,287.33
24,424,996.06

m² 41.82 182,802.50 7,644,800.55


7,644,800.55

m² 41.22 87,477.50 3,605,822.55


3,605,822.55

m² 90.43 79,315.50 7,172,500.67


7,172,500.67

m3 0.51 11,360,250.00 5,793,727.50


m2 17.99 490,105.00 8,816,988.95
m' 21.00 290,097.50 6,092,047.50
m3 0.17 10,137,490.00 1,723,373.30
m3 0.51 9,505,650.00 4,847,881.50
m2 90.43 130,229.00 11,776,608.47
m2 41.82 167,073.50 6,987,013.77
46,037,640.99

Buah 4.00 200,172.50 800,690.00


Buah 1.00 138,586.25 138,586.25
Buah 15.00 23,058.75 345,881.25
Buah 16.00 43,276.75 692,428.00
Buah 2.00 31,884.05 63,768.10
m2 6.00 100,527.63 603,165.75
2,644,519.35

m2 164.36 38,291.00 6,293,508.76


6,293,508.76

buah 1.00 2,038,509.00 2,038,509.00


Buah 1.00 525,525.00 525,525.00
Buah 1.00 1,038,400.00 1,038,400.00
3,602,434.00
24,424,996.06
162,433,093.39

Semarang, 13 Agustus 2018

HENRI RIVALDE
Estimator
DAFTAR HARGA SATUAN PEKERJAAN
BERDASAR PERMEN PUPERA NO.28/PRT/M/2016

SUMBER DATA : PASARAN BEBAS SEPTEMBER 2017


DAERAH : KOTA SEMARANG DAN SEKITAR

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM
### Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi 2,00
1 A.2.2.1.2 m' 591,802.75
m
2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 138,440.50

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 1,808,262.50

4 A.2.2.1.6 Pembuatan Rumah Jaga (Konstruksi Kayu) m2 1,462,945.00

5 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,429,078.75

6 A.2.2.1.8 Pembuatan Bedeng Pekerja m2 1,659,790.00

7 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 11,825.00

8 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 288,532.20

9 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm bh 495,902.00

10 A.2.2.1.13 Bongkaran Beton Bertulang m3 1,015,652.00

11 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 479,776.00

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 55,962.50

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 68,557.50

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 81,339.50

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 74,492.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 112,860.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 90,007.50

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 4,042.50

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 24,530.00


Pengurugan Kembali di hitung dari 1/3 kali koefisien
9 A.2.3.1.9 m3 13,475.00
Pekerjaan galian
10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 40,425.00

11 A.2.3.1.11 Urugan Pasir m3 233,585.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 387,673.00


Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang
13 A.2.3.1.13 m2 58,327.50
Resapan
14 A.2.3.1.14 Mengurug Sirtu Padat m3 257,812.50

457687078.xls 130/38 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 878,817.50

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 844,470.00

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 820,627.50

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 803,880.00

5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 780,890.00

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 701,882.50


Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 770,275.00
PP

8 A.3.2.1.8 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP m3 750,970.00

9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 503,629.50


Pasang Pondasi Siklop, 60% Beton Campuran 1PC :
10 A.3.2.1.10 m3 2,417,767.00
2PB : 3KR & 40% Batu B0elah
11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 847,203.50

IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON


Membuat Beton mutu f'c=7,4 Mpa (K100), slum
1 A.4.1.1.1 m3 917,922.50
(12±2)cm, w/c = 0,87
Membuat Beton mutu f'c=9,8 Mpa (K125), slum
2 A.4.1.1.2 m3 942,522.78
(12±2)cm, w/c = 0,78
Membuat Beton mutu f'c=12,2 Mpa (K150), slum
3 A.4.1.1.3 m3 961,702.50
(12±2)cm, w/c = 0,72
Membuat Lantai Kerja Beton mutu f'c=7,4 MPa
4 A.4.1.1.4 m3 865,185.44
(K100), slum (3-6)cm, w/c = 0,87
Membuat Beton mutu f'c=14,5 MPa (K175), slum
5 A.4.1.1.5 m3 984,353.33
(12±2)cm, w/c = 0,66
Membuat Beton mutu f'c=16,9 MPa (K200), slum
6 A.4.1.1.6 m3 1,006,182.22
(12±2)cm, w/c = 0,61
Membuat Beton mutu f'c=19,3 MPa (K225), slum
7 A.4.1.1.7 m3 1,022,440.83
(12±2)cm, w/c = 0,58
Membuat Beton mutu f'c=21,7 MPa (K250), slum
8 A.4.1.1.8 m3 1,033,492.78
(12±2)cm, w/c = 0,56
Membuat Lantai Kerja Beton mutu f'c=24,0 MPa
9 A.4.1.1.9 m3 1,052,920.00
(K275), slum (12±2)cm, w/c = 0,53
Membuat Beton mutu f'c=26,4 MPa (K300), slum
10 A.4.1.1.10 m3 1,058,765.28
(12±2)cm, w/c = 0,52
Membuat Beton mutu f'c=28,8 MPa (K325), slum
11 A.4.1.1.11 m3 1,122,913.61
(12±2)cm, w/c = 0,49
Membuat Beton mutu f'c=31,2 MPa (K350), slum
12 A.4.1.1.12 m3 1,130,769.44
(12±2)cm, w/c = 0,48
13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir Kg 13,581.70

14 A.4.1.1.18 Kabel Presstresed Polos/strand Kg 17,776.55

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh Kg 28,554.90

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 158,675.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 169,675.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 361,872.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 380,022.50

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 454,272.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 415,222.50

457687078.xls 130/39 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 339,377.50

23 A.4.1.1.27 Memasang Jembatan Cor m2 95,238.00

24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 75,916.50

25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 96,874.25

HARGA SATUAN PEKERJAAN BESI &


V A.4.2.1
ALLUMUNIUM
1 A.4.2.1.1 Pemasangan Besi Profil Kg 28,154.50

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF Kg 19,552.50

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 94,341.50


Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,
4 A.4.2.1.4 m2 791,637.00
rangka baja Siku
5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 2,184.60

6 A.4.2.1.6 Pembuatan Rangka Jendela Besi Scuare Tube m2 202,265.80

7 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 533,841.00

8 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 494,593.00

9 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 425,414.00

10 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 427,075.00

11 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 109,230.55

12 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 474,261.70

13 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 441,716.00

14 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 165,473.00

15 A.4.2.1.15 Pemasangan Teralis Besi Strip (2x3) cm m2 447,461.81

16 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 81,688.10

17 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 117,298.50


Pemasangan Talang Datar / Jurai , Seng BJLS 28
18 A.4.2.1.18 m' 176,561.00
Lebar 90 cm
Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;
19 A.4.2.1.20 m2 105,165.50
Modul 60x120 cm dinding partisi
Pemasangan Rangka Besi Hollow 1 x 40.40.2mm;
20 A.4.2.1.21 m2 131,373.00
Modul 60x60 cm dinding plafond
Pemasangan Atap Pelana Rangka Atap Baja Canal
21 A.4.2.1.22 m2 189,120.80
C dingin Profil C75
Pemasangan Atap Jurai Rangka Atap Baja Canal
22 A.4.2.1.23 m2 213,441.80
Dingin Profil C75

HARGA SATUAN PEKERJAAN PASANGAN


VI A.4.4.1
DINDING
Pemasangan Dinding Bata Merah ukuran (5x11x22)
1 A.4.4.1.1 m2 221,031.25
cm Tebal 1 bata Camp. 1SP: 2PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
2 A.4.4.1.2 m2 212,161.13
cm Tebal 1 Bata Camp. 1SP : 3PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
3 A.4.4.1.3 m2 205,495.13
cm Tebal 1 Bata Camp. 1SP : 4PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
4 A.4.4.1.4 m2 203,065.50
cm Tebal 1 Bata Camp. 1SP : 5PP

457687078.xls 130/40 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
5 A.4.4.1.5 m2 204,393.75
cm Tebal 1 Bata Camp. 1SP : 6PP
Pemasangan Dinding Bata Merah Ukuran (5x11x22)
6 A.4.4.1.6 m2 195,862.70
cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP
Pemasangan Dinding Bata Merah Ukuran
7 A.4.4.1.7 m2 106,808.63
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP
Pemasangan Dinding Bata Merah Ukuran
8 A.4.4.1.8 m2 102,194.68
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP
Pemasangan Dinding Bata Merah Ukuran
9 A.4.4.1.9 m2 99,783.75
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP
Pemasangan Dinding Bata Merah Ukuran
10 A.4.4.1.10 m2 98,281.70
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP
Pemasangan Dinding Bata Merah Ukuran
11 A.4.4.1.11 m2 97,848.30
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP
Pemasangan Dinding Bata Merah Ukuran
12 A.4.4.1.12 m2 96,071.25
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP
Pemasangan Dinding Bata Merah Ukuran
13 A.4.4.1.13 (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : m2 98,766.25
10PP
Pemasangan Dinding Bata Merah Ukuran
14 A.4.4.1.14 m2 89,545.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
Pemasangan Dinding Bata Merah Ukuran
15 A.4.4.1.15 m2 90,161.50
(5x11x22)cm Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP
Pemasangan Dinding HB/CB 20, speci camp. 1SP :
16 A.4.4.1.16 m2 334,012.80
3PP
Pemasangan Dinding HB/CB 20, speci camp. 1SP :
17 A.4.4.1.17 m2 339,280.15
4PP
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
18 A.4.4.1.18 m2 264,372.35
3PP
Pemasangan Dinding HB/CB 15, speci camp. 1SP :
19 A.4.4.1.19 m2 268,053.50
4PP
Pemasangan Dinding HB/CB 10, speci camp. 1SP :
20 A.4.4.1.20 m2 194,319.40
3PP
Pemasangan Dinding HB/CB 10, speci camp. 1SP :
21 A.4.4.1.21 m2 197,503.08
4PP
Pemasangan Dinding Terawang (Rooster) Uk,
22 A.4.4.1.22 m2 417,670.00
(12x11x24)cm Camp. 1SP : 3PP
Pemasangan Dinding Terawang (Rooster) Uk,
23 A.4.4.1.23 m2 417,670.00
(12x11x24)cm Camp. 1SP : 4PP
Pemasangan Dinding Bata Berongga Ekspose Uk,
24 A.4.4.1.24 m2 134,227.50
(12x11x24)cm Camp. 1SP : 3PP
Pemasangan Dinding Bata Ringan Tebal 7,5 cm
25 A.4.4.1.25 m2 120,061.04
dengan Mortar Siap Pakai
Pemasangan Dinding Bata Ringan Tebal 10 cm
26 A.4.4.1.26 m2 137,338.74
dengan Mortar Siap Pakai

VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.4.2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 59,418.26

2 A.4.4.2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 54,565.06

3 A.4.4.2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 52,629.94

4 A.4.4.2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 51,173.10

5 A.4.4.2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 50,532.46

6 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 49,941.54

7 A.4.4.2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 49,675.34

8 A.4.4.2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 49,409.14

457687078.xls 130/41 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15
9 A.4.4.2.9 m2 50,230.40
mm
Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15
10 A.4.4.2.10 m2 49,703.50
mm
Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15
11 A.4.4.2.11 m2 46,447.50
mm
Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15
12 A.4.4.2.12 m2 47,030.50
mm
13 A.4.4.2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 73,032.08

14 A.4.4.2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 54,182.20

15 A.4.4.2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 68,417.80

16 A.4.4.2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 67,655.28

17 A.4.4.2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 66,775.72


Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20
18 A.4.4.2.18 m2 64,806.50
mm
19 A.4.4.2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 31,859.96
Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10
20 A.4.4.2.20 m' 49,392.75
mm
Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal
21 A.4.4.2.21 m' 84,177.50
10 mm
Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10
22 A.4.4.2.22 m' 84,177.50
mm
23 A.4.4.2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 39,163.30
Pemasangan Finishing Siar Pasangan Dinding Bata
24 A.4.4.2.24 m2 22,369.27
Merah
Pemasangan Finishing Siar Pasangan Dinding
25 A.4.4.2.25 m2 10,659.00
Conblock ekspose
Pemasangan Finishing Siar Pas.Batu Kali Adukan
26 A.4.4.2.26 m2 47,985.85
1Pc : 2Pp
27 A.4.4.2.27 Pemasangan Acian m2 28,689.38

28 A.4.4.2.28 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) m2 37,578.20

29 A.4.4.2.29 Pemasangan Acian dg Mortar Siap Pakai (MSP) m2 31,460.00

HARGA SATUAN PEKERJAAN PENUTUP LANTAI


VIII A.4.4.3 dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 95,385.50

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 95,293.00

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 121,812.50

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 124,223.00

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 337,942.00

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 59,219.60

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 34,191.85

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 36,689.09


Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20
9 A.4.4.3.33 m2 188,726.73
cm
10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 192,354.28

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 182,802.50

457687078.xls 130/42 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 191,922.50
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 m2 387,596.00
variasi / border
14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 32,701.35

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 79,060.85

16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 76,728.85

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 670,911.73

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 195,189.50

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 366,437.50

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 222,289.41

21 A.4.4.3.49 Pemasangan Dinding Porselen 10x20 cm, m2 202,133.25

22 A.4.4.3.50 Pemasangan Dinding Porselen 20x20 cm, m2 211,010.25

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm, m2 202,133.25

24 A.4.4.3.54 Pemasangan Dinding Keramik 20x20 cm, m2 212,154.25

25 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 745,394.22


Pemasangan Dinding Batu Paros / Batu Tempel
26 A.4.4.3.58 m2 243,560.63
Hitam
27 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 138,373.40

28 A.4.4.3.60 Pemasangan Wallpaper Lebar 50 Cm m2 108,240.00

29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 42,339.00

30 A.4.4.3.64 Pemasangan Paving Block Natural Tebal 6 Cm m2 137,005.55

31 A.4.4.3.65 Pemasangan Paving Block Natural Tebal 8 Cm m2 206,124.05

32 A.4.4.3.66 Pemasangan Paving Block Berwarna Tebal 6 Cm m2 143,116.05

33 A.4.4.3.67 Pemasangan Paving Block Berwarna Tebal 8 Cm m2 218,345.05

HARGA SATUAN PEKERJAAN LANGIT-


IX A.4.5.1
LANGIT
Pemasangan Langit-langit Asbes (1,00x1,00) m,
1 A.4.5.1.1 m2 28,281.00
tebal 4 mm, 5 mm & 6 mm
Pemasangan Langit-langit Akustik Ukuran (30x30)
2 A.4.5.1.2 m2 98,219.00
cm
Pemasangan Langit-langit Akustik Ukuran (30x60)
3 A.4.5.1.3 m2 102,393.50
cm
Pemasangan Langit-langit Akustik Ukuran (60x120)
4 A.4.5.1.4 m2 87,477.50
cm
Memasang Langit-langit Tripleks Uk (120x240) cm,
5 A.4.5.1.5 m2 42,619.50
Tebal 3 mm, 4 mm & 6 mm
Memasang Langit-langit Lambriziring Kayu Jati, tebal
6 A.4.5.1.6 m2 502,414.00
6 mm
Memasang Langit-langit Gypsu Board, Ukuran
7 A.4.5.1.7 m2 38,351.50
(120x240) tebal 9 mm
Memasang Langit-langit Akuatik Uk (60x120) cm &
8 A.4.5.1.8 m2 196,102.50
Berikut Rangka Allumunium
9 A.4.5.1.9 List Langit-Langit Kayu Profil m1 14,448.50

457687078.xls 130/43 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
HARGA SATUAN PEKERJAAN PENUTUP
X A.4.5.2
ATAP
1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 79,315.50

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 135,740.00

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 119,845.00

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 89,562.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 101,937.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 105,787.00

7 A.4.5.2.7 Pemasangan Roof Light Fibreglass 90 x 180 m2 100,523.50


Pemasangan Atap Asbes Gelombang (2,50x0,92 m)
8 A.4.5.2.8 m2 59,521.00
x 5 mm
Pemasangan Atap Asbes Gelombang (2,25x0,92 m)
9 A.4.5.2.9 m2 61,473.50
x 5 mm
Pemasangan Atap Asbes Gelombang (2,00x0,92 m)
10 A.4.5.2.10 m2 61,803.50
x 5 mm
Pemasangan Atap Asbes Gelombang (1,80x0,92 m)
11 A.4.5.2.11 m2 69,063.50
x 5 mm
Pemasangan Atap Asbes Gelombang (3,00x1,05 m)
12 A.4.5.2.12 m2 47,283.50
x 4 mm
Pemasangan Atap Asbes Gelombang (2,70x1,05 m)
13 A.4.5.2.13 m2 51,903.50
x 4 mm
Pemasangan Atap Asbes Gelombang (2,40x1,05 m)
14 A.4.5.2.14 m2 49,813.50
x 4 mm
Pemasangan Atap Asbes Gelombang (2,10x1,05 m)
15 A.4.5.2.15 m2 48,735.50
x 4 mm
Pemasangan Atap Asbes Gelombang (1,50x1,05 m)
16 A.4.5.2.16 m2 54,763.50
x 4 mm
Pemasangan Atap Asbes Gelombang (3,00x1,08 m)
17 A.4.5.2.17 m2 61,484.50
x 6 mm
Pemasangan Atap Asbes Gelombang (2,70x1,08 m)
18 A.4.5.2.18 m2 64,839.50
x 6 mm
Pemasangan Atap Asbes Gelombang (2,40x1,08 m)
19 A.4.5.2.19 m2 61,671.50
x 6 mm
Pemasangan Atap Asbes Gelombang (2,10x1,08 m)
20 A.4.5.2.20 m2 62,683.50
x 6 mm
Pemasangan Atap Asbes Gelombang (1,80x1,08 m)
21 A.4.5.2.21 m2 66,588.50
x 6 mm
22 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 98,087.00

23 A.4.5.2.31 Pemasangan Atap Genteng Aspal m2 211,189.00

24 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 84,205.00

25 A.4.5.2.34 Pemasangan Atap Sirap m2 101,222.00

26 A.4.5.2.35 Pemasangan Nok Genteng Beton m' 110,297.00

27 A.4.5.2.36 Pemasangan Nok Genteng Aspal m' 117,518.50

28 A.4.5.2.37 Pemasangan Nok Genteng Metal m' 58,745.50

29 A.4.5.2.38 Pemasangan Nok Sirap m' 47,327.50

30 A.4.5.2.39 Pemasangan Atap Seng Gelombang m2 35,728.00

31 A.4.5.2.40 Pemasangan Atap Nok Seng m' 27,500.00

32 A.4.5.2.43 Pasang Allumunium Foil / Sisalation m2 25,030.50

457687078.xls 130/44 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 m3 26,822,125.00
Kayu klas I
Pembuatan & Pemasangan Kosen Pintu & Jendela
2 A.4.6.1.2 m3 11,360,250.00
Kayu klas II atau III
Pembuatan & Pemasangan Pintu KlampStandard
3 A.4.6.1.3 m2 447,073.00
Kayu Klas II (Kayu Kamfer)
Pembuatan & Pemasangan Daun Pintu Klamp
4 A.4.6.1.4 m2 447,073.00
Sederhana Kayu Klas III
Pembuatan & Pemasangan Daun Pintu Panel, Kayu
5 A.4.6.1.5 m2 687,362.50
Klas I atau II
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 m2 490,105.00
Kayu Klas I atau II
Pembuatan & Pemasangan Pintu & Jendela Jalusi
7 A.4.6.1.7 m2 1,925,550.00
Kayu Klas I atau II (jati)
Pembuatan&Pemasangan Pintu kayu lapis
8 A.4.6.1.8 (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 m2 535,749.50
cm)
Pembuatan&Pemasangan Pintu Plywood rangkap,
9 A.4.6.1.9 m2 577,489.00
rangka expose kayu klas I atau II
Pembuatan & Pemasangan Jalusi mati Kosen Kayu
10 A.4.6.1.10 m2 1,729,337.50
Klas I atau II
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 m2 976,987.00
Rangkap, Rangka Expose Kayu Klas I
Pembuatan & Pemasangan Pintu Teakwood
12 A.4.6.1.12 Rangkap Lapis Formika, Rangka expose Kayu Klas m2 622,902.50
II
Pembuatan&Memasang Konstruksi Kuda-kuda
13 A.4.6.1.13 m3 10,137,490.00
Konvensional Kayu I; II & III Bentang 6 meter
Pembuatan&Pemasangan Konstruksi Kuda-kuda
14 A.4.6.1.14 m3 29,187,152.50
Expose, Kayu Klas I
15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 9,505,650.00
Pemasangan Rangka Atap Genteng Keramik, Kayu
16 A.4.6.1.16 m2 154,841.50
Klas II
Pemasangan Rangka Atap Genteng Beton, Kayu
17 A.4.6.1.17 m2 182,165.50
Klas II
18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 130,229.00
Pemasangan Rangka Langit-langit (50x1,00) m,
19 A.4.6.1.19 m2 167,073.50
kayu Klas II atau III
Pemasangan Rangka Langit-langit (60x60) cm, kayu
20 A.4.6.1.20 m2 172,172.00
Klas II atau III
Pemasangan Listplank Uk. (3x20)cm Kayu klas I
21 A.4.6.1.21 m' 290,097.50
atau II
Pemasangan Listplank Uk. (3x30)cm Kayu klas I
22 A.4.6.1.22 m' 115,087.50
atau klas II
Pemasangan Rangka Dinding Pemisah (60x120) cm
23 A.4.6.1.23 m2 270,358.00
Kayu klas II atau III
Pemasangan Dinding Pemisah Teakwood Rangkap
24 A.4.6.1.24 m2 339,548.00
Rangka Kayu Klas II
Pemasangan Dinding Pemisah Plywood Rangkap
25 A.4.6.1.25 m2 345,125.00
Rangka Kayu Klas II
Pemasangan Dinding Lambriziring dari Papan Kelas
26 A.4.6.1.26 m2 393,855.00
I
Pemasangan Dinding Lambriziring dari Plywood
27 A.4.6.1.27 m2 36,443.00
ukuran (120x240) cm
Pemasangan Dinding Bilik, Rangka Kayu Klas III
28 A.4.6.1.28 m2 119,633.14
atau IV

457687078.xls 130/45 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
HARGA SATUAN PEKERJAAN KUNCI dan
XII A.4.6.2
KACA
1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 200,172.50

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 138,586.25

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 199,086.25

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 23,058.75

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 15,372.50

6 A.4.6.2.7 Pemasangan Engsel Angin Buah 43,276.75

7 A.4.6.2.9 Pemasangan Kait Angin Buah 22,005.50

8 A.4.6.2.10 Pasang Door Closer Buah 355,258.75

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 32,103.50

10 A.4.6.2.13 Pemasangan Door Stop Buah 313,051.75

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 261,310.50

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 31,884.05

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 100,527.63

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 124,727.63

15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 288,077.63

XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 m2 11,665.50
Lama
Pencucian Bidang Permukaan Tembok yang Pernah
2 A.4.7.1.2 m2 11,610.50
dicat
Pengerokan Karat Cat Lama permukaan Baja dg
3 A.4.7.1.3 m2 12,078.00
cara manual
Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp
4 A.4.7.1.4 m2 38,291.00
Cat dasar, 2 Lp Cat Penutup)
Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp
5 A.4.7.1.5 m2 51,491.00
Cat dasar, 3 Lp Cat Penutup)
6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 31,157.50

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 53,927.50

8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 8,769.75

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 33,214.50


Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar
10 A.4.7.1.10 m2 17,690.20
2 Lap.Cat Penutup)
Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat
11 A.4.7.1.11 m2 12,334.30
Penutup)
12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 6,856.30

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 12,967.90


Pelaburan Tembok lama dengan Kapur Sirih
14 A.4.7.1.14 m2 5,989.50
(pemeliharaan)
15 A.4.7.1.15 Pemasangan Wallpaper m2 79,543.75

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 22,266.75


Pengecatan Permukaan Baja dg Meni Besi &
17 A.4.7.1.17 m2 45,581.25
Perancah

457687078.xls 130/46 hspk


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM
Rp
HARGA SATUAN PEKERJAAN SANITASI
XIV A.5.1.1
DALAM GEDUNG
1 A.5.1.1.1 Pemasangan Closet Duduk / Mono Blok Unit 2,038,509.00

2 A.5.1.1.2 Pemasangan Closet Jongkok Porselen Unit 519,475.00

3 A.5.1.1.4 Pemasangan Urinoir Unit 688,765.00

4 A.5.1.1.5 Pemasangan Wastafel Unit 525,525.00

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,069,068.00

6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 1,038,400.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,309,484.27

8 A.5.1.1.11 Pemasangan Bak Beton Bertulang Vol. 1 m3 Unit 6,119,478.78

9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 335,417.50

10 A.5.1.1.14 Pemasangan Floor Drain buah 27,472.50


Pemasangan Bak Kontrol Pas.Batu Bata 30x30
11 A.5.1.1.15 bh 384,500.29
tinggi 35 cm
Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45
12 A.5.1.1.16 bh 561,336.29
tinggi 50 cm
Pemasangan Bak Kontrol Pas.Batu Bata 60x60
13 A.5.1.1.17 bh 690,273.37
tinggi 60 cm
14 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 39,350.67

15 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 78,848.00

16 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 47,875.67

17 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 53,559.00

18 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 74,119.83

19 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 151,734.00

20 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 271,084.00

21 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 19,291.25

22 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 21,422.50

23 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 24,406.25

24 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 26,024.17

25 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 30,002.50

26 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 53,624.08

27 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 59,785.00


Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø
28 A.5.1.1.33 m' 73,386.50
20 cm
Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø
29 A.5.1.1.34 m' 34,765.50
15 cm
30 A.5.1.1.35 Pemasangan Pipa Beton Ø 15 - 20 cm m' 96,162.55

31 A.5.1.1.36 Pemasangan Pipa Beton Ø 30 - 100 cm m' 543,298.25

457687078.xls 130/47 hspk


DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN B E BAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI SEPTEMBER 2017

HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)

1 Dump Truck 3 ton Jam 115,000 120,000

2 Dump Truck 9 ton Jam 160,000 170,000

3 Truk Bak Terbuka Engkel Jam 130,000 140,000

4 Truk Tanki Air Jam 290,000 300,000

5 Bulldozer 100 - 150 hp Jam 650,000 700,000

6 Motor Grader Jam 600,000 640,000

7 Wheel Loader Jam 250,000 280,000

8 Excavator Jam 610,000 660,000

9 Crane 35 ton Jam 435,000 450,000

10 Flat Bed Truck jam 400,000 440,000

11 Baby Roller / Pedestrian Jam 110,000 120,000

12 P.Tire Roller 8 - 10 ton Jam 530,000 550,000

13 Baby Roller jam 50,000 60,000

14 Vibrator Roller self 7 ton Jam 500,000 510,000

15 Pile Driver / Hammer jam 150,000 160,000

16 Water Pump Jam 35,000 40,000

17 Asphalt Sprayer Jam 135,000 140,000


18 Pick Up single cabin Jam 55,000 64,000

19 A M P Jam 5,500,000 5,600,000

20 Asphalt Finisher Jam 330,000 350,000

21 Concrete Vibrator Jam 55,000 60,000

22 Compressor Jam 300,000 320,000


23 Concrete Mixer 0,125m3 Jam 75,000 80,000

24 Concrete Cutter jam 35,000 40,000

25 Stamper Jam 35,000 40,000

26 Genset 5-25kva+bbm Jam 180,000 185,000

27 Alat Pengecat Marka Jam 300,000 320,000

28 Mesin Las jam 180,000 200,000

29 Stone Crusher jam 850,000 900,000

30 Truck Trailler trip 7,250,000 7,400,000


DAFTAR U PAH PE K E R JA

SUMBER DATA : PASARAN B E BAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI SEPTEMBER 2017

HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 65,000 75,000

2 Mandor Hr 85,000 95,000

3 Tukang listrik Hr 80,000 95,000

4 Tukang kayu Hr 80,000 95,000

5 Kep. tk. kayu Hr 90,000 110,000

6 Tukang batu Hr 80,000 90,000

7 Kep. tk. batu Hr 90,000 110,000

8 Tukang besi Hr 80,000 90,000

9 Kep. tk. besi Hr 90,000 110,000

10 T u k a n g c a t Hr 80,000 90,000

11 K e p . t k . c a t Hr 90,000 110,000

12 T u k a n g p l i t u r Hr 80,000 90,000

13 T u k a n g j a l a n Hr 65,000 75,000

14 T u k a n g g a l i Hr 65,000 75,000

15 Tukang masak aspal Hr 65,000 75,000

16 T k . l e i d e n g Hr 80,000 90,000

17 M a s i n i s Hr 150,000 175,000

18 P e m b . M a s i n i s Hr 100,000 110,000

19 P e n j a g a a p i Hr 65,000 75,000

20 P e n j a g a m a l a m Hr 65,000 75,000

21 Sopir Hr 150,000 170,000

22 Pembantu Sopir Hr 100,000 110,000

457687078.xls 130 utk


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI SEPTEMBER 2017

HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 220,000 250,000
Bulat Belah m3 250,000 300,000
Pecah 10/15 m3 250,000 300,000
Pecah 5/7 m3 300,000 350,000
Pecah 3/5 m3 330,000 360,000
2 KERIKIL Timbun m3 180,000 200,000
Sawur / Koral m3 160,000 180,000
Beton 0,5/1 m3 280,000 370,000
Beton 1/2 m3 300,000 400,000
Beton 2/3 m3 300,000 390,000
Biasa m3 240,000 260,000
Tras Giling m3 280,000 330,000
3 BATU BATA ex lokal bh 550 600

4 PASIR Urug m3 160,000 230,000


Pasang m3 250,000 370,000
Beton m3 350,000 500,000
5 TANAH Padas m3 110,000 120,000
Liat m3 110,000 140,000
6 KAPUR Pasang m3 300,000 310,000
Semen Merah m3 185,000 200,000
7 PORTLAND CEMENT
Merk I 40 kg zak 41,000 44,000
Merk I 50 kg zak 50,000 54,000
Merk II 40 kg zak 41,000 43,000
Merk II 50 kg zak 51,000 54,000
Semen Putih 40 kg zak 78,000 80,000
Semen Putih 50 kg zak 88,000 95,000
Semen warna kg 11,000 12,000

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 185,000 190,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,000 7,000


Genteng Beton Warna Special bh 9,500 10,500
Genteng Beton Warna Khusus bh 14,000 15,200
Kerpus Beton Warna Standard bh 10,000 10,050
Kerpus Beton Warna Special bh 11,500 12,000
Kerpus Beton Warna Khusus bh 13,000 13,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,200 2,400
Kodok bh 2,500 3,200
Kodok Glasur bh 4,250 4,350
Nok kerpus Kodok bh 6,500 6,800
Nok kerpus Kodok Glasur bh 8,000 12,000
Plentong super besar 18 bh/m2 bh 5,100 5,350
Nok kerpus plentong super bh 9,000 9,200
4 GENTENG KACA
Vlaam tebal 2 mm bh 12,000 13,000
Vlaam tebal 3 mm bh 13,500 15,000
Kodok tebal 2 mm bh 12,500 14,000
Kodok tebal 3 mm bh 14,500 15,500

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 85,000 115,000
. 225 cm X 102 cm X 5 mm bh 98,000 125,000
. 250 cm X 102 cm X 5 mm bh 108,000 135,000
. 200 cm X 102 cm X 6 mm bh 95,000 120,000
. 225 cm X 102 cm X 6 mm bh 97,500 130,000
. 250 cm X 102 cm X 6 mm bh 105,000 140,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 40,000 47,000
. 180 cm X 105 cm X 4 mm bh 47,000 54,000
. 210 cm X 105 cm X 4 mm bh 52,000 63,000
. 240 cm X 105 cm X 4 mm bh 62,500 72,000
. 270 cm X 105 cm X 4 mm bh 70,000 81,000
. 300 cm X 105 cm X 4 mm bh 72,000 85,000
ONDULINE : 95 cm x 200cm x 0.3mm lbr 145,000 155,000
ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 80,000 90,000
NOK Jabes nok
. Kerpus Genteng bh 31,000 40,000
. Stel Besar bh 45,000 50,000
. Paten Besar bh 43,000 47,000
Nokstel gelombang harflex
. Stel Besar bh 44,000 48,000
. Patent Besar bh 27,000 30,500
. Plat besar bh 51,000 55,000
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 105,000 110,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 15,500 17,000
. 100cm X 100 cm X 4 mm bh 16,000 20,000
. 50 cm X 200 cm X 3 mm bh 14,000 15,000
. 40 cm X 200 cm X 3 mm bh 13,000 14,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 25,000 30,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 69,000 72,500
uk. 122cm x 244cm x 4mm lbr 70,000 75,000
GRC BOARD uk.122cm x 244cm x 5mm lbr 100,000 108,000
uk.122cm x 244cm x 6mm lbr 125,000 132,000
uk.122cm x 244cm x 8mm lbr 185,000 192,000
uk.122cm x 244cm x 10mm lbr 245,000 260,000
7 FIBRE GLASS (JABES)
180 X 92 cm bh 50,000 60,000
200 X 92 cm bh 57,500 65,000
250 X 92 cm bh 65,500 74,000
180 X 105 cm bh 68,000 90,000
210 X 105 cm bh 70,000 105,000
250 X 105 cm bh 80,000 120,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 20,000 24,500
BJLS 0,20 lebar 55 cm m' 24,500 30,000
BJLS 0,28 lebar 55 cm m' 26,500 30,000
BJLS 0,30 lebar 55 cm m' 30,000 36,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 40,000 45,000
BJLS 0,20 panjang 180 cm lbr 42,000 55,000
BJLS 0,30 panjang 180 cm lbr 59,000 60,000
BJLS 0,40 panjang 180 cm lbr 69,000 75,000
III . B A H A N K A Y U
1 JATI Papan m3 22,000,000 23,000,000
Balok/pesagen m3 20,000,000 20,500,000
2 KAMPER Papan m3 7,200,000 7,800,000
Balok/pesagen m3 6,900,000 7,500,000
3 KRUING Papan m3 6,250,000 7,000,000
Balok/pesagen m3 5,500,000 6,100,000
4 MERANTI Papan m3 4,800,000 5,700,000
Balok/pesagen m3 4,500,000 5,400,000
5 LANAN Papan m3 2,050,000 3,800,000
Balok/pesagen m3 2,000,000 2,200,000
6 BENGKIRAI Papan m3 8,750,000 10,000,000
Balok/pesagen m3 9,000,000 9,850,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 21,000 24,000
Kecil 6 x 7 x 400 cm bt 18,000 21,000
Besar 10 x 12 x 400 cm bt 31,000 34,000
Kayu cetakan m3 2,200,000 2,700,000
Kayu bakar m3 150,000 170,000
Bambu bt 11,000 12,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 34,000 36,000
20 X 20 cm m2 32,000 34,000
PC warna 30 X 30 cm m2 40,000 46,000
20 X 20 cm m2 40,000 42,000
Teraso 30 X 30 cm m2 52,000 56,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,200 5,500
PC abu-abu 15 x 20 bh 5,100 6,000

3 POLIS UBIN Lantai/badan m'


Plint m'
Trap m'

4 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000 43,000
11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000
5 MOZAIK PORSELIN
10 X 20 cm m2 35,000 55,000
15 X 15 cm m2 45,000 55,000
20 X 20 cm m2 52,000 60,000
20 X 25 cm m2 52,000 56,000

6 Keramik 30 X 30 cm m2 45,000 57,000


20 X 20 cm m2 52,000 56,000
33 x 33 cm m2 52,000 60,000
25 x 25 cm m2 51,000 55,000
15 x 20 cm m2 52,000 57,000
2,250 2,500
7 Parquet Jati m2 210,000 310,000
8 Batu Paros m2 110,000 115,000
9 Batu Tempel Hitam m2 105,000 120,000
10 GRANITO 40 x 40 cm m2 220,000 250,000
30 x 30 cm m2 300,000 320,000
11 Marmer m2 475,000 480,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 29,000 40,000
Ø 20 cm - 100 cm bh 35,000 50,000
Ø 30 cm - 100 cm bh 55,000 70,000
Ø 50 cm - 100 cm bh 70,000 135,000
Ø 60 cm - 100 cm bh 80,000 190,000
Ø 70 cm - 100 cm bh 100,000 265,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
U 10 cm - 100 cm bh 22,000 22,500
U 15 cm - 100 cm bh 35,000 40,000
U 20 cm - 100 cm bh 36,000 45,000
U 30 cm - 100 cm bh 40,000 55,000
U 50 cm - 100 cm bh 65,000 70,000
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 11,000 12,000
20 X 20 cm bh 15,000 16,000
25 X 25 cm bh 16,500 17,000
30 X 30 cm bh 18,000 19,000
15 X 25 cm bh 12,500 13,000
15 X 30 cm bh 14,500 16,000
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 10,500 11,300
besi beton prestress kg 14,500 16,000
besi beton ulir kg 12,500 13,000

2 BESI PLAT Besi Strip kg 13,500 14,000

3 BESI PROFIL Besi Profil kg 14,000 14,500


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg 125,000 panj : 6 m
type CT 75 lebar : 7,5cm tebal : 0.75mm btg 85,000 panj : 6 m
lebar : 7,5cm tebal : 0,65mm btg 80,000 panj : 6 m
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 45,000 panj : 6 m
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 40,000 panj : 6 m
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,3 mm btg 18,000 22,000 panj : 4 m
tinggi 4 cm; tebal : 0,3 mm btg 24,000 30,000 panj : 4 m
4 JARING - JARING BAJA
Diameter 4 - 15 kg 13,500 14,000
Diameter 6 - 15 kg 13,500 14,500
Kawat Bronjong kg 9,500 10,000
5 BESI SIKU L 40 X 40 X 4 btg 100,000 120,000
L 50 X 50 X 5 btg 160,000 170,000
L 60 X 60 X 6 btg 230,000 250,000

6 KAWAT - Ikat beton/bendrat kg 14,000 16,000


- Harmonika 12 X 45 mm m2 20,000 20,500
- Harmonika 12 X 24 mm m2 18,000 21,000
- Harmonika 14 X 30 mm m2 15,000 20,000
- Harmonika 14 X 35 mm m2 19,000 27,500
- Kawat Nyamuk Nylon m2 10,000 18,000
- Kawat Kasa m2 15,000 20,000
- Saringan pasir m2 12,000 15,000
- Kawat loket m2 15,000 22,500
- Kawat duri rol 110,000 135,000
- Kawat bronjong kg 25,000 27,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 25,000 30,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 30,000 36,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 37,000 45,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 46,000 68,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 60,000 105,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 120,500 185,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 180,000 280,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 350,000 550,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 900,000 1,050,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg - - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg - - panjang 4 m

