BOBOT TARGET

HK TARGET
BOBOT

M1 6-Jun s/d 12-Jun 7 4.67 4.67


M2 13-Jun s/d 19-Jun 7 4.67 9.33
M3 20-Jun s/d 26-Jun 7 4.67 14.00
M4 27-Jun s/d 3-Jul 7 4.67 18.67
M5 4-Jul s/d 10-Jul 7 35 4.67 23.33
M6 11-Jul s/d 17-Jul 7 4.67 28.00
M7 18-Jul s/d 24-Jul 7 4.67 32.67
M8 25-Jul s/d 31-Jul 7 4.67 37.33
M9 1-Aug s/d 7-Aug 7 4.67 42.00
M 10 8-Aug s/d 14-Aug 7 4.67 46.67
M 11 15-Aug s/d 21-Aug 7 4.67 51.33
M 12 22-Aug s/d 28-Aug 7 4.67 56.00
M 13 29-Aug s/d 4-Sep 7 4.67 60.67
M 14 5-Sep s/d 11-Sep 7 4.67 65.33
M 15 12-Sep s/d 18-Sep 7 4.67 70.00
M 16 19-Sep s/d 25-Sep 7 4.67 74.67
M 17 26-Sep s/d 2-Oct 7 4.67 79.33
M 18 3-Oct s/d 9-Oct 7 4.67 84.00
M 19 10-Oct s/d 16-Oct 7 4.67 88.67
M 20 17-Oct s/d 23-Oct 7 4.67 93.33
M 21 24-Oct s/d 30-Oct 7 4.67 98.00
M 22 31-Oct s/d 2-Nov 3 2.00 100.00
150 100.00
BOBOT KONTRAK = 100 %
WAKTU PELAKSANAAN = 150 HK
TARGET BOBOT HARIAN = 0.6666667

115
Pekerjaan : Rekonstruksi jalan Santiago - Buhanga - Manente
LAPORAN MINGGUAN
Lokasi : Kecamatan Tahuna
Konsultan : -
Pelaksana : PT. Karya Murni Anugerah Minggu Ke - : 1 (Satu)
Tahun Anggaran : 2023 Dari Tgl : 06 Juni 2023
s/d Tgl : 12 Juni 2023

Realisasi Pelaksanaan Fisik


Kontrak
No. Mata Volume % terhadap
Uraian Pekerjaan Sat.
Pembayaran Bobot s/d Miggu Minggu s/d Minggu Item Seluruh
Volume
(%) Lalu ini ini Pek. Pek.
1 2 3 4 5 6 7 8 9 10

DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.53 - - - - -

DIVISI 2. KESELAMATAN DAN KESEHATAN KERJA


2.1 Penyiapan Dokumen Penerapan SMKK Ls 1.00 0.03 - - - - -
2.2 Sosialisasi, Promosi Dan Pelatihan Ls 1.00 0.04 - - - - -
2.3 Alat Pelindung Kerja Dan Alat Pelindung Diri Ls 1.00 0.40 - - - - -
2.4 Asuransi Dan Perijinan Terkait Keselamatan Konstruksi Ls 1.00 0.04 - - - - -
2.5 Persenil Keselamatan Konstruksi Ls 1.00 0.24 - - - - -
2.6 Fasilitas Sarana Prasarana Dan Alat Kesehatan Ls 1.00 0.03 - - - - -
2.7 Rambu Dan Perlengkapan Lalulintas Yang Diperlukan Atau Manejemen Ls 1.00 0.03 - - - - -
2.8 Konsultasi Dengan Ahli Terkait Keselamatan Konstruksi Ls 1.00 0.01 - - - - -
2.9 Kegiatan Dan Peralatan Terkait Pengendalian Resiko Keselamatan Konst Ls 1.00 0.02 - - - - -

DIVISI 3. DRAINASE
3.1.(1) Galian Untuk Selokan Drainase Dan Saluran Air M3 254.53 1.29 - - - - -
3.2.(1) Pasangan Batu Dengan Mortar M3 148.49 13.39 - - - - -

DIVISI 6. BERBUTIR DAN PERKERASAN BETON SEMEN


6.1.(1) Lapis Pondasi Agregat Kelas A M3 306.25 19.03 - - - - -

DIVISI 7. PERKERASAN ASPAL


7.1 (1) Lapis Resap Pengikat - Aspal Cair / Emulsi Ltr 1,225.00 1.99 - - - - -
7.3(5a) Laston Lapis Aus (AC-WC) Ton 215.60 43.37 - - - - -
7.3.8 Bahan anti pengelupasan Kg 35.57 0.23 - - - - -

