JADWAL PELAKSANAAN PEKERJAAN (KURVA S)

PEMBUATAN GUDANG TERBUKA PELABUHAN BUMIHARJO (CANGKANG)

Juli-2019 Agustus-2019 September-2019 Oktober-2019 November-2019 Desember-2019 Januari-2019


Volume Bobot %
No Uraian Sat. Ket M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 KET
15-Jul-19 20-Jul-19 27-Jul-19 3-Aug-19 10-Aug-19 17-Aug-19 24-Aug-19 31-Aug-19 7-Sep-19 14-Sep-19 21-Sep-19 28-Sep-19 5-Oct-19 12-Oct-19 19-Oct-19 26-Oct-19 2-Nov-19 9-Nov-19 16-Nov-19 23-Nov-19 30-Nov-19 7-Dec-19 14-Dec-19 21-Dec-19 28-Dec-19 4-Jan-20
KONTRAK ADD KONTRAK ADD
19-Jul-19 26-Jul-19 2-Aug-19 9-Aug-19 16-Aug-19 23-Aug-19 30-Aug-19 6-Sep-19 13-Sep-19 20-Sep-19 27-Sep-19 4-Oct-19 11-Oct-19 18-Oct-19 25-Oct-19 1-Nov-19 8-Nov-19 15-Nov-19 22-Nov-19 29-Nov-19 6-Dec-19 13-Dec-19 20-Dec-19 27-Dec-19 3-Jan-20 10-Jan-20

100 %
I Pekerjaan Persiapan
RENCANA 0,194 0,194 0,194 0,194 0,194 0,194
1 Mobilisasi dan Demobilisasi 1,00 1,00 ls 1,27 1,17
REALISASI 0,211 0,211 0,211 0,211 0,211 0,211
RENCANA 0,387 0,387
2 Pembersihan Lokasi 1.000,00 1.077,38 m2 0,78 0,77
REALISASI 0,782 0,056
3 RENCANA 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002 0,002
Uji dan Laporan Laboratorium 1,00 1,00 paket 0,04 0,04
REALISASI 0,017 0,002 0,004 0,002 0,002 0,002 0,002 0,002 0,008
II Pekerjaan Tanah
RENCANA 0,218 0,218
1 Galian Tanah Pondasi Telapak 82,50 82,50 m3 0,47 0,44
REALISASI 0,237 0,237
RENCANA 0,117
2 Urugan Kembali Pondasi Telapak 24,75 51,90 m3 0,06 0,12
REALISASI 0,061 0,061
3

III
Galian Untuk Saluran

Pekerjaan Beton Bertulang


46,80 61,52 m3 0,27 0,32
RENCANA
REALISASI
0,081
0,101
0,081
0,168
0,081 0,081
0,000 0,078 90 %
RENCANA 5,313
1 Pekerjaan pondasi telapak (K-250) 22,00 22,00 m3 5,78 5,31
REALISASI 5,782
RENCANA 1,623 1,623
2 Pekerjaan sloof 25/40 (K-250) 8,60 8,60 m3 3,53 3,25
REALISASI 3,532 0,143
RENCANA 3,897 3,897 3,897 3,897
3 Pekerjaan pelat lantai Tebal 20 Cm (K-300) 91,20 91,20 m3 16,96 15,59
REALISASI 8,482 8,482
RENCANA 1,120 1,120
4 Pekerjaan tiang kolom pedestal 35/20 (K-250) 4,38 4,38 m3 2,44 2,24
REALISASI 0,780 1,370 0,269
RENCANA 0,060 0,060
5 Pekerjaan Tiang Kolom Praktis 13/13 (K-225) 0,24 0,24 m3 0,13 0,12

80 %
REALISASI 0,110 0,018
RENCANA 0,541 0,541
6 Pekerjaan Ringbalok 15/15 (K-250) 1,94 1,94 m3 1,18 1,08
REALISASI 0,832 0,317
RENCANA 0,478
7 Ramp Beton (K-300) 2,79 2,79 m3 0,52 0,48
REALISASI 0,520
RENCANA 0,233 0,233 0,233
8 Lantai Kerja Pelat lantai setebal 5 cm (B-0) 22,80 22,80 m3 0,76 0,70
REALISASI 0,555 0,205
RENCANA 0,084
9 Lantai Kerja Pondasi (B-0) 2,75 2,75 m3 0,09 0,08
REALISASI 0,092
IV Pekerjaan Pasangan
RENCANA 0,310 0,310
1 Pasangan 1/2 bata 1 Pc : 5 Ps 62,00 59,60 m2 0,70 0,62
REALISASI 0,556 0,109
RENCANA 0,653
2 Plesteran 1 Pc : 5 Pc 124,00 151,40 m2 0,58 0,65

