ID TaskTask Name vol satDuration

Start Finish Predecessors


Mode Oct 7, '19 Oct 14, '19 Oct 21, '19 Oct 28, '19 Nov 4, '19 Nov 11, '19 Nov 18, '19 Nov 25, '19 Dec 2, '19 Dec 9, '19 Dec 16, '19 Dec 23, '19
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
0 0 70 days Oct 14 '19 Dec 22 '19
GEDUNG FARMASI
1 1 PEKERJAAN PERSIAPAN 0 4 days Oct 14 '19 Oct 17 '19
2 1.1 Pembuatan Papan Proyek 1 Ls 1 day Oct 14 '19 Oct 14 '19 10/14 10/14
3 1.2 Pengadaan Listrik dan Air Kerja 1 Ls 1 day Oct 14 '19 Oct 14 '19 10/14 10/14
4 1.3 Sewa Direksi Keet 1 Ls 1 day Oct 14 '19 Oct 14 '19 10/14 10/14
5 1.4 Mobilisasi dan Demobilisasi Peralatan dan Pekerja 1 Ls 1 day Oct 14 '19 Oct 14 '19 10/14 10/14
6 1.5 Pekerjaan Bongkaran Bangunan Lama 1 Ls 3 days Oct 14 '19 Oct 16 '19 10/14 10/16
7 1.6 Pembuatan Gudang dan Barak Kerja 1 Ls 1 day Oct 14 '19 Oct 14 '19 10/14 10/14
8 1.7 Pasang Pagar Keliling Lokasi Proyek 1 Ls 1 day Oct 17 '19 Oct 17 '19 6 10/17 10/17
9 1.8 Pekerjaan Pengukuran dan Pemasangan Bouwplank 1 Ls 1 day Oct 17 '19 Oct 17 '19 6 10/17 10/17
10 1.9 Biaya Operasional SMK3 1 Set1 day Oct 14 '19 Oct 14 '19 10/14 10/14
11 1.10 Biaya Administrasi, Pelaporan dan Dokumentasi 1 Ls 1 day Oct 14 '19 Oct 14 '19 10/14 10/14
12 2 PEKERJAAN TANAH DAN PASIR 0 9 days Oct 18 '19 Oct 26 '19
13 2.1 Pek. Galian Tanah Pondasi Menerus 11.21 m3 2 days Oct 18 '19 Oct 19 '19 9 10/18 10/19
14 2.2 Pek. Galian Tanah Pondasi Foot Plat 145.8 m3 3 days Oct 18 '19 Oct 20 '19 9 10/18 10/20
15 2.3 Pek. Urugan Tanah Kembali Pondasi Menerus 3.74 m3 1 day Oct 22 '19 Oct 22 '19 29 10/22 10/22
16 2.4 Pek. Urugan Tanah Kembali Foot Plat 48.6 m3 1 day Oct 26 '19 Oct 26 '19 26 10/26 10/26
17 2.5 Pek. Urugan Tanah Peninggian Lantai 163.62 m3 1 day Oct 26 '19 Oct 26 '19 26 10/26 10/26
18 2.6 Pek. Urugan Pasir Bawah Pondasi Menerus t.5cm 0.53 m3 1 day Oct 20 '19 Oct 20 '19 13 10/20 10/20
19 2.7 Pek. Urugan Pasir Bawah Pondasi Foot Plat t.10cm 3.38 m3 1 day Oct 21 '19 Oct 21 '19 14 10/21 10/21
20 2.8 Pek. Lantai Kerja Foot Plat Adk. 1:3:5 3.38 m3 1 day Oct 22 '19 Oct 22 '19 19 10/22 10/22
21 3 PEKERJAAN PONDASI 0 11 days Oct 15 '19 Oct 25 '19
22 3.1 Pek. Beton Pondasi Foot Plat PD1 K-250 0 9 days Oct 15 '19 Oct 23 '19
23 3.1.1 Pas. Beton K-250 21.87 m3 1 day Oct 23 '19 Oct 23 '19 20 10/23 10/23
24 3.1.2 Pek. Besi Tulangan 2559.6 kg 3 days Oct 15 '19 Oct 17 '19 7 10/15 10/17
25 3.2 Pek. Pedestal 40/40 K-250 0 8 days Oct 18 '19 Oct 25 '19
26 3.2.1 Pas. Beton K-250 6.29 m3 1 day Oct 25 '19 Oct 25 '19 28 10/25 10/25
27 3.2.2 Pek. Besi Tulangan 1003.63 kg 2 days Oct 18 '19 Oct 19 '19 24 10/18 10/19
28 3.2.3 Pek. Bekisting 31.44 m2 2 days Oct 23 '19 Oct 24 '19 27,23FS-1 day 10/23 10/24
