PEMERINTAH KABUPATEN SITUBONDO

KECAMATAN CIPTA DESA


DESA ..............

RINCIAN PENGGUNAAN TENAGA KERJA, BAHAN DAN ALAT

KEGIATAN : PENINGKATAN JALAN DESA


PEKERJAAN : MAKADAM
LOKASI : Dusun .......... RT.00 RW.00
VOLUME : 2.50 x 650 m2
HARGA JUMLAH
NO VOLUME SATUAN UNIT SATUAN TOTAL
(Rp) (Rp)
1. UPAH TENAGA KERJA DAN HONOR TIM PBJ
1.1. Upah Tenaga Kerja
1 Mandor 7.00 Hari - -
2 Pekerja 247.50 Hari 95,000 23,512,500
3 Tukang masak aspal 0.00 Hari 120,000 -
4 Upah gilas 0.00 Hari - -
23,512,500.00
1.2. Honor Tim Pengadaan Barang dan Jasa
1 Ketua 1.00 Paket 300,000 300,000
2 Sekretaris 1.00 Paket 250,000 250,000
3 Anggota 1.00 Paket 200,000 200,000
4 Anggota 1.00 Paket 200,000 200,000
5 Anggota 1.00 Paket 200,000 200,000
1,150,000.00
Sub Total I 24,662,500.00
2. BAHAN
1 Bahan Gilas 0.00 M3 - -
2 Batu Pecah 15/20 47.00 M3 176,000 8,272,000
3 Batu Pecah 10/15 226.00 M3 176,000 39,776,000
4 Batu Pecah 4/7 76.00 M3 206,000 15,656,000
5 Sirtu 76.00 M 3
170,000 12,920,000
6 Batu 3-5 0.00 M 3
227,000 -
7 Batu 2-3 0.00 M 3
430,000 -
8 Batu 1-1,5 Pecah Mesin 0.00 M 3
430,000 -
9 Aspalt 0.00 Drum 1,600,000 -
10 Pasir Hitam 0.00 M 3
463,000 -
11 Kayu Bakar 0.00 M 3
275,500 -
12 Riool Ø 20 Cm 0.00 M' 95,000 -
Sub Total II 76,624,000.00
3. ALAT
1 Mob. Demob. 1 Ls 1,500,000 1,500,000
2 Sewa Wales 1.00 Hari 800,000 800,000
3 Cangkul Bh 75,000 -
4 Sabit Bh 50,000 -
5 Sapu Lidi 0 Bh 10,000 -
6 Prasasti 1 Bh 350,000 350,000
Sub Total III 2,650,000.00
TOTAL BIAYA I+II+III 103,936,500.00

Mengetahui, Diverifikasi Oleh Dibuat Oleh,


Kepala Desa ............ Sekretaris Desa Pelaksana Kegiatan Anggaran

.......................... .......................... ..........................