WAKTU PELAKSANAAN PEKERJAAN (TIME SCHEDULE) PROYEK ANGKUR BAKRIE METAL

INDUSTRIES

1. Pekerjaan : Anchor Bolt M25 x 710 + 3 Nut + 1 Washer (1176.24 Kg)


Rencana pekerjaan dimulai : 20 Februari 2021
Rencana pekerjaan selesai : 26 Februari 2021

WAKTU PELAKSANAAN PEKERJAAN (TIME SCHEDULE)

PROYEK DEPO LRT

Date of : 11-02-2021
No. Pekerjaan : 01. Anchor Bolt : M25 x 710 + 3 Nut + 1 Washer (1176.24 Kg)
Owner : Bakrie Metal Industries
Contractor : PT. Bending Bintang 12
Tahun 2021
Bulan Februari
Vol
No. URAIAN PEKERJAAN Minggu 1
(SET)
Hari sab min sen sel rab kam jum
Tgl 20 21 22 23 24 25 26
1 348.00

Anchor Bolt : M25 x 710 + 3 Nut + 1 Washer


(1176.24 Kg)

JUMLAH 348.00
2 RENCANA PROGRESS HARIAN (SET) 50.00 50 50 50 50 50 50 48
3 RENCANA PROGRESS MINGGUAN (%) 14.00 14.4 14.4 14.4 14.4 14.4 14.4 13.8
4 RENCANA PROGRESS KOMULATIF (%) 14.00 14 29 43 57 72 86 100

5 REALISASI PROGRESS HARIAN (SET) 0.00 - - - - - - -


6 REALISASI PROGRESS MINGGUAN (%) 0.00 - - - - - - -
7 REALISASI PROGRESS KOMULATIF (%) 0.00 - - - - - - -

8 SELISIH (DEVIASI) HARIAN (SET) 0.00 - - - - - - -


9 SELISIH (DEVIASI) MINGGUAN (%) 0.00 - - - - - - -
10 SELISIH (DEVIASI) KOMULATIF (%) 0.00 - - - - - - -
2. Pekerjaan : Anchor Bolt M25 x 810 + 3 Nut + 1 Washer (1311.96 Kg)
Rencana pekerjaan dimulai : 27 Februari 2021
Rencana pekerjaan selesai : 5 Maret 2021

WAKTU PELAKSANAAN PEKERJAAN (TIME SCHEDULE)

PROYEK DEPO LRT

Date of : 11-02-2021
No. Pekerjaan : 02. Anchor Bolt : M25 x 810 + 3 Nut + 1 Washer (1311.96 Kg)
Owner : Bakrie Metal Industries
Contractor : PT. Bending Bintang 12
Tahun 2021
Bulan Februari-Maret
Vol
No. URAIAN PEKERJAAN Minggu 2
(SET)
Hari sab min sen sel rab kam jum
Tgl 27 28 1 2 3 4 5
1 348.00

Anchor Bolt : M25 x 810 + 3 Nut + 1 Washer


(1311.96 Kg)

JUMLAH 348.00
2 RENCANA PROGRESS HARIAN (SET) 50.00 50 50 50 50 50 50 48
3 RENCANA PROGRESS MINGGUAN (%) 14.00 14.4 14.4 14.4 14.4 14.4 14.4 13.8
4 RENCANA PROGRESS KOMULATIF (%) 14.00 14 29 43 57 72 86 100

5 REALISASI PROGRESS HARIAN (SET) 0.00 - - - - - - -


6 REALISASI PROGRESS MINGGUAN (%) 0.00 - - - - - - -
7 REALISASI PROGRESS KOMULATIF (%) 0.00 - - - - - - -

8 SELISIH (DEVIASI) HARIAN (SET) 0.00 - - - - - - -


9 SELISIH (DEVIASI) MINGGUAN (%) 0.00 - - - - - - -
10 SELISIH (DEVIASI) KOMULATIF (%) 0.00 - - - - - - -
3. Pekerjaan : Anchor Bolt : M38 x 1002 + 3 Nut + 1 Washer (8981.83 Kg)
Rencana pekerjaan dimulai : 6 Maret 2021
Rencana pekerjaan selesai : 23 Maret 2021