2 Pipa Medium B Galvanis - SII


Pipa Medium B Galvanis DN ½" btg 85,000 105,000 panjang 6 m
Pipa Medium B Galvanis DN 25 ( ¾" ) btg 115,000 150,000 panjang 6 m
Pipa Medium B Galvanis DN 32 ( 1" ) btg 135,000 180,000 panjang 6 m
Pipa Medium B Galvanis DN 50 ( 1½" ) btg 170,000 220,000 panjang 6 m
Pipa Medium B Galvanis DN 63 ( 2" ) btg 225,000 290,000 panjang 6 m
Pipa Medium B Galvanis DN 2½" btg 270,000 350,000 panjang 6 m
Pipa Medium B Galvanis DN 90 ( 3" ) btg 420,000 490,000 panjang 6 m
Pipa Medium B Galvanis DN 110 ( 4" ) btg 560,000 580,000 panjang 6 m
Pipa Medium B Galvanis DN 160 ( 6" ) btg 960,000 1,050,000 panjang 6 m
Pipa Medium B Galvanis DN 200 ( 8" ) btg 1,850,000 2,100,000 panjang 6 m
Pipa Medium B Galvanis DN 250 ( 10") btg - - panjang 6 m

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800 6,200
30 X 60 lbr 13,200 14,200
60 X 120 lbr 42,000 46,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000 68,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000 52,000
GYPROC uk.120cmx240cmx9mm lbr 57,500
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 55,000 75,000
. 120 X 240 X 3 mm lbr 75,000 95,000
. 90 X 210 X 4 mm lbr 65,000 80,000
. 90 X 210 X 9 mm lbr 95,000 125,000
. 90 X 210 X 12 mm lbr 135,000 170,000
. 90 X 210 X 15 mm lbr 165,000 240,000
. 90 X 210 X 18 mm lbr 200,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 50,000 60,000
. 120 X 240 X 4 mm lbr 60,000 70,000
. 120 X 240 X 6 mm lbr 75,000 80,000
Multipleks
. 120 X 240 X 9 mm lbr 120,000 160,000
. 120 X 240 X 12 mm lbr 145,000 180,000
. 120 X 240 X 15 mm lbr 165,000 190,000
. 120 X 240 X 18 mm lbr 195,000 230,000
Formika ukuran pintu lbr 68,000 75,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 25,000 30,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 3,000 4,100
Batu Apung kg 29,000 35,000
Cat dasar kg 34,000 36,500
. Emco kg 50,000 55,000
. Yunior 66 (nippon paint) kg 50,000 58,000
- Koas bh 7,500 8,000
. Deculux kg 55,000 58,000
. Siralax ons 10,000 20,000
. Spiritus ltr 10,000 18,000
. Plitur jadi ltr 65,000 70,000

2 TEMBOK
Kalkarium kg 4,200 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 20,000 32,000
Cat Tembok kg 22,000 23,000
Sintex 5 kg 110,000 115,000
Danabride 5 kg 105,000 115,000
Catylac 5 kg 115,000 125,000
Mowilex 2,50 kg 300,000 350,000

3 BESI
Menie kg 20,000 35,000
Cat mengkilat kg 55,000 58,000
Cat kg 40,000 85,000
Thinner A ltr 16,000 20,000
Minyak cat ltr 18,000 20,000
Thinner Super ltr 20,000 35,000
Residu (teer/aspal) drum 55,000 60,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 950,000 1,050,000
kapasitas 1100 liter. bh 1,625,000 2,000,000
Lem Aica Aibon kg 55,000 65,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 70,000 85,000
5 mm m2 90,000 95,000
2 ES KABUR 3 mm m2 75,000 85,000
5 mm m2 88,000 95,000
3 RAY BAND 3 mm m2 75,000 85,000
5 mm m2 85,000 92,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 3,100 3,300

SPLN LMK 1 X 2 1/2 mm2 m' 3,700 3,900

. 1X4 mm2 m' 5,700 6,000

1X6 mm2 m' 8,500 8,900

NYY :. 2 X 1 1/2 mm2 m' 9,000 9,450

PRIMA 2 X 2 1/2 mm2 m' 15,000 15,500

. 2X4 mm2 m' 27,000 28,000

2X6 mm2 m' 35,000 37,000

3 X 1 1/2 mm2 m' 13,200 14,000

3 X 2 1/2 mm2 m' 20,000 21,000

3X4 mm2 m' 34,500 36,500

3X6 mm2 m' 50,000 53,000

NYM :. 2 X 1 1/2 mm2 m' 7,000 8,000

PRIMA 2 X 2 1/2 mm2 m' 10,900 11,500

. 2X4 mm2 m' 21,000 23,000

3 X 1 1/2 mm2 m' 12,500 14,000

3 X 2 1/2 mm2 m' 19,000 22,000

3X4 mm2 m' 30,000 35,000

3X6 mm2 m' 43,000 48,000

2 SKAKELAR
Out bauw . Seri bh 15,000 21,000

. Engkel bh 12,000 15,000

In bauw . Seri bh 11,500 16,500

. Engkel bh 9,500 12,000

3 FUSE BOX (SEKERING KASA)


1 group bh 115,000 135,000

2 group bh 220,000 245,000

3 group bh 325,000 360,000

4 STEKER - Biasa bh 10,000 12,000

Arde bh 15,000 16,000

T Biasa bh 12,500 13,000

T dengan Arde bh 17,000 17,500


HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
5 FITING Flaon bh 7,500 11,000

Gantung bh 10,000 20,000

Kap bh 5,000 17,500

Kombinasi bh 275,000 350,000

6 STOP KONTAK - Arde Outbow putih bh 12,500 15,000

Arde Outbow hitam bh 5,000 6,000

Arde IB bh 10,000 15,000

Arde Putar bh 31,000 42,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 55,000 60,000
2 X slag bh 65,000 70,000
Yale : 1 X slag bh 85,000 95,000
2 X slag bh 140,000 155,000
Kuda : 1 X slag bh 55,000 60,000
2 X slag bh 70,000 75,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 15,000 16,000
Kupu-kupu biasa bh 4,000 4,500
Nylon kupu-kupu bh 6,000 9,000
Espagnoled - dalam negeri bh 30,000 50,000
Grendel Tanam luar negeri bh 7,500 11,000
Grendel biasa bh 10,000 20,000
Kait Angin bh 5,000 17,500
Door Stop bh 275,000 350,000

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,450,000 1,850,000
2 KLOSET JONGKOK bh 130,000 150,000
3 WASTAFEL PEDESTAL bh 850,000 1,050,000
4 WASTAFEL MEJA OVAL bh 700,000 950,000
5 WASTAFEL GANTUNG BULAT bh 275,000 450,000
6 WASTAFEL GANTUNG SUDUT bh 240,000 310,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 230,000 275,000
8 WASTAFEL BAK CUCI bh 145,000 165,000
9 TEMPAT SABUN GANTUNG bh 30,000 35,000
10 TEMPAT SABUN TANAM bh 20,000 25,000

11 SEPTIC TANK (ETERNIT GRESIK)


5 Pemakai 500 liter unit
10 Pemakai 1.000 liter unit - -
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
12 LAIN - LAIN
Kran Air bh 35,000 45,000
Seal tape bh 2,000 4,100
Floor drain bh 15,000 35,000

XIV . ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4" kg 14,000 18,000
2 PAKU - payung kg 20,000 30,000
3 PAKU - sekrup kg 6,000 8,000
4 PAKU - beton kg 25,000 30,000
5 MUR BAUT (kuda-kuda) kg 13,000 14,000
6 ANGKUR BAUT bh 13,000 13,500
7 LEM KAYU bh 12,500 20,000
8 Tali Ijuk kg 7,000 7,200

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 275,000 310,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,050,000
Fuji 250 watt bh 1,450,000 1,500,000
Shimizu . 100 watt bh 450,000 510,000
. 90 watt bh 350,000 380,000
Dab . 125 watt bh 375,000 400,000
. 175 watt bh 425,000 450,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 75,000 80,000
Merah/hitam m2 85,000 90,000
2 HOLLAND Abu-abu m2 75,000 80,000
Merah/hitam m2 85,000 90,000
3 UNIDECOR Abu-abu m2 42,000 75,000
Merah/hitam m2 85,000 90,000
4 UNI Abu-abu m2 75,000 80,000
Merah/hitam m2 85,000 90,000
5 TRIHEX Abu-abu m2 75,000 80,000
Merah/hitam m2 85,000 90,000
6 OLYMPIA HEXA Abu-abu m2 75,000 80,000
7 HEXAGONAL Abu-abu m2 85,000 90,000
Merah/hitam m2 75,000 80,000
8 CASTLE Abu-abu m2 85,000 90,000
9 TRAPEZ Abu-abu m2 75,000 80,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 75,000 80,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500 8,500
12 BATACO BH 3,000 3,500
13 KANSTEEN m' 15,000 27,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000 50,000
2 Sliding Pintu J4 bh 180,000 235,000
3 Naco per Daun bh 32,500 35,000
4 Rolling door Besi m2 300,000 325,000
Rolling door Almunium m2 230,000 275,000
5 Awning Almunium m2 210,000 225,000
6 Kusen Almunium 4" Putih m' 80,000 85,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,100,000 1,250,000

8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 950,000 1,050,000

Hotmix Tebal = 4 Cm m2 65,000 67,500


Hotmix Tebal = 5 Cm m2 80,000 82,000
Hotmix Tebal = 6 Cm m2 95,000 97,000
Hotmix Tebal = 7 Cm m2 110,000 115,000
Binder Course ton 1,300,000 1,325,000
Wearing Course ton 1,300,000 1,400,000
Hot Roller Sheet ton 1,150,000 1,250,000
Sand Sheet ton 1,100,000 1,250,000
Sand Sheet Emulsi ton 1,450,000 1,500,000
Cold Mix ton 1,750,000 1,850,000
Prime / Tack Coard RC liter 7,200 8,000
Prime Coat MC liter 7,200 8,000
Prime / Tack Coat Emulsi liter 7,200 8,000
10 K A C A
Cermin tebal 5 mm m2 225,000 275,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 175,000 200,000


Pagar BRC 120 A2 /lb 225,000 250,000
12 LAIN-LAIN
Minyak Beton & bekisting ltr 9,000 10,000
Pintu Lipat Besi m2 380,000 425,000
Sunscreen Allumunim m2 310,000 350,000
Allumunium Foil m2 7,500 8,000
Soda api kg 12,000 15,000
Sabun kg 11,000 13,000
Air m3 15,000 20,000
Koas Alang-alang ikat 1,250 2,000
Solar (Industri) ltr 7,000 7,200
Premium (Industri) ltr 6,200 6,800
Pelumas ltr 37,500 45,000
Vynil 30x30 cm bh 6,200 6,500
DAFTAR HARGA SATUAN PEKERJAAN (AHSP) NO.28/PRT/M/2016
BIDANG CIPTA KARYA
SUMBER DATA : PASARAN B E BAS
D A E R A H : KOTA SEMARANG & SEKITAR
EDISI SEPTEMBER 2017

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
I A. 2.2.1 K.3 HARGA SATUAN PEKERJAAN PERSIAPAN
Pagar Sementara dari Seng Gelombang Tinggi
A.2.2.1.2 1 m' 591,802.75 679,679.00
1 2,00 m
A TENAGA 48,500.00 57,100.00
L.01 0.2 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.4 OH Tukang Kayu 80,000.00 95,000.00 32,000.00 38,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.02 OH Mandor 85,000.00 95,000.00 1,700.00 1,900.00
B BAHAN 489,502.50 560,790.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
2.5 Kg Portalnd Semen 1,025.00 1,100.00 2,562.50 2,750.00
1.2 Lbr Seng Gelombang 3" - 5" 42,000.00 55,000.00 50,400.00 66,000.00
0.005 m3 Pasir Beton 350,000.00 500,000.00 1,750.00 2,500.00
0.009 m3 Koral Beton 300,000.00 390,000.00 2,700.00 3,510.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 5,500,000.00 6,100,000.00 396,000.00 439,200.00
0.06 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 840.00 1,080.00
0.45 Kg Meni Besi 20,000.00 35,000.00 9,000.00 15,750.00
C PERALATAN
D Jumlah A + B + C 538,002.50 617,890.00
E Overhead & Profit (contah 10%) 10% 53,800.25 61,789.00
F Harga Satuan Pekerjaan (D+E) 591,802.75 679,679.00
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 138,440.50 155,248.50
A Tenaga 15,825.00 18,575.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.1 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 110,030.00 122,560.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 5,500,000.00 6,100,000.00 66,000.00 73,200.00
0.02 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 280.00 360.00
0.007 m3 Kayu Papan 3/20 Kruing 6,250,000.00 7,000,000.00 43,750.00 49,000.00
C PERALATAN
D Jumlah A + B + C 125,855.00 141,135.00
E Overhead & Profit (contah 10%) 10% 12,585.50 14,113.50
F Harga Satuan Pekerjaan (D+E) 138,440.50 155,248.50

3 A.2.2.1.5 K.3 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran 1,808,262.50 2,074,242.50

A Tenaga 401,250.00 472,750.00


L.01 2 OH Pekerja 65,000.00 75,000.00 130,000.00 150,000.00
L.02 2 OH Tukang Kayu 80,000.00 95,000.00 160,000.00 190,000.00
L.02 1 OH Tukang Batu 80,000.00 95,000.00 80,000.00 95,000.00
L.03 0.3 OH Kepala Tukang 90,000.00 110,000.00 27,000.00 33,000.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan 1,242,625.00 1,412,925.00
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 26,250.00 30,000.00
0.18 m3 Kayu 5,500,000.00 6,100,000.00 990,000.00 1,098,000.00
0.80 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 11,200.00 14,400.00
1.1 Kg Besi Strip 13,500.00 14,000.00 14,850.00 15,400.00
35 Kg Portland Sement 1,025.00 1,100.00 35,875.00 38,500.00
0.15 m3 Pasir pasang 250,000.00 370,000.00 37,500.00 55,500.00
0.1 m3 Pasir Beton 350,000.00 500,000.00 35,000.00 50,000.00
0.15 m3 Koral Beton 300,000.00 390,000.00 45,000.00 58,500.00
30 buah Batu bata Merah 550.00 600.00 16,500.00 18,000.00
0.25 Lbr Seng Plat 20,000.00 24,500.00 5,000.00 6,125.00
0.20 buah Jendela Naco 32,500.00 35,000.00 6,500.00 7,000.00
0.08 m2 Kaca Polos 70,000.00 85,000.00 5,600.00 6,800.00
0.15 buah Kunci Tanam 65,000.00 70,000.00 9,750.00 10,500.00
0.06 Lbr Plywood 4 mm 60,000.00 70,000.00 3,600.00 4,200.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 1,643,875.00 1,885,675.00
E Overhead & Profit (contah 10%) 10% 164,387.50 188,567.50
F Harga Satuan Pekerjaan (D+E) 1,808,262.50 2,074,242.50

4 A.2.2.1.6 K.3 1 m2 Pembuatan Rumah Jaga (Konstruksi Kayu) 1,462,945.00 1,656,215.00


A Tenaga 202,750.00 238,750.00
L.01 1 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 1.50 OH Tukang Kayu 80,000.00 95,000.00 120,000.00 142,500.00
L.03 0.15 OH Kepala Tukang 90,000.00 110,000.00 13,500.00 16,500.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan 1,127,200.00 1,266,900.00
3.00 Btg Kayu Dolken Ø 8 - 10 / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
0.18 m3 Kayu 5,500,000.00 6,100,000.00 990,000.00 1,098,000.00
0.80 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 11,200.00 14,400.00
1.50 Lbr Seng Gelombang 42,000.00 55,000.00 63,000.00 82,500.00
C PERALATAN
D Jumlah A + B + C 1,329,950.00 1,505,650.00
E Overhead & Profit (contah 10%) 10% 132,995.00 150,565.00
F Harga Satuan Pekerjaan (D+E) 1,462,945.00 1,656,215.00

5. A.2.2.1.7 K.3 1 m2 Pembuatan Gudang Semen dan Peralatan 1,429,078.75 1,608,062.50


A Tenaga 247,250.00 291,750.00
L.01 1 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 2 OH Tukang Kayu 80,000.00 95,000.00 160,000.00 190,000.00
L.03 0.2 OH Kepala Tukang 90,000.00 110,000.00 18,000.00 22,000.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan 1,294,162.50 1,455,750.00
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 35,700.00 40,800.00
0.21 m3 Kayu 5,500,000.00 6,100,000.00 1,155,000.00 1,281,000.00
0.3 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 4,200.00 5,400.00
10.5 Kg Portland Semen 1,025.00 1,100.00 10,762.50 11,550.00
0.03 m3 Pasir Beton 350,000.00 500,000.00 10,500.00 15,000.00
0.05 m3 Koral Beton 300,000.00 390,000.00 15,000.00 19,500.00
1.5 Lbr Seng Gelombang 42,000.00 55,000.00 63,000.00 82,500.00
0.25 Lbr Seng Plat 20,000.00 24,500.00 5,000.00 6,125.00
C PERALATAN
D Jumlah A + B + C 1,299,162.50 1,461,875.00
E Overhead & Profit (contah 10%) 10% 129,916.25 146,187.50
F Harga Satuan Pekerjaan (D+E) 1,429,078.75 1,608,062.50

6. A.2.2.1.8 K.3 1 m2 Pembuatan Bedeng Pekerja 1,659,790.00 1,899,480.00


A Tenaga 247,250.00 291,750.00
L.01 1 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 2 OH Tukang Kayu 80,000.00 95,000.00 160,000.00 190,000.00
L.03 0.2 OH Kepala Tukang 90,000.00 110,000.00 18,000.00 22,000.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan 1,261,650.00 1,435,050.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 21,000.00 24,000.00 26,250.00 30,000.00
0.186 m3 Kayu 5,500,000.00 6,100,000.00 1,023,000.00 1,134,600.00
0.30 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 4,200.00 5,400.00
18.00 Kg Portland Semen 1,025.00 1,100.00 18,450.00 19,800.00
0.03 m3 Pasir Beton 350,000.00 500,000.00 10,500.00 15,000.00
0.05 m3 Koral Beton 300,000.00 390,000.00 15,000.00 19,500.00
1.50 Lbr Seng Gelombang 42,000.00 55,000.00 63,000.00 82,500.00
1.35 Lbr Playwood 75,000.00 95,000.00 101,250.00 128,250.00
C PERALATAN
D Jumlah A + B + C 1,508,900.00 1,726,800.00
E Overhead & Profit (contah 10%) 10% 150,890.00 172,680.00
F Harga Satuan Pekerjaan (D+E) 1,659,790.00 1,899,480.00

7. A.2.2.1.9 K.3 1 m2 Membersihkan Lapangan dan Perataan 11,825.00 13,475.00


A Tenaga 10,750.00 12,250.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 10,750.00 12,250.00
E Overhead & Profit (contah 10%) 10% 1,075.00 1,225.00
F Harga Satuan Pekerjaan (D+E) 11,825.00 13,475.00

8 A.2.2.1.10 K.3 1 m2 Pembuatan Steger/Perancah dari Bambu 288,532.20 338,898.12


A Tenaga 247,250.00 291,750.00
L.01 1.00 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 2.00 OH Tukang Kayu 80,000.00 95,000.00 160,000.00 190,000.00
L.03 0.20 OH Kepala Tukang 90,000.00 110,000.00 18,000.00 22,000.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan 15,052.00 16,339.20
1.250 Btg Bambu diameter 6 - 8 / 600 cm 11,000.00 12,000.00 13,750.00 15,000.00
0.186 Kg Tali Ijuk 7,000.00 7,200.00 1,302.00 1,339.20
C PERALATAN
D Jumlah A + B + C 262,302.00 308,089.20
E Overhead & Profit (contah 10%) 10% 26,230.20 30,808.92
F Harga Satuan Pekerjaan (D+E) 288,532.20 338,898.12

Pembuatan Kotak Adukan ukuran


9 A.2.2.1.11 1 bh 495,902.00 555,324.00
40cmx50cmx25cm
A Tenaga 26,700.00 31,800.00
L.02 0.30 OH Tukang Kayu 80,000.00 95,000.00 24,000.00 28,500.00
L.03 0.03 OH Kepala Tukang 90,000.00 110,000.00 2,700.00 3,300.00
B Bahan 424,120.00 473,040.00
0.036 m3 Kayu Papan Kelas III 6,250,000.00 7,000,000.00 225,000.00 252,000.00
0.036 m3 Kayu Balok Kelas III 5,500,000.00 6,100,000.00 198,000.00 219,600.00
0.080 kg Paku Biasa 14,000.00 18,000.00 1,120.00 1,440.00
C PERALATAN
D Jumlah A + B + C 450,820.00 504,840.00
E Overhead & Profit (contah 10%) 10% 45,082.00 50,484.00
F Harga Satuan Pekerjaan (D+E) 495,902.00 555,324.00

10 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang 1,015,652.00 1,169,652.00


A Tenaga 923,320.00 1,063,320.00
L.02 13.334 OH Pekerja 65,000.00 75,000.00 866,710.00 1,000,050.00
L.04 0.666 OH Mandor 85,000.00 95,000.00 56,610.00 63,270.00
B Bahan
C PERALATAN
D Jumlah A + B + C 923,320.00 1,063,320.00
E Overhead & Profit (contah 10%) 10% 92,332.00 106,332.00
F Harga Satuan Pekerjaan (D+E) 1,015,652.00 1,169,652.00

11 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah 479,776.00 553,476.00


B Tenaga 436,160.00 503,160.00
L.02 6.667 OH Pekerja 65,000.00 75,000.00 433,355.00 500,025.00
L.04 0.033 OH Mandor 85,000.00 95,000.00 2,805.00 3,135.00
B Bahan
C PERALATAN
D Jumlah A + B + C 436,160.00 503,160.00
E Overhead & Profit (contah 10%) 10% 43,616.00 50,316.00
F Harga Satuan Pekerjaan (D+E) 479,776.00 553,476.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 55,962.50 64,487.50


A TENAGA 50,875.00 58,625.00
L.01 0.75 OH Pekerja 65,000.00 75,000.00 48,750.00 56,250.00
L.04 0.025 OH Mandor 85,000.00 95,000.00 2,125.00 2,375.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 50,875.00 58,625.00
E Overhead & Profit (contah 10%) 10% 5,087.50 5,862.50
F Harga Satuan Pekerjaan (D+E) 55,962.50 64,487.50
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m 68,557.50 78,952.50
A TENAGA 62,325.00 71,775.00
L.01 0.90 OH Pekerja 65,000.00 75,000.00 58,500.00 67,500.00
L.04 0.045 OH Mandor 85,000.00 95,000.00 3,825.00 4,275.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 62,325.00 71,775.00
E Overhead & Profit (contah 10%) 10% 6,232.50 7,177.50
F Harga Satuan Pekerjaan (D+E) 68,557.50 78,952.50

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m 81,339.50 93,626.50


A TENAGA 73,945.00 85,115.00
L.01 1.05 OH Pekerja 65,000.00 75,000.00 68,250.00 78,750.00
L.04 0.067 OH Mandor 85,000.00 95,000.00 5,695.00 6,365.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 73,945.00 85,115.00
E Overhead & Profit (contah 10%) 10% 7,394.50 8,511.50
F Harga Satuan Pekerjaan (D+E) 81,339.50 93,626.50

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m 74,492.00 85,844.00


TENAGA 67,720.00 78,040.00
L.01 1.000 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.04 0.032 OH Mandor 85,000.00 95,000.00 2,720.00 3,040.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 67,720.00 78,040.00
E Overhead & Profit (contah 10%) 10% 6,772.00 7,804.00
F Harga Satuan Pekerjaan (D+E) 74,492.00 85,844.00

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m 112,860.00 130,020.00


A TENAGA 102,600.00 118,200.00
L.01 1.50 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.04 0.060 OH Mandor 85,000.00 95,000.00 5,100.00 5,700.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 102,600.00 118,200.00
E Overhead & Profit (contah 10%) 10% 10,260.00 11,820.00
F Harga Satuan Pekerjaan (D+E) 112,860.00 130,020.00

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m 90,007.50 103,702.50


A TENAGA 81,825.00 94,275.00
L.01 1.200 OH Pekerja 65,000.00 75,000.00 78,000.00 90,000.00
L.04 0.045 OH Mandor 85,000.00 95,000.00 3,825.00 4,275.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 81,825.00 94,275.00
E Overhead & Profit (contah 10%) 10% 8,182.50 9,427.50
F Harga Satuan Pekerjaan (D+E) 90,007.50 103,702.50

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m 4,042.50 4,647.50


A TENAGA 3,675.00 4,225.00
L.01 0.05 OH Pekerja 65,000.00 75,000.00 3,250.00 3,750.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 3,675.00 4,225.00
E Overhead & Profit (contah 10%) 10% 367.50 422.50
F Harga Satuan Pekerjaan (D+E) 4,042.50 4,647.50

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m' 24,530.00 28,270.00


A TENAGA 22,300.00 25,700.00
L.01 0.330 OH Pekerja 65,000.00 75,000.00 21,450.00 24,750.00
L.04 0.010 OH Mandor 85,000.00 95,000.00 850.00 950.00

file:///conversion/tmp/scratch/457687078.xls 130/64 abk 2-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 22,300.00 25,700.00
E Overhead & Profit (contah 10%) 10% 2,230.00 2,570.00
F Harga Satuan Pekerjaan (D+E) 24,530.00 28,270.00

Pengurugan Kembali di hitung dari 1/3 kali koefisien


9 A.2.3.1.9 1 m3 13,475.00 15,491.67
Pekerjaan galian
A TENAGA 36,750.00 42,250.00
L.01 0.50 OH Pekerja 65,000.00 75,000.00 32,500.00 37,500.00
L.04 0.050 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 36,750.00 42,250.00
E Overhead & Profit (contah 10%) 10% 3,675.00 4,225.00
F Harga Satuan Pekerjaan (D+E) 40,425.00 46,475.00

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm) 40,425.00 46,475.00


A TENAGA 36,750.00 42,250.00
L.01 0.5 OH Pekerja 65,000.00 75,000.00 32,500.00 37,500.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 36,750.00 42,250.00
E Overhead & Profit (contah 10%) 10% 3,675.00 4,225.00
F Harga Satuan Pekerjaan (D+E) 40,425.00 46,475.00

11 A.2.3.1.11 1 m3 Urugan Pasir 233,585.00 329,395.00


A TENAGA 20,350.00 23,450.00
L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.04 0.01 OH Mandor 85,000.00 95,000.00 850.00 950.00
B BAHAN 192,000.00 276,000.00
1.2 m3 Pasir Urug 160,000.00 230,000.00 192,000.00 276,000.00
C PERALATAN
D Jumlah A + B + C 212,350.00 299,450.00
E Overhead & Profit (contah 10%) 10% 21,235.00 29,945.00
F Harga Satuan Pekerjaan (D+E) 233,585.00 329,395.00

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 387,673.00 456,137.00


A TENAGA 94,400.00 108,000.00
L.01 0.800 OH Pekerja 65,000.00 75,000.00 52,000.00 60,000.00
L.02 0.400 OH Tukang Batu 80,000.00 90,000.00 32,000.00 36,000.00
L.03 0.04 OH Kepala Tukang 90,000.00 110,000.00 3,600.00 4,400.00
L.04 0.080 OH Mandor 85,000.00 95,000.00 6,800.00 7,600.00
B BAHAN 258,030.00 306,670.00
0.135 m3 Pasir Pasang 250,000.00 370,000.00 33,750.00 49,950.00
0.400 m3 Kapur Padam 300,000.00 310,000.00 120,000.00 124,000.00
0.948 m3 Tanah Liat 110,000.00 140,000.00 104,280.00 132,720.00
C PERALATAN
D Jumlah A + B + C 352,430.00 414,670.00
E Overhead & Profit (contah 10%) 10% 35,243.00 41,467.00
F Harga Satuan Pekerjaan (D+E) 387,673.00 456,137.00

Pemasangan Lapisan Ijuk tebal 10 cm untuk Bidang


13 A.2.3.1.13 1 m2 58,327.50 61,462.50
Resapan
A TENAGA 11,025.00 12,675.00
0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B BAHAN 42,000.00 43,200.00
6.00 kg Ijuk 7,000.00 7,200.00 42,000.00 43,200.00
C PERALATAN
D Jumlah A + B + C 53,025.00 55,875.00
E Overhead & Profit (contah 10%) 10% 5,302.50 5,587.50
F Harga Satuan Pekerjaan (D+E) 58,327.50 61,462.50

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat 257,812.50 287,237.50


A TENAGA 18,375.00 21,125.00
0.25 OH Pekerja 65,000.00 75,000.00 16,250.00 18,750.00
0.025 OH Mandor 85,000.00 95,000.00 2,125.00 2,375.00
B BAHAN 216,000.00 240,000.00
1.2 m3 Sirtu 180,000.00 200,000.00 216,000.00 240,000.00
C PERALATAN
D Jumlah A + B + C 234,375.00 261,125.00
E Overhead & Profit (contah 10%) 10% 23,437.50 26,112.50
F Harga Satuan Pekerjaan (D+E) 257,812.50 287,237.50

file:///conversion/tmp/scratch/457687078.xls 130/65 abk 2-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 878,817.50 1,052,727.50
A TENAGA 170,625.00 195,375.00
L.01 1.5 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.02 0.750 OH Tukang Batu 80,000.00 90,000.00 60,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B BAHAN 628,300.00 761,650.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
202 Kg Portland Sement 1,025.00 1,100.00 207,050.00 222,200.00
0.485 m3 Pasir Pasang 250,000.00 370,000.00 121,250.00 179,450.00
C PERALATAN
D Jumlah A + B + C 798,925.00 957,025.00
E Overhead & Profit (contoh 10%) 10% 79,892.50 95,702.50
F Harga Satuan Pekerjaan (D+E) 878,817.50 1,052,727.50
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 844,470.00 1,019,782.50
A TENAGA 170,625.00 195,375.00
L.01 1.5 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.02 0.750 OH Tukang Batu 80,000.00 90,000.00 60,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B BAHAN 597,075.00 731,700.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
163 Kg Portland Sement 1,025.00 1,100.00 167,075.00 179,300.00
0.52 m3 Pasir Pasang 250,000.00 370,000.00 130,000.00 192,400.00
C PERALATAN
D Jumlah A + B + C 767,700.00 927,075.00
E Overhead & Profit (contoh 10%) 10% 76,770.00 92,707.50
F Harga Satuan Pekerjaan (D+E) 844,470.00 1,019,782.50

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 820,627.50 996,880.50


A TENAGA 170,625.00 195,375.00
L.01 1.5 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.02 0.750 OH Tukang Batu 80,000.00 90,000.00 60,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B BAHAN 575,400.00 710,880.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
136 Kg Portland Sement 1,025.00 1,100.00 139,400.00 149,600.00
0.544 m3 Pasir Pasang 250,000.00 370,000.00 136,000.00 201,280.00
C PERALATAN
D Jumlah A + B + C 746,025.00 906,255.00
E Overhead & Profit (contoh 10%) 10% 74,602.50 90,625.50
F Harga Satuan Pekerjaan (D+E) 820,627.50 996,880.50

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 803,880.00 980,809.50


A TENAGA 170,625.00 195,375.00
L.01 1.5 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.02 0.750 OH Tukang Batu 80,000.00 90,000.00 60,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B BAHAN 560,175.00 696,270.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
117 Kg Portland Sement 1,025.00 1,100.00 119,925.00 128,700.00
0.561 m3 Pasir Pasang 250,000.00 370,000.00 140,250.00 207,570.00
C PERALATAN
D Jumlah A + B + C 730,800.00 891,645.00
E Overhead & Profit (contoh 10%) 10% 73,080.00 89,164.50
F Harga Satuan Pekerjaan (D+E) 803,880.00 980,809.50

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 780,890.00 958,710.50


A Tenaga 170,625.00 195,375.00
L.01 1.5 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.02 0.750 OH Tukang Batu 80,000.00 90,000.00 60,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B Bahan 539,275.00 676,180.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
91 Kg Portland Sement 1,025.00 1,100.00 93,275.00 100,100.00
0.584 m3 Pasir Pasang 250,000.00 370,000.00 146,000.00 216,080.00

file:///conversion/tmp/scratch/457687078.xls 130/66 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 709,900.00 871,555.00
E Overhead & Profit (contoh 10%) 10% 70,990.00 87,155.50
F Harga Satuan Pekerjaan (D+E) 780,890.00 958,710.50

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 701,882.50 844,662.50
A Tenaga 170,625.00 195,375.00
L.01 1.5 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.02 0.750 OH Tukang Batu 80,000.00 90,000.00 60,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B Bahan 467,450.00 572,500.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
0.17 m3 Kapur Pasang (KP) 300,000.00 310,000.00 51,000.00 52,700.00
0.17 Kg Semen Merah (SM) 185,000.00 200,000.00 31,450.00 34,000.00
0.340 m3 Pasir Pasang 250,000.00 370,000.00 85,000.00 125,800.00
C PERALATAN
D Jumlah A + B + C 638,075.00 767,875.00
E Overhead & Profit (contoh 10%) 10% 63,807.50 76,787.50
F Harga Satuan Pekerjaan (D+E) 701,882.50 844,662.50

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 770,275.00 935,093.50


A Tenaga 170,625.00 195,375.00
L.01 1.5 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.02 0.750 OH Tukang Batu 80,000.00 90,000.00 60,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B Bahan 529,625.00 654,710.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
61 kg Portland Sement 1,025.00 1,100.00 62,525.00 67,100.00
0.147 m3 Kapur Pasang 300,000.00 310,000.00 44,100.00 45,570.00
0.492 m3 Pasir Pasang 250,000.00 370,000.00 123,000.00 182,040.00
C PERALATAN
D Jumlah A + B + C 700,250.00 850,085.00
E Overhead & Profit (contoh 10%) 10% 70,025.00 85,008.50
F Harga Satuan Pekerjaan (D+E) 770,275.00 935,093.50

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP 750,970.00 918,054.50


A Tenaga 170,625.00 195,375.00
L.01 1.5 OH Pekerja 65,000.00 75,000.00 97,500.00 112,500.00
L.02 0.750 OH Tukang Batu 80,000.00 90,000.00 60,000.00 67,500.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B Bahan 512,075.00 639,220.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
41 kg Portland Sement 1,025.00 1,100.00 42,025.00 45,100.00
0.131 m3 Kapur Pasang 300,000.00 310,000.00 39,300.00 40,610.00
0.523 m3 Pasir 250,000.00 370,000.00 130,750.00 193,510.00
C PERALATAN
D Jumlah A + B + C 682,700.00 834,595.00
E Overhead & Profit (contoh 10%) 10% 68,270.00 83,459.50
F Harga Satuan Pekerjaan (D+E) 750,970.00 918,054.50

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping 503,629.50 617,050.50


A Tenaga 88,725.00 101,595.00
L.01 0.78 OH Pekerja 65,000.00 75,000.00 50,700.00 58,500.00
L.02 0.39 OH Tukang Batu 80,000.00 90,000.00 31,200.00 35,100.00
L.03 0.039 OH Kepala Tukang 90,000.00 110,000.00 3,510.00 4,290.00
L.04 0.039 OH Mandor 85,000.00 95,000.00 3,315.00 3,705.00
B Bahan 369,120.00 459,360.00
1.2 m3 Batu Belah 15/20 250,000.00 300,000.00 300,000.00 360,000.00
0.432 m3 Pasir Urug 160,000.00 230,000.00 69,120.00 99,360.00
C PERALATAN
D Jumlah A + B + C 457,845.00 560,955.00
E Overhead & Profit (contoh 10%) 10% 45,784.50 56,095.50
F Harga Satuan Pekerjaan (D+E) 503,629.50 617,050.50

file:///conversion/tmp/scratch/457687078.xls 130/67 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pasang Pondasi Siklop, 60% Beton Campuran 1PC : 2PB :
10 A.3.2.1.10 1 m3 2,417,767.00 2,687,058.00
3KR & 40% Batu B0elah
A Tenaga 309,400.00 355,100.00
L.01 3.4 OH Pekerja 65,000.00 75,000.00 221,000.00 255,000.00
L.02 0.85 OH Tukang Batu 80,000.00 90,000.00 68,000.00 76,500.00
L.03 0.085 OH Kepala Tukang 90,000.00 110,000.00 7,650.00 9,350.00
L.04 0.15 OH Mandor 85,000.00 95,000.00 12,750.00 14,250.00
B Bahan 1,888,570.00 2,087,680.00
0.480 m3 Batu Belah 15/20 cm 250,000.00 300,000.00 120,000.00 144,000.00
126 Kg Besi Beton 10,500.00 11,300.00 1,323,000.00 1,423,800.00
194 Kg Portland Semen 1,025.00 1,100.00 198,850.00 213,400.00
0.312 m3 Pasir Beton 350,000.00 500,000.00 109,200.00 156,000.00
0.468 m3 Koral Beton 240,000.00 260,000.00 112,320.00 121,680.00
1.8 Kg Kawat Beton 14,000.00 16,000.00 25,200.00 28,800.00
C PERALATAN
D Jumlah A + B + C 2,197,970.00 2,442,780.00
E Overhead & Profit (contoh 10%) 10% 219,797.00 244,278.00
F Harga Satuan Pekerjaan (D+E) 2,417,767.00 2,687,058.00

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm 847,203.50 988,003.50


A Tenaga 237,315.00 272,105.00
L.01 2.40 OH Pekerja 65,000.00 75,000.00 156,000.00 180,000.00
L.02 0.8 OH Tukang Batu 80,000.00 90,000.00 64,000.00 72,000.00
L.03 0.08 OH Kepala Tukang 90,000.00 110,000.00 7,200.00 8,800.00
L.04 0.119 OH Mandor 85,000.00 95,000.00 10,115.00 11,305.00
B Bahan 532,870.00 626,080.00
0.45 m3 Batu Belah 15/20 cm 250,000.00 300,000.00 112,500.00 135,000.00
194 Kg Portland Semen 1,025.00 1,100.00 198,850.00 213,400.00
0.312 m3 Pasir Beton 350,000.00 500,000.00 109,200.00 156,000.00
0.468 m3 Koral Beton 240,000.00 260,000.00 112,320.00 121,680.00
C PERALATAN
D Jumlah A + B + C 770,185.00 898,185.00
E Overhead & Profit (contoh 10%) 10% 77,018.50 89,818.50
F Harga Satuan Pekerjaan (D+E) 847,203.50 988,003.50

file:///conversion/tmp/scratch/457687078.xls 130/68 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV A.4.1.1 HARGA SATUAN PEKERJAAN BETON

Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c


1 A.4.1.1.1 1 m3 917,922.50 1,137,864.36
= 0,87
A Tenaga 138,825.00 159,465.00
L.01 1.65 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
B Bahan 695,650.00 874,957.14
247 Kg Portland Semen 1,025.00 1,100.00 253,175.00 271,700.00
869 Kg Pasir Beton 250.00 357.14 217,250.00 310,357.14
999 Kg Kerikil (maksimum 30 mm) 222.22 288.89 222,000.00 288,600.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 834,475.00 1,034,422.14
E Overhead & Profit (contoh 10%) 10% 83,447.50 103,442.21
F Harga Satuan Pekerjaan (D+E) 917,922.50 1,137,864.36
10%
Overhead & Profit (contoh 10%)
Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c
2 A.4.1.1.2 1 m3 942,522.78 1,160,978.33
= 0,78
A Tenaga 138,825.00 159,465.00
L.01 1.650 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
B Bahan 718,013.89 895,969.84
276 Kg Portland Semen 1,025.00 1,100.00 282,900.00 303,600.00
828 kg Pasir Beton 250.00 357.14 207,000.00 295,714.29
1,012 kg Kerikil (maksimum 30 mm) 222.22 288.89 224,888.89 292,355.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 856,838.89 1,055,434.84
E Overhead & Profit (contoh 10%) 10% 85,683.89 105,543.48
F Harga Satuan Pekerjaan (D+E) 942,522.78 1,160,978.33

Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm,


3 A.4.1.1.3 1 m3 961,702.50 1,179,004.36
w/c = 0,72
A Tenaga 138,825.00 159,465.00
L.01 1.650 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
B Bahan 735,450.00 912,357.14
299 Kg Portland Semen 1,025.00 1,100.00 306,475.00 328,900.00
799 kg Pasir Beton 250.00 357.14 199,750.00 285,357.14
1,017 kg Kerikil (maksimum 30 mm) 222.22 288.89 226,000.00 293,800.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 874,275.00 1,071,822.14
E Overhead & Profit (contoh 10%) 10% 87,427.50 107,182.21
F Harga Satuan Pekerjaan (D+E) 961,702.50 1,179,004.36

Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum


4 A.4.1.1.4 1.00 m3 865,185.44 1,081,726.21
(3-6)cm, w/c = 0,87
A Tenaga 96,310.00 110,770.00
L.01 1.200 OH Pekerja 65,000.00 75,000.00 78,000.00 90,000.00
L.02 0.200 OH Tukang Batu 80,000.00 90,000.00 16,000.00 18,000.00
L.03 0.020 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 690,222.22 872,617.46
230 Kg Portland Semen 1,025.00 1,100.00 235,750.00 253,000.00
893 kg Pasir Beton 250.00 357.14 223,250.00 318,928.57
1,027 kg Kerikil (maksimum 30 mm) 222.22 288.89 228,222.22 296,688.89
200 ltr Air 15.00 20.00 3,000.00 4,000.00
C PERALATAN
D Jumlah A + B + C 786,532.22 983,387.46
E Overhead & Profit (contoh 10%) 10% 78,653.22 98,338.75
F Harga Satuan Pekerjaan (D+E) 865,185.44 1,081,726.21

Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm,


5 A.4.1.1.5 1 m3 984,353.33 1,200,166.26
w/c = 0,66
A Tenaga 138,825.00 159,465.00
L.01 1.65 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00

file:///conversion/tmp/scratch/457687078.xls 130/69 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 756,041.67 931,595.24
326 Kg Portland Semen 1,025.00 1,100.00 334,150.00 358,600.00
760 Kg Pasir Beton 250.00 357.14 190,000.00 271,428.57
1,029 Kg Kerikil (maksimum 30 mm) 222.22 288.89 228,666.67 297,266.67
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 894,866.67 1,091,060.24
E Overhead & Profit (contoh 10%) 10% 89,486.67 109,106.02
F Harga Satuan Pekerjaan (D+E) 984,353.33 1,200,166.26

Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm,


6 A.4.1.1.6 1 m3 1,006,182.22 1,220,868.96
w/c = 0,61
A Tenaga 138,825.00 159,465.00
L.01 1.650 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
B Bahan 775,886.11 950,415.87
352 Kg Portland Semen 1,025.00 1,100.00 360,800.00 387,200.00
731 Kg Pasir Beton 250.00 357.14 182,750.00 261,071.43
1,031 Kg Kerikil (maksimum 30 mm) 222.22 288.89 229,111.11 297,844.44
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 914,711.11 1,109,880.87
E Overhead & Profit (contoh 10%) 10% 91,471.11 110,988.09
F Harga Satuan Pekerjaan (D+E) 1,006,182.22 1,220,868.96

Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm,


7 A.4.1.1.7 1 m3 1,022,440.83 1,235,979.12
w/c = 0,58
A Tenaga 138,825.00 159,465.00
L.01 1.650 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
B Bahan 790,666.67 964,152.38
371 Kg Portland Semen 1,025.00 1,100.00 380,275.00 408,100.00
698 Kg Pasir Beton 250.00 357.14 174,500.00 249,285.71
1,047 Kg Kerikil (maksimum 30 mm) 222.22 288.89 232,666.67 302,466.67
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 929,491.67 1,123,617.38
E Overhead & Profit (contoh 10%) 10% 92,949.17 112,361.74
F Harga Satuan Pekerjaan (D+E) 1,022,440.83 1,235,979.12

Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm,


8 A.4.1.1.8 1 m3 1,033,492.78 1,246,809.75
w/c = 0,56
A Tenaga 138,825.00 159,465.00
L.01 1.650 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
B Bahan 800,713.89 973,998.41
384 Kg Portland Semen 1,025.00 1,100.00 393,600.00 422,400.00
692 Kg Pasir Beton 250.00 357.14 173,000.00 247,142.86
1,039 Kg Kerikil (maksimum 30 mm) 222.22 288.89 230,888.89 300,155.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 939,538.89 1,133,463.41
E Overhead & Profit (contoh 10%) 10% 93,953.89 113,346.34
F Harga Satuan Pekerjaan (D+E) 1,033,492.78 1,246,809.75

Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum


9 A.4.1.1.9 1 m3 1,052,920.00 1,266,155.79
(12±2)cm, w/c = 0,53
A Tenaga 138,825.00 159,465.00
L.01 1.650 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
B Bahan 818,375.00 991,585.71
406 Kg Portland Semen 1,025.00 1,100.00 416,150.00 446,600.00
684 kg Pasir Beton 250.00 357.14 171,000.00 244,285.71
1,026 kg Kerikil (maksimum 30 mm) 222.22 288.89 228,000.00 296,400.00
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 957,200.00 1,151,050.71
E Overhead & Profit (contoh 10%) 10% 95,720.00 115,105.07
F Harga Satuan Pekerjaan (D+E) 1,052,920.00 1,266,155.79

file:///conversion/tmp/scratch/457687078.xls 130/70 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm,
10 A.4.1.1.10 1 m3 1,058,765.28 1,271,858.33
w/c = 0,52
A Tenaga 138,825.00 159,465.00
L.01 1.650 OH Pekerja 65,000.00 75,000.00 107,250.00 123,750.00
L.02 0.275 OH Tukang Batu 80,000.00 90,000.00 22,000.00 24,750.00
L.03 0.028 OH Kepala Tukang 90,000.00 110,000.00 2,520.00 3,080.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
B Bahan 823,688.89 996,769.84
413 Kg Portland Semen 1,025.00 1,100.00 423,325.00 454,300.00
681 Kg Pasir Beton 250.00 357.14 170,250.00 243,214.29
1,021 Kg Kerikil (maksimum 30 mm) 222.22 288.89 226,888.89 294,955.56
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 962,513.89 1,156,234.84
E Overhead & Profit (contoh 10%) 10% 96,251.39 115,623.48
F Harga Satuan Pekerjaan (D+E) 1,058,765.28 1,271,858.33

Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm,


11 A.4.1.1.11 1 m3 1,122,913.61 1,341,926.23
w/c = 0,49
A Tenaga 176,575.00 202,825.00
L.01 2.1 OH Pekerja 65,000.00 75,000.00 136,500.00 157,500.00
L.02 0.35 OH Tukang Batu 80,000.00 90,000.00 28,000.00 31,500.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.105 OH Mandor 85,000.00 95,000.00 8,925.00 9,975.00
B Bahan 844,255.56 1,017,107.94
439 Kg Portland Semen 1,025.00 1,100.00 449,975.00 482,900.00
670 Kg Pasir Beton 250.00 357.14 167,500.00 239,285.71
1,006 Kg Kerikil (maksimum 30 mm) 222.22 288.89 223,555.56 290,622.22
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,020,830.56 1,219,932.94
E Overhead & Profit (contoh 10%) 10% 102,083.06 121,993.29
F Harga Satuan Pekerjaan (D+E) 1,122,913.61 1,341,926.23

Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm,


12 A.4.1.1.12 1 m3 1,130,769.44 1,349,730.99
w/c = 0,48
A Tenaga 176,575.00 202,825.00
L.01 2.10 OH Pekerja 65,000.00 75,000.00 136,500.00 157,500.00
L.02 0.350 OH Tukang Batu 80,000.00 90,000.00 28,000.00 31,500.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.105 OH Mandor 85,000.00 95,000.00 8,925.00 9,975.00
B Bahan 851,397.22 1,024,203.17
448 Kg Portland Semen 1,025.00 1,100.00 459,200.00 492,800.00
667 Kg Pasir Beton 250.00 357.14 166,750.00 238,214.29
1,000 Kg Kerikil (maksimum 30 mm) 222.22 288.89 222,222.22 288,888.89
215 ltr Air 15.00 20.00 3,225.00 4,300.00
C PERALATAN
D Jumlah A + B + C 1,027,972.22 1,227,028.17
E Overhead & Profit (contoh 10%) 10% 102,797.22 122,702.82
F Harga Satuan Pekerjaan (D+E) 1,130,769.44 1,349,730.99

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir 135,817.00 147,125.00


A Tenaga 11,120.00 12,700.00
L.01 0.07 OH Pekerja 65,000.00 75,000.00 4,550.00 5,250.00
L.02 0.07 OH Tukang Besi 80,000.00 90,000.00 5,600.00 6,300.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.004 OH Mandor 85,000.00 95,000.00 340.00 380.00
B Bahan 112,350.00 121,050.00
10.50 Kg Besi Beton (polos/ulir) 10,500.00 11,300.00 110,250.00 118,650.00
0.150 Kg Kawat Beton 14,000.00 16,000.00 2,100.00 2,400.00
C PERALATAN
D Jumlah A + B + C 123,470.00 133,750.00
E Overhead & Profit (contoh 10%) 10% 12,347.00 13,375.00
F Harga Satuan Pekerjaan (D+E) 135,817.00 147,125.00

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand 177,765.50 196,553.50


A Tenaga 7,955.00 9,085.00
L.01 0.05 OH Pekerja 65,000.00 75,000.00 3,250.00 3,750.00
L.02 0.05 OH Tukang Besi 80,000.00 90,000.00 4,000.00 4,500.00
L.03 0.005 OH Kepala Tukang 90,000.00 110,000.00 450.00 550.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 153,650.00 169,600.00
10.5 Kg Besi presstred polos 14,500.00 16,000.00 152,250.00 168,000.00
0.1 Kg Kawat Beton 14,000.00 16,000.00 1,400.00 1,600.00

file:///conversion/tmp/scratch/457687078.xls 130/71 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 161,605.00 178,685.00
E Overhead & Profit (contoh 10%) 10% 16,160.50 17,868.50
F Harga Satuan Pekerjaan (D+E) 177,765.50 196,553.50

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh 285,549.00 314,314.00


A Tenaga 3,890.00 4,440.00
L.01 0.025 OH Pekerja 65,000.00 75,000.00 1,625.00 1,875.00
L.02 0.025 OH Tukang Besi 80,000.00 90,000.00 2,000.00 2,250.00
L.03 0.002 OH Kepala Tukang 90,000.00 110,000.00 180.00 220.00
L.04 0.001 OH Mandor 85,000.00 95,000.00 85.00 95.00
B Bahan 255,700.00 281,300.00
10.20 Kg Jaring Kawat Baja dilas 25,000.00 27,500.00 255,000.00 280,500.00
0.05 Kg Kawat Beton 14,000.00 16,000.00 700.00 800.00
C PERALATAN
D Jumlah A + B + C 259,590.00 285,740.00
E Overhead & Profit (contoh 10%) 10% 25,959.00 28,574.00
F Harga Satuan Pekerjaan (D+E) 285,549.00 314,314.00

16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi 158,675.00 178,343.00


A Tenaga 59,150.00 67,730.00
L.01 0.52 OH Pekerja 65,000.00 75,000.00 33,800.00 39,000.00
L.02 0.26 OH Tukang Kayu 80,000.00 90,000.00 20,800.00 23,400.00
L.03 0.026 OH Kepala Tukang 90,000.00 110,000.00 2,340.00 2,860.00
L.04 0.026 OH Mandor 85,000.00 95,000.00 2,210.00 2,470.00
B Bahan 85,100.00 94,400.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.3 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 4,200.00 5,400.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 144,250.00 162,130.00
E Overhead & Profit (contoh 10%) 10% 14,425.00 16,213.00
F Harga Satuan Pekerjaan (D+E) 158,675.00 178,343.00

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof 169,675.00 190,443.00


A Tenaga 59,150.00 67,730.00
L.01 0.52 OH Pekerja 65,000.00 75,000.00 33,800.00 39,000.00
L.02 0.26 OH Tukang Kayu 80,000.00 90,000.00 20,800.00 23,400.00
L.03 0.026 OH Kepala Tukang 90,000.00 110,000.00 2,340.00 2,860.00
L.04 0.026 OH Mandor 85,000.00 95,000.00 2,210.00 2,470.00
B Bahan 95,100.00 105,400.00
0.045 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 90,000.00 99,000.00
0.3 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 4,200.00 5,400.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 154,250.00 173,130.00
E Overhead & Profit (contoh 10%) 10% 15,425.00 17,313.00
F Harga Satuan Pekerjaan (D+E) 169,675.00 190,443.00

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom 361,872.50 416,531.50


A Tenaga 75,075.00 85,965.00
L.01 0.66 OH Pekerja 65,000.00 75,000.00 42,900.00 49,500.00
L.02 0.33 OH Tukang Kayu 80,000.00 90,000.00 26,400.00 29,700.00
L.03 0.033 OH Kepala Tukang 90,000.00 110,000.00 2,970.00 3,630.00
L.04 0.033 OH Mandor 85,000.00 95,000.00 2,805.00 3,135.00
B Bahan 253,900.00 292,700.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 5,600.00 7,200.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II 5,500,000.00 6,100,000.00 82,500.00 91,500.00
0.35 Lbr Plywood tebal 9mm 120,000.00 160,000.00 42,000.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 328,975.00 378,665.00
E Overhead & Profit (contoh 10%) 10% 32,897.50 37,866.50
F Harga Satuan Pekerjaan (D+E) 361,872.50 416,531.50

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok 380,022.50 436,661.50


A Tenaga 75,075.00 85,965.00
L.01 0.66 OH Pekerja 65,000.00 75,000.00 42,900.00 49,500.00
L.02 0.33 OH Tukang Kayu 80,000.00 90,000.00 26,400.00 29,700.00
L.03 0.033 OH Kepala Tukang 90,000.00 110,000.00 2,970.00 3,630.00
L.04 0.033 OH Mandor 85,000.00 95,000.00 2,805.00 3,135.00

file:///conversion/tmp/scratch/457687078.xls 130/72 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 270,400.00 311,000.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 5,600.00 7,200.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.018 m3 Balok Kayu Klas II 5,500,000.00 6,100,000.00 99,000.00 109,800.00
0.35 Lbr Plywood tebal 9mm 120,000.00 160,000.00 42,000.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 345,475.00 396,965.00
E Overhead & Profit (contoh 10%) 10% 34,547.50 39,696.50
F Harga Satuan Pekerjaan (D+E) 380,022.50 436,661.50

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai 454,272.50 522,131.50


A Tenaga 75,075.00 85,965.00
L.01 0.66 OH Pekerja 65,000.00 75,000.00 42,900.00 49,500.00
L.02 0.33 OH Tukang Kayu 80,000.00 90,000.00 26,400.00 29,700.00
L.03 0.033 OH Kepala Tukang 90,000.00 110,000.00 2,970.00 3,630.00
L.04 0.033 OH Mandor 85,000.00 95,000.00 2,805.00 3,135.00
B Bahan 337,900.00 388,700.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 80,000.00 88,000.00
0.4 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 5,600.00 7,200.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 5,500,000.00 6,100,000.00 82,500.00 91,500.00
0.35 Lbr Plywood tebal 9mm 120,000.00 160,000.00 42,000.00 56,000.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 126,000.00 144,000.00
C PERALATAN
D Jumlah A + B + C 412,975.00 474,665.00
E Overhead & Profit (contoh 10%) 10% 41,297.50 47,466.50
F Harga Satuan Pekerjaan (D+E) 454,272.50 522,131.50

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding 415,222.50 476,481.50


A Tenaga 75,075.00 85,965.00
L.01 0.66 OH Pekerja 65,000.00 75,000.00 42,900.00 49,500.00
L.02 0.33 OH Tukang Kayu 80,000.00 90,000.00 26,400.00 29,700.00
L.03 0.033 OH Kepala Tukang 90,000.00 110,000.00 2,970.00 3,630.00
L.04 0.033 OH Mandor 85,000.00 95,000.00 2,805.00 3,135.00
B Bahan 302,400.00 347,200.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 5,600.00 7,200.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.02 m3 Balok Kayu Klas II 5,500,000.00 6,100,000.00 110,000.00 122,000.00
0.35 Lbr Plywood tebal 9mm 120,000.00 160,000.00 42,000.00 56,000.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 63,000.00 72,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 5,000.00 5,500.00 20,000.00 22,000.00
C PERALATAN
D Jumlah A + B + C 377,475.00 433,165.00
E Overhead & Profit (contoh 10%) 10% 37,747.50 43,316.50
F Harga Satuan Pekerjaan (D+E) 415,222.50 476,481.50

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga 339,377.50 391,781.50


A Tenaga 75,075.00 85,965.00
L.01 0.66 OH Pekerja 65,000.00 75,000.00 42,900.00 49,500.00
L.02 0.33 OH Tukang Kayu 80,000.00 90,000.00 26,400.00 29,700.00
L.03 0.033 OH Kepala Tukang 90,000.00 110,000.00 2,970.00 3,630.00
L.04 0.033 OH Mandor 85,000.00 95,000.00 2,805.00 3,135.00
B Bahan 233,450.00 270,200.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,200,000.00 60,000.00 66,000.00
0.4 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 5,600.00 7,200.00
0.15 Ltr Minyak Bekisting 9,000.00 10,000.00 1,350.00 1,500.00
0.015 m3 Balok Kayu Klas II 5,500,000.00 6,100,000.00 82,500.00 91,500.00
0.35 Lbr Plywood tebal 9mm 120,000.00 160,000.00 42,000.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 21,000.00 24,000.00 42,000.00 48,000.00
C PERALATAN
D Jumlah A + B + C 308,525.00 356,165.00
E Overhead & Profit (contoh 10%) 10% 30,852.50 35,616.50
F Harga Satuan Pekerjaan (D+E) 339,377.50 391,781.50

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor 95,238.00 107,734.00


A Tenaga 14,880.00 17,060.00
L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.05 OH Tukang Kayu 80,000.00 90,000.00 4,000.00 4,500.00
L.03 0.005 OH Kepala Tukang 90,000.00 110,000.00 450.00 550.00
L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00
B Bahan 71,700.00 80,880.00
0.0264 m3 Kayu Terentang 2,000,000.00 2,200,000.00 52,800.00 58,080.00
0.6 kg Paku Biasa 2" - 5" 14,000.00 18,000.00 8,400.00 10,800.00
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m 21,000.00 24,000.00 10,500.00 12,000.00

file:///conversion/tmp/scratch/457687078.xls 130/73 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 86,580.00 97,940.00
E Overhead & Profit (contoh 10%) 10% 8,658.00 9,794.00
F Harga Satuan Pekerjaan (D+E) 95,238.00 107,734.00

24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 75,916.50 88,038.50
A Tenaga 17,805.00 20,515.00
L.01 0.180 OH Pekerja 65,000.00 75,000.00 11,700.00 13,500.00
L.02 0.020 OH Tukang batu 80,000.00 90,000.00 1,600.00 1,800.00
L.02 0.020 OH Tukang Kayu 80,000.00 95,000.00 1,600.00 1,900.00
L.02 0.020 OH Tukang Besi 80,000.00 90,000.00 1,600.00 1,800.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.009 OH Mandor 85,000.00 95,000.00 765.00 855.00
B Bahan 51,210.00 59,520.00
0.002 m3 Kayu Klas III 2,050,000.00 3,800,000.00 4,100.00 7,600.00
0.01 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 140.00 180.00
3.0 Kg Besi Beton Polos 10,500.00 11,300.00 31,500.00 33,900.00
0.45 Kg Kawat Beton 14,000.00 16,000.00 6,300.00 7,200.00
4.0 Kg Portland Semen 1,025.00 1,100.00 4,100.00 4,400.00
0.006 m3 Pasir Beton 350,000.00 500,000.00 2,100.00 3,000.00
0.009 m3 Kerikil 330,000.00 360,000.00 2,970.00 3,240.00
C PERALATAN
D Jumlah A + B + C 69,015.00 80,035.00
E Overhead & Profit (contoh 10%) 10% 6,901.50 8,003.50
F Harga Satuan Pekerjaan (D+E) 75,916.50 88,038.50

25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 96,874.25 113,371.50
A Tenaga 29,400.00 33,875.00
L.01 0.297 OH Pekerja 65,000.00 75,000.00 19,305.00 22,275.00
L.02 0.033 OH Tukang batu 80,000.00 90,000.00 2,640.00 2,970.00
L.02 0.033 OH Tukang Kayu 80,000.00 95,000.00 2,640.00 3,135.00
L.02 0.033 OH Tukang Besi 80,000.00 90,000.00 2,640.00 2,970.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 58,667.50 69,190.00
0.003 m3 Kayu Klas III 2,050,000.00 3,800,000.00 6,150.00 11,400.00
0.02 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 280.00 360.00
3.6 Kg Besi Beton Polos 10,500.00 11,300.00 37,800.00 40,680.00
0.05 Kg Kawat Beton 14,000.00 16,000.00 700.00 800.00
5.5 Kg Portland Semen 1,025.00 1,100.00 5,637.50 6,050.00
0.009 m3 Pasir Beton 350,000.00 500,000.00 3,150.00 4,500.00
0.015 m3 Kerikil 330,000.00 360,000.00 4,950.00 5,400.00
C PERALATAN
D Jumlah A + B + C 88,067.50 103,065.00
E Overhead & Profit (contoh 10%) 10% 8,806.75 10,306.50
F Harga Satuan Pekerjaan (D+E) 96,874.25 113,371.50

file:///conversion/tmp/scratch/457687078.xls 130/74 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

V A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil 28,154.50 30,602.00
A Tenaga 9,495.00 11,145.00
L.01 0.06 OH Pekerja 65,000.00 75,000.00 3,900.00 4,500.00
L.02 0.06 OH Tukang Besi 80,000.00 95,000.00 4,800.00 5,700.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 16,100.00 16,675.00
1.15 Kg Besi Profil 14,000.00 14,500.00 16,100.00 16,675.00
C PERALATAN
D Jumlah A + B + C 25,595.00 27,820.00
E Overhead & Profit (contoh 10%) 10% 2,559.50 2,782.00
F Harga Satuan Pekerjaan (D+E) 28,154.50 30,602.00

2 A.4.2.1.2 1 Kg Pemasangan Rangka Kuda-kuda Baja IWF 19,552.50 21,747.00


A Tenaga 9,495.00 11,145.00
L.01 0.06 OH Pekerja 65,000.00 75,000.00 3,900.00 4,500.00
L.02 0.06 OH Tukang Besi 80,000.00 95,000.00 4,800.00 5,700.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 8,280.00 8,625.00
1.15 kg Besi Baja IWF 7,200.00 7,500.00 8,280.00 8,625.00
C PERALATAN
D Jumlah A + B + C 17,775.00 19,770.00
E Overhead & Profit (contoh 10%) 10% 1,777.50 1,977.00
F Harga Satuan Pekerjaan (D+E) 19,552.50 21,747.00

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) 94,341.50 111,413.50


A Tenaga 15,015.00 17,585.00
L.01 0.100 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.100 OH Tukang Besi 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.001 OH Kepala Tukang 90,000.00 110,000.00 90.00 110.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 10,750.00 11,700.00
1 ltr Solar 7,000.00 7,200.00 7,000.00 7,200.00
0.1 ltr Minyak Pelumas 37,500.00 45,000.00 3,750.00 4,500.00
C PERALATAN 60,000 72,000
0.800 jam Sewa Alat 75,000 90,000 60,000 72,000
D Jumlah A + B + C 85,765.00 101,285.00
E Overhead & Profit (contoh 10%) 10% 8,576.50 10,128.50
F Harga Satuan Pekerjaan (D+E) 94,341.50 111,413.50

Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap,


4 A.4.2.1.4 1 m2 791,637.00 846,659.00
rangka baja Siku
A Tenaga 166,120.00 194,990.00
L.01 1.05 OH Pekerja 65,000.00 75,000.00 68,250.00 78,750.00
L.02 1.05 OH Tukang Besi 80,000.00 95,000.00 84,000.00 99,750.00
L.03 0.105 OH Kepala Tukang 90,000.00 110,000.00 9,450.00 11,550.00
L.04 0.052 OH Mandor 85,000.00 95,000.00 4,420.00 4,940.00
B Bahan 553,550.00 574,700.00
15 Kg Besi Siku L.30.30.3 7,200.00 7,500.00 108,000.00 112,500.00
32.8 Kg Besi Plat Baja 13,500.00 14,000.00 442,800.00 459,200.00
0.05 Kg Kawat Las 55,000.00 60,000.00 2,750.00 3,000.00
C PERALATAN
D Jumlah A + B + C 719,670.00 769,690.00
E Overhead & Profit (contoh 10%) 10% 71,967.00 76,969.00
F Harga Satuan Pekerjaan (D+E) 791,637.00 846,659.00

5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik 21,846.00 25,746.60


A Tenaga 4,550.00 5,310.00
L.01 0.04 OH Pekerja 65,000.00 75,000.00 2,600.00 3,000.00
L.02 0.02 OH Tukang Besi 80,000.00 95,000.00 1,600.00 1,900.00
L.03 0.002 OH Kepala Tukang 90,000.00 110,000.00 180.00 220.00
L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00
B Bahan 2,560.00 2,796.00
0.04 kg Kawat Las 55,000.00 60,000.00 2,200.00 2,400.00
0.03 ltr Solar 7,000.00 7,200.00 210.00 216.00
0.004 ltr Minyak Pelumas 37,500.00 45,000.00 150.00 180.00

file:///conversion/tmp/scratch/457687078.xls 130/75 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

C PERALATAN 12,750 15,300


0.170 jam Sewa Alat 75,000 90,000 12,750 15,300
D Jumlah A + B + C 19,860.00 23,406.00
E Overhead & Profit (contoh 10%) 10% 1,986.00 2,340.60
F Harga Satuan Pekerjaan (D+E) 21,846.00 25,746.60

6 A.4.2.1.6 1 m2 Pembuatan Rangka Jendela Besi Scuare Tube 202,265.80 238,227.22


A Tenaga 102,820.00 120,690.00
L.01 0.65 OH Pekerja 65,000.00 75,000.00 42,250.00 48,750.00
L.02 0.65 OH Tukang Las Biasa 80,000.00 95,000.00 52,000.00 61,750.00
L.03 0.065 OH Kepala Tukang 90,000.00 110,000.00 5,850.00 7,150.00
L.04 0.032 OH Mandor 85,000.00 95,000.00 2,720.00 3,040.00
B Bahan 81,058.00 95,880.20
4.760 m' Besi Scuare tube 5,000.00 6,000.00 23,800.00 28,560.00
4.522 m' Besi List Kaca 1 x 1 cm 3,000.00 3,500.00 13,566.00 15,827.00
20.000 cm Pengelasan 2,184.60 2,574.66 43,692.00 51,493.20
C PERALATAN
D Jumlah A + B + C 183,878.00 216,570.20
E Overhead & Profit (contoh 10%) 10% 18,387.80 21,657.02
F Harga Satuan Pekerjaan (D+E) 202,265.80 238,227.22

7 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi 533,841.00 597,047.00


A Tenaga 185,310.00 217,770.00
L.01 1.2 OH Pekerja 65,000.00 75,000.00 78,000.00 90,000.00
L.02 1.2 OH Tukang Besi 80,000.00 95,000.00 96,000.00 114,000.00
L.03 0.12 OH Kepala Tukang 90,000.00 110,000.00 10,800.00 13,200.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 300,000.00 325,000.00
1 m2 Pintu Gulung Besi 300,000.00 325,000.00 300,000.00 325,000.00
C PERALATAN
D Jumlah A + B + C 485,310.00 542,770.00
E Overhead & Profit (contoh 10%) 10% 48,531.00 54,277.00
F Harga Satuan Pekerjaan (D+E) 533,841.00 597,047.00

8 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door) 494,593.00 557,403.00


A Tenaga 69,630.00 81,730.00
L.01 0.44 OH Pekerja 65,000.00 75,000.00 28,600.00 33,000.00
L.02 0.44 OH Tukang Besi 80,000.00 95,000.00 35,200.00 41,800.00
L.03 0.044 OH Kepala Tukang 90,000.00 110,000.00 3,960.00 4,840.00
L.04 0.022 OH Mandor 85,000.00 95,000.00 1,870.00 2,090.00
B Bahan 380,000.00 425,000.00
1 m2 Pintu Lipat 380,000.00 425,000.00 380,000.00 425,000.00
C PERALATAN
D Jumlah A + B + C 449,630.00 506,730.00
E Overhead & Profit (contoh 10%) 10% 44,963.00 50,673.00
F Harga Satuan Pekerjaan (D+E) 494,593.00 557,403.00

9 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium 425,414.00 485,298.00


A Tenaga 76,740.00 91,180.00
L.01 0.08 OH Pekerja 65,000.00 75,000.00 5,200.00 6,000.00
L.02 0.8 OH Tukang Besi 80,000.00 95,000.00 64,000.00 76,000.00
L.03 0.08 OH Kepala Tukang 90,000.00 110,000.00 7,200.00 8,800.00
L.04 0.004 OH Mandor 85,000.00 95,000.00 340.00 380.00
B Bahan 310,000.00 350,000.00
1 m2 Sunscreen Allumunium 310,000.00 350,000.00 310,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 386,740.00 441,180.00
E Overhead & Profit (contoh 10%) 10% 38,674.00 44,118.00
F Harga Satuan Pekerjaan (D+E) 425,414.00 485,298.00

10 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium 427,075.00 506,825.00


A Tenaga 158,250.00 185,750.00
L.01 1 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 1 OH Tukang Besi 80,000.00 95,000.00 80,000.00 95,000.00
L.03 0.1 OH Kepala Tukang 90,000.00 110,000.00 9,000.00 11,000.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00

file:///conversion/tmp/scratch/457687078.xls 130/76 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 230,000.00 275,000.00


1 m2 Rolling Allumunium 230,000.00 275,000.00 230,000.00 275,000.00
C PERALATAN
D Jumlah A + B + C 388,250.00 460,750.00
E Overhead & Profit (contoh 10%) 10% 38,825.00 46,075.00
F Harga Satuan Pekerjaan (D+E) 427,075.00 506,825.00

11 A.4.2.1.11 1 m' Pemasangan Kusen Pintu Allumunium 109,230.55 117,350.75


A Tenaga 6,800.50 7,982.50
L.01 0.043 OH Pekerja 65,000.00 75,000.00 2,795.00 3,225.00
L.02 0.043 OH Tukang Besi 80,000.00 95,000.00 3,440.00 4,085.00
L.03 0.0043 OH Kepala Tukang 90,000.00 110,000.00 387.00 473.00
L.04 0.0021 OH Mandor 85,000.00 95,000.00 178.50 199.50
B Bahan 92,500.00 98,700.00
1.1 m' Profil Allumunium 80,000.00 85,000.00 88,000.00 93,500.00
2 buah Skrup Fixer 750.00 800.00 1,500.00 1,600.00
0.06 Tube Sealant 50,000.00 60,000.00 3,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 99,300.50 106,682.50
E Overhead & Profit (contoh 10%) 10% 9,930.05 10,668.25
F Harga Satuan Pekerjaan (D+E) 109,230.55 117,350.75

12 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm 474,261.70 509,062.40


A Tenaga 13,447.00 15,784.00
L.01 0.085 OH Pekerja 65,000.00 75,000.00 5,525.00 6,375.00
L.02 0.085 OH Tukang Besi 80,000.00 95,000.00 6,800.00 8,075.00
L.03 0.0085 OH Kepala Tukang 90,000.00 110,000.00 765.00 935.00
L.04 0.0042 OH Mandor 85,000.00 95,000.00 357.00 399.00
B Bahan 417,700.00 447,000.00
4.4 m' Profil Allumunium 80,000.00 85,000.00 352,000.00 374,000.00
14.6 m' Allumunium Strip 4,500.00 5,000.00 65,700.00 73,000.00
C PERALATAN
D Jumlah A + B + C 431,147.00 462,784.00
E Overhead & Profit (contoh 10%) 10% 43,114.70 46,278.40
F Harga Satuan Pekerjaan (D+E) 474,261.70 509,062.40

13 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium 441,716.00 476,426.50


A Tenaga 13,560.00 15,915.00
L.01 0.085 OH Pekerja 65,000.00 75,000.00 5,525.00 6,375.00
L.02 0.085 OH Tukang Besi 80,000.00 95,000.00 6,800.00 8,075.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 388,000.00 417,200.00
4.4 m' Pintu Allumunium 80,000.00 85,000.00 352,000.00 374,000.00
4.5 m' Profil Kaca 5,000.00 6,000.00 22,500.00 27,000.00
0.27 tube Sealant 50,000.00 60,000.00 13,500.00 16,200.00
C PERALATAN
D Jumlah A + B + C 401,560.00 433,115.00
E Overhead & Profit (contoh 10%) 10% 40,156.00 43,311.50
F Harga Satuan Pekerjaan (D+E) 441,716.00 476,426.50

14 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds 165,473.00 181,566.00


A Tenaga 55,430.00 65,060.00
L.01 0.35 OH Pekerja 65,000.00 75,000.00 22,750.00 26,250.00
L.02 0.35 OH Tukang Besi 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00
B Bahan 95,000.00 100,000.00
1 m2 Venetions Blinds atau Vertical Blinds (tirai) 95,000.00 100,000.00 95,000.00 100,000.00
C PERALATAN
D Jumlah A + B + C 150,430.00 165,060.00
E Overhead & Profit (contoh 10%) 10% 15,043.00 16,506.00
F Harga Satuan Pekerjaan (D+E) 165,473.00 181,566.00

15 A.4.2.1.15 1 m2 Pemasangan Teralis Besi Strip (2x3) cm 447,461.81 512,990.27


A Tenaga 264,235.00 310,155.00
L.01 1.67 OH Pekerja 65,000.00 75,000.00 108,550.00 125,250.00
L.02 1.67 OH Tukang Las 80,000.00 95,000.00 133,600.00 158,650.00
L.03 0.167 OH Kepala Tukang 90,000.00 110,000.00 15,030.00 18,370.00
L.04 0.083 OH Mandor 85,000.00 95,000.00 7,055.00 7,885.00
file:///conversion/tmp/scratch/457687078.xls 130/77 abk 5-14
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

B Bahan 142,548.47 156,199.79


6.177 kg Besi Strip 13,500.00 14,000.00 83,389.50 86,478.00
27.08 cm Pengelasan 2,184.60 2,574.66 59,158.97 69,721.79
C PERALATAN
D Jumlah A + B + C 406,783.47 466,354.79
E Overhead & Profit (contoh 10%) 10% 40,678.35 46,635.48
F Harga Satuan Pekerjaan (D+E) 447,461.81 512,990.27

16 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk 81,688.10 100,103.82


A Tenaga 15,825.00 18,575.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.1 OH Tukang 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 58,436.91 72,428.47
1.1 m2 Kawat Nyamuk nylon 10,000.00 18,000.00 11,000.00 19,800.00
11.11 cm Pengelasan 2,184.60 2,574.66 24,270.91 28,604.47
1.716 kg Baja Strip (0,2x2) cm 13,500.00 14,000.00 23,166.00 24,024.00
C PERALATAN
D Jumlah A + B + C 74,261.91 91,003.47
E Overhead & Profit (contoh 10%) 10% 7,426.19 9,100.35
F Harga Satuan Pekerjaan (D+E) 81,688.10 100,103.82

17 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis 117,298.50 131,224.50


A Tenaga 30,885.00 36,295.00
L.01 0.2 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.2 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.001 OH Mandor 85,000.00 95,000.00 85.00 95.00
B Bahan 75,750.00 83,000.00
1.1 m2 Jendela Nako 32,500.00 35,000.00 35,750.00 38,500.00
10 buah Paku Skrup 1 - 2,5 cm 500.00 600.00 5,000.00 6,000.00
7 m' Besi Strip 5,000.00 5,500.00 35,000.00 38,500.00
C PERALATAN
D Jumlah A + B + C 106,635.00 119,295.00
E Overhead & Profit (contoh 10%) 10% 10,663.50 11,929.50
F Harga Satuan Pekerjaan (D+E) 117,298.50 131,224.50

