COST CONTROL PEMBUATAN GUDANG LIMBAH SP.

BENGKULU
Finish
TOTAL RAB REALISASI SELISIH TOTAL RAB - REALISASI
No Item pekerjaan
Satuan Volume Harga satuan Nilai Satuan Volume Harga satuan Nilai Satuan Volume Harga satuan Nilai
1 Semen zak 18,0 56.000 1.008.000 zak 16,0 56.000 896.000 zak 2 56.000 112.000
2 Batu split m3 2,0 380.000 760.000 m3 2,0 380.000 760.000 m3 - 380.000 -
3 Pasir cor m3 6,0 200.000 1.200.000 m3 - m3 6 200.000 1.200.000
4 Tanah merah rit 3,0 200.000 600.000 rit - rit 3 200.000 600.000
5 Pipa paralon 2 inch batang 1,0 100.000 100.000 batang 1,0 110.000 110.000 batang - 100.000 (10.000)
6 Besi 8 sloof batang 50.000 - batang - batang - 50.000 -
7 Besi 6 cincin batang 24.000 - batang - batang - 24.000 -
Batu bata p = 15 cm x t =
8 8 cm buah 2.000,0 800 1.600.000 buah 2.000,0 670 1.340.000 buah - 800 260.000
9 Pagar kawat m2 12,0 75.000 900.000 m2 10,0 50.000 500.000 m2 2 75.000 400.000
10 Pintu 0,6 m x 2 m buah 2,0 600.000 1.200.000 buah 1,0 1.300.000 1.300.000 buah 1 600.000 (100.000)
11 Kusen pintu 1,2 m x 2 m buah 1,0 300.000 300.000 buah - buah 1 300.000 300.000
Pipa besi 3 inch / pipa giv
12 polos 3 tebal (2,0) batang 2,0 635.000 1.270.000 batang 2,0 495.000 990.000 batang - 635.000 280.000
13 Taso 75/65 batang 15,0 125.000 1.875.000 batang 15,0 120.000 1.800.000 batang - 125.000 75.000
14 Spandek 3 m x 0,8 m lembar 12,0 150.000 1.800.000 lembar 12,0 150.000 1.800.000 lembar - 150.000 -
15 Tools dan lain2 ls 1,0 750.000 750.000 ls 1.737.000 ls 1 750.000 (987.000)
Lisplang GRC - keping 6,0 50.000 300.000 keping
perabung MR keping 4,0 38.000 152.000 keping
baut Canal kg 1,0 75.000 75.000 kg
Bola-bola MRN keping 8,0 30.000 240.000 keping
papan cor keping 4,0 45.000 180.000 keping
paku 21/2 " kg 1,0 20.000 20.000 kg
baut roffing kotak 1,0 200.000 200.000 kotak
handel barcelona SGBT
#17 pcs 1,0 150.000 150.000 pcs

body pelor belocca #31/5 pcs 1,0 120.000 120.000 pcs


engsel wanly 4 in 31/5 psg 2,0 25.000 50.000 psg

grendel vaniro 8 in #02/0 pcs 2,0 20.000 40.000 pcs


GRC keping 3,0 70.000 210.000 keping
16 3 Tukang hari 10,0 200.000 2.000.000 hari 12,0 150.000 1.800.000 hari (2) 200.000 200.000
- - - -
TOTAL 15.363.000 13.033.000 2.330.000
Finish Data tgl. 17 Juni 2021
Catt : Star Pekerjaan Mulai 02 s/d 10 Juli 2021
Estimasi pekerjaan +- 12 hari
untuk bon tukang belum bisa dilampirkan dikarenakan sedang Isoman