29 3.3 Pek. Pondasi Batu Belah Adk. 1:4 6.8 m3 3 days Oct 19 '19 Oct 21 '19 13FS-50% 10/19 10/21
30 4 PEKERJAAN BETON 0 37 days Oct 20 '19 Nov 25 '19
31 4.1 S T R U K T U R L A N T A I 1 0 30 days Oct 20 '19 Nov 18 '19
32 4.1.1 Pek. Sloof 25/40 K-250 (S1) 0 8 days Oct 20 '19 Oct 27 '19
33 4.1.1.1 Pas. Beton K-250 10.16 m3 1 day Oct 27 '19 Oct 27 '19 35 10/27 10/27
34 4.1.1.2 Pek. Besi Tulangan 1285.77 kg 2 days Oct 20 '19 Oct 21 '19 27 10/20 10/21
35 4.1.1.3 Pek. Bekisting 50.8 m2 2 days Oct 25 '19 Oct 26 '19 34,26FS-1 day 10/25 10/26
36 4.1.2 Pek. Sloof 15/20 K-250 (S2) 0 3 days Oct 25 '19 Oct 27 '19
37 4.1.2.1 Pas. Beton K-250 0.2 m3 1 day Oct 27 '19 Oct 27 '19 35 10/27 10/27
38 4.1.2.2 Pek. Besi Tulangan 25.7 kg 1 day Oct 26 '19 Oct 26 '19 27FF,39 10/26 10/26
39 4.1.2.3 Pek. Bekisting 1.99 m2 1 day Oct 25 '19 Oct 25 '19 34,26FS-1 day 10/25 10/25
40 4.1.3 Pek. Sloof 20/30 K-250 0 3 days Oct 25 '19 Oct 27 '19
41 4.1.3.1 Pas. Beton K-250 0.84 m3 1 day Oct 27 '19 Oct 27 '19 35 10/27 10/27
42 4.1.3.2 Pek. Besi Tulangan 63 kg 1 day Oct 26 '19 Oct 26 '19 27FF,43 10/26 10/26
43 4.1.3.3 Pek. Beksiting 8.44 m2 1 day Oct 25 '19 Oct 25 '19 34,26FS-1 day 10/25 10/25
44 4.1.4 Pek. Kolom H Beam 350.350.12.19 8220 kg 2 days Nov 4 '19 Nov 5 '19 46FS+7 days 11/4 11/5
45 4.1.5 Base Plate Plat 15mm x 4' x 8' 19.44 kg 1 day Nov 5 '19 Nov 5 '19 44FF 11/5 11/5
46 4.1.6 Angkur Ø 19 L : 60cm 120 Unit1 day Oct 27 '19 Oct 27 '19 41FF 10/27 10/27
47 4.1.7 Pengelasan t : 4mm 2625 cm 1 day Nov 5 '19 Nov 5 '19 44FF 11/5 11/5
48 4.1.8 Pek. Kolom Teras K2 20x50 K-250 0 3 days Oct 27 '19 Oct 29 '19
49 4.1.8.1 Pas. Beton K-250 1.23 m3 1 day Oct 29 '19 Oct 29 '19 51 10/29 10/29
50 4.1.8.2 Pek. Besi Tulangan 8.61 kg 1 day Oct 27 '19 Oct 27 '19 38 10/27 10/27
51 4.1.8.3 Pek. Bekisting 17.22 m2 1 day Oct 28 '19 Oct 28 '19 50 10/28 10/28
52 4.1.9 Pek. Kolom Teras K3 20x20 K-250 0 3 days Oct 27 '19 Oct 29 '19
53 4.1.9.1 Pas. Beton K-250 0.49 m3 1 day Oct 29 '19 Oct 29 '19 55 10/29 10/29
54 4.1.9.2 Pek. Besi Tulangan 318.12 kg 1 day Oct 27 '19 Oct 27 '19 38 10/27 10/27
55 4.1.9.3 Pek. Bekisting 9.84 m2 1 day Oct 28 '19 Oct 28 '19 54 10/28 10/28
56 4.1.10 Pek. Kolom Praktis 11/11 K-175 0 7 days Nov 12 '19 Nov 18 '19
57 4.1.10.1 Pas. Beton K-175 0.23 m3 7 days Nov 12 '19 Nov 18 '19 115FF 11/12 11/18
58 4.1.10.2 Pek. Besi Tulangan 69.05 kg 7 days Nov 12 '19 Nov 18 '19 115FF 11/12 11/18
59 4.1.10.3 Pek. Bekisting 4.27 m2 7 days Nov 12 '19 Nov 18 '19 115FF 11/12 11/18
60 4.1.11 Pek. Balok BW1 250.125.6.9 3195 kg 2 days Nov 6 '19 Nov 7 '19 44 11/6 11/7
61 4.1.12 Plate Plat 10mm x 4' x 8' 192.39 kg 1 day Nov 7 '19 Nov 7 '19 60FF 11/7 11/7
