REKAPITULASI KEBUTUHAN BAHAN DAN TENAGA KERJA

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : PEMBUATAN POS JAGA MATA AIR SANGIA
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016

NO URAIAN VOLUME SATUAN


HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
BAHAN
1 Pasir Urug 0.5 M3 250,000 125,000.00
2 Batu belah 15/20 cm 1.5 M3 140,000 210,000.00
3 Semen 3.9 zak 80,000 312,000.00
4 Pasir pasang 0.55 m3 250,000 137,500.00
5 Tanah Timbunan 0.5 m3 77,000 38,500.00
6 Pasir beton 0.1 m3 250,000 25,000.00
7 Kerikil 0.1 M3 300,000 30,000.00
8 Ubin abu-abu 30x30 cm 27 buah 5,500 148,500.00
9 Kayu Kelas II , balok 0.3 M3 2,000,000 600,000.00
10 Besi strip 4.1 Kg 13,000 53,300.00
11 Paku biasa 2" - 5" 0.5 Kg 17,000 8,500.00
12 Kayu Kelas II, papan 0.05 M3 2,000,000 100,000.00
13 Seng gelombang 3" x 6" bjls 20 Ukuran 90x180 cm 4 lbr 90,000 360,000.00
14 Paku Seng 0.2 Kg 35,000 7,000.00
15 Seng plat 3" x 6" bjls 20 Lebar 45 cm 0.8 lbr 25,000 20,000.00
16 Cat meni 1.2 Kg 42,000 50,400.00
17 Plamir 0.92 Kg 25,000 23,000.00
18 Cat dasar 1.05 Kg 60,000 63,000.00
19 Cat Penutup 1.6 Kg 60,000 96,000.00
20 Pembuatan Portal 1 buah 1,500,000.00 1,500,000.00
TENAGA
1 Pekerja 7.41 OH 95,000.00 703,950.00
2 Tukang 7.09 OH 125,000.00 886,250.00
3 Kepala Tukang 0.77 OH 150,000.00 115,950.00
4 Mandor 0.54 OH 125,000.00 67,500.00
JUMLAH 5,681,350.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : PEMBUATAN POS JAGA MATA AIR SANGIA
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016

JUMLAH HARGA JUMLAH HARGA


NO URAIAN HARGA DAN UPAH SATUAN KOEFISIEN KET
KEBUTUHAN SATUAN (Rp) (Rp)
1 2 3 4 5 (VOLUME X (4)) 6 7 (5 X 6) 8
A PEKERJAAN TANAH
1 Galian Pondasi
Volume = 0.9 m3
Tenaga
Pekerja OH 0.4 0.4 95,000 38,000.0
Mandor OH 0.04 0.04 125,000 5,000.0

B PEKERJAAN PONDASI
1 Urugan Pasir Bawah Pondasi tebal 5 cm
Volume = 0.15 m3
Bahan
Pasir Urug m3 1.2 0.2 250,000 50,000.0
Tenaga
Pekerja OH 0.3 0.05 95,000 4,750.0
Mandor OH 0.01 0.12 125,000 15,000.0

2 Pasangan Batu Kosong Pondasi


Volume = 0.6 m3
Bahan
Batu belah 15/20 cm M3 1.200 0.7 140,000 98,000.0
Pasir urug M3 0.300 0.2 250,000 50,000.0
Tenaga
Pekerja OH 0.780 0.5 95,000 47,500.0
Tukang batu OH 0.390 0.2 125,000 25,000.0
Kepala tukang OH 0.039 0.02 150,000 3,000.0
Mandor OH 0.039 0.02 125,000 2,500.0

3 Pasangan Batu Gunung 1:4 Pondasi


Volume = 0.75 m3
Bahan
Batu belah 15/20 cm M3 1.100 0.8 140,000 112,000.0
Semen zak 3.260 2.4 80,000 192,000.0
Pasir pasang M3 0.520 0.4 250,000 100,000.0
Tenaga
Pekerja OH 1.500 1.1 95,000 104,500.0
Tukang batu OH 0.600 0.5 125,000 62,500.0
Kepala tukang OH 0.060 0.05 150,000 7,500.0
Mandor OH 0.075 0.06 125,000 7,500.0

4 Plesteran Pondasi (1 PC : 5 PP) ; tebal 15 mm


Volume = 3.06 m2
Bahan
Semen zak 0.0864 0.3 80,000 24,000.0
Pasir pasang M3 0.0220 0.1 250,000 25,000.0
Tenaga
Pekerja OH 0.200 0.6 95,000 57,000.0
Tukang batu OH 0.150 0.5 125,000 62,500.0
Kepala tukang OH 0.015 0.05 150,000 7,500.0
Mandor OH 0.010 0.03 125,000 3,750.0

5 Acian Semen
Volume = 3.06 m2
Bahan
Semen zak 0.0650 0.2 80,000 16,000.0
Tenaga
Pekerja OH 0.200 0.6 95,000 57,000.0
Tukang batu OH 0.100 0.3 125,000 37,500.0
Kepala tukang OH 0.010 0.03 150,000 4,500.0
Mandor OH 0.010 0.03 125,000 3,750.0
C PEKERJAAN LANTAI
1 Urugan Tanah Bawah Lantai
Volume = 0.45 m3
Bahan
Tanah Timbunan m3 1.2 0.5 77,000 38,500.0
Tenaga
Pekerja OH 0.3 0.1 95,000 9,500.0

