006 ABK-I.006 Pembersihan lapangan dan perataan 1,00 m2 15.750,00 - - 15.

750,00
0,100 OH Pekerja 95.000,00 9.500,00 9.500,00
UPA H

0,050 OH Mandor 125.000,00 6.250,00 6.250,00


ALAT BAHAN

JUMLAH : (A) 15.750,00


KEUNTUNGAN 10% : (B) = 10% x (A) 1.575,00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 17.325,00
010 ABK-I.010 Pembuatan gudang semen dan peralatan 1,00 m2 376.250,00 532.938,16 - 909.188,16
1,000 OH Pekerja 95.000,00 95.000,00 95.000,00
2,000 OH Tukang Kayu 125.000,00 250.000,00 250.000,00
UPA H

0,200 OH Kepala Tukang 125.000,00 25.000,00 25.000,00


0,050 OH Mandor 125.000,00 6.250,00 6.250,00

1,700 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 116.178,00 116.178,00


0,210 m3 Kayu Arbise Persegian 1.110.780,00 233.263,80 233.263,80
0,300 kg Paku Biasa 2-5" 15.432,00 4.629,60 4.629,60
10,500 kg Semen PC (uk. 50 kg) 1.300,00 13.650,00 13.650,00
BAHAN

0,030 m3 Pasir Beton 320.892,00 9.626,76 9.626,76


0,050 m3 Koral Beton 246.840,00 12.342,00 12.342,00
1,500 lmbr Seng Gelombang ( BJLS. 30 ) 87.664,00 131.496,00 131.496,00
0,250 lmbr Seng Plat ( BJLS.30 ) 47.008,00 11.752,00 11.752,00
ALAT

JUMLAH : (A) 909.188,16


KEUNTUNGAN 10% : (B) = 10% x (A) 90.918,82
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1.000.106,98

HARGA JUMLAH HARGA


NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp)
SATUAN (Rp) (Rp)
012 ABK-I.012 Pembuatan kantor sementara lantai plesteran 1,00 m2 608.750,00 555.148,71 - 1.163.898,71
2,000 OH Pekerja 95.000,00 190.000,00 190.000,00
2,000 OH Tukang Kayu 125.000,00 250.000,00 250.000,00
1,000 OH Tukang Batu 125.000,00 125.000,00 125.000,00
UPA H

0,300 OH Kepala Tukang 125.000,00 37.500,00 37.500,00


0,050 OH Mandor 125.000,00 6.250,00 6.250,00

1,250 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 85.425,00 85.425,00


0,180 m3 Kayu Arbise Persegian 1.110.780,00 199.940,40 199.940,40
0,080 kg Paku Biasa 2-5" 15.432,00 1.234,56 1.234,56
1,100 kg Besi Strip 45.303,00 49.833,30 49.833,30
35,000 kg Semen PC (uk. 50 kg) 1.300,00 45.500,00 45.500,00
0,150 m3 Pasir Pasang 259.182,00 38.877,30 38.877,30
0,100 m3 Pasir Beton 320.892,00 32.089,20 32.089,20
BAHAN

0,150 m3 Koral Beton 246.840,00 37.026,00 37.026,00


30,000 bh Bata Merah 1.020,00 30.600,00 30.600,00
0,250 lmbr Seng Plat ( BJLS.30 ) 47.008,00 11.752,00 11.752,00
0,200 set Jendela Nako 18.513,00 3.702,60 3.702,60
0,080 m2 Kaca Polos ( Tebal 5 mm ) 98.940,00 7.915,20 7.915,20
0,150 bh Kunci Tanam Biasa 43.197,00 6.479,55 6.479,55
0,060 lmbr Plywood ( uk. 4 mm ) 79.560,00 4.773,60 4.773,60
ALAT

JUMLAH : (A) 1.163.898,71


KEUNTUNGAN 10% : (B) = 10% x (A) 116.389,87
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1.280.288,58

009 ABK-I.009 Pembuatan bedeng pekerja 1,00 m2 376.250,00 580.930,44 - 957.180,44


1,000 OH Pekerja 95.000,00 95.000,00 95.000,00
2,000 OH Tukang Kayu 125.000,00 250.000,00 250.000,00
UPA H

