1 PEKERJAAN TANAH
A.2.3.1.1 PENGGALIAN 1 M3 TANAH BIASA SEDALAM 1 METER M3 62.920,00
Dihit 1 PENGGALIAN 1 M' BORE PILE MENGGUNAKAN ALAT M' 104.737,60
Dihit 2 PENGURUGAN 1 M3 DENGAN TANAH PADAT M3 154.770,00
A.2.3.1.9 PENGURUGAN KEMBALI 1 M3 GALIAN TANAH M3 15.179,99
A.2.3.1.11 PENGURUGAN 1 M3 DENGAN ABU BATU M3 249.964,00
2 PEKERJAAN PONDASI
A.3.2.1.5 PEMASANGAN 1 M3 PONDASI BATU BELAH HITAM, CAMPURAN 1 PC : 8 PB M3 809.267,47
8 PEKERJAAN KACA
A.4.6.2.17 PEMASANGAN 1 M² KACA BENING TEBAL 5 MM M2 195.756,99
A.4.6.2.18 PEMASANGAN 1 M² KACA RAYBAND TEBAL 5 MM M2 234.509,99
9 PEKERJAAN LANGIT-LANGIT
Dihit 18 PEMASANGAN 1 M² LANGIT - LANGIT GYPSUM BOARD UKURAN (120x240x9) MM, TEBAL 9 MM M2 177.217,15
Dihit 19 PEMASANGAN 1 M² LANGIT - LANGIT KALSIBOARD UKURAN (120x240x4) MM, TEBAL 4 MM M2 167.834,15
Dihit 20 PEMASANGAN 1 M' LIST GYPSUM LEBAR 10 cm M' 26.375,25
1
NO KODE SATUAN PEKERJAAN SAT HARGASATUAN
A.4.7.1.10 PENGECATAN 1 M² BIDANG TEMBOK BARU (1 LAPIS PLAMUUR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) M2 23.175,08
A.4.7.1.16 PENGECATAN 1 M² PERMUKAAN BAJA DENGAN MENIE BESI M2 28.693,50
Dihit 21 PENGECATAN 1 M² BIDANG WATERPROOFING M2 22.319,28
Dihit 22 PENGECATAN 1 M² BIDANG MENGGUNAKAN CAT MINYAK M2 36.386,08