PROJECT : PENAMBAHAN LINE STEAM, PEMINDAHAN DAN PENGGANTIAN HEADER WTP-DRP

USER : WTP - DRP


NO PROPOSAL : PS/PRJ/2018/078

NO PEKERJAAN M. 44 M. 45 M. 46 M. 47
28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 BUKA PPB X X
2 PROSES APPROVE X X X X X X X X X X X X X X X X X X X
3 KEDATANGAN MATERIAL
4 PEMBUATAN KEDUDUKAN PANGGUNG HEADER WTP - DRP
5 PEMBUATAN HEADER WTP
6 PEMASANGAN SUPPORT PIPA STEAM (6" dan 8")
7 PEMASANGAN PIPA STEAM KE HEADER WTP DAN DRP (6" dan 8")
8 PEMASANGAN ISOLASI PIPA STEAM KE HEADER WTP DAN DRP (6" dan 8")
9 PEMBUATAN SUPPORT PIPA KE WTP DAN DRP DARI HEADER BARU
10 PEMASANGAN PIPA STEAM WTP DAN DRP ( 3" 4" dan 5" )
11 PEMASANGAN ISOLASI PIPA STEAM WTP DAN DRP ( 3" 4" dan 5" )
12 JOIN PIPA HEADER WTP DRP ( PROYEK LEBARAN )
13 FINISING
14 PEMBONGKARAN PIPA LAMA
15
16
17

SCHEDULE

ACTUAL
M. 48 M. 49 M. 50 M. 51 M. 52 M. 1 M. 2
24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8
PT.PULAU SAMBU
SCHEDULE PEKERJAAN PEMINDAHAN HEADER WTP - DRP

WAKTU
M. 2 M. 3 M. 4 M. 5 M. 6 M. 7 M. 8
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
WAKTU DAN LAMA PEKERJAAN
M. 9 M. 10 M .11 M. 12 M. 13 M.14 M. 15
24 25 26 27 28 29 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9
M. 15 M. 16 M .17 M. 18 M. 19 M. 20 M. 21
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Tanggal : 01-10-2019
Departemen : Boiler
Halaman : 01
Revisi : 00

M. 22 M.23 M.24 M.25 M.26


26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

Dibuat Oleh Dicek Oleh Disetujui Oleh

Nama : Koko Tri Widodo Nama : Husin Nama : Pramudjito CH


Jabatan : M. E BLR Jabatan : KB BLR Jabatan : MGR UTL
Tanggal : Tanggal : Tanggal :