Pemasangan Talang Datar / Jurai , Seng BJLS 28 Lebar 90


18 A.4.2.1.18 1 m' 176,561.00 210,094.50
cm
A Tenaga 48,100.00 56,700.00
L.01 0.20 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.4 OH Tukang Kayu 80,000.00 95,000.00 32,000.00 38,000.00
L.03 0.025 OH Kepala Tukang 90,000.00 110,000.00 2,250.00 2,750.00
L.04 0.01 OH Mandor 85,000.00 95,000.00 850.00 950.00
B Bahan 112,410.00 134,295.00
1.05 Lbr Seng Plaat 20,000.00 24,500.00 21,000.00 25,725.00
0.015 Kg Paku Biasa 1 - 2,5 cm 14,000.00 18,000.00 210.00 270.00
0.019 m3 Kayu Papan Klas II atau III 4,800,000.00 5,700,000.00 91,200.00 108,300.00
C PERALATAN
D Jumlah A + B + C 160,510.00 190,995.00
E Overhead & Profit (contoh 10%) 10% 16,051.00 19,099.50
F Harga Satuan Pekerjaan (D+E) 176,561.00 210,094.50

Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat


19 A.4.2.1.19 1 m' 64,652.50 76,120.00
BJLS 30 Lebar 45 cm
A Tenaga 30,885.00 36,295.00
L.01 0.20 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.20 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.001 OH Mandor 85,000.00 95,000.00 85.00 95.00
B Bahan 27,890.00 32,905.00
1.05 Lbr Seng Plaat 20,000.00 24,500.00 21,000.00 25,725.00
0.01 Kg Paku Biasa 1 - 2,5 cm 14,000.00 18,000.00 140.00 180.00
0.5 Kg Besi strip 13,500.00 14,000.00 6,750.00 7,000.00
C PERALATAN
D Jumlah A + B + C 58,775.00 69,200.00
E Overhead & Profit (contoh 10%) 10% 5,877.50 6,920.00
F Harga Satuan Pekerjaan (D+E) 64,652.50 76,120.00

file:///conversion/tmp/scratch/457687078.xls 130/78 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


20 A.4.2.1.20 1 m2 105,165.50 116,583.50
60x120 cm dinding partisi
A Tenaga 39,605.00 46,485.00
L.01 0.250 OH Pekerja 65,000.00 75,000.00 16,250.00 18,750.00
L.02 0.250 OH Tukang Besi 80,000.00 95,000.00 20,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 90,000.00 110,000.00 2,250.00 2,750.00
L.04 0.013 OH Mandor 85,000.00 95,000.00 1,105.00 1,235.00
B Bahan 56,000.00 59,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 28,000.00 29,750.00
1.00 **) Assesoris (perkuatan; las dll) 28,000.00 29,750.00 28,000.00 29,750.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 95,605.00 105,985.00
E Overhead & Profit (contoh 10%) 10% 9,560.50 10,598.50
F Harga Satuan Pekerjaan (D+E) 105,165.50 116,583.50

Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul


21 A.4.2.1.21 1 m2 131,373.00 146,366.00
60x60 cm dinding plafond
A Tenaga 55,430.00 65,060.00
L.01 0.350 OH Pekerja 65,000.00 75,000.00 22,750.00 26,250.00
L.02 0.350 OH Tukang Besi 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00
B Bahan 64,000.00 68,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 8,000.00 8,500.00 32,000.00 34,000.00
1.00 **) Assesoris (perkuatan; las dll) 32,000.00 34,000.00 32,000.00 34,000.00
**) 100% x rangka
C PERALATAN
D Jumlah A + B + C 119,430.00 133,060.00
E Overhead & Profit (contoh 10%) 10% 11,943.00 13,306.00
F Harga Satuan Pekerjaan (D+E) 131,373.00 146,366.00

Pemasangan Atap Pelana Rangka Atap Baja Canal C


22 A.4.2.1.22 1 m2 189,120.80 213,510.28
dingin Profil C75
A Tenaga 116,145.00 136,325.00
L.01 0.734 OH Pekerja 65,000.00 75,000.00 47,710.00 55,050.00
L.02 0.734 OH Tukang Besi 80,000.00 95,000.00 58,720.00 69,730.00
L.03 0.073 OH Kepala Tukang 90,000.00 110,000.00 6,570.00 8,030.00
L.04 0.037 OH Mandor 85,000.00 95,000.00 3,145.00 3,515.00
B Bahan 51,492.00 53,331.00
3.065 kg Baja Ringan Canal Dingin C75 14,000.00 14,500.00 42,910.00 44,442.50
C PERALATAN 4,291.00 4,444.25
10 % Peralatan *) harga bahan 42,910.00 44,442.50 4,291.00 4,444.25
D Jumlah A + B + C 171,928.00 194,100.25
E Overhead & Profit (contoh 10%) 10% 17,192.80 19,410.03
F Harga Satuan Pekerjaan (D+E) 189,120.80 213,510.28

Pemasangan Atap Jurai Rangka Atap Baja Canal Dingin


23 A.4.2.1.23 1 m2 213,441.80 239,338.55
Profil C75
A Tenaga 120,328.00 141,238.00
L.01 0.7604 OH Pekerja 65,000.00 75,000.00 49,426.00 57,030.00
L.02 0.7604 OH Tukang Besi 80,000.00 95,000.00 60,832.00 72,238.00
L.03 0.0760 OH Kepala Tukang 90,000.00 110,000.00 6,840.00 8,360.00
L.04 0.0380 OH Mandor 85,000.00 95,000.00 3,230.00 3,610.00
B Bahan 68,040.00 70,470.00
4.05 kg Baja Ringan Canal Dingin C75 14,000.00 14,500.00 56,700.00 58,725.00
C PERALATAN 5,670.00 5,872.50
10 % Peralatan *) harga bahan 56,700.00 58,725.00 5,670.00 5,872.50
D Jumlah A + B + C 194,038.00 217,580.50
E Overhead & Profit (contoh 10%) 10% 19,403.80 21,758.05
F Harga Satuan Pekerjaan (D+E) 213,441.80 239,338.55

file:///conversion/tmp/scratch/457687078.xls 130/79 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VI A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan Dinding Bata Merah ukuran (5x11x22) cm
1 A.4.4.1.1 1 m2 221,031.25 252,450.00
Tebal 1 bata Camp. 1SP: 2PP

A Tenaga 59,350.00 68,050.00


L.01 0.6 OH Pekerja 65,000.00 75,000.00 39,000.00 45,000.00
L.02 0.2 OH Tukang Batu 80,000.00 90,000.00 16,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.03 OH Mandor 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 141,587.50 161,450.00
140 Buah Bata Merah 550.00 600.00 77,000.00 84,000.00
43.5 Kg Portland Semen (PC) 1,025.00 1,100.00 44,587.50 47,850.00
0.08 m3 Pasir Pasang (PP) 250,000.00 370,000.00 20,000.00 29,600.00
C PERALATAN
D Jumlah A + B + C 200,937.50 229,500.00
E Overhead & Profit (contoh 10%) 10% 20,093.75 22,950.00
F Harga Satuan Pekerjaan (D+E) 221,031.25 252,450.00
Overhead & Profit (contoh 10%)

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


2 A.4.4.1.2 1 m2 212,161.13 244,161.50
Tebal 1 Bata Camp. 1SP : 3PP
A Tenaga 59,350.00 68,050.00
L.01 0.6 OH Pekerja 65,000.00 75,000.00 39,000.00 45,000.00
L.02 0.2 OH Tukang Batu 80,000.00 90,000.00 16,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.03 OH Mandor 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 133,523.75 153,915.00
140 Buah Bata Merah 550.00 600.00 77,000.00 84,000.00
32.95 Kg Portland Semen (PC) 1,025.00 1,100.00 33,773.75 36,245.00
0.091 m3 Pasir Pasang (PP) 250,000.00 370,000.00 22,750.00 33,670.00
C PERALATAN
D Jumlah A + B + C 192,873.75 221,965.00
E Overhead & Profit (contoh 10%) 10% 19,287.38 22,196.50
F Harga Satuan Pekerjaan (D+E) 212,161.13 244,161.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


3 A.4.4.1.3 1 m2 205,495.13 237,231.50
Tebal 1 Bata Camp. 1SP : 4PP
A Tenaga 59,350.00 68,050.00
L.01 0.6 OH Pekerja 65,000.00 75,000.00 39,000.00 45,000.00
L.02 0.2 OH Tukang Batu 80,000.00 90,000.00 16,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.03 OH Mandor 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 127,463.75 147,615.00
140 Buah Bata Merah 550.00 600.00 77,000.00 84,000.00
26.55 Kg Portland Semen (PC) 1,025.00 1,100.00 27,213.75 29,205.00
0.093 m3 Pasir Pasang (PP) 250,000.00 370,000.00 23,250.00 34,410.00
C PERALATAN
D Jumlah A + B + C 186,813.75 215,665.00
E Overhead & Profit (contoh 10%) 10% 18,681.38 21,566.50
F Harga Satuan Pekerjaan (D+E) 205,495.13 237,231.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


4 A.4.4.1.4 1 m2 203,065.50 235,631.00
Tebal 1 Bata Camp. 1SP : 5PP

A Tenaga 59,350.00 68,050.00


L.01 0.6 OH Pekerja 65,000.00 75,000.00 39,000.00 45,000.00
L.02 0.2 OH Tukang Batu 80,000.00 90,000.00 16,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.03 OH Mandor 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 125,255.00 146,160.00
140 Buah Bata Merah 550.00 600.00 77,000.00 84,000.00
22.2 Kg Portland Semen (PC) 1,025.00 1,100.00 22,755.00 24,420.00
0.102 m3 Pasir Pasang (PP) 250,000.00 370,000.00 25,500.00 37,740.00
C PERALATAN
D Jumlah A + B + C 184,605.00 214,210.00
E Overhead & Profit (contoh 10%) 10% 18,460.50 21,421.00
F Harga Satuan Pekerjaan (D+E) 203,065.50 235,631.00

file:///conversion/tmp/scratch/457687078.xls 130/80 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm
5 A.4.4.1.5 1 m2 204,393.75 239,294.00
Tebal 1 Bata Camp. 1SP : 6PP
A Tenaga 59,350.00 68,050.00
L.01 0.6 OH Pekerja 65,000.00 75,000.00 39,000.00 45,000.00
L.02 0.2 OH Tukang Batu 80,000.00 90,000.00 16,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.03 OH Mandor 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 126,462.50 149,490.00
140 Buah Bata Merah 550.00 600.00 77,000.00 84,000.00
18.5 Kg Portland Semen (PC) 1,025.00 1,100.00 18,962.50 20,350.00
0.122 m3 Pasir Pasang (PP) 250,000.00 370,000.00 30,500.00 45,140.00
C PERALATAN
D Jumlah A + B + C 185,812.50 217,540.00
E Overhead & Profit (contoh 10%) 10% 18,581.25 21,754.00
F Harga Satuan Pekerjaan (D+E) 204,393.75 239,294.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm


6 A.4.4.1.6 1 m2 195,862.70 226,476.80
Tebal 1 Bata Camp. 1SP : 3 KP :10PP

A Tenaga 59,350.00 68,050.00


L.01 0.6 OH Pekerja 65,000.00 75,000.00 39,000.00 45,000.00
L.02 0.2 OH Tukang Batu 80,000.00 90,000.00 16,000.00 18,000.00
L.03 0.02 OH Kepala Tukang Batu 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.03 OH Mandor 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 118,707.00 137,838.00
140 Buah Bata Merah 550.00 600.00 77,000.00 84,000.00
10.08 Kg Portland Semen (PC) 1,025.00 1,100.00 10,332.00 11,088.00
0.0925 m3 Pasir Pasang (PP) 250,000.00 370,000.00 23,125.00 34,225.00
0.0275 m3 Kapur Pasang (KP) 300,000.00 310,000.00 8,250.00 8,525.00
C PERALATAN
D Jumlah A + B + C 178,057.00 205,888.00
E Overhead & Profit (contoh 10%) 10% 17,805.70 20,588.80
F Harga Satuan Pekerjaan (D+E) 195,862.70 226,476.80

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


7 A.4.4.1.7 1 m2 106,808.63 122,023.00
Tebal 1/2 Bata Camp. 1SP : 2PP

A Tenaga 29,675.00 34,025.00


L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 67,423.75 76,905.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
18.95 Kg Portland Semen 1,025.00 1,100.00 19,423.75 20,845.00
0.038 m3 Pasir Pasang 250,000.00 370,000.00 9,500.00 14,060.00
C PERALATAN
D Jumlah A + B + C 97,098.75 110,930.00
E Overhead & Profit (contoh 10%) 10% 9,709.88 11,093.00
F Harga Satuan Pekerjaan (D+E) 106,808.63 122,023.00

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


8 A.4.4.1.8 1 m2 102,194.68 117,295.20
Tebal 1/2 Bata Camp. 1SP : 3PP

A Tenaga 29,675.00 34,025.00


L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 63,229.25 72,607.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
14.37 Kg Portland Semen 1,025.00 1,100.00 14,729.25 15,807.00
0.04 m3 Pasir Pasang 250,000.00 370,000.00 10,000.00 14,800.00

file:///conversion/tmp/scratch/457687078.xls 130/81 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 92,904.25 106,632.00
E Overhead & Profit (contoh 10%) 10% 9,290.43 10,663.20
F Harga Satuan Pekerjaan (D+E) 102,194.68 117,295.20

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


9 A.4.4.1.9 1 m2 99,783.75 115,043.50
Tebal 1/2 Bata Camp. 1SP : 4PP

A Tenaga 29,675.00 34,025.00


L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 61,037.50 70,560.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
11.50 Kg Portland Semen 1,025.00 1,100.00 11,787.50 12,650.00
0.043 m3 Pasir Pasang 250,000.00 370,000.00 10,750.00 15,910.00
C PERALATAN
D Jumlah A + B + C 90,712.50 104,585.00
E Overhead & Profit (contoh 10%) 10% 9,071.25 10,458.50
F Harga Satuan Pekerjaan (D+E) 99,783.75 115,043.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


10 A.4.4.1.10 1 m2 98,281.70 113,655.30
Tebal 1/2 Bata Camp. 1SP : 5PP

A Tenaga 29,675.00 34,025.00


L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 59,672.00 69,298.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
9.68 Kg Portland Semen 1,025.00 1,100.00 9,922.00 10,648.00
0.045 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 89,347.00 103,323.00
E Overhead & Profit (contoh 10%) 10% 8,934.70 10,332.30
F Harga Satuan Pekerjaan (D+E) 98,281.70 113,655.30

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


11 A.4.4.1.11 1 m2 97,848.30 113,637.70
Tebal 1/2 Bata Camp. 1SP : 6PP
A Tenaga 29,675.00 34,025.00
L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 59,278.00 69,282.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
8.32 Kg Portland Semen 1,025.00 1,100.00 8,528.00 9,152.00
0.049 m3 Pasir Pasang 250,000.00 370,000.00 12,250.00 18,130.00
C PERALATAN
D Jumlah A + B + C 88,953.00 103,307.00
E Overhead & Profit (contoh 10%) 10% 8,895.30 10,330.70
F Harga Satuan Pekerjaan (D+E) 97,848.30 113,637.70

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


12 A.4.4.1.12 1 m2 96,071.25 111,842.50
Tebal 1/2 Bata Camp. 1SP : 8PP
A Tenaga 29,675.00 34,025.00
L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 57,662.50 67,650.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
6.50 Kg Portland Semen 1,025.00 1,100.00 6,662.50 7,150.00
0.05 m3 Pasir Pasang 250,000.00 370,000.00 12,500.00 18,500.00

file:///conversion/tmp/scratch/457687078.xls 130/82 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 87,337.50 101,675.00
E Overhead & Profit (contoh 10%) 10% 8,733.75 10,167.50
F Harga Satuan Pekerjaan (D+E) 96,071.25 111,842.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


13 A.4.4.1.13 1 m2 98,766.25 114,537.50
Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP
A Tenaga 29,675.00 34,025.00
L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 60,112.50 70,100.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
4.5 Kg Portland Semen 1,025.00 1,100.00 4,612.50 4,950.00
0.05 m3 Pasir Pasang 250,000.00 370,000.00 12,500.00 18,500.00
0.015 m3 Kapur Padam 300,000.00 310,000.00 4,500.00 4,650.00
C PERALATAN
D Jumlah A + B + C 89,787.50 104,125.00
E Overhead & Profit (contoh 10%) 10% 8,978.75 10,412.50
F Harga Satuan Pekerjaan (D+E) 98,766.25 114,537.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


14 A.4.4.1.14 1 m2 89,545.50 101,051.50
Tebal 1/2 Bata Camp. 1SP : 1KP : 1PP
A Tenaga 29,675.00 34,025.00
L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 51,730.00 57,840.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
0.018 m3 Semen Merah 185,000.00 200,000.00 3,330.00 3,600.00
0.018 m3 Pasir Pasang 250,000.00 370,000.00 4,500.00 6,660.00
0.018 m3 Kapur Padam 300,000.00 310,000.00 5,400.00 5,580.00
C PERALATAN
D Jumlah A + B + C 81,405.00 91,865.00
E Overhead & Profit (contoh 10%) 10% 8,140.50 9,186.50
F Harga Satuan Pekerjaan (D+E) 89,545.50 101,051.50

Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm


15 A.4.4.1.15 1 m2 90,161.50 102,877.50
Tebal 1/2 Bata Camp. 1SM : 1KP : 2PP

A Tenaga 29,675.00 34,025.00


L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 52,290.00 59,500.00
70 Buah Bata Merah 5 x 11 x 22 550.00 600.00 38,500.00 42,000.00
0.014 m3 Semen Merah 185,000.00 200,000.00 2,590.00 2,800.00
0.028 m3 Pasir Pasang 250,000.00 370,000.00 7,000.00 10,360.00
0.014 m3 Kapur Padam 300,000.00 310,000.00 4,200.00 4,340.00
C PERALATAN
D Jumlah A + B + C 81,965.00 93,525.00
E Overhead & Profit (contoh 10%) 10% 8,196.50 9,352.50
F Harga Satuan Pekerjaan (D+E) 90,161.50 102,877.50

16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 334,012.80 442,322.10
A Tenaga 37,630.00 43,110.00
L.01 0.350 OH Pekerja 65,000.00 75,000.00 22,750.00 26,250.00
L.02 0.150 OH Tukang Batu 80,000.00 90,000.00 12,000.00 13,500.00
L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00
L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00

file:///conversion/tmp/scratch/457687078.xls 130/83 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 266,018.00 359,001.00
12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
30.320 kg PC 1,025.00 1,100.00 31,078.00 33,352.00
0.728 m3 Pasir Pasang 250,000.00 370,000.00 182,000.00 269,360.00
0.280 kg Besi Angkur Ø 8 mm 10,500.00 11,300.00 2,940.00 3,164.00
C PERALATAN
D Jumlah A + B + C 303,648.00 402,111.00
E Overhead & Profit (contoh 10%) 10% 30,364.80 40,211.10
F Harga Satuan Pekerjaan (D+E) 334,012.80 442,322.10

17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 339,280.15 452,897.50
A Tenaga 37,630.00 43,110.00
L.01 0.350 OH Pekerja 65,000.00 75,000.00 22,750.00 26,250.00
L.02 0.150 OH Tukang Batu 80,000.00 90,000.00 12,000.00 13,500.00
L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00
L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00

B Bahan 270,806.50 368,615.00


12.500 buah Batako 4,000.00 4,250.00 50,000.00 53,125.00
24.260 kg PC 1,025.00 1,100.00 24,866.50 26,686.00
0.772 m3 Pasir Pasang 250,000.00 370,000.00 193,000.00 285,640.00
0.280 kg Besi Angkur Ø 8 mm 10,500.00 11,300.00 2,940.00 3,164.00
C PERALATAN
D Jumlah A + B + C 308,436.50 411,725.00
E Overhead & Profit (contoh 10%) 10% 30,843.65 41,172.50
F Harga Satuan Pekerjaan (D+E) 339,280.15 452,897.50

18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 264,372.35 347,124.80
A Tenaga 32,840.00 37,640.00
L.01 0.320 OH Pekerja 65,000.00 75,000.00 20,800.00 24,000.00
L.02 0.120 OH Tukang Batu 80,000.00 90,000.00 9,600.00 10,800.00
L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00
L.04 0.016 OH Mandor 85,000.00 95,000.00 1,360.00 1,520.00
B Bahan 207,498.50 277,928.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,025.00 1,100.00 23,308.50 25,014.00
0.550 m3 Pasir Pasang 250,000.00 370,000.00 137,500.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 10,500.00 11,300.00 2,940.00 3,164.00
C PERALATAN
D Jumlah A + B + C 240,338.50 315,568.00
E Overhead & Profit (contoh 10%) 10% 24,033.85 31,556.80
F Harga Satuan Pekerjaan (D+E) 264,372.35 347,124.80

19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 268,053.50 354,655.40
A Tenaga 32,840.00 37,640.00
L.01 0.320 OH Pekerja 65,000.00 75,000.00 20,800.00 24,000.00
L.02 0.120 OH Tukang Batu 80,000.00 90,000.00 9,600.00 10,800.00
L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00
L.04 0.016 OH Mandor 85,000.00 95,000.00 1,360.00 1,520.00
B Bahan 210,845.00 284,774.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,025.00 1,100.00 18,655.00 20,020.00
0.582 m3 Pasir Pasang 250,000.00 370,000.00 145,500.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 10,500.00 11,300.00 2,940.00 3,164.00
C PERALATAN
D Jumlah A + B + C 243,685.00 322,414.00
E Overhead & Profit (contoh 10%) 10% 24,368.50 32,241.40
F Harga Satuan Pekerjaan (D+E) 268,053.50 354,655.40

20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 194,319.40 255,524.50
A Tenaga 29,675.00 34,025.00
L.01 0.300 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.100 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00

file:///conversion/tmp/scratch/457687078.xls 130/84 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 146,979.00 198,270.00
12.500 buah Batako 3,000.00 3,500.00 37,500.00 43,750.00
15.160 kg PC 1,025.00 1,100.00 15,539.00 16,676.00
0.364 m3 Pasir Pasang 250,000.00 370,000.00 91,000.00 134,680.00
0.280 kg Besi Angkur Ø 8 mm 10,500.00 11,300.00 2,940.00 3,164.00
C PERALATAN
D Jumlah A + B + C 176,654.00 232,295.00
E Overhead & Profit (contoh 10%) 10% 17,665.40 23,229.50
F Harga Satuan Pekerjaan (D+E) 194,319.40 255,524.50

21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 197,503.08 261,626.20
A Tenaga 29,675.00 34,025.00
L.01 0.300 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.100 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00

B Bahan 149,873.25 203,817.00


12.500 buah Batako 3,000.00 3,500.00 37,500.00 43,750.00
12.130 kg PC 1,025.00 1,100.00 12,433.25 13,343.00
0.388 m3 Pasir Pasang 250,000.00 370,000.00 97,000.00 143,560.00
0.280 kg Besi Angkur Ø 8 mm 10,500.00 11,300.00 2,940.00 3,164.00
C PERALATAN
D Jumlah A + B + C 179,548.25 237,842.00
E Overhead & Profit (contoh 10%) 10% 17,954.83 23,784.20
F Harga Satuan Pekerjaan (D+E) 197,503.08 261,626.20

Pemasangan Dinding Terawang (Rooster) Uk,


22 A.4.4.1.22 1 m2 417,670.00 460,982.50
(12x11x24)cm Camp. 1SP : 3PP

A Tenaga 29,675.00 34,025.00


L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 350,025.00 385,050.00
30 Buah Terawang / Roster 11,000.00 12,000.00 330,000.00 360,000.00
11 kg Portland Semen 1,025.00 1,100.00 11,275.00 12,100.00
0.035 m3 Pasir Pasang 250,000.00 370,000.00 8,750.00 12,950.00
C PERALATAN
D Jumlah A + B + C 379,700.00 419,075.00
E Overhead & Profit (contoh 10%) 10% 37,970.00 41,907.50
F Harga Satuan Pekerjaan (D+E) 417,670.00 460,982.50

Pemasangan Dinding Terawang (Rooster) Uk,


23 A.4.4.1.23 1 m2 417,670.00 460,982.50
(12x11x24)cm Camp. 1SP : 4PP

A Tenaga 29,675.00 34,025.00


L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 350,025.00 385,050.00
30 Buah Terawang / Roster 11,000.00 12,000.00 330,000.00 360,000.00
11 kg Portland Semen 1,025.00 1,100.00 11,275.00 12,100.00
0.035 m3 Pasir Pasang 250,000.00 370,000.00 8,750.00 12,950.00
C PERALATAN
D Jumlah A + B + C 379,700.00 419,075.00
E Overhead & Profit (contoh 10%) 10% 37,970.00 41,907.50
F Harga Satuan Pekerjaan (D+E) 417,670.00 460,982.50

Pemasangan Dinding Bata Berongga Ekspose Uk,


24 A.4.4.1.24 1 m2 134,227.50 148,241.50
(12x11x24)cm Camp. 1SP : 3PP
m2 Tenaga 29,675.00 34,025.00
L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00
L.02 0.1 OH Tukang Batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00

file:///conversion/tmp/scratch/457687078.xls 130/85 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
OH Bahan 92,350.00 100,740.00
70 Buah Bata Roster 1,000.00 1,050.00 70,000.00 73,500.00
14 kg Portland Semen 1,025.00 1,100.00 14,350.00 15,400.00
0.032 m3 Pasir Pasang 250,000.00 370,000.00 8,000.00 11,840.00
C PERALATAN
D Jumlah A + B + C 122,025.00 134,765.00
E Overhead & Profit (contoh 10%) 10% 12,202.50 13,476.50
F Harga Satuan Pekerjaan (D+E) 134,227.50 148,241.50

Pemasangan Dinding Bata Ringan Tebal 7,5 cm dengan


25 A.4.4.1.25 1 m2 120,061.04 131,285.06
Mortar Siap Pakai
m2 Tenaga 0.075 55,375.00 63,665.00
L.01 0.67 OH Pekerja 0.12 725000 65,000.00 75,000.00 43,550.00 50,250.00
L.02 0.13 OH Tukang Batu 1 6525 80,000.00 90,000.00 10,400.00 11,700.00
L.03 0.01 OH Kepala Tukang 13.3333333333 90,000.00 110,000.00 1,170.00 1,430.00
L.04 0.003 OH Mandor 111.1111111111 85,000.00 95,000.00 255.00 285.00
OH Bahan 53,771.40 55,685.05
8.40 Buah Bata Ringan Tebal 7,5 cm 90000 6,300.00 6,525.00 52,920.00 54,810.00
0.473 kg Mortar Siap Pakai 1,800.00 1,850.00 851.40 875.05

C PERALATAN
D Jumlah A + B + C 109,146.40 119,350.05
E Overhead & Profit (contoh 10%) 10% 10,914.64 11,935.01
F Harga Satuan Pekerjaan (D+E) 120,061.04 131,285.06

Pemasangan Dinding Bata Ringan Tebal 10 cm dengan


26 A.4.4.1.26 1 m2 137,338.74 147,858.21
Mortar Siap Pakai
m2 Tenaga 0.075 55,440.00 63,740.00
L.01 0.671 OH Pekerja 0.12 700000 65,000.00 75,000.00 43,615.00 50,325.00
L.02 0.130 OH Tukang Batu 0.1 8400 80,000.00 90,000.00 10,400.00 11,700.00
L.03 0.013 OH Kepala Tukang 10 90,000.00 110,000.00 1,170.00 1,430.00
L.04 0.003 OH Mandor 83.3333333333 85,000.00 95,000.00 255.00 285.00
OH Bahan 69,413.40 70,676.55
8.40 Buah Bata Ringan Tebal 10 cm 90000 8,250.00 8,400.00 69,300.00 70,560.00
0.063 kg Mortar Siap Pakai 1,800.00 1,850.00 113.40 116.55

C PERALATAN
D Jumlah A + B + C 124,853.40 134,416.55
E Overhead & Profit (contoh 10%) 10% 12,485.34 13,441.66
F Harga Satuan Pekerjaan (D+E) 137,338.74 147,858.21

file:///conversion/tmp/scratch/457687078.xls 130/86 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VII A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.4.2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 59,418.26 68,254.34
A Tenaga 34,125.00 39,075.00

L.01 0.3 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


B Bahan 19,891.60 22,974.40
15.504 Kg Portland Semen 1,025.00 1,100.00 15,891.60 17,054.40
0.016 m3 Pasir Pasang 250,000.00 370,000.00 4,000.00 5,920.00
C PERALATAN
D Jumlah A + B + C 54,016.60 62,049.40
E Overhead & Profit (contoh 10%) 10% 5,401.66 6,204.94
F Harga Satuan Pekerjaan (D+E) 59,418.26 68,254.34
Overhead & Profit (contoh 10%)
2 A.4.4.2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 54,565.06 63,493.54
A Tenaga 34,125.00 39,075.00

L.01 0.3 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


B Bahan 15,479.60 18,646.40
10.224 Kg Portland Semen 1,025.00 1,100.00 10,479.60 11,246.40
0.020 m3 Pasir Pasang 250,000.00 370,000.00 5,000.00 7,400.00
C PERALATAN
D Jumlah A + B + C 49,604.60 57,721.40
E Overhead & Profit (contoh 10%) 10% 4,960.46 5,772.14
F Harga Satuan Pekerjaan (D+E) 54,565.06 63,493.54

3 A.4.4.2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 52,629.94 61,752.46


A Tenaga 34,125.00 39,075.00

L.01 0.3 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


B Bahan 13,720.40 17,063.60
7.776 Kg Portland Semen 1,025.00 1,100.00 7,970.40 8,553.60
0.023 m3 Pasir Pasang 250,000.00 370,000.00 5,750.00 8,510.00
C PERALATAN
D Jumlah A + B + C 47,845.40 56,138.60
E Overhead & Profit (contoh 10%) 10% 4,784.54 5,613.86
F Harga Satuan Pekerjaan (D+E) 52,629.94 61,752.46

4 A.4.4.2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 51,173.10 60,300.90


A Tenaga 34,125.00 39,075.00

L.01 0.3 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


B Bahan 12,396.00 15,744.00
6.240 Kg Portland Semen 1,025.00 1,100.00 6,396.00 6,864.00
0.024 m3 Pasir Pasang 250,000.00 370,000.00 6,000.00 8,880.00
C PERALATAN
D Jumlah A + B + C 46,521.00 54,819.00
E Overhead & Profit (contoh 10%) 10% 4,652.10 5,481.90
F Harga Satuan Pekerjaan (D+E) 51,173.10 60,300.90

5 A.4.4.2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 50,532.46 59,837.14


A Tenaga 34,125.00 39,075.00

L.01 0.3 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


B Bahan 11,813.60 15,322.40
5.184 Kg Portland Semen 1,025.00 1,100.00 5,313.60 5,702.40
0.026 m3 Pasir Pasang 250,000.00 370,000.00 6,500.00 9,620.00
C PERALATAN
D Jumlah A + B + C 45,938.60 54,397.40
E Overhead & Profit (contoh 10%) 10% 4,593.86 5,439.74
F Harga Satuan Pekerjaan (D+E) 50,532.46 59,837.14

file:///conversion/tmp/scratch/457687078.xls 130/87 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 49,941.54 59,314.86
Tenaga 34,125.00 39,075.00

L.01 0.3 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


Bahan 11,276.40 14,847.60
4.416 Kg Portland Semen 1,025.00 1,100.00 4,526.40 4,857.60
0.027 m3 Pasir Pasang 250,000.00 370,000.00 6,750.00 9,990.00
C PERALATAN
D Jumlah A + B + C 45,401.40 53,922.60
E Overhead & Profit (contoh 10%) 10% 4,540.14 5,392.26
F Harga Satuan Pekerjaan (D+E) 49,941.54 59,314.86

7 A.4.4.2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 49,675.34 59,141.06


A Tenaga 34,125.00 39,075.00

L.01 0.3 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


B Bahan 11,034.40 14,689.60
3.936 Kg Portland Semen 1,025.00 1,100.00 4,034.40 4,329.60
0.028 m3 Pasir Pasang 250,000.00 370,000.00 7,000.00 10,360.00
C PERALATAN
D Jumlah A + B + C 45,159.40 53,764.60
E Overhead & Profit (contoh 10%) 10% 4,515.94 5,376.46
F Harga Satuan Pekerjaan (D+E) 49,675.34 59,141.06

8 A.4.4.2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 49,409.14 58,967.26


A Tenaga 34,125.00 39,075.00

L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


B Bahan 10,792.40 14,531.60
3.456 Kg Portland Semen 1,025.00 1,100.00 3,542.40 3,801.60
0.029 m3 Pasir Pasang 250,000.00 370,000.00 7,250.00 10,730.00
C PERALATAN
D Jumlah A + B + C 44,917.40 53,606.60
E Overhead & Profit (contoh 10%) 10% 4,491.74 5,360.66
F Harga Satuan Pekerjaan (D+E) 49,409.14 58,967.26

9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc :1/2 Kp:3 Pp Tebal 15 mm 50,230.40 58,196.60


A Tenaga 35,610.00 40,830.00

L.01 0.36 OH Pekerja 65,000.00 75,000.00 23,400.00 27,000.00

L.02 0.12 OH Tukang batu 80,000.00 90,000.00 9,600.00 10,800.00

L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00

L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00


B Bahan 10,054.00 12,076.00
5.760 Kg Portland Semen 1,025.00 1,100.00 5,904.00 6,336.00
0.003 m3 Kapur Pasang 300,000.00 310,000.00 900.00 930.00
0.013 m3 Pasir Pasang 250,000.00 370,000.00 3,250.00 4,810.00
C PERALATAN
D Jumlah A + B + C 45,664.00 52,906.00
E Overhead & Profit (contoh 10%) 10% 4,566.40 5,290.60
F Harga Satuan Pekerjaan (D+E) 50,230.40 58,196.60

10 A.4.4.2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 49,703.50 58,388.00


A Tenaga 35,610.00 40,830.00

L.01 0.36 OH Pekerja 65,000.00 75,000.00 23,400.00 27,000.00

L.02 0.12 OH Tukang batu 80,000.00 90,000.00 9,600.00 10,800.00

L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00

L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00


B Bahan 9,575.00 12,250.00
3 kg Portland Semen 1,025.00 1,100.00 3,075.00 3,300.00
0.005 m3 Kapur Padam 300,000.00 310,000.00 1,500.00 1,550.00
0.020 m3 Pasir Pasang 250,000.00 370,000.00 5,000.00 7,400.00
C PERALATAN
D Jumlah A + B + C 45,185.00 53,080.00
E Overhead & Profit (contoh 10%) 10% 4,518.50 5,308.00
F Harga Satuan Pekerjaan (D+E) 49,703.50 58,388.00

file:///conversion/tmp/scratch/457687078.xls 130/88 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.4.2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 46,447.50 53,625.00
A Tenaga 35,610.00 40,830.00

L.01 0.36 OH Pekerja 65,000.00 75,000.00 23,400.00 27,000.00

L.02 0.12 OH Tukang batu 80,000.00 90,000.00 9,600.00 10,800.00

L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00

L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00


B Bahan 6,615.00 7,920.00
0.009 m3 Semen Merah 185,000.00 200,000.00 1,665.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.009 m3 Pasir Pasang 250,000.00 370,000.00 2,250.00 3,330.00
C PERALATAN
D Jumlah A + B + C 42,225.00 48,750.00
E Overhead & Profit (contoh 10%) 10% 4,222.50 4,875.00
F Harga Satuan Pekerjaan (D+E) 46,447.50 53,625.00

12 A.4.4.2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 47,030.50 54,945.00


A Tenaga 35,610.00 40,830.00

L.01 0.36 OH Pekerja 65,000.00 75,000.00 23,400.00 27,000.00

L.02 0.12 OH Tukang batu 80,000.00 90,000.00 9,600.00 10,800.00

L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00

L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00


B Bahan 7,145.00 9,120.00
0.007 m3 Semen Merah 185,000.00 200,000.00 1,295.00 1,400.00
0.007 m3 Kapur Padam 300,000.00 310,000.00 2,100.00 2,170.00
0.015 m3 Pasir Pasang 250,000.00 370,000.00 3,750.00 5,550.00
C PERALATAN
D Jumlah A + B + C 42,755.00 49,950.00
E Overhead & Profit (contoh 10%) 10% 4,275.50 4,995.00
F Harga Satuan Pekerjaan (D+E) 47,030.50 54,945.00

13 A.4.4.2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 73,032.08 85,002.72


A Tenaga 45,670.00 52,290.00

L.01 0.40 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00

L.02 0.20 OH Tukang batu 80,000.00 90,000.00 16,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00

L.04 0.022 OH Mandor 85,000.00 95,000.00 1,870.00 2,090.00


B Bahan 20,722.80 24,985.20
13.632 kg Portland Semen 1,025.00 1,100.00 13,972.80 14,995.20
0.027 m3 Pasir Pasang 250,000.00 370,000.00 6,750.00 9,990.00
C PERALATAN
D Jumlah A + B + C 66,392.80 77,275.20
E Overhead & Profit (contoh 10%) 10% 6,639.28 7,727.52
F Harga Satuan Pekerjaan (D+E) 73,032.08 85,002.72

14 A.4.4.2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 54,182.20 63,809.80


A Tenaga 35,805.00 40,935.00
L.01 0.26 OH Pekerja 65,000.00 75,000.00 16,900.00 19,500.00
L.02 0.2 OH Tukang batu 80,000.00 90,000.00 16,000.00 18,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.013 OH Mandor 85,000.00 95,000.00 1,105.00 1,235.00
B Bahan 18,377.20 22,874.80
10.368 Kg Portland Semen 1,025.00 1,100.00 10,627.20 11,404.80
0.031 m3 Pasir Pasang 250,000.00 370,000.00 7,750.00 11,470.00
C PERALATAN
D Jumlah A + B + C 55,287.20 65,044.80
E Overhead & Profit (contoh 10%) 10% 5,528.72 6,504.48
F Harga Satuan Pekerjaan (D+E) 60,815.92 71,549.28

15 A.4.4.2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 68,417.80 80,610.20


A Tenaga 45,670.00 52,290.00

L.01 0.40 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00

L.02 0.20 OH Tukang batu 80,000.00 90,000.00 16,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00

