Anda di halaman 1dari 170

HARGA SATUAN PEKERJAAN

WILAYAH KOTA BANJAR

TAHUN ANGGARAN 2020

KODE
NO ITEM SATUAN PEKERJAAN HARGA SATUAN
ANALIS SNI

I PEKERJAAN PERSIAPAN

1 A.2.2.1.4. 1 M' PENGUKURAN DAN PEMASANGAN BOUPLANK 63,549.00

2 A.2.2.1.8. 1 M2 PEKERJAAN MEMBERSIHKAN LAPANGAN DAN PERATAAN 16,675.00

3 A.2.2.1.10. 1 BUAH PEMBUATAN BAK ADUKAN, UKURAN (40 x 50 x 25) cm 136,896.00

4 A.2.2.1.11. 1 M2 PEMBUATAN STEGGER DARI BAMBU 38,887.25

5 A.2.2.1.12. 1 M2 PEMBUATAN JALAN SEMENTARA 293,997.50

6 A.2.2.1.13. 1 M3 BONGKARAN BETON BERTULANG 1,395,306.50

7 A.2.2.1.14. 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH 69,765.33

8 A.2.2.1.17. 1 M2 BONGKARAN PLESTERAN DINDING 8,337.50

9 A.2.2.1.18. 1 M2 BONGKARAN GENTENG 18,400.00

10 A.2.2.1.19. 1 M2 BONGKARAN RANGKA ATAP /RENG+KASO 13,800.00

11 A.2.2.1.20. 1 M3 BONGKARAN KUDA-KUDA, GORDING /BALOK 780,850.00

12 A.2.2.1.21. 1 m2 BONGKARAN PLAFOND 12,908.75

II PEKERJAAN PELAKSANAAN

A PEKERJAAN TANAH

1 A.2.3.1.1. PENGGALIAN 1M3 TANAH BIASA SEDALAM 1 M' 76,762.50

2 A.2.3.1.2. PENGGALIAN 1M3 TANAH BIASA SEDALAM 2 M' 94,185.00

3 A.2.3.1.3. PENGGALIAN 1M3 TANAH BIASA SEDALAM 3 M' 111,883.50

4 A.2.3.1.4. PENGGALIAN 1M3 TANAH KERAS SEDALAM 1 M' 102,166.00

5 A.2.3.1.5. PENGGALIAN 1M3 TANAH CADAS SEDALAM 1 M' 154,905.00

6 A.2.3.1.6. PENGGALIAN 1M3 TANAH LUMPUR SEDALAM 1 M' 123,510.00

7 A.2.3.1.7. MENGERJAKAN 1M2 STRIPPING TEBING SETINGGI 1 M 5,577.50

8 A.2.3.1.8. PEMBUANGAN 1 M3 TANAH SEJAUH 30 M 33,637.50

9 A.2.3.1.8.1 1 M3 PEMBUANGAN TANAH SEJAUH 100 METER 62,790.00

10 A.2.3.1.9. PENGURUGAN KEMBALI 1 M3 GALIAN 55,775.00

11 A.2.3.1.10. 1 m3 PEMADATAN TANAH (PER 20 CM) 55,775.00

12 A.2.3.1.11. PENGURUGAN 1 M3 PASIR URUG 148,005.00

13 A.2.3.1.14. PENGURUGAN 1M3 SIRTU PADAT 165,887.50

B PEKERJAAN PONDASI

1 A.3.2.1.1. PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP : 3 PP 780,591.25

2 A.3.2.1.2. PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP : 4 PP 731,802.50


3 A.3.2.1.2.1 PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP : 4 PP 773,662.50

4 A.3.2.1.9. 1 M3 PASANGAN PONDASI BATU KOSONG (ANSTAMPING) 353,038.50

C PEKERJAAN BETON

1 A.4.1.1.1. 1 M3 BETON UNTUK LANTAI KERJA ( BEDDING) 828,639.65

2 D.02 1 M3 BETON 1 PC : 2 PB : 3KR MANUAL 867,836.00

3 D-03 1 M3 BETON 1 PC : 2 PB : 3 KR MOLEN 892,342.50

4 D-04 1 M3 BETON 1 PC : 3 PB : 5 KR MANUAL 872,838.50

5 D-05 1 M3 BETON 1 PC : 3 PB : 5 KR MOLEN 897,345.00

6 A.4.1.1.7. 1 M3 BETON F'c = 7,4 Mpa (K100), SLUMP (12±2), W/C=0,87 MOLEN 924,817.68

7 A.4.1.1.9. 1 M3 BETON F'c = 9,8 Mpa (K125), SLUMP (12±2), W/C=0,78 MOLEN 960,872.76

8 A.4.1.1.11. 1 M3 BETON F'c = 12,2 Mpa (K150), SLUMP (12±2), W/C=0,72 MOLEN 988,968.51

9 A.4.1.1.13. 1 M3 BETON F'c = 14,5 Mpa (K175), SLUMP (12±2), W/C=0,66 MOLEN 1,022,383.77

10 A.4.1.1.14. 1 M3 BETON F'c = 14,5 Mpa (K175), SLUMP (12±2), W/C=0,66 READIMIX + POMPA 1,468,297.00

11 A.4.1.1.16. 1 M3 BETON F'c = 16,9 Mpa (K200), SLUMP (12±2), W/C=0,61 MOLEN 1,054,018.96

12 A.4.1.1.17. 1 M3 BETON F'c = 16,9 Mpa (K200), SLUMP (12±2), W/C=0,61 READYMIX+POMPA 1,516,597.00

13 A.4.1.1.19. 1 M3 BETON F'c = 19,3 Mpa (K225), SLUMP (12±2), W/C=0,58 MOLEN 1,078,156.03

14 A.4.1.1.20. 1 M3 BETON F'c = 19,3 Mpa (K225), SLUMP (12±2), W/C=0,58 READYMIX+POMPA 1,589,047.00

15 A.4.1.1.22. 1 M3 BETON F'c = 21,7 Mpa (K250), SLUMP (12±2), W/C=0,56 MOLEN 1,093,533.48

16 A.4.1.1.23. 1 M3 BETON F'c = 21,7 Mpa (K250), SLUMP (12±2), W/C=0,56 READYMIX+POMPA 1,589,047.00

17 A.4.1.1.25. 1 M3 BETON F'c = 24 Mpa (K275), SLUMP (12±2), W/C=0,53 MOLEN 1,120,009.64

18 A.4.1.1.26. 1 M3 BETON F'c = 24 Mpa (K275), SLUMP (12±2), W/C=0,53 READYMIX+POMPA 1,649,422.00

19 A.4.1.1.28. 1 M3 BETON F'c = 26,4 Mpa (K300), SLUMP (12±2), W/C=0,52 MOLEN 1,128,188.18

20 A.4.1.1.29. 1 M3 BETON F'c = 26,4 Mpa (K300), SLUMP (12±2), W/C=0,52 READYMIX+POMPA 1,649,422.00

21 A.4.1.1.31. 1 M3 BETON F'c = 28,8 Mpa (K325), SLUMP (12±2), W/C=0,49 MOLEN 1,203,727.94

22 A.4.1.1.32. 1 M3 BETON F'c = 28,8 Mpa (K325), SLUMP (12±2), W/C=0,49 READYMIX+POMPA 1,729,565.50

23 A.4.1.1.34. 1 M3 BETON F'c = 31,2 Mpa (K350), SLUMP (12±2), W/C=0,48 MOLEN 1,214,466.29

24 A.4.1.1.35. 1 M3 BETON F'c = 31,2 Mpa (K350), SLUMP (12±2), W/C=0,48 READYMIX+POMPA 1,777,865.50

25 A.4.1.1.38. PEMAKAIAN VIBRATOR PADA PENGECORAN BETON/M3 53,187.50

26 A.4.1.1.17.1 PEMBESIAN 1 KG BESI POLOS ATAU ULIR 16,465.13

27 A.4.1.1.18.1 PEMBESIAN 1 KG JARING KAWAT BAJA (WIREMESH) 21,155.98

28 A.4.1.1.20.1 1 m2 PASANG BEKISTING UNTUK PONDASI 178,112.00

29 DIHITUNG 1 m2 PASANG BEKISTING UNTUK PONDASI (2x PAKAI) 133,607.00

30 A.4.1.1.21.1 1 m2 PASANG BEKISTING UNTUK SLOOF 188,462.00

31 DIHITUNG 1 m2 PASANG BEKISTING UNTUK SLOOF (2x PAKAI) 147,062.00

32 A.4.1.1.22.1 1 m2 PASANG BEKISTING UNTUK KOLOM 293,052.20

33 DIHITUNG 1 m2 PASANG BEKISTING UNTUK KOLOM (2X PAKAI) 215,855.00

34 A.4.1.1.23.1 1 m2 PASANG BEKISTING UNTUK BALOK 299,262.20

35 DIHITUNG 1 m2 PASANG BEKISTING UNTUK BALOK (2X PAKAI) 219,305.00

36 A.4.1.1.24.1 1 m2 PASANG BEKISTING PLAT LANTAI 329,889.00

37 DIHITUNG 1 m2 PASANG BEKISTING PLAT LANTAI (2X PAKAI) 231,955.00

38 A.4.1.1.25.1 1 m2 PASANG BEKISTING PLAT TANGGA 276,989.00


10 D-50 1 m2 PASANG JEMBATAN UNTUK PENGECORAN 99,601.50

8 DIHITUNG 1 m3 MEMBUAT PLAT BETON T = 7 CM 6,090,694.28

DIHITUNG 1 m3 MEMBUAT PLAT BETON T = 7 CM 5,493,482.18

9 DIHITUNG 1 m3 MEMBUAT PLAT BETON T = 10 CM 4,845,083.89

10 DIHITUNG 1 m3 MEMBUAT PLAT BETON T = 15 CM 6,634,803.30

DIHITUNG 1 m3 MEMBUAT BALOK BETON BERTULANG 20/30 3,059,931.90

DIHITUNG 1 m3 MEMBUAT BALOK BETON BERTULANG 25/60 4,176,226.75

DIHITUNG 1 m3 MEMBUAT KOLOM BETON BERTULANG 15/15 6,399,744.67

DIHITUNG 1 m3 MEMBUAT KOLOM BETON BERTULANG 20/20 4,603,622.92

D PEKERJAAN DINDING

1 E-01 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 2 Ps 289,800.00

2 A.4.4.1.2. 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 3 Ps 276,822.25

3 A.4.4.1.3. 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 4 Ps 268,277.75

4 A.4.4.1.4. 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 5 Ps 263,568.50

5 E-07 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 2 Ps 140,748.50

6 A.4.4.1.8. 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 Ps 134,715.60

7 A.4.4.1.9. 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 4 Ps 131,186.25

8 A.4.4.1.10. 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 Ps 128,962.15

A.4.4.1.25. 1 m2 PASANGAN DINDING BATA RINGAN TEBAL 7,5 CM DENGAN MORTAR SIAP PAKAI 674,440.28

A.4.4.1.26. 1 m2 PASANGAN DINDING BATA RINGAN TEBAL 10 CM DENGAN MORTAR SIAP PAKAI 672,504.69

