Anda di halaman 1dari 12

Check list dokumentasi kelengkapan eBAST

No. Folder dokumentasi


0 Cover dan Daftar Isi Dokumentasi

1 Dokumen Tender :
01_RKS Administrasi
02_RKS Teknis

2 Dokumen Administrasi Awal : Copy PO


Kontrak Pekerjaan XXX YYY ZZZ (HOC16xxx) PT XYZ
Dokumen Aanweijzing ( MoM )

3 Dokumen Jadwal dan Perencanaan :


01_ Project Schedule & MOM KOM
02_ Kurva S_ Pekerjaan ( file xlsx)
03_ Struktur Organisasi
04_ Daftar Tenaga kerja ( Nomer Kartu Halo + KTP )

4 Persetujuan Material:
01_ Pekerjaan Sipil
02_ Pekerjaan Arsitektur
03_ Pekerjaan Elektrikal
04_ Pekerjaan Mechanikal ( AC/PAC)
05_ Pekerjaan Security System
06_ Pekerjaan Fire System

5 Dokumen Change Request – (CR jika Ada)


Ada berapa CR ?

6 Dokumen MOP ( Ada berapa MoP ? )

7 Dokumen Testing/ Pra ATP


Ada berapa Test ? (Grounding, Insulation Resistance, Phase Rotation, Battery Load Test,
integration Test, dll )

8 Drawing :
a.    Shop Drawing / As plan Drawing
b.   1. As Built Drawing Hard Copy
b.    2. Soft Copy As Built Drawing ( dwg, pdf from dwg, pdfscan ttd )

9 Dokumen Inventarisasi ( untuk pelaporan aset ke Operation & Asset )


Sesuai format (sheet 2)
10 Dokumen Training (jika ada)
a.    Pekerjaan Elektrikal
b.    Pekerjaan Mechanikal
c.     Pekerjaan Security System
d.    Pekerjaan Fire System

11 Dokumen eBAST (ebast pertama)/Dokumen ATP

12 a. Dokumen Garansi
b. Dokumen Perawatan rutin (Maintenance) / dokumen pending Item yang telah dilaksanakan
c. Surat Bebas Claim Pernyataan Subcon tidak ada tunggakan pembayaran, pending item dll

