REKAP PEKERJAAN GALIAN - M RESORT GILI MENO

NO ITEM PEKERJAAN
1 PEMBERSIHAN LAHAN TERMASUK RUMPUT , SEMAK BELUKAR , SAMPAH , MENEBANG
ATAU MEMINDAHKAN POHON BESAR , AKAR POHON TERMASUK BUANGAN
DAN IZIN KELOLA
2 GALIAN TANAH / POTONG TANAH UNTUK MENCAPAI ELEVASI BANGUNAN
3 GALIAN TANAH UNTUK PANDASI
4 URUGAN TANAH TERMASUK PEMADATAN
5 URUGAN TANAH DILOKASI PROYEK
6 URUGAN TANAH DARI LOMBOK
( SUDAH TERMASUK TRANSPORT BOAT DAN PORTER TURUN NAIK )
7 BUANG TANAH

NOTE :
HARGA DIATAS BELUM TERMASUK
ONGKOS TRANSPORT ALAT BERAT DARI GUDANG KE PELABUHAN DAN SEBALIKNYA
6,000,000
ONGKOS BOAT MEMBAWA ALAT BERAT DARI PELABUHAN KE GILI MENO
20,000,000

TOTAL : 26,000,000
GILI MENO

SATUAN VOLUME HARGA MANUAL HARGA MESIN TOTAL MANUAL


M3 9,487 45,000 30,000 426,912,300

M3 2,585 125,000 80,000 323,120,000


M3 4,022 130,000 80,000 522,879,500
M3 73 180,000 100,000 13,132,800
M3 1,424 140,000 60,000 199,322,200
BOAT 750,000 750,000

M3 4,984 175,000 175,000 872,242,000

GRAND TOTAL 2,357,608,800


TOTAL MESIN
284,608,200

206,796,800
321,772,000
7,296,000
85,423,800

872,242,000

1,778,138,800