Anda di halaman 1dari 30

PEMBANGUNAN REHAB/RENOV BANGUNAN

PENDIDIKAN ANAK USIA DINI

SPS AL-MARDHIYYAH
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT

RENCANA ANGGARAN BIAYA


SCHEDULE PELAKSANAAN
LEMBAGA : SPS AL-MARDHIYYAH
KAB/PROP. : KABUPATEN PURWAKARTA PROPINSI JAWA BARAT Waktu Pelaksanaan : 45 hari kalender

BOBOT REALISASI PEKERJAAN MINGGUAN


NO. URAIAN PEKERJAAN JUMLAH HARGA PEK. NOTE
% 1 2 3 4 5 6

I PEKERJAAN PERSIAPAN Rp - - -
II PEKERJAAN TANAH Rp - - - - -
III PEKERJAAN PONDASI Rp - - - -
IV PEKERJAAN BETON Rp - - - - -
V PEKERJAAN PASANGAN, PLESTERAN & KERAMIK Rp - - - - -
VI PEKERJAAN ATAP Rp - - -
VII PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 12,769,250.50 34.470 10.341 13.788 10.341
VIII PEKERJAAN PLAFOND Rp 11,434,840.69 30.867 30.867
IX ALAT PENGGANTUNG DAN PENGUNCI Rp 3,146,750.00 8.494 8.494
X PEKERJAAN PENGECATAN Rp 9,694,099.11 26.168 13.084 13.084
XI PEK INSTALASI PENERANGAN DAN STOP KONTAK Rp - - -

TOTAL PEKERJAAN PHISIK Rp 37,044,940.30 100.000

Rencana Mingguan - - 10.341 13.788 54.293 21.579


Komulatip Rencana Mingguan - - - 10.341 24.129 78.421 100.000
Realisasi Mingguan
Komulatip Realisasi Mingguan -
DEVIASI

Purwakarta, September 2020


Diketahui Oleh, Dibuat Oleh,

Nurdiatul Jahroh, S.Ud Andi Fardiansyah. ST


Kepala Sekolah Perencana
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEMBANGUNAN RUANG KELAS BARU
SPS AL-MARDHIYYAH
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT

NO. URAIAN PEKERJAAN JUMLAH HARGA

REKAPITULASI:
I PEKERJAAN PERSIAPAN Rp -
II PEKERJAAN TANAH Rp -
III PEKERJAAN PONDASI Rp -
IV PEKERJAAN BETON Rp -
V PEKERJAAN PASANGAN, PLESTERAN & KERAMIK Rp -
VI PEKERJAAN ATAP Rp -
VII PEKERJAAN KUSEN, PINTU DAN JENDELA Rp 12,769,250.50
VIII PEKERJAAN PLAFOND Rp 11,434,840.69
IX ALAT PENGGANTUNG DAN PENGUNCI Rp 3,146,750.00
X PEKERJAAN PENGECATAN Rp 9,694,099.11
XI PEK INSTALASI PENERANGAN DAN STOP KONTAK Rp -

SUB TOTAL Rp 37,044,940.30

Biaya Perencanaan (maksimum 3%) Rp 1,111,348.21


Biaya Pengawasan (maksimum 2%) Rp 740,898.81
Biaya Pengelolaan (maksimum 1%) Rp 370,449.40
TOTAL PEKERJAAN Rp 39,267,636.72
DIBULATKAN Rp 39,000,000.00

NOTE : LUAS BANGUNAN 78.3 M2


BIAYA PERSATUAN LUAS/M2 Rp 473,115.46

Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh, Purwakarta, September 2020


Pejabat Pembuat Komitmen SPS AL-MARDHIYYAH

Nor Ilman Saputra,SH Ir, Yus Rizal Andi Fardiansyah. ST Nurdiatul Jahroh, S.Ud
NIP. 197812062005011001 Team Teknis Perencana Kepala Sekolah

Rekap
RENCANA ANGGARAN BIAYA REHABILITASI
LEMBAGA : SPS AL-MARDHIYYAH
LOKASI : KABUPATEN PURWAKARTA
PROVINSI : JAWA BARAT

TOTAL %
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA JUMLAH
KERUSAKAN

I PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pintu type P1 (Pintu Double) 2.00 unit 3,237,049.25 6,474,098.50 3.25%
2 Jendela type J1 1.00 unit 2,292,974.25 2,292,974.25 1.15%
3 Jendela type J2 4.00 unit 1,000,544.44 4,002,177.75 2.01%
Sub Total 12,769,250.50 6.41%
II PEKERJAAN PLAFOND
1 Pasang Rangka Langit-langit (0.60x1.20) m, Kayu Kelas III 97.37 m2 89,937.00 8,757,165.69 4.40%
2 Pek. Plafond Calsiboard uk. 120x240 cm, tebal 4 mm 97.37 m2 27,500.00 2,677,675.00 1.34%
Sub Total 11,434,840.69 5.74%
III ALAT PENGGANTUNG DAN PENGUNCI
1 Engsel pintu kuningan 5" 8.00 Bh 84,375.00 675,000.00 0.34%
2 Engsel jendela kuningan 3" 10.00 Bh 54,375.00 543,750.00 0.27%
3 Kunci pintu 2.00 Bh 205,250.00 410,500.00 0.21%
4 Grendel jendela 4.00 Bh 88,750.00 355,000.00 0.18%
5 Grendel pintu 10.00 M2 116,250.00 1,162,500.00 0.58%
Sub Total 3,146,750.00 1.58%
IV PEKERJAAN PENGECATAN
1 Cat dinding 172.44 M2 30,906.00 5,329,430.64 2.68%
2 Cat Plafond 97.37 M2 30,906.00 3,009,317.22 1.51%
3 Cat kayu kusen, daun pintu dan jendela 29.87 M2 45,375.00 1,355,351.25 0.68%
Sub Total 9,694,099.11 4.87%
37,044,940.30 20.47%
Biaya Perencanaan (maksimum 3%) Rp 1,111,348.21
Biaya Pengawasan (maksimum 2%) Rp 740,898.81
Biaya Pengelolaan (maksimum 1%) Rp 370,449.40
TOTAL BANTUAN REHABILITASI Rp 39,267,636.72
DIBULATKAN Rp 39,000,000.00

Luas Total Bangunan m2 78.30


Harga Satuan Pembangunan Konstruksi Fisik Bangunan
Rp 2,544,205.77
PAUD Kabupaten Purwakarta Provinsi Jawa Barat Tahun 2020
ESTIMASI HARGA BANGUNAN berdasarkan IKK Rp 199,211,311.79 100.00%

Keterangan : Kesimpulan Pengamatan :


Tingkat Kerusakan ≤ 30% = Rehabilitasi Ringan % Tingkat Kerusakan = 20.47%
Tingkat Kerusakan > 30% s/d ≤ 45% = Rehabilitasi Sedang Jenis Perawatan =
Tingkat Kerusakan > 45% s/d ≤ 65% = Rehabilitasi Berat Luas Bangunan (m2) = 78.30
Tingkat Kerusakan > 65% = Rusak Total

Disetujui Oleh, Diperiksa Oleh, Disusun oleh


Pejabat Pembuat Komitmen SPS AL-MARDHIYYAH

Nor Ilman Saputra,SH Ir. Yusrizal Andi Fardiansyah. ST Nurdiatul Jahroh, S.Ud
NIP. 197812062005011001 Team Teknis Perencana Lembaga Kepala Sekolah

Rincian RAB Lembar ke : 4


ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

I. PEKERJAAN PERSIAPAN

1 Pekerjaan Pengukuran & Pasang Bowplank / M¹


Bahan :
Bahan Kayu Klas Kuat IV 0.0120 m3 x Rp. 2,200,000.00 = Rp 26,400.00
Paku Biasa 2" - 5" 0.0200 Kg x Rp. 15,000.00 = Rp 300.00
Kayu papan 3/20, Kelas IV 0.0070 m3 x Rp. 1,850,000.00 = Rp 12,950.00
Total Bahan 39,650.00
Upah :
Pekerja 0.1000 Hr x Rp. 120,000.00 = Rp 12,000.00
Tukang Kayu 0.1000 Hr x Rp. 145,000.00 = Rp 14,500.00
Kepala Tukang 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor / Juru Ukur 0.0100 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 28,050.00
Total Pekerjaan = Rp 67,700.00

I. PEKERJAAN BONGKARAN
1 Bongkar Dinding 1/2 batu per m2
Pekerja 0.15 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.01 ohr x Rp. 0.00 = Rp -
Total Upah -

2 Bongkar Batu Kali per m3


Pekerja 1.5 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.075 ohr x Rp. 0.00 = Rp -
Total Upah -

3 Bongkar Beton per m3


Tukang Batu 1.2 ohr x Rp. 0.00 = Rp -
Pekerja 6 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.12 ohr x Rp. 0.00 = Rp -
Total Upah -

4 Bongkar Lantai per m2


Pekerja 0.1 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.01 ohr x Rp. 0.00 = Rp -
Total Upah -