0,200 OH Kepala Tukang 125.000,00 25.000,00 25.000,00


0,050 OH Mandor 125.000,00 6.250,00 6.250,00

1,250 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 85.425,00 85.425,00


0,186 m3 Kayu Arbise Persegian 1.110.780,00 206.605,08 206.605,08
0,300 kg Paku Biasa 2-5" 15.432,00 4.629,60 4.629,60
18,000 kg Semen PC (uk. 50 kg) 1.300,00 23.400,00 23.400,00
BAHAN

0,030 m3 Pasir Beton 320.892,00 9.626,76 9.626,76


0,050 m3 Koral Beton 246.840,00 12.342,00 12.342,00
1,500 lmbr Seng Gelombang ( BJLS. 30 ) 87.664,00 131.496,00 131.496,00
1,350 lmbr Plywood ( uk. 4 mm ) 79.560,00 107.406,00 107.406,00
ALAT

JUMLAH : (A) 957.180,44


KEUNTUNGAN 10% : (B) = 10% x (A) 95.718,04
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1.052.898,48
HARGA JUMLAH HARGA
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp)
SATUAN (Rp) (Rp)
021 ABK-I.021 Pengukuran dan pemasangan bouwplank 1,00 m 23.875,00 29.188,92 - 53.063,92
0,100 OH Pekerja 95.000,00 9.500,00 9.500,00
0,100 OH Tukang Kayu 125.000,00 12.500,00 12.500,00
UPA H

0,010 OH Kepala Tukang 125.000,00 1.250,00 1.250,00


0,005 OH Mandor 125.000,00 625,00 625,00

0,012 m3 Kayu Arbise Persegian 1.110.780,00 13.329,36 13.329,36


BAHAN

0,020 kg Paku Biasa 2-5" 15.432,00 308,64 308,64


0,007 m3 Kayu Arbise Papan ( Kruing ) 2.221.560,00 15.550,92 15.550,92
ALAT

JUMLAH : (A) 53.063,92


KEUNTUNGAN 10% : (B) = 10% x (A) 5.306,39
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 58.370,31

023 ABK-I.023 Pembuatan direksiket dan gudang 1,00 m2 128.750,00 521.186,16 - 649.936,16
1,000 OH Pekerja 95.000,00 95.000,00 95.000,00
0,200 OH Tukang Kayu 125.000,00 25.000,00 25.000,00
UPA H

0,020 OH Kepala Tukang 125.000,00 2.500,00 2.500,00


0,050 OH Mandor 125.000,00 6.250,00 6.250,00

1,700 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 116.178,00 116.178,00


0,210 m3 Kayu Arbise Persegian 1.110.780,00 233.263,80 233.263,80
0,300 kg Paku Biasa 2-5" 15.432,00 4.629,60 4.629,60
BAHAN

10,500 kg Semen PC (uk. 50 kg) 1.300,00 13.650,00 13.650,00


0,030 m3 Pasir Beton 320.892,00 9.626,76 9.626,76
0,050 m3 Koral Beton 246.840,00 12.342,00 12.342,00
1,500 lmbr Seng Gelombang ( BJLS. 30 ) 87.664,00 131.496,00 131.496,00
ALAT

JUMLAH : (A) 649.936,16


KEUNTUNGAN 10% : (B) = 10% x (A) 64.993,62
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 714.929,78

Pembuatan pagar sementara dari seng gelombang tinggi


017 ABK-I.017 1,00 m2 74.000,00 453.699,22 - 527.699,22
2 meter
0,200 OH Pekerja 95.000,00 19.000,00 19.000,00
0,400 OH Tukang Kayu 125.000,00 50.000,00 50.000,00
UPA H

0,020 OH Kepala Tukang 125.000,00 2.500,00 2.500,00


0,020 OH Mandor 125.000,00 2.500,00 2.500,00

1,250 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 85.425,00 85.425,00


2,500 kg Semen PC (uk. 50 kg) 1.300,00 3.250,00 3.250,00
1,200 lmbr Seng Gelombang ( BJLS. 30 ) 87.664,00 105.196,80 105.196,80
0,005 m3 Pasir Beton 320.892,00 1.604,46 1.604,46
BAHAN

0,009 m3 Koral Beton 246.840,00 2.221,56 2.221,56


0,072 m3 Kayu Balok 5/7 3.332.340,00 239.928,48 239.928,48
0,060 kg Paku Biasa 2-5" 15.432,00 925,92 925,92
0,450 kg Meni Besi Strip 33.660,00 15.147,00 15.147,00
ALAT

