BILL OF QUANTITY (BQ)
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
SUB KEGIATAN : PENINGKATAN SPAM JARINGAN PERPIPAAN DI KAWASAN PERDESAAN
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
SUMBER ANGGARAN : APBN - DAK TA. 2021
SUB PEKERJAAN : PEMBUATAN SUMUR BOR
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp) JUMLAH (Rp)
SUB TOTAL -
BILL OF QUANTITY (BQ)
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
SUB KEGIATAN : PENINGKATAN SPAM JARINGAN PERPIPAAN DI KAWASAN PERDESAAN
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
SUMBER ANGGARAN : APBN - DAK TA. 2021
SUB PEKERJAAN : PENGADAAN DAN PEMASANGAN POMPA & WELLHEAD DAN ACCESORISNYA
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp) JUMLAH (Rp)
SUB TOTAL -
BILL OF QUANTITY (BQ)
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
SUB KEGIATAN : PENINGKATAN SPAM JARINGAN PERPIPAAN DI KAWASAN PERDESAAN
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
SUMBER ANGGARAN : APBN - DAK TA. 2021
SUB PEKERJAAN : GROUND RESEVOAR
NO. URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN (Rp) JUMLAH (Rp)
SUB TOTAL -
PERHITUNGAN VOLUME GROUND RESEVOAR
RUMUS
No. URAIAN
area x pjg. x lebar x tinggi x sisi = volume sat
HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SATUAN JUMLAH (Rp)
(Rp)
SUB TOTAL -
RENCANA ANGGARAN BIAYA
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
TAHUN ANGGARAN : APBN - DAK TA. 2021
SUB PEKERJAAN : SUMUR INTAKE
HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SATUAN (Rp) JUMLAH (Rp)
RUMUS
No. URAIAN
area x pjg. x lebar x tinggi x sisi = volume sat
A Beton K-225
1 Poor t : 30cm 0.60 x 0.60 x 0.30 x 2.00 = 0.22 m3
0.60 x 0.60 x 0.30 x 2.00 = 0.22 m3
= 0.43 m3
2 Kolom 15x30 1.00 x 0.15 x 0.30 x 4.00 = 0.18 m3
3 Balok 15x30 2.85 x 0.15 x 0.30 x 4.00 = 0.51 m3
Balok 15x20 2.70 x 0.15 x 0.20 x 2.00 = 0.16 m3
4 Plat Lantai t : 12cm 3.00 x 3.00 x 0.12 x 1.00 = 1.08 m3
5 Kolom praktis 15/15 0.15 x 0.15 x 3.20 x 4.00 = 0.29 m3
6 Ring balk dan balok latai 1.50 x 0.15 x 0.20 x 5.00 = 0.23 m3
7 Plat Atap t : 10cm 2.65 x 2.65 x 0.10 x 1.00 = 0.70 m3
total volume beton k-225 = 3.58 m3
RUMUS
No. URAIAN
dia kg/m x pjg. x jml x sisi = volume sat
B Pembesian
1 Footplat t : 30cm x 12 0.89 x 2.00 x 4.00 x 4.00 = 28.41 kg
y 12 0.89 x 2.00 x 4.00 x 4.00 = 28.41 kg
= 56.82 kg
2 Kolom 15x30 tul. Utama 12 0.888 x 1.64 x 6.00 x 4.00 = 34.94 kg
begel 8 0.395 x 0.84 x 13.00 x 4.00 = 17.23 kg
= 52.18 kg
3 Balok 15x30 tul. Utama 12 0.888 x 2.85 x 6.00 x 4.00 = 60.72 kg
begel 8 0.395 x 0.84 x 19.00 x 4.00 = 25.19 kg