62 4.1.13 Baut M16 540 Bh 1 day Nov 7 '19 Nov 7 '19 60FF 11/7 11/7
63 4.1.14 Pengelasan t : 4mm 2850 cm 2 days Nov 6 '19 Nov 7 '19 60FF 11/6 11/7
64 4.1.15 Pek. Balok BW2 200.100.5,5.8 1173.33 kg 2 days Nov 6 '19 Nov 7 '19 44 11/6 11/7
65 4.1.16 Plate Plat 10mm x 4' x 8' 25.92 kg 1 day Nov 7 '19 Nov 7 '19 64FF 11/7 11/7
66 4.1.17 Baut M16 128 Bh 1 day Nov 7 '19 Nov 7 '19 64FF 11/7 11/7
67 4.1.18 Pengelasan t : 4mm 1350 cm 1 day Nov 7 '19 Nov 7 '19 64FF 11/7 11/7
68 4.1.19 Pek. Balok BW2 200.100.5,5.8 Teras 320 kg 2 days Nov 6 '19 Nov 7 '19 44 11/6 11/7
69 4.1.20 Plate Plat 10mm x 4' x 8' 16.2 kg 1 day Nov 7 '19 Nov 7 '19 68FF 11/7 11/7
70 4.1.21 Baut M16 80 Bh 1 day Nov 7 '19 Nov 7 '19 68FF 11/7 11/7
71 4.1.22 Pengelasan t : 4mm 1125 cm 1 day Nov 7 '19 Nov 7 '19 68FF 11/7 11/7
72 4.1.23 PLAT LANTAI 2 0 4 days Nov 8 '19 Nov 11 '19
73 4.1.23.1 Pek. Plat Latai K-250 0 4 days Nov 8 '19 Nov 11 '19
74 4.1.23.1.1 Pas. Beton K-250 22.64 m3 1 day Nov 11 '19 Nov 11 '19 75 11/11 11/11
75 4.1.23.1.2 Pembesian Wiremesh M8 (1 layer) 1028.38 kg 2 days Nov 9 '19 Nov 10 '19 76FS-1 day 11/9 11/10
76 4.1.23.1.3 Pek. Bekisting Bondek t : 0,7mm 188.69 m2 2 days Nov 8 '19 Nov 9 '19 60,64,68 11/8 11/9

Task Project Summary Rolled Up Baseline External Tasks Inactive Summary Manual Summary Critical
Project: GEDUNG FARMASI Split Group By Summary Rolled Up Baseline Milestone External Milestone Manual Task Start-only Critical Split
Date: Sep 24 '19 Milestone Rolled Up Task Rolled Up Progress Inactive Task Duration-only Finish-only Progress

Summary Rolled Up Milestone Baseline Split Inactive Milestone Manual Summary Rollup Deadline Slippage

Page 1
ID TaskTask Name vol satDuration
Start Finish Predecessors
Mode Oct 7, '19 Oct 14, '19 Oct 21, '19 Oct 28, '19 Nov 4, '19 Nov 11, '19 Nov 18, '19 Nov 25, '19 Dec 2, '19 Dec 9, '19 Dec 16, '19 Dec 23, '19
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
77 4.1.23.2 Pek. Plat Teras K-250 0 4 days Nov 8 '19 Nov 11 '19
78 4.1.23.2.1 Pas. Beton K-250 3.67 m3 1 day Nov 11 '19 Nov 11 '19 79,74FF 11/11 11/11
79 4.1.23.2.2 Pembesian Wiremesh M8 (1 layer) 166.77 kg 1 day Nov 9 '19 Nov 9 '19 80 11/9 11/9
80 4.1.23.2.3 Pek. Bekisting Bondek t : 0,7mm 30.6 m2 1 day Nov 8 '19 Nov 8 '19 60,64,68 11/8 11/8
81 4.1.24 TANGGA LANTAI 2 0 5 days Nov 12 '19 Nov 16 '19
82 4.1.24.1 Pek. Plat Tangga K-250 0 5 days Nov 12 '19 Nov 16 '19
83 4.1.24.1.1 Pas. Beton K-250 1.33 m3 1 day Nov 16 '19 Nov 16 '19 84 11/16 11/16
84 4.1.24.1.2 Pek. Besi Tulangan 328.85 kg 2 days Nov 14 '19 Nov 15 '19 85 11/14 11/15
85 4.1.24.1.3 Pek. Bekisting 7.8 m2 2 days Nov 12 '19 Nov 13 '19 78 11/12 11/13