JUMLAH : (A) 527.699,22


KEUNTUNGAN 10% : (B) = 10% x (A) 52.769,92
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 580.469,14
007 ABK-II.007 Penggalian tanah biasa (kedalaman 1 m) 1,00 m3 74.375,00 - - 74.375,00
0,750 OH Pekerja 95.000,00 71.250,00 71.250,00
UPA H

0,025 OH Mandor 125.000,00 3.125,00 3.125,00


ALAT BAHAN

JUMLAH : (A) 74.375,00


KEUNTUNGAN 10% : (B) = 10% x (A) 7.437,50
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 81.812,50

008 ABK-II.008 Penggalian tanah biasa (kedalaman 2 m) 1,00 m3 91.125,00 - - 91.125,00


0,900 OH Pekerja 95.000,00 85.500,00 85.500,00
UPA H

0,045 OH Mandor 125.000,00 5.625,00 5.625,00


ALAT BAHAN

JUMLAH : (A) 91.125,00


KEUNTUNGAN 10% : (B) = 10% x (A) 9.112,50
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 100.237,50

009 ABK-II.009 Penggalian tanah biasa (kedalaman 3 m) 1,00 m3 108.125,00 - - 108.125,00


1,050 OH Pekerja 95.000,00 99.750,00 99.750,00
UPA H

0,067 OH Mandor 125.000,00 8.375,00 8.375,00


ALAT BAHAN

JUMLAH : (A) 108.125,00


KEUNTUNGAN 10% : (B) = 10% x (A) 10.812,50
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 118.937,50

010 ABK-II.010 Pengurugan dengan pasir urug 1,00 m3 29.750,00 131.824,80 - 161.574,80
0,300 OH Pekerja 95.000,00 28.500,00 28.500,00
UPA H

0,010 OH Mandor 125.000,00 1.250,00 1.250,00


ALAT BAHAN

1,200 m3 Pasir Urug 109.854,00 131.824,80 131.824,80

JUMLAH : (A) 161.574,80


KEUNTUNGAN 10% : (B) = 10% x (A) 16.157,48
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 177.732,28

012 ABK-II.012 Pengurugan kembali galian tanah 1,00 m3 53.750,00 - - 53.750,00


0,500 OH Pekerja 95.000,00 47.500,00 47.500,00
UPA H

0,050 OH Mandor 125.000,00 6.250,00 6.250,00


ALAT BAHAN

JUMLAH : (A) 53.750,00


KEUNTUNGAN 10% : (B) = 10% x (A) 5.375,00
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 59.125,00
HARGA JUMLAH HARGA
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp)
SATUAN (Rp) (Rp)
001 ABK-IV.001 Pemasangan bekisting untuk balok 1,00 m2 112.200,00 353.308,40 - 465.508,40
0,660 OH Pekerja 95.000,00 62.700,00 62.700,00
0,330 OH Tukang Kayu 125.000,00 41.250,00 41.250,00
UPA H

0,033 OH Kepala Tukang 125.000,00 4.125,00 4.125,00


0,033 OH Mandor 125.000,00 4.125,00 4.125,00

0,040 m3 Kayu Papan 3/20 1.836.000,00 73.440,00 73.440,00


0,400 kg Paku Biasa 2-5" 15.432,00 6.172,80 6.172,80
0,200 ltr Minyak Bekisting 39.448,00 7.889,60 7.889,60
BAHAN

0,018 m3 Kayu Kamper Medan Persegian 4.635.000,00 83.430,00 83.430,00


0,350 lmbr Plywood ( uk. 9 mm ) 130.560,00 45.696,00 45.696,00
2,000 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 136.680,00 136.680,00
ALAT

JUMLAH : (A) 465.508,40


KEUNTUNGAN 10% : (B) = 10% x (A) 46.550,84
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 512.059,24

003 ABK-IV.003 Pemasangan bekisting untuk kolom 1,00 m2 112.200,00 339.403,40 - 451.603,40
0,660 OH Pekerja 95.000,00 62.700,00 62.700,00
0,330 OH Tukang Kayu 125.000,00 41.250,00 41.250,00
UPA H

0,033 OH Kepala Tukang 125.000,00 4.125,00 4.125,00


0,033 OH Mandor 125.000,00 4.125,00 4.125,00

0,040 m3 Kayu Papan 3/20 1.836.000,00 73.440,00 73.440,00


0,400 kg Paku Biasa 2-5" 15.432,00 6.172,80 6.172,80
0,200 ltr Minyak Bekisting 39.448,00 7.889,60 7.889,60
BAHAN