13 Foto-Foto Dokumentasi
Foto-Foto Pelaksanaan Proyek, dari Kick of Meeting, Penggalian Fondasi sampai proses
BAST.

14 Dokumentasi Lainnya
IMB, Sertifikat, dll
Nilai Bobot % OK / NOK
1 1

3
1 ok
2 ok

5
3 ok
2 ok

4
1 ok
1 ok
1 ok
1 ok

3 ok
0.5
0.5
0.5
0.5
0.5
0.5

2
2

2 2 ok

15

15

49
19
20
10

2
2
4
1
1
1
1

2 2

4 2
1
1

2
2
100 100
No. Number PO Site ID Site Name Floor Lokasi (ruang) Terpasang

1 HOC141423 Rooftop Lantai Rooftop


2 HOC151612 Rooftop Lantai Rooftop
3 HOC141423 Rooftop Lantai Rooftop
4 HOC151612 Rooftop Lantai Rooftop
5 HOC160818 Rooftop Lantai Rooftop
6 HOC151392 Rooftop Lantai Rooftop
7 HOC151612 Rooftop Lantai Rooftop
8 HOC141423 Rooftop Lantai Rooftop
9 HOC141423 Rooftop Lantai Rooftop
10 HOC141423 Rooftop Lantai Rooftop
11 HOC151612 Rooftop Lantai Rooftop
12 HOC141423 Rooftop Lantai Rooftop
13 HOC141423 Rooftop Lantai Rooftop
14 HOC141423 Rooftop Lantai Rooftop
15 HOC160818 Rooftop Lantai Rooftop
16 HOC151392 Rooftop Lantai Rooftop
17 HOC141423 Rooftop Lantai Rooftop
18 HOC141423 Rooftop Lantai Rooftop
19 HOC151612 Rooftop Lantai Rooftop
20 HOC151612 Rooftop Lantai Rooftop
21 HOC141204 Basement 1 Lantai B1 Ruang Power House
22 HOC141204 Basement 1 Lantai B1 Ruang Power House
23 HOC141204 Basement 1 Lantai B1 Ruang Power House
24 HOC151612 Basement 1 Lantai B1 Ruang Power House
25 HOC141204 Basement 1 Lantai B1 Ruang Power House
26 HOC151612 Basement 1 Lantai B1 Ruang Power House
27 HOC151612 Basement 1 Lantai B1 Ruang Power House
28 HOC151612 Basement 1 Lantai B1 Ruang Power House
29 HOC151612 Basement 1 Lantai B1 Ruang Power House
30 By Telkomsel Basement 1 Lantai B1 Ruang Power House
31 HOC151612 Basement 1 Lantai B1 Ruang Power House
32 HOC151612 Basement 1 Lantai B1 Ruang Power House
33 HOC151612 Basement 1 Lantai B1 Ruang Power House
34 HOC151612 Basement 1 Lantai B1 Ruang Power House
35 By Telkomsel Basement 1 Lantai B1 Ruang Power House
36 By Telkomsel Basement 1 Lantai B1 Ruang Power House
37 By Telkomsel Basement 1 Lantai B1 Ruang Power House
38 By Telkomsel Basement 1 Lantai B1 Ruang Power House
39 HOC151612 Basement 1 Lantai B1 Ruang Power House
40 HOC141204 Basement 1 Lantai B1 Ruang Power House
41 HOC141204 Basement 1 Lantai B1 Ruang Power House
42 HOC141204 Basement 1 Lantai B1 Ruang Power House
43 HOC141204 Basement 1 Lantai B1 Ruang Power House
44 HOC141204 Basement 1 Lantai B1 Ruang Power House
45 HOC151612 Basement 1 Lantai B1 Ruang Power House
46 HOC151612 Basement 1 Lantai B1 Ruang Power House
47 HOC141204 Basement 2 Lantai B2 Ruang Pompa
48 HOC151612 Basement 2 Lantai B2 Ruang Pompa
49 HOC141423 Basement 2 Lantai B2 Ruang Pompa
50 HOC151612 Basement 2 Lantai B2 Ruang Pompa
51 HOC151612 Basement 2 Lantai B2 Ruang Pompa
52 HOC151612 Basement 2 Lantai B2 Ruang Pompa
53 HOC151612 Basement 2 Lantai B2 Ruang Pompa
54 HOC151612 Basement 2 Lantai B2 Ruang Pompa
55 HOC151612 Basement 2 Lantai B2 Ruang Pompa
56 HOC151612 Basement 2 Lantai B2 Ruang Pompa
57 HOC151612 Basement 2 Lantai B2 Ruang Pompa
58 HOC141423 Basement 2 Lantai B2 Ruang Pompa
59 HOC141423 Basement 2 Lantai B2 Ruang Pompa
60 HOC151612 Basement 2 Lantai B2 Ruang Pompa
61 HOC151612 Lantai 7 Lantai 7 Ruang Power-B
Perangkat
Nama Panel/ Perangkat terpasang Scope Pekerjaan Proyek
Merk
Panel Control Cooling Tower-A Cooling Phase-1
Panel Control Cooling Tower-B Phase-2
Panel Outdoor AC VRV-A Cooling Phase-1
Panel Outdoor AC VRV-B Phase-2
Panel Outdoor Unit IOC IOC
Panel Outdoor Unit Cafetaria Cafetaria
Panel EMS Phase-2
Panel Control Water Treatment Cooling Phase-1
Torrent Chemical Water Treatment Cooling Phase-1
Cooling Tower-A Cooling Phase-1
Cooling Tower-B Phase-2
Bak Make Up Water Cooling Phase-1
Booster Pump Cooling Phase-1
Feed Pump CT-2 Cooling Phase-1
Outdoor Unit IOC IOC
Outdoor Unit Cafetaria Cafetaria
Outdoor Unit AC VRV Cooling Phase-1
Outdoor Unit AC VRV Cooling Phase-1
APAR 3kg Phase-2
CCTV Phase-2
Trafo (Relokasi Ex. TTC BSD) Phase-1
Panel LVMDP Phase-1
Panel COS-A Phase-1
Panel COS-B Phase-2
Panel PKG-A Phase-1
Panel Utility B1 Phase-2
Panel EMS Phase-2
Panel ACS Phase-2
Panel HUB CCTV Phase-2
Panel Pompa Genset Pengadaan Genset
APAR 3kg Phase-2
APAR 20kg Phase-2
Access System Phase-2
CCTV Phase-2
Genset Komatsu 1000kVA Pengadaan Genset
Tangki Solar Genset Weekly (10000 liter) Pengadaan Genset
Tangki Solar Genset Daily (1000 liter) Pengadaan Genset
Exhause Fan Pengadaan Genset
Sensor Temperature & Humidity Phase-2
Section Busduct Genset ke Panel PKG-A Phase-1
Section Busduct Trafo ke Panel LVMDP Phase-1