86 4.1.24.2 Pek. Plat Bordes Tangga K-250 0 5 days Nov 12 '19 Nov 16 '19
87 4.1.24.2.1 Pas. Beton K-250 0.17 m3 1 day Nov 16 '19 Nov 16 '19 88,83FF 11/16 11/16
88 4.1.24.2.2 Pek. Besi Tulangan 42.85 kg 1 day Nov 13 '19 Nov 13 '19 89 11/13 11/13
89 4.1.24.2.3 Pek. Bekisting 1.44 m2 1 day Nov 12 '19 Nov 12 '19 78 11/12 11/12
90 4.2 S T R U K T U R L A N T A I 2 0 20 days Nov 6 '19 Nov 25 '19
91 4.2.1 KOLOM 0 20 days Nov 6 '19 Nov 25 '19
92 4.2.1.1 Pek. Kolom H Beam 350.350.12.19 8220 kg 2 days Nov 6 '19 Nov 7 '19 44 11/6 11/7
93 4.2.1.2 Pengelasan t : 4mm 2775 cm 2 days Nov 6 '19 Nov 7 '19 92FF 11/6 11/7
94 4.2.1.3 Pek. Kolom Praktis 11/11 K-175 0 7 days Nov 19 '19 Nov 25 '19
95 4.2.1.3.1 Pas. Beton K-175 0.28 m3 7 days Nov 19 '19 Nov 25 '19 150FF 11/19 11/25
96 4.2.1.3.2 Pek. Besi Tulangan 82.86 kg 7 days Nov 19 '19 Nov 25 '19 150FF 11/19 11/25
97 4.2.1.3.3 Pek. Bekisting 2.56 m2 7 days Nov 19 '19 Nov 25 '19 150FF 11/19 11/25
98 4.2.2 BALOK 0 2 days Nov 8 '19 Nov 9 '19
99 4.2.2.1 Pek. Balok BW1 250.125.6.9 3195 kg 2 days Nov 8 '19 Nov 9 '19 92 11/8 11/9
100 4.2.2.2 Plate Plat 10mm x 4' x 8' 192.39 kg 1 day Nov 9 '19 Nov 9 '19 99FF 11/9 11/9
101 4.2.2.3 Baut M16 540 Bh 1 day Nov 9 '19 Nov 9 '19 99FF 11/9 11/9
102 4.2.2.4 Pengelasan t : 4mm 3268 cm 1 day Nov 9 '19 Nov 9 '19 99FF 11/9 11/9
103 4.2.2.5 Pek. Balok BW2 200.100.5,5.8 1024 kg 1 day Nov 8 '19 Nov 8 '19 92 11/8 11/8
104 4.2.2.6 Plate Plat 10mm x 4' x 8' 25.92 kg 1 day Nov 8 '19 Nov 8 '19 103FF 11/8 11/8
105 4.2.2.7 Baut M16 128 Bh 1 day Nov 8 '19 Nov 8 '19 103FF 11/8 11/8
106 4.2.2.8 Pengelasan t : 4mm 1376 cm 1 day Nov 8 '19 Nov 8 '19 103FF 11/8 11/8
107 4.2.3 PLAT ROOF TOP 0 5 days Nov 14 '19 Nov 18 '19
108 4.2.3.1 Pek. Plat Latai K-250 0 5 days Nov 14 '19 Nov 18 '19
109 4.2.3.1.1 Pas. Beton K-250 23.5 m3 1 day Nov 18 '19 Nov 18 '19 110 11/18 11/18
110 4.2.3.1.2 Pek. Pembesian Wiremesh M8 (1 layer) 1067.33 kg 3 days Nov 15 '19 Nov 17 '19 111FS-2 days 11/15 11/17
111 4.2.3.1.3 Pek. Bekisting 195.84 m2 3 days Nov 14 '19 Nov 16 '19 74FS+2 days 11/14 11/16
112 5 PEKERJAAN ARSITEKTUR 0 41 days Nov 12 '19 Dec 22 '19
113 5.1 A R S I T E K T U R L A N T A I 1 0 27 days Nov 12 '19 Dec 8 '19
114 5.1.1 PEKERJAAN PASANGAN 0 15 days Nov 12 '19 Nov 26 '19
115 5.1.1.1 Pek. Pas. Dinding Bata adk. 1:4 216.59 m2 7 days Nov 12 '19 Nov 18 '19 74 11/12 11/18
116 5.1.1.2 Pek. Pas. Plesteran Dinding Bata 460.65 m2 7 days Nov 16 '19 Nov 22 '19 115FS-3 days 11/16 11/22
117 5.1.1.3 Pek. Pas. Acian Dinding dan Kolom 460.65 m2 7 days Nov 20 '19 Nov 26 '19 116FS-3 days 11/20 11/26