L.04 0.022 OH Mandor 85,000.00 95,000.00 1,870.00 2,090.00


B Bahan 16,528.00 20,992.00
8.320 kg Portland Semen 1,025.00 1,100.00 8,528.00 9,152.00
0.032 m3 Pasir Pasang 250,000.00 370,000.00 8,000.00 11,840.00

file:///conversion/tmp/scratch/457687078.xls 130/89 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 62,198.00 73,282.00
E Overhead & Profit (contoh 10%) 10% 6,219.80 7,328.20
F Harga Satuan Pekerjaan (D+E) 68,417.80 80,610.20

16 A.4.4.2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 67,655.28 80,127.52


A Tenaga 45,670.00 52,290.00

L.01 0.400 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00

L.02 0.200 OH Tukang batu 80,000.00 90,000.00 16,000.00 18,000.00

L.03 0.020 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00

L.04 0.022 OH Mandor 85,000.00 95,000.00 1,870.00 2,090.00


B Bahan 15,834.80 20,553.20
6.912 Kg Portland Semen 1,025.00 1,100.00 7,084.80 7,603.20
0.035 m3 Pasir Pasang 250,000.00 370,000.00 8,750.00 12,950.00
C PERALATAN
D Jumlah A + B + C 61,504.80 72,843.20
E Overhead & Profit (contoh 10%) 10% 6,150.48 7,284.32
F Harga Satuan Pekerjaan (D+E) 67,655.28 80,127.52

17 A.4.4.2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 66,775.72 79,295.48


A Tenaga 45,670.00 52,290.00

L.01 0.40 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00

L.02 0.2 OH Tukang batu 80,000.00 90,000.00 16,000.00 18,000.00

L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00

L.04 0.022 OH Mandor 85,000.00 95,000.00 1,870.00 2,090.00


B Bahan 15,035.20 19,796.80
5.888 Kg Portland Semen 1,025.00 1,100.00 6,035.20 6,476.80
0.036 m3 Pasir Pasang 250,000.00 370,000.00 9,000.00 13,320.00
C PERALATAN
D Jumlah A + B + C 60,705.20 72,086.80
E Overhead & Profit (contoh 10%) 10% 6,070.52 7,208.68
F Harga Satuan Pekerjaan (D+E) 66,775.72 79,295.48

18 A.4.4.2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 64,806.50 75,416.00


A Tenaga 50,050.00 57,310.00

L.01 0.440 OH Pekerja 65,000.00 75,000.00 28,600.00 33,000.00

L.02 0.22 OH Tukang batu 80,000.00 90,000.00 17,600.00 19,800.00

L.03 0.022 OH Kepala Tukang 90,000.00 110,000.00 1,980.00 2,420.00

L.04 0.022 OH Mandor 85,000.00 95,000.00 1,870.00 2,090.00


B Bahan 8,865.00 11,250.00
0.009 m3 Semen Merah 185,000.00 200,000.00 1,665.00 1,800.00
0.009 m3 Kapur Padam 300,000.00 310,000.00 2,700.00 2,790.00
0.018 m3 Pasir Pasang 250,000.00 370,000.00 4,500.00 6,660.00
C PERALATAN
D Jumlah A + B + C 58,915.00 68,560.00
E Overhead & Profit (contoh 10%) 10% 5,891.50 6,856.00
F Harga Satuan Pekerjaan (D+E) 64,806.50 75,416.00

19 A.4.4.2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm 31,859.96 38,458.64


A Tenaga 17,150.00 19,640.00

L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00

L.02 0.075 OH Tukang batu 80,000.00 90,000.00 6,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 90,000.00 110,000.00 720.00 880.00

L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00


B Bahan 11,813.60 15,322.40
5.184 Kg Portland Semen 1,025.00 1,100.00 5,313.60 5,702.40
0.026 m3 Pasir Pasang 250,000.00 370,000.00 6,500.00 9,620.00
C PERALATAN
D Jumlah A + B + C 28,963.60 34,962.40
E Overhead & Profit (contoh 10%) 10% 2,896.36 3,496.24
F Harga Satuan Pekerjaan (D+E) 31,859.96 38,458.64

20 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 49,392.75 57,354.00

A Tenaga 41,140.00 46,780.00

L.01 0.080 OH Pekerja 65,000.00 75,000.00 5,200.00 6,000.00

L.02 0.40 OH Tukang batu 80,000.00 90,000.00 32,000.00 36,000.00

L.03 0.040 OH Kepala Tukang 90,000.00 110,000.00 3,600.00 4,400.00

L.04 0.004 OH Mandor 85,000.00 95,000.00 340.00 380.00

file:///conversion/tmp/scratch/457687078.xls 130/90 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 3,762.50 5,360.00
0.5 Kg Portland Semen 1,025.00 1,100.00 512.50 550.00
0.013 m3 Pasir Pasang 250,000.00 370,000.00 3,250.00 4,810.00
C PERALATAN
D Jumlah A + B + C 44,902.50 52,140.00
E Overhead & Profit (contoh 10%) 10% 4,490.25 5,214.00
F Harga Satuan Pekerjaan (D+E) 49,392.75 57,354.00

Pemasangan Plesteran Granit 1Pc : 2 Granit , Tebal 10


21 A.4.4.2.21 1 m' 84,177.50 94,836.50
mm
A Tenaga 51,275.00 58,715.00
L.01 0.450 OH Pekerja 65,000.00 75,000.00 29,250.00 33,750.00
L.02 0.225 OH Tukang batu 80,000.00 90,000.00 18,000.00 20,250.00
L.03 0.023 OH Kepala Tukang 90,000.00 110,000.00 2,070.00 2,530.00
L.04 0.023 OH Mandor 85,000.00 95,000.00 1,955.00 2,185.00
B Bahan 25,250.00 27,500.00
10 Kg Portland Semen 1,025.00 1,100.00 10,250.00 11,000.00
15 Kg Batu Granit 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 76,525.00 86,215.00
E Overhead & Profit (contoh 10%) 10% 7,652.50 8,621.50
F Harga Satuan Pekerjaan (D+E) 84,177.50 94,836.50

22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 84,177.50 94,836.50

A Tenaga 51,275.00 58,715.00


L.01 0.450 OH Pekerja 65,000.00 75,000.00 29,250.00 33,750.00
L.02 0.225 OH Tukang batu 80,000.00 90,000.00 18,000.00 20,250.00
L.03 0.023 OH Kepala Tukang 90,000.00 110,000.00 2,070.00 2,530.00
L.04 0.023 OH Mandor 85,000.00 95,000.00 1,955.00 2,185.00
B Bahan 25,250.00 27,500.00
10 Kg Portland Semen 1,025.00 1,100.00 10,250.00 11,000.00
15 m3 Batu Traso 1,000.00 1,100.00 15,000.00 16,500.00
C PERALATAN
D Jumlah A + B + C 76,525.00 86,215.00
E Overhead & Profit (contoh 10%) 10% 7,652.50 8,621.50
F Harga Satuan Pekerjaan (D+E) 84,177.50 94,836.50

23 A.4.4.2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp 39,163.30 45,096.70


Tenaga 29,675.00 34,025.00

L.01 0.30 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.1 OH Tukang batu 80,000.00 90,000.00 8,000.00 9,000.00

L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


Bahan 5,928.00 6,972.00
4.32 Kg Portland Semen 1,025.00 1,100.00 4,428.00 4,752.00
0.006 m3 Pasir Pasang 250,000.00 370,000.00 1,500.00 2,220.00
C PERALATAN
D Jumlah A + B + C 35,603.00 40,997.00
E Overhead & Profit (contoh 10%) 10% 3,560.30 4,099.70
F Harga Satuan Pekerjaan (D+E) 39,163.30 45,096.70

Pemasangan Finishing Siar Pasangan Dinding Bata


24 A.4.4.2.24 1 m2 22,369.27 25,364.68
Merah
A Tenaga 17,150.00 19,640.00

L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00

L.02 0.075 OH Tukang batu 80,000.00 90,000.00 6,000.00 6,750.00

L.03 0.008 OH Kepala Tukang 90,000.00 110,000.00 720.00 880.00

L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00


B Bahan 3,185.70 3,418.80
3.108 Kg Portland Semen 1,025.00 1,100.00 3,185.70 3,418.80
C PERALATAN
D Jumlah A + B + C 20,335.70 23,058.80
E Overhead & Profit (contoh 10%) 10% 2,033.57 2,305.88
F Harga Satuan Pekerjaan (D+E) 22,369.27 25,364.68

file:///conversion/tmp/scratch/457687078.xls 130/91 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Finishing Siar Pasangan Dinding Conblock
25 A.4.4.2.25 1 m2 10,659.00 12,078.00
ekspose
A Tenaga 8,050.00 9,220.00

L.01 0.070 OH Pekerja 65,000.00 75,000.00 4,550.00 5,250.00

L.02 0.035 OH Tukang batu 80,000.00 90,000.00 2,800.00 3,150.00

L.03 0.004 OH Kepala Tukang 90,000.00 110,000.00 360.00 440.00

L.04 0.004 OH Mandor 85,000.00 95,000.00 340.00 380.00


B Bahan 1,640.00 1,760.00
1.600 Kg Portland Semen 1,025.00 1,100.00 1,640.00 1,760.00
C PERALATAN
D Jumlah A + B + C 9,690.00 10,980.00
E Overhead & Profit (contoh 10%) 10% 969.00 1,098.00
F Harga Satuan Pekerjaan (D+E) 10,659.00 12,078.00

Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc :


26 A.4.4.2.26 1 m2 47,985.85 55,537.90
2Pp
Tenaga 34,125.00 39,075.00

L.01 0.3 OH Pekerja 65,000.00 75,000.00 19,500.00 22,500.00

L.02 0.15 OH Tukang batu 80,000.00 90,000.00 12,000.00 13,500.00

L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00

L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00


Bahan 9,498.50 11,414.00
6.34 Kg Portland Semen 1,025.00 1,100.00 6,498.50 6,974.00
0.012 m3 Pasir Pasang 250,000.00 370,000.00 3,000.00 4,440.00
C PERALATAN
D Jumlah A + B + C 43,623.50 50,489.00
E Overhead & Profit (contoh 10%) 10% 4,362.35 5,048.90
F Harga Satuan Pekerjaan (D+E) 47,985.85 55,537.90

27 A.4.4.2.27 1 m2 Pemasangan Acian 28,689.38 32,587.50

Tenaga 22,750.00 26,050.00


L.01 0.20 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.10 OH Tukang batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.010 OH Mandor 85,000.00 95,000.00 850.00 950.00
Bahan 3,331.25 3,575.00
3.25 Kg Portland Semen 1,025.00 1,100.00 3,331.25 3,575.00
C PERALATAN
D Jumlah A + B + C 26,081.25 29,625.00
E Overhead & Profit (contoh 10%) 10% 2,608.13 2,962.50
F Harga Satuan Pekerjaan (D+E) 28,689.38 32,587.50

28 A.4.4.2.28 1 m2 Pemasangan Plesteran dg Mortar Siap Pakai (MSP) 37,578.20 41,556.90

Tenaga 22,750.00 26,050.00


L.01 0.20 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.10 OH Tukang batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.010 OH Mandor 85,000.00 95,000.00 850.00 950.00
Bahan 11,412.00 11,729.00
6.34 Kg Portland Semen 1,800.00 1,850.00 11,412.00 11,729.00
C PERALATAN
D Jumlah A + B + C 34,162.00 37,779.00
E Overhead & Profit (contoh 10%) 10% 3,416.20 3,777.90
F Harga Satuan Pekerjaan (D+E) 37,578.20 41,556.90

29 A.4.4.2.29 1 m2 Pemasangan Acian dg Mortar Siap Pakai (MSP) 31,460.00 35,268.75

Tenaga 22,750.00 26,050.00


L.01 0.20 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.10 OH Tukang batu 80,000.00 90,000.00 8,000.00 9,000.00
L.03 0.010 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.010 OH Mandor 85,000.00 95,000.00 850.00 950.00
Bahan 5,850.00 6,012.50
3.25 Kg Mortar Siap Pakai 1,800.00 1,850.00 5,850.00 6,012.50
C PERALATAN
D Jumlah A + B + C 28,600.00 32,062.50
E Overhead & Profit (contoh 10%) 10% 2,860.00 3,206.25
F Harga Satuan Pekerjaan (D+E) 31,460.00 35,268.75

file:///conversion/tmp/scratch/457687078.xls 130/92 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan


VIII A.4.4.3
DINDING

1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm 95,385.50 109,766.00


A Tenaga 28,525.00 33,290.00
L.01 0.25 OH Pekerja 65,000.00 75,000.00 16,250.00 18,750.00
L.02 0.125 OH Tukang Batu 80,000.00 95,000.00 10,000.00 11,875.00
L.03 0.013 OH Kepala Tukang 90,000.00 110,000.00 1,170.00 1,430.00
L.04 0.013 OH Mandor 85,000.00 95,000.00 1,105.00 1,235.00
B Bahan 58,189.09 66,497.27
11.87 Buah Ubin Abu-abu 30x30 cm 11.1111 3,090.91 3,272.73 36,689.09 38,847.27
10.0 Kg Portland Semen 0.3 1,025.00 1,100.00 10,250.00 11,000.00
0.0450 m3 Pasir Pasang 0.09 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 86,714.09 99,787.27
E Overhead & Profit (contoh 10%) 10% 8,671.41 9,978.73
F Harga Satuan Pekerjaan (D+E) 95,385.50 109,766.00

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm 95,293.00 110,082.50


A Tenaga 30,800.00 35,945.00
L.01 0.27 OH Pekerja 65,000.00 75,000.00 17,550.00 20,250.00
L.02 0.135 OH Tukang Batu 80,000.00 95,000.00 10,800.00 12,825.00
L.03 0.014 OH Kepala Tukang 90,000.00 110,000.00 1,260.00 1,540.00
L.04 0.014 OH Mandor 85,000.00 95,000.00 1,190.00 1,330.00
B Bahan 55,830.00 64,130.00
26.5 Buah Ubin Abu-abu 20x20 cm 1,280.00 1,360.00 33,920.00 36,040.00
10.4 Kg Portland Semen 1,025.00 1,100.00 10,660.00 11,440.00
0.0450 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 86,630.00 100,075.00
E Overhead & Profit (contoh 10%) 10% 8,663.00 10,007.50
F Harga Satuan Pekerjaan (D+E) 95,293.00 110,082.50

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm 121,812.50 142,783.50


A Tenaga 29,575.00 34,515.00
L.01 0.26 OH Pekerja 65,000.00 75,000.00 16,900.00 19,500.00
L.02 0.130 OH Tukang Batu 80,000.00 95,000.00 10,400.00 12,350.00
L.03 0.013 OH Kepala Tukang 90,000.00 110,000.00 1,170.00 1,430.00
L.04 0.013 OH Mandor 85,000.00 95,000.00 1,105.00 1,235.00
B Bahan 81,163.64 95,288.18
11.87 Buah Ubin Warna 30x30 cm 3,636.36 4,181.82 43,163.64 49,638.18
10.0 Kg Portland Semen 1,025.00 1,100.00 10,250.00 11,000.00
1.50 Kg Semen warna 11,000.00 12,000.00 16,500.00 18,000.00
0.0450 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 110,738.64 129,803.18
E Overhead & Profit (contoh 10%) 10% 11,073.86 12,980.32
F Harga Satuan Pekerjaan (D+E) 121,812.50 142,783.50

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm 124,223.00 140,794.50


A Tenaga 30,800.00 35,945.00
L.01 0.27 OH Pekerja 65,000.00 75,000.00 17,550.00 20,250.00
L.02 0.135 OH Tukang Batu 80,000.00 95,000.00 10,800.00 12,825.00
L.03 0.014 OH Kepala Tukang 90,000.00 110,000.00 1,260.00 1,540.00
L.04 0.014 OH Mandor 85,000.00 95,000.00 1,190.00 1,330.00
B Bahan 82,130.00 92,050.00
26.5 Buah Ubin Warna 20x20 cm 1,600.00 1,680.00 42,400.00 44,520.00
10.4 Kg Portland Semen 1,025.00 1,100.00 10,660.00 11,440.00
1.62 Kg Semen warna 11,000.00 12,000.00 17,820.00 19,440.00
0.0450 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 112,930.00 127,995.00
E Overhead & Profit (contoh 10%) 10% 11,293.00 12,799.50

F Harga Satuan Pekerjaan (D+E) 124,223.00 140,794.50


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 337,942.00 387,827.00
A Tenaga 28,525.00 33,290.00
L.01 0.250 OH Pekerja 65,000.00 75,000.00 16,250.00 18,750.00
L.02 0.125 OH Tukang Batu 80,000.00 95,000.00 10,000.00 11,875.00
L.03 0.013 OH Kepala Tukang 90,000.00 110,000.00 1,170.00 1,430.00
L.04 0.013 OH Mandor 85,000.00 95,000.00 1,105.00 1,235.00
B Bahan 278,695.00 319,280.00
6.63 Buah Ubin Granito 40x40 cm 0.4 36,666.67 41,666.67 243,100.00 276,250.00
9.8 Kg Portland Semen 0.16 1,025.00 1,100.00 10,045.00 10,780.00
1.300 Kg Semen warna 6.25 11,000.00 12,000.00 14,300.00 15,600.00
0.045 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 307,220.00 352,570.00
E Overhead & Profit (contoh 10%) 10% 30,722.00 35,257.00
F Harga Satuan Pekerjaan (D+E) 337,942.00 387,827.00

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm 59,219.60 73,236.90

A Tenaga 14,285.00 16,765.00


L.01 0.090 OH Pekerja 65,000.00 75,000.00 5,850.00 6,750.00
L.02 0.090 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 39,551.00 49,814.00
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 5,100.00 6,000.00 27,030.00 31,800.00
1.2 Kg Portland Semen 1,025.00 1,100.00 1,271.00 1,364.00
0.045 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 53,836.00 66,579.00
E Overhead & Profit (contoh 10%) 10% 5,383.60 6,657.90
F Harga Satuan Pekerjaan (D+E) 59,219.60 73,236.90

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm 34,191.85 38,394.40


A Tenaga 14,285.00 16,765.00
L.01 0.090 OH Pekerja 65,000.00 75,000.00 5,850.00 6,750.00
L.02 0.090 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 16,798.50 18,139.00
2.65 Buah Ubin Plin Pc SWarna 15x20 cm 5,200.00 5,500.00 13,780.00 14,575.00
1.14 Kg Portland Semen 1,025.00 1,100.00 1,168.50 1,254.00
0.100 Kg Semen Warna 11,000.00 12,000.00 1,100.00 1,200.00
0.003 m3 Pasir Pasang 250,000.00 370,000.00 750.00 1,110.00
C PERALATAN
D Jumlah A + B + C 31,083.50 34,904.00
E Overhead & Profit (contoh 10%) 10% 3,108.35 3,490.40
F Harga Satuan Pekerjaan (D+E) 34,191.85 38,394.40

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 183,281.73 230,872.40


A Tenaga 79,625.00 92,925.00
L.01 0.70 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 0.350 OH Tukang Batu 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 86,994.75 116,959.00
53.00 Buah Keramik 10 x 20 cm 700.00 1,100.00 37,100.00 58,300.00
8.19 Kg Portland Semen 1,025.00 1,100.00 8,394.75 9,009.00
2.75 Kg Semen Warna 11,000.00 12,000.00 30,250.00 33,000.00
0.0450 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00

C PERALATAN
D Jumlah A + B + C 166,619.75 209,884.00
E Overhead & Profit (contoh 10%) 10% 16,661.98 20,988.40
F Harga Satuan Pekerjaan (D+E) 183,281.73 230,872.40
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 188,726.73 236,812.40
A Tenaga 79,625.00 92,925.00
L.01 0.70 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 0.350 OH Tukang Batu 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 91,944.75 122,359.00
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 350.00 550.00 37,100.00 58,300.00
8.19 Kg Portland Semen 1,025.00 1,100.00 8,394.75 9,009.00
3.20 Kg Semen Warna 11,000.00 12,000.00 35,200.00 38,400.00
0.0450 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 171,569.75 215,284.00
E Overhead & Profit (contoh 10%) 10% 17,156.98 21,528.40
F Harga Satuan Pekerjaan (D+E) 188,726.73 236,812.40

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 192,354.28 225,159.73


A Tenaga 79,625.00 92,925.00
L.01 0.70 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 0.35 OH Tukang Batu 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 95,242.53 111,765.67
10 Buah Ubin Keramik 33 x 33 cm 5,777.78 6,666.67 57,777.78 66,666.67
8.19 Kg Portland Semen 1,025.00 1,100.00 8,394.75 9,009.00

0.045 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00


1.62 Kg Semen Warna 11,000.00 12,000.00 17,820.00 19,440.00
C PERALATAN
D Jumlah A + B + C 174,867.53 204,690.67
E Overhead & Profit (contoh 10%) 10% 17,486.75 20,469.07
F Harga Satuan Pekerjaan (D+E) 192,354.28 225,159.73

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 182,802.50 220,091.50


A Tenaga 79,625.00 92,925.00
L.01 0.70 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 0.35 OH Tukang Batu 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 86,559.09 107,158.18
11.87 Buah Ubin Keramik 30 x 30 cm 4,090.91 5,181.82 48,559.09 61,508.18
10.00 Kg Portland Semen 1,025.00 1,100.00 10,250.00 11,000.00
0.045 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
1.50 Kg Semen Warna 11,000.00 12,000.00 16,500.00 18,000.00
C PERALATAN
D Jumlah A + B + C 166,184.09 200,083.18
E Overhead & Profit (contoh 10%) 10% 16,618.41 20,008.32
F Harga Satuan Pekerjaan (D+E) 182,802.50 220,091.50

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 191,922.50 219,796.50


A Tenaga 79,625.00 92,925.00
L.01 0.70 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 0.35 OH Tukang Batu 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 94,850.00 106,890.00
26.5 Buah Ubin Keramik 20 x 20 cm 2,080.00 2,240.00 55,120.00 59,360.00
10.40 Kg Portland Semen 1,025.00 1,100.00 10,660.00 11,440.00
1.62 Kg Semen Warna 11,000.00 12,000.00 17,820.00 19,440.00
0.045 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 174,475.00 199,815.00
E Overhead & Profit (contoh 10%) 10% 17,447.50 19,981.50
F Harga Satuan Pekerjaan (D+E) 191,922.50 219,796.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Lantai Keramik uk.10 x 33 cm, untuk
13 A.4.4.3.37 1 m2 387,596.00 428,175.00
variasi / border
A Tenaga 117,995.00 137,780.00
L.01 1.05 OH Pekerja 65,000.00 75,000.00 68,250.00 78,750.00
L.02 0.525 OH Tukang Batu 80,000.00 95,000.00 42,000.00 49,875.00
L.03 0.053 OH Kepala Tukang 90,000.00 110,000.00 4,770.00 5,830.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 234,365.00 251,470.00
33.0 Buah Ubin Keramik 5,000.00 5,200.00 165,000.00 171,600.00
9.80 Kg Portland Semen 1,025.00 1,100.00 10,045.00 10,780.00
4.37 Kg Semen Warna 11,000.00 12,000.00 48,070.00 52,440.00
0.045 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
C PERALATAN
D Jumlah A + B + C 352,360.00 389,250.00
E Overhead & Profit (contoh 10%) 10% 35,236.00 38,925.00
F Harga Satuan Pekerjaan (D+E) 387,596.00 428,175.00

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 32,701.35 38,861.90


A Tenaga 14,285.00 16,765.00
L.01 0.09 OH Pekerja 65,000.00 75,000.00 5,850.00 6,750.00
L.02 0.09 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 15,443.50 18,564.00
5.3 Buah Ubin Keramik 2,500.00 3,000.00 13,250.00 15,900.00
1.14 Kg Portland Semen 1,025.00 1,100.00 1,168.50 1,254.00
0.003 m3 Pasir Pasang 250,000.00 370,000.00 750.00 1,110.00
0.025 Kg Semen Warna 11,000.00 12,000.00 275.00 300.00
C PERALATAN
D Jumlah A + B + C 29,728.50 35,329.00
E Overhead & Profit (contoh 10%) 10% 2,972.85 3,532.90
F Harga Satuan Pekerjaan (D+E) 32,701.35 38,861.90

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 79,060.85 85,831.90


A Tenaga 14,285.00 16,765.00
L.01 0.09 OH Pekerja 65,000.00 75,000.00 5,850.00 6,750.00
L.02 0.09 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 57,588.50 61,264.00
10.6 Buah Ubin Keramik 5,200.00 5,500.00 55,120.00 58,300.00
1.14 Kg Portland Semen 1,025.00 1,100.00 1,168.50 1,254.00
0.003 m3 Pasir Pasang 250,000.00 370,000.00 750.00 1,110.00
0.05 Kg Semen Warna 11,000.00 12,000.00 550.00 600.00
C PERALATAN
D Jumlah A + B + C 71,873.50 78,029.00
E Overhead & Profit (contoh 10%) 10% 7,187.35 7,802.90
F Harga Satuan Pekerjaan (D+E) 79,060.85 85,831.90

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 76,728.85 84,665.90


A Tenaga 14,285.00 16,765.00
L.01 0.09 OH Pekerja 65,000.00 75,000.00 5,850.00 6,750.00
L.02 0.09 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 55,468.50 60,204.00
10.6 Buah Ubin Keramik 5,000.00 5,400.00 53,000.00 57,240.00
1.14 Kg Portland Semen 1,025.00 1,100.00 1,168.50 1,254.00
0.003 m3 Pasir Pasang 250,000.00 370,000.00 750.00 1,110.00
0.05 Kg Semen Warna 11,000.00 12,000.00 550.00 600.00
C PERALATAN
D Jumlah A + B + C 69,753.50 76,969.00
E Overhead & Profit (contoh 10%) 10% 6,975.35 7,696.90
F Harga Satuan Pekerjaan (D+E) 76,728.85 84,665.90
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 670,911.73 698,702.40
A Tenaga 79,625.00 92,925.00
L.01 0.7 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 0.35 OH Tukang Batu 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 530,294.75 542,259.00
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
8.19 kg Portland Semen 1,025.00 1,100.00 8,394.75 9,009.00
0.045 m3 Pasir Pasang 250,000.00 370,000.00 11,250.00 16,650.00
0.65 kg Semen Warna 11,000.00 12,000.00 7,150.00 7,800.00
C PERALATAN
D Jumlah A + B + C 609,919.75 635,184.00
E Overhead & Profit (contoh 10%) 10% 60,991.98 63,518.40
F Harga Satuan Pekerjaan (D+E) 670,911.73 698,702.40

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 195,189.50 209,962.50


A Tenaga 26,945.00 31,625.00
L.01 0.17 OH Pekerja 65,000.00 75,000.00 11,050.00 12,750.00
L.02 0.17 OH Tukang Batu 80,000.00 95,000.00 13,600.00 16,150.00
L.03 0.017 OH Kepala Tukang 90,000.00 110,000.00 1,530.00 1,870.00
L.04 0.009 OH Mandor 85,000.00 95,000.00 765.00 855.00
B Bahan 150,500.00 159,250.00
1.05 m2 Karpet 125,000.00 130,000.00 131,250.00 136,500.00
0.35 kg Lem 55,000.00 65,000.00 19,250.00 22,750.00
C PERALATAN
D Jumlah A + B + C 177,445.00 190,875.00
E Overhead & Profit (contoh 10%) 10% 17,744.50 19,087.50
F Harga Satuan Pekerjaan (D+E) 195,189.50 209,962.50

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 366,437.50 503,167.50


A Tenaga 79,625.00 92,925.00
L.01 0.70 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 0.35 OH Tukang Batu 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 253,500.00 364,500.00
1.05 m2 Parquet Jati 210,000.00 310,000.00 220,500.00 325,500.00
0.6 Kg Lem Vynil 55,000.00 65,000.00 33,000.00 39,000.00
C PERALATAN
D Jumlah A + B + C 333,125.00 457,425.00
E Overhead & Profit (contoh 10%) 10% 33,312.50 45,742.50
F Harga Satuan Pekerjaan (D+E) 366,437.50 503,167.50

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 222,289.41 250,511.32


A Tenaga 113,750.00 132,750.00
L.01 1.00 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 0.50 OH Tukang Batu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.050 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.050 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan 88,331.28 94,987.56
86 bh Porselen 512.20 524.39 44,048.78 45,097.56
9.30 Kg Portland Semen 82.6446 1,025.00 1,100.00 9,532.50 10,230.00

2.750 Kg Semen Warna 0.0121 11,000.00 12,000.00 30,250.00 33,000.00

0.018 m3 Pasir Pasang 0.11 250,000.00 370,000.00 4,500.00 6,660.00


C PERALATAN
D Jumlah A + B + C 202,081.28 227,737.56
E Overhead & Profit (contoh 10%) 10% 20,208.13 22,773.76
F Harga Satuan Pekerjaan (D+E) 222,289.41 250,511.32

21 A.4.4.3.49 1 m2 Pemasangan Dinding Porselen 10x20 cm, 202,133.25 250,431.50


A Tenaga 102,375.00 119,475.00
L.01 0.9 OH Pekerja 65,000.00 75,000.00 58,500.00 67,500.00
L.02 0.45 OH Tukang Batu 80,000.00 95,000.00 36,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 90,000.00 110,000.00 4,050.00 4,950.00
L.04 0.045 OH Mandor 85,000.00 95,000.00 3,825.00 4,275.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 81,382.50 108,190.00
53 Buah Keramik 700.00 1,100.00 37,100.00 58,300.00
9.3 Kg Portland Semen 1,025.00 1,100.00 9,532.50 10,230.00
0.018 m3 Pasir Pasang 250,000.00 370,000.00 4,500.00 6,660.00
2.75 Kg Semen Warna 11,000.00 12,000.00 30,250.00 33,000.00
C PERALATAN
D Jumlah A + B + C 183,757.50 227,665.00
E Overhead & Profit (contoh 10%) 10% 18,375.75 22,766.50
F Harga Satuan Pekerjaan (D+E) 202,133.25 250,431.50

22 A.4.4.3.50 1 m2 Pemasangan Dinding Porselen 20x20 cm, 211,010.25 244,249.50


A Tenaga 102,375.00 119,475.00
L.01 0.9 OH Pekerja 65,000.00 75,000.00 58,500.00 67,500.00
L.02 0.45 OH Tukang Batu 80,000.00 95,000.00 36,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 90,000.00 110,000.00 4,050.00 4,950.00
L.04 0.045 OH Mandor 85,000.00 95,000.00 3,825.00 4,275.00
B Bahan 89,452.50 102,570.00
26.0 Buah Keramik 2,080.00 2,400.00 54,080.00 62,400.00
9.3 Kg Portland Semen 1,025.00 1,100.00 9,532.50 10,230.00
0.018 m3 Pasir Pasang 250,000.00 370,000.00 4,500.00 6,660.00
1.94 Kg Semen Warna 11,000.00 12,000.00 21,340.00 23,280.00
C PERALATAN
D Jumlah A + B + C 191,827.50 222,045.00
E Overhead & Profit (contoh 10%) 10% 19,182.75 22,204.50
F Harga Satuan Pekerjaan (D+E) 211,010.25 244,249.50

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm, 202,133.25 250,431.50


A Tenaga 102,375.00 119,475.00
L.01 0.9 OH Pekerja 65,000.00 75,000.00 58,500.00 67,500.00
L.02 0.45 OH Tukang Batu 80,000.00 95,000.00 36,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 90,000.00 110,000.00 4,050.00 4,950.00
L.04 0.045 OH Mandor 85,000.00 95,000.00 3,825.00 4,275.00
B Bahan 81,382.50 108,190.00
53.0 Buah Keramik 700.00 1,100.00 37,100.00 58,300.00
9.3 Kg Portland Semen 1,025.00 1,100.00 9,532.50 10,230.00
0.018 m3 Pasir Pasang 250,000.00 370,000.00 4,500.00 6,660.00
2.75 Kg Semen Warna 11,000.00 12,000.00 30,250.00 33,000.00
C PERALATAN
D Jumlah A + B + C 183,757.50 227,665.00
E Overhead & Profit (contoh 10%) 10% 18,375.75 22,766.50
F Harga Satuan Pekerjaan (D+E) 202,133.25 250,431.50

24 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm, 212,154.25 245,569.50


A Tenaga 102,375.00 119,475.00
L.01 0.9 OH Pekerja 65,000.00 75,000.00 58,500.00 67,500.00
L.02 0.45 OH Tukang Batu 80,000.00 95,000.00 36,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 90,000.00 110,000.00 4,050.00 4,950.00
L.04 0.045 OH Mandor 85,000.00 95,000.00 3,825.00 4,275.00
B Bahan 90,492.50 103,770.00
26.5 Buah Keramik 2,080.00 2,400.00 55,120.00 63,600.00
9.3 Kg Portland Semen 1,025.00 1,100.00 9,532.50 10,230.00
0.018 m3 Pasir Pasang 250,000.00 370,000.00 4,500.00 6,660.00
1.94 Kg Semen Warna 11,000.00 12,000.00 21,340.00 23,280.00
C PERALATAN
D Jumlah A + B + C 192,867.50 223,245.00
E Overhead & Profit (contoh 10%) 10% 19,286.75 22,324.50
F Harga Satuan Pekerjaan (D+E) 212,154.25 245,569.50

25 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 745,394.22 783,435.52


A Tenaga 147,875.00 172,575.00
L.01 1.3 OH Pekerja 65,000.00 75,000.00 84,500.00 97,500.00
L.02 0.65 OH Tukang Batu 80,000.00 95,000.00 52,000.00 61,750.00
L.03 0.065 OH Kepala Tukang 90,000.00 110,000.00 5,850.00 7,150.00
L.04 0.065 OH Mandor 85,000.00 95,000.00 5,525.00 6,175.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 529,756.11 539,639.11
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
3.003 buah Paku 12 cm 35.00 35.00 105.11 105.11
12.44 kg Portlan Semen 1,025.00 1,100.00 12,751.00 13,684.00
0.025 m3 Pasir Pasang 250,000.00 370,000.00 6,250.00 9,250.00
0.65 kg Semen Warna 11,000.00 12,000.00 7,150.00 7,800.00
C PERALATAN
D Jumlah A + B + C 677,631.11 712,214.11
E Overhead & Profit (contoh 10%) 10% 67,763.11 71,221.41
F Harga Satuan Pekerjaan (D+E) 745,394.22 783,435.52

26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 243,560.63 269,830.00
A Tenaga 79,625.00 92,925.00
L.01 0.70 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 0.35 OH Tukang Batu 80,000.00 95,000.00 28,000.00 33,250.00
L.03 0.035 OH Kepala Tukang 90,000.00 110,000.00 3,150.00 3,850.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 141,793.75 152,375.00
1.10 m2 Batu Paros 110,000.00 115,000.00 121,000.00 126,500.00
11.75 Kg Portland Semen 1,025.00 1,100.00 12,043.75 12,925.00
0.035 m3 Pasir Pasang 250,000.00 370,000.00 8,750.00 12,950.00
C PERALATAN
D Jumlah A + B + C 221,418.75 245,300.00
E Overhead & Profit (contoh 10%) 10% 22,141.88 24,530.00
F Harga Satuan Pekerjaan (D+E) 243,560.63 269,830.00

27 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 138,373.40 152,174.00


A Tenaga 38,450.00 44,935.00
L.01 0.35 OH Pekerja 65,000.00 75,000.00 22,750.00 26,250.00
L.02 0.175 OH Tukang Batu 80,000.00 95,000.00 14,000.00 16,625.00
L.03 0.017 OH Kepala Tukang 90,000.00 110,000.00 1,530.00 1,870.00
L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00
B Bahan 87,344.00 93,405.00
11.87 bh Vynil 30x30cm 6,200.00 6,500.00 73,594.00 77,155.00
0.25 kg Lem 55,000.00 65,000.00 13,750.00 16,250.00

C PERALATAN
D Jumlah A + B + C 125,794.00 138,340.00
E Overhead & Profit (contoh 10%) 10% 12,579.40 13,834.00
F Harga Satuan Pekerjaan (D+E) 138,373.40 152,174.00

28 A.4.4.3.60 1 m2 Pemasangan Wallpaper Lebar 50 Cm 108,240.00 118,068.50


A Tenaga 38,450.00 44,935.00
L.01 0.35 OH Pekerja 65,000.00 75,000.00 22,750.00 26,250.00
L.02 0.175 OH Tukang Batu 80,000.00 95,000.00 14,000.00 16,625.00
L.03 0.017 OH Kepala Tukang 90,000.00 110,000.00 1,530.00 1,870.00
L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00
B Bahan 59,950.00 62,400.00
2.2 m' Wallpaper 26,000.00 27,000.00 57,200.00 59,400.00
0.25 kg Lem 11,000.00 12,000.00 2,750.00 3,000.00
C PERALATAN
D Jumlah A + B + C 98,400.00 107,335.00
E Overhead & Profit (contoh 10%) 10% 9,840.00 10,733.50
F Harga Satuan Pekerjaan (D+E) 108,240.00 118,068.50

29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 42,339.00 48,499.00
Tenaga 18,990.00 22,290.00
L.01 0.12 OH Pekerja 65,000.00 75,000.00 7,800.00 9,000.00
L.02 0.12 OH Tukang Batu 80,000.00 95,000.00 9,600.00 11,400.00
L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
Bahan 19,500.00 21,800.00
0.003 m3 Papan Kayu Klas II 6,250,000.00 7,000,000.00 18,750.00 21,000.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 38,490.00 44,090.00
E Overhead & Profit (contoh 10%) 10% 3,849.00 4,409.00
F Harga Satuan Pekerjaan (D+E) 42,339.00 48,499.00

30 A.4.4.3.64 1 m2 Pemasangan Paving Block Natural Tebal 6 Cm 137,005.55 164,305.35


Tenaga 60,860.50 71,873.50
L.01 0.25 OH Pekerja 65,000.00 75,000.00 16,250.00 18,750.00
L.02 0.5 OH Tukang Batu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.0013 OH Mandor 85,000.00 95,000.00 110.50 123.50
Bahan 57,900.00 70,450.00
1.01 m2 Paving Block Tebal 6 Cm 40,000.00 45,000.00 40,400.00 45,450.00
0.05 m3 Pasir Beton 350,000.00 500,000.00 17,500.00 25,000.00
C PERALATAN 5,790.00 7,045.00
10 % Peralatan 57,900.00 70,450.00 5,790.00 7,045.00
D Jumlah A + B + C 124,550.50 149,368.50
E Overhead & Profit (contoh 10%) 10% 12,455.05 14,936.85
F Harga Satuan Pekerjaan (D+E) 137,005.55 164,305.35