5 Bongkar Plesteran per m2


Pekerja 0.05 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.025 ohr x Rp. 0.00 = Rp -
Total Upah -

6 Bongkar Atap Genteng per m2


Pekerja 0.2 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.01 ohr x Rp. 0.00 = Rp -
Total Upah -

7 Bongkar Atap Seng/Asbes Gelombang per m2


Pekerja 0.15 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.01 ohr x Rp. 0.00 = Rp -
Total Upah -

8 Bongkar kaso & reng kayu per m2


Tukang Batu 0.025 ohr x Rp. 0.00 = Rp -
Pekerja 0.1 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.025 ohr x Rp. 0.00 = Rp -
Total Upah -

9 Bongkar kuda kuda kayu per m3


Tukang Kayu 0.5 ohr x Rp. 0.00 = Rp -
Pekerja 0.35 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.05 ohr x Rp. 0.00 = Rp -
Total Upah -

ANALISA Lembar ke : 5
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

10 Bongkar plafon + rangka per m2


Pekerja 0.04 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.02 ohr x Rp. 0.00 = Rp -
Total Upah -

11 Bongkar kosen kayu per m3


Tukang Kayu 0.75 ohr x Rp. 0.00 = Rp -
Pekerja 1 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.025 ohr x Rp. 0.00 = Rp -
Total Upah = Rp -
m3 jendela type 1 0.15 = Rp -
m2 jendela type 1 3.57 = Rp -
upah bongkar per m2 -

12 Bongkar rabat beton per m2


Pekerja 0.05 ohr x Rp. 0.00 = Rp -
Kepala Tukang 0.025 ohr x Rp. 0.00 = Rp -
Total Upah -

II. PEKERJAAN TANAH


DIBULATKAN
1 Pekerjaan Galian Tanah Biasa Kedalaman 1 m / M³

Upah :
Pekerja 0.7500 Hr x Rp. 120,000.00 = Rp 90,000.00
Mandor 0.0250 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 90,000.00
Total Pekerjaan = Rp 90,000.00
2 Pekerjaan Urugan tanah kembali / M3

Upah :
Pekerja 0.2500 Hr x Rp. 120,000.00 = Rp 30,000.00
Mandor 0.0083 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 30,000.00
Total Pekerjaan = Rp 30,000.00
3 Urugan Pasir Bawah Lantai & Pondasi / M³

Bahan :
Pasir urug 1.2000 m³ x Rp. 165,000.00 = Rp 198,000.00
Total Bahan = Rp 198,000.00

Upah :
Pekerja 0.3000 Hr x Rp. 120,000.00 = Rp 36,000.00
Mandor 0.0100 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 36,000.00
Total Pekerjaan = Rp 234,000.00

III PEKERJAAN PONDASI

1 Pasangan Batu Kosong (Aanstamping) / M3

Bahan :
Batu belah 15/20 cm 1.2000 m³ x Rp. 250,000.00 = Rp 300,000.00
Pasir Pasang 0.4320 m³ x Rp. 200,000.00 = Rp 86,400.00
Total Bahan = Rp 386,400.00
Upah :
Pekerja 0.7800 Hr x Rp. 120,000.00 = Rp 93,600.00
Tukang batu 0.3900 Hr x Rp. 135,000.00 = Rp 52,650.00
Kepala Tukang 0.0390 Hr x Rp. 155,000.00 = Rp 6,045.00
Mandor 0.0390 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 152,295.00
Total Pekerjaan = Rp 538,695.00

2 Pasangan Pondasi Batu Kali 1 pc : 4 Ps / M³

Bahan :
Batu belah 15/20 cm 1.2000 m³ x Rp. 250,000.00 = Rp 300,000.00

ANALISA Lembar ke : 6
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Semen pc 163.0000 kg x Rp. 1,250.00 = Rp 203,750.00


Pasir Pasang 0.5200 m³ x Rp. 200,000.00 = Rp 104,000.00
Total Bahan = Rp 607,750.00
Upah :
Pekerja 1.5000 Hr x Rp. 120,000.00 = Rp 180,000.00
Tukang batu 0.7500 Hr x Rp. 145,000.00 = Rp 108,750.00
Kepala Tukang 0.0750 Hr x Rp. 155,000.00 = Rp 11,625.00
Mandor 0.0075 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 300,375.00

Total Pekerjaan = Rp 908,125.00

3 Pek. Dinding Bata Pasangan 1 batu, 1 pc : 2 ps / M²

Bahan :
Batu Bata Merah 140.0000 Bh x Rp. 750.00 = Rp 105,000.00
PC 24.0000 Zak x Rp. 1,250.00 = Rp 30,000.00
Pasir Pasang 0.0800 m³ x Rp. 200,000.00 = Rp 16,000.00
Total Bahan = Rp 151,000.00
Upah :
Pekerja 0.6000 Hr x Rp. 120,000.00 = Rp 72,000.00
Tukang batu 0.2000 Hr x Rp. 145,000.00 = Rp 29,000.00
Kepala Tukang 0.0200 Hr x Rp. 155,000.00 = Rp 3,100.00
Mandor 0.0300 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 104,100.00

Total Pekerjaan = Rp 255,100.00

IV. PEKERJAAN BETON

Bobot isi pasir = 1.400 kg/m3, bobot isi kerikil = 1.350 kg/m3, buckling factor pasir = 20 %

1 Beton mutu f'c=12,2 Mpa (K 150), slump (12+/-2) cm, w/c= 0,72

Bahan :
Koral Beton 0.7533 m³ x Rp. 265,000.00 = Rp 199,624.50
PC 299.0000 kg x Rp. 1,250.00 = Rp 373,750.00
Pasir Beton 0.5707 m³ x Rp. 260,000.00 = Rp 148,382.00
Air 215.0000 liter x Rp. 7,000.00 = Rp 1,505,000.00
Total Bahan = Rp 721,756.50
Upah :
Pekerja 1.6500 Hr x Rp. 120,000.00 = Rp 198,000.00
Tukang batu 0.2750 Hr x Rp. 135,000.00 = Rp 37,125.00
Kepala Tukang 0.0280 Hr x Rp. 155,000.00 = Rp 4,340.00
Mandor 0.0830 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 239,465.00

Total Pekerjaan = Rp 961,221.50


2 Pembesian Dengan Besi Polos atau Besi Ulir / KG

Bahan :
Besi beton (polos) 1.0500 kg x Rp. 10,500.00 = Rp 11,025.00
Kawat beton 0.0015 kg x Rp. 25,000.00 = Rp 37.50
Total Bahan = Rp 11,062.50
Upah :
Pekerja 0.0070 Hr x Rp. 120,000.00 = Rp 840.00
Tukang besi 0.0070 Hr x Rp. 145,000.00 = Rp 1,015.00
Kepala tukang 0.0007 Hr x Rp. 155,000.00 = Rp 108.50
Mandor 0.0004 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 1,963.50

Total Pekerjaan = Rp 13,026.00

3 Bekisting untuk sloof dan kolom/ M²

Bahan :
Kayu kelas IV 0.0450 m³ x Rp. 2,200,000.00 = Rp 99,000.00

ANALISA Lembar ke : 7
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Paku biasa 2" - 5" 0.3000 Kg x Rp. 15,000.00 = Rp 4,500.00


Minyak bekisting 0.1000 lt x Rp. 6,000.00 = Rp 600.00
Total Bahan = Rp 104,100.00
Upah :
Pekerja 0.3000 Hr x Rp. 120,000.00 = Rp 36,000.00
Tukang Kayu 0.2600 Hr x Rp. 145,000.00 = Rp 37,700.00
Kepala Tukang 0.0260 Hr x Rp. 155,000.00 = Rp 4,030.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 77,730.00

Total Pekerjaan = Rp 181,830.00

4 Balok Sloof Praktis , (15x20) cm, beton mutu f'c = 12,2 (K 150), slump (12+/-2) cm, w/c = 0,52, pembesian = 156 kg/m3

Beton mutu f'c = 26,4 (K 150) 1.0000 m³ x Rp. 961,221.50 = Rp 961,221.50


Pembesian 156.3167 kg x Rp. 13,026.00 = Rp 2,036,180.90
Bekisting 10.0000 m2 x Rp. 181,830.00 = Rp 1,818,300.00
Total Harga = Rp 4,815,702.40

6 Ring Balok , (15x25) cm, beton mutu f'c = 12,2 (K 150), slump (12+/-2) cm, w/c = 0,52, pembesian = 135 kg/m3

Beton mutu f'c = 12,2 (K 150) 1.0000 m³ x Rp. 961,221.50 = Rp 961,221.50


Pembesian 135.5333 kg x Rp. 13,026.00 = Rp 1,765,457.20
Bekisting 7.1111 m2 x Rp. 181,830.00 = Rp 1,293,013.33
Total Harga = Rp 4,019,692.03