DIVISI 8. STRUKTUR
8.1 (7a) Beton Struktur fc' 15 Mpa M3 96.86 16.07 - - - - -
8.14 (2) Pembongkaran Pasangan Batu M3 18.00 0.25 - - - - -

Total Bobot 100.00 0.00


Bobot sampai dengan minggu lalu 0.00
Bobot dalam minggu ini 0.00

BOBOT TERHADAP KURVA S


bobot realisasi -
bobot rencana 0.65
deviasi (0.65)
Pekerjaan : Rekonstruksi jalan Santiago - Buhanga - Manente
LAPORAN MINGGUAN
Lokasi : Kecamatan Tahuna
Konsultan : -
Pelaksana : PT. Karya Murni Anugerah Minggu Ke - : 2
Tahun Anggaran : 2023 Dari Tgl : 13 Juni 2023
s/d Tgl : 19 Juni 2023

Realisasi Pelaksanaan Fisik


Kontrak
No. Mata Volume % terhadap
Uraian Pekerjaan Sat.
Pembayaran Bobot s/d Miggu Minggu s/d Minggu Item Seluruh
Volume
(%) Lalu ini ini Pek. Pek.
1 2 3 4 5 6 7 8 9 10

DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.53 - 0.10 0.10 10.00 0.35

DIVISI 2. KESELAMATAN DAN KESEHATAN KERJA


2.1 Penyiapan Dokumen Penerapan SMKK Ls 1.00 0.03 - - - - -
2.2 Sosialisasi, Promosi Dan Pelatihan Ls 1.00 0.04 - - - - -
2.3 Alat Pelindung Kerja Dan Alat Pelindung Diri Ls 1.00 0.40 - - - - -
2.4 Asuransi Dan Perijinan Terkait Keselamatan Konstruksi Ls 1.00 0.04 - - - - -
2.5 Persenil Keselamatan Konstruksi Ls 1.00 0.24 - - - - -
2.6 Fasilitas Sarana Prasarana Dan Alat Kesehatan Ls 1.00 0.03 - - - - -
2.7 Rambu Dan Perlengkapan Lalulintas Yang Diperlukan Atau Manejemen Ls 1.00 0.03 - - - - -
2.8 Konsultasi Dengan Ahli Terkait Keselamatan Konstruksi Ls 1.00 0.01 - - - - -
2.9 Kegiatan Dan Peralatan Terkait Pengendalian Resiko Keselamatan Konst Ls 1.00 0.02 - - - - -

DIVISI 3. DRAINASE
3.1.(1) Galian Untuk Selokan Drainase Dan Saluran Air M3 254.53 1.29 - - - - -
3.2.(1) Pasangan Batu Dengan Mortar M3 148.49 13.39 - - - - -

DIVISI 6. BERBUTIR DAN PERKERASAN BETON SEMEN


6.1.(1) Lapis Pondasi Agregat Kelas A M3 306.25 19.03 - - - - -

DIVISI 7. PERKERASAN ASPAL


7.1 (1) Lapis Resap Pengikat - Aspal Cair / Emulsi Ltr 1,225.00 1.99 - - - - -
7.3(5a) Laston Lapis Aus (AC-WC) Ton 215.60 43.37 - - - - -
7.3.8 Bahan anti pengelupasan Kg 35.57 0.23 - - - - -

DIVISI 8. STRUKTUR
8.1 (7a) Beton Struktur fc' 15 Mpa M3 96.86 16.07 - - - - -
8.14 (2) Pembongkaran Pasangan Batu M3 18.00 0.25 - - - - -

Total Bobot 100.00 0.35


Bobot sampai dengan minggu lalu 0.00
Bobot dalam minggu ini 0.35

BOBOT TERHADAP KURVA S


bobot realisasi 0.35
bobot rencana 1.31
deviasi (0.96)
Pekerjaan : Rekonstruksi jalan Santiago - Buhanga - Manente
LAPORAN MINGGUAN
Lokasi : Kecamatan Tahuna
Konsultan : -
Pelaksana : PT. Karya Murni Anugerah Minggu Ke - : 3
Tahun Anggaran : 2023 Dari Tgl : 20 Juni 2023
s/d Tgl : 26 Juni 2023

Realisasi Pelaksanaan Fisik


Kontrak
No. Mata Volume % terhadap
Uraian Pekerjaan Sat.
Pembayaran Bobot s/d Miggu Minggu s/d Minggu Item Seluruh
Volume
(%) Lalu ini ini Pek. Pek.
1 2 3 4 5 6 7 8 9 10

DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.53 0.10 0.10 0.20 20.00 0.71