= 85.91 kg
Balok anak 15x20 tul. Utama 12 0.888 x 2.70 x 4.00 x 2.00 = 19.18 kg
begel 8 0.395 x 0.69 x 18.00 x 2.00 = 9.80 kg
= 28.98 kg
4 Plat Lantai x 10 0.617 x 5.92 x 15.00 x 1.00 = 54.75 kg
y 10 0.617 x 5.92 x 15.00 x 1.00 = 54.75 kg
= 109.49 kg
5 Kolom praktis 15/15 tul. Utama 12 0.888 x 3.00 x 4.00 x 4.00 = 42.61 kg
begel 8 0.395 x 0.02 x 20.00 x 4.00 = 0.69 kg
= 43.31 kg
6 Ring balok 15/20 12 0.888 x 1.50 x 4.00 x 4.00 = 21.31 kg
8 0.395 x 0.69 x 10.00 x 4.00 = 10.89 kg
= 32.20 kg
7 Plat atap t : 10cm x 10.00 0.617 x 5.52 x 13.00 x 1.00 = 44.24 kg
y 10 0.617 x 5.52 x 13.00 x 1.00 = 44.24 kg
= 88.48 kg
total volume Pembesian = 419.28 kg
RUMUS
No. URAIAN
area x pjg. x lebar x tinggi x sisi = volume sat
C Begesting
1 Footplat t : 30cm 2.40 x x 0.30 x 4.00 = 2.88 m2
= 2.88 m2
2 Kolom 35x35 7.00 x x 1.40 x 4.00 = 39.20 m2
3 Balok 20x35 2.15 x x 0.90 x 8.00 = 15.48 m2
15x20 2.15 x x 0.65 x 2.00 = 2.80 m2
= 18.28 m2
4 Plat Lantai t : 15cm 4.00 x 4.00 x x 1.00 = 16.00 m2
5 Kolom praktis 15/15 2.90 x 0.30 x 4.00 = 3.48 m2
6 Ring balok 15/20 dan balok latai 1.50 x 0.40 x 5.00 = 3.00 m2
7 Plat atap 2.65 x 2.65 x x 1.00 = 7.02 m2
RENCANA ANGGARAN BIAYA
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
TAHUN ANGGARAN : APBN - DAK TA. 2021
SUB PEKERJAAN : PENGADAAN DAN PEMASANGAN POMPA & WELLHEAD DAN ACCESORIS
RUMUS
No. URAIAN
area x pjg. x lebar x tinggi x sisi = volume sat
A Beton K-225
2 Sloof 15x20 1.00 x 0.15 x 0.20 x 4.00 = 0.12 m3
Kolom praktis 15/15 0.15 x 0.15 x 2.30 x 4.00 = 0.21 m3
Ring balk dan balok latai 1.00 x 0.15 x 0.20 x 4.00 = 0.12 m3
Plat Atap t : 12 cm 2.00 x 2.00 x 0.10 x 1.00 = 0.40 m3
Plat listplank 4.00 0.30 0.10 1.00 0.12 m3
total volume beton k-225 = 0.85 m3
RUMUS
No. URAIAN
dia kg/m x pjg. x jml x sisi = volume sat
B Pembesian
Sloof 15x20 10 0.617 x 1.00 x 4.00 x 4.00 = 9.86 kg
6 0.222 x 0.69 x 7.00 x 4.00 = 4.29 kg
= 14.15 kg
Kolom praktis 15/15 tul. Utama 10 0.617 x 2.75 x 4.00 x 4.00 = 27.13 kg
begel 6 0.222 x 0.02 x 15.00 x 4.00 = 0.29 kg
= 27.42 kg
Ring balok 15/20 10 0.617 x 1.00 x 4.00 x 4.00 = 9.86 kg
6 0.222 x 0.69 x 7.00 x 4.00 = 4.29 kg
= 14.15 kg
Plat atap t : 10cm x 10 0.617 x 4.16 x 10.00 x 1.00 = 25.65 kg
y 10 0.617 x 4.16 x 10.00 x 1.00 = 25.65 kg
= 51.29 kg
Plat listplank t : 10cm x 8 0.395 x 0.40 x 27.00 x 1.00 = 4.26 kg
y 8 0.395 x 4.00 x 4.00 x 1.00 = 6.31 kg
= 10.57 kg
total volume Pembesian = 117.59 kg
RUMUS
No. URAIAN
area x pjg. x lebar x tinggi x sisi = volume sat
C Begesting
Sloof 4.00 x 0.40 x 1.00 = 1.60 m2
Kolom praktis 15/15 2.30 x 0.30 x 4.00 = 2.76 m2