0,015 m3 Kayu Kamper Medan Persegian 4.635.000,00 69.525,00 69.525,00


0,350 lmbr Plywood ( uk. 9 mm ) 130.560,00 45.696,00 45.696,00
2,000 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 136.680,00 136.680,00
ALAT

JUMLAH : (A) 451.603,40


KEUNTUNGAN 10% : (B) = 10% x (A) 45.160,34
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 496.763,74

HARGA JUMLAH HARGA


NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp)
SATUAN (Rp) (Rp)
004 ABK-IV.004 Pemasangan bekisting untuk lantai 1,00 m2 112.200,00 612.763,40 - 724.963,40
0,660 OH Pekerja 95.000,00 62.700,00 62.700,00
0,330 OH Tukang Kayu 125.000,00 41.250,00 41.250,00
UPA H

0,033 OH Kepala Tukang 125.000,00 4.125,00 4.125,00


0,033 OH Mandor 125.000,00 4.125,00 4.125,00

0,040 m3 Kayu Papan 3/20 1.836.000,00 73.440,00 73.440,00


0,400 kg Paku Biasa 2-5" 15.432,00 6.172,80 6.172,80
0,200 ltr Minyak Bekisting 39.448,00 7.889,60 7.889,60
BAHAN

0,015 m3 Kayu Kamper Medan Persegian 4.635.000,00 69.525,00 69.525,00


0,350 lmbr Plywood ( uk. 9 mm ) 130.560,00 45.696,00 45.696,00
6,000 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 410.040,00 410.040,00
ALAT

JUMLAH : (A) 724.963,40


KEUNTUNGAN 10% : (B) = 10% x (A) 72.496,34
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 797.459,74
005 ABK-IV.005 Pemasangan bekisting untuk pondasi 1,00 m2 88.400,00 202.214,40 - 290.614,40
0,520 OH Pekerja 95.000,00 49.400,00 49.400,00
0,260 OH Tukang Kayu 125.000,00 32.500,00 32.500,00
UPA H

0,026 OH Kepala Tukang 125.000,00 3.250,00 3.250,00


0,026 OH Mandor 125.000,00 3.250,00 3.250,00

0,040 m3 Kayu Meranti Bukit Persegian 4.841.000,00 193.640,00 193.640,00


BAHAN

0,300 kg Paku Biasa 2-5" 15.432,00 4.629,60 4.629,60


0,100 ltr Minyak Bekisting 39.448,00 3.944,80 3.944,80
ALAT

JUMLAH : (A) 290.614,40


KEUNTUNGAN 10% : (B) = 10% x (A) 29.061,44
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 319.675,84

006 ABK-IV.006 Pemasangan bekisting untuk sloof 1,00 m2 88.400,00 226.419,40 - 314.819,40
0,520 OH Pekerja 95.000,00 49.400,00 49.400,00
0,260 OH Tukang Kayu 125.000,00 32.500,00 32.500,00
UPA H

0,026 OH Kepala Tukang 125.000,00 3.250,00 3.250,00


0,026 OH Mandor 125.000,00 3.250,00 3.250,00

0,045 m3 Kayu Meranti Bukit Persegian 4.841.000,00 217.845,00 217.845,00


BAHAN

0,300 kg Paku Biasa 2-5" 15.432,00 4.629,60 4.629,60


0,100 ltr Minyak Bekisting 39.448,00 3.944,80 3.944,80
ALAT

JUMLAH : (A) 314.819,40


KEUNTUNGAN 10% : (B) = 10% x (A) 31.481,94
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 346.301,34

007 ABK-IV.007 Pemasangan bekisting untuk tangga 1,00 m2 112.200,00 319.071,00 - 431.271,00
0,660 OH Pekerja 95.000,00 62.700,00 62.700,00
0,330 OH Tukang Kayu 125.000,00 41.250,00 41.250,00
UPA H

0,033 OH Kepala Tukang 125.000,00 4.125,00 4.125,00


0,033 OH Mandor 125.000,00 4.125,00 4.125,00

0,030 m3 Kayu Papan 3/20 1.836.000,00 55.080,00 55.080,00


0,400 kg Paku Biasa 2-5" 15.432,00 6.172,80 6.172,80
0,150 ltr Minyak Bekisting 39.448,00 5.917,20 5.917,20
BAHAN