8 Dihitung 1 m2 PASANGAN DINDING GLASS BOX (20X20X10) cm

E PEKERJAAN PLESTERAN

1 F-02 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 15 mm 68,389.12

2 A.4.4.2.3. PEMASANGAN 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 15 mm 65,442.13

1 A.4.4.2.4. PEMASANGAN 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 15 mm 63,466.20

2 A.4.4.2.5. PEMASANGAN 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 15 mm 62,296.42

2 A.4.4.2.26. PEMASANGAN 1 m2 FINISHING SIAR PASANGAN BATU KALI, 1 PC : 2 Ps 61,879.20

3 A.4.4.2.27. PEMASANGAN 1 m2 ACIAN 38,755.00

F PEKERJAAN KAYU

A.4.6.1.2. 1 M3 MEMBUAT DAN MEMASANG KUSEN PINTU DAN KUSEN JENDELA, KAYU KELAS II ATAU III 6,780,975.00

A.4.6.1.5. 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PANEL, KAYU KELAS I ATAU II 664,470.00

A.4.6.1.6. 1 M2 MEMBUAT DAN MEMASANG PINTU DAN JENDELA KACA, KAYU KELAS I ATAU II 499,652.00

A.4.6.1.23. 1 M2 MEMASANG RANGKA DINDING PEMISAH (60x120) cm, KAYU KELAS II ATAU III 165,841.50

G PEKERJAAN PENUTUP ATAP

A.4.5.2.1. 1 m2 PASANG ATAP GENTENG PALENTONG KECIL 94,771.50

A.4.5.2.3. 1 m2 PASANG ATAP GENTENG PALENTONG SUPER / BESAR 23,770.50

A.4.5.2.4. 1 m1 PASANG GENTENG BUBUNG PALENTONG 191,521.00

A.4.5.2.6. 1 m' PASANG BUBUNG GENTENG PALENTONG BESAR 81,696.00

A.4.5.2.32. 1 m2 PASANG ATAP GENTENG METAL UKURAN 80 x 100 ATAP PELANA 242,730.50

A.4.5.2.33. 1 m2 PASANG ATAP GENTENG METAL UKURAN 80 x 100 ATAP JURAI 353,418.00
A.4.5.2.33. 1 m' PASANG NOK GENTENG METAL 152,651.00

PEK. SANITASI

1 A.5.1.1.21. PEMASANGAN 1 M' PIPA GALVANIS Ø 1" 21,010.50

2 A.5.1.1.22. PEMASANGAN 1 M' PIPA GALVANIS Ø 1 1/2" 35,259.00

3 A.5.1.1.23. PEMASANGAN 1 M' PIPA GALVANIS Ø 3" 44,240.50

4 A.5.1.1.25. PEMASANGAN 1 M' PIPA PVC type AW Ø 1/2" 23,830.88

5 A.5.1.1.26. PEMASANGAN 1 M' PIPA PVC type AW Ø 3/4" 27,395.88

6 A.5.1.1.27. PEMASANGAN 1 M' PIPA PVC type AW Ø 1" 31,852.13

7 A.5.1.1.28. PEMASANGAN 1 M' PIPA PVC type AW Ø 1 1/2" 51,120.38

8 A.5.1.1.33. PEMASANGAN 1 M' PIPA AIR LIMBAH JENIS PIPA TANAH Ø 20 CM 448,722.33

1 P.16 MEMASANG 1 METER PIPA SULING-SULING Ø 1 1/2" 30,920.63

A.5.1.1.32 PEMASANGAN 1 METER PIPA PVC Ø 4" 31,083.75

PEKERJAAN BESI DAN ALUMINIUM

1 A.4.2.1.1. 1 Kg PASANG BESI PROFIL 34,120.50

PEKERJAAN PENUTUP LANTAI

1 A.4.4.3.64. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 6 CM 189,641.90

2 A.4.4.3.66. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 6 CM 102,529.40

PEKERJAAN PENGECATAN

1 A.4.7.1.10. PENGECATAN 1 m2 TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup) 23,239.20

PEKERJAAN JALAN

1 AN.01 1 TON PENGHAMPARAN LATASTON ( HRS - WC ) 1,498,506.11

2 K.516 1 M2 LAPIS PONDASI BAWAH ( LPB ) KONSTRUKSI TELFORD 71,408.10

3 K.521 1 M3 LAPIS PONDASI ATAS KLAS A AGREGAT PECAH TERSARING ( MENGGUNAKAN BURUH ) 356,556.35

4 K.618 1 M2 LAPIS PENETRASI / PERMUKAAN MACADAM 50 MM LAPEN ( MENGGUNAKAN BURUH ) 101,880.80

5 K.618.1 1 M2 LAPIS PENETRASI / PERMUKAAN MACADAM 50 MM LAPEN ( MENGGUNAKAN BURUH ) TANPA SC 100,040.80

6 K.422 PEMBERSIHAN SEMAK DLL PADA BAHU JALAN ( MENGGUNAKAN BURUH ) 12,370.17

7 K.424 PEMBERSIHAN PARIT ( MENGGUNAKAN BURUH ) 10,350.92

8 AN. 18 1 M2 LAPIS PEREKAT 15,095.03

9 K.880 PERBAIKAN LUBANG ( 10 CM ) JALAN ASPAL 57,061.11


DAFTAR HARGA UPAH
KOTA Banjar
TAHUN 2020

No JENIS TENAGA KERJA SATUAN

1 Pekerja HOK
2 Pekerja (setengah terampil) HOK
3 Pekerja ( terampil) HOK
4 Tukang Gali HOK
5 Tukang Batu ( setengah terampil) HOK
5 Tukang Batu ( terampil) HOK
6 Kepala Tukang Batu HOK
8 Tukang Kayu ( setengah terampil) HOK
7 Tukang Kayu ( terampil) HOK
8 Kepala Tukang Kayu HOK
9 Tukang Cat / Plitur ( setengah terampil) HOK
9 Tukang Cat / Plitur ( terampil) HOK
10 Kepala Tukang Cat / Plitur HOK
11 Tukang Besi Beton ( terampil) HOK
12 Kepala Tukang Besi Beton HOK
13 Tukang Besi Frofil ( setengah terampil) HOK
13 Tukang Besi Frofil ( terampil) HOK
14 Kepala Tukang Besi Frofil HOK
15 Mandor HOK
16 Operator Alat Besar HOK
17 Pembantu Operator / Mekanik HOK
18 Supir Truk HOK
19 Kenek Truk / Pembantu Supir Truk HOK
20 Penjaga Malam HOK
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

A. AGREGAT KASAR, BAHAN PEREKAT DAN BAHAN JADINYA


1 Abu Batu m3
2 Tanah Urug m3
2 Tanah Liat m3
3 Sirtu ( tersaring bergradasi ) m3
3 Pasir Urug /Bawah lantai m3
4 Pasir Pasang /gunung pilihan m3
4 Pasir pasang gunung m3
5 Pasir Pasang kali m3
5 Pasir Beton m3
6 Batu Belah m3
6 Batu Pecah ( tersaring bergradasi ) m3
7 Batu Pecah 0,5/1 ( Screen ) m3
7 Batu Pecah 1/2 m3
8 Batu Pecah 2/3 m3
8 Batu Pecah 3/5 m3
9 Batu Pecah 5/7 m3
9 Batu Pecah 10/15 m3
10 Batu Tempel Hitam ( yang beraturan ) m2
10 Batako Kecil ( 8x10x20 ) bh
11 Batako Besar ( 8x20x30 ) bh
11 Hollow Block 15 cm (HB-15) /batako lubang bh
12 Hollow Block 20 cm (HB-20) /batako lubang bh
12 Teracotta 10 cmx20 cm bh
13 Bata Merah bh
13 Bata Ringan Tebal 7,5cm m3
14 Roster Genteng 10cm x 20cm ( Klingker ) bh
14 Roster Genteng 20cm x 20cm ( Klingker ) bh
15 Roster Beton 20cm x 20cm bh
15 Roster Beton 30cm x 30cm bh
16 Grass Block Natural 6 cm m2
16 Grass Block Warna 6 cm m2
17 Grass Block Natural 8 cm m2
17 Grass Block Warna 8 cm m2
18 Paving Block Natural 6 cm ( Cisangkan )* m2
18 Paving Block Natural 6 cm ( Setempat ) m2
19 Paving Block Warna 6 cm ( Cisangkan )* m2
19 Paving Block Warna 6 cm ( Setempat ) m2
20 Paving Block Natural 8 cm ( Cisangkan )* m2
20 Paving Block Natural 8 cm ( Setempat ) m2
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

21 Paving Block Warna 8 cm ( Cisangkan )* m2


21 Paving Block Warna 8 cm ( Setempat ) m2
22 Tegel Badak 30x30 Natural m2
22 Tegel Badak 30x30 Warna m2
23 Kanstin Taman Ukuran 11x20 cm - p=0,40 m' (Press) bh
23 Kanstin Jalan Ukuran 11x20 cm - p=0,50 m' (Std. Bina Marga /Cor) bh
24 Kanstin Jalan Ukuran 11x40 cm - p=0,50 m' (Std. Bina Marga /Cor) bh
24 Kanstin Jalan Ukuran 11x20-40 cm (Trapesium) p=0,50 m' (Std. Bina Marga /Cor) bh
25 Semen Portland ( PC ) /50 Kg (H) Zak
25 Semen Portland (PC) Putih Zak
26 Semen Warna Kg
Semen Instan /MU-380 Kg
26 Sewa Molen 0,35 M3 hari
27 Redymix Beton K-300 , tanpa pompa ( Selang ) m3
27 Redymix Beton K-175 (14,5 MPa) m3
28 Redymix Beton K-200 (16,9 MPa) m3
28 Redymix Beton K-225 (19,3 MPa) m3
29 Redymix Beton K-250 (21,7 MPa) m3
29 Redymix Beton K-275 (24 MPa) m3
30 Redymix Beton K-300 (26,4 MPa) m3
30 Redymix Beton K-325 (28,8 MPa) m3
31 Redymix Beton K-350 (31,2 MPa) m3
31 Sewa Vibrator Pengecoran/ Hari
32 Sewa Pompa < 20 m3/M3
32 Sewa Mesin Potong Besi hari
<100 m3
Penambahan lebih dari 100 M3
33 Kapur pasang ( 1 Karung = 25 Kg ) m3
34 Urugan Pilihan m3