Ring balok 15/20 dan balok latai 4.00 x 0.40 x 1.00 = 1.60 m2
Plat atap 2.00 x 2.00 x x 1.00 = 4.00 m2
Plat listplank 4.00 x x 0.50 x 1.00 2.00 m2
BILL OF QUANTITY (BQ)
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
SUB KEGIATAN : PENINGKATAN SPAM JARINGAN PERPIPAAN DI KAWASAN PERDESAAN
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
SUMBER ANGGARAN : APBN - DAK TA. 2021
SUB PEKERJAAN : PENGADAAN DAN PEMASANGAN PIPA & SAMBUNGAN RUMAH
SUB TOTAL -
BILL OF QUANTITY (BQ)
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
SUB KEGIATAN : PENINGKATAN SPAM JARINGAN PERPIPAAN DI KAWASAN PERDESAAN
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
TAHUN ANGGARAN : APBN - DAK TA. 2021
SUB PEKERJAAN : SISTIM MANAJEMEN KESELAMATAN DAN KESEHATAN KERJA ( SMK 3 )
HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SATUAN JUMLAH (Rp)
(Rp)
SUB TOTAL -
BASK UP PERHITUNGAN VOLUME PEKERJAAN MENARA AIR
RUMUS
No. URAIAN
area x pjg. x lebar x tinggi x sisi = volume sat
A Beton K-250
1 Poor t : 40cm 1.25 x 1.25 x 0.40 x 4.00 = 2.50 m3
2 Strouss p=3 0.07 3.00 4.00 = 0.85 m3
3 Sloof 30x40 2.65 x 0.30 x 0.40 x 4.00 = 1.27 m3
20x30 2.70 x 0.20 x 0.30 x 1.00 = 0.16 m3
4 Kolom 35x35 4.00 x 0.35 x 0.35 x 4.00 = 1.96 m3
5 Balok 25x40 2.65 x 0.25 x 0.40 x 4.00 = 1.06 m3
20x30 2.65 x 0.20 x 0.30 x 2.00 = 0.32 m3
balok latai 15x20 1.20 x 0.15 x 0.20 x 1.00 = 0.04 m3
6 Plat Lantai t : 20 cm 3.35 x 3.35 x 0.20 x 1.00 = 2.24 m3
7 Dinding t : 15 cm 1.88 x 1.88 x 0.15 x 4.00 = 2.12 m3
8 Atap resevoir t : 12 cm 3.35 x 3.35 x 0.12 x 1.00 = 1.35 m3
9 Kolom Praktis 0.11 x 0.11 x 2.60 x 2.00 = 0.06 m3
total volume beton = 13.93 m3
RUMUS
No. URAIAN
dia kg/m x pjg. x jml x sisi = volume sat
B Pembesian
1 Poor t : 40cm x 12 0.89 x 3.10 x 8.00 x 4.00 = 88.07 kg
y 12 0.89 x 3.30 x 8.00 x 4.00 = 93.75 kg
= 181.81 kg
2 Strouss p=3 12 0.89 x 3.55 x 6.00 x 4.00 = 75.64 kg
8 0.395 x 0.73 x 24.00 x 4.00 = 27.58 kg
103.21 kg
3 Sloof 30x40 tul. Utama 12 0.888 x 2.65 x 12.00 x 4.00 = 112.92 kg
begel 8 0.395 x 1.29 x 18.00 x 4.00 = 36.65 kg
= 149.57 kg
20x30 tul. Utama 10 0.617 x 2.65 x 6.00 x 1.00 = 9.80 kg
begel 8 0.395 x 1.29 x 18.00 x 1.00 = 9.16 kg
= 18.96 kg
4 Kolom 35x35 tul. Utama 12 0.888 x 4.48 x 12.00 x 4.00 = 190.90 kg
begel 8 0.395 x 1.30 x 30.00 x 4.00 = 61.55 kg
= 252.46 kg
5 Balok 25x40 tul. Utama 12 0.888 x 2.65 x 10.00 x 4.00 = 94.10 kg
begel 8 0.395 x 1.17 x 21.00 x 4.00 = 38.78 kg
= 132.88 kg
20x30 tul. Utama 10 0.617 x 2.65 x 6.00 x 2.00 = 19.60 kg
begel 6 0.222 x 0.87 x 18.00 x 2.00 = 6.95 kg