DIVISI 2. KESELAMATAN DAN KESEHATAN KERJA


2.1 Penyiapan Dokumen Penerapan SMKK Ls 1.00 0.03 - - - - -
2.2 Sosialisasi, Promosi Dan Pelatihan Ls 1.00 0.04 - - - - -
2.3 Alat Pelindung Kerja Dan Alat Pelindung Diri Ls 1.00 0.40 - - - - -
2.4 Asuransi Dan Perijinan Terkait Keselamatan Konstruksi Ls 1.00 0.04 - - - - -
2.5 Persenil Keselamatan Konstruksi Ls 1.00 0.24 - - - - -
2.6 Fasilitas Sarana Prasarana Dan Alat Kesehatan Ls 1.00 0.03 - - - - -
2.7 Rambu Dan Perlengkapan Lalulintas Yang Diperlukan Atau Manejemen Ls 1.00 0.03 - - - - -
2.8 Konsultasi Dengan Ahli Terkait Keselamatan Konstruksi Ls 1.00 0.01 - - - - -
2.9 Kegiatan Dan Peralatan Terkait Pengendalian Resiko Keselamatan Konst Ls 1.00 0.02 - - - - -

DIVISI 3. DRAINASE
3.1.(1) Galian Untuk Selokan Drainase Dan Saluran Air M3 254.53 1.29 - - - - -
3.2.(1) Pasangan Batu Dengan Mortar M3 148.49 13.39 - - - - -

DIVISI 6. BERBUTIR DAN PERKERASAN BETON SEMEN


6.1.(1) Lapis Pondasi Agregat Kelas A M3 306.25 19.03 - - - - -

DIVISI 7. PERKERASAN ASPAL


7.1 (1) Lapis Resap Pengikat - Aspal Cair / Emulsi Ltr 1,225.00 1.99 - - - - -
7.3(5a) Laston Lapis Aus (AC-WC) Ton 215.60 43.37 - - - - -
7.3.8 Bahan anti pengelupasan Kg 35.57 0.23 - - - - -

DIVISI 8. STRUKTUR
8.1 (7a) Beton Struktur fc' 15 Mpa M3 96.86 16.07 - - - - -
8.14 (2) Pembongkaran Pasangan Batu M3 18.00 0.25 - - - - -

Total Bobot 100.00 0.71


Bobot sampai dengan minggu lalu 0.35
Bobot dalam minggu ini 0.35

BOBOT TERHADAP KURVA S


bobot realisasi 0.71
bobot rencana 2.03
deviasi (1.32)
Pekerjaan : Rekonstruksi jalan Santiago - Buhanga - Manente
LAPORAN MINGGUAN
Lokasi : Kecamatan Tahuna
Konsultan : -
Pelaksana : PT. Karya Murni Anugerah Minggu Ke - : 4
Tahun Anggaran : 2023 Dari Tgl : 27 Juni 2023
s/d Tgl : 03 Juli 2023

Realisasi Pelaksanaan Fisik


Kontrak
No. Mata Volume % terhadap
Uraian Pekerjaan Sat.
Pembayaran Bobot s/d Miggu Minggu s/d Minggu Item Seluruh
Volume
(%) Lalu ini ini Pek. Pek.
1 2 3 4 5 6 7 8 9 10

DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.53 0.20 0.20 0.40 40.00 1.41

DIVISI 2. KESELAMATAN DAN KESEHATAN KERJA


2.1 Penyiapan Dokumen Penerapan SMKK Ls 1.00 0.03 - - - - -
2.2 Sosialisasi, Promosi Dan Pelatihan Ls 1.00 0.04 - - - - -
2.3 Alat Pelindung Kerja Dan Alat Pelindung Diri Ls 1.00 0.40 - - - - -
2.4 Asuransi Dan Perijinan Terkait Keselamatan Konstruksi Ls 1.00 0.04 - - - - -
2.5 Persenil Keselamatan Konstruksi Ls 1.00 0.24 - - - - -
2.6 Fasilitas Sarana Prasarana Dan Alat Kesehatan Ls 1.00 0.03 - - - - -
2.7 Rambu Dan Perlengkapan Lalulintas Yang Diperlukan Atau Manejemen Ls 1.00 0.03 - - - - -
2.8 Konsultasi Dengan Ahli Terkait Keselamatan Konstruksi Ls 1.00 0.01 - - - - -
2.9 Kegiatan Dan Peralatan Terkait Pengendalian Resiko Keselamatan Konst Ls 1.00 0.02 - - - - -

DIVISI 3. DRAINASE
3.1.(1) Galian Untuk Selokan Drainase Dan Saluran Air M3 254.53 1.29 - - - - -
3.2.(1) Pasangan Batu Dengan Mortar M3 148.49 13.39 - - - - -