7 Kolom Praktis Kp (15x15) cm , beton mutu f'c = 12,2 (K 150), slump (12+/-2) cm, w/c = 0,72, pembesian = 90 kg/m3

Beton mutu f'c = 26,4 (K 150) 1.0000 m³ x Rp. 961,221.50 = Rp 961,221.50


Pembesian 89.9556 kg x Rp. 13,026.00 = Rp 1,171,761.07
Bekisting 13.3333 m2 x Rp. 181,830.00 = Rp 2,424,400.00
Total Harga = Rp 4,557,382.57

8 Kolom Praktis Kp (20x20) cm , beton mutu f'c = 12,2 (K 150), slump (12+/-2) cm, w/c = 0,72, pembesian = 152 kg/m3

Beton mutu f'c = 26,4 (K 150) 1.0000 m³ x Rp. 961,221.50 = Rp 961,221.50


Pembesian 152.9583 kg x Rp. 13,026.00 = Rp 1,992,435.25
Bekisting 10.0000 m2 x Rp. 181,830.00 = Rp 1,818,300.00
Total Harga = Rp 4,771,956.75

9 Balok Kuda-Kuda Kp (20x15) cm , beton mutu f'c = 12,2 (K 150), slump (12+/-2) cm, w/c = 0,72, pembesian = 115 kg/m3

Beton mutu f'c = 26,4 (K 150) 1.0000 m³ x Rp. 961,221.50 = Rp 961,221.50


Pembesian 115.1833 kg x Rp. 13,026.00 = Rp 1,500,378.10
Bekisting 11.8519 m2 x Rp. 181,830.00 = Rp 2,155,022.22
Total Harga = Rp 4,616,621.82

V PEKERJAAN DINDING

1 Pek. Dinding Bata Pasangan 1/2 batu, 1 pc : 4 ps / M²

Bahan :
Batu Bata Merah 70.0000 Bh x Rp. 750.00 = Rp 52,500.00
PC 11.5000 Zak x Rp. 1,250.00 = Rp 14,375.00
Pasir Pasang 0.0430 m³ x Rp. 200,000.00 = Rp 8,600.00
Total Bahan = Rp 75,475.00
Upah :
Pekerja 0.3000 Hr x Rp. 120,000.00 = Rp 36,000.00
Tukang batu 0.1000 Hr x Rp. 135,000.00 = Rp 13,500.00
Kepala Tukang 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor 0.0150 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 51,050.00
Total Pekerjaan = Rp 126,525.00

1a Pek. Dinding Bataco 1 pc : 5 ps / M²

Bahan :

ANALISA Lembar ke : 8
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Bataco 12.5000 Bh x Rp. 1,000.00 = Rp 12,500.00


PC 9.6800 kg x Rp. 1,250.00 = Rp 12,100.00
Pasir Pasang 0.0450 m³ x Rp. 200,000.00 = Rp 9,000.00
Besi angkur 8 mm 0.2800 kg x Rp. 0.00 = Rp 0.00
Total Bahan = Rp 33,600.00
Upah :
Pekerja 0.3000 Hr x Rp. 120,000.00 = Rp 36,000.00
Tukang batu 0.1000 Hr x Rp. 135,000.00 = Rp 13,500.00
Kepala Tukang 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor 0.0150 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 51,050.00
Total Pekerjaan = Rp 84,650.00
2 Pek Plester + Aci 1 : 4 (t=15 mm) /M²
Bahan :
PC 6.2400 kg x Rp. 1,250.00 = Rp 7,800.00
Pasir 0.0240 m' x Rp. 200,000.00 = Rp 4,800.00
Total Bahan = Rp 12,600.00
Upah :
Pekerja 0.3000 Hr x Rp. 120,000.00 = Rp 36,000.00
Tukang Batu 0.1500 Hr x Rp. 135,000.00 = Rp 20,250.00
Kepala Tukang 0.0150 Hr x Rp. 155,000.00 = Rp 2,325.00
Mandor 0.0150 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 58,575.00
Total Pekerjaan = Rp 71,175.00

VI PEKERJAAN ATAP

1 Pekerjaan Atap Genteng / M²

Bahan :
Genteng plentong 25.0000 lbr x Rp. 3,000.00 = Rp 75,000.00
Paku biasa 2" - 5" 0.0300 kg x Rp 25,000.00 = Rp 750.00
Total Bahan = Rp 75,750.00
Upah :
Pekerja 0.2000 Hr x Rp. 120,000.00 = Rp 24,000.00
Tukang kayu 0.1000 Hr x Rp. 135,000.00 = Rp 13,500.00
Kepala Tukang Kayu 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor 0.0100 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 39,050.00
Total Pekerjaan = Rp 114,800.00
2 Pekerjaan Nok Genteng / M'

Bahan :
Nok genteng plentong 3.5000 bh x Rp. 25,000.00 = Rp 87,500.00
Paku biasa 2" - 5" 0.0500 kg x Rp. 15,000.00 = Rp 750.00
semen abu-abu 10.8000 kg x Rp. 1,250.00 = Rp 13,500.00
Pasing pasang 0.0320 m3 x Rp. 200,000.00 = Rp 6,400.00
Semen warna 1.0000 kg x Rp. 8,500.00 = Rp 8,500.00
Total Bahan = Rp 116,650.00
Upah :
Pekerja 0.4000 Hr x Rp. 120,000.00 = Rp 48,000.00
Tukang kayu 0.2000 Hr x Rp. 135,000.00 = Rp 27,000.00
Kepala Tukang Kayu 0.0200 Hr x Rp. 155,000.00 = Rp 3,100.00
Mandor 0.0200 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 78,100.00
Total Pekerjaan = Rp 194,750.00

3 Pekerjaan Atap Seng Gelombang / M²

Bahan :
Seng Gelombang 0.7000 lbr x Rp. 25,000.00 = Rp 17,500.00
Paku seng 0.0400 kg x Rp 25,000.00 = Rp 1,000.00
Total Bahan = Rp 18,500.00
Upah :
Pekerja 0.1200 Hr x Rp. 120,000.00 = Rp 14,400.00
Tukang kayu 0.0600 Hr x Rp. 135,000.00 = Rp 8,100.00
Kepala Tukang Kayu 0.0060 Hr x Rp. 155,000.00 = Rp 930.00
ANALISA Lembar ke : 9
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Mandor 0.0060 Hr x Rp. 0.00 = Rp 0.00


Total Upah = Rp 23,430.00
Total Pekerjaan = Rp 41,930.00

4 Pekerjaan Nok atap seng / M'

Bahan :
Seng plat 3"x6" BJLS 25 1.1000 m' x Rp. 65,000.00 = Rp 71,500.00
Paku seng 0.0500 kg x Rp. 25,000.00 = Rp 1,250.00
Total Bahan = Rp 72,750.00
Upah :
Pekerja 0.1500 Hr x Rp. 120,000.00 = Rp 18,000.00
Tukang kayu 0.0700 Hr x Rp. 145,000.00 = Rp 10,150.00
Kepala Tukang Kayu 0.0080 Hr x Rp. 155,000.00 = Rp 1,240.00
Mandor 0.0060 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 29,390.00

Total Pekerjaan = Rp 102,140.00

8 Memasang Kuda kuda Baja Ringan Berikut reng untuk atap genteng biasa/metal per m2
Bahan :
Profil C - 7.5, 08 2.8000 m' x Rp. 13,333.33 = Rp 37,333.33
Baut (screw driver) dia.6 x 20mm 25.0000 bh x Rp. 200.00 = Rp 5,000.00
Baut (screw driver) dia.4 x 16mm 25.0000 bh x Rp. 200.00 = Rp 5,000.00
Dynabolt dia 12 x 120mm 1.0000 bh x Rp. 2,000.00 = Rp 2,000.00
Reng R-33, 045 5.4000 m' x Rp. 35,000.00 = Rp 189,000.00
Total Bahan = Rp 238,333.33
Upah :
Pekerja 0.2000 Hr x Rp. 120,000.00 = Rp 24,000.00
Tukang Besi 0.1750 Hr x Rp. 145,000.00 = Rp 25,375.00
Kepala Tukang 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 50,925.00
Total Pekerjaan = Rp 289,258.33

9 Memasang Kuda kuda Baja Ringan Berikut reng untuk atap seng/spandek per m2
Bahan :
Profil C - 7.5, 08 2.8000 m' x Rp. 13,333.33 = Rp 37,333.33
Baut (screw driver) dia.6 x 20mm 25.0000 bh x Rp. 200.00 = Rp 5,000.00
Baut (screw driver) dia.4 x 16mm 25.0000 bh x Rp. 200.00 = Rp 5,000.00
Dynabolt dia 12 x 120mm 1.0000 bh x Rp. 2,000.00 = Rp 2,000.00
Reng R-33, 045 3.6000 m' x Rp. 35,000.00 = Rp 126,000.00
Total Bahan = Rp 175,333.33
Upah :
Pekerja 0.2000 Hr x Rp. 0.00 = Rp 0.00
Tukang Batu 0.1750 Hr x Rp. 0.00 = Rp 0.00
Kepala Tukang 0.0100 Hr x Rp. 0.00 = Rp 0.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 0.00
Total Pekerjaan = Rp 175,333.33