= 26.56 kg
Balok latai pin 15/20 tul. Utama 10 0.617 x 1.20 x 4.00 x 1.00 = 2.96 kg
begel 6 0.222 x 1.03 x 8.00 x 1.00 = 1.83 kg
= 4.79 kg
6 Plat Lantai x 10 0.617 x 6.75 x 17.00 x 1.00 = 70.74 kg
y 10 0.617 x 6.75 x 17.00 x 1.00 = 70.74 kg
= 141.49 kg
7 Dinding x 10 0.617 x 3.86 x 9.00 x 4.00 = 85.67 kg
y 10 0.617 x 3.86 x 9.00 x 4.00 = 85.67 kg
= 171.34 kg
8 Atap resevoir x 10 0.617 x 6.70 x 17.00 x 1.00 = 70.22 kg
y 10 0.617 x 6.70 x 17.00 x 1.00 = 70.22 kg
= 140.44 kg
9 Kolom Praktis 11/11 tul. Utama 10 0.617 x 3.24 x 4.00 x 2.00 = 15.98 kg
begel 6 0.222 x 0.39 x 22.00 x 2.00 = 3.81 kg
19.79 kg
total volume Pembesian = 1,343.29 kg
RUMUS
No. URAIAN
area x pjg. x lebar x tinggi x sisi = volume sat
C Begesting
Sloof 30x40 2.65 x x 0.80 x 4.00 = 8.48 m2
20x30 2.70 x x 0.60 x 1.00 = 1.62 m2
Kolom 35x35 1.40 x x 4.00 x 4.00 = 22.40 m2
Balok 25x40 2.65 x x 1.05 x 4.00 = 11.13 m2
20x30 2.70 x x 0.80 x 2.00 = 4.32 m2
Balok Latai 15/20 1.20 x x 0.40 x 1.00 = 0.48 m2
Plat Lantai t : 20 cm 3.35 x 3.35 x x 1.00 = 11.01 m2
Dinding t : 15 cm 1.88 x 3.35 x x 4.00 = 24.98 m2
Atap resevoir t : 12 cm 3.05 x 3.05 x x 1.00 = 9.30 m2
Kolom Praktis 11/11 0.22 x x 2.60 x 2.00 = 1.14 m2
RENCANA ANGGARAN BIAYA
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
SUMBER ANGGARAN : APBN - DAK TA. 2021
SUB PEKERJAAN : PEMBANGUNAN MENARA AIR
HARGA SATUAN
NO. URAIAN PEKERJAAN VOLUME SATUAN (Rp) JUMLAH (Rp)
1 m3 Pekerjaan Aanstamping
(AHSP) Bahan :
2020 Batu belah (15/20) 1.2000 m3 - -
Pasir urug 0.4320 m3 - -
Upah :
Pekerja 0.7800 Oh - -
Tukang batu 0.3900 Oh - -
Kepala tukang 0.0390 Oh - -
Mandor 0.0390 Oh - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
1 m2 Pekerjaan Acian
(AHSP) Bahan :
2020 Semen / PC 3.2500 kg - -
Upah :
Pekerja 0.2000 Oh - -
Tukang batu 0.1000 Oh - -
Kepala tukang 0.0100 Oh - -
Mandor 0.0100 Oh - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
1 m2 Pekerjaan Pengecatan Tembok Baru untuk interior 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup
(AHSP) Bahan :
2020 Plamir dinding 0.1000 kg - -
Cat dasar interior 0.1000 kg - -
Cat penutup 0.2600 kg - -
Upah :
Pekerja 0.0200 Oh - -
Tukang Cat 0.0630 Oh - -
Kepala Tukang 0.0063 Oh - -
Mandor 0.0030 Oh - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
1 m2 Pekerjaan Pengecatan Tembok Baru untuk exterior 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup
(AHSP) Bahan :
2020 Plamir dinding 0.1000 kg - -
Cat dasar exterior 0.1000 kg - -
Cat penutup exterior 0.2600 kg - -
Upah :
Pekerja 0.0200 Oh - -
HARGA JUMLAH HARGA SAT.