B. BAHAN PENGIKAT KONSTRUKSI JALAN


1 Aspal Bitumen Kg
2 Aspal Congcrete (AC-BC) /Laston ton
3 Aspal Congcrete (AC-WC) /Laston #
4 HRS ( Hot Rolled Sheet ) /Lataston ton
5 ATB ( Aspalt Treatment Base ) ton
6 AC. Base ton
2 Minyak Tanah liter
3 Kayu Bakar m3

B. BAHAN LOGAM DAN BAHAN JADINYA


DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

1 Besi Plat Kg
1 Besi Beton (ukuran rata rata) Kg
Besi Ø 6 Lente
Besi Ø 8 Lente
Besi Ø 10 Lente
Besi Ø 12 Lente
Besi Ø 13 Lente
2 Besi Profil Kg
3 Pagar BRC lengkap tiang ( tanpa pondasi t=90 cm) lbr
4 Pagar BRC lengkap tiang ( tanpa pondasi t=90 cm) lbr
5 Pagar BRC lengkap tiang ( tanpa pondasi t=180 cm) m2
6 Bondek m2
7 IWF Ex DN SII Kg
8 WireMesh 6 mm kg
9 WireMesh 7 mm m2
10 DOP 2.5" Bh
3 Kawat Beton Kg
4 Kawat Duri m'
5 Kawat Harmonika 4cm m2
6 Kawat Ram 1x1 cm m2
7 Kawat Boronjong Ø 3 mm Kg
8 Kawat Boronjong Ø 4 mm Kg
9 Kawat Las Listrik Kg
10 Kawat Tembaga Kg
11 Timah ( L=1 m x Tebal=1 mm ) /12 Kg Kg
12 Seng Plat BJLS 30 L= 60 cm (p=100 m) rool
13 Seng Plat BJLS 30 L= 90 cm (P=100 m) rool
14 Seng Plat BJLS 28 " lbr
15 Sikat Kawat bh
16 Plat Besi Tipis 0.50 mm
17 Plat Besi Tipis 1 mm
18 Plat Besi Tipis 2 mm s/d 5 mm
19 Plat Besi Tipis 6 mm s/d 10 mm
20 Plat Besi Tipis 10 mm keatas
21 Pintu besi baja ( termasuk rel dan kunci )
22 Lem Kuning ( Setara AICA AIBON, FOX ) Kg
23 Lem Fox Kg
24 Bronjong Kawat D3mm (1,00x0,5x2,00) Bh
25 Bronjong Kawat D4mm (1,00x0,5x2,00) Bh
26 Bronjong Kawat D5mm (1,00x0,5x2,00) Bh
27 Rangka Atap Baja Ringan m2
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

28 Besi Gril Berikut Pengelasan Kg


29 Pagar Kawat Jaring Lbr

C. BAHAN SALURAN AIR KOTOR /BERSIH


1 Grefel U-20 cm m'
2 Grefel U-30 cm m'
3 Grefel U-40 cm m'
4 Buis Beton Ø 20 cm ( 1 m') m'
5 Buis Beton Ø 30 cm ( 1 m') m'
6 Buis Beton Ø 40 cm ( 1 m') m'
7 Buis Beton Ø 50 cm ( 0,5 m') m'
8 Buis Beton Ø 60 cm ( 0,5 m') bh (0.5m1)
9 Buis Beton Ø 70 cm ( 0,5 m') bh (0.5m1)
10 Buis Beton Ø 80 cm ( 0,5 m') bh (0.5m1)
11 Buis Beton Ø 100 cm ( 0,5 m') bh (0.5m1)
4 Ijuk KG

D. BAHAN PERPIPAAN
1 Besi Pipa untuk Hydrant BSP Ø 1" btg
2 Besi Pipa untuk Hydrant BSP Ø 1,25" btg
3 Besi Pipa untuk Hydrant BSP Ø 1,5" btg
4 Besi Pipa untuk Hydrant BSP Ø 2" btg
1 Pipa Galvanis Ø 1/2" btg
2 Pipa Galvanis Ø 3/4" btg
1 Pipa Galvanis Ø 1" btg
2 Pipa Galvanis Ø 1 1/4" btg
2 Pipa Galvanis Ø 1 1/2" btg
2 Pipa Galvanis Ø 2" btg
3 Pipa Galvanis Ø 2 1/2" btg
3 Pipa Galvanis Ø 3" btg
4 Pipa Galvanis Ø 4" btg
5 Pipa Ø 1-1/4" Black Steel /SII btg
6 Pipa Ø 2" Black Steel /SII btg
7 Pipa Ø 3" Black Steel /SII btg
8 Pipa Ø 6" Black Steel /SII btg
1 Pipa PVC Ø 1/2" ( Setara Rucika ) btg
2 Pipa PVC Ø 3/4" ( Setara Rucika ) btg
3 Pipa PVC Ø 1" ( Setara Rucika ) btg
4 Pipa PVC Ø 1 1/2" ( Setara Rucika ) btg
5 Pipa PVC Ø 2" ( Setara Rucika ) btg
6 Pipa PVC Ø 2 1/2" ( Setara Rucika ) btg
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

7 Pipa PVC Ø 3" ( Setara Rucika ) btg


8 Pipa PVC Ø 4" btg
9 Pipa PVC Ø 6" ( Setara Rucika ) btg
5 Pipa PVC Ø 8" Type aw btg
Sambungan Pipa PVC Ø 4"
6 Sambungan Pipa PVC Ø 8" bh
7 Knee Pipa PVC Ø 8" bh
10 Talang 4 M' btg
11 Gantungan Plat bh
12 Gantungan Plastik bh
13 Pipa PVC Diameter 20 mm/ Ø 1/2 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
14 Pipa PVC Diameter 25 mm/ Ø 3/4 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
15 Pipa PVC Diameter 32 mm/ Ø 1 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
16 Pipa PVC Diameter 40 mm/ Ø 1 1/4 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
17 Pipa PVC Diameter 50 mm/ Ø 1 1/2 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
18 Pipa PVC Diameter 63 mm/ Ø 2 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
19 Pipa PVC Diameter 75 mm/ Ø 2 1/2 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
20 Pipa PVC Diameter 90 mm/ Ø 3 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
21 Pipa PVC Diameter 110 mm/ Ø 4 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
22 Pipa PVC Diameter 140 mm/ Ø 5 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
23 Pipa PVC Diameter 160 mm/ Ø 6 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
24 Pipa PVC Diameter 200 mm/ Ø 8 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
25 Pipa PVC Diameter 225 mm/ Ø 8 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
26 Pipa PVC Diameter 250 mm/ Ø 10 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
27 Pipa PVC Diameter 315 mm/ Ø 12 " ( Setara Pralon P.6 m S.10 Plain End/Ts. End ) btg
28 Pipa PVC Diameter 63 mm/ Ø 2 " ( Setara Pralon P.6 m S.10 Bell End ) btg
29 Pipa PVC Diameter 75 mm/ Ø 2 1/2 " ( Setara Pralon P.6 m S.10 Bell End ) btg
30 Pipa PVC Diameter 90 mm/ Ø 3 " ( Setara Pralon P.6 m S.10 Bell End ) btg
31 Pipa PVC Diameter 110 mm/ Ø 4 " ( Setara Pralon P.6 m S.10 Bell End ) btg
32 Pipa PVC Diameter 140 mm/ Ø 5 " ( Setara Pralon P.6 m S.10 Bell End ) btg
33 Pipa PVC Diameter 160 mm/ Ø 6 " ( Setara Pralon P.6 m S.10 Bell End ) btg
34 Pipa PVC Diameter 200 mm/ Ø 8 " ( Setara Pralon P.6 m S.10 Bell End ) btg
35 Pipa PVC Diameter 225 mm/ Ø 8 " ( Setara Pralon P.6 m S.10 Bell End ) btg
36 Pipa PVC Diameter 250 mm/ Ø 10 " ( Setara Pralon P.6 m S.10 Bell End ) btg
37 Pipa PVC Diameter 315 mm/ Ø 12 " ( Setara Pralon P.6 m S.10 Bell End ) btg
38 Pipa PVC Diameter 355 mm/ Ø 14 " ( Setara Pralon P.6 m S.10 Bell End ) btg
39 Pipa PVC Diameter 400 mm/ Ø 16 " ( Setara Pralon P.6 m S.10 Bell End ) btg
40 Pipa PVC Diameter 500 mm/ Ø 20 " ( Setara Pralon P.6 m S.10 Bell End ) btg
41 Pipa PVC Diameter 630 mm/ Ø 24 " ( Setara Pralon P.6 m S.10 Bell End ) btg
42 Pipa PVC Diameter 63 mm/ Ø 2 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
43 Pipa PVC Diameter 75 mm/ Ø 2 1/2 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