10 Memasang Atap Spandek Zincalum per m2


Bahan :
Atap Spandek Zincalum 1.1000 m2 x Rp. Err:509 = Rp Err:509
Screw 6.0000 bh x Rp. Err:509 = Rp Err:509
Total Bahan = Rp Err:509
Upah :
Pekerja 0.0200 Hr x Rp. 0.00 = Rp 0.00
Tukang Atap 0.0800 Hr x Rp. 0.00 = Rp 0.00
Kepala Tukang 0.0100 Hr x Rp. 0.00 = Rp 0.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 0.00
Total Pekerjaan = Rp Err:509

11 Memasang Nok Zincalum per m1


Bahan :
Nok Zincalum tebal 0,35mm 1.1000 m1 x Rp. Err:509 = Rp Err:509

ANALISA Lembar ke : 10
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Screw 6.0000 bh x Rp. Err:509 = Rp Err:509


Total Bahan = Rp Err:509
Upah :
Pekerja 0.0200 Hr x Rp. 0.00 = Rp 0.00
Tukang Atap 0.0800 Hr x Rp. 0.00 = Rp 0.00
Kepala Tukang 0.0100 Hr x Rp. 0.00 = Rp 0.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 0.00
Total Pekerjaan = Rp Err:509

VII PEKERJAAN KAYU

1 Pekerjaan Kusen Kayu Kelas II / M³


Bahan :
Kayu Kelas II 1.2000 m³ x Rp. 6,500,000.00 = Rp 7,800,000.00
Paku 10 cm 1.2500 kg x Rp. 15,000.00 = Rp 18,750.00
Lem Kayu 1.0000 kg x Rp. 15,000.00 = Rp 15,000.00
Total Bahan = Rp 7,833,750.00
Upah :
Pekerja 6.0000 Hr x Rp. 120,000.00 = Rp 720,000.00
Tukang Kayu 18.0000 Hr x Rp. 135,000.00 = Rp 2,430,000.00
Kepala Tukang Kayu 1.8000 Hr x Rp. 155,000.00 = Rp 279,000.00
Mandor 0.3000 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 3,429,000.00

Total Pekerjaan = Rp 11,262,750.00

2 Daun Pintu Double Tripleks / m2


Bahan :
Rangka Kayu Klas II 0.0250 M³ x Rp. 7,000,000.00 = Rp 175,000.00
Triplek untuk pintu uk. pintu 6mm 1.0000 Lbr x Rp. 75,000.00 = Rp 75,000.00
Lem putih 0.3000 Kg x Rp. 15,000.00 = Rp 4,500.00
Paku triplex 0.0300 Kg x Rp. 15,000.00 = Rp 450.00
ANALISA Lembar ke : 11
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Total Bahan = Rp 254,950.00


Upah :
Pekerja 0.8000 Hr x Rp. 120,000.00 = Rp 96,000.00
Tukang kayu 2.4000 Hr x Rp. 135,000.00 = Rp 324,000.00
Kepala Tukang Kayu 0.2400 Hr x Rp. 155,000.00 = Rp 37,200.00
Mandor 0.0400 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 457,200.00

Total Pekerjaan = Rp 712,150.00


Daun Pintu Double Tripleks / unit (0,8x2,1) = Rp 1,196,412.00
Daun Pintu Double Tripleks / unit (0,9x2,1) = Rp 1,345,963.50

3 Daun Pintu Kaca Polos, Kayu Kelas II / m2


Bahan :
Rangka kayu Kelas II 0.0240 M³ x Rp. 7,000,000.00 = Rp 168,000.00
Kaca Polos 5 mm 1.0000 M² x Rp. 175,000.00 = Rp 175,000.00
Lem Putih 0.3000 Kg x Rp. 15,000.00 = Rp 4,500.00
Lem Kayu 0.0300 Kg x Rp. 15,000.00 = Rp 450.00
Total Bahan = Rp 347,950.00
Upah :
Pekerja 0.8000 Hr x Rp. 120,000.00 = Rp 96,000.00
Tukang kayu 2.4000 Hr x Rp. 135,000.00 = Rp 324,000.00
Kepala Tukang Kayu 0.2400 Hr x Rp. 155,000.00 = Rp 37,200.00
Mandor 0.0400 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 457,200.00

Total Pekerjaan = Rp 805,150.00


Daun Pintu Kaca Polos, Kayu Kelas II / unit (0,8x2,1) = Rp 1,352,652.00

4 Pasang Kaca Mati tebal 5 mm / M²

Bahan :
Kaca (t=5 mm) 1.1000 M² x Rp. 175,000.00 = Rp 192,500.00
Sealent (300 ml) 0.3837 tube x Rp. 0.00 = Rp 0.00
Total Bahan = Rp 192,500.00
Upah :
Pekerja 0.0165 Hr x Rp. 120,000.00 = Rp 1,980.00
Tukang Kayu 0.1650 Hr x Rp. 135,000.00 = Rp 22,275.00
Kepala Tukang 0.0165 Hr x Rp. 155,000.00 = Rp 2,557.50
Mandor 0.0008 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 26,812.50

Total Pekerjaan = Rp 219,312.50

5 Pintu P 1 / unit
Pekerjaan Kusen Kayu Kelas II 0.0660 m³ x Rp. 11,262,750.00 = Rp 743,341.50
Daun Pintu Double Tripleks 2.0000 unit x Rp. 1,196,412.00 = Rp 2,392,824.00
Pasang Kaca Mati tebal 5 mm 0.4600 m2 x Rp. 219,312.50 = Rp 100,883.75
Total Pekerjaan \ = Rp 3,237,049.25

6 Pintu P 2 / unit
Pekerjaan Kusen Kayu Kelas II 0.0525 m³ x Rp. 11,262,750.00 = Rp 591,294.38
Daun Pintu Double Tripleks 1.0000 unit x Rp. 1,345,963.50 = Rp 1,345,963.50
Pasang Kaca Mati tebal 5 mm 0.3600 m2 x Rp. 219,312.50 = Rp 78,952.50
Total Pekerjaan = Rp 2,016,210.38

6 Jendela J.1 / unit


Pekerjaan Kusen Kayu Kelas II 0.0915 m³ x Rp. 11,262,750.00 = Rp 1,030,541.63
Pasang Kaca Mati tebal 5 mm 0.6900 m2 x Rp. 219,312.50 = Rp 151,325.63
Daun Jendela Kaca Polos, Kayu Kelas II 1.3800 m2 x Rp. 805,150.00 = Rp 1,111,107.00
Total Pekerjaan = Rp 2,292,974.25

Jendela J.2 / unit


Pekerjaan Kusen Kayu Kelas II 0.0653 m³ x Rp. 11,262,750.00 = Rp 734,894.44
Pasang Kaca Mati tebal 5 mm 0.0000 m2 x Rp. 219,312.50 = Rp 0.00
Daun Jendela Kaca Polos, Kayu Kelas II 1.3800 m2 x Rp. 192,500.00 = Rp 265,650.00
Total Pekerjaan = Rp 1,000,544.44
ANALISA Lembar ke : 12
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

7 Bovenlicht BV.1 / unit


Pekerjaan Kusen Kayu Kelas II 0.0420 m³ x Rp. 11,262,750.00 = Rp 473,035.50
Pasang Kaca Mati tebal 5 mm 0.8775 m2 x Rp. 219,312.50 = Rp 192,446.72
Total Pekerjaan = Rp 665,482.22

8 Bovenlicht BV.3 / unit


Pekerjaan Kusen Kayu Kelas II 0.0185 m³ x Rp. 11,262,750.00 = Rp 207,797.74
Pasang Kaca Mati tebal 5 mm 0.2920 m2 x Rp. 219,312.50 = Rp 64,039.25
Total Pekerjaan = Rp 271,836.99

9 Pasangan 1 BH Kunci Tanam 2 X Slag ( Union)


Bahan :
Kunci Tanam 2 x Slag 1.0000 bh x Rp. 135,000.00 = Rp 135,000.00
Total Bahan = Rp 135,000.00
Upah :
Pekerja 0.0100 Hr x Rp. 120,000.00 = Rp 1,200.00
Tukang Kayu 0.5000 Hr x Rp. 135,000.00 = Rp 67,500.00
Kepala Tukang 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 70,250.00
Total Pekerjaan = Rp 205,250.00

10 Pasangan 1 BH Engsel Pintu


Bahan :
Engsel Pintu 1.0000 bh x Rp. 60,000.00 = Rp 60,000.00
Total Bahan = Rp 60,000.00
Upah :
Pekerja 0.0150 Hr x Rp. 120,000.00 = Rp 1,800.00
Tukang Kayu 0.1500 Hr x Rp. 135,000.00 = Rp 20,250.00
Kepala Tukang 0.0150 Hr x Rp. 155,000.00 = Rp 2,325.00
Mandor 0.0008 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 24,375.00
Total Pekerjaan = Rp 84,375.00