SUMBER URAIAN PEKERJAAN VOL. SAT.
Rp. Rp. Rp.
Tukang Cat 0.0630 Oh - -
Kepala Tukang 0.0063 Oh - -
Mandor 0.0030 Oh - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 32 mm ( 1" ) - SC. S12.5 Tanah biasa
Galian Tanah Biasa 0.1200 m3 - -
Urugan Tanah Kembali 0.1100 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
HARGA JUMLAH HARGA SAT.
SUMBER URAIAN PEKERJAAN VOL. SAT.
Rp. Rp. Rp.
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 32 mm ( 1" ) - SC. S12.5 Tanah Keras
Galian Tanah Keras 0.1200 m3 - -
Urugan Tanah Kembali 0.1100 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 50 mm ( 1.5" ) - SC. S12.5 Tanah biasa
Galian Tanah Biasa 0.1200 m3 - -
Urugan Tanah Kembali 0.1100 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 50 mm ( 1" ) - SC. S12.5 Tanah Keras
Galian Tanah Keras 0.1200 m3 - -
Urugan Tanah Kembali 0.1100 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 63 mm ( 2" ) - SC. S12.5 Tanah biasa
Galian Tanah Biasa 0.1800 m3 - -
Urugan Tanah Kembali 0.1779 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 63 mm ( 2" ) - SC. S12.5 Tanah Keras
Galian Tanah Keras 0.1800 m3 - -
Urugan Tanah Kembali 0.1779 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 75 mm ( 2.5" ) - SC. S12.5 Tanah biasa
Galian Tanah Biasa 0.1800 m3 - -
Urugan Tanah Kembali 0.1770 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 75 mm ( 2.5" ) - SC. S12.5 Tanah Keras
Galian Tanah Keras 0.1800 m3 - -
Urugan Tanah Kembali 0.1770 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 90 mm ( 3" ) - SC. S12.5 Tanah biasa
Galian Tanah Biasa 0.2400 m3 - -
Urugan Tanah Kembali 0.2357 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa PVC dia. 90 mm ( 3" ) - SC. S12.5 Tanah Keras
Galian Tanah Keras 0.2400 m3 - -
Urugan Tanah Kembali 0.2357 m3 - -
Pengadaan dan Pemasangan pipa & Acc 1.0000 m' - -
Jumlah - -
HARGA JUMLAH HARGA SAT.
SUMBER URAIAN PEKERJAAN VOL. SAT.
Rp. Rp. Rp.
1 m' Pengadaan dan pemasangan pipa HDPE dia. 50 mm ( 1.5" ) Galian Tanah Biasa
Galian Tanah Biasa 0.0800 m3 - -
Urugan Tanah Kembali 0.0787 m3 - -
Pengadaan dan Pemasangan pipa hdpe 50 mm 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa HDPE dia. 50 mm ( 1.5" ) Galian Tanah Keras
Galian Tanah Keras 0.0800 m3 - -
Urugan Tanah Kembali 0.0787 m3 - -
Pengadaan dan Pemasangan pipa hdpe 50 mm 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa HDPE dia. 63 mm ( 2" ) Galian Tanah Biasa
Galian Tanah Biasa 0.1200 m3 - -
Urugan Tanah Kembali 0.1157 m3 - -
Pengadaan dan Pemasangan pipa hdpe 63 mm 1.0000 m' - -
Jumlah - -
1 m' Pengadaan dan pemasangan pipa HDPE dia. 63 mm ( 2" ) Galian Tanah Keras
HARGA JUMLAH HARGA SAT.
SUMBER URAIAN PEKERJAAN VOL. SAT.
Rp. Rp. Rp.
