RINCIAN RENCANA ANGGARAN BIAYA (RAB)

PRASARANA SMK PEMBANGUNAN 2 RUANG KELAS BARU

PEKERJAAN : PRASARANA SMK PEMBANGUNAN 2 RUANG KELAS BARU SMK NEGERI 2 SAMARINDA
LOKASI : JALAN A. WAHAB SYAHRANIE, SAMARINDA
TAHUN : ANGGARAN 2015

HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(RP) (RP)
1 PEKERJAAN PENDAHULUAN.
- Pembersihan lokasi 1.00 ls 1,500,000.00 1,500,000.00
- Pembuatan Perancah 1.00 ls 4,500,000.00 4,500,000.00
- Pemindahan Genset 1.00 ls 500,000.00 500,000.00
- Administrasi, Pelaporan & Dokumentasi 1.00 ls 1,000,000.00 1,000,000.00
- Pasang bouwplank 64.00 m' 57,900.00 3,705,600.00
11,205,600.00
2 PEKERJAAN TANAH
- Galian tanah pondasi 34.40 m3 71,250.00 2,451,000.00
- Urugan tanah bawah lantai 144.00 m3 100,500.00 14,472,000.00
- Urugan pasir bawah lantai 18.00 m3 118,500.00 2,133,000.00
- Urugan pasir bawah pondasi 21.80 m3 118,500.00 2,583,300.00
21,639,300.00
3 PEKERJAAN PASANGAN PONDASI
- Pancang ulin 10/10 x 2 m + sunduk dan
kalang ulin setiap jarak 1,5 m 43.00 ttk 55,000.00 2,365,000.00
- Pasangan aanstamping batu gunung 10.08 m3 503,865.00 5,078,959.20
- Pasangan batu gunung campuran 1 : 4 40.32 m3 925,500.00 37,316,160.00

44,760,119.20
4 PEKERJAAN BETON
- Kolom beton utama ukuran 15/25 2.10 m3 6,267,210.00 13,161,141.00
- Kolom beton praktis ukuran 13/13 0.20 m3 6,267,210.00 1,253,442.00
- Sloof beton ukuran 15/20 2.52 m3 6,216,865.00 15,666,499.80
- Ringbalk beton ukuran 15/20 2.52 m3 6,274,710.00 15,812,269.20
- Balok latai 10/13 0.47 m3 6,267,210.00 2,933,054.28
- Kolom beton untuk teras ukuran 15/25 0.76 m3 6,267,210.00 4,747,411.58
- Cor rabat bawah lantai tebal 5 cm 9.00 m3 1,254,255.00 11,288,295.00
- Cor rabat keliling bangunan tebal 7 cm 2.80 m3 1,254,255.00 3,511,914.00
68,374,026.86
5 PEKERJAAN PASANGAN
- Pasangan bata merah 1 : 2 18.00 m2 119,375.00 2,148,750.00
- Pasangan bata merah 1 : 4 206.60 m2 108,575.00 22,431,595.00
- Pasangan tangga 3.00 bh 500,000.00 1,500,000.00
26,080,345.00
6 PEKERJAAN PLESTERAN
- Plesteran 1 : 2 36.00 m2 82,745.00 2,978,820.00
- Plesteran 1 : 4 413.20 m2 60,025.00 24,802,330.00
- Pekerjaan Acian 449.20 m2 30,000.00 13,476,000.00
41,257,150.00
7 PEKERJAAN LANTAI
Pasangan lantai keramik 40 x 40 cm 180.00 m2 181,125.00 32,602,500.00
32,602,500.00
8 PEKERJAAN KUSEN
- Kozen kayu bengkirai 125.60 m1 75,000.00 9,420,000.00
- Jalusi pintu dan jendela 136.00 bh 50,000.00 6,800,000.00
16,220,000.00
9 PEKERJAAN DAUN PINTU DAN JENDELA
- Daun pintu panil Multiplex 12 mm ( 80x210 ) 2.00 bh 600,000.00 1,200,000.00
- Daun pintu panil Multiplex 12 mm ( 50x210 ) 2.00 bh 500,000.00 1,000,000.00
- Daun jendela kaca bening 5 mm ( 60X100 ) 24.00 bh 275,000.00 6,600,000.00