WAKTU PELAKSANAAN PEKERJAAN (TIME SCHEDULE)

PROYEK DEPO LRT

Date of : 11-02-2021
No. Pekerjaan : 03. Anchor Bolt : M38 x 1002 + 3 Nut + 1 Washer (8981.83 Kg)
Owner : Bakrie Metal Industries
Contractor : PT. Bending Bintang 12
Tahun 2021
Bulan Maret
Vol
No. URAIAN PEKERJAAN Minggu 3
(SET)
Hari sab min sen sel rab kam jum sab min sen sel rab kam jum sab min sen sel
Tgl 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 864.00

Anchor Bolt : M38 x 1002 + 3 Nut + 1 Washer


(8981.83 Kg)

JUMLAH 864.00
2 RENCANA PROGRESS HARIAN (SET) 50.00 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 14
3 RENCANA PROGRESS MINGGUAN (%) 5.80 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 5.8 1.6
4 RENCANA PROGRESS KOMULATIF (%) 5.80 5.8 12 17 23 29 35 41 46 52 58 64 69 75 81 87 93 98 100

5 REALISASI PROGRESS HARIAN (SET) 0.00 - - - - - - - - - - - - - - - - - -


6 REALISASI PROGRESS MINGGUAN (%) 0.00 - - - - - - - - - - - - - - - - - -
7 REALISASI PROGRESS KOMULATIF (%) 0.00 - - - - - - - - - - - - - - - - - -

8 SELISIH (DEVIASI) HARIAN (SET) 0.00 - - - - - - - - - - - - - - - - - -


9 SELISIH (DEVIASI) MINGGUAN (%) 0.00 - - - - - - - - - - - - - - - - - -
10 SELISIH (DEVIASI) KOMULATIF (%) 0.00 - - - - - - - - - - - - - - - - - -
4. Pekerjaan : Anchor Bolt M38 x 792 + 3 Nut + 1 Washer (3689.21 Kg)
Rencana pekerjaan dimulai : 24 Maret 2021
Rencana pekerjaan selesai : 1 April 2021

WAKTU PELAKSANAAN PEKERJAAN (TIME SCHEDULE)

PROYEK DEPO LRT

Date of : 11-02-2021
No. Pekerjaan : 04. Anchor Bolt : M38 x 792 + 3 Nut + 1 Washer (3689.21 Kg)
Owner : Bakrie Metal Industries
Contractor : PT. Bending Bintang 12
Tahun 2021
Bulan Maret-April
Vol
No. URAIAN PEKERJAAN Minggu 4
(SET)
Hari sel rab kam jum sab min sen sel rab
Tgl 24 25 26 27 28 29 30 31 1
1 432.00

Anchor Bolt : M38 x 792 + 3 Nut + 1 Washer


(3689.21 Kg)

JUMLAH 432.00
2 RENCANA PROGRESS HARIAN (SET) 50.00 50 50 50 50 50 50 50 50 32
3 RENCANA PROGRESS MINGGUAN (%) 11.60 11.6 11.6 11.6 11.6 11.6 11.6 11.6 11.6 7.4
4 RENCANA PROGRESS KOMULATIF (%) 12.00 12 23 35 46 58 69 81 93 100

5 REALISASI PROGRESS HARIAN (SET) 0.00 - - - - - - - - -


6 REALISASI PROGRESS MINGGUAN (%) 0.00 - - - - - - - - -
7 REALISASI PROGRESS KOMULATIF (%) 0.00 - - - - - - - - -

8 SELISIH (DEVIASI) HARIAN (SET) 0.00 - - - - - - - - -


9 SELISIH (DEVIASI) MINGGUAN (%) 0.00 - - - - - - - - -
10 SELISIH (DEVIASI) KOMULATIF (%) 0.00 - - - - - - - - -