Anda di halaman 1dari 2

RENCANA DAN REALISASI

BULAN MEI
BULAN PERIODE KONTRAK
KET
NO NAMA JABATAN RC/RL APRIL MEI JUNI JULI AGUST SEPT OKT NOP DES
I II I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV

1 IR.SUNARIYADI Site Engineer RC


RL

2 NYOMAN B. SATRIAWAN,ST QE/CI RC


RL

3 YUFANTO PIU,ST Lab.Tecnikal RC


RL

4 SOEN VAN GOBE;L Inspektor 1 RC


RL

5 ROWIN Y. LAQUNE,A.Md Inspektor 2 RC


RL

6 SUPRATMAN DARISE,A.Md Surveyor RC


RL

7 MUHAMAD AGUS M. SULAEMAN Supprting Staof RC


RL

8 HAMDAN AL HAKIM Supporting Staf RC


RL
RENCANA DAN REALISASI
BULAN JUNI
BULAN PERIODE KONTRAK
KET
NO NAMA JABATAN RC/RL APRIL MEI JUNI JULI AGUST SEPT OKT NOP DES
I II I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV

1 IR.SUNARIYADI Site Engineer RC


RL

2 NYOMAN B. SATRIAWAN,ST QE/CI RC


RL

3 YUFANTO PIU,ST Lab.Tecnikal RC


RL

4 SOEN VAN GOBE;L Inspektor 1 RC


RL

5 ROWIN Y. LAQUNE,A.Md Inspektor 2 RC


RL

6 SUPRATMAN DARISE,A.Md Surveyor RC


RL

7 MUHAMAD AGUS M. SULAEMAN Supporting Staf RC


RL

8 HAMDAN AL HAKIM Supporting Staf RC


RL

Anda mungkin juga menyukai