118 5.1.1.4 Pek. Railling Tangga Hollow 4x4 dan 2x4 7.8 m2 1 day Nov 18 '19 Nov 18 '19 125 11/18 11/18
119 5.1.1.5 Pek. Pas. Step Nozing Tangga 23.52 m1 2 days Nov 18 '19 Nov 19 '19 125 11/18 11/19
120 5.1.2 PEKERJAAN LANTAI DAN DIDNING 0 22 days Nov 17 '19 Dec 8 '19
121 5.1.2.1 Pek. Pas. Lantai Keramik Motif 50x50 cm (Ruangan) 178.09 m2 7 days Nov 30 '19 Dec 6 '19 146 11/30 12/6
122 5.1.2.2 Pek. Pas. Lantai Keramik Kasar 50x50 cm (teras) 26.12 m2 3 days Nov 30 '19 Dec 2 '19 146 11/30 12/2
123 5.1.2.3 Pek. Pas. Lantai Keramik Kasar km/wc 20x20 cm 2.41 m2 1 day Dec 1 '19 Dec 1 '19 124 12/1 12/1
124 5.1.2.4 Pek. Pas. Dinding Keramik Motif km/wc 20x25 cm 9.44 m2 1 day Nov 30 '19 Nov 30 '19 146 11/30 11/30
125 5.1.2.5 Pek. Pas. Lantai Keramik Tangga 50x50 cm 10.61 m2 1 day Nov 17 '19 Nov 17 '19 83 11/17 11/17
126 5.1.2.6 Pek. Pas. Plint Lantai Keramik Ruangan 10x50 72 m2 2 days Dec 7 '19 Dec 8 '19 121 12/7 12/8
127 5.1.2.7 Pek. Pas. Plint Lantai Keramik Luar 10x50 12 m2 1 day Dec 3 '19 Dec 3 '19 122 12/3 12/3
128 5.1.3 PEKERJAAN KUSEN, PINTU DAN ALLUMINIUM 0 2 days Dec 1 '19 Dec 2 '19
129 5.1.3.1 Pas. Pintu Folding Gate 10.85 m2 2 days Dec 1 '19 Dec 2 '19 143 12/1 12/2
130 5.1.3.2 Pas. Pintu Type P2 2.35 m2 1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
131 5.1.3.3 Pas. Pintu KMWC/P3 1 Unit1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
132 5.1.3.4 Pas. Jendela Type J2 5.66 m2 1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
133 5.1.3.5 Pas. Boven Type BV1 4.8 m2 1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
134 5.1.3.6 Pas. Boven Type BV2 0.32 m2 1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
135 5.1.4 PEKERJAAN PLAFOND 0 6 days Nov 23 '19 Nov 28 '19
136 5.1.4.1 Pek. Pas. Rangka Plafond Hollow 4x4 cm 178.09 m2 3 days Nov 23 '19 Nov 25 '19 116 11/23 11/25
137 5.1.4.2 Pek. Pas. Penutup Plafond Gypsum Ruangan t.9mm 178.09 m2 3 days Nov 25 '19 Nov 27 '19 136FS-1 day 11/25 11/27
138 5.1.4.3 Pek. Pas. Penutup Plafond GRC Luar Ruangan t.6mm 22.39 m2 1 day Nov 26 '19 Nov 26 '19 136 11/26 11/26
139 5.1.4.4 Pek. Pas. List Plafond Gypsum t.15 cm (Ruangan) 72 m1 1 day Nov 28 '19 Nov 28 '19 137 11/28 11/28
140 5.1.4.5 Pek. Pas. List Plafond GRC t.15 cm (Luar) 27.06 m1 1 day Nov 27 '19 Nov 27 '19 138 11/27 11/27
141 5.1.5 PEKERJAAN PENGECATAN 0 5 days Nov 26 '19 Nov 30 '19
142 5.1.5.1 Pek. Pengecatan Dinding Luar 216.59 m2 4 days Nov 27 '19 Nov 30 '19 117 11/27 11/30
143 5.1.5.2 Pek. Pengecatan Dinding Dalam 244.06 m2 4 days Nov 27 '19 Nov 30 '19 117 11/27 11/30
144 5.1.5.3 Pek. Pengecatan Kolom Teras 44.1 m2 2 days Nov 27 '19 Nov 28 '19 117 11/27 11/28
145 5.1.5.4 Pek. Pencecatan Waterprofing Rooftop dan Dak Teras 223.87 m2 2 days Nov 26 '19 Nov 27 '19 109FS+7 days 11/26 11/27