Galian Tanah Keras 0.1200 m3 - -
Urugan Tanah Kembali 0.1157 m3 - -
Pengadaan dan Pemasangan pipa hdpe 63 mm 1.0000 m' - -
Jumlah - -
Upah :
Pekerja 0.6500 Oh - -
Tukang 0.6500 Oh - -
Kepala Tukang 0.0650 Oh - -
Mandor 0.0320 Oh - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
(Perhitungan) 1 m' buah Pasang tangga stainless stell Ø 1.25 " dengan anak tangga Ø 1"
Bahan :
Pipa Stainless stell Ø 32 mm 2.000 m' - -
Pipa Stainless stell Ø 25 mm 1.200 m' - -
Pengelasan 1.206 cm - -
Angkur baut 2.000 bh - -
Upah :
Pekerja 0.650 Oh - -
Tukang Besi 0.650 Oh - -
Kepala Tukang 0.065 Oh - -
Mandor 0.032 Oh - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
Upah :
Pekerja 3.2000 Oh - -
Tukang Batu 1.1500 Oh - -
Kepala Tukang 0.0110 Oh - -
Mandor 0.0160 Oh - -
HARGA JUMLAH HARGA SAT.
SUMBER URAIAN PEKERJAAN VOL. SAT.
Rp. Rp. Rp.
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
Upah :
Tenaga trampil elctro 1.0000 ls - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
Upah :
Pekerja 0.3000 Oh - -
Tukang 0.5000 Oh - -
Kepala Tukang 0.0500 Oh - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
Upah :
Pekerja 0.0010 Oh - -
Tukang 0.0500 Oh - -
Kepala Tukang 0.0200 Oh - -
Jumlah -
Overhead + Profit (15%) -
Nilai HSPK - -
ANALISA HARGA SATUAN SUMUR BOR
Peralatan :
Sewa Truk 3.5 Ton 2.000 Hari - -
Jumlah Rp. 0.00
Overhead + Profit (15%) Rp. 0.00
Harga Satuan Pekerjaan Rp. 0.00
JUMLAH Rp -
SUB ANALISA RENCANA ANGGARAN BIAYA PENGADAAN DAYA LISTRIK 6600 W, 380 V 3 PHASE
NO URAIAN PEKERJAAN SAT VOL HRG SATUAN TOTAL BIAYA
1 Biaya Penyambungan Ls 1.00 Rp - Rp -
2 Token Perdana Ls 1.00 Rp - Rp -
3 Pajak Penerangan Jalan Ls 1.00 Rp - Rp -
4 PPn Ls 1.00 Rp - Rp -
5 Konversi Token Ls 1.00 Rp - Rp -
6 Materai Ls 1.00 Rp - Rp -
7 SLO Ls 1.00 Rp - Rp -
8 Biaya lain - lain Ls 1.00 Rp - Rp -
TOTAL Rp -
Overhead + Profit (15%) Rp -
JUMLAH Rp -
DIBULATKAN Rp -
DAFTAR HARGA SATUAN BAHAN BANGUNAN
PROGRAM : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM
KEGIATAN : PENGELOLAAN DAN PENGEMBANGAN SISTEM PENYEDIAAN AIR MINUM (SPAM) DI DAERAH KAB. / KOTA
SUB KEGIATAN : PENINGKATAN SPAM JARINGAN PERPIPAAN DI KAWASAN PERDESAAN
PEKERJAAN : PENAMBAHAN SUMUR DALAM TERLINDUNGI/BRONCAPTERING UNTUK DS. KLEPU KEC. SOOKO (DAK)
LOKASI : KAB. PONOROGO
TAHUN ANGGARAN : APBN - DAK TA. 2021
HARGA SATUAN
NO. URAIAN SATUAN
Rp.
HARGA SATUAN
NO. URAIAN SATUAN
Rp.
1 Kepala Tukang OH
2 Mandor OH
3 Operator OH
4 Tool pusher OH
5 Pembantu Operator OH
6 Pembantu Supir OH
7 Pekerja OH
8 Supir OH
9 Tukang Kayu OH
10 Tukang Batu OH
11 Tukang Besi OH
12 Tukang Las OH
13 Tukang Cat OH
14 Tukang Pipa OH
15 Tukang Gali sumur OH
16 Tenaga Ahli elektro pasang panel pompa OH
HARGA SATUAN
NO. URAIAN SATUAN
Rp.