31 A.4.4.3.65 1 m2 Pemasangan Paving Block Natural Tebal 8 Cm 206,124.05 239,803.85


Tenaga 77,110.50 90,623.50
L.01 0.5 OH Pekerja 65,000.00 75,000.00 32,500.00 37,500.00
L.02 0.5 OH Tukang Batu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.0013 OH Mandor 85,000.00 95,000.00 110.50 123.50
Bahan 100,250.00 115,800.00
1.01 m2 Paving Block Tebal 8 Cm 75,000.00 80,000.00 75,750.00 80,800.00
0.07 m3 Pasir Beton 350,000.00 500,000.00 24,500.00 35,000.00
C PERALATAN 10,025.00 11,580.00
10 % Peralatan 100,250.00 115,800.00 10,025.00 11,580.00
D Jumlah A + B + C 187,385.50 218,003.50
E Overhead & Profit (contoh 10%) 10% 18,738.55 21,800.35
F Harga Satuan Pekerjaan (D+E) 206,124.05 239,803.85

32 A.4.4.3.66 1 m2 Pemasangan Paving Block Berwarna Tebal 6 Cm 143,116.05 170,415.85


Tenaga 60,860.50 71,873.50
L.01 0.25 OH Pekerja 65,000.00 75,000.00 16,250.00 18,750.00
L.02 0.5 OH Tukang Batu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.0013 OH Mandor 85,000.00 95,000.00 110.50 123.50
Bahan 62,950.00 75,500.00
1.01 m2 Paving Block Berwarna Tebal 6 Cm 45,000.00 50,000.00 45,450.00 50,500.00
0.05 m3 Pasir Beton 350,000.00 500,000.00 17,500.00 25,000.00
C PERALATAN 6,295.00 7,550.00
10 % Peralatan 62,950.00 75,500.00 6,295.00 7,550.00
D Jumlah A + B + C 130,105.50 154,923.50
E Overhead & Profit (contoh 10%) 10% 13,010.55 15,492.35
F Harga Satuan Pekerjaan (D+E) 143,116.05 170,415.85

33 A.4.4.3.67 1 m2 Pemasangan Paving Block Berwarna Tebal 8 Cm 218,345.05 252,024.85


Tenaga 77,110.50 90,623.50
L.01 0.5 OH Pekerja 65,000.00 75,000.00 32,500.00 37,500.00
L.02 0.5 OH Tukang Batu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.0013 OH Mandor 85,000.00 95,000.00 110.50 123.50
Bahan 110,350.00 125,900.00
1.01 m2 Paving Block Tebal Berwarna 8 Cm 85,000.00 90,000.00 85,850.00 90,900.00
0.07 m3 Pasir Beton 350,000.00 500,000.00 24,500.00 35,000.00
C PERALATAN 11,035.00 12,590.00
10 % Peralatan 110,350.00 125,900.00 11,035.00 12,590.00
D Jumlah A + B + C 198,495.50 229,113.50
E Overhead & Profit (contoh 10%) 10% 19,849.55 22,911.35
F Harga Satuan Pekerjaan (D+E) 218,345.05 252,024.85
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4


1 A.4.5.1.1 1 m2 28,281.00 31,823.00
mm, 5 mm & 6 mm

A Tenaga 8,520.00 10,050.00


L.01 0.03 OH Pekerja 65,000.00 75,000.00 1,950.00 2,250.00
L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.004 OH Mandor 85,000.00 95,000.00 340.00 380.00
B Bahan 17,190.00 18,880.00
1.1 Lbr Plat Asbes 15,500.00 17,000.00 17,050.00 18,700.00
0.01 Kg Paku 14,000.00 18,000.00 140.00 180.00
C PERALATAN
D Jumlah A + B + C 25,710.00 28,930.00
E Overhead & Profit (contoh 10%) 10% 2,571.00 2,893.00
F Harga Satuan Pekerjaan (D+E) 28,281.00 31,823.00
Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 98,219.00 107,349.00
A Tenaga 18,990.00 22,290.00
L.01 0.12 OH Pekerja 65,000.00 75,000.00 7,800.00 9,000.00
L.02 0.12 OH Tukang Kayu 80,000.00 95,000.00 9,600.00 11,400.00
L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 70,300.00 75,300.00
12.0 Lbr Akustik Uk.30 x 30 cm 5,800.00 6,200.00 69,600.00 74,400.00
0.05 Kg Paku 14,000.00 18,000.00 700.00 900.00
C PERALATAN
D Jumlah A + B + C 89,290.00 97,590.00
E Overhead & Profit (contoh 10%) 10% 8,929.00 9,759.00
F Harga Satuan Pekerjaan (D+E) 98,219.00 107,349.00

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) cm 102,393.50 112,018.50


A Tenaga 15,825.00 18,575.00
L.01 0.10 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.10 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 77,260.00 83,260.00
5.80 Lbr Akustik 13,200.00 14,200.00 76,560.00 82,360.00
0.05 Kg Paku 14,000.00 18,000.00 700.00 900.00
C PERALATAN
D Jumlah A + B + C 93,085.00 101,835.00
E Overhead & Profit (contoh 10%) 10% 9,308.50 10,183.50
F Harga Satuan Pekerjaan (D+E) 102,393.50 112,018.50

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120) cm 87,477.50 97,322.50


A Tenaga 15,825.00 18,575.00
L.01 0.10 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.10 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 63,700.00 69,900.00
1.50 Lbr Akustik 42,000.00 46,000.00 63,000.00 69,000.00
0.05 Kg Paku 14,000.00 18,000.00 700.00 900.00
C PERALATAN
D Jumlah A + B + C 79,525.00 88,475.00
E Overhead & Profit (contoh 10%) 10% 7,952.50 8,847.50
F Harga Satuan Pekerjaan (D+E) 87,477.50 97,322.50

Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3


5 A.4.5.1.5 1 m2 42,619.50 49,901.50
mm, 4 mm & 6 mm

A Tenaga 15,825.00 18,575.00


L.01 0.10 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.10 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00

file:///conversion/tmp/scratch/457687078.xls 130/101 abk 9-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 22,920.00 26,790.00
0.375 Lbr Tripleks (4 mm) 60,000.00 70,000.00 22,500.00 26,250.00
0.03 Kg Paku Tripleks 14,000.00 18,000.00 420.00 540.00
C PERALATAN
D Jumlah A + B + C 38,745.00 45,365.00
E Overhead & Profit (contoh 10%) 10% 3,874.50 4,536.50
F Harga Satuan Pekerjaan (D+E) 42,619.50 49,901.50

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 502,414.00 543,158.00


A Tenaga 126,600.00 148,600.00
L.01 0.8 OH Pekerja 65,000.00 75,000.00 52,000.00 60,000.00
L.02 0.8 OH Tukang Kayu 80,000.00 95,000.00 64,000.00 76,000.00
L.03 0.08 OH Kepala Tukang 90,000.00 110,000.00 7,200.00 8,800.00
L.04 0.04 OH Mandor 85,000.00 95,000.00 3,400.00 3,800.00
B Bahan 330,140.00 345,180.00
0.015 m3 Kayu Jati,Papan 22,000,000.00 23,000,000.00 330,000.00 345,000.00
0.01 Kg Paku 14,000.00 18,000.00 140.00 180.00
C PERALATAN
D Jumlah A + B + C 456,740.00 493,780.00
E Overhead & Profit (contoh 10%) 10% 45,674.00 49,378.00
F Harga Satuan Pekerjaan (D+E) 502,414.00 543,158.00

Memasang Langit-langit Gypsu Board, Ukuran (120x240)


7 A.4.5.1.7 1 m2 38,351.50 43,705.20
tebal 9 mm

A Tenaga 11,375.00 13,275.00


L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.05 OH Tukang Kayu 80,000.00 95,000.00 4,000.00 4,750.00
L.03 0.005 OH Kepala Tukang 90,000.00 110,000.00 450.00 550.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 23,490.00 26,457.00
0.364 Lbr Gypsum Board 60,000.00 68,000.00 21,840.00 24,752.00
0.11 Kg Paku Sekrup 15,000.00 15,500.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 34,865.00 39,732.00
E Overhead & Profit (contoh 10%) 10% 3,486.50 3,973.20
F Harga Satuan Pekerjaan (D+E) 38,351.50 43,705.20

Memasang Langit-langit Akuatik Uk (60x120) cm & Berikut


8 A.4.5.1.8 1 m2 196,102.50 220,467.50
Rangka Allumunium

A Tenaga 79,125.00 92,875.00


L.01 0.5 OH Pekerja 65,000.00 75,000.00 32,500.00 37,500.00
L.02 0.5 OH Tukang Kayu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.025 OH Mandor 85,000.00 95,000.00 2,125.00 2,375.00
B Bahan 99,150.00 107,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat Ø 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 42,000.00 46,000.00 63,000.00 69,000.00
C PERALATAN
D Jumlah A + B + C 178,275.00 200,425.00
E Overhead & Profit (contoh 10%) 10% 17,827.50 20,042.50
F Harga Satuan Pekerjaan (D+E) 196,102.50 220,467.50

9 A.4.5.1.9 1 m1 List Langit-Langit Kayu Profil 14,448.50 16,241.50


A Tenaga 7,955.00 9,335.00
L.01 0.05 OH Pekerja 65,000.00 75,000.00 3,250.00 3,750.00
L.02 0.05 OH Tukang Kayu 80,000.00 95,000.00 4,000.00 4,750.00
L.03 0.005 OH Kepala Tukang 90,000.00 110,000.00 450.00 550.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 5,180.00 5,430.00
1.05 m1 List Kayu Profil 4,800.00 5,000.00 5,040.00 5,250.00
0.01 Kg Paku 14,000.00 18,000.00 140.00 180.00
C PERALATAN
D Jumlah A + B + C 13,135.00 14,765.00
E Overhead & Profit (contoh 10%) 10% 1,313.50 1,476.50
F Harga Satuan Pekerjaan (D+E) 14,448.50 16,241.50

file:///conversion/tmp/scratch/457687078.xls 130/102 abk 9-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

X A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 79,315.50 87,956.00

A Tenaga 17,105.00 19,960.00


L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.075 OH Tukang Kayu 80,000.00 95,000.00 6,000.00 7,125.00

L.03 0.0075 OH Kepala Tukang 90,000.00 110,000.00 675.00 825.00


L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00

B Bahan 55,000.00 60,000.00

25 Buah Genteng Plentong 2,200.00 2,400.00 55,000.00 60,000.00

C PERALATAN

D Jumlah A + B + C 72,105.00 79,960.00

E Overhead & Profit (contoh 10%) 10% 7,210.50 7,996.00

F Harga Satuan Pekerjaan (D+E) 79,315.50 87,956.00

Overhead & Profit (contoh 10%)


2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur 135,740.00 141,641.50

A Tenaga 17,150.00 20,015.00


L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.075 OH Tukang Kayu 80,000.00 95,000.00 6,000.00 7,125.00
L.03 0.008 OH Kepala Tukang 90,000.00 110,000.00 720.00 880.00
L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00

B Bahan 106,250.00 108,750.00

25 Buah Genteng Kodok / Glasur 4,250.00 4,350.00 106,250.00 108,750.00

C PERALATAN

D Jumlah A + B + C 123,400.00 128,765.00

E Overhead & Profit (contoh 10%) 10% 12,340.00 12,876.50

F Harga Satuan Pekerjaan (D+E) 135,740.00 141,641.50

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar 119,845.00 127,946.50

A Tenaga 17,150.00 20,015.00


L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00

L.02 0.075 OH Tukang Kayu 80,000.00 95,000.00 6,000.00 7,125.00


L.03 0.008 OH Kepala Tukang 90,000.00 110,000.00 720.00 880.00
L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00

B Bahan 91,800.00 96,300.00

12 Buah Genteng Plentong Super / Besar 7,650.00 8,025.00 91,800.00 96,300.00

C PERALATAN

D Jumlah A + B + C 108,950.00 116,315.00

E Overhead & Profit (contoh 10%) 10% 10,895.00 11,631.50

F Harga Satuan Pekerjaan (D+E) 119,845.00 127,946.50

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong 89,562.00 103,158.00

A Tenaga 43,970.00 51,390.00

L.01 0.4 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00


L.02 0.2 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00

L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00

B Bahan 37,450.00 42,390.00

5 Buah Genteng Bubung Plentong 4,250.00 4,350.00 21,250.00 21,750.00

8 Kg Portland Semen 1,025.00 1,100.00 8,200.00 8,800.00

0.032 m3 Pasir Pasang 250,000.00 370,000.00 8,000.00 11,840.00

C PERALATAN

D Jumlah A + B + C 81,420.00 93,780.00

E Overhead & Profit (contoh 10%) 10% 8,142.00 9,378.00

F Harga Satuan Pekerjaan (D+E) 89,562.00 103,158.00

file:///conversion/tmp/scratch/457687078.xls 130/103 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur 101,937.00 116,633.00

A Tenaga 43,970.00 51,390.00


L.01 0.4 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00
L.02 0.2 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00

L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00


L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00

B Bahan 48,700.00 54,640.00

5 Buah Genteng Bubung Kodok / Glasur 6,500.00 6,800.00 32,500.00 34,000.00

8 Kg Portland Semen 1,025.00 1,100.00 8,200.00 8,800.00

0.032 m3 Pasir Pasang 250,000.00 370,000.00 8,000.00 11,840.00

C PERALATAN

D Jumlah A + B + C 92,670.00 106,030.00

E Overhead & Profit (contoh 10%) 10% 9,267.00 10,603.00

F Harga Satuan Pekerjaan (D+E) 101,937.00 116,633.00

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar 105,787.00 119,713.00

A Tenaga 43,970.00 51,390.00


L.01 0.4 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00
L.02 0.2 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00

L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00


L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00

B Bahan 52,200.00 57,440.00

4 Buah Genteng Bubung Plentong Besar 9,000.00 9,200.00 36,000.00 36,800.00

8 Kg Portland Semen 1,025.00 1,100.00 8,200.00 8,800.00

0.032 m3 Pasir Pasang 250,000.00 370,000.00 8,000.00 11,840.00

C PERALATAN

D Jumlah A + B + C 96,170.00 108,830.00

E Overhead & Profit (contoh 10%) 10% 9,617.00 10,883.00

F Harga Satuan Pekerjaan (D+E) 105,787.00 119,713.00

7 A.4.5.2.7 1 m2 Pemasangan Roof Light Fibreglass 90 x 180 100,523.50 113,520.00

A Tenaga 15,685.00 18,300.00


L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.067 OH Tukang Kayu 80,000.00 95,000.00 5,360.00 6,365.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00

B Bahan 75,700.00 84,900.00

0.6 Lbr Rooflight 90 x 180 125,000.00 140,000.00 75,000.00 84,000.00

0.05 Kg Paku Biasa 14,000.00 18,000.00 700.00 900.00

C PERALATAN

D Jumlah A + B + C 91,385.00 103,200.00

E Overhead & Profit (contoh 10%) 10% 9,138.50 10,320.00

F Harga Satuan Pekerjaan (D+E) 100,523.50 113,520.00

Pemasangan Atap Asbes Gelombang (2,50x0,92 m) x 5


8 A.4.5.2.8 1 m2 59,521.00 68,029.50
mm

A Tenaga 16,500.00 19,265.00


L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.075 OH Tukang Kayu 80,000.00 95,000.00 6,000.00 7,125.00

L.03 0.008 OH Kepala Tukang 90,000.00 110,000.00 720.00 880.00


L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00

B Bahan 37,610.00 42,580.00

0.5 Lbr Asbes Gelombang 71,500.00 81,200.00 35,750.00 40,600.00

0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

C PERALATAN

D Jumlah A + B + C 54,110.00 61,845.00

E Overhead & Profit (contoh 10%) 10% 5,411.00 6,184.50

F Harga Satuan Pekerjaan (D+E) 59,521.00 68,029.50

file:///conversion/tmp/scratch/457687078.xls 130/104 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5
9 A.4.5.2.9 1 m2 61,473.50 70,273.50
mm

A Tenaga 15,925.00 18,585.00

L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00


L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00

L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00

B Bahan 39,960.00 45,300.00

0.6 Lbr Asbes Gelombang 63,500.00 72,200.00 38,100.00 43,320.00

0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

C PERALATAN

D Jumlah A + B + C 55,885.00 63,885.00

E Overhead & Profit (contoh 10%) 10% 5,588.50 6,388.50

F Harga Satuan Pekerjaan (D+E) 61,473.50 70,273.50

Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5


10 A.4.5.2.10 1 m2 61,803.50 70,933.50
mm

A Tenaga 15,925.00 18,585.00


L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00

L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00


L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00

B Bahan 40,260.00 45,900.00

0.6 Lbr Asbes Gelombang 64,000.00 73,200.00 38,400.00 43,920.00

0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

C PERALATAN

D Jumlah A + B + C 56,185.00 64,485.00

E Overhead & Profit (contoh 10%) 10% 5,618.50 6,448.50

F Harga Satuan Pekerjaan (D+E) 61,803.50 70,933.50

Pemasangan Atap Asbes Gelombang (1,80x0,92 m) x 5


11 A.4.5.2.11 1 m2 69,063.50 73,771.50
mm

A Tenaga 15,925.00 18,585.00


L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00

L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00


L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00

B Bahan 46,860.00 48,480.00

0.75 Lbr Asbes Gelombang 60,000.00 62,000.00 45,000.00 46,500.00

0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

C PERALATAN

D Jumlah A + B + C 62,785.00 67,065.00

E Overhead & Profit (contoh 10%) 10% 6,278.50 6,706.50

F Harga Satuan Pekerjaan (D+E) 69,063.50 73,771.50

Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4


12 A.4.5.2.12 1 m2 47,283.50 55,346.50
mm
A Tenaga 15,925.00 18,585.00
L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 27,060.00 31,730.00
0.35 Lbr Asbes Gelombang 72,000.00 85,000.00 25,200.00 29,750.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 42,985.00 50,315.00
E Overhead & Profit (contoh 10%) 10% 4,298.50 5,031.50
F Harga Satuan Pekerjaan (D+E) 47,283.50 55,346.50

file:///conversion/tmp/scratch/457687078.xls 130/105 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pemasangan Atap Asbes Gelombang (2,70x1,05 m) x 4
13 A.4.5.2.13 1 m2 51,903.50 60,043.50
mm
A Tenaga 15,925.00 18,585.00
L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 31,260.00 36,000.00
0.42 Lbr Asbes Gelombang 70,000.00 81,000.00 29,400.00 34,020.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 47,185.00 54,585.00
E Overhead & Profit (contoh 10%) 10% 4,718.50 5,458.50
F Harga Satuan Pekerjaan (D+E) 51,903.50 60,043.50

Pemasangan Atap Asbes Gelombang (2,40x1,05 m) x 4


14 A.4.5.2.14 1 m2 49,813.50 57,469.50
mm
A Tenaga 15,925.00 18,585.00
L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.070 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 29,360.00 33,660.00
0.44 Lbr Asbes Gelombang 62,500.00 72,000.00 27,500.00 31,680.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 45,285.00 52,245.00
E Overhead & Profit (contoh 10%) 10% 4,528.50 5,224.50
F Harga Satuan Pekerjaan (D+E) 49,813.50 57,469.50

Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4


15 A.4.5.2.15 1 m2 48,735.50 57,964.50
mm
A Tenaga 15,925.00 18,585.00
L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.070 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 28,380.00 34,110.00
0.51 Lbr Asbes Gelombang 52,000.00 63,000.00 26,520.00 32,130.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 44,305.00 52,695.00
E Overhead & Profit (contoh 10%) 10% 4,430.50 5,269.50
F Harga Satuan Pekerjaan (D+E) 48,735.50 57,964.50

Pemasangan Atap Asbes Gelombang (1,50x1,05 m) x 4


16 A.4.5.2.16 1 m2 54,763.50 63,981.50
mm
A Tenaga 15,925.00 18,585.00
L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.070 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 33,860.00 39,580.00
0.80 Lbr Asbes Gelombang 40,000.00 47,000.00 32,000.00 37,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 49,785.00 58,165.00
E Overhead & Profit (contoh 10%) 10% 4,978.50 5,816.50
F Harga Satuan Pekerjaan (D+E) 54,763.50 63,981.50

Pemasangan Atap Asbes Gelombang (3,00x1,08 m) x 6


17 A.4.5.2.17 1 m2 61,484.50 65,356.50
mm
A Tenaga 15,925.00 18,585.00
L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 39,970.00 40,830.00
0.37 Lbr Asbes Gelombang 103,000.00 105,000.00 38,110.00 38,850.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00

file:///conversion/tmp/scratch/457687078.xls 130/106 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 55,895.00 59,415.00
E Overhead & Profit (contoh 10%) 10% 5,589.50 5,941.50
F Harga Satuan Pekerjaan (D+E) 61,484.50 65,356.50

Pemasangan Atap Asbes Gelombang (2,70x1,08 m) x 6


18 A.4.5.2.18 1 m2 64,839.50 68,821.50
mm

A Tenaga 15,925.00 18,585.00


L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 43,020.00 43,980.00
0.42 Lbr Asbes Gelombang 98,000.00 100,000.00 41,160.00 42,000.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 58,945.00 62,565.00
E Overhead & Profit (contoh 10%) 10% 5,894.50 6,256.50
F Harga Satuan Pekerjaan (D+E) 64,839.50 68,821.50

Pemasangan Atap Asbes Gelombang (2,40x1,08 m) x 6


19 A.4.5.2.19 1 m2 61,671.50 66,181.50
mm

A Tenaga 15,925.00 18,585.00


L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.070 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 40,140.00 41,580.00
0.44 Lbr Asbes Gelombang 87,000.00 90,000.00 38,280.00 39,600.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 56,065.00 60,165.00
E Overhead & Profit (contoh 10%) 10% 5,606.50 6,016.50
F Harga Satuan Pekerjaan (D+E) 61,671.50 66,181.50

Pemasangan Atap Asbes Gelombang (2,10x1,08 m) x 6


20 A.4.5.2.20 1 m2 62,683.50 67,358.50
mm

A Tenaga 15,925.00 18,585.00


L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.070 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 41,060.00 42,650.00
0.49 Lbr Asbes Gelombang 80,000.00 83,000.00 39,200.00 40,670.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 56,985.00 61,235.00
E Overhead & Profit (contoh 10%) 10% 5,698.50 6,123.50
F Harga Satuan Pekerjaan (D+E) 62,683.50 67,358.50

Pemasangan Atap Asbes Gelombang (1,80x1,08 m) x 6


21 A.4.5.2.21 1 m2 66,588.50 70,900.50
mm

A Tenaga 15,925.00 18,585.00


L.01 0.14 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.070 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 44,610.00 45,870.00
0.57 Lbr Asbes Gelombang 75,000.00 77,000.00 42,750.00 43,890.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 60,535.00 64,455.00
E Overhead & Profit (contoh 10%) 10% 6,053.50 6,445.50
F Harga Satuan Pekerjaan (D+E) 66,588.50 70,900.50

file:///conversion/tmp/scratch/457687078.xls 130/107 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
22 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton 98,087.00 114,499.00
A Tenaga 22,750.00 26,550.00
L.01 0.2 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.1 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.01 OH Mandor 85,000.00 95,000.00 850.00 950.00
B Bahan 66,420.00 77,540.00
11 Lbr Genteng Beton Standrad 6,000.00 7,000.00 66,000.00 77,000.00
0.03 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 420.00 540.00
C PERALATAN
D Jumlah A + B + C 89,170.00 104,090.00
E Overhead & Profit (contoh 10%) 10% 8,917.00 10,409.00
F Harga Satuan Pekerjaan (D+E) 98,087.00 114,499.00

23 A.4.5.2.31 1 m2 Pemasangan Atap Genteng Aspal 211,189.00 236,302.00


A Tenaga 38,120.00 44,780.00
L.01 0.2 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.3 OH Tukang Kayu 80,000.00 95,000.00 24,000.00 28,500.00
L.03 0.003 OH Kepala Tukang 90,000.00 110,000.00 270.00 330.00
L.04 0.01 OH Mandor 85,000.00 95,000.00 850.00 950.00
B Bahan 153,870.00 170,040.00
6.9 Buah Genteng Aspal 18,000.00 20,000.00 124,200.00 138,000.00
0.35 lbr Plywood 6 mm 75,000.00 80,000.00 26,250.00 28,000.00
0.03 kg Paku Biasa 2" - 5" 14,000.00 18,000.00 420.00 540.00
0.50 buah Plastic Aerotor 6,000.00 7,000.00 3,000.00 3,500.00
C PERALATAN
D Jumlah A + B + C 191,990.00 214,820.00
E Overhead & Profit (contoh 10%) 10% 19,199.00 21,482.00
F Harga Satuan Pekerjaan (D+E) 211,189.00 236,302.00

24 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal 84,205.00 100,485.00


A Tenaga 22,750.00 26,550.00
L.01 0.2 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.1 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.01 OH Mandor 85,000.00 95,000.00 850.00 950.00
B Bahan 53,800.00 64,800.00
1.02 m2 Genteng Metal 50,000.00 60,000.00 51,000.00 61,200.00
0.20 Kg Paku Biasa Ø ½" - 1" 14,000.00 18,000.00 2,800.00 3,600.00
C PERALATAN
D Jumlah A + B + C 76,550.00 91,350.00
E Overhead & Profit (contoh 10%) 10% 7,655.00 9,135.00
F Harga Satuan Pekerjaan (D+E) 84,205.00 100,485.00

25 A.4.5.2.34 1 m2 Pemasangan Atap Sirap 101,222.00 110,341.00


A Tenaga 33,720.00 39,710.00
L.01 0.166 OH Pekerja 65,000.00 75,000.00 10,790.00 12,450.00
L.02 0.25 OH Tukang Kayu 80,000.00 95,000.00 20,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 90,000.00 110,000.00 2,250.00 2,750.00
L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00
B Bahan 58,300.00 60,600.00
30 Lbr Genteng Sirap 1,850.00 1,900.00 55,500.00 57,000.00
0.2 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 2,800.00 3,600.00
C PERALATAN
D Jumlah A + B + C 92,020.00 100,310.00
E Overhead & Profit (contoh 10%) 10% 9,202.00 10,031.00
F Harga Satuan Pekerjaan (D+E) 101,222.00 110,341.00

26 A.4.5.2.35 1 m' Pemasangan Nok Genteng Beton 110,297.00 124,184.50


A Tenaga 45,500.00 53,100.00
L.01 0.4 OH Pekerja 65,000.00 75,000.00 26,000.00 30,000.00
L.02 0.2 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.02 OH Mandor 85,000.00 95,000.00 1,700.00 1,900.00
B Bahan 54,770.00 59,795.00
3.5 Buah Nok Genteng Beton 10,000.00 10,050.00 35,000.00 35,175.00
0.05 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 700.00 900.00
10.8 Kg Portland Semen 1,025.00 1,100.00 11,070.00 11,880.00
0.032 m3 Pasir Pasang 250,000.00 370,000.00 8,000.00 11,840.00
1 Kg Semen Warna 11,000.00 12,000.00 11,000.00 12,000.00

file:///conversion/tmp/scratch/457687078.xls 130/108 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 100,270.00 112,895.00
E Overhead & Profit (contoh 10%) 10% 10,027.00 11,289.50
F Harga Satuan Pekerjaan (D+E) 110,297.00 124,184.50

27 A.4.5.2.36 1 m' Pemasangan Nok Genteng Aspal 117,518.50 130,564.50


A Tenaga 30,885.00 36,445.00
L.01 0.125 OH Pekerja 65,000.00 75,000.00 8,125.00 9,375.00
L.02 0.250 OH Tukang Kayu 80,000.00 95,000.00 20,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 90,000.00 110,000.00 2,250.00 2,750.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 75,950.00 82,250.00
2.0 Buah Nok Genteng Beton 28,000.00 30,000.00 56,000.00 60,000.00
0.05 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 700.00 900.00
0.0035 m3 Balok Kayu 5,500,000.00 6,100,000.00 19,250.00 21,350.00
C PERALATAN
D Jumlah A + B + C 106,835.00 118,695.00
E Overhead & Profit (contoh 10%) 10% 10,683.50 11,869.50
F Harga Satuan Pekerjaan (D+E) 117,518.50 130,564.50

28 A.4.5.2.37 1 m' Pemasangan Nok Genteng Metal 58,745.50 67,688.50


A Tenaga 30,705.00 35,885.00
L.01 0.250 OH Pekerja 65,000.00 75,000.00 16,250.00 18,750.00
L.02 0.150 OH Tukang Kayu 80,000.00 95,000.00 12,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00
L.04 0.013 OH Mandor 85,000.00 95,000.00 1,105.00 1,235.00
B Bahan 22,700.00 25,650.00
1.1 Buah Nok Genteng 20,000.00 22,500.00 22,000.00 24,750.00
0.05 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 700.00 900.00

C PERALATAN
D Jumlah A + B + C 53,405.00 61,535.00
E Overhead & Profit (contoh 10%) 10% 5,340.50 6,153.50
F Harga Satuan Pekerjaan (D+E) 58,745.50 67,688.50

29 A.4.5.2.38 1 m' Pemasangan Nok Sirap 47,327.50 55,467.50


A Tenaga 30,885.00 36,445.00
L.01 0.125 OH Pekerja 65,000.00 75,000.00 8,125.00 9,375.00
L.02 0.25 OH Tukang Kayu 80,000.00 95,000.00 20,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 90,000.00 110,000.00 2,250.00 2,750.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 12,140.00 13,980.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 26,500.00 30,000.00 10,600.00 12,000.00
0.06 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 840.00 1,080.00
0.05 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 700.00 900.00

C PERALATAN
D Jumlah A + B + C 43,025.00 50,425.00
E Overhead & Profit (contoh 10%) 10% 4,302.50 5,042.50
F Harga Satuan Pekerjaan (D+E) 47,327.50 55,467.50

30 A.4.5.2.39 1 m2 Pemasangan Atap Seng Gelombang 35,728.00 41,019.00


A Tenaga 13,650.00 15,930.00
L.01 0.12 OH Pekerja 65,000.00 75,000.00 7,800.00 9,000.00
L.02 0.06 OH Tukang Kayu 80,000.00 95,000.00 4,800.00 5,700.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 18,830.00 21,360.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 26,500.00 30,000.00 18,550.00 21,000.00
0.02 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 280.00 360.00
C PERALATAN
D Jumlah A + B + C 32,480.00 37,290.00
E Overhead & Profit (contoh 10%) 10% 3,248.00 3,729.00
F Harga Satuan Pekerjaan (D+E) 35,728.00 41,019.00

file:///conversion/tmp/scratch/457687078.xls 130/109 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
31 A.4.5.2.40 1 m' Pemasangan Atap Nok Seng 27,500.00 31,856.00
A Tenaga 16,490.00 19,240.00
L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.07 OH Tukang Kayu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 8,510.00 9,720.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 26,500.00 30,000.00 7,950.00 9,000.00
0.04 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 560.00 720.00
C PERALATAN
D Jumlah A + B + C 25,000.00 28,960.00
E Overhead & Profit (contoh 10%) 10% 2,500.00 2,896.00
F Harga Satuan Pekerjaan (D+E) 27,500.00 31,856.00

32 A.4.5.2.43 1 m2 Pasang Allumunium Foil / Sisalation 25,030.50 28,281.00


A Tenaga 14,880.00 17,310.00
L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.05 OH Tukang Kayu 80,000.00 95,000.00 4,000.00 4,750.00
L.03 0.005 OH Kepala Tukang 90,000.00 110,000.00 450.00 550.00
L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00
B Bahan 7,875.00 8,400.00
1.05 m2 Sisalation / Allumunium Foil 7,500.00 8,000.00 7,875.00 8,400.00
C PERALATAN
D Jumlah A + B + C 22,755.00 25,710.00
E Overhead & Profit (contoh 10%) 10% 2,275.50 2,571.00
F Harga Satuan Pekerjaan (D+E) 25,030.50 28,281.00

file:///conversion/tmp/scratch/457687078.xls 130/110 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
Pembuatan & Pemasangan Kosen Pintu & Jendela
1 A.4.6.1.1 1 m3 26,822,125.00 27,914,425.00
Kayu klas I
A Tenaga 2,353,750.00 2,784,250.00
L.01 7 OH Pekerja 65,000.00 75,000.00 455,000.00 525,000.00
L.02 21 OH Tukang Kayu 80,000.00 95,000.00 1,680,000.00 1,995,000.00
L.03 2.10 OH Kepala Tukang 90,000.00 110,000.00 189,000.00 231,000.00
L.04 0.35 OH Mandor 85,000.00 95,000.00 29,750.00 33,250.00
B Bahan 22,030,000.00 22,592,500.00
1.1 m3 Kayu Klas I (Jati) , Balok 20,000,000.00 20,500,000.00 22,000,000.00 22,550,000.00
1.25 kg Paku Biasa 2" - 5 " 14,000.00 18,000.00 17,500.00 22,500.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 24,383,750.00 25,376,750.00
E Overhead & Profit (contoh 10%) 10% 2,438,375.00 2,537,675.00
F Harga Satuan Pekerjaan (D+E) 26,822,125.00 27,914,425.00

Pembuatan & Pemasangan Kosen Pintu & Jendela


2 A.4.6.1.2 1 m3 11,360,250.00 12,571,900.00
Kayu klas II atau III
Tenaga 2,017,500.00 2,386,500.00
L.01 6.00 OH Pekerja 65,000.00 75,000.00 390,000.00 450,000.00
L.02 18.00 OH Tukang Kayu 80,000.00 95,000.00 1,440,000.00 1,710,000.00
L.03 1.80 OH Kepala Tukang 90,000.00 110,000.00 162,000.00 198,000.00
L.04 0.30 OH Mandor 85,000.00 95,000.00 25,500.00 28,500.00
Bahan 8,310,000.00 9,042,500.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 6,900,000.00 7,500,000.00 8,280,000.00 9,000,000.00
1.25 kg Paku Biasa 2" - 5 " 14,000.00 18,000.00 17,500.00 22,500.00
1 kg Lem Kayu 12,500.00 20,000.00 12,500.00 20,000.00
C PERALATAN
D Jumlah A + B + C 10,327,500.00 11,429,000.00
E Overhead & Profit (contoh 10%) 10% 1,032,750.00 1,142,900.00
F Harga Satuan Pekerjaan (D+E) 11,360,250.00 12,571,900.00

Pembuatan & Pemasangan Pintu KlampStandard


3 A.4.6.1.3 1 m2 447,073.00 497,376.00
Kayu Klas II (Kayu Kamfer)
A Tenaga 117,730.00 139,260.00
L.01 0.35 OH Pekerja 65,000.00 75,000.00 22,750.00 26,250.00
L.02 1.05 OH Tukang Kayu 80,000.00 95,000.00 84,000.00 99,750.00
L.03 0.105 OH Kepala Tukang 90,000.00 110,000.00 9,450.00 11,550.00
L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00
B Bahan 288,700.00 312,900.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 14,000.00 18,000.00 700.00 900.00
C PERALATAN
D Jumlah A + B + C 406,430.00 452,160.00
E Overhead & Profit (contoh 10%) 10% 40,643.00 45,216.00
F Harga Satuan Pekerjaan (D+E) 447,073.00 497,376.00

Pembuatan & Pemasangan Daun Pintu Klamp


4 A.4.6.1.4 1 m2 447,073.00 497,376.00
Sederhana Kayu Klas III
Tenaga 117,730.00 139,260.00
L.01 0.35 OH Pekerja 65,000.00 75,000.00 22,750.00 26,250.00
L.02 1.05 OH Tukang Kayu 80,000.00 95,000.00 84,000.00 99,750.00
L.03 0.105 OH Kepala Tukang 90,000.00 110,000.00 9,450.00 11,550.00
L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00
Bahan 288,700.00 312,900.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 14,000.00 18,000.00 700.00 900.00
C PERALATAN
D Jumlah A + B + C 406,430.00 452,160.00
E Overhead & Profit (contoh 10%) 10% 40,643.00 45,216.00
F Harga Satuan Pekerjaan (D+E) 447,073.00 497,376.00

Pembuatan & Pemasangan Daun Pintu Panel, Kayu


5 A.4.6.1.5 1 m2 687,362.50 781,825.00
Klas I atau II
A Tenaga 336,250.00 397,750.00
L.01 1.00 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 3.00 OH Tukang Kayu 80,000.00 95,000.00 240,000.00 285,000.00
L.03 0.30 OH Kepala Tukang 90,000.00 110,000.00 27,000.00 33,000.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan 288,625.00 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 288,000.00 312,000.00
0.050 kg Lem Kayu 12,500.00 20,000.00 625.00 1,000.00
C PERALATAN
D Jumlah A + B + C 624,875.00 710,750.00
E Overhead & Profit (contoh 10%) 10% 62,487.50 71,075.00
F Harga Satuan Pekerjaan (D+E) 687,362.50 781,825.00

file:///conversion/tmp/scratch/457687078.xls 130/111 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu & Jendela Kaca
6 A.4.6.1.6 1 m2 490,105.00 562,540.00
Kayu Klas I atau II
A Tenaga 269,000.00 318,200.00
L.01 0.800 OH Pekerja 65,000.00 75,000.00 52,000.00 60,000.00
L.02 2.400 OH Tukang Kayu 80,000.00 95,000.00 192,000.00 228,000.00
L.03 0.240 OH Kepala Tukang 90,000.00 110,000.00 21,600.00 26,400.00
L.04 0.040 OH Mandor 85,000.00 95,000.00 3,400.00 3,800.00
B Bahan 176,550.00 193,200.00
0.024 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 172,800.00 187,200.00
0.300 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
C PERALATAN
D Jumlah A + B + C 445,550.00 511,400.00
E Overhead & Profit (contoh 10%) 10% 44,555.00 51,140.00
F Harga Satuan Pekerjaan (D+E) 490,105.00 562,540.00