44 Pipa PVC Diameter 90 mm/ Ø 3 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
45 Pipa PVC Diameter 110 mm/ Ø 4 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
46 Pipa PVC Diameter 140 mm/ Ø 5 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
47 Pipa PVC Diameter 160 mm/ Ø 6 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
48 Pipa PVC Diameter 200 mm/ Ø 8 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
49 Pipa PVC Diameter 225 mm/ Ø 8 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
50 Pipa PVC Diameter 250 mm/ Ø 10 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
51 Pipa PVC Diameter 315 mm/ Ø 12 " ( Setara Pralon P.6 S.12,5 Plain End/Ts. End) btg
52 Pipa PVC Diameter 63 mm/ Ø 2 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
53 Pipa PVC Diameter 75 mm/ Ø 2 1/2 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
54 Pipa PVC Diameter 90 mm/ Ø 3 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
55 Pipa PVC Diameter 110 mm/ Ø 4 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
56 Pipa PVC Diameter 140 mm/ Ø 5 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
57 Pipa PVC Diameter 160 mm/ Ø 6 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
58 Pipa PVC Diameter 200 mm/ Ø 8 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
59 Pipa PVC Diameter 225 mm/ Ø 8 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
60 Pipa PVC Diameter 250 mm/ Ø 10 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
61 Pipa PVC Diameter 315 mm/ Ø 12 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
62 Pipa PVC Diameter 355 mm/ Ø 14 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
63 Pipa PVC Diameter 400 mm/ Ø 16 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
64 Pipa PVC Diameter 500 mm/ Ø 20 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
65 Pipa PVC Diameter 630 mm/ Ø 24 " ( Setara Pralon P.6 m S.12,5 Bell End ) btg
66 Ts. Faucet Socket (Inj) Ø 1/2" x 1/2" bh
67 Ts. Faucet Socket (Inj) Ø 1/4" x 1/4" bh
68 Ts. Faucet Socket (Inj) Ø 1" x 1" bh
69 Ts. Faucet Elbow (Inj) Ø 1/2" x 1/2" bh
70 Ts. Faucet Elbow (Inj) Ø 1/4" x 1/4" bh
71 Ts. Faucet Elbow (Inj) Ø 1" x 1" bh
72 Ts. Faucet Tee (Inj) Ø 1/2" x 1/2" bh
73 Ts. Faucet Tee (Inj) Ø 1/4" x 1/4" bh
74 Ts. Faucet Tee (Inj) Ø 1" x 1" bh
75 Ts. Valve Socket (Inj) Ø 1/2" bh
76 Ts. Valve Socket (Inj) Ø 3/4" bh
77 Ts. Valve Socket (Inj) Ø 1" bh
78 Ts. Valve Socket (Inj) Ø 1 1/4" bh
79 Ts. Valve Socket (Inj) Ø 1 1/2" bh
80 Ts. Valve Socket (Inj) Ø 2" bh
81 Ts. Valve Socket (Inj) Ø 2 1/2" bh
82 Ts. Valve Socket (Inj) Ø 3" bh
83 Ts. Valve Socket (Inj) Ø 4" bh
84 Bell Cap (Inj- Heat Process) Ø 2" bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

85 Bell Cap (Inj- Heat Process) Ø 3" bh


86 Bell Cap (Inj- Heat Process) Ø 4" bh
87 Bell Cap (Inj- Heat Process) Ø 5" bh
88 Bell Cap (Inj- Heat Process) Ø 8" bh
89 Bell Cap (Inj- Heat Process) Ø 10" bh
90 Bell Cap (Inj- Heat Process) Ø 12" bh
91 Bell Cap (Inj- Heat Process) Ø 14" bh
92 Bell Cap (Inj- Heat Process) Ø 16" bh
93 Dresser Joint (C.l + PVC Body ) Ø 2" bh
94 Dresser Joint (C.l + PVC Body ) Ø 3" bh
95 Dresser Joint (C.l + PVC Body ) Ø 4" bh
96 Dresser Joint (C.l + PVC Body ) Ø 6" bh
97 Dresser Joint (C.l + PVC Body ) Ø 8" bh
98 Dresser Joint (C.l + PVC Body ) Ø 10" bh
99 Dresser Joint (C.l + PVC Body ) Ø 12" bh
100 Dresser Joint (C.l + PVC Body ) Ø 14" bh
101 Dresser Joint (C.l + PVC Body ) Ø 16" bh
102 Ts. Socket - W (Heat Process) Ø 1/2" bh
103 Ts. Socket - W (Heat Process) Ø 3/4" bh
104 Ts. Socket - W (Heat Process) Ø 1" bh
105 Ts. Socket - W (Heat Process) Ø 1 1/4" bh
106 Ts. Socket - W (Heat Process) Ø 1 1/2" bh
107 Ts. Socket - W (Heat Process) Ø 2" bh
108 Ts. Socket - W (Heat Process) Ø 2 1/2" bh
109 Ts. Socket - W (Heat Process) Ø 3" bh
110 Ts. Socket - W (Heat Process) Ø 4" bh
111 Ts. Cap (Inj) Ø 1/2" bh
112 Ts. Cap (Inj) Ø 3/4" bh
113 Ts. Cap (Inj) Ø 1" bh
114 Ts. Cap (Inj) Ø 1 1/4" bh
115 Ts. Cap (Inj) Ø 1 1/2" bh
116 Ts. Cap (Inj) Ø 2" bh
117 Ts. Cap (Inj) Ø 2 1/2" bh
118 Ts. Cap (Inj) Ø 3" bh
119 Ts. Cap (Inj) Ø 4" bh
120 Ts. Cap (Inj) Ø 6" bh
121 Ts. Cap (Inj) Ø 8" bh
122 Ts. Cap (Inj) Ø 10" bh
123 Vc. Socket - W (Heat Process) Ø 3" (10 Kg/cm2) bh
124 Vc. Socket - W (Heat Process) Ø 4" (10 Kg/cm2) bh
125 Vc. Socket - W (Heat Process) Ø 5" (10 Kg/cm2) bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

126 Vc. Socket - W (Heat Process) Ø 6" (10 Kg/cm2) bh


127 Vc. Socket - W (Heat Process) Ø 8" (10 Kg/cm2) bh
128 Vc. Socket - W (Heat Process) Ø 10" (10 Kg/cm2) bh
129 Vc. Socket - W (Heat Process) Ø 12" (10 Kg/cm2) bh
130 Bell Va Socket (Heat Process) Ø 2" (10 Kg/cm2) bh
131 Bell Va Socket (Heat Process) Ø 3" (10 Kg/cm2) bh
132 Bell Va Socket (Heat Process) Ø 4" (10 Kg/cm2) bh
133 Bell Va Socket (Heat Process) Ø 5" (10 Kg/cm2) bh
134 Bell Va Socket (Heat Process) Ø 6" (10 Kg/cm2) bh
135 Bell Va Socket (Heat Process) Ø 8" (10 Kg/cm2) bh
136 Bell Va Socket (Heat Process) Ø 10" (10 Kg/cm2) bh
137 Bell Va Socket (Heat Process) Ø 12" (10 Kg/cm2) bh
138 Spicot Bell End (Heat Process) Ø 2" (10 Kg/cm2) bh
139 Spicot Bell End (Heat Process) Ø 3" (10 Kg/cm2) bh
140 Spicot Bell End (Heat Process) Ø 4" (10 Kg/cm2) bh
141 Spicot Bell End (Heat Process) Ø 5" (10 Kg/cm2) bh
142 Spicot Bell End (Heat Process) Ø 6" (10 Kg/cm2) bh
143 Spicot Bell End (Heat Process) Ø 8" (10 Kg/cm2) bh
144 Spicot Bell End (Heat Process) Ø 10" (10 Kg/cm2) bh
145 Spicot Bell End (Heat Process) Ø 12" (10 Kg/cm2) bh
146 Spicot Bell End (Heat Process) Ø 14" (10 Kg/cm2) bh
147 Spicot Bell End (Heat Process) Ø 16" (10 Kg/cm2) bh
148 Spicot Bell End (Heat Process) Ø 20" (10 Kg/cm2) bh
149 Spicot Bell End (Heat Process) Ø 24" (10 Kg/cm2) bh
150 Spicot Bell End (Heat Process) Ø 2" (5 Kg/cm2) bh
151 Spicot Bell End (Heat Process) Ø 3" (5 Kg/cm2) bh
152 Spicot Bell End (Heat Process) Ø 4" (5 Kg/cm2) bh
153 Spicot Bell End (Heat Process) Ø 5" (5 Kg/cm2) bh
154 Spicot Bell End (Heat Process) Ø 6" (5 Kg/cm2) bh
155 Spicot Bell End (Heat Process) Ø 8" (5 Kg/cm2) bh
156 Spicot Bell End (Heat Process) Ø 10" (5 Kg/cm2) bh
157 Spicot Bell End (Heat Process) Ø 12" (5 Kg/cm2) bh
158 Ts. Elbow (Inj) Ø 1/2" (10 Kg/cm2) bh
159 Ts. Elbow (Inj) Ø 3/4" (10 Kg/cm2) bh
160 Ts. Elbow (Inj) Ø 1" (10 Kg/cm2) bh
161 Ts. Elbow (Inj) Ø 1 1/4" (10 Kg/cm2) bh
162 Ts. Elbow (Inj) Ø 1 1/2" (10 Kg/cm2) bh
163 Ts. Elbow (Inj) Ø 2" (10 Kg/cm2) bh
164 Ts. Elbow (Inj) Ø 2 1/2" (10 Kg/cm2) bh
165 Ts. Elbow (Inj) Ø 3" (10 Kg/cm2) bh
166 Ts. Elbow (Inj) Ø 4" (10 Kg/cm2) bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