70 %
REALISASI 0,559 0,139
RENCANA 0,326
3 Pekerjaan Acian 124,00 151,40 m2 0,29 0,33
REALISASI 0,279 0,069
V Pekerjaan Instalasi Listrik
RENCANA 0,652
1 Pemasangan Lampu Sorot LED + Instalasi 6,00 6,00 titik 0,71 0,65
REALISASI 0,652
RENCANA 0,023
2 MCB 10A 2,00 2,00 titik 0,03 0,02
REALISASI 0,023
RENCANA 0,031
3 Box Panel Uk. 25x35x12 cm 1,00 1,00 titik 0,03 0,03
REALISASI 0,031
VI Pekerjaan Atap
RENCANA 2,481 2,481
1 Kolom Baja WF 400x200x8x12 2.640,00 2.640,00 kg 5,40 4,96
REALISASI 5,401

60 %
RENCANA 3,671 3,671
2 Rafter WF 300x150x6,5x9 4.057,19 3.905,61 kg 8,30 7,34
REALISASI 5,401 0,000
RENCANA 1,726 1,726
3 Regel WF 200x150x6x9 1.836,00 1.836,00 kg 3,76 3,45
REALISASI 7,989 Reschedule
RENCANA 2,264 2,264
4 Gording Baja Canal 125x50x20x3 3.005,60 3.005,60 kg 4,93 4,53
REALISASI 3,756
RENCANA 0,035 0,035
5 Backing Gording L 50.50.5 37,70 37,70 kg 0,08 0,07
REALISASI 4,929
RENCANA 0,593 0,593
6 Ikatan angin besi dia. 16 mm 294,40 376,93 kg 1,01 1,19
REALISASI 0,077 1,008 0,260
RENCANA 0,278 0,278
7 Ikatan Antar Gording (Sargod) Dia. 12 mm 172,80 176,64 kg 0,59 0,56
REALISASI 0,592 0,012
RENCANA 0,194 0,194
8 Angker Dia. 19 mm 40,00 40,00 bh 0,42 0,39

50 %
REALISASI 0,423
RENCANA 0,033 0,033
9 Baut M20 210,00 210,00 bh 0,07 0,07
REALISASI 0,071
RENCANA 0,031 0,031
10 Baut gording M12 mm 200,00 200,00 bh 0,07 0,06
REALISASI 0,068
RENCANA 0,155 0,155
11 Baseplate 130,56 130,56 kg 0,34 0,31
REALISASI 0,337
RENCANA 0,578 0,578
12 Endplate 522,24 488,40 kg 1,35 1,16
REALISASI 1,259
RENCANA 0,262 0,262
13 Plat Pengaku Badan dan Stiffeners 221,37 221,37 kg 0,57 0,52
REALISASI 0,571
RENCANA 2,542 2,542
14 Penutup Atap Dari Zincalum 553,28 553,28 m2 5,53 5,08
REALISASI 5,533

40 %
Juli-2019 Agustus-2019 September-2019 Oktober-2019 November-2019 Desember-2019 Januari-2019
Volume Bobot %
No Uraian Sat. Ket M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24 M25 M26 KET
15-Jul-19 20-Jul-19 27-Jul-19 3-Aug-19 10-Aug-19 17-Aug-19 24-Aug-19 31-Aug-19 7-Sep-19 14-Sep-19 21-Sep-19 28-Sep-19 5-Oct-19 12-Oct-19 19-Oct-19 26-Oct-19 2-Nov-19 9-Nov-19 16-Nov-19 23-Nov-19 30-Nov-19 7-Dec-19 14-Dec-19 21-Dec-19 28-Dec-19 4-Jan-20
KONTRAK ADD KONTRAK ADD
19-Jul-19 26-Jul-19 2-Aug-19 9-Aug-19 16-Aug-19 23-Aug-19 30-Aug-19 6-Sep-19 13-Sep-19 20-Sep-19 27-Sep-19 4-Oct-19 11-Oct-19 18-Oct-19 25-Oct-19 1-Nov-19 8-Nov-19 15-Nov-19 22-Nov-19 29-Nov-19 6-Dec-19 13-Dec-19 20-Dec-19 27-Dec-19 3-Jan-20 10-Jan-20
VII
1
Pekerjaan Drainase dan Sanitasi
Pekerjaan Talang Air 52,00 52,00 m1 0,53 0,49
RENCANA
REALISASI
0,487
0,530
100
40 %%
RENCANA 0,136
2 Pipa Vertikal dari Talang Air 24,00 21,00 m1 0,17 0,14
REALISASI 0,170
RENCANA 0,356 0,356 0,356 0,356
3 Pekerjaan Pasangan Batu Kali 37,25 17,97 m3 3,21 1,42
REALISASI 0,616 1,024 0,420 0,074
RENCANA 0,143 0,143 0,143 0,143
4 Pekerjaan Plesteran 141,30 132,46 m2 0,66 0,57
REALISASI 0,180 0,300 0,142
RENCANA 0,023 0,023
5 Pekerjaan Rabat Beton (untuk dibawah saluran) 4,71 1,52 m3 0,16 0,05
REALISASI 0,060 0,028
VIII Pekerjaan Pengecatan
RENCANA 0,274
1 Pekerjaan Cat Tembok 124,00 124,00 m2 0,30 0,27

