REKAPITULASI KEBUTUHAN BAHAN DAN TENAGA KERJA

SATUAN KERJA : DESA MAROBO


PEKERJAAN : PEMBUATAN DEUKER
LOKASI : DESA MAROBO KECAMATAN MAROBO
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016

NO URAIAN VOLUME SATUAN


HARGA SATUAN (Rp) JUMLAH HARGA (Rp)
BAHAN
1 Pasir Urug 1.40 m3 250,000.00 350,000.00
2 Batu belah 15/20 cm 8.40 m3 140,000.00 1,176,000.00
3 Semen Portland 33.70 zak 80,000.00 2,696,000.00
4 Pasir pasang 3.00 m3 250,000.00 750,000.00
5 Pasir Beton 0.90 m3 250,000.00 225,000.00
6 Kerikil 1.10 m3 300,000.00 330,000.00
7 Air 377.00 liter 100.00 37,700.00
8 Besi Beton diameter 16 mm 10.00 btg 220,000.00 2,200,000.00
9 Besi Beton diameter 12 mm 11.00 btg 135,000.00 1,485,000.00

TENAGA
1 Pekerja 22.20 OH 95,000.00 2,109,000.00
2 Tukang 9.40 OH 125,000.00 1,175,000.00
3 Kepala tukang 0.96 OH 150,000.00 144,000.00
4 Mandor 1.34 OH 125,000.00 167,500.00
JUMLAH 12,845,200.00

Marobo, 2016

Mengetahui Dibuat Oleh


Kepala Desa Marobo Pelaksana Kegiatan

(______________________________________) (______________________________________)
RENCANA ANGGARAN BIAYA (RAB)

SATUAN KERJA : DESA MAROBO


PEKERJAAN : PEMBUATAN DEUKER
LOKASI : DESA MAROBO KECAMATAN MAROBO
KABUPATEN : MUNA
TAHUN ANGGARAN : 2016

JUMLAH HARGA JUMLAH HARGA


NO URAIAN HARGA DAN UPAH SATUAN KOEFISIEN KET
KEBUTUHAN SATUAN (Rp) (Rp)
1 2 3 4 5 (VOLUME X (4)) 6 7 (5 X 6) 8
1 Galian Pondasi Deuker
Volume = 4.2768 m3
Tenaga
Pekerja OH 0.4 1.7 95,000 161,500.0
Mandor OH 0.04 0.2 125,000 25,000.0

2 Urugan Pasir Deuker tebal = 5 cm


Volume = 0.594 m3
Bahan
Pasir Urug m3 1.2 0.7 250,000 175,000.0
Tenaga
Pekerja OH 0.3 0.2 95,000 19,000.0
Mandor OH 0.01 0.12 125,000 15,000.0

3 Pasangan Batu Kosong Pondasi Deuker


Volume = 2.376 m3
Bahan
Batu belah 15/20 cm M3 1.200 2.9 140,000 406,000.0
Pasir urug M3 0.300 0.7 250,000 175,000.0
Tenaga
Pekerja OH 0.780 1.9 95,000 180,500.0
Tukang batu OH 0.390 0.9 125,000 112,500.0
Kepala tukang OH 0.039 0.1 150,000 15,000.0
Mandor OH 0.039 0.1 125,000 12,500.0

4 Pasangan Batu Gunung 1:4 Pondasi Deuker


Volume = 4.84 m3
Bahan
Batu belah 15/20 cm M3 1.100 5.3 140,000 742,000.0
Semen Portland zak 3.260 15.8 80,000 1,264,000.0
Pasir pasang M3 0.520 2.5 250,000 625,000.0
Tenaga
Pekerja OH 1.500 7.3 95,000 693,500.0
Tukang batu OH 0.600 2.9 125,000 362,500.0
Kepala tukang OH 0.060 0.3 150,000 45,000.0
Mandor OH 0.075 0.4 125,000 50,000.0

5 Pasangan Batu Gunung 1:5 Leaning Deuker


Volume = 0.156 m3
Bahan
Batu belah 15/20 cm M3 1.100 0.2 140,000 28,000.0
Semen Portland zak 2.720 0.4 80,000 32,000.0
Pasir pasang M3 0.544 0.1 250,000 25,000.0
Tenaga
Pekerja OH 1.500 0.2 95,000 19,000.0
Tukang batu OH 0.600 0.1 125,000 12,500.0
Kepala tukang OH 0.060 0.01 150,000 1,500.0
Mandor OH 0.075 0.02 125,000 2,500.0
6 Beton Bertulang K-300 Plat Deuker
Volume = 1.76 m3
Bahan
Semen Portland zak 8.2600 14.5 80,000 1,160,000.0
Pasir beton m3 0.4864 0.9 250,000 225,000.0
Kerikil m3 0.6006 1.1 300,000 330,000.0
Air Liter 215.0000 377 100 37,700.0
Besi Beton diameter 16 mm Btg 10 220,000 2,200,000.0
Besi Beton diameter 12 mm Btg 11 135,000 1,485,000.0
Tenaga
Pekerja OH 1.6500 2.9 95,000 275,500.0
Tukang batu OH 0.2750 0.5 125,000 62,500.0
Kepala tukang OH 0.0280 0.05 150,000 7,500.0
Mandor OH 0.0830 0.1 125,000 12,500.0

8 Plesteran Deuker (1 PC : 5 PP) ; tebal 15 mm


Volume = 19.78 m2
Bahan
Semen Portland zak 0.0864 1.7 80,000 136,000.0
Pasir pasang M3 0.0220 0.4 250,000 100,000.0
Tenaga
Pekerja OH 0.200 4 95,000 380,000.0
Tukang batu OH 0.150 3 125,000 375,000.0
Kepala tukang OH 0.015 0.3 150,000 45,000.0
Mandor OH 0.010 0.2 125,000 25,000.0

9 Acian Semen
Volume = 19.78 m2
Bahan
Semen Portland zak 0.0650 1.3 80,000 104,000.0
Tenaga
Pekerja OH 0.200 4 95,000 380,000.0
Tukang batu OH 0.100 2 125,000 250,000.0
Kepala tukang OH 0.010 0.2 150,000 30,000.0
Mandor OH 0.010 0.2 125,000 25,000.0

12,845,200.00

Marobo, 2016

Mengetahui Dibuat Oleh


Kepala Desa Marobo Pelaksana Kegiatan

(______________________________________) (______________________________________)
RENCANA ANGGARAN BIAYA (RAB)
#REF!

PEKERJAAN

pembangunan talud

LOKASI
desa marobo
KECAMATAN marobo

TAHUN ANGGARAN
2016