11 Pasangan 1 BH Engsel Jendela

Bahan :
Engsel Jendela 1.0000 bh x Rp. 30,000.00 = Rp 30,000.00
Total Bahan = Rp 30,000.00
Upah :
Pekerja 0.0150 Hr x Rp. 120,000.00 = Rp 1,800.00
Tukang Kayu 0.1500 Hr x Rp. 135,000.00 = Rp 20,250.00
Kepala Tukang 0.0150 Hr x Rp. 155,000.00 = Rp 2,325.00
Mandor 0.0008 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 24,375.00
Total Pekerjaan = Rp 54,375.00
12 Pasangan 1 Bh Grendel Pintu

Bahan :
Grendel Pintu 1.0000 bh x Rp. 35,000.00 = Rp 35,000.00
Total Bahan = Rp 35,000.00
Upah :
Pekerja 0.0500 Hr x Rp. 120,000.00 = Rp 6,000.00
Tukang Kayu 0.5000 Hr x Rp. 135,000.00 = Rp 67,500.00
Kepala Tukang 0.0500 Hr x Rp. 155,000.00 = Rp 7,750.00
Mandor 0.0008 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 81,250.00
Total Pekerjaan = Rp 116,250.00

12 Pasangan 1 Bh Grendel Jendela

Bahan :
Grendel Jendela 1.0000 bh x Rp. 7,500.00 = Rp 7,500.00
Total Bahan = Rp 7,500.00
Upah :
Pekerja 0.0500 Hr x Rp. 120,000.00 = Rp 6,000.00

ANALISA Lembar ke : 13
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Tukang Kayu 0.5000 Hr x Rp. 135,000.00 = Rp 67,500.00


Kepala Tukang 0.0500 Hr x Rp. 155,000.00 = Rp 7,750.00
Mandor 0.0008 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 81,250.00
Total Pekerjaan = Rp 88,750.00

VIII PEKERJAAN RANGKA ATAP

1 Pasang Konstruksi Kuda-kuda Kayu Klas III / M3

Bahan :
Kayu balok klas III 1.1000 M³ x Rp. 3,750,000.00 = Rp 4,125,000.00
Besi strip 15.0000 Kg x Rp. 10,500.00 = Rp 157,500.00
Paku biasa 2" - 5" 5.6000 Kg x Rp. 15,000.00 = Rp 84,000.00
Total Bahan = Rp 4,366,500.00
Upah :
Pekerja 4.0000 Hr x Rp. 120,000.00 = Rp 480,000.00
Tukang kayu 12.0000 Hr x Rp. 135,000.00 = Rp 1,620,000.00
Kepala Tukang Kayu 1.2000 Hr x Rp. 155,000.00 = Rp 186,000.00
Mandor 0.2000 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 2,286,000.00
Total Pekerjaan = Rp 6,652,500.00

2 Pasang Konstruksi Gording Kayu Klas III / M3

Bahan :
Kayu kruing, balok 1.1000 M³ x Rp. 3,750,000.00 = Rp 4,125,000.00
Besi strip 15.0000 Kg x Rp. 10,500.00 = Rp 157,500.00
Paku biasa 2" - 5" 3.0000 Kg x Rp. 15,000.00 = Rp 45,000.00
Total Bahan = Rp 4,327,500.00
Upah :
Pekerja 2.4000 Hr x Rp. 120,000.00 = Rp 288,000.00
Tukang kayu 7.2000 Hr x Rp. 135,000.00 = Rp 972,000.00
Kepala Tukang Kayu 0.7200 Hr x Rp. 155,000.00 = Rp 111,600.00
Mandor 0.1200 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 1,371,600.00
Total Pekerjaan = Rp 5,699,100.00

3 Pasang Kaso + Reng Genteng Kayu Klas III / M2

Bahan :
Kaso & reng 0.0140 M³ x Rp. 3,750,000.00 = Rp 52,500.00
Paku biasa 2" - 5" 0.1500 Kg x Rp. 15,000.00 = Rp 2,250.00
Total Bahan = Rp 54,750.00
Upah :
Pekerja 0.1000 Hr x Rp. 120,000.00 = Rp 12,000.00
Tukang kayu 0.1000 Hr x Rp. 135,000.00 = Rp 13,500.00
Kepala Tukang Kayu 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 27,050.00

Total Pekerjaan = Rp 81,800.00


4 Pekerjaan Lystplank Kayu Kelas III / M'

Bahan :
Kayu Kelas III / Borneo / Meranti 0.0095 M³ x Rp. 3,500,000.00 = Rp 33,250.00
Paku 0.1000 Kg x Rp 15,000.00 = Rp 1,500.00
Total Bahan = Rp 34,750.00
Upah :
Pekerja 0.0750 Hr x Rp. 120,000.00 = Rp 9,000.00
Tukang kayu 0.1500 Hr x Rp. 135,000.00 = Rp 20,250.00
Kepala Tukang Kayu 0.0150 Hr x Rp. 155,000.00 = Rp 2,325.00
Mandor 0.0300 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 31,575.00

Total Pekerjaan = Rp 66,325.00


IX PEKERJAAN LANTAI DAN DINDING

ANALISA Lembar ke : 14
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

1 Screeding 5 CM / M²
Bahan :
PC 0.2270 Zak x Rp. 62,500.00 = Rp 14,187.50
Pasir 0.0195 M³ x Rp. 260,000.00 = Rp 5,070.00
Total Bahan = Rp 19,257.50
Upah :
Pekerja 0.4400 Hr x Rp. 120,000.00 = Rp 52,800.00
Tukang Batu 0.2200 Hr x Rp. 135,000.00 = Rp 29,700.00
Kepala Tukang Batu 0.0220 Hr x Rp. 155,000.00 = Rp 3,410.00
Mandor 0.0220 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 85,910.00
Total Pekerjaan = Rp 105,167.50

2 Pasang Lantai Keramik ukr. 40x40 cm / M2

Bahan :
Keramik 1.0608 M² xRp. 105,000.00 = Rp 111,384.00
PC 8.1900 kg xRp. 1,250.00 = Rp 10,237.50
Pasir pasang 0.0450 M² xRp. 200,000.00 = Rp 9,000.00
Semen warna 1.3000 kg xRp. 8,500.00 = Rp 11,050.00
Total Bahan = Rp 141,671.50
Upah :
Pekerja 0.7000 Hr x Rp. 120,000.00 = Rp 84,000.00
Tukang Batu 0.3500 Hr x Rp. 135,000.00 = Rp 47,250.00
Kepala Tukang 0.0350 Hr x Rp. 155,000.00 = Rp 5,425.00
Mandor 0.0350 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 136,675.00

Total Pekerjaan = Rp 278,346.50

X PEKERJAAN PLAFOND

1 Pasang Rangka Langit-langit (0.60x1.20) m, Kayu Borneo / M2

Bahan :
Kayu borneo, balok 0.0088 M³ x Rp. 3,750,000.00 = Rp 32,812.50
Paku biasa 2" - 5" 0.1000 Kg x Rp. 15,000.00 = Rp 1,500.00
Total Bahan = Rp 34,312.50
Upah :
Pekerja 0.1500 Hr x Rp. 120,000.00 = Rp 18,000.00
Tukang kayu 0.2500 Hr x Rp. 135,000.00 = Rp 33,750.00
Kepala Tukang Kayu 0.0250 Hr x Rp. 155,000.00 = Rp 3,875.00
Mandor 0.0750 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 55,625.00

Total Pekerjaan = Rp 89,937.00

2 Pek. Plafond GRC uk. 60x120 cm, tebal 4 mm / M²

Bahan :
Calsiboard 120x240x4 mm 0.3750 Lbr x Rp. 0.00 = Rp 0.00
Paku 0.0300 Kg x Rp. 15,000.00 = Rp 450.00
Total Bahan = Rp 450.00
Upah :
Pekerja 0.1000 Hr x Rp. 120,000.00 = Rp 12,000.00
Tukang Kayu 0.1000 Hr x Rp. 135,000.00 = Rp 13,500.00
Kepala Tukang 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 27,050.00

Total Pekerjaan = Rp 27,500.00

3 Pek. Plafond Tripleks uk. 120x240 cm, tebal 4 mm / M²

Bahan :
Triplek Ukr. 4x8 FT x 4 mm 0.3750 Lbr x Rp. 75,000.00 = Rp 28,125.00
ANALISA Lembar ke : 15
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Paku 0.0300 Kg x Rp. 900.00 = Rp 27.00


Total Bahan = Rp 28,152.00
Upah :
Pekerja 0.1000 Hr x Rp. 120,000.00 = Rp 12,000.00
Tukang Kayu 0.1000 Hr x Rp. 135,000.00 = Rp 13,500.00
Kepala Tukang 0.0100 Hr x Rp. 155,000.00 = Rp 1,550.00
Mandor 0.0050 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 27,050.00