2 Urugan Pasir Bawah Lantai


Volume = 0.1125 m3
Bahan
Pasir Urug m3 1.2 0.1 250,000 25,000.0
Tenaga
Pekerja OH 0.3 0.03 95,000 2,850.0
Mandor OH 0.01 0.001 125,000 125.0

3 Rabat Beton 1 PC : 3 PS : 5 KR
Volume = 0.1125 m3
Bahan
Semen zak 4.360 0.5 80,000 40,000.0
Pasir beton m3 0.520 0.1 250,000 25,000.0
Kerikil m3 0.870 0.1 300,000 30,000.0
Tenaga
Pekerja OH 1.650 0.2 95,000 19,000.0
Tukang batu OH 0.250 0.03 125,000 3,750.0
Kepala tukang OH 0.025 0.003 150,000 450.0
Mandor OH 0.080 0.009 125,000 1,125.0

4 Lantai Keramik 30 x 30 cm
Volume = 2.25 m2
Bahan
Ubin abu-abu 30x30 cm Bh 11.870 27 5,500 148,500.0
Semen zak 0.200 0.5 80,000 40,000.0
Pasir pasang M3 0.0215 0.05 250,000 12,500.0
Tenaga
Pekerja Oh 0.260 0.6 95,000 57,000.0
Tukang batu Oh 0.125 0.3 125,000 37,500.0
Kepala tukang Oh 0.0125 0.03 150,000 4,500.0
Mandor Oh 0.013 0.03 125,000 3,750.0

D PEKERJAAN KAYU
1 Kuda Kuda Kayu Kelas II
Volume
Kolom (10/10 x 3 m) = 0.12 m3
Rangka Kuda-Kuda 5/10 = 0.11 m3
Kayu Gording 5/7 = 0.042 m3
Jumlah Volume Kayu = 0.272 m3

Bahan
Kayu Kelas II , balok M3 1.100 0.3 2,000,000 600,000.0
Besi strip Kg 15.000 4.1 13,000 53,300.0
Paku biasa 2" - 5" Kg 0.800 0.2 17,000 3,400.0
Tenaga
Pekerja Oh 4.000 1.1 95,000 104,500.0
Tukang kayu Oh 12.000 3.3 125,000 412,500.0
Kepala tukang Oh 1.200 0.3 150,000 45,000.0
Mandor Oh 0.200 0.1 125,000 12,500.0

2 List Plank Papan 3x20 Kayu Kelas II


Volume = 6.8 m'
Bahan
Kayu Kelas II, papan M3 0.007 0.05 2,000,000 100,000.0
Paku biasa 2" - 5" Kg 0.050 0.3 17,000 5,100.0
Tenaga
Pekerja Oh 0.100 0.7 95,000 66,500.0
Tukang kayu Oh 0.200 1.4 125,000 175,000.0
Kepala tukang Oh 0.025 0.2 150,000 30,000.0
Mandor Oh 0.005 0.03 125,000 3,750.0

3 Pembuatan Portal buah 1 1,500,000 1,500,000.0


E PEKERJAAN ATAP
1 Atap Seng Gelombang
Volume = 5 m2
Bahan
Seng gelombang 3" x 6" bjls 20 Ukuran 90x180 cm Lbr 0.700 4 90,000 360,000.0
Paku Seng Kg 0.020 0.1 35,000 3,500.0
Tenaga
Pekerja Oh 0.120 0.6 95,000 57,000.0
Tukang kayu Oh 0.060 0.3 125,000 37,500.0
Kepala tukang Oh 0.006 0.03 150,000 4,500.0
Mandor Oh 0.006 0.03 125,000 3,750.0

2 Nok Seng
Volume = 2.7 m2
Bahan
Seng plat 3" x 6" bjls 20 Lebar 45 cm Lbr 0.300 0.8 25,000 20,000.0
Paku Seng Kg 0.040 0.1 35,000 3,500.0
Tenaga
Pekerja Oh 0.150 0.4 95,000 38,000.0
Tukang kayu Oh 0.070 0.2 125,000 25,000.0
Kepala tukang Oh 0.008 0.02 150,000 3,000.0
Mandor Oh 0.006 0.02 125,000 2,500.0

E PEKERJAAN PENGECATAN
1 Pengecatan List Plank dan Kolom (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Volume = 6.16 m2
Bahan
Cat meni Kg 0.200 1.2 42,000 50,400.0
Plamir Kg 0.150 0.92 25,000 23,000.0
Cat dasar Kg 0.170 1.05 60,000 63,000.0
Cat Penutup Kg 0.260 1.6 60,000 96,000.0
Tenaga
Pekerja Oh 0.070 0.43 95,000 40,850.0
Tukang kayu Oh 0.009 0.06 125,000 7,500.0
Kepala tukang Oh 0.006 0.04 150,000 6,000.0
Mandor Oh 0.003 0.02 125,000 2,500.0

5,681,350.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


REKAPITULASI KEBUTUHAN BAHAN DAN TENAGA KERJA

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : PEMBUATAN SARANA MCK MATA AIR SANGIA
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016

