RENCANA ANGGARAN BIAYA

PEKERJAAN : RUMAH TEMBOK


NAMA :
POSISI :

HARGA JUMLAH
NO URAIAN PEKERJAAN VOLUME SATUAN
SATUAN (Rp) HARGA (Rp)
1 2 3 4 5 6

I. Pondasi
1 Batu Kali 5.40 m3 210,000.00 1,134,000.00
2 Semen 17.60 sak 75,000.00 1,320,300.00
3 Pasir 2.81 m3 160,000.00 449,280.00

II Beton (sloof, kolom, ring balok)


1 Semen 11.24 sak 75,000.00 843,231.60
2 Pasir Beton 0.94 m3 190,000.00 177,906.35
3 Kerikil 0.98 m3 350,000.00 344,621.34
4 Papan Bekisting 44.37 lbr 50,000.00 2,218,500.00
5 Besi Beton - dia 12 mm 10.67 btg 92,000.00 981,333.33
6 Besi Beton - dia 10 mm 16.00 btg 62,000.00 992,000.00
7 Besi Beton - dia 8 mm 23.28 btg 45,000.00 1,047,575.00
8 Kawat Bendrat 10.00 kg 18,000.00 180,000.00
9 Paku 12.00 kg 23,000.00 276,000.00

III Dinding
1 Batako 1,577.09 bh 1,200.00 1,892,505.60
2 Semen 0.43 sak 75,000.00 32,287.68
3 Pasir Pasang 25.86 m3 160,000.00 4,137,369.60
0.00
IV Atap 0.00
1 Kayu 5/7 – 4 m 15.00 btg 45,000.00 675,000.00
2 Kayu 5/10 – 4 m 6.63 btg 65,000.00 430,950.00
3 Kayu 8/12 – 4 m 4.50 btg 85,000.00 382,500.00
4 Papan 2/20 – 4 m 9.66 lbr 50,000.00 483,000.00
5 Seng Gelombang 0,2 mm x 180 x 80 cm 43.75 lbr 60,000.00 2,625,000.00
6 Bubungan Seng 7.00 lbr 11,000.00 77,000.00
7 Paku 5.00 kg 23,000.00 115,000.00
0.00
V Lantai 0.00
1 Semen 7.20 sak 75,000.00 540,000.00
2 Pasir Pasang 0.94 m3 160,000.00 150,336.00
3 Kerikil 1.55 m3 350,000.00 543,060.00
0.00
VI Pintu dan Jendela 0.00
1 Kusen Pintu 2.00 unit 450,000.00 900,000.00
2 Daun Pintu 2.00 unit 400,000.00 800,000.00
3 Kusen Jendela 7.00 unit 350,000.00 2,450,000.00
4 Daun Jendela 7.00 unit 250,000.00 1,750,000.00

VII MCK
1 Kloset 1.00 bh 125,000.00 125,000.00

28,073,756.50
28,725,036.50
Daftar Harga Satuan Bahan Bangunan

No Nama Barang Satuan Harga (Rp.)


1 Semen @ 50 kg Sak 75,000
2 Pasir Pasang m3 160,000
3 Pasir Beton m3 190,000
4 Kerikil/Split m3 350,000
5 Batu Kali m3 210,000
6 Batako buah 1200
7 Besi Beton - Æ 8 mm batang 45,000
8 Besi Beton - Æ 10 mm batang 62,000
9 Besi Beton - Æ 12 mm batang 92,000
10 Kawat Bendrat kg 18,000
11 Kayu 5/7 – 4 m batang 45,000
12 Kayu 5/10 – 4 m batang 65,000
13 Kayu 8/12 – 4 m batang 85,000
14 Papan 2/20 – 4 m lembar 50,000
15 Seng Gelombang 0,2 mm x 180 x 80 cm lembar 60,000
16 Papan Bekisting lembar 15,000
17 Bubungan Seng lembar 11,000
18 Kusen Pintu unit 450,000
19 Daun Pintu unit 400,000
20 Kusen Jendela unit 350,000
21 Daun Jendela unit 250,000
22 Kloset unit 125,000
23 Paku kg 23,000
( harga satuan merupakan harga Asumsi bukan harga pasar)
Daftar Analisa Pekerjaan

Pasangan 1 m3 pondasi batu kali campuran 1PC : 4 PS

No. URAIAN PEKERJAAN SATUAN KUANTITAS

1 2 3 5
A BAHAN
1 Batu kali/batu belah M3 1.200
2 Semen sak 3.260
3 Pasir Pasang M3 0.520
Jumlah
B Jumlah A
C Overhead + Profit (13,5%)
D Harga Satuan Pekerjaan

Membuat 1 m3 beton mutu f’c = 14,5 Mpa

No. URAIAN PEKERJAAN SATUAN KUANTITAS

1 2 3 5
A BAHAN
1 Semen Sak 6.520
2 Pasir Beton M3 0.543
3 Krikil/ Split 3 0.571
M
Jumlah
B Jumlah A
C Overhead + Profit (13,5%)
D Harga Satuan Pekerjaan

Pasangan 1 m2 dinding batako (15x30x7) cm campuran 1PC : 3 PS

No. URAIAN PEKERJAAN SATUAN KUANTITAS

1 2 3 5
A BAHAN
1 Batako buah 22.200
2 Semen Kg 0.303
3 Pasir Pasang 3 0.364
M
Jumlah
B Jumlah A
C Overhead + Profit (13,5%)
D Harga Satuan Pekerjaan
Plesteran 1 m2 campuran 1PC : 3 PS tebal 15 mm

No. URAIAN PEKERJAAN SATUAN KUANTITAS

1 2 3 5
A BAHAN
1 Semen Kg 7.776
2 Pasir Pasang 3 0.023
M

Jumlah
B Jumlah A
C Overhead + Profit (13,5%)
D Harga Satuan Pekerjaan
Membuat 1 m3 rabat beton

No. URAIAN PEKERJAAN SATUAN KUANTITAS

1 2 3 5
A BAHAN
1 Semen Sak 4.000
2 Pasir 3 0.522
M
3 Krikil/ Split 3 0.862
M
Jumlah
B Jumlah A
C Overhead + Profit (13,5%)
D Harga Satuan Pekerjaan