Total Pekerjaan = Rp 55,202.00

XI PEKERJAAN CAT

1 Pengecatan Bidang Kayu Baru (1 Lapis Plamir), 1 Lapis Cat Dasar,


2 Lapis Cat Penutup
Bahan :
Cat meni 0.2000 Kg x Rp. 30,000.00 = Rp 6,000.00
Plamir 0.1500 Kg x Rp. 35,000.00 = Rp 5,250.00
Cat dasar 0.1700 Kg x Rp. 50,000.00 = Rp 8,500.00
Cat penutup 2 kali 0.2600 Kg x Rp. 58,000.00 = Rp 15,080.00
Total Bahan = Rp 34,830.00
Upah :
Pekerja 0.0700 Hr x Rp. 120,000.00 = Rp 8,400.00
Tukang Cat 0.0090 Hr x Rp. 135,000.00 = Rp 1,215.00
Kepala Tukang Cat 0.0060 Hr x Rp. 155,000.00 = Rp 930.00
Mandor 0.0025 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 10,545.00

Total Pekerjaan = Rp 45,375.00

2 Pengecatan Tembok Baru (1 lapis Plamir, 1 Lapis Cat Dasar,


2 Lapis cat Penutup)
Bahan :
Plamir 0.1000 Kg x Rp. 55,000.00 = Rp 5,500.00
Cat dasar 0.1000 Kg x Rp. 31,250.00 = Rp 3,125.00
Cat penutup 2 kali 0.2600 Kg x Rp. 40,000.00 = Rp 10,400.00
Total Bahan = Rp 19,025.00
Upah :
Pekerja 0.0200 Hr x Rp. 120,000.00 = Rp 2,400.00
Tukang Cat 0.0630 Hr x Rp. 135,000.00 = Rp 8,505.00
Kepala Tukang Cat 0.0063 Hr x Rp. 155,000.00 = Rp 976.50
Mandor 0.0025 Hr x Rp. 0.00 = Rp 0.00
Total Upah = Rp 11,881.50

Total Pekerjaan = Rp 30,906.00

XII PEKERJAAN INSTALASI PENERANGAN DAN STOP KONTAK

1 Instalasi Penerangan / titik

Bahan :
Kabel NYM 3 x 1,5 mm² 15.0000 M¹ x Rp. 12,000.00 = Rp 180,000.00
Perlengkapan (35% harga kabel) 0.3500 lot x Rp. 180,000.00 = Rp 63,000.00
Total Bahan = Rp 243,000.00
Upah :
Kepala Tukang 0.1065 Hr x Rp. 145,000.00 = Rp 15,442.50
Tukang Instalasi 0.2306 Hr x Rp. 135,000.00 = Rp 31,131.00
Pekerja 0.3714 Hr x Rp. 120,000.00 = Rp 44,568.00
Total Upah = Rp 91,141.50
Total Pekerjaan = Rp 334,141.50

2 Instalasi Stop kontak / titik

Bahan :
Kabel NYM 3 x 2,5 mm² 10.0000 M¹ x Rp. 13,000.00 = Rp 130,000.00
ANALISA Lembar ke : 16
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Perlengkapan (35% harga kabel) 0.3500 lot x Rp. 130,000.00 = Rp 45,500.00


Total Bahan = Rp 175,500.00
Upah :
Kepala Tukang 0.1065 Hr x Rp. 145,000.00 = Rp 15,442.50
Tukang Instalasi 0.2306 Hr x Rp. 135,000.00 = Rp 31,131.00
Pekerja 0.3714 Hr x Rp. 120,000.00 = Rp 44,568.00
Total Upah = Rp 91,141.50

Total Pekerjaan = Rp 266,641.50

2 Lampu TL 1 x 36 Watt / 1 x 40 watt (TKI) / buah


Bahan :
Lampu TL 1 x 36 watt / 1 x 40 watt (TKI) 1.0000 Bh x Rp. 75,000.00 = Rp 75,000.00
Perlengkapan (35% harga) 0.3500 lot x Rp. 75,000.00 = Rp 26,250.00
Total Bahan = Rp 101,250.00
Upah :
Kepala Tukang 0.1045 Hr x Rp. 145,000.00 = Rp 15,152.50
Tukang Instalasi 0.2294 Hr x Rp. 135,000.00 = Rp 30,969.00
Pekerja 0.3912 Hr x Rp. 120,000.00 = Rp 46,944.00
Total Upah = Rp 93,065.50

Total Pekerjaan = Rp 194,315.50

3 Lampu Pijar / buah


Bahan :
LampuPijari SL 1 x 9 Watt 1.0000 Bh x Rp. 12,500.00 = Rp 12,500.00
Perlengkapan (35% harga) 0.3500 lot x Rp. 12,500.00 = Rp 4,375.00
Total Bahan = Rp 12,500.00
Upah :
Kepala Tukang 0.0350 Hr x Rp. 145,000.00 = Rp 5,075.00
Tukang Instalasi 0.0772 Hr x Rp. 135,000.00 = Rp 10,417.50
Pekerja 0.1304 Hr x Rp. 120,000.00 = Rp 15,648.00
Total Upah = Rp 31,140.50
Total Pekerjaan = Rp 43,640.50

4 Stop kontak / titik


Bahan :
Stop kontak 10A /16A, 1 phase 1.0000 Bh x Rp. 20,000.00 = Rp 20,000.00
Perlengkapan (35% harga) 0.3500 lot x Rp. 20,000.00 = Rp 7,000.00
Total Bahan = Rp 27,000.00
Upah :
Kepala Tukang 0.0350 Hr x Rp. 145,000.00 = Rp 5,075.00
Tukang Instalasi 0.0772 Hr x Rp. 135,000.00 = Rp 10,417.50
Pekerja 0.1304 Hr x Rp. 120,000.00 = Rp 15,648.00
Total Upah = Rp 31,140.50
Total Pekerjaan = Rp 58,140.50

5 Saklar Tunggal / buah


Bahan :
Saklar tunggal 1.0000 Bh x Rp. 17,000.00 = Rp 17,000.00
Total Bahan = Rp 17,000.00
Upah :
Kepala Tukang 0.0350 Hr x Rp. 145,000.00 = Rp 5,075.00
Tukang Instalasi 0.0772 Hr x Rp. 135,000.00 = Rp 10,417.50
Pekerja 0.1304 Hr x Rp. 120,000.00 = Rp 15,648.00
Total Upah = Rp 31,140.50

Total Pekerjaan = Rp 48,140.50

6 Saklar Seri / buah

Bahan :
ANALISA Lembar ke : 17
ANALISA HARGA SATUAN PEKERJAAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

Saklar tunggal 1.0000 Bh x Rp. 20,000.00 = Rp 20,000.00


Total Bahan = Rp 20,000.00
Upah :
Kepala Tukang 0.0350 Hr x Rp. 145,000.00 = Rp 5,075.00
Tukang Instalasi 0.0772 Hr x Rp. 135,000.00 = Rp 10,417.50
Pekerja 0.1304 Hr x Rp. 120,000.00 = Rp 15,648.00
Total Upah = Rp 31,140.50

Total Pekerjaan = Rp 51,140.50

ANALISA Lembar ke : 18
DAFTAR HARGA SATUAN BAHAN
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020
AN-BYA.WK4

NO. URAIAN SATUAN HARGA (Rp.)

I PASIR DAN BATU


1 Batu Kali (Bulat Belah) M³ 250,000.00
2 Batu Pecah/Split Ukr. 2-3 cm M³ 265,000.00
3 Koral Beton M³ 265,000.00
4 Pasir Beton M³ 260,000.00
5 Pasir Pasang M³ 200,000.00
6 Pasir Urug Darat M³ 165,000.00
7 Tanah Timbun/Material Tanah Timbunan M³ 100,000.00
8 Air l 7,000.00
9 Batu Bata Merah Ukr. Besar 22x11x5 bh 750.00
10 Bataco 10x20x40 cm bh 1,000.00
II SEMEN DAN KAPUR
11 Semen Portland 50 kg Zak 62,500.00
Kg 1,250.00
12 Semen Putih 40 kg Zak 300,000.00
Kg 7,500.00
13 Semen Warna Kg 8,500.00
III KAYU
14 Kayu (Papan) Klas II M³ 7,000,000.00
15 Kayu (Balok) Klas II M³ 6,500,000.00
16 Kayu (Papan) Klas III M³ 3,500,000.00
17 Kayu (Balok) Klas III M³ 3,750,000.00
18 Kayu Bekisting (Papan) Klas IV M³ 2,200,000.00
19 Kayu Bekisting (Balok) Klas IV M³ 1,850,000.00
20 Dolken dia. 8 cm Ukr. 350 - 400 cm btg 22,000.00

IV BAJA, BESI DAN KAWAT


21 Besi Strip Kg 10,500.00
22 Besi Beton Polos Kg 10,500.00
23 Besi Beton Ulir Kg 10,500.00
24 Kawat Beton Kg 25,000.00
25 Paku Asbes buah 900.00
26 Paku segala Ukuran (rata-rata) Kg 15,000.00
27 Paku Seng Kg 25,000.00
28 Baja Ringan Profil C - 75 ≠08 btg 80,000.00
29 Baja Ringan Profil C - 75 ≠06 btg 77,500.00
30 Reng btg 35,000.00
31 Dynabolt ø10 s/d ø12 bh 2,000.00
IV CAT
28 Cat Besi/kayu kg 58,000.00
29 Cat Besi/Kayu dasar kg 50,000.00
30 Cat tembok dasar kg 31,250.00
31 Cat tembok kg 40,000.00
32 Meni Kayu kg 30,000.00
33 Minyak cat/Thinner ltr 22,500.00
34 Minyak bekisting ltr 6,000.00
35 Plamur Kayu kg 35,000.00

