Jumlah
Harga Satuan
No Uraian Pekerjaan Analis Vol Sat Harga
(Rp)
(Rp)
I PEKERJAAN DIGESTER BIOGAS 20 m3 (5 UNIT)
A PERSIAPAN
1 Survei dan pengukuran LS 5,00 Hok 410.000,00 2.050.000,00
2 Pemasangan Pengaman bangunan LS 30,00 m2 75.000,00 2.250.000,00
3 Operasional pompa LS 25,00 Hari 75.000,00 1.875.000,00
JUMLAH A 6.175.000,00
B PEKERJAAN TANAH
1 Pembersihan Lahan A153 225,00 m2 49.755,00 11.194.875,00
2 Galian tanah A006 279,25 m3 79.680,00 22.250.640,00
3
3 Pasir urug A020A 9,35 m 269.850,00 2.523.097,50
4 Urugan tanah A014 57,85 m3 20.805,00 1.203.569,25
5 Buang galian tanah A013B 221,40 m3 35.625,00 7.887.375,00
JUMLAH B 45.059.556,75
C PEKERJAAN PASANGAN DAN PLESTERAN
1 Lantai Kerja 1:3:5 A024 9,35 m3 929.725,00 8.692.928,75
2 Pas. beton bertulang 1:2:3 A026A 23,10 m3 5.881.680,00 135.866.808,00
3 Pasangan 1/2 batu bata 1 pc : 4 ps A067 128,55 m2 145.878,25 18.752.649,04
2
4 Plesteran 1:4 A075 128,55 m 127.305,00 16.365.057,75
5 Plesteran 1:2,5 kedap gas T.02 70,15 m2 62.325,00 4.372.098,75
6 Acian A073 Ac 128,55 m2 36.543,75 4.697.699,06
JUMLAH C 188.747.241,35
D PERLENGKAPAN
1 Pipa PVC AW Ø 4" A141E 20,00 m' 158.571,00 3.171.420,00
2 Pipa PVC AW Ø 3/4" A141A 100,00 m' 35.081,50 3.508.150,00
3 Pipa PVC AW Ø 1/2" A141 250,00 m' 21.257,50 5.314.375,00
4 Instalasi Kompor biogas 1 kran T.03B 25,00 bh 465.000,00 11.625.000,00
5 Instalasi Lampu biogas T.03A 10,00 bh 465.000,00 4.650.000,00
6 Pemasangan Water Drain T.03C 5,00 bh 162.600,00 813.000,00
7 Pemasangan Pipa Utama T.03D 5,00 m' 253.050,00 1.265.250,00
8 Pemasangan bak Inlet dan Mixer T.03E 5,00 bh 573.500,00 2.867.500,00
9 Manometer T.03 25,00 bh 330.000,00 8.250.000,00
JUMLAH D 41.464.695,00
JUMLAH I (A+B+C+D) 281.446.493,10
3
II PEKERJAAN DIGESTER BIOGAS 10 m (1 UNIT)
A PERSIAPAN
1 Survei dan pengukuran LS 1,00 Hok 410.000,00 410.000,00
2 Pemasangan Pengaman bangunan LS 4,00 m2 75.000,00 300.000,00
3 Operasional pompa LS 3,00 Hari 75.000,00 225.000,00
JUMLAH A 935.000,00
B PEKERJAAN TANAH
1 Pembersihan Lahan A153 13,00 m2 49.755,00 646.815,00
2 Galian tanah A006 19,65 m3 79.680,00 1.566.016,38
3 Pasir urug A020A 1,52 m3 269.850,00 410.539,00
4 Urugan tanah A014 5,60 m3 20.805,00 116.508,00
5 Buang galian tanah A013B 14,05 m3 35.625,00 500.667,34
JUMLAH B 3.240.545,71
Jumlah
Harga Satuan
No Uraian Pekerjaan Analis Vol Sat Harga
(Rp)
(Rp)
C PEKERJAAN PASANGAN DAN PLESTERAN
1 Lantai Kerja 1:3:5 A024 0,74 m3 929.725,00 684.026,57
2 Pas. beton bertulang 1:2:3 A026A 2,20 m3 5.881.680,00 12.946.276,42
3 Pasangan 1/2 batu bata 1 pc : 4 ps A067 16,76 m2 145.878,25 2.444.525,60
4 Plesteran 1:4 A075 16,76 m2 127.305,00 2.133.288,08
5 Plesteran 1:2,5 kedap gas T.02 6,04 m2 62.325,00 376.136,36
