A. BAHAN BANGUNAN
No Jenis Bahan Satuan Harga
1 Batu kali m3 375,000.00
2 Kayu meranti balok m3
6,188,000.00
3 Kayu meranti papan m3 6,188,000.00
4 Kayu meranti reng m3 6,000,000.00
5 Kayu meranti usuk m3
6,000,000.00
6 Paku 7 cm Kg 12,750.00
7 Paku 12 cm Kg 14,150.00
8 Pasir pasang m3 204,380.00
9 Pasir urug m3 174,500.00
10 Semen PC Tiga Roda 50 Kg Zak 76,500.00
11 Tanah urug m3 128,000.00
B. DAFTAR UPAH
No Jenis Upah Satuan Harga
1 Kepala tukang batu Hari 130,000.00
2 Mandor Hari 164,500.00
3 Mandor' Jam 20,562.50
4 Pekerja Hari 75,000.00
5 Pekerja' Jam 9,375.00
6 Tukang batu Hari 120,000.00
7 Tukang kayu Hari 120,000.00
8 Tukang gali Hari 100,000.00
DAFTAR ANALISA PEKERJAAN
Harga Satuan Harga Upah
No Uraian Pekerjaan
(Rp) (Rp)
1 10 m' Pasang Bowplank
0.090 m³ Kayu Meranti Papan 6,188,000.00
0.047 m³ Kayu Meranti Usuk 6,000,000.00
0.100 kg Paku 7 (Usuk) 12,750.00
0.800 hari Tukang Kayu 120,000.00 96,000.00
0.280 hari Pekerja 75,000.00 21,000.00
0.140 hari Mandor 164,500.00 23,030.00
140,030.00
556,920.00
282,000.00
1,275.00
840,195.00 980,225.00
1 m' = 98,022.50
- 60,362.50
153,600.00
153,600.00 173,995.00
209,400.00
209,400.00 233,545.00
450,000.00
52,350.00
502,350.00 627,187.50
450,000.00
217,795.50
109,752.06
777,547.56 1,164,757.56
RENCANA ANGGARAN BIAYA
NAMA PEKERJAAN :
LOKASI :
TAHUN :
II PEK. TANAH
1 Galian Tanah Biasa 475.995 m³ 36,250.00 17,254,818.75
2 Urugan Kembali 190.320 m³ 165,460.00 31,490,347.20
3 Urugan Pasir Lantai dan Pondasi 24.830 m³ 167,835.00 4,167,343.05
52,912,509.00
No Uraian n Volume
I Pekerjaan Persiapan
1 Pembersihan Lapangan 18 12 216
2 Pas. Papan Bowplank 18 12 30 2 60
II Pekerjaan Tanah
1 Galian Tanah Biasa 7.323 1 7.323 65 475.995
2 Urugan Kembali 1.134 0.33 2.928 65 190.320
3 Urugan Pasir Lantai dan Pondasi 0.382 1 0.382 65 24.83