NO URAIAN VOLUME SATUAN


HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
BAHAN
1 Pasir Urug 3.8 M3 250,000 950,000.00
2 Batu belah 15/20 cm 10.1 M3 140,000 1,414,000.00
3 Semen 77.64 zak 80,000 6,211,200.00
4 Pasir pasang 9.42 m3 250,000 2,355,000.00
5 Tanah Timbunan 9.7 m3 77,000 746,900.00
6 Pasir beton 2.2 m3 250,000 550,000.00
7 Kerikil 3.4 M3 300,000 1,020,000.00
8 Besi diameter 6 mm panjang 12 m 25 Btg 44,000 1,100,000.00
9 Besi diameter 10 mm panjang 12 m 34 Btg 100,000 3,400,000.00
10 Kawat Beton 3 Kg 34,000 102,000.00
11 Bata merah 5 x 11 x 22 4060 buah 800 3,248,000.00
12 Keramik 15x15 cm, warna 1200 buah 2,100 2,520,000.00
13 Semen warna 90 Kg 3,000 270,000.00
14 Ubin abu-abu 20x20 cm 600 buah 1,680 1,008,000.00
15 Kayu Kelas II, balok 0.3 M3 2,000,000 600,000.00
16 Besi strip 4.6 Kg 13,000 59,800.00
17 Paku biasa 2" - 5" 1.5 Kg 17,000 25,500.00
18 Kayu Kelas II, papan 0.18 M3 2,000,000 360,000.00
19 Kayu Jati, balok 0.145 m3 3,000,000 435,000.00
20 Kayu jati, papan 0.165 m3 3,000,000 495,000.00
21 Kunci tanam kamar mandi 4 buah 30,000 120,000.00
22 Seng gelombang 3" x 6" bjls 20 Ukuran 90x180 cm 26 lbr 90,000 2,340,000.00
23 Paku Seng 0.8 Kg 35,000 28,000.00
24 Seng plat 3" x 6" bjls 20 Lebar 45 cm 1.2 lbr 25,000 30,000.00
25 Kloset jongkok porselen 2 buah 230,000 460,000.00
26 Pipa PVC 12 m 30,000 360,000.00
27 Perlengkapan Pipa 0.35 Harga pipa 126,000.00
28 Cat meni 15.6 Kg 42,000 655,200.00
29 Plamir 11.72 Kg 25,000 293,000.00
30 Cat dasar 13.28 Kg 60,000 796,800.00
31 Cat Penutup 20.31 Kg 60,000 1,218,600.00

TENAGA
1 Pekerja 144.88 OH 95,000.00 13,763,600.00
2 Tukang 96.38 OH 125,000.00 12,047,500.00
3 Kepala Tukang 12.85 OH 150,000.00 1,927,500.00
4 Mandor 7.72 OH 125,000.00 965,000.00
JUMLAH 62,001,600.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan
GUSTAF MARPAUNG (______________________________________)
RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : PEMBUATAN SARANA MCK MATA AIR SANGIA
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016

JUMLAH HARGA JUMLAH HARGA


NO URAIAN HARGA DAN UPAH SATUAN KOEFISIEN
KEBUTUHAN SATUAN (Rp) (Rp)
1 2 3 4 5 (VOLUME X (4)) 6 7 (5 X 6)
A PEKERJAAN TANAH
1 Galian Pondasi
Volume = 5.85 m3
Tenaga
Pekerja OH 0.4 2.3 95,000 218,500.0
Mandor OH 0.04 0.2 125,000 25,000.0

B PEKERJAAN PONDASI
1 Urugan Pasir Bawah Pondasi tebal 5 cm
Volume = 0.975 m3
Bahan
Pasir Urug m3 1.2 1.2 250,000 300,000.0
Tenaga
Pekerja OH 0.3 0.3 95,000 28,500.0
Mandor OH 0.01 0.12 125,000 15,000.0

2 Pasangan Batu Kosong Pondasi


Volume = 3.9 m3
Bahan
Batu belah 15/20 cm M3 1.200 4.7 140,000 658,000.0
Pasir urug M3 0.300 1.2 250,000 300,000.0
Tenaga
Pekerja OH 0.780 3 95,000 285,000.0
Tukang batu OH 0.390 1.5 125,000 187,500.0
Kepala tukang OH 0.039 0.2 150,000 30,000.0
Mandor OH 0.039 0.2 125,000 25,000.0

3 Pasangan Batu Gunung 1:4 Pondasi


Volume = 4.875 m3
Bahan
Batu belah 15/20 cm M3 1.100 5.4 140,000 756,000.0
Semen zak 3.260 15.9 80,000 1,272,000.0
Pasir pasang M3 0.520 2.5 250,000 625,000.0
Tenaga
Pekerja OH 1.500 7.3 95,000 693,500.0
Tukang batu OH 0.600 2.9 125,000 362,500.0
Kepala tukang OH 0.060 0.3 150,000 45,000.0
Mandor OH 0.075 0.4 125,000 50,000.0