8,800,000.00
HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA
(RP) (RP)
10 PEKERJAAN RANGKA KAP
-Rangka atap Baja ringan 288.00 m2 120,000.00 34,560,000.00
- Listplank kalsiboard 75.20 m' 70,000.00 5,264,000.00
- Jalusi atap dan di cat 2.00 bh 650,000.00 1,300,000.00
41,124,000.00
11 PEKERJAAN PENTUTUP ATAP
- Atap metal setara Sakura Colour 288.00 m2 100,000.00 28,800,000.00
- Bubungan atap metal model bulat ( C ) 20.40 m' 87,900.00 1,793,160.00
30,593,160.00
12 PEKERJAAN PLAFOND
- Rangka plafond dari kayu & kalsiboard 241.76 m2 110,000.00 26,593,600.00
- List plafond profil 1/4 cm dan di cat 173.00 m' 20,000.00 3,460,000.00
30,053,600.00
13 PEKERJAAN INSTALASI LISTRIK
- Lampu SL 18 watt 18.00 Bh 50,000.00 900,000.00
Lampu pijar 18 watt 6.00 Bh 25,000.00 150,000.00
- Saklar double setara " Brocco" 6.00 Bh 40,000.00 240,000.00
- Stop kontak setara "Brocco" 2.00 Bh 35,000.00 70,000.00
- Instalasi Listrik 25.00 Ttk 150,000.00 3,750,000.00
- Zekering cast 2.00 unit 500,000.00 1,000,000.00
- Biaya penyambungan listrik 1.00 Ls 2,000,000.00 2,000,000.00
- Stop Kontak AC + Instalasi 4.00 bh 250,000.00 1,000,000.00
9,110,000.00
14 PEKERJAAN PENGGANTUNG.
- Engsel pintu kuningan 5" 12.00 Bh 42,500.00 510,000.00
- Engsel jendela kuningan 3" 48.00 Bh 30,000.00 1,440,000.00
- Grendel jendela kuningan 48.00 Bh 25,000.00 1,200,000.00
- Hak angin kuningan 48.00 Bh 12,000.00 576,000.00
- Handle jendela kuningan 24.00 Bh 12,000.00 288,000.00
- Expagnolet (Grendel Tanam) 4.00 Bh 125,000.00 500,000.00
4,514,000.00
15 PEKERJAAN KUNCI PINTU
- Kunci tanam 2 x putar merk setara SES 2.00 Bh 150,000.00 300,000.00
300,000.00
16 PEKERJAAN CAT DINDING
-Plamir dan Cat dinding 449.20 m2 15,863.00 7,125,659.60
-Benangan Kolom 117.60 m2 80,000.00 9,408,000.00
-Benang Ring Balk 22.40 ls 80,000.00 1,792,000.00
18,325,659.60
17 PEKERJAAN CAT PLAFOND DAN KAYU
- Cat plafond 241.76 m2 66,050.00 15,968,248.00
- Cat kalsiboard listplank 75.20 m1 35,000.00 2,632,000.00
- Cat kayu kusen 31.65 m2 35,000.00 1,107,750.00
- Cat kayu daun pintu Ukuran (0.8 x 2.10) 2.00 bh 250,000.00 500,000.00
- Cat daun pintu Ukuran (0.5 x 2.10) 2.00 bh 150,000.00 300,000.00
- Cat kayu daun jendela 24.00 bh 100,000.00 2,400,000.00
- Cat kayu jalusi pintu dan jendela 136.00 bh 25,000.00 3,400,000.00

26,307,998.00

Samarinda,
Tim Perencana & Pengawasan Tim Pembangunan
Ketua Ketua

ANUGRAH RAHMADHANI, ST DRS . BUDI WIDJAYANTO


NIP. NIP. 19600305 198903 1 010
DAFTAR ANALISA PEKERJAAN

PEKERJAAN : PRASARANA SMK PEMBANGUNAN 2 RUANG KELAS BARU SMK NEGERI 2 SAMARINDA
LOKASI : JALAN A. WAHAB SYAHRANIE, SAMARINDA
TAHUN : ANGGARAN 2015

HARGA JUMLAH
NO URAIAN PEKERJAAN KOEF SATUAN SATUAN HARGA
(RP) (RP)

A.1 1 M' PEK. PASANG BOUWPLANK


Kayu Meranti 0.012 M³ 2,500,000.00 30,000.00
Paku 0.020 Kg 20,000.00 400.00
Papan kayu meranti 0.007 M³ 2,500,000.00 17,500.00
Ongkos pasang 1.000 Ls 10,000.00 10,000.00
57,900.00
A.2 1 M3 GALIAN TANAH
Pekerja 0.750 Org 90,000.00 67,500.00
Mandor 0.025 Org 150,000.00 3,750.00
71,250.00

