n = Px2+Vk
Kebutuhan bahan dan tenaga untuk Pekerjaan Beton = 70.00 x 2.00 + 43.20
Kayu Kls III 105.00 x 0.003 = 0.32 M3 = 183.20 183.20 M
Paku 105.00 x 0.020 = 2.10 kg
Besi Beton 105.00 x 3.600 = 378.00 kg Volume Lantai Papan
Kawat Beton 105.00 x 0.050 = 5.25 kg v PxL
Kerikil/split 105.00 x 0.015 = 1.58 M3 70.00 1.20
Pasir pasangan 105.00 x 0.009 = 0.95 M3 84.00 84.00 M
Semen 105.00 x 5.500 = 11.55 Zak
Air 105.00 x - = - Ltr Volume Relling Kayu
Pekerja 105.00 x 0.297 = 31.19 HOK v 3xPx2
Tukang 105.00 x 0.100 = 10.50 HOK 70.00 2.00
Kepala tukang 105.00 x 0.010 = 1.05 HOK 420.00 420.00 M
Mandor 105.00 x 0.015 = 1.58 HOK
Paku 23.21
Besi Beton 378.00
Kawat Beton 5.25
Kerikil/split 1.58
Pasir pasangan 0.95
Semen 11.55
Papan Mall 0.32
Kayu 6x12 1.45
Kayu 5x7 1.05
Papan Lantai 1.26
Pekerja 51.15
Tukang 55.70 18.57
Kepala tukang 8.30
Dibuat oleh
Syafrudin Husain, ST
PERENCANA