0,015 m3 Kayu Kamper Medan Persegian 4.635.000,00 69.525,00 69.525,00


0,350 lmbr Plywood ( uk. 9 mm ) 130.560,00 45.696,00 45.696,00
2,000 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 136.680,00 136.680,00
ALAT

JUMLAH : (A) 431.271,00


KEUNTUNGAN 10% : (B) = 10% x (A) 43.127,10
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 474.398,10

HARGA JUMLAH HARGA


NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp)
SATUAN (Rp) (Rp)
026 ABK-IV.026 Membuat beton mutu f'c = 24,0 Mpa (mutu K-300) 1,00 m3 205.000,00 1.121.592,97 - 1.326.592,97
1,650 OH Pekerja 95.000,00 156.750,00 156.750,00
0,275 OH Tukang Batu 125.000,00 34.375,00 34.375,00
UPA H

0,028 OH Kepala Tukang 125.000,00 3.500,00 3.500,00


0,083 OH Mandor 125.000,00 10.375,00 10.375,00

406,000 kg Semen PC (uk. 50 kg) 1.300,00 527.800,00 527.800,00


0,684 m3 Pasir Beton 320.892,00 219.490,13 219.490,13
BAHAN

1,026 m3 Koral Beton 246.840,00 253.257,84 253.257,84


215,000 ltr Air 563,00 121.045,00 121.045,00
ALAT

JUMLAH : (A) 1.326.592,97


KEUNTUNGAN 10% : (B) = 10% x (A) 132.659,30
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1.459.252,26
HARGA JUMLAH HARGA
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp)
SATUAN (Rp) (Rp)
066 ABK-IV.066 Pembesian dengan besi polos atau besi ulir 1,00 kg 16.775,00 175.207,95 - 191.982,95
0,070 OH Pekerja 95.000,00 6.650,00 6.650,00
0,070 OH Tukang Besi 125.000,00 8.750,00 8.750,00
UPA H

0,007 OH Kepala Tukang 125.000,00 875,00 875,00


0,004 OH Mandor 125.000,00 500,00 500,00

10,500 kg Besi Beton ( U - 24 ) 16.422,00 172.431,00 172.431,00


BAHAN

0,150 kg Kawat Beton 18.513,00 2.776,95 2.776,95


ALAT

JUMLAH : (A) 191.982,95


KEUNTUNGAN 10% : (B) = 10% x (A) 19.198,30
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 211.181,25

HARGA JUMLAH HARGA


NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp)
SATUAN (Rp) (Rp)
026 ABK-IV.026 Membuat beton mutu f'c = 24,0 Mpa (mutu K-300) 1,00 m3 205.000,00 1.121.592,97 - 1.326.592,97
1,650 OH Pekerja 95.000,00 156.750,00 156.750,00
0,275 OH Tukang Batu 125.000,00 34.375,00 34.375,00
UPA H

0,028 OH Kepala Tukang 125.000,00 3.500,00 3.500,00


0,083 OH Mandor 125.000,00 10.375,00 10.375,00

406,000 kg Semen PC (uk. 50 kg) 1.300,00 527.800,00 527.800,00


0,684 m3 Pasir Beton 320.892,00 219.490,13 219.490,13
BAHAN

1,026 m3 Koral Beton 246.840,00 253.257,84 253.257,84


215,000 ltr Air 563,00 121.045,00 121.045,00
ALAT

JUMLAH : (A) 1.326.592,97


KEUNTUNGAN 10% : (B) = 10% x (A) 132.659,30
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 1.459.252,26

Pemasangan plaat beton komposit tebal 10-15 cm


051 ABK-IV.051 1,00 m2 104.461,88 614.383,32 - 718.845,19
(krisdek + besi 10-12,5 engkel)
0,447 OH Pekerja 95.000,00 42.465,00 42.465,00
0,026 OH Tukang Batu 125.000,00 3.281,25 3.281,25
0,210 OH Tukang Kayu 125.000,00 26.250,00 26.250,00
UPA H

0,210 OH Tukang Besi 125.000,00 26.250,00 26.250,00


0,034 OH Kepala Tukang 125.000,00 4.265,63 4.265,63
0,016 OH Mandor 125.000,00 1.950,00 1.950,00

1,100 m2 Krisdek (Pendukung Plat Lantai Beton Komposit) 329.531,40 362.484,54 362.484,54
3,600 kg Besi Beton ( U - 24 ) 16.422,00 59.119,20 59.119,20
4,200 kg Kawat Beton 18.513,00 77.754,60 77.754,60
BAHAN