SATBHN Hal : 19
NO. URAIAN SATUAN HARGA (Rp.)
36 Plamur Tembok setera Matex kg 55,000.00
37 Lem Kayu kg 15,000.00
38 Sealent tube 21,000.00
39 Hampelas Gosok lembar 5,000.00

V UBIN
40 Ubin Keramik Ukr. 40/40 M² 105,000.00

VI KAYU LAPIS / AKUSTIK / GYPSUMBOARD


41 Triplek Ukr. 4x8 FT x 4 mm lbr 75,000.00
42 Multiplek Ukr. 4x8 FT x 6 mm lbr 165,000.00
43 Calsiboard 120x240x4 mm lbr

VII ALAT PENGUNCI & ATAP


44 Kaca t=5 mm, polos m² 175,000.00
45 Kunci Tanam Cilinder bh 135,000.00
46 Engsel pintu kuningan 5" bh 60,000.00
47 Engsel jendela kuningan 3" bh 30,000.00
48 Grendel jendela bh 7,500.00
49 Grendel pintu bh 35,000.00
50 Genteng bh 3,000.00
51 Nok Genteng bh 25,000.00
52 Seng Gelombang Besar BJLS 30 (0,3mm) lbr 25,000.00
53 Seng plat lebar 90 BJLS 30 m' 65,000.00
54 Atap spandek Zincalum m2 130,000.00
55 Screw Cteck bh 200.00
56 Nok Zincalum Tebal 0,35 mm m' 25,000.00

XII LAMPU, KABEL & SAKLAR (ALAT LISTRIK)


54 Kabel NYM 2x1,5 mm² m¹ 12,000.00
55 Kabel NYM 3x2,5 mm² m¹ 13,000.00
56 Lampu TL 1x36 watt & 1x40 watt (TKI) bh 75,000.00
57 Lampu Pijar SL 14 watt bh 12,500.00
58 Stop kontak 10A,16A, 1 phase ttk 20,000.00
59 Saklar tunggal bh 17,000.00
60 Saklar Seri bh 20,000.00

SPS AL-MARDHIYYAH

Nurdiatul Jahroh, S.Ud


Kepala Sekolah

SATBHN Hal : 20
DAFTAR HARGA SATUAN UPAH
KABUPATEN PURWAKARTA PROPINSI JAWA BARAT
PROYEK PEMBANGUNAN PER TAHUN 2020

NO. URAIAN SATUAN HARGA (Rp.)

1 Mandor Hari
2 Kepala Tukang Hari 155,000.00
3 Tukang Besi Hari 145,000.00
4 Tukang Kayu Hari 135,000.00
5 Tukang Batu Hari 135,000.00
6 Tukang Cat Hari 135,000.00
7 Kepala Tukang Listrik / Plumbing Hari 145,000.00
8 Tukang Listrik / Plumbing Hari 135,000.00
9 Pekerja Hari 120,000.00

SPS AL-MARDHIYYAH

Nurdiatul Jahroh, S.Ud


Kepala Sekolah

Daftar Analisa Pekerjaan Hal : 21


RENCANA ANGGARAN BIAYA ( RAB )
KEGIATAN : Perencanaa Pembangunan
PEKERJAAN : Renovasi Ruang Kelas
LOKASI : Jalan Jendral Sudirman Senayan, Jakarta 10270
TAHUN ANGGARAN : 2020

Panjang Lebar Tinggi / Tebal Bidang Jumlah


No Uraian Kegiatan Volume Satuan Satuan
( Meter) (Meter) (Meter) unit Volume
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pembersihan Lapangan dan Perataan 42.00 m2 7.00 6.00 1.00 42.00
1.00 0.00
42.00 m2

Memanjang
2 Pekerjaan Pengukuran & Pasang Bowplank 30.00 m' 8.00 2.00 16.00
1.00 0.00
Melintang
7.00 2.00 14.00
1.00 0.00
30.00 m1

II Pekerjaan Galian tanah


1 Pekerjaan Urugan tanah Peninggian lantai 8.40 m3 7.00 6.00 0.20 1.00 8.40
8.40 m3

Memanjang
2 Pekerjaan Galian Tanah Biasa Kedalaman 1 m' 13.65 m3 7.00 0.70 0.75 1.00 3.68
7.00 0.70 0.75 1.00 3.68
0.00 0.40 0.45 1.00 0.00
Melintang
6.00 0.70 0.75 1.00 3.15
6.00 0.70 0.75 1.00 3.15
0.00 0.40 0.45 1.00 0.00
0.00 0.40 0.45 1.00 0.00
13.65 m3

3 Urugan Pasir Bawah Pondasi 0.91 m3 Memanjang


7.00 0.70 0.05 1.00 0.25
7.00 0.70 0.05 1.00 0.25
0.00 0.40 0.05 1.00 0.00
Melintang
6.00 0.70 0.05 1.00 0.21
6.00 0.70 0.05 1.00 0.21
0.00 0.40 0.05 1.00 0.00
0.00 0.40 0.05 1.00 0.00
0.91 m3

4 Urugan Pasir Bawah Lantai 2.10 m3 7.00 6.00 0.05 1.00 2.10
0.00 2.00 0.05 1.00 0.00
2.10 m3

III PEKERJAAN PONDASI


1 Pekerjaan Batu Kosong (Aanstamping) 0.00 m3 Memanjang
0.00 0.70 0.15 1.00 0.00
0.00 0.70 0.15 1.00 0.00
Melintang
0.00 0.70 0.15 1.00 0.00
0.00 0.70 0.15 1.00 0.00

0.00 0.70 0.15 3.00 0.00


0.00 m3

2 Pasangan Pondasi Batu Kali 1 pc : 4 psr 8.21 m3 Memanjang


7.00 0.45 0.70 1.00 2.21
7.00 0.45 0.70 1.00 2.21
0.30 0.45 1.00 0.00
Melintang
6.00 0.45 0.70 1.00 1.89
6.00 0.45 0.70 1.00 1.89
0.30 0.45 1.00 0.02
8.21 m3

3 Pasangan Rolag Bata 1 pc : 2 psr 0.00 m3 Memanjang


0.00 0.40 0.40 1.00 0.00
Melintang
0.00 0.40 0.40 2.00 0.00
0.00 m3
4 Balok Sloof Praktis , (15x20) cm, beton mutu f'c = 26,4 (K 150), 0.78 m3 Memanjang
slump (12+/-2) cm, w/c = 0,52, pembesian = 118 kg/m3 7.00 0.15 0.20 1.00 0.21
7.00 0.15 0.20 1.00 0.21
0.15 0.20 1.00 0.00
Melintang
6.00 0.15 0.20 1.00 0.18
6.00 0.15 0.20 1.00 0.18
0.15 0.20 1.00 0.00
0.78 m3

Pekerjaan Besi Sloof 121.93 kg Sengkang


156.32 kg/m3 0.50 130.00 65.00 m
jumlah x kof.
65.00 0.395 = 25.68 kg
Tulangan
26.00 6.00 156.00 m
jumlah x kof.
156.00 0.617 = 96.25 kg
jumlah total 121.93 kg

Pekerjaan Bekisting Sloof 15.60 m2 Memanjang


20.00 m2/m3 7.00 0.40 1.00 2.80
7.00 0.40 1.00 2.80
7.00 0.40 1.00 2.80
Melintang
6.00 0.40 1.00 2.40
6.00 0.40 1.00 2.40
6.00 0.40 1.00 2.40
15.60 m2

IV PEKERJAAN BETON
1 Kolom Praktis Kp (15x15) cm , beton mutu f'c = 12,2 (K 150), 0.27 m3 3.00 0.15 0.15 4.00 0.27 m3
slump (12+/-2) cm, w/c = 0,72, pembesian = 149 kg/m3 0.27 m3

Pekerjaan Pembesian Kolom 15/15 24.29 kg Sengkang


89.96 kg/m3 0.40 60.00 24.00
jumlah x kof.
24.00 0.222 = 5.33 kg
Tulangan
12.00 4.00 48.00
jumlah x kof.
48.00 0.395 = 18.96 kg
jumlah total 24.29 kg

Pekerjaan Bekisting Kolom 15/15 7.20 m2 3.00 0.60 4.00 7.20 m2


26.67 m2/m3 7.20 m2

2 Kolom Praktis Kp (20x20) cm , beton mutu f'c = 12,2 (K 150), 0.48 m3 3.00 0.20 0.20 4.00 0.48 m3
slump (12+/-2) cm, w/c = 0,72, pembesian = 131 kg/m3 0.48 m3
Sengkang
Pekerjaan Pembesian Kolom 20/20 73.42 kg 0.60 60.00 36.00
152.96 kg/m3 jumlah x kof.
36.00 0.395 = 14.22 kg
Tulangan
12.00 8.00 96.00
jumlah x kof.
96.00 0.617 = 59.20 kg
jumlah total 73.42 kg
73.42 kg