167 Ts. Elbow (Inj) Ø 6" (10 Kg/cm2) bh


168 Ts. Elbow (Inj) Ø 8" (10 Kg/cm2) bh
169 Ts. Tee (Inj) Ø 1/2" x 1/2" (10 Kg/cm2) bh
170 Ts. Tee (Inj) Ø 3/4" x 1/2" (10 Kg/cm2) bh
171 Ts. Tee (Inj) Ø 3/4" x 3/4" (10 Kg/cm2) bh
172 Ts. Tee (Inj) Ø 1" x 1/2" (10 Kg/cm2) bh
173 Ts. Tee (Inj) Ø 1" x 3/4" (10 Kg/cm2) bh
174 Ts. Tee (Inj) Ø 1" x 1" (10 Kg/cm2) bh
175 Ts. Tee (Inj) Ø 1 1/4" x 1" (10 Kg/cm2) bh
176 Ts. Tee (Inj) Ø 1 1/4" x 1 1/4" (10 Kg/cm2) bh
177 Ts. Tee (Inj) Ø 1 1/2" x 1" (10 Kg/cm2) bh
178 Ts. Tee (Inj) Ø 1 1/2" x 1 1/4" (10 Kg/cm2) bh
179 Ts. Tee (Inj) Ø 1 1/2" x 1 1/2" (10 Kg/cm2) bh
180 Ts. Tee (Inj) Ø 2" x 1/2" (10 Kg/cm2) bh
181 Ts. Tee (Inj) Ø 2" x 3/4" (10 Kg/cm2) bh
182 Ts. Tee (Inj) Ø 2" x 1" (10 Kg/cm2) bh
183 Ts. Tee (Inj) Ø 2" x 1 1/2" (10 Kg/cm2) bh
184 Ts. Tee (Inj) Ø 2" x 2" (10 Kg/cm2) bh
185 Ts. Tee (Inj) Ø 2 1/2" x 1 1/2" (10 Kg/cm2) bh
186 Ts. Tee (Inj) Ø 2 1/2" x 2" (10 Kg/cm2) bh
187 Ts. Tee (Inj) Ø 2 1/2" x 2 1/2" (10 Kg/cm2) bh
188 Ts. Tee (Inj) Ø 3" x 1 1/2" (10 Kg/cm2) bh
189 Ts. Tee (Inj) Ø 3" x 2" (10 Kg/cm2) bh
190 Ts. Tee (Inj) Ø 3" x 2 1/2" (10 Kg/cm2) bh
191 Ts. Tee (Inj) Ø 3" x 3" (10 Kg/cm2) bh
192 Ts. Tee (Inj) Ø 4" x 2" (10 Kg/cm2) bh
193 Ts. Tee (Inj) Ø 4" x 3" (10 Kg/cm2) bh
194 Ts. Tee (Inj) Ø 4" x 4" (10 Kg/cm2) bh
195 Ts. Tee (Inj) Ø 5" x 5" (10 Kg/cm2) bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

F. BAHAN FASILITAS PENGAIRAN


1 Karet Penyekat Air / Rubber Water Stop Lebar 150 Cm
2 Karet Penyekat Air / Rubber Water Stop Lebar 225 Cm
3 Lampu Senter
4 Rantai Kunci
5 Cangkul
6 Gacok
7 Mesin Babad Rumput Setara TANAKA
8 Parang
9 Sabuk Pengaman
10 Slang Inpet Pompa Air 2 "
11 Slang Inpet Pompa Air 4 "
12 Stempet
13 Takel ( Kapasitas 3 Ton )
14 Tambang Plastik
15 Mistar Ukuran Panjang 0.50 - 1.00 meter (feil schal)
16 Mistar Ukuran Panjang 1.00 - 1.50 meter (feil schal)
17 Mistar Ukuran Panjang 1.50 - 2.00 meter (feil schal)
18 Mistar Ukuran Panjang 2.00 - 3.00 meter (feil schal)
19 Mistar Ukuran Panjang 3.00 - 4.00 meter (feil schal)
20 Papan Nama Bangunan / Nomenklatur
21 Papan Nama Saluran
22 Papan Oprasi Bendung
23 Papan Exploitasi
24 Kotak Baja Penyimpan Data
25 Plat Tanda Muka Air / Peil Schaal
26 Patok Hektometer ( Pengairan )
27 Pintu Angkat Type 1.B = 0.30 meter
28 Pintu Angkat Type 1.B = 0.40 meter
29 Pintu Angkat Type 1.B = 0.50 meter
30 Pintu Angkat Type II.B = 0.30 meter
31 Pintu Angkat Type II.B = 0.40 meter
32 Pintu Angkat Type II.B = 0.50 meter
33 Pintu Sorong baja type 1A ukuran ( B=0.30-0.60)&(H=0.30-0.60 ) m
34 Pintu Sorong baja type 2A ukuran ( B=0.60-0.80)&(H=0.30-1.00 ) m
35 Pintu Sorong baja type 3A ukuran ( B=0.30-1.20)&(H=0.40-1.50 ) m
36 Pintu Sorong baja type 4A ukuran ( B=1.00-1.00)&(H=0.50-2.00 ) m
37 Pintu Sorong baja type 5A ukuran ( B=1.00-1.50)&(H=0.70-0.90 ) m
38 Pintu Sorong baja type 6A ukuran ( B=1.60-2.00)&(H=0.90-1.35 ) m
39 Pintu Sorong baja type 7A ukuran ( B=2.10-2.50)&(H=1.35-1.70 ) m
40 Pintu sorong baja type 2 draadstang ulir dengan 3 stel roda gigi b = 1.00 m;H=1.60 m
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

41 Pintu sorong baja type 2 draadstang ulir dengan 3 stel roda gigi b = 1.20 m;H=1.70 m
42 Pintu sorong baja type 2 draadstang ulir dengan 3 stel roda gigi b = 1.50 m;H=1.80 m
43 Pintu sorong baja type 2 draadstang ulir dengan 3 stel roda gigi b = 2.00 m;H=2.00 m
44 Pintu Skot Balk Jati Jateng
45 Pintu Skot Balk Jati Jabar
E. BAHAN KAYU BERIKUT BAHAN JADINYA
1 Bambu Diameter 5 s/d 7 cm btg
2 Bambu Diameter 7 s/d 10 cm btg
3 Bambu Gombong btg
4 Dolken 5 s.d 7 btg
5 Dolken 7 s.d 10 btg
6 Kayu Balok Borneo 6/12, 8/12, 8/15 * m3
7 Kayu Balok Borneo Super m3
8 Kayu Balok Damar Laut 6/12, 8/12, 8/15* m3
9 Kayu Balok Kamper Banjar 6/12, 8/12, 8/15* m3
10 Kayu Balok Kamper Medan ( Kruing ) m3
11 Kayu Balok Kamper Medan 6/12, 8/12, 8/15* m3
12 Kayu Balok Kamper Samarinda m3
13 Kayu Balok Kayu Gunung Klas II 6/12, 8/12, 8/15* m3
14 Kayu Balok Rasamala* m3
15 Kayu Jati Jabar Ø 40 CM ke bawah m3
16 Kayu Jati Jabar Tua Lepas Mata dari Ø 80 CM ke atas m3
17 Kayu Jati Jateng Tua Lepas Mata dari Ø 80 CM ke atas m3
18 Kayu Jati Jatim Lepas Mata dari Ø 80 CM ke atas m3
19 Kayu Kamper Singkil /Kapur ( Kamper Samarinda Kls II ) m3
20 Kayu Kaso 5/7, 5/10 Borneo* m3
21 Kayu Kaso 5/7, 5/10 Kamper Banjar* m3
22 Kayu Kaso 5/7, 5/10 Kamper Medan* m3
2 Kayu Kaso 5/7, 5/10 Kayu Gunung Klas II* m3
3 Kayu Klas II ( Cayur )* Sekelas Rasamala m3
1 Kayu Kaso, Kayu Gunung Klas III ( Albasia ) 4m* btg
2 Kayu Kaso, Kayu Gunung Klas III ( Albasia )* btg
2 Kayu Balok/Papan /Kayu Gunung Klas III ( Albasia )* m3
3 Kayu Bekisting m3
4 Kayu Papan Borneo* m3
5 Kayu Papan Damar Laut* m3
6 Kayu Papan Kamper Banjar* m3
7 Kayu Papan Kamper Medan ( Kruing ) m3
8 Kayu Papan Kamper Medan* m3
9 Kayu Papan Kamper Samarinda m3
10 Kayu Reng 2/3 Kamper Banjar m'
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

11 Kayu Reng 2/3 Kamper Medan m3


12 Kayu Stootwerk btg
13 List Profil Kamper 1 cm m'
14 List Profil Kamper 2 cm m'
15 List Profil Kamper 4 cm m'
16 List Profil Kamper 5 cm m'
17 List Profil Kamper 10 cm m'
18 List Profil Kayu Kelas II, 5 cm m'
19 Pegangan Tangga Profil Jati m'
20 Pegangan Tangga Profil Kamper m'
21 Batang kelapa (Ø 30cm p=6 m) btg

F. BAHAN PENUTUP RANGKA PLAFOND


1 Bahan Plapon Hardpleks 5 mm 120 x 240 cm lbr
2 GRC BOARD / GYPSUM Lbr
3 Eternit 1x1 M2 Lbr
4 Eternit 1x1 M2 peti
5 Gypsun 120 x 240 cm , t = 9 mm ex DN lbr
6 Gypsun 120 x 240 cm , t = 9 mm ex luar lbr
7 List Plafond Gypsum m'
8 Tepung Gypsum Kg
G. BAHAN KAYU LAPIS DAN DINDING PELAPIS
1 Fornika ukuran 120x240 cm Lbr
2 Jabar Wood 4 mm Lbr
3 Melamin 4 mm 120 x 240 Lbr
4 Multiplek 6 mm 120 x 240 Lbr
5 Multiplek 9 mm 120 x 240 Lbr
6 Multiplek 12 mm 120 x 240 Lbr
7 Multiplek 18 mm 120 x 240 Lbr
8 Plywood 4 mm 120 x 240 Lbr
9 Plywood 9mm 120 x 240 Lbr
10 Plywood 18 mm 120 x 240 Lbr
11 Teakwood 3 mm 120 x 240 Lbr
12 Teakwood 3 mm Uk/ Pintu Lbr
13 Teakwood 4 mm 120 x 240 Lbr
14 Teakwood 4 mm Uk/ Pintu Lbr
15 Triplek 3 mm 120 x 240 Lbr
16 Triplek 4 mm 120 x 240 Lbr
17 Bilik ( dengan kulit /Hinis ) m2
18 Bilik ( tanpa Kulit ) m2
19 Bilik ( corak khusus /Besar ) m2
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

