Anda di halaman 1dari 3

RENCANA ANGGARAN BIAYA

NAMA PEKERJAAN : JALAN TITIAN


LOKASI PEKERJAAN : RW 03 (Komp. Masri)
TAHUN ANGGARAN : 2023
RAB NO : 1
VOLUME BIAYA (Rp)
Harga Satuan
NO URAIAN Sat
Anggaran Swadaya Total (Rp) Swadaya (Rp) Total (Rp) Jumlah Total (Rp)

A. BAHAN LOKAL/NON LOKAL


1 Kayu Kelas III (bowplank+bekisting)
Pasir Beton 0.32 - 0.30 m3 2,500,000.00 - 750,000.00 750,000.00
2 (Maks 30mm) 0.95 - 0.90 m3 150,000.00 - 135,000.00 135,000.00
3 1.58 - 1.60 m3 175,000.00 - 280,000.00 280,000.00
4 Kayu Kelas II (6x10) 1.45 1.50 m3 3,250,000.00 - 4,875,000.00 4,875,000.00
5 Kayu Kelas II (5x7) 1.05 1.10 m3 3,250,000.00 - 3,575,000.00 3,575,000.00
6 Kayu Kelas II (Papan Lantai) 1.26 1.30 m3 3,250,000.00 - 4,225,000.00 4,225,000.00
5 Besi 12 36.00 - 36.00 ujg 110,000.00 - 3,960,000.00 3,960,000.00
6 Besi 8 37.19 - 37.20 ujg 35,000.00 - 1,302,000.00 1,302,000.00
7 Kawat Beton/Bendrat
Semen Portland 5.25 - 5.30 kg 25,000.00 - 132,500.00 132,500.00
6 11.55 - 11.60 zak 87,500.00 - 1,015,000.00 1,015,000.00
7 Paku Campur 23.21 - 23.20 kg 20,000.00 - 464,000.00 464,000.00
Sub Total (1) - 20,713,500.00 20,713,500.00
B. Peralatan Penunjang -
1 Papan Proyek 1.00 - 1.00 bh 250,000.00 - 250,000.00 250,000.00
2 Prasasti 1.00 - 1.00 bh 350,000.00 - 350,000.00 350,000.00
3 Peralatan Penunjang 1.00 - 1.00 ls 342,000.00 - 342,000.00 342,000.00
Sub Total (2) - 942,000.00 942,000.00
C. UPAH -
1 Pekerja 51.15 - 51.20 Hok 100,000.00 - 5,120,000.00 5,120,000.00
2 Tukang 55.70 - 55.70 Hok 150,000.00 - 8,355,000.00 8,355,000.00
3 Kepala Tukang 8.30 - 8.30 Hok 175,000.00 - 1,452,500.00 1,452,500.00
Sub Total (3) - 14,927,500.00 14,927,500.00
D. HONOR TPK -
1 Pokmas 10% - - 1.00 Ls 3,600,000.00 - 3,600,000.00 3,600,000.00
2 Pastek 5% - - 1.00 Org 1,800,000.00 - 1,800,000.00 1,800,000.00
Sub Total (4) - 5,400,000.00 5,400,000.00

Jumlah Total (1+2+3+4) - 41,983,000.00 41,983,000.00

Gorontalo, 15 Juni 2022


Disetujui Oleh Diperiksa Oleh Dibuat Oleh,
KEPALA KELURAHAN PTPKD PERENCANA

,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, Syafrudin Husain, ST


KELURAHAN : Dembe 1 NAMA KEGIATAN : JALAN TITIAN
KECAMATAN : Kota Barat TAKE OF SHEET LOKASI : RW 03 (Komp. Masri)
KOTA : Gorontalo VOLUME : 70.00 M
HITUNGAN VOLUME