146 5.1.5.5 Pek. Pengecatan Plafond Gypsum Ruangan 178.09 m2 2 days Nov 28 '19 Nov 29 '19 137 11/28 11/29
147 5.1.5.6 Pek. Pengecatan Plafond GRC Luar 22.39 m2 1 day Nov 27 '19 Nov 27 '19 138 11/27 11/27
148 5.2 A R S I T E K T U R L A N T A I 2 0 34 days Nov 19 '19 Dec 22 '19
149 5.2.1 PEKERJAAN PASANGAN 0 18 days Nov 19 '19 Dec 6 '19
150 5.2.1.1 Pek. Pas. Dinding Bata adk. 1:4 296.17 m2 7 days Nov 19 '19 Nov 25 '19 109 11/19 11/25
151 5.2.1.2 Pek. Pas. Plesteran Dinding Bata 597.09 m2 7 days Nov 23 '19 Nov 29 '19 150FS-3 days 11/23 11/29
152 5.2.1.3 Pek. Pas. Acian Dinding 597.09 m2 7 days Nov 27 '19 Dec 3 '19 151FS-3 days 11/27 12/3
153 5.2.1.4 Pek. Pasangan Profil Acian semen dan Tali air 17.4 m2 5 days Nov 30 '19 Dec 4 '19 151 11/30 12/4

Task Project Summary Rolled Up Baseline External Tasks Inactive Summary Manual Summary Critical
Project: GEDUNG FARMASI Split Group By Summary Rolled Up Baseline Milestone External Milestone Manual Task Start-only Critical Split
Date: Sep 24 '19 Milestone Rolled Up Task Rolled Up Progress Inactive Task Duration-only Finish-only Progress

Summary Rolled Up Milestone Baseline Split Inactive Milestone Manual Summary Rollup Deadline Slippage

Page 2
ID TaskTask Name vol satDuration
Start Finish Predecessors
Mode Oct 7, '19 Oct 14, '19 Oct 21, '19 Oct 28, '19 Nov 4, '19 Nov 11, '19 Nov 18, '19 Nov 25, '19 Dec 2, '19 Dec 9, '19 Dec 16, '19 Dec 23, '19
S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
154 5.2.1.5 Pek. Pasangan Profil semen t:10cm 7.63 m1 2 days Dec 5 '19 Dec 6 '19 153 12/5 12/6
155 5.2.1.6 Pas. Batu Tempel Hitam 9.42 m2 2 days Nov 26 '19 Nov 27 '19 150 11/26 11/27
156 5.2.2 PEKERJAAN LANTAI DAN DINDING 0 7 days Dec 11 '19 Dec 17 '19
157 5.2.2.1 Pek. Pas. Lantai Keramik Granit 60x60 (Ruangan) 169.74 m2 5 days Dec 11 '19 Dec 15 '19 176 12/11 12/15
158 5.2.2.2 Pek. Pas. Lantai Keramik Kasar km/wc 20x20 cm 6.85 m2 2 days Dec 14 '19 Dec 15 '19 159 12/14 12/15
159 5.2.2.3 Pek. Pas. Dinding Keramik Motif km/wc 20x25 cm 21.15 m2 3 days Dec 11 '19 Dec 13 '19 176 12/11 12/13
160 5.2.2.4 Pek. Pas. Dinding Keramik Motif km/wc 40x40 cm 4.82 m2 1 day Dec 11 '19 Dec 11 '19 176 12/11 12/11
161 5.2.2.5 Pek. Pas. Plint Lantai Keramik Ruangan 10x60 89 m1 2 days Dec 16 '19 Dec 17 '19 157 12/16 12/17
162 5.2.3 PEKERJAAN KUSEN, PINTU DAN ALLUMINIUM 0 2 days Dec 9 '19 Dec 10 '19
163 5.2.3.1 Pas. Pintu Type P2 9.41 m2 2 days Dec 9 '19 Dec 10 '19 175 12/9 12/10
164 5.2.3.2 Pas. Pintu KMWC/P3 2 Unit1 day Dec 9 '19 Dec 9 '19 175 12/9 12/9
165 5.2.3.3 Pas. Jendela Type J1 7.5 m2 1 day Dec 9 '19 Dec 9 '19 174 12/9 12/9