C PEKERJAAN BETON
1 Pengecoran Sloof, Kolom dan Balok ( 1 Pc : 2 Ps : 3 Kr)
Volume = 2.0925 m3
Bahan
Semen Portland zak 4.640 9.7 80,000 776,000.0
Pasir beton M3 0.520 1.1 250,000 275,000.0
Kerikil M3 0.780 1.6 300,000 480,000.0
Besi diameter 6 mm panjang 12 m Btg 25 44,000 1,100,000.0
Besi diameter 10 mm panjang 12 m Btg 34 100,000 3,400,000.0
Kawat Beton Kg 3 34,000 102,000.0
Tenaga
Pekerja Oh 1.650 3.5 95,000 332,500.0
Tukang batu Oh 0.250 0.5 125,000 62,500.0
Kepala tukang Oh 0.025 0.1 150,000 15,000.0
Mandor Oh 0.080 0.2 125,000 25,000.0
D PEKERJAAN DINDING
1 Dinding bata merah tebal ½ bata, 1 PC : 5 Ps
Volume = 58 m2
Bahan
Bata merah 5 x 11 x 22 bh 70.000 4060 800 3,248,000.0
Semen Portland zak 0.192 11.1 80,000 888,000.0
Pasir pasang M3 0.045 2.6 250,000 650,000.0
Tenaga
Pekerja Oh 0.320 18.6 95,000 1,767,000.0
Tukang batu Oh 0.100 5.8 125,000 725,000.0
Kepala tukang Oh 0.010 0.6 150,000 90,000.0
Mandor Oh 0.015 0.9 125,000 112,500.0

2 Plesteran (1 PC : 5 PP) ; tebal 15 mm


Volume = 122.20 m2
Bahan
Semen zak 0.0864 10.6 80,000 848,000.0
Pasir pasang M3 0.0220 2.7 250,000 675,000.0
Tenaga
Pekerja OH 0.200 24.4 95,000 2,318,000.0
Tukang batu OH 0.150 18.3 125,000 2,287,500.0
Kepala tukang OH 0.015 1.8 150,000 270,000.0
Mandor OH 0.010 1.2 125,000 150,000.0

5 Acian Semen
Volume = 78.10 m2
Bahan
Semen zak 0.0650 5.1 80,000 408,000.0
Tenaga
Pekerja OH 0.200 15.6 95,000 1,482,000.0
Tukang batu OH 0.100 7.8 125,000 975,000.0
Kepala tukang OH 0.010 0.8 150,000 120,000.0
Mandor OH 0.010 0.8 125,000 100,000.0

6 Dinding Keramik 20 x 25
Volume = 60.00 m2
Bahan
Keramik 15x15 cm, warna Bh 20.000 1200 2,100 2,520,000.0
Semen portland Kg 0.186 11.2 80,000 896,000.0
Pasir pasang M3 0.0180 1.1 250,000 275,000.0
Semen warna Kg 1.500 90 3,000 270,000.0
Tenaga
Pekerja Oh 0.600 36 95,000 3,420,000.0
Tukang batu Oh 0.450 27 125,000 3,375,000.0
Kepala tukang Oh 0.045 2.7 150,000 405,000.0
Mandor Oh 0.0300 1.8 125,000 225,000.0

E PEKERJAAN LANTAI
1 Urugan Tanah Bawah Lantai
Volume = 8.064 m3
Bahan
Tanah Timbunan m3 1.2 9.7 77,000 746,900.0
Tenaga
Pekerja OH 0.3 2.4 95,000 228,000.0
Mandor OH 0.01 0.1 125,000 12,500.0

2 Urugan Pasir Bawah Lantai


Volume = 1.152 m3
Bahan
Pasir Urug m3 1.2 1.4 250,000 350,000.0
Tenaga
Pekerja OH 0.3 0.3 95,000 28,500.0
Mandor OH 0.01 0.01 125,000 1,250.0
3 Rabat Beton 1 PC : 3 PS : 5 KR
Volume = 1.152 m3
Bahan
Semen zak 4.360 5 80,000 400,000.0
Pasir beton m3 0.520 0.6 250,000 150,000.0
Kerikil m3 0.870 1 300,000 300,000.0
Tenaga
Pekerja OH 1.650 1.9 95,000 180,500.0
Tukang batu OH 0.250 0.3 125,000 37,500.0
Kepala tukang OH 0.025 0.03 150,000 4,500.0
Mandor OH 0.080 0.1 125,000 12,500.0

4 Lantai Keramik 20 x 20 cm
Volume = 24 m2
Bahan
Ubin abu-abu 20x20 cm Bh 25.000 600 1,680 1,008,000.0
Semen zak 0.200 4.8 80,000 384,000.0
Pasir pasang M3 0.0215 0.5 250,000 125,000.0
Tenaga
Pekerja Oh 0.260 6.2 95,000 589,000.0
Tukang batu Oh 0.125 3 125,000 375,000.0
Kepala tukang Oh 0.0125 0.3 150,000 45,000.0
Mandor Oh 0.013 0.3 125,000 37,500.0

F PEKERJAAN KAYU
1 Kuda Kuda Kayu Kelas II
Volume
Rangka Kuda-Kuda 5/10 = 0.072 m3
Kayu Gording 5/7 = 0.189 m3
Balok Nok 5/10 = 0.045 m3
Jumlah Volume Kayu = 0.306 m3

Bahan
Kayu Kelas II, balok M3 1.100 0.3 2,000,000 600,000.0
Besi strip Kg 15.000 4.6 13,000 59,800.0
Paku biasa 2" - 5" Kg 0.800 0.2 17,000 3,400.0
Tenaga
Pekerja Oh 4.000 1.2 95,000 114,000.0
Tukang kayu Oh 12.000 3.7 125,000 462,500.0
Kepala tukang Oh 1.200 0.4 150,000 60,000.0
Mandor Oh 0.200 0.1 125,000 12,500.0