Pekerjaan Bekisting Kolom 20/20 9.60 m2 3.00 0.80 4.00 9.60 m2


20.00 m2/m3 9.60 m2

3 Ring Balok , (15x15) cm, beton mutu f'c = 26,4 (K 150), slump 0.00 m3 Memanjang
(12+/-2) cm, w/c = 0,52, pembesian = 153 kg/m3 0.00 0.15 0.15 1.00 0.00
0.00 0.15 0.15 1.00 0.00
Melintang
0.00 0.15 0.15 1.00 0.00
0.00 0.15 0.15 1.00 0.00
0.00 m3

Pekerjaan Pembesian Ring Balk 1.11 kg Sengkang


#DIV/0! kg/m3 0.40 7.00 2.80
jumlah x kof.
2.80 0.395 = 1.11 kg
Tulangan
0.00 4.00 0.00
jumlah x kof.
0.00 0.617 = 0.00 kg
jumlah total 1.11 kg
Pekerjaan Bekisting Ring Balk 2.10 m2 Memanjang
#DIV/0! m2/m3 7.00 0.30 1.00 2.10
0.00 0.30 1.00 0.00
Melintang
0.00 0.30 1.00 0.00
0.00 0.40 1.00 0.00
2.10 m3

4 Ring Balok , (25x15) cm, beton mutu f'c = 26,4 (K 150), slump 1.46 m3 Memanjang
(12+/-2) cm, w/c = 0,52, pembesian = 153 kg/m3 7.00 0.25 0.15 1.00 0.26
7.00 0.25 0.15 1.00 0.26
7.00 0.25 0.15 1.00 0.26
Melintang
6.00 0.25 0.15 1.00 0.23
6.00 0.25 0.15 1.00 0.23
6.00 0.25 0.15 1.00 0.23
1.46 m3

Pekerjaan Pembesian Ring Balk 198.22 kg Sengkang


135.53 kg/m3 0.70 195.00 136.50
jumlah x kof.
136.50 0.395 = 53.92 kg
Tulangan
39.00 6.00 234.00
jumlah x kof.
234.00 0.617 = 144.30 kg
jumlah total 198.22 kg

Pekerjaan Bekisting Ring Balk 20.80 m2 Memanjang


14.22 m2/m3 7.00 0.65 1.00 4.55
7.00 0.65 1.00 4.55
0.00 0.65 1.00 0.00
Melintang
6.00 0.65 1.00 3.90
6.00 0.65 1.00 3.90
6.00 0.65 1.00 3.90
20.80 m2

V PEKERJAAN PASANGAN, PLESTERAN & KERAMIK


1 Pek Pasangan Dinding Bata 1 : 2 Trasram 0.00 m2 Memanjang
0.00 6.00 0.00 0.00
0.00 0.00 0.00 0.00
Melintang
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 m3
Kusen
0.70 1.50 0.00 0.00
jumlah 0.00

luas total - luas kusen


0.00 0.00 = 0.00 m2

2 Pek. Dinding Bata Pasangan 1/2 batu, 1 pc : 4 ps 18.20 m2 Memanjang


7.00 0.00 1.40 9.80
0.00 2.00 0.00
Melintang
6.00 0.00 1.40 8.40
0.00 2.00 0.00
0.00 2.00 2.00 0.00 sopi2
0.00 0.40 1.00 0.00 Tempat Bunga
18.20
Kusen
1.70 1.00 0.00 P1
2.00 2.00 0.00 J1
0.50 2.00 0.00 0.00 BV1
jumlah 0.00

luas total - luas kusen


18.20 0.00 = 18.20 m2

3 Pek Plester + Aci 1 : 4 (t=15 mm) 40.60 m2 Memanjang


7.00 0.00 1.40 9.80
7.00 0.00 2.00 14.00
Melintang
6.00 0.00 1.40 8.40
6.00 0.00 1.40 8.40

40.60
Kusen
0.00 1.70 2.00 0.00
0.00 2.00 4.00 0.00
0.00 2.00 0.00 0.00
jumlah 0.00

luas total - luas kusen


40.60 0.00 = 40.60 m2

4 Pasang Lantai Keramik ukr. 40x40 cm 42.00 m2 7.00 6.00 1.00 42.00 42.00
0.00 6.00 1.00 0.00
42.00 m2

7 Pasangan Lantai Keramik Kamar Mandi ukuran 20x20 0.00 m2 0.00 0.00 1.00 0.00
0.00 0.00 1.00 0.00
0.00 m2

VI PEKERJAAN ATAP
1 Pekerjaan Atap Genteng Keramik Natural 65.12 m2 8.00 7.00 1.00 65.12
Sudut Kemiringan 15 derajat
jumlah 65.12 m2

2 a. Pekerjaan Balok Kuda-kuda Beton (20/15) 0.19 m3 4.23 0.15 0.20 1.50 0.19
0.00 0.15 0.20 1.00 0.00
jumlah 0.19 m3

b. Pekerjaan Besi Kuda-kuda Beton 21.93 kg Sengkang


0.50 31.73 15.86
115.18 kg/m3 jumlah x kof.
15.86 0.395 = 6.27
Tulangan
6.35 4.00 25.38
jumlah x kof.
25.38 0.617 = 15.66 kg
jumlah 21.93 kg

c. Pekerjaan Begisting Kuda-kuda Beton 6.77 m2 4.23 0.40 4.00 6.77 m2


0.00 0.55 2.00 0.00 m2
0.00 0.70 1.00 0.00 m2
35.56 m2/m3 jumlah 6.77

3 Pekerjaan Atap Genteng 65.12 m3 8.00 7.00 1.00 65.12 m3


4 Pekerjaan Bubungan 8.00 m1 8.00 1.00 8.00 m1

5 Pekerjaan Talang 7.00 m1 7.00 1.00 7.00 m1

6 Pekerjaan Lisplank Kayu 15.46 m1 15.46 1.00 15.46 m1

VI Pintu Tipe P1
1 Pintu Tipe P1 2.00 unit
2 Pintu Tipe P2 0.00 unit
3 Pintu Tipe P3 0.00 unit
4 Jendela J1 5.00 unit
5 Jendela J2 0.00 unit
6 Boven BV 1 5.00 unit
7 Boven BV 2 0.00 unit
VII PEKERJAAN PLAFOND
1 Pasang Rangka Plafond Kayu 97.37 m2 10.70 9.10 1.00 97.37
0.00 1.00 1.00 0.00
0.00 1.00 2.00 0.00
0.00 4.23 2.00 2.00 0.00
97.37 m2
Toilet
0.00 0.00 1.00 0.00
0.00 0.00 1.00 0.00
0.00 m2

2 Pek. Plafond Tripleks 36.00 m2 6.00 6.00 1.00 36.00

36.00 m2
Toilet
3 Pek Plafon GRC / Kalsi Board 6 mm 100.00 m2 10.00 10.00 1.00 100.00
0.00 1.00 2.00 0.00
0.00 4.23 2.00 2.00 0.00
100.00 m2

IX ALAT PENGGANTUNG DAN KUNCI


1 Engsel Pintu 8.00 buah
2 Engsel Jendela 10.00 buah
3 Kunci pintu 2.00 buah
4 Gerendel Pintu 4.00 buah
5 Gerendel Jendela 10.00 buah
X PEKERJAAN ENGECATAN DAN LABURAN
1 Cat Dinding 200.40 m2 8.70 3.00 4.00 104.40 m2
8.00 3.00 4.00 96.00 m2
200.40
2 Cat Plafond 100.00 m2 10.00 10.00 1.00 100.00
3.00 0.00
2.00 0.00
2.00 1.00 0.00
100.00 m2
Toilet
0.00 0.00 1.00 0.00
0.00 0.00 1.00 0.00
0.00 m2

3 Cat Kayu Kusen, Daun Pintu dan Jendela 120.40 m2 2.50 2.00 5.00 m2 (Kusen Pintu P1)
92.40 0.80 2.10 2.00 2.00 6.72 m2 ( Daun Pintu P1)
28.00 3.83 1.00 3.83 m2 (Kusen Jendela J1)
7.00 0.02 0.06 1.00 1.12 m2 (Daun Jendela J1)
3.30 4.00 13.20 m2 (Bovenlicht BV1)
15.46 0.30 2.00 2.00 Lisplang
29.87 m2
XIII PEK. INSTALASI ELEKTRIKAL
1 Instalasi titik lampu (NYM 2 x 1.5 mm) in PVC Conduit 5.00 Titik
2 Instalasi Stop Kontak (NYM 3 x 2.5 mm) in PVC Conduit 2.00 Titik
3 Lampu TL 36 W 4.00 Buah
4 Lampu Pijar SL, 14 W + Fitting 1.00 Buah
5 Saklar Tunggal 3.00 Buah
6 Saklar Seri 0.00 Buah
7 Box MCB Power dan Penerangan 0.00 unit
8 Penyambungan Daya Listrik PLN 0.00 Lot