A.3 1 M3 URUGAN TANAH KEMBALI


Pekerja 0.250 Org 90,000.00 22,500.00
Mandor 0.060 Org 150,000.00 9,000.00
31,500.00
A.4 1 M3 URUGAN TANAH
Tanah urug 1.200 M³ 60,000.00 72,000.00
Pekerja 0.300 Org 90,000.00 27,000.00
Mandor 0.010 Org 150,000.00 1,500.00
100,500.00
A.5 1 M3 URUGAN BATU PADAS
Batu padas 1.200 M³ 200,000.00 240,000.00
Pekerja 1.500 Org 90,000.00 135,000.00
Mandor 0.075 Org 150,000.00 11,250.00
386,250.00
A.6 1 M3 URUGAN PASIR
Pasir urug 1.200 M³ 75,000.00 90,000.00
Pekerja 0.300 Org 90,000.00 27,000.00
Mandor 0.010 Org 150,000.00 1,500.00
118,500.00
B.1 1 M3 PASANGAN AANSTAMPING
Batu gunung 1.200 M³ 280,000.00 336,000.00
Pasir urug 0.432 M³ 75,000.00 32,400.00
Pekerja 0.780 Org 90,000.00 70,200.00
Tukang batu 0.390 Org 125,000.00 48,750.00
Kepala tukang batu 0.039 Org 135,000.00 5,265.00
Mandor 0.075 Org 150,000.00 11,250.00
503,865.00
B.2 1 M3 PASANGAN BATU GUNUNG
Batu gunung 1.200 M³ 280,000.00 336,000.00
Semen 202.000 Kg 1,500.00 303,000.00
Pasir pasang 0.485 M³ 75,000.00 36,375.00
Tukang batu 0.750 Org 125,000.00 93,750.00
Kepala tukang batu 0.075 Org 135,000.00 10,125.00
Pekerja 1.500 Org 90,000.00 135,000.00
Mandor 0.075 Org 150,000.00 11,250.00
925,500.00
HARGA JUMLAH
NO URAIAN PEKERJAAN KOEF SATUAN SATUAN HARGA
(RP) (RP)

B.3 1 M2 PAS. BATA 1 PC:2 PSR


Bata Merah 50.000 Bh 900.00 45,000.00
Semen 18.950 Kg 1,500.00 28,425.00
Pasir pasang 0.038 M³ 75,000.00 2,850.00
Tukang batu 0.100 Org 125,000.00 12,500.00
Kepala tukang batu 0.010 Org 135,000.00 1,350.00
Pekerja 0.300 Org 90,000.00 27,000.00
Mandor 0.015 Org 150,000.00 2,250.00
119,375.00
B.4 1 M2 PAS. BATA 1 PC:4 PSR
Bata Merah 50.000 Bh 900.00 45,000.00
Semen 11.500 Kg 1,500.00 17,250.00
Pasir pasang 0.043 M³ 75,000.00 3,225.00
Tukang batu 0.100 Org 125,000.00 12,500.00
Kepala tukang batu 0.010 Org 135,000.00 1,350.00
Pekerja 0.300 Org 90,000.00 27,000.00
Mandor 0.015 Org 150,000.00 2,250.00
108,575.00
B.5 1 M2 PASANGAN LANTAI COR
Kawat harmonika 1.000 M2 47,500.00 47,500.00
Semen 0.320 Kg 1,500.00 480.00
Pasir pasang 0.019 M³ 150,000.00 2,850.00
Paku ulin 0.200 kg 22,500.00 4,500.00
Tukang batu 0.214 OH 125,000.00 26,750.00
Kepala tukang batu 0.021 OH 135,000.00 2,835.00
Pekerja 0.286 OH 90,000.00 25,740.00
Mandor 0.021 OH 150,000.00 3,150.00
113,805.00
B.6 1 M2 TEGEL KERAMIK 40 X 40 CM
Tegel keramik 40 x 40 cm 6.250 M² 12,500.00 78,125.00
Semen 8.190 kg 1,500.00 12,285.00
Pasir pasang 0.045 M³ 150,000.00 6,750.00
Semen Warna 1.620 Kg 2,000.00 3,240.00
Tukang batu 0.350 Org 125,000.00 43,750.00
Kepala tukang batu 0.035 Org 135,000.00 4,725.00
Pekerja 0.300 Org 90,000.00 27,000.00
Mandor 0.035 Org 150,000.00 5,250.00
181,125.00