2 List Plank Papan 3x20 Kayu Kelas II


Volume = 25.2 m'
Bahan
Kayu Kelas II, papan M3 0.007 0.18 2,000,000 360,000.0
Paku biasa 2" - 5" Kg 0.050 1.3 17,000 22,100.0
Tenaga
Pekerja Oh 0.100 2.5 95,000 237,500.0
Tukang kayu Oh 0.200 5 125,000 625,000.0
Kepala tukang Oh 0.025 0.6 150,000 90,000.0
Mandor Oh 0.005 0.1 125,000 12,500.0

3 Kusen Pintu dan Ventilasi Kayu Jati


Volume = 0.121 m3
Bahan
Kayu Jati, balok M3 1.200 0.145 3,000,000 435,000.0
Tenaga
Pekerja Oh 6.000 0.7 95,000 66,500.0
Tukang kayu Oh 18.000 2.18 125,000 272,500.0
Kepala tukang Oh 2.000 0.24 150,000 36,000.0
Mandor Oh 0.300 0.04 125,000 5,000.0
4 Pintu Kayu Jati
Volume = 4.7 m2
Bahan
Kayu jati, papan M3 M3 0.035 0.165 3,000,000 495,000.0
Tenaga
Pekerja Oh Oh 0.800 3.76 95,000 357,200.0
Tukang kayu Oh Oh 2.000 9.4 125,000 1,175,000.0
Kepala tukang Oh Oh 0.200 0.94 150,000 141,000.0
Mandor Oh Oh 0.040 0.19 125,000 23,750.0

5 Kunci Tanam Kamar Mandi


Volume = 4 buah
Bahan
Kunci tanam kamar mandi Bh 1.000 4 30,000 120,000.0
Tenaga
Pekerja Oh 0.005 0.02 95,000 1,900.0
Tukang kayu Oh 0.500 2 125,000 250,000.0
Kepala tukang Oh 0.005 0.02 150,000 3,000.0
Mandor Oh 0.0025 0.01 125,000 1,250.0

G PEKERJAAN ATAP
1 Atap Seng Gelombang
Volume = 32.4 m2
Bahan
Seng gelombang 3" x 6" bjls 20 Ukuran 90x180 cm Lbr 0.700 26 90,000 2,340,000.0
Paku Seng Kg 0.020 0.6 35,000 21,000.0
Tenaga
Pekerja Oh 0.120 3.9 95,000 370,500.0
Tukang kayu Oh 0.060 1.9 125,000 237,500.0
Kepala tukang Oh 0.006 0.2 150,000 30,000.0
Mandor Oh 0.006 0.2 125,000 25,000.0

2 Nok Seng
Volume = 4.05 m2
Bahan
Seng plat 3" x 6" bjls 20 Lebar 45 cm Lbr 0.300 1.2 25,000 30,000.0
Paku Seng Kg 0.040 0.2 35,000 7,000.0
Tenaga
Pekerja Oh 0.150 0.6 95,000 57,000.0
Tukang kayu Oh 0.070 0.3 125,000 37,500.0
Kepala tukang Oh 0.008 0.03 150,000 4,500.0
Mandor Oh 0.006 0.02 125,000 2,500.0

G PEKERJAAN SANITASI
1 Galian Bak Penampungan (Kedalaman = 3 m)
Volume = 2.36 m3
Tenaga
Pekerja OH 0.4 0.9 95,000 85,500.0
Mandor OH 0.04 0.1 125,000 12,500.0

2 Beton Tumbuk 1 PC : 3 PS : 5 KR (Dinding Bak Penampung dan Penutup tebal = 10 cm


Volume = 0.93 m3
Bahan
Semen zak 4.360 4 80,000 320,000.0
Pasir beton m3 0.520 0.5 250,000 125,000.0
Kerikil m3 0.870 0.8 300,000 240,000.0
Tenaga
Pekerja OH 1.650 1.5 95,000 142,500.0
Tukang batu OH 0.250 0.2 125,000 25,000.0
Kepala tukang OH 0.025 0.02 150,000 3,000.0
Mandor OH 0.080 0.1 125,000 12,500.0
3 Kloset Jongkok Porselen
Volume = 2.00 buah
Bahan
Kloset jongkok porselen Bh 1.000 2 230,000 460,000.0
Semen portland zak 0.120 0.24 80,000 19,200.0
Pasir pasang M3 0.010 0.02 250,000 5,000.0
Tenaga
Pekerja Oh 1.000 2 95,000 190,000.0
Tukang batu Oh 1.500 3 125,000 375,000.0
Kepala tukang Oh 1.500 3 150,000 450,000.0
Mandor Oh 0.160 0.3 125,000 37,500.0

4 Pipa PVC Tipe AW Diameter 2"


Volume = 10.00 m
Bahan
Pipa PVC M' 1.200 12 30,000 360,000.0
Perlengkapan Pipa Harga pipa 35% 126,000.0
Tenaga
Pekerja Oh 0.054 0.5 95,000 47,500.0
Tukang batu Oh 0.090 0.9 125,000 112,500.0
Kepala tukang Oh 0.009 0.1 150,000 15,000.0
Mandor Oh 0.0027 0.03 125,000 3,750.0

