Anda di halaman 1dari 1

REKAPITULASI

RENCANA ANGGARAN BIAYA

PEKERJAAN : PEMBANGUNAN JALAN RABAT BETON


LOKASI : RT.48

PAPAN
PANJANG RABAT VOLUME BATU KERIKIL / MALL L= 10 KAYU 4/6 PAKU
SEMEN ZAK PASIR / M3
BETON M1 BETON / M3 PECAH SPLIT /M3 P=4M BATANG /KG
NO URAIAN KETERANGAN
/BATANG

MATERIAL DIDANAI
A VOLUME dan JUMLAH MATERIAL RABAT BETON ( BANGKIT BERDAYA) PANJANG OLEH BANGKIT
(90 X 3 X 0.1 )M 27 176 15.00 20 23 23 2 BERDAYA

1 JALAN DEPAN RUMAH PAK Dr.ALFINDRA /DEPAN TAMAN 32 X 7M 22.4 156.80 11.70 17.11 12.00 13.00 1.00
2 JALAN SAMPING RUMAH Dr.IKHSAN SAMPAI SAMBUNGAN RIGIT LAMA (TAMAN) 25 X 7 M 17.5 122.50 9.14 18.26 11.00 10.00 1.00

TOTAL JUMLAH KEBUTUHAN VOLUME / MATERIAL BERDASARKAN RENCANA


B KEBUTUHAN DAN KONDISI EXISTING (80 X 4.8 X 0.1) M (SESUAI GAMBAR) 57 M 39.9 279.30 20.83 35.37 23.00 23.00 2.00
DIDANAI OLEH
SWADAYA
C JUMLAH KEBUTUHAN KEKURANGAN VOLUME / MATERIAL B - A 12.9 103.30 5.83 15.37 - - - MASYARAKAT MELALUI
UANG KAS
LINGKUNGAN
D. PEMBULATAN MATERIAL 13 104 6 16 8

;=== CATATAN VOLUME DAN JUMLAH MATERIAL DIBULATKAN

TOTAL RENCANA PENAMBAHAN VOLUME / MATERIAL JALAN RABAT BETON ARGENTINA MENGGUNAKAN DANA SWADAYA

UPAH COR /M3 39.9 250,000.00 9,975,000.00


SEMEN 104.00 ZAK 65,000.00 6,760,000.00
BATU SPLIT 16.00 M3 400,000.00 6,400,000.00
PASIR 6.00 M3 120,000.00 720,000.00
PAPAN MALL 8.00 KPG 20,000.00 160,000.00

JUMLAH TOTAL BIAYA SWADAYA SESUAI RENCANA 23,855,000.00

Anda mungkin juga menyukai