C. PEKERJAAN BETON

C.1. 1 M³ BETON STRUKTUR SLOOF DENGAN MUTU K-225


Semen 7.420 Zak 75,000.00 556,500.00
Pasir Beton 0.499 M³ 150,000.00 74,850.00
Koral Beton (Ex. Palu) 0.776 M³ 450,000.00 349,200.00
Air Kerja 215.000 Ltr 1,000.00 215,000.00
Pekerja 1.650 Org 90,000.00 148,500.00
Tukang Batu 0.275 Org 125,000.00 34,375.00
Kepala tukang batu 0.028 Org 135,000.00 3,780.00
Mandor 0.083 Org 150,000.00 12,450.00
1,394,655.00
HARGA JUMLAH
NO URAIAN PEKERJAAN KOEF SATUAN SATUAN HARGA
(RP) (RP)

2. TULANGAN BESI BETON 1KG MENGERJAKAN BESI BETON


Besi Beton 157.000 Kg 19,000.00 2,983,000.00
Kawat bendrat 1.500 Kg 19,000.00 28,500.00
Pekerja 7.000 Org 90,000.00 630,000.00
Tukang Besi 7.000 Org 125,000.00 875,000.00
Kepala Tukang 0.700 Org 135,000.00 94,500.00
Mandor 0.040 Org 150,000.00 6,000.00
4,617,000.00
3. 1 M³ CETAKAN (BEGESTING) BETON DIPERLUKAN
Kayu Meranti 0.045 M³ 2,500,000.00 112,500.00
Paku Biasa 0.300 Kg 20,000.00 6,000.00
Tukang 0.260 Org 125,000.00 32,500.00
Kepala Tukang 0.026 Org 135,000.00 3,510.00
Pekerja 0.520 Org 90,000.00 46,800.00
Mandor 0.026 Org 150,000.00 3,900.00
205,210.00

TOTAL PEKERJAAN C.1 Rp. 6,216,865.00

C.2 1 M³ BETON STRUKTUR KOLOM / BALOK DENGAN MUTU K-225


1. ADUKAN BETON
Semen 7.420 Zak 75,000.00 556,500.00
Pasir Beton 0.499 M³ 150,000.00 74,850.00
Koral Beton (Ex. Palu) 0.776 M³ 450,000.00 349,200.00
Air Kerja 215.000 Ltr 1,000.00 215,000.00
Pekerja 1.650 Org 90,000.00 148,500.00
Tukang Batu 0.275 Org 125,000.00 34,375.00
Kepala tukang batu 0.028 Org 135,000.00 3,780.00
Mandor 0.083 Org 150,000.00 12,450.00
1,394,655.00
2. TULANGAN BESI BETON 1KG MENGERJAKAN BESI BETON
Besi Beton 157.000 Kg 19,000.00 2,983,000.00
Kawat bendrat 1.500 Kg 19,000.00 28,500.00
Pekerja 7.000 Org 90,000.00 630,000.00
Tukang Besi 7.000 Org 125,000.00 875,000.00
Kepala Tukang 0.700 Org 135,000.00 94,500.00
Mandor 0.040 Org 150,000.00 6,000.00
4,617,000.00
3. 1 M³ CETAKAN (BEGESTING) BETON DIPERLUKAN
Kayu Meranti 0.055 M³ 2,500,000.00 137,500.00
Paku Biasa 0.400 Kg 20,000.00 8,000.00
Tukang 0.330 Org 125,000.00 41,250.00
Kepala Tukang 0.033 Org 135,000.00 4,455.00
Pekerja 0.660 Org 90,000.00 59,400.00
Mandor 0.033 Org 150,000.00 4,950.00
255,555.00

TOTAL PEKERJAAN C.2 Rp. 6,267,210.00

HARGA JUMLAH
NO URAIAN PEKERJAAN KOEF SATUAN SATUAN HARGA
(RP) (RP)

C.3 1 M³ BETON STRUKTUR RINGBALK DENGAN MUTU K-225


1. ADUKAN BETON
Semen 7.420 Zak 75,000.00 556,500.00
Tukang Batu 0.275 Org 125,000.00 34,375.00
Kepala tukang batu 0.028 Org 135,000.00 3,780.00
Mandor 0.083 Org 150,000.00 12,450.00
1,394,655.00