20 Triplek 4 mm Uk/ Pintu Lbr


21 Kalsiboard (2,4x1,22) Lbr

H. BAHAN FINISHING : LABURAN, PENGISIAN DAN ALATNYA


1 Ampelas Lbr
2 Ampelas M
1 Cat Besi Kg
2 Cat Bron Kg
2 Cat Genting Kg
3 Cat Kayu stara AVIAN Kg
4 Cat Kayu stara SIEV Kg
5 Cat Kayu stara AMCO Kg
6 Cat Marka / Spotlight Kg
7 Cat Plincote Kg
8 Cat Soligneum Galon /5 Ltr
9 Cat Tahan Asam Kg
10 Cat Tembok setara ICI Eksterior Gall
11 Cat Tembok setara ICI interior ( Flapond & Dinding ) Gall
3 Cat Tembok setara Sanlex Gall
4 Cat Tembok setara Sanlex Kg
5 Cat Tembok setara Sanlex ( Putih ) Kg
6 Cat Tembok setara Metrolite Kg
7 Cat Tembok setara Mowilex exterior Kg
8 Cat Tembok setara Mowilex interior Kg
9 Cat Tembok setara Dulux exterior Kg
10 Cat Tembok setara Dulux interior Kg
11 Dempul Halus (Wood Filler) setara INFRA Kg
12 Dempul Kayu Kg
13 Kape Kayu Bh
14 Kape Tembok Bh
1 Kuas 2,5" Bh
5 Kuas 3 " bh
2 Kuas 4 " bh
3 Kumpon Kg
6 Meni Kayu /Besi Kg
7 Oker Coklat Kg
8 Oker Putih Kg
9 Plamir Cat Kg
7 Plamir Tembok Kg
8 Rol cat Tembok Bh
9 Sincromat Kg
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

10 Sirlak Ex India Kg
11 Spirtus Ltr
12 Terpentin Ltr
13 Tiner A Ltr
14 Tiner setara ND Ltr
15 Water Profing Emulision Kg
16 Vernis Kg

I. BAHAN KACA
1 Glass Block 20 x 20 ex DN bh
2 Glass Block 20 x 20 ex LN bh
3 Kaca Polos 2 mm m2
4 Kaca Polos 3 mm m2
5 Kaca Polos 5 mm m2
6 Kaca Ryben 5 mm m2
7 Kaca Ryben 8 mm m2

J. BAHAN PAKU DAN MUR-BAUT


1 Angker Mur Baut Ø19, panjang 60 cm bh
2 Baut /Mur Kg
3 Beugel Kuda-kuda Kg
4 Dak Angker Kg
5 Mur Baut 20 cm s/d 35 mm ( berikut ring ) bh
6 Mur Baut Biasa Ø 19 s/d 16 ( 15 cm ) bh
7 Mur Baut HTM Ø 19 s/d 16 cm bh
7 Paku (berbagai macam ukuran /rata-rata) Kg
8 Paku Beton 2 cm s/d 5 cm bh
9 Paku Cacing Kg
10 Paku Kait ( lengkap ) Bh
11 Piser Ø 12 s/d 20 cm bh
K. BAHAN SANITER
1 Bak fibreglass Bh
2 Closet Duduk Keramik LN ( lengkap ) Unit
1 Closet Duduk Setara TOTO CW421 Unit
2 Closet Jongkok Porselin Setara Toto CE7 bh
3 Closet Jongkok Porselin Warna bh
4 Floor Drain bh
5 Kran Bebek 1/2 " bh
6 Kitchen Zink Stailess Lengkap Sipon & Sparing bh
7 Kitchen Zink Stailess Standar lokal ( 1 Lobang ) bh
8 Kitchen Zink Stailess Non Standar franke ( 1 Lobang ) bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

9 Kitchen Zink Stailess Non Standar franke ( 2 Lobang ) bh


10 Kran Panas-Dingin ( standar ) bh
3 Kran Tembok 1/2 " bh
4 Kran Tembok 3/4 " bh
5 Penyekat Urinoir Lbr
4 Seal tape Set
5 Shower ( dengan tiang ) bh
6 Shower ( tanpa tiang ) bh
7 Stop kran 1 " setara KIT bh
8 Stop kran 1¼ " setara KIT bh
9 Tempat Sabun Porselin bh
10 Urinoir Warna Standar ( lengkap ) bh
11 Wastafel Bulat Warna Standar ( lengkap ) Unit
5 Wastafel setara merk TOTO LW 220J bh
6 Wastafel setara merk TOTO LW 220J ( lengkap ) bh
7 Water Thurn 500 liter (standar) Bh
8 Water Thurn 250 liter (standar) bh
9 Water Thurn 1000 liter (standar) Bh
10 Tangki Fiber Glass 3m3 Bh
11 Tangki Fiber Glass 10m3 # Bh
12 Tangki 3m3 PE # Bh
13 Tangki 6m3 PE # Bh

N. BAHAN PENUTUP ATAP


1 Aksesoris nat bh
2 Asbes Gelombang besar Lbr
1 Atap Asbes Gelombang Besar 5 mm 80 x 180 Lbr
1 Atap Asbes Gelombang Kecil 4 mm 80 x 180 Lbr
2 Atap Fiberglass ( datar ) /Roof light fibreglass Lbr
3 Atap Fiber Glass Tebal 90 x 180 ( Gelombang ) Lbr
4 Atap Fiber Glass Tipis 90 x 180 ( Gelombang ) Lbr
5 Atap Genteng Beton Warna 14,5/m2 m2
2 Atap Genteng Plentong m2
3 Atap Plastik 80 x 180 ( Gelombang ) Lbr
4 Atap Seng BJLS 28 /32 90 x 180 ( Gelombang ) Lbr
2 Bubung Asbes bh
3 Bubung Morando glasur bh
3 Bubung Morando natural bh
4 Bubungan Genteng Beton Pres bh
4 Bubungan Genteng Plentong bh
5 Genteng Palentong Kecil bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

7 Genteng Palentong Besar bh


6 Genteng Beton Pres bh
7 Genteng Cisangkan bh
8 Genteng Morando Glasur 18 bh/m2 bh
6 Genteng Morando Natural 18 bh/m2 bh
7 Genting Bubungan bh
Nok Genteng Metal bh
Genteng Metal (Kualitas Rainbowroof, Multiroof) Buah
8 Atap Fiber Setara Canopy m2

O. BAHAN MEKANIKAL & ELEKTRIKAL ( ME )


1 Arde /box schreeng Ls
2 Box Sikring In-bouw C4 bh
3 Box Sikring Out-bouw C1 + Patron Broco bh
4 BP dan UJL 1200 Watt + tiang 2 Bh Ls
5 BP dan UJL 1300 Watt Ls
6 #REF! #REF!
7 BP dan UJL 2200 Watt Ls
8 Canopy Impralon m2
9 Jarum Penangkal Petir 16 s.d19 Unit
10 Kawat Penagkal Petir ( Tembaga ) 16 Kg
11 Lampu Baret 30 cm + Neon Set
12 Lampu Dinding bh
13 Lampu Down Light sedang bh
14 Lampu Gantung Uk. Besar Unit
15 Lampu Gantung uk. Kecil Unit
16 Lampu Gantung uk. Sedang Unit
17 Lampu Hologin 500 Watt + Box bh
18 Lampu Mercury 60 Watt bh
19 Lampu Pijar 25 Watt bh
20 Lampu Pijar 40 Watt bh
21 Lampu SLE 5 Watt bh
22 Lampu SL 18 Watt bh
23 Lampu Sorot Philips 40 Watt bh
24 Lampu spot light 120 Watt / 150 Watt bh
25 Lampu spot light 300 Wattt bh
26 Lampu Tanam bh
27 Lampu TL 1 x 20 Watt bh
28 Lampu TL 1 x 40 Watt bh
29 Lampu TL 2 x 20 Watt bh
30 Lampu TL RM 2 x 20 Watt bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

31 Lampu TL RM 4 x 20 Watt bh
32 MLL 160 Watt bh
33 Panel LP-A bh
34 Panel LP-B bh
35 Panel LP-C bh
36 Panel LP-D bh
37 Panel LP-E bh
38 Panel SDP bh
39 Pasang telepon Ls
40 Saklar Ganda Broco bh
41 Saklar tunggal Broco bh
42 Stop kontak Broco bh
43 Tiang Listrik bh
44 Titik Cahaya Ttk
45 Trafo 80 Watt / 220 bh
46 Box Street bh
47 Genset STC 20 Kw Mesin Hopper Starter Setara Produk Cina bh
48 Genset STC 7,5 KW - Mesin 15,5 3 phase Hopper Starter, Setara Yanmar # bh
49 Kabel NYY 3x6,5mm m
50 Kabel NYY 3x10mm m

L. BAHAN ALAT PENGGANTUNG KUNCI


1 Engsel Jendela bh
2 Engsel Jendela setara UNION bh
3 Engsel Pintu bh
4 Engsel Pintu setara UNION bh
5 Espangnolet Psg
6 Grendel 15 cm bh
7 Grendel 5 cm bh
8 Hak Angin Biasa Psg
9 Hak Angin endok Stanless/Kuningan bh
10 Hak Angin Jendela Antik Psg
11 Hak Angin Kait Jendela Biasa Psg
12 Kunci 2 Slaag setara "ANCOR" / "ASTON" bh
13 Kunci tanam setara TESA bh
14 Kunci Gembok (lengkap) bh
15 Kunci tanam Antik bh
16 Kunci Kamar Bulat setara merk ALFA bh
17 Kunci Kamar Bulat setara Biasa bh
18 Kunci KM/WC setara Merk ALFA bh
19 Kunci Silinder setara ALFA untuk Pintu Alumunium bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

20 Kunci Slaag setaraANCOR ASLI bh


21 Kunci Slaag setara ISO bh
22 Kunci Slaag Silinder setara SEIS Asli Type 210 s.d 226 bh
23 Rel Henderson Lengkap bh
24 Rel Maraton 1 Pintu Unit
25 Slot Jendela bh
26 Slot Pintu Berikut Rantai Set
27 Kunci lemari bh
28 Tarikan Almari Rata - rata bh
29 Tarikan Pintu Almunium bh

Q. BAHAN PENGISAP SUMUR AIR DALAM


1 Depp Well dengan kelengkapannya Kap.150 Ltr/menit Unit
2 Gear Pump Kap./Menit Unit
3 Hand Oil pump Unit
4 Pompa setara Dragon Asli Unit
5 Pompa setara Dragon Tegal Unit
6 Pompa Jet-Pump 250 W setara SANYO Unit
7 Pompa Jet-Pump 450 W setara SANYO Unit
8 Pompa Kodok Unit
9 Pompa listrik 100 Watt setara "SANYO" Unit
10 Pompa listrik 125 Watt setara "SANYO" Unit
11 Pompa listrik 250 Watt setara "SANYO" Unit
12 Pompa listrik 500 Watt setara "SANYO" Unit
13 Pompa Sumbersible Kap 150 Liter/menit 3 KW Unit
14 Pompa Sentripugal Kap 20L/D Head 65M Unit

