RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : JALAN TITIAN


LOKASI PEKERJAAN : RW 03 (Komp. Wilis Djafar)
TAHUN ANGGARAN : 2023
RAB NO : 1
VOLUME BIAYA (Rp)
Harga Satuan
NO URAIAN Sat
Anggaran Swadaya Total (Rp) Swadaya (Rp) Total (Rp) Jumlah Total (Rp)

A. BAHAN LOKAL/NON LOKAL


1 Kayu Kelas III (bowplank+bekisting)
Pasir Beton 0.10 - 0.20 m3 2,500,000.00 - 500,000.00 500,000.00
2 (Maks 30mm) 0.31 - 0.50 m3 150,000.00 - 75,000.00 75,000.00
3 0.52 - 1.00 m3 175,000.00 - 175,000.00 175,000.00
4 Kayu Kelas II (6x10) 0.48 0.50 m3 3,250,000.00 - 1,625,000.00 1,625,000.00
5 Kayu Kelas II (5x7) 0.35 0.50 m3 3,250,000.00 - 1,625,000.00 1,625,000.00
6 Kayu Kelas II (Papan Lantai) 0.41 0.50 m3 3,250,000.00 - 1,625,000.00 1,625,000.00
5 Besi 12 12.50 - 13.00 ujg 110,000.00 - 1,430,000.00 1,430,000.00
6 Besi 8 12.22 - 13.00 ujg 35,000.00 - 455,000.00 455,000.00
7 Kawat Beton/Bendrat
Semen Portland 1.73 - 2.00 kg 25,000.00 - 50,000.00 50,000.00
6 3.80 - 4.00 zak 87,500.00 - 350,000.00 350,000.00
7 Paku Campur 7.64 - 8.00 kg 20,000.00 - 160,000.00 160,000.00
Sub Total (1) - 8,070,000.00 8,070,000.00
B. Peralatan Penunjang -
1 Papan Proyek 1.00 - 1.00 bh 250,000.00 - 250,000.00 250,000.00
2 Prasasti 1.00 - 1.00 bh 350,000.00 - 350,000.00 350,000.00
3 Peralatan Penunjang 1.00 - 1.00 ls 310,000.00 - 310,000.00 310,000.00
Sub Total (2) - 910,000.00 910,000.00
C. UPAH -
1 Pekerja 16.82 - 17.00 Hok 100,000.00 - 1,700,000.00 1,700,000.00
2 Tukang 18.34 - 19.00 Hok 150,000.00 - 2,850,000.00 2,850,000.00
3 Kepala Tukang 2.73 - 3.00 Hok 175,000.00 - 525,000.00 525,000.00
Sub Total (3) - 5,075,000.00 5,075,000.00
D. HONOR TPK -
1 Pokmas 10% - - 1.00 Ls 1,390,000.00 - 1,390,000.00 1,390,000.00
2 Pastek 5% - - 1.00 Org 695,000.00 - 695,000.00 695,000.00
Sub Total (4) - 2,085,000.00 2,085,000.00

Jumlah Total (1+2+3+4) - 16,140,000.00 16,140,000.00

Gorontalo, 15 Juni 2022


Disetujui Oleh Diperiksa Oleh Dibuat Oleh,
KEPALA KELURAHAN PTPKD PERENCANA

,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, Syafrudin Husain, ST


KELURAHAN : Dembe 1 NAMA KEGIATAN : JALAN TITIAN
KECAMATAN : Kota Barat TAKE OF SHEET LOKASI : RW 03 (Komp. Wilis Djafar)
KOTA : Gorontalo VOLUME : 23.00 M
HITUNGAN VOLUME

KETERANGAN : Volume beton


V = P/L2xL1x2
Panjang jalan = 23.00 M (P) = 23.00 / 2.00 x 1.50 x 2.00 34.50 M1
Lebar badan jalan = 1.20 M (L)
Besar Kolom = 0.30 M (T) Volume Kayu Pemisah
Tinggi Kolom = 1.50 M ( L1 ) Vk = L3xL
Jarak Kolom = 2.00 M ( L2 ) = 12.50 x 1.20 15.00 M
Jumlah Kolom = 12.50 M ( L3 )
Volume Balok Induk

n = Px2+Vk
Kebutuhan bahan dan tenaga untuk Pekerjaan Beton = 23.00 x 2.00 + 15.00
Kayu Kls III 34.50 x 0.003 = 0.10 M3 = 61.00 61.00 M
Paku 34.50 x 0.020 = 0.69 kg
Besi Beton 34.50 x 3.600 = 124.20 kg Volume Lantai Papan
Kawat Beton 34.50 x 0.050 = 1.73 kg v PxL
Kerikil/split 34.50 x 0.015 = 0.52 M3 23.00 1.20
Pasir pasangan 34.50 x 0.009 = 0.31 M3 27.60 27.60 M
Semen 34.50 x 5.500 = 3.80 Zak
Air 34.50 x - = - Ltr Volume Relling Kayu
Pekerja 34.50 x 0.297 = 10.25 HOK v 3xPx2
Tukang 34.50 x 0.100 = 3.45 HOK 23.00 2.00
Kepala tukang 34.50 x 0.010 = 0.35 HOK 138.00 138.00 M
Mandor 34.50 x 0.015 = 0.52 HOK

Volume Tiang Relling


Kebutuhan bahan dan tenaga untuk Pekerjaan Balok Kayu Luas = 1xPx2
Kayu Kls II 0.44 x 1.100 = 0.48 M3 = 1.00 23.00 2.00
Paku 0.44 x 3.000 = 1.32 kg = 46.00 46.00 M
Pekerja 0.44 x 2.400 = 1.05 HOK
Tukang 0.44 x 7.200 = 3.16 HOK
Kepala tukang 0.44 x 0.720 = 0.32 HOK 0.85
Mandor 0.44 x 0.120 = 0.05 HOK
34.50
Kebutuhan bahan dan tenaga untuk Pekerjaan Relling Kayu 0.80 34.50 172.50
Kayu Kls II 23.00 x 0.015 = 0.35 M3 0.03 15.25 146.63
Paku 23.00 x 0.200 = 4.60 kg 34.72 12.22
Pekerja 23.00 x 0.150 = 3.45 HOK
Tukang 23.00 x 0.300 = 6.90 HOK
Kepala tukang 23.00 x 0.030 = 0.69 HOK 34.50 0.01
Mandor 23.00 x 0.010 = 0.23 HOK 71.43

Kebutuhan bahan dan tenaga untuk Pekerjaan Lantai Kayu


Kayu Kls II 6.90 x 0.060 = 0.41 M3
KELURAHAN : Dembe 1 NAMA KEGIATAN : JALAN TITIAN
KECAMATAN : Kota Barat TAKE OF SHEET LOKASI : RW 03 (Komp. Wilis Djafar)
KOTA : Gorontalo VOLUME : 23.00 M
HITUNGAN VOLUME
Paku 6.90 x 0.150 = 1.04 kg
Pekerja 6.90 x 0.300 = 2.07 HOK
Tukang 6.90 x 0.700 = 4.83 HOK
Kepala tukang 6.90 x 0.200 = 1.38 HOK
Mandor 6.90 x 0.335 = 2.31 HOK

Paku 7.64
Besi Beton 124.20
Kawat Beton 1.73
Kerikil/split 0.52
Pasir pasangan 0.31
Semen 3.80
Papan Mall 0.10
Kayu 6x12 0.48
Kayu 5x7 0.35
Papan Lantai 0.41

Pekerja 16.82
Tukang 18.34 6.11
Kepala tukang 2.73

Dibuat oleh

Syafrudin Husain, ST