2. TULANGAN BESI BETON 1KG MENGERJAKAN BESI BETON


Besi Beton 157.000 Kg 19,000.00 2,983,000.00
Kawat bendrat 1.500 Kg 19,000.00 28,500.00
Pekerja 7.000 Org 90,000.00 630,000.00
Tukang Besi 7.000 Org 125,000.00 875,000.00
Kepala Tukang 0.700 Org 135,000.00 94,500.00
Mandor 0.040 Org 150,000.00 6,000.00
4,617,000.00
HARGA JUMLAH
NO URAIAN PEKERJAAN KOEF SATUAN SATUAN HARGA
(RP) (RP)

3. 1 M³ CETAKAN (BEGESTING) BETON DIPERLUKAN


Kayu Meranti 0.058 M³ 2,500,000.00 145,000.00
Paku Biasa 0.400 Kg 20,000.00 8,000.00
Tukang 0.330 Org 125,000.00 41,250.00
Kepala Tukang 0.033 Org 135,000.00 4,455.00
Pekerja 0.660 Org 90,000.00 59,400.00
Mandor 0.033 Org 150,000.00 4,950.00
263,055.00
Pasir Beton 0.591 M³ 150,000.00 88,650.00
Koral Beton (Ex. Palu) 0.750 M³ 450,000.00 337,500.00
Air Kerja 215.000 Ltr 1,000.00 215,000.00
Pekerja 1.650 Org 90,000.00 148,500.00
Tukang Batu 0.275 Org 125,000.00 34,375.00
Kepala tukang batu 0.028 Org 135,000.00 3,780.00
Mandor 0.083 Org 150,000.00 12,450.00
1,254,255.00

D.1 1 M2 PLESTERAN 1 PC: 2 PSR + ACIAN


Semen 14.280 Kg 1,500.00 21,420.00
Kepala tukang batu 0.021 Org 135,000.00 2,835.00
Pekerja 0.286 Org 90,000.00 25,740.00
Mandor 0.021 Org 150,000.00 3,150.00
82,745.00
D.2 1 M2 PLESTERAN 1 PC: 4 PSR + ACIAN
Semen 2.500 Kg 1,500.00 3,750.00
Pasir pasang 0.028 M³ 150,000.00 4,200.00
Tukang batu 0.200 Org 125,000.00 25,000.00
Kepala tukang batu 0.020 Org 135,000.00 2,700.00
Pekerja 0.250 Org 90,000.00 22,500.00
Mandor 0.013 Org 150,000.00 1,875.00
60,025.00
E.1 1 M3 KOZEN PINTU DAN JENDELA
Kayu bengkirai 1.100 M³ 4,500,000.00 4,950,000.00
Paku 4.000 Kg 20,000.00 80,000.00
Tukang kayu 12.000 Org 125,000.00 1,500,000.00
Kepala tukang kayu 1.200 Org 135,000.00 162,000.00
Pekerja 9.000 Org 90,000.00 810,000.00
Mandor 0.450 Org 150,000.00 67,500.00
7,569,500.00

E.2 1 M2 PAS. PLAFOND + RANGKA


Plywood + 3,6 mm 0.360 Lbr 55,000.00 19,800.00
Kayu meranti 0.012 M³ 2,500,000.00 30,000.00
Paku 0.150 Kg 20,000.00 3,000.00
Tukang kayu 0.150 Org 125,000.00 18,750.00
Kepala tukang kayu 0.015 Org 135,000.00 2,025.00
Pekerja 0.200 Org 12,500.00 2,500.00
Mandor 0.010 Org 150,000.00 1,500.00
77,575.00

HARGA JUMLAH
NO URAIAN PEKERJAAN KOEF SATUAN SATUAN HARGA
(RP) (RP)
E.3 1 M2 MEMASANG ATAP
Atap metal setara 'Sakura Color" ( 2 x 4 daun) 1.650 Lbr 60,000.00 99,000.00
Paku atap 0.150 Bh 500.00 75.00
Tukang kayu 0.100 Org 125,000.00 12,500.00
Kepala tukang kayu 0.010 Org 135,000.00 1,350.00
Pekerja 0.200 Org 90,000.00 18,000.00
Mandor 0.001 Org 150,000.00 150.00
131,075.00