H PEKERJAAN PENGECATAN
1 Pengecatan List Plank dan Kolom (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Volume = 78.10 m2
Bahan
Cat meni Kg 0.200 15.6 42,000 655,200.0
Plamir Kg 0.150 11.72 25,000 293,000.0
Cat dasar Kg 0.170 13.28 60,000 796,800.0
Cat Penutup Kg 0.260 20.31 60,000 1,218,600.0
Tenaga
Pekerja Oh 0.070 5.5 95,000 522,500.0
Tukang kayu Oh 0.009 0.7 125,000 87,500.0
Kepala tukang Oh 0.006 0.47 150,000 70,500.0
Mandor Oh 0.003 0.2 125,000 25,000.0

62,001,600.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


REKAPITULASI KEBUTUHAN BAHAN DAN TENAGA KERJA

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : PEMBUATAN SAUNG MATA AIR SANGIA
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016

NO URAIAN VOLUME SATUAN


HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
BAHAN
1 Pasir Urug 4.5 M3 250,000 1,125,000.00
2 Batu belah 15/20 cm 7.3 M3 140,000 1,022,000.00
3 Semen 34 zak 80,000 2,720,000.00
4 Pasir pasang 3.2 m3 250,000 800,000.00
5 Tanah Timbunan 11.8 m3 77,000 908,600.00
6 Pasir beton 1.3 m3 250,000 325,000.00
7 Kerikil 2.1 M3 300,000 630,000.00
8 Ubin abu-abu 30x30 cm 581.6 buah 5,500 3,198,800.00
9 Kayu jati, balok 1.7 M3 3,000,000 5,100,000.00
10 Besi strip 22.9 Kg 13,000 297,700.00
11 Paku biasa 2" - 5" 3.1 Kg 17,000 52,700.00
12 Kayu jati, papan 0.3 M3 3,000,000 900,000.00
13 Seng gelombang 3" x 6" bjls 20 Ukuran 90x270 cm 52 lbr 135,000 7,020,000.00
14 Paku Seng 2 Kg 35,000 70,000.00
15 Seng plat 3" x 6" bjls 20 Lebar 45 cm 1.2 lbr 25,000 30,000.00
16 Cat meni 3.7 Kg 42,000 155,400.00
17 Plamir 2.76 Kg 25,000 69,000.00
18 Cat dasar 3.13 Kg 60,000 187,800.00
19 Cat Penutup 4.78 Kg 60,000 286,800.00
-
TENAGA
1 Pekerja 58.09 OH 95,000.00 5,518,550.00
2 Tukang 45.17 OH 125,000.00 5,646,250.00
3 Kepala Tukang 4.74 OH 150,000.00 711,000.00
4 Mandor 2.91 OH 125,000.00 363,700.00
JUMLAH 37,138,300.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : PEMBUATAN SAUNG MATA AIR SANGIA
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016

JUMLAH HARGA JUMLAH HARGA


NO URAIAN HARGA DAN UPAH SATUAN KOEFISIEN KET
KEBUTUHAN SATUAN (Rp) (Rp)
1 2 3 4 5 (VOLUME X (4)) 6 7 (5 X 6) 8
A PEKERJAAN TANAH
1 Galian Pondasi
Volume = 4.2 m3
Tenaga
Pekerja OH 0.4 1.7 95,000 161,500.0
Mandor OH 0.04 0.2 125,000 25,000.0

B PEKERJAAN PONDASI
1 Urugan Pasir Bawah Pondasi tebal 5 cm
Volume = 0.7 m3
Bahan
Pasir Urug m3 1.2 0.8 250,000 200,000.0
Tenaga
Pekerja OH 0.3 0.2 95,000 19,000.0
Mandor OH 0.01 0.12 125,000 15,000.0

2 Pasangan Batu Kosong Pondasi


Volume = 2.8 m3
Bahan
Batu belah 15/20 cm M3 1.200 3.4 140,000 476,000.0
Pasir urug M3 0.300 0.8 250,000 200,000.0
Tenaga
Pekerja OH 0.780 2.2 95,000 209,000.0
Tukang batu OH 0.390 1.1 125,000 137,500.0
Kepala tukang OH 0.039 0.1 150,000 15,000.0
Mandor OH 0.039 0.1 125,000 12,500.0

3 Pasangan Batu Gunung 1:4 Pondasi


Volume = 3.5 m3
Bahan
Batu belah 15/20 cm M3 1.100 3.9 140,000 546,000.0
Semen zak 3.260 11.4 80,000 912,000.0
Pasir pasang M3 0.520 1.8 250,000 450,000.0
Tenaga
Pekerja OH 1.500 5.3 95,000 503,500.0
Tukang batu OH 0.600 2.1 125,000 262,500.0
Kepala tukang OH 0.060 0.2 150,000 30,000.0
Mandor OH 0.075 0.3 125,000 37,500.0

4 Plesteran Pondasi (1 PC : 5 PP) ; tebal 15 mm


Volume = 14.28 m2
Bahan
Semen zak 0.0864 1.2 80,000 96,000.0
Pasir pasang M3 0.0220 0.3 250,000 75,000.0
Tenaga
Pekerja OH 0.200 2.9 95,000 275,500.0
Tukang batu OH 0.150 2.1 125,000 262,500.0
Kepala tukang OH 0.015 0.2 150,000 30,000.0
Mandor OH 0.010 0.1 125,000 12,500.0