Section Busduct Panel LVMDP ke Panel COS-A Phase-1
Section Busduct Panel PKG-A ke Panel COS-A Phase-1
Section Busduct Panel COS-A ke Panel MDP-A Phase-1
Section Busduct Panel LVMDP ke Panel COS-B Phase-2
Section Busduct Panel COS-B ke Panel MDP-B Phase-2
Panel Cooling Tower-A Phase-1
Panel Cooling Tower-B Phase-2
Panel Control Pompa CT-A Cooling Phase-1
Panel Control Pompa CT-B Phase-2
Panel ATS Pompa CT Phase-2
Panel EMS Phase-2
Panel ACS Phase-2
Panel HUB CCTV Phase-2
Access System Phase-2
APAR 3kg Phase-2
CCTV Phase-2
Pompa CT-1 Cooling Phase-1
Pompa CT-2 Cooling Phase-1
Pompa CT-3 Phase-2
Panel MDP-B Phase-2
Perangkat Quantity Garansi
Nama Vendor/Suplayer No BAST
Kapasitas Volume Unit Mulai Masa Garansi
1 Unit PT. Schneider Electric 29-Mar-16
1 Unit PT. Schneider Electric 10-Aug-16
1 Unit PT. Schneider Electric 29-Mar-16
1 Unit PT. Schneider Electric Dimulai ketika BAST ditandatangani
1 Unit PT. Westindo 19-Apr-16
1 Unit PT. Westindo 9-Mei-2017
1 Unit PT. Pusaka Graha Teknik Dimulai ketika BAST ditandatangani
1 Unit PT. Schneider Electric 29-Mar-16
1 Unit PT. Schneider Electric N/A
1 Unit PT. Schneider Electric 29-Mar-16
1 Unit PT. Schneider Electric Dimulai ketika BAST ditandatangani
1 Unit PT. Schneider Electric N/A
2 Unit PT. Schneider Electric 29-Mar-16
2 Unit PT. Schneider Electric 29-Mar-16
12 Unit PT. Westindo 19-Apr-16
6 Unit PT. Westindo 9-Mei-2017
2 Unit PT. Westindo (under Schneider) 29-Mar-16
1 Unit PT. Westindo (under Schneider) 29-Mar-16
3 Unit PT. Citra Inti Semesta Dimulai ketika BAST ditandatangani
2 Unit PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
1 Unit PT. SMBE NA
1 Unit PT. SMBE 29-Des-2015
1 Unit PT. SMBE 29-Des-2015
1 Unit PT. SMBE Dimulai ketika BAST ditandatangani
1 Unit PT. SMBE 29-Des-2015
1 Unit PT. SMBE Dimulai ketika BAST ditandatangani
1 Unit PT. Pusaka Graha Teknik Dimulai ketika BAST ditandatangani
1 Unit PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
1 Unit PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
1 Unit PT. Bina Pertiwi By Telkomsel
3 Unit PT. Citra Inti Semesta Dimulai ketika BAST ditandatangani
1 Unit PT. Citra Inti Semesta Dimulai ketika BAST ditandatangani
1 Unit PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
5 Bh PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
1 Unit PT. Bina Pertiwi By Telkomsel
1 Unit PT. Bina Pertiwi By Telkomsel
1 Unit PT. Bina Pertiwi By Telkomsel
2 Unit PT. Bina Pertiwi By Telkomsel
1 Unit PT. Pusaka Graha Teknik Dimulai ketika BAST ditandatangani
1 Set PT. Visi Lokamas 29-Des-2015
1 Set PT. Visi Lokamas 29-Des-2015
1 Set PT. Visi Lokamas 29-Des-2015
1 Set PT. Visi Lokamas 29-Des-2015
1 Set PT. Visi Lokamas 29-Des-2015
1 Set PT. Visi Lokamas 18-Agst-2016
1 Set PT. Visi Lokamas 18-Agst-2016
1 Unit PT. SMBE 29-Des-2015
1 Unit PT. SMBE Dimulai ketika BAST ditandatangani
1 Unit PT. Schneider Electric 29-Mar-16
1 Unit PT. Schneider Electric Dimulai ketika BAST ditandatangani
3 Unit PT. Schneider Electric Dimulai ketika BAST ditandatangani
1 Unit PT. Pusaka Graha Teknik Dimulai ketika BAST ditandatangani
1 Unit PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
1 Unit PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
1 Unit PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
3 Unit PT. Citra Inti Semesta Dimulai ketika BAST ditandatangani
2 Unit PT. Panca Pastika Mandiri Dimulai ketika BAST ditandatangani
1 Unit PT. Schneider Electric 29-Mar-16
1 Unit PT. Schneider Electric 29-Mar-16
1 Unit PT. Schneider Electric Dimulai ketika BAST ditandatangani
1 Unit PT. SMBE Dimulai ketika BAST ditandatangani
Garansi
Catatan
Berakhir Masa Garansi
28-Mar-17
Satu tahun setelah BAST ditandatangani
28-Mar-17
Satu tahun setelah BAST ditandatangani
18-Apr-17
8-Mei-2018
Satu tahun setelah BAST ditandatangani
28-Mar-17
N/A
28-Mar-17
Satu tahun setelah BAST ditandatangani
N/A
28-Mar-17
28-Mar-17
18-Apr-17
8-Mei-2018
28-Mar-17
28-Mar-17
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
NA
28-Des-2016
28-Des-2016
Satu tahun setelah BAST ditandatangani
28-Des-2016
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
By Telkomsel
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
By Telkomsel
By Telkomsel
By Telkomsel
By Telkomsel
Satu tahun setelah BAST ditandatangani
28-Des-2016
28-Des-2016
28-Des-2016
28-Des-2016
28-Des-2016
17-Agst-2017
17-Agst-2017
28-Des-2016
Satu tahun setelah BAST ditandatangani
28-Mar-17
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani
28-Mar-17
28-Mar-17
Satu tahun setelah BAST ditandatangani
Satu tahun setelah BAST ditandatangani