E.4 1 M' BUBUNGAN ATAP


Bubungan atap model bulat ( C ) 2.000 Bh 28,000.00 56,000.00
Plamur 0.100 Kg 15,000.00 1,500.00
Amplas 0.250 Lbr 4,000.00 1,000.00
Tukang cat 0.063 Org 125,000.00 7,875.00
Kepala tukang cat 0.006 Org 135,000.00 850.50
Pekerja 0.020 Org 90,000.00 1,800.00
Mandor 0.003 Org 135,000.00 337.50
15,863.00
E.6 1 M2 MENGECAT KAYU
Meni kayu 0.200 Kg 25,000.00 5,000.00
Plamur 0.170 Kg 15,000.00 2,550.00
Cat kayu 0.170 Kg 35,000.00 5,950.00
Amplas 0.400 Lbr 4,000.00 1,600.00
Tukang cat 0.090 Org 125,000.00 11,250.00
Kepala tukang cat 0.006 Org 135,000.00 810.00
Pekerja 0.070 Org 90,000.00 6,300.00
Mandor 0.003 Org 150,000.00 375.00
33,835.00
E.7 1 M2 MENGECAT PLAFOND
Cat tembok 0.200 Kg 25,000.00 5,000.00
Tukang cat 0.300 Org 125,000.00 37,500.00
Kepala tukang cat 0.030 Org 135,000.00 4,050.00
Pekerja 0.200 Org 90,000.00 18,000.00
Mandor 0.010 Org 150,000.00 1,500.00
66,050.00

E.8 1 M2 PLITURAN
Pinotex 0.172 ltr 35,000.00 6,020.00
Amplas 1.000 Lbr 4,000.00 4,000.00
Tukang cat 0.340 Org 125,000.00 42,500.00
Kepala tukang cat 0.030 Org 135,000.00 4,050.00
Pekerja 0.200 Org 90,000.00 18,000.00
Mandor 0.010 Org 150,000.00 1,500.00
76,070.00
DAFTAR BAHAN DAN UPAH
PEKERJAAN : PRASARANA SMK PEMBANGUNAN 2 RUANG KELAS BARU SMK NEGERI 2 SAMARINDA
LOKASI : JALAN A. WAHAB SYAHRANIE, SAMARINDA
TAHUN : ANGGARAN 2015

HARGA SATUAN
NO JENIS BAHAN SATUAN BAHAN KETERANGAN
( Rp )

A. AGREGAT KASAR, BAHAN PEREKAT DAN


BAHAN JADINYA
1 Tanah urug m3 60,000.00 DIPROYEK
2 Pasir urug m3 75,000.00 DIPROYEK
3 Pasir pasang m3 150,000.00 DIPROYEK
4 Batu kerikil / koral m3 450,000.00 DIPROYEK
5 Batu gunung m3 280,000.00 DIPROYEK
6 Batu padas m3 200,000.00 DIPROYEK
7 Bata merah Bh 900.00 DIPROYEK
8 Semen 50 kg/zak Kg 1,500.00 DIPROYEK
9 Semen warna 50 kg/zak Kg 2,000.00 DIPROYEK
10 Semen 50 kg/zak Zak 75,000.00 DIPROYEK
11 Air Kerja Ltr 1,000.00 DIPROYEK

B. BAHAN FINISHING
1 Meni kayu kg 25,000.00 DIPROYEK
2 Cat tembok kg 25,000.00 DIPROYEK
3 Cat kayu kg 35,000.00 DIPROYEK
4 Plituran ltr 35,000.00 DIPROYEK
5 Plamur kg 15,000.00 DIPROYEK
6 Amplas Lbr 4,000.00 DIPROYEK

C. BAHAN KAYU BERIKUT BAHAN JADINYA


1 Papan Bengkirai m3 5,000,000.00 DIPROYEK
2 Papan ulin m3 5,000,000.00 DIPROYEK
3 Papan Meranti m3 2,500,000.00 DIPROYEK
4 Papan sejenis kayu Kapur m3 4,000,000.00 DIPROYEK
5 Balok Meranti m3 2,300,000.00 DIPROYEK
6 Balok Bengkirai m3 4,500,000.00 DIPROYEK
7 Balok Ulin m3 4,000,000.00 DIPROYEK
8 Balok sejenis kayu Kapur m3 3,500,000.00 DIPROYEK
9 Plywood ukuran + 3,6 mm lembar 55,000.00 DIPROYEK

D. BAHAN LANTAI DAN PELAPIS DINDING


1 Tegel Keramik 40 x 40 cm Biji 12,500.00 DIPROYEK

E. BAHAN KACA
1 Kaca bening tebal 5 mm m2 140,000.00 DIPROYEK
2 Kaca es tebal 5 mm m2 160,000.00 DIPROYEK
HARGA SATUAN
NO JENIS BAHAN SATUAN BAHAN KETERANGAN
( Rp )