Pembuatan & Pemasangan Pintu & Jendela Jalusi


7 A.4.6.1.7 1 m2 1,925,550.00 2,067,725.00
Kayu Klas I atau II (jati)
A Tenaga 336,250.00 397,750.00
L.01 1 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 3 OH Tukang Kayu 80,000.00 95,000.00 240,000.00 285,000.00
L.03 0.3 OH Kepala Tukang 90,000.00 110,000.00 27,000.00 33,000.00
L.04 0.05 OH Mandor 85,000.00 95,000.00 4,250.00 4,750.00
B Bahan 1,414,250.00 1,482,000.00
0.064 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,408,000.00 1,472,000.00
0.5 kg Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
C PERALATAN
D Jumlah A + B + C 1,750,500.00 1,879,750.00
E Overhead & Profit (contoh 10%) 10% 175,050.00 187,975.00
F Harga Satuan Pekerjaan (D+E) 1,925,550.00 2,067,725.00

Pembuatan&Pemasangan Pintu kayu lapis (Plywood)


8 A.4.6.1.8 1 m2 535,749.50 620,361.50
Rangkap rangka Kayu Klas II (lbr s/d 90 cm)

A Tenaga 235,375.00 278,425.00


L.01 0.700 OH Pekerja 65,000.00 75,000.00 45,500.00 52,500.00
L.02 2.100 OH Tukang Kayu 80,000.00 95,000.00 168,000.00 199,500.00
L.03 0.210 OH Kepala Tukang 90,000.00 110,000.00 18,900.00 23,100.00
L.04 0.035 OH Mandor 85,000.00 95,000.00 2,975.00 3,325.00
B Bahan 251,670.00 285,540.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 180,000.00 195,000.00
0.030 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 420.00 540.00
0.500 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 487,045.00 563,965.00
E Overhead & Profit (contoh 10%) 10% 48,704.50 56,396.50
F Harga Satuan Pekerjaan (D+E) 535,749.50 620,361.50

Pembuatan&Pemasangan Pintu Plywood rangkap,


9 A.4.6.1.9 1 m2 577,489.00 669,262.00
rangka expose kayu klas I atau II
A Tenaga 269,000.00 318,200.00
L.01 0.800 OH Pekerja 65,000.00 75,000.00 52,000.00 60,000.00
L.02 2.400 OH Tukang Kayu 80,000.00 95,000.00 192,000.00 228,000.00
L.03 0.240 OH Kepala Tukang 90,000.00 110,000.00 21,600.00 26,400.00
L.04 0.040 OH Mandor 85,000.00 95,000.00 3,400.00 3,800.00
B Bahan 255,990.00 290,220.00
0.0256 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 184,320.00 199,680.00
0.03 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 420.00 540.00
0.5 Ltr Lem Kayu 12,500.00 20,000.00 6,250.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 524,990.00 608,420.00
E Overhead & Profit (contoh 10%) 10% 52,499.00 60,842.00
F Harga Satuan Pekerjaan (D+E) 577,489.00 669,262.00

Pembuatan & Pemasangan Jalusi mati Kosen Kayu


10 A.4.6.1.10 1 m2 1,729,337.50 1,844,452.50
Klas I atau II
A Tenaga 250,025.00 294,075.00
L.01 0.670 OH Pekerja 65,000.00 75,000.00 43,550.00 50,250.00
L.02 2.000 OH Tukang Kayu 80,000.00 95,000.00 160,000.00 190,000.00
L.03 0.200 OH Kepala Tukang 90,000.00 110,000.00 18,000.00 22,000.00
L.04 0.335 OH Mandor 85,000.00 95,000.00 28,475.00 31,825.00
B Bahan 1,322,100.00 1,382,700.00
0.06 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,320,000.00 1,380,000.00
0.15 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 2,100.00 2,700.00
C PERALATAN
D Jumlah A + B + C 1,572,125.00 1,676,775.00
E Overhead & Profit (contoh 10%) 10% 157,212.50 167,677.50
F Harga Satuan Pekerjaan (D+E) 1,729,337.50 1,844,452.50

file:///conversion/tmp/scratch/457687078.xls 130/112 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pembuatan & Pemasangan Pintu Teakwood
11 A.4.6.1.11 1 m2 976,987.00 1,077,714.00
Rangkap, Rangka Expose Kayu Klas I
A Tenaga 269,000.00 318,200.00
L.01 0.80 OH Pekerja 65,000.00 75,000.00 52,000.00 60,000.00
L.02 2.40 OH Tukang Kayu 80,000.00 95,000.00 192,000.00 228,000.00
L.03 0.24 OH Kepala Tukang 90,000.00 110,000.00 21,600.00 26,400.00
L.04 0.04 OH Mandor 85,000.00 95,000.00 3,400.00 3,800.00
B Bahan 619,170.00 661,540.00
0.025 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 550,000.00 575,000.00
0.03 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 420.00 540.00
0.3 kg Lem Kayu 12,500.00 20,000.00 3,750.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 80,000.00 65,000.00 80,000.00
C PERALATAN
D Jumlah A + B + C 888,170.00 979,740.00
E Overhead & Profit (contoh 10%) 10% 88,817.00 97,974.00
F Harga Satuan Pekerjaan (D+E) 976,987.00 1,077,714.00

Pembuatan & Pemasangan Pintu Teakwood Rangkap


12 A.4.6.1.12 1 m2 622,902.50 718,052.50
Lapis Formika, Rangka expose Kayu Klas II

A Tenaga 285,855.00 338,135.00


L.01 0.850 OH Pekerja 65,000.00 75,000.00 55,250.00 63,750.00
L.02 2.550 OH Tukang Kayu 80,000.00 95,000.00 204,000.00 242,250.00
L.03 0.255 OH Kepala Tukang 90,000.00 110,000.00 22,950.00 28,050.00
L.04 0.043 OH Mandor 85,000.00 95,000.00 3,655.00 4,085.00
B Bahan 280,420.00 314,640.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,200,000.00 7,800,000.00 180,000.00 195,000.00
0.03 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 420.00 540.00
0.08 kg Lem Kayu 12,500.00 20,000.00 1,000.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 80,000.00 65,000.00 80,000.00
0.5 Lbr Formika 68,000.00 75,000.00 34,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 566,275.00 652,775.00
E Overhead & Profit (contoh 10%) 10% 56,627.50 65,277.50
F Harga Satuan Pekerjaan (D+E) 622,902.50 718,052.50

Pembuatan&Memasang Konstruksi Kuda-kuda


13 A.4.6.1.13 1 m3 10,137,490.00 11,166,980.00
Konvensional Kayu I; II & III Bentang 6 meter
A Tenaga 1,345,000.00 1,591,000.00
L.01 4 OH Pekerja 65,000.00 75,000.00 260,000.00 300,000.00
L.02 12 OH Tukang Kayu 80,000.00 95,000.00 960,000.00 1,140,000.00
L.03 1.2 OH Kepala Tukang 90,000.00 110,000.00 108,000.00 132,000.00
L.04 0.2 OH Mandor 85,000.00 95,000.00 17,000.00 19,000.00
B Bahan 7,870,900.00 8,560,800.00
1.1 m3 Kayu Kamfer, balok 6,900,000.00 7,500,000.00 7,590,000.00 8,250,000.00
15 Kg Besi Strip 13,500.00 14,000.00 202,500.00 210,000.00
5.6 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 78,400.00 100,800.00
C PERALATAN
D Jumlah A + B + C 9,215,900.00 10,151,800.00
E Overhead & Profit (contoh 10%) 10% 921,590.00 1,015,180.00
F Harga Satuan Pekerjaan (D+E) 10,137,490.00 11,166,980.00

Pembuatan&Pemasangan Konstruksi Kuda-kuda


14 A.4.6.1.14 1 m3 29,187,152.50 30,333,297.50
Expose, Kayu Klas I
A Tenaga 2,252,875.00 2,664,925.00
L.01 6.7 OH Pekerja 65,000.00 75,000.00 435,500.00 502,500.00
L.02 20.1 OH Tukang Kayu 80,000.00 95,000.00 1,608,000.00 1,909,500.00
L.03 2.01 OH Kepala Tukang 90,000.00 110,000.00 180,900.00 221,100.00
L.04 0.335 OH Mandor 85,000.00 95,000.00 28,475.00 31,825.00
B Bahan 24,280,900.00 24,910,800.00
1.2 m3 Kayu Klas I (jati), balok 20,000,000.00 20,500,000.00 24,000,000.00 24,600,000.00
15 Kg Besi Strip 13,500.00 14,000.00 202,500.00 210,000.00
5.6 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 78,400.00 100,800.00
C PERALATAN
D Jumlah A + B + C 26,533,775.00 27,575,725.00
E Overhead & Profit (contoh 10%) 10% 2,653,377.50 2,757,572.50
F Harga Satuan Pekerjaan (D+E) 29,187,152.50 30,333,297.50

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II 9,505,650.00 10,415,460.00


A Tenaga 807,000.00 954,600.00
L.01 2.4 OH Pekerja 65,000.00 75,000.00 156,000.00 180,000.00
L.02 7.2 OH Tukang Kayu 80,000.00 95,000.00 576,000.00 684,000.00
L.03 0.72 OH Kepala Tukang 90,000.00 110,000.00 64,800.00 79,200.00
L.04 0.12 OH Mandor 85,000.00 95,000.00 10,200.00 11,400.00

file:///conversion/tmp/scratch/457687078.xls 130/113 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 7,834,500.00 8,514,000.00
1.1 m3 Kayu Klas I (Kamfer), balok 6,900,000.00 7,500,000.00 7,590,000.00 8,250,000.00
15 Kg Besi Strip 13,500.00 14,000.00 202,500.00 210,000.00
3 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 42,000.00 54,000.00
C PERALATAN
D Jumlah A + B + C 8,641,500.00 9,468,600.00
E Overhead & Profit (contoh 10%) 10% 864,150.00 946,860.00
F Harga Satuan Pekerjaan (D+E) 9,505,650.00 10,415,460.00

Pemasangan Rangka Atap Genteng Keramik, Kayu


16 A.4.6.1.16 1 m2 154,841.50 170,582.50
Klas II
A Tenaga 15,825.00 18,575.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.1 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 124,940.00 136,500.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,900,000.00 7,500,000.00 96,600.00 105,000.00
0.0036 m3 Reng (2x3) cm 6,900,000.00 7,500,000.00 24,840.00 27,000.00
0.25 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 3,500.00 4,500.00
C PERALATAN
D Jumlah A + B + C 140,765.00 155,075.00
E Overhead & Profit (contoh 10%) 10% 14,076.50 15,507.50
F Harga Satuan Pekerjaan (D+E) 154,841.50 170,582.50

Pemasangan Rangka Atap Genteng Beton, Kayu Klas


17 A.4.6.1.17 1 m2 182,165.50 200,282.50
II
A Tenaga 15,825.00 18,575.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.1 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 149,780.00 163,500.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,900,000.00 7,500,000.00 96,600.00 105,000.00
0.0072 m3 Reng (2x3) cm 6,900,000.00 7,500,000.00 49,680.00 54,000.00
0.25 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 3,500.00 4,500.00
C PERALATAN
D Jumlah A + B + C 165,605.00 182,075.00
E Overhead & Profit (contoh 10%) 10% 16,560.50 18,207.50
F Harga Satuan Pekerjaan (D+E) 182,165.50 200,282.50

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II 130,229.00 143,979.00


A Tenaga 18,990.00 22,290.00
L.01 0.12 OH Pekerja 65,000.00 75,000.00 7,800.00 9,000.00
L.02 0.12 OH Tukang Kayu 80,000.00 95,000.00 9,600.00 11,400.00
L.03 0.012 OH Kepala Tukang 90,000.00 110,000.00 1,080.00 1,320.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 99,400.00 108,600.00
0.014 m3 Kayu Klas II (Kamfer), balok 6,900,000.00 7,500,000.00 96,600.00 105,000.00
0.2 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 2,800.00 3,600.00
C PERALATAN
D Jumlah A + B + C 118,390.00 130,890.00
E Overhead & Profit (contoh 10%) 10% 11,839.00 13,089.00
F Harga Satuan Pekerjaan (D+E) 130,229.00 143,979.00

Pemasangan Rangka Langit-langit (50x1,00) m, kayu


19 A.4.6.1.19 1 m2 167,073.50 186,202.50
Klas II atau III
A Tenaga 42,825.00 50,175.00
L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.30 OH Tukang Kayu 80,000.00 95,000.00 24,000.00 28,500.00
L.03 0.030 OH Kepala Tukang 90,000.00 110,000.00 2,700.00 3,300.00
L.04 0.075 OH Mandor 85,000.00 95,000.00 6,375.00 7,125.00
B Bahan 109,060.00 119,100.00
0.0154 m3 Kayu Klas II (Kamfer), balok 6,900,000.00 7,500,000.00 106,260.00 115,500.00
0.2 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 2,800.00 3,600.00
C PERALATAN
D Jumlah A + B + C 151,885.00 169,275.00
E Overhead & Profit (contoh 10%) 10% 15,188.50 16,927.50
F Harga Satuan Pekerjaan (D+E) 167,073.50 186,202.50

Pemasangan Rangka Langit-langit (60x60) cm, kayu


20 A.4.6.1.20 1 m2 172,172.00 191,950.00
Klas II atau III
A Tenaga 40,550.00 47,750.00
L.01 0.2 OH Pekerja 65,000.00 75,000.00 13,000.00 15,000.00
L.02 0.3 OH Tukang Kayu 80,000.00 95,000.00 24,000.00 28,500.00
L.03 0.03 OH Kepala Tukang 90,000.00 110,000.00 2,700.00 3,300.00
L.04 0.01 OH Mandor 85,000.00 95,000.00 850.00 950.00

file:///conversion/tmp/scratch/457687078.xls 130/114 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 115,970.00 126,750.00
0.0163 m3 Kayu Klas II (Kamfer), balok 6,900,000.00 7,500,000.00 112,470.00 122,250.00
0.25 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 3,500.00 4,500.00
C PERALATAN
D Jumlah A + B + C 156,520.00 174,500.00
E Overhead & Profit (contoh 10%) 10% 15,652.00 17,450.00
F Harga Satuan Pekerjaan (D+E) 172,172.00 191,950.00

Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau


21 A.4.6.1.21 1 m' 290,097.50 307,312.50
II
A Tenaga 24,725.00 29,175.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.2 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.020 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 239,000.00 250,200.00
0.0108 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 237,600.00 248,400.00
0.10 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 1,400.00 1,800.00
C PERALATAN
D Jumlah A + B + C 263,725.00 279,375.00
E Overhead & Profit (contoh 10%) 10% 26,372.50 27,937.50
F Harga Satuan Pekerjaan (D+E) 290,097.50 307,312.50

Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau


22 A.4.6.1.22 1 m' 115,087.50 127,462.50
klas II
A Tenaga 24,725.00 29,175.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.2 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 79,900.00 86,700.00
0.011 m3 Kayu klas II (Kamfer), papan 7,200,000.00 7,800,000.00 79,200.00 85,800.00
0.05 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 700.00 900.00
C PERALATAN
D Jumlah A + B + C 104,625.00 115,875.00
E Overhead & Profit (contoh 10%) 10% 10,462.50 11,587.50
F Harga Satuan Pekerjaan (D+E) 115,087.50 127,462.50

Pemasangan Rangka Dinding Pemisah (60x120) cm


23 A.4.6.1.23 1 m2 270,358.00 299,651.00
Kayu klas II atau III
A Tenaga 50,480.00 59,710.00
L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.45 OH Tukang Kayu 80,000.00 95,000.00 36,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 90,000.00 110,000.00 4,050.00 4,950.00
L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00
B Bahan 195,300.00 212,700.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 2,100.00 2,700.00
C PERALATAN
D Jumlah A + B + C 245,780.00 272,410.00
E Overhead & Profit (contoh 10%) 10% 24,578.00 27,241.00
F Harga Satuan Pekerjaan (D+E) 270,358.00 299,651.00

Pemasangan Dinding Pemisah Teakwood Rangkap


24 A.4.6.1.24 1 m2 339,548.00 387,651.00
Rangka Kayu Klas II
A Tenaga 50,480.00 59,710.00
L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.45 OH Tukang Kayu 80,000.00 95,000.00 36,000.00 42,750.00
L.03 0.045 OH Kepala Tukang 90,000.00 110,000.00 4,050.00 4,950.00
L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00
B Bahan 258,200.00 292,700.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 2,100.00 2,700.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 65,000.00 80,000.00 55,900.00 68,800.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 308,680.00 352,410.00
E Overhead & Profit (contoh 10%) 10% 30,868.00 35,241.00
F Harga Satuan Pekerjaan (D+E) 339,548.00 387,651.00

Pemasangan Dinding Pemisah Plywood Rangkap


25 A.4.6.1.25 1 m2 345,125.00 394,625.00
Rangka Kayu Klas II
A Tenaga 55,550.00 66,050.00
L.01 0.020 OH Pekerja 65,000.00 75,000.00 1,300.00 1,500.00
L.02 0.600 OH Tukang Kayu 80,000.00 95,000.00 48,000.00 57,000.00
L.03 0.060 OH Kepala Tukang 90,000.00 110,000.00 5,400.00 6,600.00
L.04 0.010 OH Mandor 85,000.00 95,000.00 850.00 950.00

file:///conversion/tmp/scratch/457687078.xls 130/115 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 258,200.00 292,700.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 2,100.00 2,700.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 65,000.00 80,000.00 55,900.00 68,800.00
0.56 Ltr Lem 12,500.00 20,000.00 7,000.00 11,200.00
C PERALATAN
D Jumlah A + B + C 313,750.00 358,750.00
E Overhead & Profit (contoh 10%) 10% 31,375.00 35,875.00
F Harga Satuan Pekerjaan (D+E) 345,125.00 394,625.00

26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan Kelas I 393,855.00 442,915.00

A Tenaga 201,750.00 238,650.00


L.01 0.6 OH Pekerja 65,000.00 75,000.00 39,000.00 45,000.00
L.02 1.8 OH Tukang Kayu 80,000.00 95,000.00 144,000.00 171,000.00
L.03 0.18 OH Kepala Tukang 90,000.00 110,000.00 16,200.00 19,800.00
L.04 0.03 OH Mandor 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 156,300.00 164,000.00
0.007 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 154,000.00 161,000.00
0.1 Kg Paku Biasa 2" - 5" 14,000.00 18,000.00 1,400.00 1,800.00
0.15 Kg Paku Sekrup 3,5" 6,000.00 8,000.00 900.00 1,200.00
C PERALATAN
D Jumlah A + B + C 358,050.00 402,650.00
E Overhead & Profit (contoh 10%) 10% 35,805.00 40,265.00
F Harga Satuan Pekerjaan (D+E) 393,855.00 442,915.00

Pemasangan Dinding Lambriziring dari Plywood


27 A.4.6.1.27 1 m2 36,443.00 42,762.50
ukuran (120x240) cm
A Tenaga 8,430.00 9,975.00
L.01 0.025 OH Pekerja 65,000.00 75,000.00 1,625.00 1,875.00
L.02 0.075 OH Tukang Kayu 80,000.00 95,000.00 6,000.00 7,125.00
L.03 0.0080 OH Kepala Tukang 90,000.00 110,000.00 720.00 880.00
L.04 0.0010 OH Mandor 85,000.00 95,000.00 85.00 95.00
B Bahan 24,700.00 28,900.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 60,000.00 70,000.00 24,000.00 28,000.00
0.05 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 700.00 900.00
C PERALATAN
D Jumlah A + B + C 33,130.00 38,875.00
E Overhead & Profit (contoh 10%) 10% 3,313.00 3,887.50
F Harga Satuan Pekerjaan (D+E) 36,443.00 42,762.50

Pemasangan Dinding Bilik, Rangka Kayu Klas III atau


28 A.4.6.1.28 1 m2 119,633.14 139,761.60
IV
A Tenaga 11,375.00 13,275.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.05 OH Tukang Kayu 80,000.00 95,000.00 4,000.00 4,750.00
L.03 0.005 OH Kepala Tukang 90,000.00 110,000.00 450.00 550.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 97,382.40 113,781.00
1.500 m2 Bilik Bambu 20,000.00 22,500.00 30,000.00 33,750.00
0.014 m3 Kayu Klas III (Meranti) 4,800,000.00 5,700,000.00 67,200.00 79,800.00
0.012 Kg Paku Biasa 1/2" - 1" 14,000.00 18,000.00 168.00 216.00
0.003 m' List Kayu 2/4 4,800.00 5,000.00 14.40 15.00
C PERALATAN
D Jumlah A + B + C 108,757.40 127,056.00
E Overhead & Profit (contoh 10%) 10% 10,875.74 12,705.60
F Harga Satuan Pekerjaan (D+E) 119,633.14 139,761.60

file:///conversion/tmp/scratch/457687078.xls 130/116 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA
1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 200,172.50 225,307.50
A Tenaga 41,975.00 49,825.00
L.01 0.01 OH Pekerja 65,000.00 75,000.00 650.00 750.00
L.02 0.5 OH Tukang Kayu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 140,000.00 155,000.00
1 Buah Kunci Tanam Biasa 140,000.00 155,000.00 140,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 181,975.00 204,825.00
E Overhead & Profit (contoh 10%) 10% 18,197.50 20,482.50
F Harga Satuan Pekerjaan (D+E) 200,172.50 225,307.50
Overhead & Profit (contoh 10%)

2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi 138,586.25 158,028.75


A Tenaga 40,987.50 48,662.50
L.01 0.005 OH Pekerja 65,000.00 75,000.00 325.00 375.00
L.02 0.5 OH Tukang Kayu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.005 OH Kepala Tukang 90,000.00 110,000.00 450.00 550.00
L.04 0.0025 OH Mandor 85,000.00 95,000.00 212.50 237.50
B Bahan 85,000.00 95,000.00
1 Buah Kunci Tanam Kamar Mandi 85,000.00 95,000.00 85,000.00 95,000.00
C PERALATAN
D Jumlah A + B + C 125,987.50 143,662.50
E Overhead & Profit (contoh 10%) 10% 12,598.75 14,366.25
F Harga Satuan Pekerjaan (D+E) 138,586.25 158,028.75

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder 199,086.25 224,028.75


A Tenaga 40,987.50 48,662.50
L.01 0.005 OH Pekerja 65,000.00 75,000.00 325.00 375.00
L.02 0.5 OH Tukang Kayu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.005 OH Kepala Tukang 90,000.00 110,000.00 450.00 550.00
L.04 0.0025 OH Mandor 85,000.00 95,000.00 212.50 237.50
B Bahan 140,000.00 155,000.00
1 Buah Kunci Selinder 140,000.00 155,000.00 140,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 180,987.50 203,662.50
E Overhead & Profit (contoh 10%) 10% 18,098.75 20,366.25
F Harga Satuan Pekerjaan (D+E) 199,086.25 224,028.75

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu 23,058.75 29,411.25


A Tenaga 14,962.50 17,737.50
L.01 0.015 OH Pekerja 65,000.00 75,000.00 975.00 1,125.00
L.02 0.15 OH Tukang Kayu 80,000.00 95,000.00 12,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00
L.04 0.0075 OH Mandor 85,000.00 95,000.00 637.50 712.50
B Bahan 6,000.00 9,000.00
1 Buah Engsel pintu 6,000.00 9,000.00 6,000.00 9,000.00
C PERALATAN
D Jumlah A + B + C 20,962.50 26,737.50
E Overhead & Profit (contoh 10%) 10% 2,096.25 2,673.75
F Harga Satuan Pekerjaan (D+E) 23,058.75 29,411.25

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 15,372.50 17,957.50


A Tenaga 9,975.00 11,825.00
L.01 0.01 OH Pekerja 65,000.00 75,000.00 650.00 750.00
L.02 0.1 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 4,000.00 4,500.00
1 Buah Engsel Jendela 4,000.00 4,500.00 4,000.00 4,500.00
C PERALATAN
D Jumlah A + B + C 13,975.00 16,325.00
E Overhead & Profit (contoh 10%) 10% 1,397.50 1,632.50
F Harga Satuan Pekerjaan (D+E) 15,372.50 17,957.50

file:///conversion/tmp/scratch/457687078.xls 130/117 abk 12-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin 43,276.75 49,222.25
A Tenaga 24,342.50 28,747.50
L.01 0.10 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.02 0.20 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.0005 OH Mandor 85,000.00 95,000.00 42.50 47.50
B Bahan 15,000.00 16,000.00
1 Buah Engsel Angin 15,000.00 16,000.00 15,000.00 16,000.00
C PERALATAN
D Jumlah A + B + C 39,342.50 44,747.50
E Overhead & Profit (contoh 10%) 10% 3,934.25 4,474.75
F Harga Satuan Pekerjaan (D+E) 43,276.75 49,222.25

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin 22,005.50 38,813.50


A Tenaga 15,005.00 17,785.00
L.01 0.015 OH Pekerja 65,000.00 75,000.00 975.00 1,125.00
L.02 0.15 OH Tukang Kayu 80,000.00 95,000.00 12,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00
L.04 0.008 OH Mandor 85,000.00 95,000.00 680.00 760.00
B Bahan 5,000.00 17,500.00
1 Buah Kait Angin 5,000.00 17,500.00 5,000.00 17,500.00
C PERALATAN
D Jumlah A + B + C 20,005.00 35,285.00
E Overhead & Profit (contoh 10%) 10% 2,000.50 3,528.50
F Harga Satuan Pekerjaan (D+E) 22,005.50 38,813.50

8 A.4.6.2.10 1 Buah Pasang Door Closer 355,258.75 447,686.25


A Tenaga 47,962.50 56,987.50
L.01 0.05 OH Pekerja 65,000.00 75,000.00 3,250.00 3,750.00
L.02 0.5 OH Tukang Kayu 80,000.00 95,000.00 40,000.00 47,500.00
L.03 0.05 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.0025 OH Mandor 85,000.00 95,000.00 212.50 237.50
B Bahan 275,000.00 350,000.00
1 Buah Door Closer 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 322,962.50 406,987.50
E Overhead & Profit (contoh 10%) 10% 32,296.25 40,698.75
F Harga Satuan Pekerjaan (D+E) 355,258.75 447,686.25

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot 32,103.50 47,074.50


A Tenaga 19,185.00 22,795.00
L.01 0.02 OH Pekerja 65,000.00 75,000.00 1,300.00 1,500.00
L.02 0.2 OH Tukang Kayu 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.02 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.001 OH Mandor 85,000.00 95,000.00 85.00 95.00
B Bahan 10,000.00 20,000.00
1 Buah Kunci Selot 10,000.00 20,000.00 10,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 29,185.00 42,795.00
E Overhead & Profit (contoh 10%) 10% 2,918.50 4,279.50
F Harga Satuan Pekerjaan (D+E) 32,103.50 47,074.50

10 A.4.6.2.13 1 Buah Pemasangan Door Stop 313,051.75 397,537.25


A Tenaga 9,592.50 11,397.50
L.01 0.01 OH Pekerja 65,000.00 75,000.00 650.00 750.00
L.02 0.1 OH Tukang Kayu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.01 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.0005 OH Mandor 85,000.00 95,000.00 42.50 47.50
B Bahan 275,000.00 350,000.00
1 Buah Door Stop 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 284,592.50 361,397.50
E Overhead & Profit (contoh 10%) 10% 28,459.25 36,139.75
F Harga Satuan Pekerjaan (D+E) 313,051.75 397,537.25

file:///conversion/tmp/scratch/457687078.xls 130/118 abk 12-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong 261,310.50 333,723.50
A Tenaga 57,555.00 68,385.00
L.01 0.06 OH Pekerja 65,000.00 75,000.00 3,900.00 4,500.00
L.02 0.6 OH Tukang Kayu 80,000.00 95,000.00 48,000.00 57,000.00
L.03 0.06 OH Kepala Tukang 90,000.00 110,000.00 5,400.00 6,600.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 180,000.00 235,000.00
1 Buah Rel Pintu Dorong 180,000.00 235,000.00 180,000.00 235,000.00
C PERALATAN
D Jumlah A + B + C 237,555.00 303,385.00
E Overhead & Profit (contoh 10%) 10% 23,755.50 30,338.50
F Harga Satuan Pekerjaan (D+E) 261,310.50 333,723.50

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari 31,884.05 39,598.35


A Tenaga 23,985.50 28,498.50
L.01 0.025 OH Pekerja 65,000.00 75,000.00 1,625.00 1,875.00
L.02 0.25 OH Tukang Kayu 80,000.00 95,000.00 20,000.00 23,750.00
L.03 0.025 OH Kepala Tukang 90,000.00 110,000.00 2,250.00 2,750.00
L.04 0.00130 OH Mandor 85,000.00 95,000.00 110.50 123.50
B Bahan 5,000.00 7,500.00
1 Buah Kunci Lemari 5,000.00 7,500.00 5,000.00 7,500.00
C PERALATAN
D Jumlah A + B + C 28,985.50 35,998.50
E Overhead & Profit (contoh 10%) 10% 2,898.55 3,599.85
F Harga Satuan Pekerjaan (D+E) 31,884.05 39,598.35

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm 100,527.63 121,655.88


A Tenaga 14,388.75 17,096.25
L.01 0.015 OH Pekerja 65,000.00 75,000.00 975.00 1,125.00
L.02 0.15 OH Tukang Kayu 80,000.00 95,000.00 12,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00
L.04 0.00075 OH Mandor 85,000.00 95,000.00 63.75 71.25
B Bahan 77,000.00 93,500.00
1.1 m2 Kaca tebal 3mm 70,000.00 85,000.00 77,000.00 93,500.00
C PERALATAN
D Jumlah A + B + C 91,388.75 110,596.25
E Overhead & Profit (contoh 10%) 10% 9,138.88 11,059.63
F Harga Satuan Pekerjaan (D+E) 100,527.63 121,655.88

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm 124,727.63 133,755.88


A Tenaga 14,388.75 17,096.25
L.01 0.015 OH Pekerja 65,000.00 75,000.00 975.00 1,125.00
L.02 0.15 OH Tukang Kayu 80,000.00 95,000.00 12,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00
L.04 0.00075 OH Mandor 85,000.00 95,000.00 63.75 71.25
B Bahan 99,000.00 104,500.00
1.1 m2 Kaca tebal 5mm 90,000.00 95,000.00 99,000.00 104,500.00
C PERALATAN
D Jumlah A + B + C 113,388.75 121,596.25
E Overhead & Profit (contoh 10%) 10% 11,338.88 12,159.63
F Harga Satuan Pekerjaan (D+E) 124,727.63 133,755.88

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm 288,077.63 351,555.88


A Tenaga 14,388.75 17,096.25
L.01 0.015 OH Pekerja 65,000.00 75,000.00 975.00 1,125.00
L.02 0.15 OH Tukang Kayu 80,000.00 95,000.00 12,000.00 14,250.00
L.03 0.015 OH Kepala Tukang 90,000.00 110,000.00 1,350.00 1,650.00
L.04 0.00075 OH Mandor 85,000.00 95,000.00 63.75 71.25
B Bahan 247,500.00 302,500.00
1.1 m2 Kaca Cermin 225,000.00 275,000.00 247,500.00 302,500.00
C PERALATAN
D Jumlah A + B + C 261,888.75 319,596.25
E Overhead & Profit (contoh 10%) 10% 26,188.88 31,959.63
F Harga Satuan Pekerjaan (D+E) 288,077.63 351,555.88

file:///conversion/tmp/scratch/457687078.xls 130/119 abk 12-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

Pengikisan / pengerokan Permukaan Cat Tembok


1 A.4.7.1.1 1 m2 11,665.50 13,513.50
Lama
A Tenaga 10,005.00 11,535.00

L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00

L.04 0.0030 OH Mandor 85,000.00 95,000.00 255.00 285.00

B Bahan 600.00 750.00

0.05 Kg Soda Api 12,000.00 15,000.00 600.00 750.00

C PERALATAN

D Jumlah A + B + C 10,605.00 12,285.00

E Overhead & Profit (contoh 10%) 10% 1,060.50 1,228.50

F Harga Satuan Pekerjaan (D+E) 11,665.50 13,513.50

Pencucian Bidang Permukaan Tembok yang Pernah


2 A.4.7.1.2 1 m2 11,610.50 13,403.50
dicat
A Tenaga 10,005.00 11,535.00

L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00

L.04 0.0030 OH Mandor 85,000.00 95,000.00 255.00 285.00

B Bahan 550.00 650.00

0.05 Kg Sabun 11,000.00 13,000.00 550.00 650.00

C PERALATAN

D Jumlah A + B + C 10,555.00 12,185.00

E Overhead & Profit (contoh 10%) 10% 1,055.50 1,218.50

F Harga Satuan Pekerjaan (D+E) 11,610.50 13,403.50

Pengerokan Karat Cat Lama permukaan Baja dg cara


3 A.4.7.1.3 1 m2 12,078.00 13,926.00
manual
A Tenaga 10,430.00 12,010.00
L.01 0.15 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.04 0.0080 OH Mandor 85,000.00 95,000.00 680.00 760.00
B Bahan 550.00 650.00
0.05 Kg Sabun 11,000.00 13,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 10,980.00 12,660.00
E Overhead & Profit (contoh 10%) 10% 1,098.00 1,266.00
F Harga Satuan Pekerjaan (D+E) 12,078.00 13,926.00

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


4 A.4.7.1.4 1 m2 38,291.00 44,368.50
dasar, 2 Lp Cat Penutup)
A Tenaga 6,065.00 7,050.00
L.01 0.070 OH Pekerja 65,000.00 75,000.00 4,550.00 5,250.00
L.02 0.009 OH Tukang Cat 80,000.00 95,000.00 720.00 855.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 28,745.00 33,285.00
0.2000 kg Cat Menie 25,000.00 30,000.00 5,000.00 6,000.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 34,000.00 36,500.00 5,780.00 6,205.00
0.2600 kg Cat Penutup 50,000.00 58,000.00 13,000.00 15,080.00
0.0100 bh Kuas 7,500.00 8,000.00 75.00 80.00
0.0300 kg Pengencer 18,000.00 20,000.00 540.00 600.00
0.2000 lbr Amplas 3,000.00 4,100.00 600.00 820.00
C PERALATAN
D Jumlah A + B + C 34,810.00 40,335.00
E Overhead & Profit (contoh 10%) 10% 3,481.00 4,033.50
F Harga Satuan Pekerjaan (D+E) 38,291.00 44,368.50

Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat


5 A.4.7.1.5 1 m2 51,491.00 59,900.50
dasar, 3 Lp Cat Penutup)
A Tenaga 13,565.00 15,950.00
L.01 0.070 OH Pekerja 65,000.00 75,000.00 4,550.00 5,250.00
L.02 0.105 OH Tukang Cat 80,000.00 95,000.00 8,400.00 9,975.00
L.03 0.004 OH Kepala Tukang 90,000.00 110,000.00 360.00 440.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00

file:///conversion/tmp/scratch/457687078.xls 130/120 abk 13-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 33,245.00 38,505.00
0.2000 kg Cat Menie 25,000.00 30,000.00 5,000.00 6,000.00
0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00
0.1700 kg Cat Dasar 34,000.00 36,500.00 5,780.00 6,205.00
0.3500 kg Cat Penutup 50,000.00 58,000.00 17,500.00 20,300.00
0.0100 bh Kuas 7,500.00 8,000.00 75.00 80.00
0.0300 kg Pengencer 18,000.00 20,000.00 540.00 600.00
0.2000 lbr Amplas 3,000.00 4,100.00 600.00 820.00
C PERALATAN
D Jumlah A + B + C 46,810.00 54,455.00
E Overhead & Profit (contoh 10%) 10% 4,681.00 5,445.50
F Harga Satuan Pekerjaan (D+E) 51,491.00 59,900.50

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 31,157.50 34,452.00


A Tenaga 13,565.00 16,200.00
L.01 0.04 OH Pekerja 65,000.00 75,000.00 2,600.00 3,000.00
L.02 0.063 OH Tukang Cat 80,000.00 95,000.00 5,040.00 5,985.00
L.03 0.063 OH Kepala Tukang 90,000.00 110,000.00 5,670.00 6,930.00
L.04 0.0030 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 14,760.00 15,120.00
0.36 Ltr Teak Oil 41,000.00 42,000.00 14,760.00 15,120.00
C PERALATAN
D Jumlah A + B + C 28,325.00 31,320.00
E Overhead & Profit (contoh 10%) 10% 2,832.50 3,132.00
F Harga Satuan Pekerjaan (D+E) 31,157.50 34,452.00

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur 53,927.50 61,033.50


A Tenaga 9,095.00 10,745.00
L.01 0.04 OH Pekerja 65,000.00 75,000.00 2,600.00 3,000.00
L.02 0.06 OH Tukang Cat 80,000.00 95,000.00 4,800.00 5,700.00
L.03 0.016 OH Kepala Tukang 90,000.00 110,000.00 1,440.00 1,760.00
L.04 0.0030 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 39,930.00 44,740.00
0.15 Ltr Politur 65,000.00 70,000.00 9,750.00 10,500.00
0.372 Ltr Politur Jadi 65,000.00 70,000.00 24,180.00 26,040.00
2 Lbr Ampelas 3,000.00 4,100.00 6,000.00 8,200.00
C PERALATAN
D Jumlah A + B + C 49,025.00 55,485.00
E Overhead & Profit (contoh 10%) 10% 4,902.50 5,548.50
F Harga Satuan Pekerjaan (D+E) 53,927.50 61,033.50

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 8,769.75 10,032.00
A Tenaga 7,010.00 8,070.00
L.01 0.1 OH Pekerja 65,000.00 75,000.00 6,500.00 7,500.00
L.04 0.006 OH Mandor 85,000.00 95,000.00 510.00 570.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 7,972.50 9,120.00
E Overhead & Profit (contoh 10%) 10% 797.25 912.00
F Harga Satuan Pekerjaan (D+E) 8,769.75 10,032.00