0,960 kg Semen PC (uk. 50 kg) 1.300,00 1.248,00 1.248,00


0,125 m3 Pasir Beton 320.892,00 40.047,32 40.047,32
0,187 m3 Batu Pecah ( uk. 2 - 3 (Mesin) ) 393.855,00 73.729,66 73.729,66
ALAT

JUMLAH : (A) 718.845,19


KEUNTUNGAN 10% : (B) = 10% x (A) 71.884,52
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 790.729,71
HARGA JUMLAH HARGA
NO. ANALIS JENIS PEKERJAAN VOL. SAT. UPAH (Rp) BAHAN (Rp) ALAT (Rp)
SATUAN (Rp) (Rp)
052 ABK-IV.052 Pemasangan plat beton 12 cm 1,00 m3 1.217.825,00 5.244.858,29 - 6.462.683,29
5,960 OH Pekerja 95.000,00 566.200,00 566.200,00
0,350 OH Tukang Batu 125.000,00 43.750,00 43.750,00
2,800 OH Tukang Kayu 125.000,00 350.000,00 350.000,00
UPA H

1,400 OH Tukang Besi 125.000,00 175.000,00 175.000,00


0,455 OH Kepala Tukang 125.000,00 56.875,00 56.875,00
0,208 OH Mandor 125.000,00 26.000,00 26.000,00

0,200 m3 Kayu Papan Cor 2.344.980,00 468.996,00 468.996,00


2,000 kg Paku Reng / Usuk 24.684,00 49.368,00 49.368,00
1,600 ltr Oli 24.700,00 39.520,00 39.520,00
123,108 kg Besi Beton ( U - 24 ) 16.422,00 2.021.685,05 2.021.685,05
4,500 kg Kawat Beton 18.513,00 83.308,50 83.308,50
BAHAN

323,000 kg Semen PC (uk. 50 kg) 1.300,00 419.900,00 419.900,00


0,520 m3 Pasir Beton 320.892,00 166.863,84 166.863,84
0,780 m3 Batu Pecah ( uk. 2 - 3 (Mesin) ) 393.855,00 307.206,90 307.206,90
0,150 m3 Kayu Meranti Bukit Persegian 4.841.000,00 726.150,00 726.150,00
3,500 lmbr Plywood ( uk. 4 mm ) 79.560,00 278.460,00 278.460,00
10,000 btg Kayu Dolken dia 8 cm - 4 m 68.340,00 683.400,00 683.400,00
ALAT

JUMLAH : (A) 6.462.683,29


KEUNTUNGAN 10% : (B) = 10% x (A) 646.268,33
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 7.108.951,62

056 ABK-IV.056 Pemasangan pondasi beton 1,00 m3 726.750,00 4.712.513,33 - 5.439.263,33


3,900 OH Pekerja 95.000,00 370.500,00 370.500,00
0,350 OH Tukang Batu 125.000,00 43.750,00 43.750,00
1,040 OH Tukang Kayu 125.000,00 130.000,00 130.000,00
UPA H

1,050 OH Tukang Besi 125.000,00 131.250,00 131.250,00


0,245 OH Kepala Tukang 125.000,00 30.625,00 30.625,00
0,165 OH Mandor 125.000,00 20.625,00 20.625,00

0,200 m3 Kayu Papan Cor 2.344.980,00 468.996,00 468.996,00


1,500 kg Paku Reng / Usuk 24.684,00 37.026,00 37.026,00
0,400 ltr Oli 24.700,00 9.880,00 9.880,00
198,416 kg Besi Beton ( U - 24 ) 16.422,00 3.258.386,34 3.258.386,34
BAHAN

2,250 kg Kawat Beton 18.513,00 41.654,25 41.654,25


325,000 kg Semen PC (uk. 50 kg) 1.300,00 422.500,00 422.500,00
0,520 m3 Pasir Beton 320.892,00 166.863,84 166.863,84
0,780 m3 Batu Pecah ( uk. 2 - 3 (Mesin) ) 393.855,00 307.206,90 307.206,90
ALAT

JUMLAH : (A) 5.439.263,33


KEUNTUNGAN 10% : (B) = 10% x (A) 543.926,33
HARGA SATUAN (+ KEUNTUNGAN) : (C) = (A+B) 5.983.189,66