RENCANA ANGGARAN BIAYA ( RAB )

PEKERJAAN : PEMBANGUNAN GAPURA MUSHOLLAH AN - NAIM

HARGA SAT. JUMLAH HARGA


NO. URAIAN PEKERJAAN VOLUME SAT.
(Rp.) (Rp.)
1 2 4 5 6 7

A. BIAYA BAHAN/MATERIAL

1 Semen 50 kg 45.00 zak 80,000.00 3,600,000.00


2 Pasir palu 1.00 ret 1,600,000.00 1,600,000.00
3 Pasir sambera 1.00 ret 1,100,000.00 1,100,000.00
4 Kerikil 1.00 ret 1,600,000.00 1,600,000.00
5 Batu bata 520.00 bh 1,000.00 520,000.00
6 Besi Ø13 26.00 btg 140,000.00 3,640,000.00
7 Besi Ø8 20.00 btg 40,000.00 800,000.00
8 Pengikat besi 4.00 kg 20,000.00 80,000.00
9 Multipleks 9 mm 7.00 lbr 110,000.00 770,000.00
10 Balok kayu 0.50 m3 3,000,000.00 1,500,000.00
11 Batu alam 8.50 m2 200,000.00 1,700,000.00
12 Granit 60 x 60 3.00 dos 250,000.00 750,000.00

B. BIAYA TENAGA KERJA 1.00 ls 20,000,000.00 20,000,000.00

TOTALA BIAYA....................................... 37,660,000.00