F. BAHAN LOGAM DAN PAKU


1 Paku segala ukuran kg 20,000.00 DIPROYEK
2 Paku seng kg 20,000.00 DIPROYEK
3 Paku ulin kg 22,500.00 DIPROYEK
4 Paku kecil plywood kg 20,000.00 DIPROYEK
5 Kawat Bendrat kg 19,000.00 DIPROYEK
6 Besi beton kg 19,000.00 DIPROYEK
7 Kawat harmonika m2 47,500.00 DIPROYEK

G. BAHAN PENUTUP ATAP


1 Atap metal setara Sakura Colour lbr 60,000.00 DIPROYEK
2 Bubungan atap metal model bulat ( C ) bh 28,000.00 DIPROYEK

H. BAHAN ELEKTRIKAL
1 Lampu TL 1 x 20 Watt bh 150,000.00 DIPASANG
2 Lampu pijar 25 Watt bh 30,000.00 DIPASANG
3 Saklar tunggal setara merk BROCCO bh 20,000.00 DIPASANG
4 Saklar double setara merk BROCCO bh 25,000.00 DIPASANG
5 Stop kontak setara merk BROCCO bh 35,000.00 DIPASANG
6 Instalasi listrik Ttk 150,000.00 DIPASANG
7 Zekring kast Group 250,000.00 DIPASANG

I. BAHAN PENGGANTUNG DAN KUNCI


1 Kunci tanam 2 slagh setara merk SES bh 150,000.00 DIPASANG
2 Kunci tanam bulat setara merk ALPHA bh 100,000.00 DIPASANG
3 Engsel pintu kuningan 5" bh 42,500.00 DIPASANG
4 Engsel jendela kuningan 3" bh 30,000.00 DIPASANG
5 Grendel jendela kuningan bh 25,000.00 DIPASANG
6 Handle jendela kuningan bh 12,000.00 DIPASANG
7 Kait/hak angin kuningan bh 12,000.00 DIPASANG
8 Expagnolet bh 125,000.00 DIPASANG

J. BAHAN SANITASI DAN PERPIPAAN


1 Pipa PVC Ø 1/2" AW m' 8,500.00 DIPASANG
2 Pipa PVC Ø 4" AW m' 25,000.00 DIPASANG
3 Pipa PVC Ø 2" AW m' 15,000.00 DIPASANG
4 Kran air diameter 1/2" bh 30,000.00 DIPASANG
5 Klosed jongkok bh 250,000.00 DIPASANG
6 Floor drain bh 30,000.00 DIPASANG
7 Bak mandi fiberglass 70/70 lapis keramik 20/25 bh 50,000.00 DIPASANG
8 Septicktank + peresapan Unit 4,000,000.00 DIPASANG
9 Saluran air hujan m' 90,000.00 DIPASANG
10 Bak kontrol bh 120,000.00 DIPASANG

K. PERALATAN
1 Exavator JE 500,000.00 PER JAM

HARGA SATUAN
NO JENIS UPAH SATUAN UPAH KETERANGAN
( Rp )

1 Pekerja biasa Hari 90,000.00 PERORANG


2 Mandor Hari 150,000.00 PERORANG
3 Tukang batu Hari 125,000.00 PERORANG
4 Kepala Tukang batu Hari 135,000.00 PERORANG
5 Tukang kayu Hari 125,000.00 PERORANG
6 Kepala Tukang kayu Hari 135,000.00 PERORANG
7 Tukang Cat Hari 125,000.00 PERORANG
8 Kepala Tukang Cat Hari 135,000.00 PERORANG
9 Tukang Besi Hari 125,000.00 PERORANG
10 Kepala Tukang Besi Hari 135,000.00 PERORANG
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
PRASARANA SMK PEMBANGUNAN 2 RUANG KELAS BARU
SMK NEGERI 2 SAMARINDA
TAHUN 2015