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis 33,214.50 38,395.50


A Tenaga 24,895.00 29,245.00
L.01 0.16 OH Pekerja 65,000.00 75,000.00 10,400.00 12,000.00
L.02 0.16 OH Tukang Cat 80,000.00 95,000.00 12,800.00 15,200.00
L.03 0.016 OH Kepala Tukang 90,000.00 110,000.00 1,440.00 1,760.00
L.04 0.0030 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 5,300.00 5,660.00
0.15 Ltr Vernis 25,000.00 25,000.00 3,750.00 3,750.00
0.05 Ltr Dempul 25,000.00 30,000.00 1,250.00 1,500.00
0.1 Lbr Ampelas 3,000.00 4,100.00 300.00 410.00
- -
C PERALATAN
D Jumlah A + B + C 30,195.00 34,905.00
E Overhead & Profit (contoh 10%) 10% 3,019.50 3,490.50
F Harga Satuan Pekerjaan (D+E) 33,214.50 38,395.50

file:///conversion/tmp/scratch/457687078.xls 130/121 abk 13-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2
10 A.4.7.1.10 1 m2 17,690.20 21,057.30
Lap.Cat Penutup)
A Tenaga 7,162.00 8,463.00
L.01 0.02 OH Pekerja 65,000.00 75,000.00 1,300.00 1,500.00
L.02 0.063 OH Tukang Cat 80,000.00 95,000.00 5,040.00 5,985.00
L.03 0.0063 OH Kepala Tukang 90,000.00 110,000.00 567.00 693.00
L.04 0.0030 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 8,920.00 10,680.00
0.1 Kg Plamir 20,000.00 32,000.00 2,000.00 3,200.00
0.1 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.26 Kg Cat Penutup 2 kali 22,000.00 23,000.00 5,720.00 5,980.00
C PERALATAN
D Jumlah A + B + C 16,082.00 19,143.00
E Overhead & Profit (contoh 10%) 10% 1,608.20 1,914.30
F Harga Satuan Pekerjaan (D+E) 17,690.20 21,057.30

Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat


11 A.4.7.1.11 1 m2 12,334.30 14,054.70
Penutup)
A Tenaga 5,813.00 6,837.00
L.01 0.028 OH Pekerja 65,000.00 75,000.00 1,820.00 2,100.00
L.02 0.042 OH Tukang Cat 80,000.00 95,000.00 3,360.00 3,990.00
L.03 0.0042 OH Kepala Tukang 90,000.00 110,000.00 378.00 462.00
L.04 0.0030 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 5,400.00 5,940.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
0.18 Kg Cat Penutup 2 kali 22,000.00 23,000.00 3,960.00 4,140.00
C PERALATAN
D Jumlah A + B + C 11,213.00 12,777.00
E Overhead & Profit (contoh 10%) 10% 1,121.30 1,277.70
F Harga Satuan Pekerjaan (D+E) 12,334.30 14,054.70

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium 6,856.30 8,070.70


A Tenaga 5,813.00 6,837.00
L.01 0.028 OH Pekerja 65,000.00 75,000.00 1,820.00 2,100.00
L.02 0.042 OH Tukang Cat 80,000.00 95,000.00 3,360.00 3,990.00
L.03 0.0042 OH Kepala Tukang 90,000.00 110,000.00 378.00 462.00
L.04 0.0030 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 420.00 500.00
0.1 Kg Kalkarium 4,200.00 5,000.00 420.00 500.00
- -
C PERALATAN
D Jumlah A + B + C 6,233.00 7,337.00
E Overhead & Profit (contoh 10%) 10% 623.30 733.70
F Harga Satuan Pekerjaan (D+E) 6,856.30 8,070.70

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih 12,967.90 15,073.85


A Tenaga 10,051.50 11,593.50
L.01 0.150 OH Pekerja 65,000.00 75,000.00 9,750.00 11,250.00
L.02 0.001 OH Tukang Cat 80,000.00 95,000.00 80.00 95.00
L.03 0.0001 OH Kepala Tukang 90,000.00 110,000.00 9.00 11.00
L.04 0.0025 OH Mandor 85,000.00 95,000.00 212.50 237.50
B Bahan 1,737.50 2,110.00
0.15 Kg Kapur Sirih 7,500.00 8,000.00 1,125.00 1,200.00
0.1 lbr Amplas 3,000.00 4,100.00 300.00 410.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 11,789.00 13,703.50
E Overhead & Profit (contoh 10%) 10% 1,178.90 1,370.35
F Harga Satuan Pekerjaan (D+E) 12,967.90 15,073.85

Pelaburan Tembok lama dengan Kapur Sirih


14 A.4.7.1.14 1 m2 5,989.50 7,163.75
(pemeliharaan)
A Tenaga 3,257.50 3,767.50
L.01 0.040 OH Pekerja 65,000.00 75,000.00 2,600.00 3,000.00
L.02 0.005 OH Tukang Cat 80,000.00 95,000.00 400.00 475.00
L.03 0.0005 OH Kepala Tukang 90,000.00 110,000.00 45.00 55.00
L.04 0.0025 OH Mandor 85,000.00 95,000.00 212.50 237.50

file:///conversion/tmp/scratch/457687078.xls 130/122 abk 13-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,187.50 2,745.00
0.30 Kg Kapur Sirih 4,250.00 4,750.00 1,275.00 1,425.00
0.2 lbr Amplas 3,000.00 4,100.00 600.00 820.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 5,445.00 6,512.50
E Overhead & Profit (contoh 10%) 10% 544.50 651.25
F Harga Satuan Pekerjaan (D+E) 5,989.50 7,163.75

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper 79,543.75 92,331.25


A Tenaga 19,312.50 22,937.50
L.01 0.020 OH Pekerja 65,000.00 75,000.00 1,300.00 1,500.00
L.02 0.200 OH Tukang Cat 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.0200 OH Kepala Tukang 90,000.00 110,000.00 1,800.00 2,200.00
L.04 0.0025 OH Mandor 85,000.00 95,000.00 212.50 237.50
B Bahan 53,000.00 61,000.00
1.20 lbr Wall Paper 35,000.00 40,000.00 42,000.00 48,000.00
0.2 kg Lem 55,000.00 65,000.00 11,000.00 13,000.00

C PERALATAN
D Jumlah A + B + C 72,312.50 83,937.50
E Overhead & Profit (contoh 10%) 10% 7,231.25 8,393.75
F Harga Satuan Pekerjaan (D+E) 79,543.75 92,331.25

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi 22,266.75 27,618.25


A Tenaga 17,692.50 20,957.50
L.01 0.02 OH Pekerja 65,000.00 75,000.00 1,300.00 1,500.00
L.02 0.2 OH Tukang Cat 80,000.00 95,000.00 16,000.00 19,000.00
L.03 0.002 OH Kepala Tukang 90,000.00 110,000.00 180.00 220.00
L.04 0.0025 OH Mandor 85,000.00 95,000.00 212.50 237.50
B Bahan 2,550.00 4,150.00
0.1 Kg Meni Besi 20,000.00 35,000.00 2,000.00 3,500.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 20,242.50 25,107.50
E Overhead & Profit (contoh 10%) 10% 2,024.25 2,510.75
F Harga Satuan Pekerjaan (D+E) 22,266.75 27,618.25

Pengecatan Permukaan Baja dg Meni Besi &


17 A.4.7.1.17 1 m2 45,581.25 54,326.25
Perancah
A Tenaga 34,887.50 40,837.50
L.01 0.25 OH Pekerja 65,000.00 75,000.00 16,250.00 18,750.00
L.02 0.225 OH Tukang Cat 80,000.00 95,000.00 18,000.00 21,375.00
L.04 0.0075 OH Mandor 85,000.00 95,000.00 637.50 712.50
B Bahan 6,550.00 8,550.00
0.1 Kg Meni Besi 20,000.00 35,000.00 2,000.00 3,500.00
0.01 Kg Perekat / Lem 55,000.00 65,000.00 550.00 650.00
0.002 m3 Perancah Kayu 2,000,000.00 2,200,000.00 4,000.00 4,400.00
C PERALATAN
D Jumlah A + B + C 41,437.50 49,387.50
E Overhead & Profit (contoh 10%) 10% 4,143.75 4,938.75
F Harga Satuan Pekerjaan (D+E) 45,581.25 54,326.25

file:///conversion/tmp/scratch/457687078.xls 130/123 abk 13-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
HARGA SATUAN PEKERJAAN SANITASI DALAM
XIV A.5.1.1
GEDUNG
1 A.5.1.1.1 1 Unit Pemasangan Closet Duduk / Mono Blok 2,038,509.00 2,561,141.00
A Tenaga 316,190.00 367,310.00
L.01 3.3 OH Pekerja 65,000.00 75,000.00 214,500.00 247,500.00
L.02 1.1 OH Tukang Batu 80,000.00 95,000.00 88,000.00 104,500.00
L.03 0.001 OH Kepala Tukang 90,000.00 110,000.00 90.00 110.00
L.04 0.16 OH Mandor 85,000.00 95,000.00 13,600.00 15,200.00
Buah Bahan 1,537,000.00 1,961,000.00
1 Buah Kloset Duduk / Monoblok 1,450,000.00 1,850,000.00 1,450,000.00 1,850,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,450,000.00 1,850,000.00 87,000.00 111,000.00
C PERALATAN
D Jumlah A + B + C 1,853,190.00 2,328,310.00
E Overhead & Profit (contoh 10%) 10% 185,319.00 232,831.00
F Harga Satuan Pekerjaan (D+E) 2,038,509.00 2,561,141.00
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Pemasangan Closet Jongkok Porselen 519,475.00 613,800.00
A Tenaga 333,600.00 397,700.00
L.01 1 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 1.5 OH Tukang Batu 80,000.00 95,000.00 120,000.00 142,500.00
L.03 1.5 OH Kepala Tukang 90,000.00 110,000.00 135,000.00 165,000.00
L.04 0.16 OH Mandor 85,000.00 95,000.00 13,600.00 15,200.00
B Bahan 138,650.00 160,300.00
1 Buah Kloset Jongkok 130,000.00 150,000.00 130,000.00 150,000.00
6 Kg Portland Semen 1,025.00 1,100.00 6,150.00 6,600.00
0.01 m3 Pasir Pasang 250,000.00 370,000.00 2,500.00 3,700.00
C PERALATAN
D Jumlah A + B + C 472,250.00 558,000.00
E Overhead & Profit (contoh 10%) 10% 47,225.00 55,800.00
F Harga Satuan Pekerjaan (D+E) 519,475.00 613,800.00

3 A.5.1.1.4 1 Unit Pemasangan Urinoir 688,765.00 757,130.00


A Tenaga 162,500.00 190,500.00
L.01 1 OH Pekerja 65,000.00 75,000.00 65,000.00 75,000.00
L.02 1 OH Tukang Batu 80,000.00 95,000.00 80,000.00 95,000.00
L.03 0.1 OH Kepala Tukang 90,000.00 110,000.00 9,000.00 11,000.00
L.04 0.1 OH Mandor 85,000.00 95,000.00 8,500.00 9,500.00
B Bahan 463,650.00 497,800.00
1 Buah Urinoir 350,000.00 375,000.00 350,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 350,000.00 375,000.00 105,000.00 112,500.00
6 Kg Portland Semen 1,025.00 1,100.00 6,150.00 6,600.00
0.01 m3 Pasir Pasang 250,000.00 370,000.00 2,500.00 3,700.00
C PERALATAN
D Jumlah A + B + C 626,150.00 688,300.00
E Overhead & Profit (contoh 10%) 10% 62,615.00 68,830.00
F Harga Satuan Pekerjaan (D+E) 688,765.00 757,130.00

4 A.5.1.1.5 1 Unit Pemasangan Wastafel 525,525.00 797,582.50


A Tenaga 111,600.00 129,775.00
L.01 1.2 OH Pekerja 65,000.00 75,000.00 78,000.00 90,000.00
L.02 0.145 OH Tukang Batu 80,000.00 95,000.00 11,600.00 13,775.00
L.03 0.15 OH Kepala Tukang 90,000.00 110,000.00 13,500.00 16,500.00
L.04 0.1 OH Mandor 85,000.00 95,000.00 8,500.00 9,500.00
B Bahan 366,150.00 595,300.00
1 Buah Wastafel 275,000.00 450,000.00 275,000.00 450,000.00
0.3 - Perlengkapan 30% Harga Wastafel 275,000.00 450,000.00 82,500.00 135,000.00
6 Kg Portland Semen 1,025.00 1,100.00 6,150.00 6,600.00
0.01 m3 Pasir Pasang 250,000.00 370,000.00 2,500.00 3,700.00
C PERALATAN
D Jumlah A + B + C 477,750.00 725,075.00
E Overhead & Profit (contoh 10%) 10% 47,775.00 72,507.50
F Harga Satuan Pekerjaan (D+E) 525,525.00 797,582.50

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen 1,069,068.00 1,149,951.00

A Tenaga 71,880.00 85,410.00


L.01 0.075 OH Pekerja 65,000.00 75,000.00 4,875.00 5,625.00
L.02 0.75 OH Tukang Batu 80,000.00 95,000.00 60,000.00 71,250.00
L.03 0.075 OH Kepala Tukang 90,000.00 110,000.00 6,750.00 8,250.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00

file:///conversion/tmp/scratch/457687078.xls 130/124 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 900,000.00 960,000.00
1 Buah Batchuip 750,000.00 800,000.00 750,000.00 800,000.00
0.2 - Perlengkapan 20% Harga Bathcuip 750,000.00 800,000.00 150,000.00 160,000.00
C PERALATAN
D Jumlah A + B + C 971,880.00 1,045,410.00
E Overhead & Profit (contoh 10%) 10% 97,188.00 104,541.00
F Harga Satuan Pekerjaan (D+E) 1,069,068.00 1,149,951.00

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3 1,038,400.00 1,187,450.00


A Tenaga 636,000.00 743,500.00

L.01 3 OH Pekerja 65,000.00 75,000.00 195,000.00 225,000.00


L.02 4.5 OH Tukang Batu 80,000.00 95,000.00 360,000.00 427,500.00
L.03 0.05 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.9 OH Mandor 85,000.00 95,000.00 76,500.00 85,500.00
B Tukang Batu 308,000.00 336,000.00
1 Buah Bak Fibreglass 275,000.00 300,000.00 275,000.00 300,000.00
0.12 - Perlengkapan 12% Bak Fibreglass 275,000.00 300,000.00 33,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 944,000.00 1,079,500.00
E Overhead & Profit (contoh 10%) 10% 94,400.00 107,950.00
F Harga Satuan Pekerjaan (D+E) 1,038,400.00 1,187,450.00

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,309,484.27 1,501,093.54
A Tenaga 659,550.00 770,850.00
L.01 6.00 OH Pekerja 65,000.00 75,000.00 390,000.00 450,000.00
L.02 3.00 OH Tukang Batu 80,000.00 95,000.00 240,000.00 285,000.00
L.03 0.30 OH Kepala Tukang 90,000.00 110,000.00 27,000.00 33,000.00
L.04 0.03 OH Mandor 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 530,890.24 593,780.49
150.0 bh Batu Bata 550.00 600.00 82,500.00 90,000.00
120 Kg Portland Semen 0.11 1,025.00 1,100.00 123,000.00 132,000.00
0.3 m3 Pasir Pasang 0.0121 250,000.00 370,000.00 75,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 11,000.00 12,000.00 66,000.00 72,000.00
C PERALATAN
D Jumlah A + B + C 1,190,440.24 1,364,630.49
E Overhead & Profit (contoh 10%) 10% 119,044.02 136,463.05
F Harga Satuan Pekerjaan (D+E) 1,309,484.27 1,501,093.54

8 A.5.1.1.11 1 Unit Pemasangan Bak Beton Bertulang Vol. 1 m3 6,119,478.78 6,952,874.90


A Tenaga 593,530.00 697,210.00
L.01 3.50 OH Pekerja 65,000.00 75,000.00 227,500.00 262,500.00
L.02 4.50 OH Tukang Batu 80,000.00 95,000.00 360,000.00 427,500.00
L.03 0.05 OH Kepala Tukang 90,000.00 110,000.00 4,500.00 5,500.00
L.04 0.018 OH Mandor 85,000.00 95,000.00 1,530.00 1,710.00
B Bahan 1,086,625.66 1,330,119.30 4,969,632.52 5,623,585.36
0.9 m3 Beton K.150 961,702.50 1,179,004.36 865,532.25 1,061,103.92
180 Kg Baja Tulangan 0.11 13,581.70 14,712.50 2,444,706.00 2,648,250.00
8.0 m2 Kayu Bekisting 0.05 0.0121 110,000.00 135,000.00 880,000.00 1,080,000.00
500 buah Porselen 11 x 11 cm 20 82.6446 1,341.46 1,402.44 670,731.71 701,219.51
10 % Perlengkapan 1,086,625.66 1,330,119.30 108,662.57 133,011.93
C PERALATAN
D Jumlah A + B + C 5,563,162.52 6,320,795.36
E Overhead & Profit (contoh 10%) 10% 556,316.25 632,079.54
F Harga Satuan Pekerjaan (D+E) 6,119,478.78 6,952,874.90

9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 335,417.50 380,022.50
A Tenaga 29,925.00 35,475.00
L.01 0.030 OH Pekerja 65,000.00 75,000.00 1,950.00 2,250.00
L.02 0.300 OH Tukang Batu 80,000.00 95,000.00 24,000.00 28,500.00
L.03 0.030 OH Kepala Tukang 90,000.00 110,000.00 2,700.00 3,300.00
L.04 0.015 OH Mandor 85,000.00 95,000.00 1,275.00 1,425.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 304,925.00 345,475.00
E Overhead & Profit (contoh 10%) 10% 30,492.50 34,547.50
F Harga Satuan Pekerjaan (D+E) 335,417.50 380,022.50

file:///conversion/tmp/scratch/457687078.xls 130/125 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.5.1.1.14 1 buah Pemasangan Floor Drain 27,472.50 51,507.50
A Tenaga 9,975.00 11,825.00
L.01 0.010 OH Pekerja 65,000.00 75,000.00 650.00 750.00
L.02 0.100 OH Tukang Batu 80,000.00 95,000.00 8,000.00 9,500.00
L.03 0.010 OH Kepala Tukang 90,000.00 110,000.00 900.00 1,100.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 15,000.00 35,000.00
1 bh Floor Drain 15,000.00 35,000.00 15,000.00 35,000.00

C PERALATAN
D Jumlah A + B + C 24,975.00 46,825.00
E Overhead & Profit (contoh 10%) 10% 2,497.50 4,682.50
F Harga Satuan Pekerjaan (D+E) 27,472.50 51,507.50

Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi


11 A.5.1.1.15 1 bh 384,500.29 450,345.50
35 cm
A Tenaga 205,415.00 239,365.00
L.01 2.160 OH Pekerja 65,000.00 75,000.00 140,400.00 162,000.00
L.02 0.720 OH Tukang Batu 80,000.00 95,000.00 57,600.00 68,400.00
L.03 0.072 OH Kepala Tukang 90,000.00 110,000.00 6,480.00 7,920.00
L.04 0.011 OH Mandor 85,000.00 95,000.00 935.00 1,045.00
B Bahan 144,130.72 170,040.00
40.00 bh Batu Bata 550.00 600.00 22,000.00 24,000.00
44.00 kg Semen Portland 1,025.00 1,100.00 45,100.00 48,400.00
0.07 m3 Pasir Pasang 250,000.00 370,000.00 17,500.00 25,900.00
0.06 m3 Pasir Beton 350,000.00 500,000.00 21,000.00 30,000.00
0.07 m3 Kerikil 240,000.00 260,000.00 16,800.00 18,200.00
1.60 kg Baja Tulangan 13,581.70 14,712.50 21,730.72 23,540.00
C PERALATAN
D Jumlah A + B + C 349,545.72 409,405.00
E Overhead & Profit (contoh 10%) 10% 34,954.57 40,940.50
F Harga Satuan Pekerjaan (D+E) 384,500.29 450,345.50

Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45


12 A.5.1.1.16 1 bh 561,336.29 660,572.00
tinggi 50 cm
A Tenaga 302,350.00 351,980.00
L.01 3.200 OH Pekerja 65,000.00 75,000.00 208,000.00 240,000.00
L.02 1.150 OH Tukang Batu 80,000.00 95,000.00 92,000.00 109,250.00
L.03 0.011 OH Kepala Tukang 90,000.00 110,000.00 990.00 1,210.00
L.04 0.016 OH Mandor 85,000.00 95,000.00 1,360.00 1,520.00
B Bahan 207,955.72 248,540.00
70.00 bh Batu Bata 550.00 600.00 38,500.00 42,000.00
77.00 kg Semen Portland 1,025.00 1,100.00 78,925.00 84,700.00
0.13 m3 Pasir Pasang 250,000.00 370,000.00 32,500.00 48,100.00
0.09 m3 Pasir Beton 350,000.00 500,000.00 31,500.00 45,000.00
0.02 m3 Kerikil 240,000.00 260,000.00 4,800.00 5,200.00
1.60 kg Baja Tulangan 13,581.70 14,712.50 21,730.72 23,540.00
C PERALATAN
D Jumlah A + B + C 510,305.72 600,520.00
E Overhead & Profit (contoh 10%) 10% 51,030.57 60,052.00
F Harga Satuan Pekerjaan (D+E) 561,336.29 660,572.00

Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi


13 A.5.1.1.17 1 bh 690,273.37 793,997.19
60 cm
A Tenaga 302,350.00 351,980.00
L.01 3.200 OH Pekerja 65,000.00 75,000.00 208,000.00 240,000.00
L.02 1.150 OH Tukang Batu 80,000.00 95,000.00 92,000.00 109,250.00
L.03 0.011 OH Kepala Tukang 90,000.00 110,000.00 990.00 1,210.00
L.04 0.016 OH Mandor 85,000.00 95,000.00 1,360.00 1,520.00
B Bahan 325,171.25 369,835.63
123.00 bh Batu Bata 550.00 600.00 67,650.00 73,800.00
114.00 kg Semen Portland 1,025.00 1,100.00 116,850.00 125,400.00
0.18 m3 Pasir Pasang 250,000.00 370,000.00 46,000.00 68,080.00
0.12 m3 Pasir Beton 240,000.00 260,000.00 28,800.00 31,200.00
4.85 kg Baja Tulangan 13,581.70 14,712.50 65,871.25 71,355.63
C PERALATAN
D Jumlah A + B + C 627,521.25 721,815.63
E Overhead & Profit (contoh 10%) 10% 62,752.12 72,181.56
F Harga Satuan Pekerjaan (D+E) 690,273.37 793,997.19

file:///conversion/tmp/scratch/457687078.xls 130/126 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
14 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½" 39,350.67 47,608.00
A Tenaga 13,815.00 16,155.00
L.01 0.054 OH Pekerja 65,000.00 75,000.00 3,510.00 4,050.00
L.02 0.090 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.027 OH Mandor 85,000.00 95,000.00 2,295.00 2,565.00
B Bahan 21,958.33 27,125.00
1.20 m' Pipa Galvanis Ø ½" 14,166.67 17,500.00 17,000.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 14,166.67 17,500.00 4,958.33 6,125.00
C PERALATAN
D Jumlah A + B + C 35,773.33 43,280.00
E Overhead & Profit (contoh 10%) 10% 3,577.33 4,328.00
F Harga Satuan Pekerjaan (D+E) 39,350.67 47,608.00

15 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 78,848.00 97,498.78


A Tenaga 36,675.00 43,625.00
L.01 0.010 OH Pekerja 65,000.00 75,000.00 650.00 750.00
L.02 0.400 OH Tukang Batu 80,000.00 95,000.00 32,000.00 38,000.00
L.03 0.040 OH Kepala Tukang 90,000.00 110,000.00 3,600.00 4,400.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 35,005.00 45,010.25
1.00 bh Kran Air 35,000.00 45,000.00 35,000.00 45,000.00
0.0025 bh Sealtape 2,000.00 4,100.00 5.00 10.25
C PERALATAN
D Jumlah A + B + C 71,680.00 88,635.25
E Overhead & Profit (contoh 10%) 10% 7,168.00 8,863.53
F Harga Satuan Pekerjaan (D+E) 78,848.00 97,498.78

16 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾" 47,875.67 60,395.50


A Tenaga 13,815.00 16,155.00
L.01 0.054 OH Pekerja 65,000.00 75,000.00 3,510.00 4,050.00
L.02 0.090 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.027 OH Mandor 85,000.00 95,000.00 2,295.00 2,565.00
B Bahan 29,708.33 38,750.00
1.20 m' Pipa Galvanis Ø ¾" 19,166.67 25,000.00 23,000.00 30,000.00
0.35 Ls Perlengkapan 35% x pipa 19,166.67 25,000.00 6,708.33 8,750.00
C PERALATAN
D Jumlah A + B + C 43,523.33 54,905.00
E Overhead & Profit (contoh 10%) 10% 4,352.33 5,490.50
F Harga Satuan Pekerjaan (D+E) 47,875.67 60,395.50

17 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1" 53,559.00 68,920.50


A Tenaga 13,815.00 16,155.00
L.01 0.054 OH Pekerja 65,000.00 75,000.00 3,510.00 4,050.00
L.02 0.090 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.027 OH Mandor 85,000.00 95,000.00 2,295.00 2,565.00
B Bahan 34,875.00 46,500.00
1.20 m' Pipa Galvanis Ø 1" 22,500.00 30,000.00 27,000.00 36,000.00
0.35 Ls Perlengkapan 35% x pipa 22,500.00 30,000.00 7,875.00 10,500.00
C PERALATAN
D Jumlah A + B + C 48,690.00 62,655.00
E Overhead & Profit (contoh 10%) 10% 4,869.00 6,265.50
F Harga Satuan Pekerjaan (D+E) 53,559.00 68,920.50

18 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ " 74,119.83 92,937.17


A Tenaga 23,465.00 27,655.00
L.01 0.108 OH Pekerja 65,000.00 75,000.00 7,020.00 8,100.00
L.02 0.180 OH Tukang Batu 80,000.00 95,000.00 14,400.00 17,100.00
L.03 0.018 OH Kepala Tukang 90,000.00 110,000.00 1,620.00 1,980.00
L.04 0.005 OH Mandor 85,000.00 95,000.00 425.00 475.00
B Bahan 43,916.67 56,833.33
1.20 m' Pipa Galvanis Ø 1½" 28,333.33 36,666.67 34,000.00 44,000.00
0.35 Ls Perlengkapan 35% x pipa 28,333.33 36,666.67 9,916.67 12,833.33
C PERALATAN
D Jumlah A + B + C 67,381.67 84,488.33
E Overhead & Profit (contoh 10%) 10% 6,738.17 8,448.83
F Harga Satuan Pekerjaan (D+E) 74,119.83 92,937.17

file:///conversion/tmp/scratch/457687078.xls 130/127 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
19 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3" 151,734.00 177,406.17
A Tenaga 29,440.00 34,695.00
L.01 0.135 OH Pekerja 65,000.00 75,000.00 8,775.00 10,125.00
L.02 0.225 OH Tukang Batu 80,000.00 95,000.00 18,000.00 21,375.00
L.03 0.023 OH Kepala Tukang 90,000.00 110,000.00 2,070.00 2,530.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 108,500.00 126,583.33
1.20 m' Pipa Galvanis Ø 3" 70,000.00 81,666.67 84,000.00 98,000.00
0.35 Ls Perlengkapan 35% x pipa 70,000.00 81,666.67 24,500.00 28,583.33
C PERALATAN
D Jumlah A + B + C 137,940.00 161,278.33
E Overhead & Profit (contoh 10%) 10% 13,794.00 16,127.83
F Harga Satuan Pekerjaan (D+E) 151,734.00 177,406.17

20 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4" 271,084.00 285,389.50


A Tenaga 29,440.00 34,695.00
L.01 0.135 OH Pekerja 65,000.00 75,000.00 8,775.00 10,125.00
L.02 0.225 OH Tukang Batu 80,000.00 95,000.00 18,000.00 21,375.00
L.03 0.023 OH Kepala Tukang 90,000.00 110,000.00 2,070.00 2,530.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 217,000.00 224,750.00
1.20 m' Pipa Galvanis Ø 4" 140,000.00 145,000.00 168,000.00 174,000.00
0.35 Ls Perlengkapan 35% x pipa 140,000.00 145,000.00 49,000.00 50,750.00
C PERALATAN
D Jumlah A + B + C 246,440.00 259,445.00
E Overhead & Profit (contoh 10%) 10% 24,644.00 25,944.50
F Harga Satuan Pekerjaan (D+E) 271,084.00 285,389.50

21 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½" 19,291.25 22,962.50


A Tenaga 7,850.00 9,250.00
L.01 0.036 OH Pekerja 65,000.00 75,000.00 2,340.00 2,700.00
L.02 0.060 OH Tukang Batu 80,000.00 95,000.00 4,800.00 5,700.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00
B Bahan 9,687.50 11,625.00
1.20 m' Pipa PVC Ø ½" 6,250.00 7,500.00 7,500.00 9,000.00
0.35 Ls Perlengkapan 35% x pipa 6,250.00 7,500.00 2,187.50 2,625.00
C PERALATAN
D Jumlah A + B + C 17,537.50 20,875.00
E Overhead & Profit (contoh 10%) 10% 1,753.75 2,087.50
F Harga Satuan Pekerjaan (D+E) 19,291.25 22,962.50

22 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 21,422.50 25,520.00


A Tenaga 7,850.00 9,250.00
L.01 0.036 OH Pekerja 65,000.00 75,000.00 2,340.00 2,700.00
L.02 0.060 OH Tukang Batu 80,000.00 95,000.00 4,800.00 5,700.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00
B Bahan 11,625.00 13,950.00
1.20 m' Pipa PVC Ø ¾" 7,500.00 9,000.00 9,000.00 10,800.00
0.35 Ls Perlengkapan 35% x pipa 7,500.00 9,000.00 2,625.00 3,150.00
C PERALATAN
D Jumlah A + B + C 19,475.00 23,200.00
E Overhead & Profit (contoh 10%) 10% 1,947.50 2,320.00
F Harga Satuan Pekerjaan (D+E) 21,422.50 25,520.00

23 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1" 24,406.25 29,356.25


A Tenaga 7,850.00 9,250.00
L.01 0.036 OH Pekerja 65,000.00 75,000.00 2,340.00 2,700.00
L.02 0.060 OH Tukang Batu 80,000.00 95,000.00 4,800.00 5,700.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00
B Bahan 14,337.50 17,437.50
1.20 m' Pipa PVC Ø 1" 9,250.00 11,250.00 11,100.00 13,500.00
0.35 Ls Perlengkapan 35% x pipa 9,250.00 11,250.00 3,237.50 3,937.50
C PERALATAN
D Jumlah A + B + C 22,187.50 26,687.50
E Overhead & Profit (contoh 10%) 10% 2,218.75 2,668.75
F Harga Satuan Pekerjaan (D+E) 24,406.25 29,356.25

file:///conversion/tmp/scratch/457687078.xls 130/128 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
24 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½" 26,024.17 34,585.83
A Tenaga 11,775.00 13,875.00
L.01 0.054 OH Pekerja 65,000.00 75,000.00 3,510.00 4,050.00
L.02 0.090 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 11,883.33 17,566.67
1.20 m' Pipa PVC Ø 1½" 7,666.67 11,333.33 9,200.00 13,600.00
0.35 Ls Perlengkapan 35% x pipa 7,666.67 11,333.33 2,683.33 3,966.67
C PERALATAN
D Jumlah A + B + C 23,658.33 31,441.67
E Overhead & Profit (contoh 10%) 10% 2,365.83 3,144.17
F Harga Satuan Pekerjaan (D+E) 26,024.17 34,585.83

25 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 30,002.50 45,100.00


A Tenaga 11,775.00 13,875.00
L.01 0.054 OH Pekerja 65,000.00 75,000.00 3,510.00 4,050.00
L.02 0.090 OH Tukang Batu 80,000.00 95,000.00 7,200.00 8,550.00
L.03 0.009 OH Kepala Tukang 90,000.00 110,000.00 810.00 990.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 15,500.00 27,125.00
1.20 m' Pipa PVC Ø 2" 10,000.00 17,500.00 12,000.00 21,000.00
0.35 Ls Perlengkapan 35% x pipa 10,000.00 17,500.00 3,500.00 6,125.00
C PERALATAN
D Jumlah A + B + C 27,275.00 41,000.00
E Overhead & Profit (contoh 10%) 10% 2,727.50 4,100.00
F Harga Satuan Pekerjaan (D+E) 30,002.50 45,100.00

26 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 53,624.08 75,412.33


A Tenaga 17,620.00 20,765.00
L.01 0.081 OH Pekerja 65,000.00 75,000.00 5,265.00 6,075.00
L.02 0.135 OH Tukang Batu 80,000.00 95,000.00 10,800.00 12,825.00
L.03 0.0135 OH Kepala Tukang 90,000.00 110,000.00 1,215.00 1,485.00
L.04 0.004 OH Mandor 85,000.00 95,000.00 340.00 380.00
B Bahan 31,129.17 47,791.67
1.20 m' Pipa PVC Ø 3" 20,083.33 30,833.33 24,100.00 37,000.00
0.35 Ls Perlengkapan 35% x pipa 20,083.33 30,833.33 7,029.17 10,791.67
C PERALATAN
D Jumlah A + B + C 48,749.17 68,556.67
E Overhead & Profit (contoh 10%) 10% 4,874.92 6,855.67
F Harga Satuan Pekerjaan (D+E) 53,624.08 75,412.33

27 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4" 59,785.00 89,741.67


A Tenaga 7,850.00 9,250.00
L.01 0.036 OH Pekerja 65,000.00 75,000.00 2,340.00 2,700.00
L.02 0.060 OH Tukang Batu 80,000.00 95,000.00 4,800.00 5,700.00
L.03 0.006 OH Kepala Tukang 90,000.00 110,000.00 540.00 660.00
L.04 0.002 OH Mandor 85,000.00 95,000.00 170.00 190.00
B Bahan 46,500.00 72,333.33
1.20 m' Pipa PVC Ø 4" 30,000.00 46,666.67 36,000.00 56,000.00
0.35 Ls Perlengkapan 35% x pipa 30,000.00 46,666.67 10,500.00 16,333.33
C PERALATAN
D Jumlah A + B + C 54,350.00 81,583.33
E Overhead & Profit (contoh 10%) 10% 5,435.00 8,158.33
F Harga Satuan Pekerjaan (D+E) 59,785.00 89,741.67

28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 73,386.50 84,392.00
cm
A Tenaga 9,100.00 10,620.00
L.01 0.080 OH Pekerja 65,000.00 75,000.00 5,200.00 6,000.00
L.02 0.040 OH Tukang Batu 80,000.00 95,000.00 3,200.00 3,800.00
L.03 0.004 OH Kepala Tukang 90,000.00 110,000.00 360.00 440.00
L.04 0.004 OH Mandor 85,000.00 95,000.00 340.00 380.00
B Bahan 57,615.00 66,100.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,025.00 1,100.00 35,875.00 38,500.00
0.014 m3 Pasir Pasang 250,000.00 370,000.00 3,500.00 5,180.00
0.014 m3 Pasir Urug 160,000.00 230,000.00 2,240.00 3,220.00
- -

file:///conversion/tmp/scratch/457687078.xls 130/129 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 66,715.00 76,720.00
E Overhead & Profit (contoh 10%) 10% 6,671.50 7,672.00
F Harga Satuan Pekerjaan (D+E) 73,386.50 84,392.00

Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15


29 A.5.1.1.34 1 m' 34,765.50 41,783.50
cm
A Tenaga 6,825.00 7,965.00
L.01 0.060 OH Pekerja 65,000.00 75,000.00 3,900.00 4,500.00
L.02 0.030 OH Tukang Batu 80,000.00 95,000.00 2,400.00 2,850.00
L.03 0.003 OH Kepala Tukang 90,000.00 110,000.00 270.00 330.00
L.04 0.003 OH Mandor 85,000.00 95,000.00 255.00 285.00
B Bahan 24,780.00 30,020.00
1.60 bh pipa tanah 8,000.00 9,500.00 12,800.00 15,200.00
6.80 kg Semen Portlan 1,025.00 1,100.00 6,970.00 7,480.00
0.013 m3 Pasir Pasang 250,000.00 370,000.00 3,250.00 4,810.00
0.011 m3 Pasir Urug 160,000.00 230,000.00 1,760.00 2,530.00
,
C PERALATAN
D Jumlah A + B + C 31,605.00 37,985.00
E Overhead & Profit (contoh 10%) 10% 3,160.50 3,798.50
F Harga Satuan Pekerjaan (D+E) 34,765.50 41,783.50

30 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 15 - 20 cm 96,162.55 127,915.70


A Tenaga 15,925.00 18,585.00
L.01 0.140 OH Pekerja 65,000.00 75,000.00 9,100.00 10,500.00
L.02 0.070 OH Tukang Batu 80,000.00 95,000.00 5,600.00 6,650.00
L.03 0.007 OH Kepala Tukang 90,000.00 110,000.00 630.00 770.00
L.04 0.007 OH Mandor 85,000.00 95,000.00 595.00 665.00
B Bahan 71,495.50 97,702.00
1.10 bh pipa beton 35,000.00 50,000.00 38,500.00 55,000.00
0.027 m3 Batu Bata 412,500.00 450,000.00 11,137.50 12,150.00
3.920 kg Semen Portlan 1,025.00 1,100.00 4,018.00 4,312.00
0.056 m3 Pasir Pasang 250,000.00 370,000.00 14,000.00 20,720.00
0.024 m3 Pasir Urug 160,000.00 230,000.00 3,840.00 5,520.00
C PERALATAN
D Jumlah A + B + C 87,420.50 116,287.00
E Overhead & Profit (contoh 10%) 10% 8,742.05 11,628.70
F Harga Satuan Pekerjaan (D+E) 96,162.55 127,915.70

31 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 30 - 100 cm 543,298.25 594,929.50


A Tenaga 43,225.00 50,445.00
L.01 0.380 OH Pekerja 65,000.00 75,000.00 24,700.00 28,500.00
L.02 0.190 OH Tukang Batu 80,000.00 95,000.00 15,200.00 18,050.00
L.03 0.019 OH Kepala Tukang 90,000.00 110,000.00 1,710.00 2,090.00
L.04 0.019 OH Mandor 85,000.00 95,000.00 1,615.00 1,805.00
B Bahan 450,682.50 490,400.00
1.10 bh pipa beton 180,000.00 190,000.00 198,000.00 209,000.00
0.55 m3 Batu Bata 412,500.00 450,000.00 226,875.00 247,500.00
10.300 kg Semen Portlan 1,025.00 1,100.00 10,557.50 11,330.00
0.061 m3 Pasir Pasang 250,000.00 370,000.00 15,250.00 22,570.00
0.069 m3 Pasir Urug 160,000.00 230,000.00 11,040.00 15,870.00
C PERALATAN
D Jumlah A + B + C 493,907.50 540,845.00
E Overhead & Profit (contoh 10%) 10% 49,390.75 54,084.50
F Harga Satuan Pekerjaan (D+E) 543,298.25 594,929.50

file:///conversion/tmp/scratch/457687078.xls 130/130 abk 14-14

Anda mungkin juga menyukai