FAKTOR YANG BERPENGARUH PADA PROSES

MODELING – DETAILING :

1. KETERSEDIAAN INFORMASI PADA REFERENCE DRAWING


2. TINGKAT KOMPLEKSITAS STRUCTURE
3. KUALITAS OUTPUT DRAWING YANG DI SYARATKAN
4. KUALITAS MODELLER/DRAFTER

by EDNMJ
PENGUKURAN MAN HOUR VS TONNASE
BEBERAPA DATA REFERENCE HASIL STUDI
ANTARA Man hours vs Tonnase
X AXIS = HOUR / TON
1. MODELLING Y AXIS = VARIASI JENIS
PROFILE DI TINJAU DARI
SEGI BERAT KG/M

< 10 Kg/m = <L80 , <UNP-100


~ 20 Kg/m = WF200, H150 , L100 , UNP-150
~30 Kg/m = WF250, UNP200,
~40 Kg/m = WF300, L150
~50 Kg/m = HB200,WF350 , L200, UNP300
~60 Kg/m = WF400 ,
~70 Kg/m = WF450, HB250
~80 Kg/m =WF500
>90 Kg/m = HB300, HB400, WF600,WF588

by EDNMJ
2. DETAILING ( SHOP DRAWING)

3. KOMBINASI

Data tersebut hanya sebagai Referensi , sedangkan Schedule Actual


tetap harus menyesuaikan dgn Komitemen dgn Customer dan
Skala Prioritas
by EDNMJ