6 Acian A073 Ac 16,76 m2 36.543,75 612.374,58
JUMLAH C 19.196.627,62
D PERLENGKAPAN
1 Pipa PVC AW Ø 4" A141E 4,00 m' 158.571,00 634.284,00
2 Pipa PVC AW Ø 1/2" A141 30,00 m' 21.257,50 637.725,00
3 Instalasi Kompor biogas 1kran T.03B 3,00 bh 465.000,00 1.395.000,00
4 Pemasangan Water Drain T.03C 1,00 bh 162.600,00 162.600,00
5 Pemasangan Pipa Utama T.03D 1,00 m' 253.050,00 253.050,00
6 Pemasangan bak Inlet dan Mixer T.03E 1,00 bh 573.500,00 573.500,00
7 Manometer T.03 3,00 bh 330.000,00 990.000,00
JUMLAH D 4.646.159,00
JUMLAH II (A+B+C+D) 28.018.332,33
III BIAYA SISTEM MANAGEMEN K3 LS 1,00 Paket 1.750.000,00 1.750.000,00
SUB TOTAL (I+II+III) 311.214.825,43
PPN 10% 31.121.482,54
TOTAL 342.336.307,97
DIBULATKAN 342.336.000,00
Terbilang:
PT/CV .........................
......................................
.....................
ANALISA HARGA SATUAN PEKERJAAN
PT/CV .........................
......................................
.....................
RINCIAN BIAYA SISTEM MANAGEMEN K3
PT/CV .........................
......................................
.....................
HARGA SATUAN BAHAN DAN UPAH
HARGA
NO JENIS BAHAN SATUAN
(Rp)
A HARGA SATUAN BAHAN
1 Batu bata merah buah 1.000,00
2 Besi beton kg 18.000,00
3 Bambu btg 20.000,00
4 Kawat beton kg 17.000,00
5 Kayu meranti m3 2.600.000,00
6 Keramik lantai warna anti slip 20x20 m2 62.500,00
7 Kompor Biogas 1 Kran bh 250.000,00
8 Lampu Biogas bh 250.000,00
9 Manometer bh 150.000,00
10 Mikser bh 250.000,00
11 Paku kg 17.000,00
12 Pasir Beton m3 300.000,00
13 Pasir pasang m3 300.000,00
14 Pasir uruk m3 200.000,00
15 Papan cor m3 1.500.000,00
16 Pipa PVC Ø 1/2" m' 5.990,00
17 Pipa PVC Ø 3/4" m' 8.930,00
18 Pipa PVC Ø 4" m' 97.500,00
19 PC 50 kg zak 61.250,00
20 Split 1-2 cm pecah mesin m3 350.000,00
21 Tricosal lt 60.000,00
22 Plywood 9 mm lb 145.000,00
24 Minyak Begisting Lt 3.000,00
25 Kran Air bh 26.000,00
26 Stop Kran 1/2 bh 93.000,00
27 Sewa Dump Truk + Bahan Bakar Hari 475.000,00
28 Biaya angkat tanah ke Dump Truck m3 6.875,00
29 Alat Bantu Ls 200,00
30 Survei dan pengukuran Ls 410.000,00
31 Pemasangan Pengaman bangunan Ls 75.000,00
32 Operasinal pompa Ls 75.000,00
33 Pengadaan APD (Alat Pelindung Diri) Paket 1.500.000,00
34 Kotak P3K dan isinya Paket 250.000,00
B HARGA SATUAN UPAH
1 Pekerja OH 95.000,00
2 Mandor OH 135.000,00
3 Tukang batu OH 125.000,00
4 Kepala tukang batu OH 135.000,00
5 Tukang besi OH 125.000,00
6 Tukang kayu OH 125.000,00
7 Kepala tukang kayu OH 135.000,00
8 Pembantu Tenaga Ahli OH 40.000,00
9 Tenaga Semi Ahli OH 50.000,00
10 Tenaga Ahli OH 60.000,00
11 Sopir Truk OH 100.000,00
......................................
.....................