166 5.2.3.4 Pas. Jendela Type J2 22.63 m2 2 days Dec 9 '19 Dec 10 '19 174 12/9 12/10
167 5.2.3.5 Pas. Jendela Type J3 1.28 m2 1 day Dec 9 '19 Dec 9 '19 174 12/9 12/9
168 5.2.3.6 Pas. Boven Type BV2 0.63 m2 1 day Dec 9 '19 Dec 9 '19 174 12/9 12/9
169 5.2.4 PEKERJAAN PLAFOND 0 10 days Nov 30 '19 Dec 9 '19
170 5.2.4.1 Pek. Pas. Rangka Plafond Hollow 4x4 cm 184.04 m2 4 days Nov 30 '19 Dec 3 '19 151 11/30 12/3
171 5.2.4.2 Pek. Pas. Penutup Plafond Gypsum Ruangan t.9mm 184.04 m2 4 days Dec 4 '19 Dec 7 '19 170 12/4 12/7
172 5.2.4.3 Pek. Pas. List Plafond Gypsum t.15 cm (Ruangan) 89 m2 2 days Dec 8 '19 Dec 9 '19 171 12/8 12/9
173 5.2.5 PEKERJAAN PENGECATAN 0 7 days Dec 4 '19 Dec 10 '19
174 5.2.5.1 Pek. Pengecatan Dinding Luar 286.08 m2 5 days Dec 4 '19 Dec 8 '19 152 12/4 12/8
175 5.2.5.2 Pek. Pengecatan Dinding Dalam 311.01 m2 5 days Dec 4 '19 Dec 8 '19 152 12/4 12/8
176 5.2.5.3 Pek. Pengecatan Plafond Gypsum Ruangan 184.04 m2 3 days Dec 8 '19 Dec 10 '19 171 12/8 12/10
177 5.2.6 PEKERJAAN PARTISI 0 7 days Dec 16 '19 Dec 22 '19
178 5.2.6.1 Pek. Pasangan Partisi Type 1 1 Unit3 days Dec 16 '19 Dec 18 '19 157 12/16 12/18
179 5.2.6.2 Pek. Pasangan Partisi Type 2 1 Unit3 days Dec 16 '19 Dec 18 '19 157 12/16 12/18
180 5.2.6.3 Pek. Pasangan Partisi Type 3 1 Unit3 days Dec 19 '19 Dec 21 '19 179 12/19 12/21
181 5.2.6.4 Pek. Pasangan Partisi Type 4 1 Unit3 days Dec 20 '19 Dec 22 '19 179FS+1 day 12/20 12/22
182 6 PEKERJAAN SANITAIR DAN PLUMBING 0 60 days Oct 14 '19 Dec 12 '19
183 6.1 PEKERJAAN SANITAIR LANTAI 1 0 50 days Oct 14 '19 Dec 2 '19
191 6.2 PEKERJAAN PLAMBING 0 7 days Oct 15 '19 Oct 21 '19
192 6.2.1 Pek. Pas. Pipa Distribusi Dari Sumber Air ke-Tower, PVC 3/4" 35 m1 1 day Oct 15 '19 Oct 15 '19 189 10/15 10/15
193 6.2.2 Pek. Pas. Pipa Distribusi Dari Tower ke-KM/WC, PVC 1/2" 30 m1 2 days Oct 16 '19 Oct 17 '19 192 10/16 10/17
194 6.2.3 Pek. Pas. Pipa Buangan Dari KM/WC, PVC 3" 30 m1 1 day Oct 21 '19 Oct 21 '19 187 10/21 10/21
195 6.2.4 Pek. Pas. Pipa Buangan Air Tinja Manusia, PVC 4" 30 m1 1 day Oct 21 '19 Oct 21 '19 187 10/21 10/21
196 6.2.5 Pek. Pembuatan Bak Kontrol 1 ls 1 day Oct 21 '19 Oct 21 '19 187 10/21 10/21
197 6.3 PEKERJAAN SANITAIR LANTAI 2 0 31 days Nov 12 '19 Dec 12 '19
198 6.3.1 Pek. Pas. Kloset Jongkok 2 Bh 1 day Dec 12 '19 Dec 12 '19 160 12/12 12/12
199 6.3.2 Pek. Pas. Floor Drain 2 Bh 1 day Dec 12 '19 Dec 12 '19 160 12/12 12/12
200 6.3.3 Pek. Pas. Kran Air 2 Bh 1 day Dec 12 '19 Dec 12 '19 160 12/12 12/12
201 6.3.4 Pek. Pas. Westafel 1 Bh 1 day Dec 12 '19 Dec 12 '19 160 12/12 12/12
202 6.3.5 Pek. Pas. Pipa Distribusi Dari Tower ke-KM/WC, PVC 1/2" 40 m1 2 days Nov 12 '19 Nov 13 '19 74 11/12 11/13