30 %
REALISASI 0,274
RENCANA 0,618 0,618
2 Pekerjaan Cat Besi 243,91 357,46 m2 0,92 1,24
REALISASI 0,917 0,392
IX Pekerjaan Pengadaan Container
Pengadaan Container Office + Toilet 2 uk. 20 RENCANA -
1 1,00 - unit 5,16 -
feet (Inc elektrical dan Sanitasi dalam)
REALISASI

Sanitasi (Tandon Air, Biofill, Pipa Air Bersih, dan RENCANA -


2 1,00 - ls 0,93 -
Pipa Air Kotor)
REALISASI
B. PEKERJAAN LANDSCAPE GUDANG TERBUKA
I Pekerjaan Tanah
Pekerjaan pematangan lahan (galian &
1 peralatan) s/d elevasi rencana
(Area Gudang dan Parkir)
2.081,96 1.754,67 m3 4,22 3,27
RENCANA

REALISASI
1,635

1,056
1,635

2,504
20 %
Pengadaan dan Pemasangan Cerucuk galam RENCANA 2,423 2,423
2 - 1.920,00 titik - 4,85
D=10Cm , jarak 50cm , t=2m REALISASI 4,847
II Pekerjaan Paving Block
RENCANA 1,498 1,498
Pekerjaan Paving Block K-400
1 521,31 150,00 m2 11,33 3,00
(Termasuk Sand Bedding)
REALISASI 1,631 1,498
RENCANA 0,420 0,420 0,420
2 Base Coarse A (CBR 70%) 114,69 74,30 m3 2,12 1,26
REALISASI 0,646
Pekerjaan Beton bertulang K-250 (Wiremesh RENCANA 1,240 1,240 1,240 1,240

10 %
3 29,22 m3 - 4,96
M10-1 Lapis) dibawah Paving REALISASI 4,959
III Pekerjaan Beton Bertulang
RENCANA 0,175 0,175
1 Pembongkaran Beton Bertulang 9,65 9,13 m3 0,40 0,35
REALISASI 0,251 0,119
RENCANA -
2 Pekerjaan Plat Beton Bertulang 4,55 - m3 0,85 -
REALISASI
Pekerjaan Beton bertulang K-250 RENCANA 2,314 2,314 2,314 2,314 2,314
3 68,18 m3 - 11,57
(Wiremesh M10-1 Lapis) REALISASI 11,571
RENCANA 0,575 0,575 0,575 0,575
4 Pekerjaan Beton Jembatan Diatas Saluran 4,55 m3 - 2,30
REALISASI 2,301
RENCANA 0,289 0,289
5 Base Coarse A (CBR 70%) Dibawah Beton 34,09 m3 - 0,58
REALISASI 0,579

Rencana Progress
Total 100,00 100,00
0,211 0,211 0,368 1,227 1,212 1,371 1,294 3,095 1,958 3,955 3,217 1,240 5,908 5,922 9,495 5,292 6,516 6,664 7,014 7,014 4,561 1,745 5,077 10,408 3,979 1,047
0%
Kumulatif Rencana 0,211 0,423 0,790 2,017 3,229 4,600 5,894 8,989 10,947 14,902 18,119 19,359 25,267 31,189 40,684 45,976 52,492 59,156 66,170 73,183 77,744 79,489 84,566
Kontrak

Realisasi Progress 0,210 0,993 2,461 4,536 6,771 0,211 - 0,020 - 0,002 0,483 - 5,481 3,267 9,525 8,837 24,459 2,519 0,002 0,002 - 6,232 2,150
Kumulatif Realisasi 0,210 1,203 3,664 8,200 14,971 15,182 15,182 15,202 15,202 15,204 15,688 15,688 21,168 24,435 33,960 42,798 67,257 69,776 69,778 69,780 69,780 76,012 78,163
Deviasi (0,001) 0,781 2,873 6,183 11,742 10,582 9,289 6,213 4,255 0,302 (2,431) (3,671) (4,098) (6,754) (6,724) (3,178) 14,765 10,620 3,608 (3,403) (7,964) (3,477) (6,403)
Rencana Progress 0,196 0,583 2,652 2,713 6,435 0,002 0,002 0,002 0,002 0,002 0,118 0,002 3,479 3,190 2,676 4,673 4,439 3,898 3,898 15,940 15,462 7,451 8,342 5,918 5,419 2,508
Addendum

Kumulatif Rencana 0,196 0,778 3,431 6,144 12,579 12,580 12,582 12,583 12,585 12,586 12,705 12,706 16,185 19,375 22,052 26,725 31,164 35,062 38,961 54,901 70,363 77,813 86,155 92,073 97,492 100,000
Realisasi Progress 28,720 0,063 -
Kumulatif Realisasi 71,216 99,937 100,000
Deviasi

Mengetahui, Kontraktor Pelaksana


Unit Proyek Investasi Pengawas Individu PT Cipta Mandiri Nusantara Abadi
Pekerjaan Gudang Terbuka Pelabuhan Bumiharjo ( Cangkang)
PT Pelabuhan Indonesia III (Persero)

1. Erwan Khanissuma : ......................................


Pemimpin Proyek

Adhan Anugrah O M. Rohmanul Aziz


2. Budiman Jaya : ......................................
Manajer