JUMLAH
NO JENIS BAHAN HARGA
(RP)
1 PEKERJAAN PENDAHULUAN Rp 11,205,600.00
2 PEKERJAAN TANAH Rp 21,639,300.00
3 PEKERJAAN PASANGAN PONDASI Rp 44,760,119.20
4 PEKERJAAN BETON Rp 68,374,026.86
5 PEKERJAAN PASANGAN Rp 26,080,345.00
6 PEKERJAAN PLESTERAN Rp 41,257,150.00
7 PEKERJAAN LANTAI Rp 32,602,500.00
8 PEKERJAAN KOSEN Rp 16,220,000.00
9 PEKERJAAN DAUN PINTU DAN JENDELA Rp 8,800,000.00
10 PEKERJAAN RANGKA KAP Rp 41,124,000.00
11 PEKERJAAN PENUTUP ATAP Rp 30,593,160.00
12 PEKERJAAN PLAFOND Rp 30,053,600.00
13 PEKERJAAN INSTALASI LISTRIK Rp 9,110,000.00
14 PEKERJAAN PENGGANTUNG Rp 4,514,000.00
15 PEKERJAAN KUNCI PINTU Rp 300,000.00
16 PEKERJAAN CAT DINDING Rp 18,325,659.60
17 PEKERJAAN CAT PLAFOND DAN KAYU Rp 26,307,998.00

A. JUMLAH BIAYA Rp 431,267,458.66

B. PPN 10 % Rp 43,126,745.87

C. JUMLAH ( A + B) Rp 474,394,204.52

D. DIBULATKAN Rp 474,394,000.00

TERBILANG : Empat Ratus Tujuh Puluh Empat Juta Tiga Ratus Sembilan Puluh Empat Ribu Rupiah

Samarinda,
Tim Perencana & Pengawasan Tim Pembangunan
Ketua Ketua

ANUGRAH RAHMADHANI, ST DRS . BUDI WIDJAYANTO


NIP. NIP. 19600305 198903 1 010
5 -Plamir dan Cat dinding 696.41 m2 15,863.00
11,047,189.90
URAIAN LUAS PENAMPANG X PANJANG = VOLUME(M³)

Aanstamping 1 0.10 X 145.12 = 14.15


Aanstamping 2 0.10 X 145.12 = 14.15
Aanstamping 3 0.15 X 145.12 = 21.77
TOTAL AANSTAMPING = 50.07
PONDASI 1 0.13 X 46.50 = 6.05
PONDASI 2 0.36 X 15.50 = 5.58
PONDASI 3 0.44 X 82.10 = 36.12
TOTAL PONDASI = 47.75
PAS BATA MERAH 1:2 LUAS DINDING - LUBANG KUSEN = JUMLAH
v1 13.87 - 1.28 = 12.59
v2 26.05 - 2.56 = 23.49
v3 46.60 - 1.15 = 45.45
TOTAL PAS BATA MERAH 1:2 = 81.53
v1 56.73 - 2.76 = 53.97
v2 101.62 - 12.18 = 89.44
v3 163.17 - 39.90 = 123.27
TOTAL PAS BATA MERAH 1:4 = 266.68
RINCIAN RENCANA ANGGARAN BIAYA (RAB)
PRASARANA SMK PEMBANGUNAN 2 RUANG KELAS BARU
Nama : ANGGA LEO PRASETYA LINGGA
kelas : XII TEKNIK GAMBAR BANGUNAN
pekerja : ANGGARAN BIAYA PEKERJAAN PONDASI DAN DINDING

HARGA
NO URAIAN PEKERJAAN VOLUME SAT SATUAN
(RP)
1 PEKERJAAN PASANGAN PONDASI
- Galian tanah pondasi 89.97 m3 71,250.00
-Pancang ulin 10/10 x 2 m + sunduk dan
kalang ulin setiap jarak 1,5 m 73.00 ttk 55,000.00
-Pasangan aanstamping 50.07 m3 503,865.00
-Pasangan batu gunung campuran 1 : 4 47.75 m3 925,500.00
- Urugan pasir bawah aanstamping 7.26 m3 118,500.00

2 PEKERJAAN PASANGAN
- Pasangan bata merah 1 : 2 81.53 m2 119,375.00
- Pasangan bata merah 1 : 4 266.68 m2 108,575.00

3 PEKERJAAN PLESTERAN
- Plesteran 1 : 2 163.06 m2 82,745.00
- Plesteran 1 : 4 533.35 m2 60,025.00

PEKERJAAN PENGECETAN
4 -Plamir dan Cat dinding 696.41 m2 15,863.00
BIAYA (RAB)
NG KELAS BARU

JUMLAH
HARGA
(RP)

6,410,505.00

4,015,000.00
25,226,011.30
44,191,699.50
859,812.30
80,703,028.10

9,732,524.38
28,954,476.99
38,687,001.37

13,492,234.21
32,014,597.86
Err:522

11,047,189.90