5 Acian Semen
Volume = 14.28 m2
Bahan
Semen zak 0.0650 0.9 80,000 72,000.0
Tenaga
Pekerja OH 0.200 2.9 95,000 275,500.0
Tukang batu OH 0.100 1.4 125,000 175,000.0
Kepala tukang OH 0.010 0.1 150,000 15,000.0
Mandor OH 0.010 0.1 125,000 12,500.0
C PEKERJAAN LANTAI
1 Urugan Tanah Bawah Lantai
Volume = 9.8 m3
Bahan
Tanah Timbunan m3 1.2 11.8 77,000 908,600.0
Tenaga
Pekerja OH 0.3 2.9 95,000 275,500.0
Mandor OH 0.01 0.1 125,000 12,500.0

2 Urugan Pasir Bawah Lantai


Volume = 2.45 m3
Bahan
Pasir Urug m3 1.2 2.9 250,000 725,000.0
Tenaga
Pekerja OH 0.3 0.7 95,000 66,500.0
Mandor OH 0.01 0.02 125,000 2,500.0

3 Rabat Beton 1 PC : 3 PS : 5 KR
Volume = 2.45 m3
Bahan
Semen zak 4.360 10.7 80,000 856,000.0
Pasir beton m3 0.520 1.3 250,000 325,000.0
Kerikil m3 0.870 2.1 300,000 630,000.0
Tenaga
Pekerja OH 1.650 4 95,000 380,000.0
Tukang batu OH 0.250 0.6 125,000 75,000.0
Kepala tukang OH 0.025 0.1 150,000 15,000.0
Mandor OH 0.080 0.2 125,000 25,000.0

4 Lantai Keramik 30 x 30 cm
Volume = 49 m2
Bahan
Ubin abu-abu 30x30 cm Bh 11.870 581.6 5,500 3,198,800.0
Semen zak 0.200 9.8 80,000 784,000.0
Pasir pasang M3 0.0215 1.1 250,000 275,000.0
Tenaga
Pekerja Oh 0.260 12.7 95,000 1,206,500.0
Tukang batu Oh 0.125 6.1 125,000 762,500.0
Kepala tukang Oh 0.0125 0.6 150,000 90,000.0
Mandor Oh 0.013 0.6 125,000 75,000.0

D PEKERJAAN KAYU
1 Kuda Kuda Kayu Jati
Volume
Kolom (10/10 x 3 m) = 0.27 m3
Siku 5/10 0.1 m3
Rangka Kuda-Kuda 8/10 = 0.624 m3
Balok angin 5/10 = 0.08 m3
Kayu Gording 5/7 = 0.378 m3
Balok Nok 8/10 = 0.072 m3
Jumlah Volume Kayu = 1.524 m3

Bahan
Kayu jati, balok M3 1.100 1.7 3,000,000 5,100,000.0
Besi strip Kg 15.000 22.9 13,000 297,700.0
Paku biasa 2" - 5" Kg 0.800 1.2 17,000 20,400.0
Tenaga
Pekerja Oh 4.000 6.1 95,000 579,500.0
Tukang kayu Oh 12.000 18.3 125,000 2,287,500.0
Kepala tukang Oh 1.200 1.8 150,000 270,000.0
Mandor Oh 0.200 0.3 125,000 37,500.0

2 List Plank Papan 3x20 Kayu jati


Volume = 38 m'
Bahan
Kayu jati, papan M3 0.007 0.3 3,000,000 900,000.0
Paku biasa 2" - 5" Kg 0.050 1.9 17,000 32,300.0
Tenaga
Pekerja Oh 0.100 3.8 95,000 361,000.0
Tukang kayu Oh 0.200 7.6 125,000 950,000.0
Kepala tukang Oh 0.025 1 150,000 150,000.0
Mandor Oh 0.005 0.2 125,000 25,000.0
E PEKERJAAN ATAP
1 Atap Seng Gelombang
Volume = 90 m2
Bahan
Seng gelombang 3" x 6" bjls 20 Ukuran 90x270 cm Lbr 0.700 52 135,000 7,020,000.0
Paku Seng Kg 0.020 1.8 35,000 63,000.0
Tenaga
Pekerja Oh 0.120 10.8 95,000 1,026,000.0
Tukang kayu Oh 0.060 5.4 125,000 675,000.0
Kepala tukang Oh 0.006 0.5 150,000 75,000.0
Mandor Oh 0.006 0.5 125,000 62,500.0

2 Nok Seng
Volume = 4.05 m2
Bahan
Seng plat 3" x 6" bjls 20 Lebar 45 cm Lbr 0.300 1.2 25,000 30,000.0
Paku Seng Kg 0.040 0.2 35,000 7,000.0
Tenaga
Pekerja Oh 0.150 0.6 95,000 57,000.0
Tukang kayu Oh 0.070 0.3 125,000 37,500.0
Kepala tukang Oh 0.008 0.03 150,000 4,500.0
Mandor Oh 0.006 0.02 125,000 2,500.0

E PEKERJAAN PENGECATAN
1 Pengecatan List Plank dan Kolom (1 Lapis Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup)
Volume = 18.4 m2
Bahan
Cat meni Kg 0.200 3.7 42,000 155,400.0
Plamir Kg 0.150 2.76 25,000 69,000.0
Cat dasar Kg 0.170 3.13 60,000 187,800.0
Cat Penutup Kg 0.260 4.78 60,000 286,800.0
Tenaga
Pekerja Oh 0.070 1.29 95,000 122,550.0
Tukang kayu Oh 0.009 0.17 125,000 21,250.0
Kepala tukang Oh 0.006 0.11 150,000 16,500.0
Mandor Oh 0.003 0.050 125,000 6,200.0

