SCHEDULE AND NETWORK PLANING

PROJECT : CLUSTER TYPE 36


ID Task Name Duration Start Finish Predecessors 23 Nov '15 30 Nov '15 07 Dec '15
S S M T W T F S S M T W T F S S M T W T F S
1 PROYEK PEMBANGUNAN CLUSTER TYPE 36 15 days Mon 23/11/15 Fri 11/12/15
2
3 Pekerjaan Persiapan 3 days Mon 23/11/15 Wed 25/11/15
4
5 Pekerjaan Tanah 1 day Wed 25/11/15 Wed 25/11/15 3SS+2 days
6
7 Pekerjaan Pondasi Batu Kali 1 day Thu 26/11/15 Thu 26/11/15 5
8
9 Pekerjaan Struktural 3 days Fri 27/11/15 Tue 01/12/15 7
10
11 Pekerjaan Dinding dan Pengecatan 5 days Tue 01/12/15 Mon 07/12/15 9SS+2 days
12
13 Pekerjaan Pintu dan Jendela 2 days Fri 04/12/15 Mon 07/12/15 11FF
14
15 Pekerjaan Atap 3 days Fri 04/12/15 Tue 08/12/15 11SS+3 days
16
17 Pekerjaan Plafond 2 days Tue 08/12/15 Wed 09/12/15 15SS+2 days
18
19 Pekerjaan Keramik 3 days Wed 09/12/15 Fri 11/12/15 17SS+1 day
20
21 Pekerjaan Instalasi Listrik 1 day Mon 07/12/15 Mon 07/12/15 11FF
22
23 Pekerjaan Instalasi Air 1 day Mon 07/12/15 Mon 07/12/15 11FF
24
25 Pekerjaan Septictank dan Rembesan 1 day Fri 11/12/15 Fri 11/12/15 19FF

Task Rolled Up Task External Tasks


Critical Task Rolled Up Critical Task Project Summary
Project: Schedule Pembangunan Clus
Progress Rolled Up Milestone Group By Summary
Date: Thu 26/11/15
Milestone Rolled Up Progress Deadline
Summary Split

Page 1