KETERANGAN : Volume beton


V = P/L2xL1x2
Panjang jalan = 70.00 M (P) = 70.00 / 2.00 x 1.50 x 2.00 105.00 M1
Lebar badan jalan = 1.20 M (L)
Besar Kolom = 0.30 M (T) Volume Kayu Pemisah
Tinggi Kolom = 1.50 M ( L1 ) Vk = L3xL
Jarak Kolom = 2.00 M ( L2 ) = 36.00 x 1.20 43.20 M
Jumlah Kolom = 36.00 M ( L3 )
Volume Balok Induk

n = Px2+Vk
Kebutuhan bahan dan tenaga untuk Pekerjaan Beton = 70.00 x 2.00 + 43.20
Kayu Kls III 105.00 x 0.003 = 0.32 M3 = 183.20 183.20 M
Paku 105.00 x 0.020 = 2.10 kg
Besi Beton 105.00 x 3.600 = 378.00 kg Volume Lantai Papan
Kawat Beton 105.00 x 0.050 = 5.25 kg v PxL
Kerikil/split 105.00 x 0.015 = 1.58 M3 70.00 1.20
Pasir pasangan 105.00 x 0.009 = 0.95 M3 84.00 84.00 M
Semen 105.00 x 5.500 = 11.55 Zak
Air 105.00 x - = - Ltr Volume Relling Kayu
Pekerja 105.00 x 0.297 = 31.19 HOK v 3xPx2
Tukang 105.00 x 0.100 = 10.50 HOK 70.00 2.00
Kepala tukang 105.00 x 0.010 = 1.05 HOK 420.00 420.00 M
Mandor 105.00 x 0.015 = 1.58 HOK

Volume Tiang Relling


Kebutuhan bahan dan tenaga untuk Pekerjaan Balok Kayu Luas = 1xPx2
Kayu Kls II 1.32 x 1.100 = 1.45 M3 = 1.00 70.00 2.00
Paku 1.32 x 3.000 = 3.96 kg = 140.00 140.00 M
Pekerja 1.32 x 2.400 = 3.17 HOK
Tukang 1.32 x 7.200 = 9.50 HOK
Kepala tukang 1.32 x 0.720 = 0.95 HOK 0.85
Mandor 1.32 x 0.120 = 0.16 HOK
105.00
Kebutuhan bahan dan tenaga untuk Pekerjaan Relling Kayu 0.80 105.00 525.00
Kayu Kls II 70.00 x 0.015 = 1.05 M3 0.03 45.80 446.25
Paku 70.00 x 0.200 = 14.00 kg 34.72 37.19
Pekerja 70.00 x 0.150 = 10.50 HOK
Tukang 70.00 x 0.300 = 21.00 HOK
Kepala tukang 70.00 x 0.030 = 2.10 HOK 105.00 0.01
Mandor 70.00 x 0.010 = 0.70 HOK 71.43

Kebutuhan bahan dan tenaga untuk Pekerjaan Lantai Kayu


Kayu Kls II 21.00 x 0.060 = 1.26 M3
KELURAHAN : Dembe 1 NAMA KEGIATAN : JALAN TITIAN
KECAMATAN : Kota Barat TAKE OF SHEET LOKASI : RW 03 (Komp. Masri)
KOTA : Gorontalo VOLUME : 70.00 M
HITUNGAN VOLUME
Paku 21.00 x 0.150 = 3.15 kg
Pekerja 21.00 x 0.300 = 6.30 HOK
Tukang 21.00 x 0.700 = 14.70 HOK
Kepala tukang 21.00 x 0.200 = 4.20 HOK
Mandor 21.00 x 0.335 = 7.04 HOK

Paku 23.21
Besi Beton 378.00
Kawat Beton 5.25
Kerikil/split 1.58
Pasir pasangan 0.95
Semen 11.55
Papan Mall 0.32
Kayu 6x12 1.45
Kayu 5x7 1.05
Papan Lantai 1.26

Pekerja 51.15
Tukang 55.70 18.57
Kepala tukang 8.30

Dibuat oleh

Syafrudin Husain, ST
PERENCANA