37,138,300.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : PEMBUKAAN JALAN USAHA TANI DAN PEMBUATAN SALURAN PEMBATAS
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016
TARGET : 650 M'

JUMLAH HARGA JUMLAH HARGA


NO URAIAN HARGA DAN UPAH SATUAN KOEFISIEN KET
KEBUTUHAN SATUAN (Rp) (Rp)
1 2 3 4 5 (VOLUME X (4)) 6 7 (5 X 6) 8
I UMUM
1. Mobilisasi/ Demobilisasi Ls 1 1 16,000,000 16,000,000.0

II. PEKERJAAN TANAH


1 Galian Biasa
Volume = 4290.00 m3
Tenaga
Pekerja Jam 0.0278 120.00 13,600.0 1,632,000.0
Mandor Jam 0.0139 60.00 18,100.0 1,086,000.0

Peralatan
Excavator Jam 0.0387 166.14 650,000.0 107,992,800.0

III. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


1 Pembersihan dan Pembongkaran Tanaman (diamater < 30 cm)
Volume = 6500.00 M2
Tenaga
Pekerja Jam 0.0700 455.00 13,600.00 6,188,000.0
Mandor Jam 0.0139 91.00 18,100.00 1,647,100.0

2 Pemotongan Pohon diameter 30 - 50 cm

Volume = 100.00 Buah


Tenaga
Pekerja Jam 3.5000 350.00 13,600.00 4,760,000.0
Mandor Jam 0.3500 35.00 18,100.00 633,500.0
Peralatan
Chainsaw Jam 1.0000 100.00 278,400.00 27,840,000.0
JUMLAH 167,779,400.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


REKAPITULASI KEBUTUHAN BAHAN DAN TENAGA KERJA

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : PEMBUKAAN JALAN USAHA TANI DAN PEMBUATAN SALURAN PEMBATAS
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016
TARGET : 650 M'

NO URAIAN VOLUME SATUAN


HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
UMUM
1 Mobilisasi/ Demobilisasi 1 Ls 16,000,000 16,000,000.00

PERALATAN
1 Excavator 166.14 Jam 650,000.00 107,992,800.00
2 Chainsaw 100.00 Jam 278,400.00 27,840,000.00

TENAGA
1 Pekerja 925.00 Jam 13,600.00 12,580,000.00
2 Mandor 186.00 Jam 18,100.00 3,366,600.00
JUMLAH 167,779,400.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : NORMALISASI MATA AIR SANGIA
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016
TARGET : 3200 M2

JUMLAH HARGA JUMLAH HARGA


NO URAIAN HARGA DAN UPAH SATUAN KOEFISIEN KET
KEBUTUHAN SATUAN (Rp) (Rp)
1 2 3 4 5 (VOLUME X (4)) 6 7 (5 X 6) 8
I UMUM
1. Mobilisasi/ Demobilisasi Ls 1 1 16,000,000 16,000,000.0

II. PEKERJAAN TANAH


1 Galian Biasa
Volume = 4800.00 M3
Tenaga
Pekerja Jam 0.0278 134.00 13,600.0 1,822,400.0
Mandor Jam 0.0139 67.00 18,100.0 1,212,700.0

Peralatan
Excavator Jam 0.0326 156.48 650,000.0 101,713,800.0

III. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR


2 Pemotongan Pohon diameter 30 - 50 cm

Volume = 28.00 Buah


Tenaga
Pekerja Jam 3.5000 98.00 13,600.00 1,332,800.0
Mandor Jam 0.3500 10.00 18,100.00 181,000.0
Peralatan
Chainsaw Jam 1.0000 28.00 278,400.00 7,795,200.0
JUMLAH 130,057,900.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


REKAPITULASI KEBUTUHAN BAHAN DAN TENAGA KERJA

SATUAN KERJA : DESA KABANGKA


PEKERJAAN : NORMALISASI MATA AIR SANGIA
LOKASI : DESA KABANGKA KECAMATAN KABANGKA
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016
TARGET : 3200 M2

NO URAIAN VOLUME SATUAN


HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
UMUM
1 Mobilisasi/ Demobilisasi 1 Ls 16,000,000 16,000,000.00

PERALATAN
1 Excavator 156.48 Jam 650,000.00 101,713,800.00
2 Chainsaw 28.00 Jam 278,400.00 7,795,200.00

TENAGA
1 Pekerja 232.00 Jam 13,600.00 3,155,200.00
2 Mandor 77.00 Jam 18,100.00 1,393,700.00
JUMLAH 130,057,900.00

Kabangka, 2016

Mengetahui Dibuat Oleh


Kepala Desa Kabangka Pelaksana Kegiatan

GUSTAF MARPAUNG (______________________________________)


RENCANA ANGGARAN BIAYA (RAB)
0

PEKERJAAN

PEMBUKAAN JALAN USAHA TANI DAN PEMBUATAN


SALURAN PEMBATAS

LOKASI
DESA KABANGKA
KECAMATAN KABANGKA

TAHUN ANGGARAN
2016

Anda mungkin juga menyukai