DIVISI 6. BERBUTIR DAN PERKERASAN BETON SEMEN


6.1.(1) Lapis Pondasi Agregat Kelas A M3 306.25 19.03 - - - - -

DIVISI 7. PERKERASAN ASPAL


7.1 (1) Lapis Resap Pengikat - Aspal Cair / Emulsi Ltr 1,225.00 1.99 - - - - -
7.3(5a) Laston Lapis Aus (AC-WC) Ton 215.60 43.37 - - - - -
7.3.8 Bahan anti pengelupasan Kg 35.57 0.23 - - - - -

DIVISI 8. STRUKTUR
8.1 (7a) Beton Struktur fc' 15 Mpa M3 96.86 16.07 - - - - -
8.14 (2) Pembongkaran Pasangan Batu M3 18.00 0.25 - - - - -

Total Bobot 100.00 1.41


Bobot sampai dengan minggu lalu 0.71
Bobot dalam minggu ini 0.71

BOBOT TERHADAP KURVA S


bobot realisasi 1.41
bobot rencana 2.68
deviasi (1.27)
Pekerjaan : Rekonstruksi jalan Santiago - Buhanga - Manente
LAPORAN MINGGUAN
Lokasi : Kecamatan Tahuna
Konsultan : -
Pelaksana : PT. Karya Murni Anugerah Minggu Ke - : Minggu ke 5
Tahun Anggaran : 2023 Dari Tgl : 04 Juli 2023
s/d Tgl : 10 Juli 2023

Realisasi Pelaksanaan Fisik


Kontrak
No. Mata Volume % terhadap
Uraian Pekerjaan Sat.
Pembayaran Bobot s/d Miggu Minggu s/d Minggu Item Seluruh
Volume
(%) Lalu ini ini Pek. Pek.
1 2 3 4 5 6 7 8 9 10

DIVISI 1. UMUM
1.2 Mobilisasi Ls 1.00 3.53 0.40 0.10 0.50 50.00 1.77

DIVISI 2. KESELAMATAN DAN KESEHATAN KERJA


2.1 Penyiapan Dokumen Penerapan SMKK Ls 1.00 0.03 - - - - -
2.2 Sosialisasi, Promosi Dan Pelatihan Ls 1.00 0.04 - - - - -
2.3 Alat Pelindung Kerja Dan Alat Pelindung Diri Ls 1.00 0.40 - - - - -
2.4 Asuransi Dan Perijinan Terkait Keselamatan Konstruksi Ls 1.00 0.04 - - - - -
2.5 Persenil Keselamatan Konstruksi Ls 1.00 0.24 - - - - -
2.6 Fasilitas Sarana Prasarana Dan Alat Kesehatan Ls 1.00 0.03 - - - - -
2.7 Rambu Dan Perlengkapan Lalulintas Yang Diperlukan Atau Manejemen Ls 1.00 0.03 - - - - -
2.8 Konsultasi Dengan Ahli Terkait Keselamatan Konstruksi Ls 1.00 0.01 - - - - -
2.9 Kegiatan Dan Peralatan Terkait Pengendalian Resiko Keselamatan Konst Ls 1.00 0.02 - - - - -

DIVISI 3. DRAINASE
3.1.(1) Galian Untuk Selokan Drainase Dan Saluran Air M3 254.53 1.29 - - - - -
3.2.(1) Pasangan Batu Dengan Mortar M3 148.49 13.39 - - - - -

DIVISI 6. BERBUTIR DAN PERKERASAN BETON SEMEN


6.1.(1) Lapis Pondasi Agregat Kelas A M3 306.25 19.03 - - - - -

DIVISI 7. PERKERASAN ASPAL


7.1 (1) Lapis Resap Pengikat - Aspal Cair / Emulsi Ltr 1,225.00 1.99 - - - - -
7.3(5a) Laston Lapis Aus (AC-WC) Ton 215.60 43.37 - - - - -
7.3.8 Bahan anti pengelupasan Kg 35.57 0.23 - - - - -

DIVISI 8. STRUKTUR
8.1 (7a) Beton Struktur fc' 15 Mpa M3 96.86 16.07 - - - - -
8.14 (2) Pembongkaran Pasangan Batu M3 18.00 0.25 - - - - -

Total Bobot 100.00 1.77


Bobot sampai dengan minggu lalu 1.41
Bobot dalam minggu ini 0.35

BOBOT TERHADAP KURVA S


bobot realisasi 1.77
bobot rencana 2.76
deviasi (1.00)