203 6.3.6 Pek. Pas. Pipa Buangan Dari KM/WC, PVC 3" 40 m1 2 days Nov 12 '19 Nov 13 '19 74 11/12 11/13
204 6.3.7 Pek. Pas. Pipa Buangan Air Tinja Manusia, PVC 4" 35 m1 2 days Nov 12 '19 Nov 13 '19 74 11/12 11/13
205 6.4 PEKERJAAN PLAMBING 0 5 days Oct 18 '19Oct 22 '19
206 6.4.1 Pek. Pas. Pipa Distribusi Dari Tower ke-KM/WC, PVC 1/2" 35 m1 1 day Oct 18 '19Oct 18 '19193 10/18 10/18
207 6.4.2 Pek. Pas. Pipa Buangan Dari KM/WC, PVC 3" 35 m1 1 day Oct 22 '19Oct 22 '19194 10/22 10/22
208 6.4.3 Pek. Pas. Pipa Buangan Air Tinja Manusia, PVC 4" 35 m1 1 day Oct 22 '19Oct 22 '19195 10/22 10/22
209 7 PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 0 17 days Nov 25 '19 Dec 11 '19
210 7.1 L A N T A I 1 0 7 days Nov 25 '19 Dec 1 '19
211 7.1.1 Pek. Pas. Titik Lampu 10 Bh 1 day Nov 25 '19 Nov 25 '19 136FF 11/25 11/25
212 7.1.2 Pek. Pas. Lampu TL 2 x 18 Watt Inbouw 8 Bh 1 day Nov 28 '19 Nov 28 '19 137 11/28 11/28
213 7.1.3 Pek. Pas. Lampu SL 18 Watt 2 Bh 1 day Nov 28 '19 Nov 28 '19 137 11/28 11/28
214 7.1.4 Pek. Pas. Stop Kontak 1 Bh 1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
215 7.1.5 Pek. Pas. Saklar Tunggal 1 Bh 1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
216 7.1.6 Pek. Pas. Saklar Ganda 3 Bh 1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
217 7.1.7 Pek. Pas. Daya Listrik 3600 Watt 1 Ls 1 day Nov 25 '19 Nov 25 '19 136FF 11/25 11/25
218 7.1.8 Pek. Pas. MCB 6 A 1 Sett1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
219 7.1.9 Pek. Pasangan Box Panel 1 Sett1 day Dec 1 '19 Dec 1 '19 143 12/1 12/1
220 7.2 L A N T A I 2 0 9 days Dec 3 '19 Dec 11 '19
221 7.2.1 Pek. Pas. Titik Lampu 37 Bh 1 day Dec 3 '19 Dec 3 '19 170FF 12/3 12/3
222 7.2.2 Pek. Pas. Lampu TL 2 x 18 Watt Inbouw 6 Bh 1 day Dec 11 '19 Dec 11 '19 176 12/11 12/11
223 7.2.3 Pek. Pas. Lampu SL 18 Watt 31 Bh 1 day Dec 11 '19 Dec 11 '19 176 12/11 12/11
224 7.2.4 Pek. Pas. Stop Kontak 5 Bh 1 day Dec 9 '19 Dec 9 '19 175 12/9 12/9
225 7.2.5 Pek. Pas. Saklar Tunggal 7 Bh 1 day Dec 9 '19 Dec 9 '19 175 12/9 12/9
226 7.2.6 Pek. Pas. Saklar Ganda 5 Bh 1 day Dec 9 '19 Dec 9 '19 175 12/9 12/9
227 7.2.7 Pek. Pas. MCB 6 A 1 Sett1 day Dec 9 '19 Dec 9 '19 175 12/9 12/9

Task Project Summary Rolled Up Baseline External Tasks Inactive Summary Manual Summary Critical
Project: GEDUNG FARMASI Split Group By Summary Rolled Up Baseline Milestone External Milestone Manual Task Start-only Critical Split
Date: Sep 24 '19 Milestone Rolled Up Task Rolled Up Progress Inactive Task Duration-only Finish-only Progress

Summary Rolled Up Milestone Baseline Split Inactive Milestone Manual Summary Rollup Deadline Slippage