C. ALAT TUKANG
1 Cangkul bh
2 Karbit Kg
3 Linggis bh
4 Palu bh
5 Pengki bh
6 Rool Meter 30 Meter ( Bahan besi ) bh
7 Rool Meter 5 Meter ( Bahan besi ) bh
8 Singkup bh
9 Slang Plastik untuk Water Pas di.0.5cm m'
10 Water Pass Alumunium bh
11 Ember bh
12 Gacok bh
13 Gergaji bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

D. STANDAR SEWA ALAT BERAT, TRUK, KENDARAAN RODA EMPAT, DLL


1 Aspalt Finisher Jam
2 Aspalt Miixing Plant Jam
3 Aspalt mileting Kalte Jam
1 Aspalt Spayer Jam
2 Exavator Backoe ( Short ) Jam
3 Exavator Backoe ( Long ) Jam
4 Buldozer 100 - 150 HP( E.04 ) Jam
5 Concrete Mixer 0.125 M3 Jam
6 Concrete Mixer 0.3-0.6 m ( E. 06 ) Jam
7 Concrete Vibrator ( E.20 ) Jam
2 Tree Wheel Roller Jam
3 Tandam Roller 6-8 Ton Jam
3 Tire Roller 8-10 Ton Jam
4 Roller Vibrator 5-8 Ton Jam
5 Pedestrian Roller Jam
6 Roller Pneumatic 8-15 Ton Jam
7 Wheel Loader 1-1,6 m3 Jam
8 Crane 10 15 Ton Jam
9 Genset Jam
10 Draklint Jam
11 Track Loader 75 100 HP Jam
12 Motor Grader 100 HP Jam
13 Pneumatic Drill Hammer Jam
14 Ship Foot Roller Jam
15 Stone Crusher Jam
16 Teractor Equipnment Jam
17 Screening Plent Jam
18 Spreyer,Self - Proop 1001 Jam
19 Tamper, Viberator Plate Jam
20 Crusher / SCB Jam
21 Concerate Viberator Jam
22 Pick Up Jam
4 Dump Truck 3-4 ton Jam
5 Dump Truck 5 Ton 125 HP Jam
6 Flatbad Truck 3,5 Ton Jam
7 Truck 3/4 Jam
8 Truck Fuso Jam
9 Mesin Las Listrik 18 PK Jam
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

10 Mesin Pompa Air 3" Jam


11 Jack Hammer Jam
5 Compressor 4000 - 6500/m( E.05 ) Jam
6 Pump Water 70 100 mm Jam
7 Trailler, Towed 1 Ton Jam
8 Water Tank 3000 - 4500 Liter Jam

M. BAHAN LANTAI DAN PELAPIS DINDING


1 Keramik 40 x 40 KW I DN ( polos) m2 /Dus
2 Keramik 40 x 40 KW I DN Warna m2 /Dus
3 Keramik 30 x 30 KW I DN ( polos) m2 /Dus
4 Keramik 30 x 30 KW I DN Warna m2 /Dus
5 Keramik 30 x 30 KW I DN Warna (anti selip) m2 /Dus
6 Keramik 60 x 60 Roman m2 /Dus
7 Keramik 20 x 20 Roman m2 /Dus
8 Keramik 20 x 20 KW I DN Putih ( polos) m2 /Dus
9 Keramik 20 x 20 KW I DN Putih (warna) m2 /Dus
10 Keramik 20 x 20 KW I DN Warna (Anti Slip) m2 /Dus
11 Keramik 20 x 40 KW Roman m2 /Dus
12 Keramik 20 x 25 KW I DN Warna m2 /Dus
13 Keramik 10 x 20 KW I DN Warna ( anti selip) m2 /Dus
14 Tegel Warna 30 x 30 cm bh

U. BAHAN-BAHAN LAINNYA
1 Profil Alumunium m'
2 Alumunium Strip m'
3 Alumunium 0.10 mm Lbr
4 Alumunium 0.30 mm Lbr
5 Kusen Pintu WC PVC Set
6 Kusen Pintu WC Aluminium Set
7 L 50.50 4 Pj. 6 M Lente
8 L 50.50 5 Pj. 6 M Lente
9 Jendela Nako bh
10 Panel Beton Pracetak LBR
11 Kolom Beton Pracetak BTG
12 Air L
13 Skrup Fixer bh
14 sealant tube

V. ALAT PERENCANAAN
1 GPS setara Garmin 76 map Bh
DAFTAR HARGA BAHAN
KOTA BANJAR
TAHUN 2020

No JENIS BAHAN BANGUNAN SATUAN

2 GPS setara Garmin 76 map S Bh


3 GPS setara Garmin 76 Col map Bh
4 GPS setara Garmin 76 S Col Bh
5 GPS setara Garmin 178 C Bh
6 Kalkulator Scientific setara CASIO fx-P Bh
7 Plotter Designjet 500 ukuran A0 Bh
8 Plotter Designjet 800 ukuran A0 Bh
9 Printer setara Canon Pixma 1000 Bh
10 Printer setara Canon Pixma 2000 Bh
11 Memory Card 128 MB setara Nexus Bh
12 Memory Card 256 MB setara Nexus Bh
13 Auto Switch Printer 1 to 4 Channel Bh
14 Manual Switch Printer 1 to 4 Channel Bh
15 Lemari Gambar Ukuran A0 ( Horizontal ) Bh
16 Lemari Gambar Ukuran A0 ( Vertikal ) Bh
17 Filling Kabinet 4 Laci Bh
18 Meja + Mesin Gambar Set
19 Rafido Set ( 8 Pencil + Jangka + Tinta) setara Rothring Set
20 Distance Meter (Laser) Bh
21 Meteran Roll ( Pita ) 50 Meter Bh
22 Meteran Roll ( Pita ) 100 Meter Bh
23 Meteran Roll ( Roda ) Bh
24 Teodolith setara Top Con (Digital) DT 202 Bh
25 Teodolith setara Top Con (Digital) DT 205 Bh
26 Teodolith setara Top Con (Digital) DT 207 Bh
27 Teodolith setara Top Con (Digital) DT 209 Bh

E. HARGA BBM
1 Premium Ltr
2 Minyak Solar Ltr
3 Residu /Ter Ltr
4 Plux Oil Ltr
5 Minyak Bakar Ltr
6 Olie SAE (Mesran, Pertamina) Ltr
1 Oli Bekas Ltr
DAFTAR HARGA UPAH
KOTA Banjar
TAHUN 2020

HARGA
(Rp)

85,000
70,000
85,000
85,000

100,000
110,000

105,000
110,000

105,000
110,000
105,000
110,000

105,000
110,000
120,000
150,000
85,000
115,000
85,000
100,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

185,000 2
0
50,000 1
50,000 9
100,000
85,000
125,000

195,000
130,000
140,000
200,000
220,000
235,000
220,000
210,000
150,000
120,000

800
44,800

75,000

85,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9

60,000
110,000
13,000
4,313
300,000

800,000
840,000
900,000
900,000
950,000
950,000
990,000
1,030,000
250,000
2,750,000
50,000

Penambahan lebih dari 100 M3


50,000

10,581
1,330,000
1,350,000
1,400,000

12,000
175,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
9,500 O
M
12,000
2
0
1
9

15,000

15,000

17,500
5,000

50,000

61,600
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M
100,000
2
0
1
40,000 9
50,000
60,000

185,000

8,000

108,000
138,000

27,000
35,000
45,000
75,000
100,000
140,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
200,000 O
M
295,000
600,000 2
0
750,000 1
9
35,000
75,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9

7,000

29,700

2,700,000
3,800,000
18,000

1,800,000
2,000,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9

7,500

60,000
9,000
88,000
80,000
60,000
11,000
4,000

35,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
5,000 9

54,000

45,000
55,000
45,000
55,000

97,500
25,000

74,000
50,000

37,000
16,500

10,000
13,000

23,600

15,000
25,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9

18,000

21,000
24,000
33,000
52,000
65,000
90,000
265,000

18,000

285,000

1,700,000
210,000

45,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

15,000 2
0
15,000 1
9
1,500

650,000

1,250,000

68,600
27,600

74,400

19,100
2,400
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M
6,800
2
0
1
9

83,300
137,500
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9

10,000
4,200
18,500
10,100
36,400
21,800
4,200
9,500
43,700
26,200
3,500
82,600
135,000
5,100
35,000
58,400
35,000
61,400
70,100
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9
5,000
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
154,000 1
982,000 9
147,000
80,000.00

310,000.00
600,000.00

49,000.00

300,000.00
122,400
83,400
65,300
83,400
47,300
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
23,500 O
M
23,500
225,000.00 2
0
19,400 1
261,500 9
101,400

52,500
56,700
39,500
45,000
80,000
100,000
90,000
36,500
46,000
42,500
95,000
49,000

50,000
150,000
150,000
50
H
A
R
DAFTAR HARGA BAHAN G
A
KOTA BANJAR
TAHUN 2020 H
P
S

C
HARGA U
(Rp) S
T
O
M

2
0
1
9

5,000
BILL OF QUANTITY
PEKERJAAN : PEKERJAAN PEMBANGUNAN GEDUNG KANTOR PPPD WILAYAH KOTA BANJAR TAHAP.II
LOKASI : KOTA BANJAR
TAHUN ANGGARAN : 2019

NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

BANGUNAN PENUNJANG
I PEKERJAAN STRUKTUR
A PEKERJAAN TANAH DAN URUGAN
1 Pembersihan Lokasi termasuk babat rumput 1.00 LS 1,000,000.00 1,000,000.00
2 Pasangan Bouwplank 86.00 m1 42,491.00 3,654,226.00
3 Galian Tanah :
- Galian Tanah Pondasi / Sloof 64.37 m3 61,880.00 3,983,401.24
4 Urugan Pasir :
- Urugan Pasir Dibawah Pondasi / Sloof 6.85 m3 196,400.00 1,345,693.52
5 Lantai kerja di bawah Sloof dan pondasi 3.43 m3 808,900.00 2,771,210.51
6 Urugan tanah Peninggian Lantai 59.70 m3 65,000.00 3,880,302.40
7 Buangan Tanah Bekas Galian Ke area peninggian lantai 32.19 m3 18,800.00 605,106.20
8 Urugan Pasir di bawah Plat Lantai 1 T=10cm 27.03 m3 196,400.00 5,309,257.63
9 Lantai Kerja dibawah plat lantai 1 T=5cm 13.52 m3 808,900.00 10,933,448.32
10 Rabat Beton 1:3:5 T=10cm 30.15 m3 808,900.00 24,388,335.00
JUMLAH A : 57,870,980.82
B PEKERJAAN SUB STRUKTUR DAN PONDASI
1 Pondasi Batu Belah 1 : 5 5.30 m3 675,300.00 3,578,414.70
2 Rolag Bata 4.02 m3 859,000.00 3,449,958.75
B.2 PEKERJAAN PONDASI SETEMPAT
1 Pondasi setempat ukuran 150 x 150 cm
Beton Bertulang K 300 8.44 m3 3,561,500.00 30,050,156.25
2 Cerucuk bambu diameter 4 Inch T=2M 135.00 bh 8,000.00 1,080,000.00
B.3 PEKERJAAN SLOOF BETON
1 Sloof Beton TB1 20 x 40 cm
Beton Bertulang K 300 6.38 m3 6,901,200.00 44,057,260.80
2 Sloof Beton TB2 15 x 25 cm
Beton Bertulang K 300 2.37 m3 6,635,800.00 15,701,961.75
3 Pedestal PD.1
Beton Bertulang K 300 1.53 m3 5,406,900.00 8,272,557.00
4 Pedestal PD.2
Beton Bertulang K 300 0.77 m3 6,307,000.00 4,856,390.00

JUMLAH B : 111,046,699.25
C PEKERJAAN STRUKTUR ATAS
C.1 PEKERJAAN KOLOM
C.1.1 LANTAI 1
1 Kolom Tipe K1 30 x 30 cm
Beton Bertulang K 300 2.88 m3 8,071,800.00 23,246,784.00
2 Kolom Tipe K2 30 x 30 cm
Beton Bertulang K 300 1.44 m3 7,125,300.00 10,260,432.00
C.1.2 LANTAI 2
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

1 Kolom Tipe K2 30 x 30 cm
Beton Bertulang K 300 3.74 m3 7,125,300.00 26,677,123.20
JUMLAH C.1 : 60,184,339.20
C.2 PEKERJAAN BALOK
C.2.1 LANTAI 2
1 Balok Tipe B1 25 x 50
Beton Bertulang K 300 10.125 m3 4,772,200.00 48,318,525.00
2 Balok Tipe B2 25 x 40
Beton Bertulang K 300 4.242 m3 5,519,700.00 23,414,567.40
C.2.1 ATAP
1 Balok Tipe B2 20 x 35
Beton Bertulang K 300 6.51 m3 4,676,900.00 30,446,619.00
2 Balok Tipe B2 25 x 40
Beton Bertulang K 300 2.1 m3 5,519,700.00 11,591,370.00
JUMLAH C.2 : 113,771,081.40
C.3 PEKERJAAN PLAT
C.3.1 LANTAI 1
1 Plat Lantai Tebal 10 cm
Beton Campuran K175 (1 : 2 : 3) 22.80 m3 2,505,500.00 57,125,400.00
2 Beton Canopy T= 8 5.60 m3 3,355,000.00 18,788,000.00
3 Talang Beton 0.96 m3 3,355,000.00 3,220,800.00
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

C.3.2 LANTAI 2
1 Plat Lantai Tebal 12 cm
Beton Bertulang K 300 17.86 m3 5,006,500.00 89,396,064.00
2 Beton Canopy T= 8 5.04 m3 3,355,000.00 16,909,200.00
3 Talang Beton 2.36 m3 3,355,000.00 7,917,800.00
C.3.3 LANTAI ATAP
1 Plat Lantai Tebal 15 cm
Beton Bertulang K 300 1.35 m3 4,465,500.00 6,028,425.00
JUMLAH C.3 : 199,385,689.00

C.4 PEKERJAAN TANGGA


1 Tangga Beton
Beton Bertulang K 300 2.71 m3 5,044,600.00 13,685,495.34
JUMLAH C.4 : 13,685,495.34
JUMLAH C : 387,026,604.94
JUMLAH PEKERJAAN STRUKTUR : 555,944,285.01
II PEKERJAAN ARSITEKTUR
A PEKERJAAN DINDING
A.1 LANTAI 1
1 Dinding Bata Ringan Tebal 10 cm Dengan Perekat Jenis Mortar 319.41 m2 120,300.00 38,425,413.98
2 Plesteran + Acian Dinding Bata Ringan Dengan Perekat Jenis Mortar 638.83 m2 60,500.00 38,649,003.25
3 Dinding Partisi Gypsum Berikut Rangka 36.00 m2 103,800.00 3,736,800.00
4 Ringbalk Kusen 10/15 45.47 m1 114,100.00 5,188,127.00
5 Kolom Praktis 10/10 84.00 m1 94,800.00 7,963,200.00
A.2 LANTAI 2
1 Dinding Bata Ringan Tebal 10 cm Dengan Perekat Jenis Mortar 283.73 m2 120,300.00 34,132,719.00
2 Plesteran + Acian Dinding Bata Ringan Dengan Perekat Jenis Mortar 587.46 m2 60,500.00 35,541,330.00
3 Ringbalk Kusen 10/15 72.53 m1 114,100.00 8,275,673.00
4 Kolom Praktis 10/10 108.00 m1 94,800.00 10,238,400.00
JUMLAH A : 182,150,666.23
B PEK. KUSEN PINTU DAN JENDELA TERMASUK FINISHING DAN ACCESSORIES
B.1 LANTAI 1
1 PJ1 1.00 unit 10,173,700.00 10,173,700.00
2 PJ2 2.00 unit 8,539,700.00 17,079,400.00
3 P1 2.00 unit 7,177,400.00 14,354,800.00
4 P2 3.00 unit 3,831,200.00 11,493,600.00
5 P3 2.00 unit 4,362,400.00 8,724,800.00
5 J1 2.00 unit 2,114,600.00 4,229,200.00
6 J3 2.00 unit 3,152,800.00 6,305,600.00
7 BV1 2.00 unit 1,379,500.00 2,759,000.00
8 PS 1.00 unit 4,631,250.00 4,631,250.00
B.2 LANTAI 2
1 PJ2 1.00 unit 8,539,700.00 8,539,700.00
3 P3 5.00 unit 4,362,400.00 21,812,000.00
4 P4 8.00 unit 3,900,600.00 31,204,800.00
5 J1 11.00 unit 2,114,600.00 23,260,600.00
6 J2 1.00 unit 1,726,400.00 1,726,400.00
7 BV1 6.00 unit 1,379,500.00 8,277,000.00
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

JUMLAH B : 174,571,850.00
C PEKERJAAN LANGIT - LANGIT
C.1 LANTAI 1
1 Plafon Gypsum Tile Tb. 9 mm Berikut Rangka Hollow Galvanized 225.00 m2 103,800.00 23,355,000.00
2 Plafond GRC Tb. 6 mm Berikut Rangka Hollow 16.35 m2 121,500.00 1,986,525.00
3 List Plafon U Channel 221.65 m1 29,300.00 6,494,345.00
C.2 LANTAI 2
1 Plafon Gypsum Tile Tb. 9 mm Berikut Rangka Hollow Galvanized 161.70 m2 103,800.00 16,783,941.00
2 Plafond GRC Tb. 6 mm Berikut Rangka Hollow 18.31 m2 121,500.00 2,224,057.50
3 List Plafon U Channel 233.75 m1 29,300.00 6,848,875.00
JUMLAH C : 57,692,743.50
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

D PEKERJAAN FINISHING LANTAI DAN DINDING


D.1 LANTAI 1
1 Homogenius Tile 60 x 60 cm Indogress 295.65 m2 295,400.00 87,335,010.00
2 Homogenius Tile KM/WC 30 x 30 cm Indogress 16.35 m2 295,400.00 4,829,790.00
3 Dinding Homogenius Tile 30 x 60 cm Indogress 58.52 m2 303,900.00 17,784,228.00
Homogenius Tile Tangga 30 x 60 cm Indogress ( termasuk pembuatan jalur
4 25.00 m2 303,900.00 7,597,500.00
step nosing)
5 Plint Homogenius tile 10 x 60 Indogress 170.50 m1 78,600.00 13,401,300.00
6 Waterproofing Talang Beton 74.87 m2 89,400.00 6,693,378.00
D.1 LANTAI 2
1 Homogenius Tile 60 x 60 cm Indogress 149.70 m2 295,400.00 44,219,903.00
2 Homogenius Tile KM/WC 30 x 30 cm Indogress 18.31 m2 295,400.00 5,407,297.00
3 Dinding Homogenius Tile 30 x 60 cm Indogress 66.42 m2 303,900.00 20,185,038.00
4 Floor Hardener 18.00 m2 68,200.00 1,227,600.00
5 Plint Homogenius tile 10 x 60 Indogress 112.20 m1 78,600.00 8,818,920.00
6 Waterproofing toilet, Plat Dak dan talang beton 84.73 m2 89,400.00 7,574,415.00
JUMLAH D : 225,074,379.00
E PEKERJAAN SANITAIR
E.1 LANTAI 1
1 Closet Jongkok Tipe CE 7 2.00 unit 542,400.00 1,084,800.00
2 Wastafel Lengkap Tipe LW 241 CJ 2.00 unit 3,055,300.00 6,110,600.00
3 Floor Drain Tipe TX 1 BN 6.00 unit 374,600.00 2,247,600.00
4 Kran Dinding Tipe T 23B 13V7NB 8.00 unit 293,400.00 2,347,200.00
5 Kaca Cermin Diatas Wastafel 1.00 unit 416,072.00 416,072.00
6 Kitchen Zink Lengkap + Kran Angsa TOTO 4.00 unit 704,000.00 2,816,000.00
7 Meja Beton lapis Homogenius tlle 7.20 m2 550,000.00 3,960,000.00
8 Tanggulan tempat wudhu T=30cm + grill besi besi siku + cat 1.80 m2 450,000.00 810,000.00
9 Clean Out dia 100 Toto 1.00 bh 374,600.00 374,600.00
E.2 LANTAI 2
1 Closet Jongkok Tipe CE 7 5.00 unit 542,400.00 2,712,000.00
2 Kran Dinding Tipe T 23B 13V7NB 7.00 unit 293,400.00 2,053,800.00
3 Floor Drain Tipe TX 1 BN 7.00 unit 374,600.00 2,622,200.00
4 Hand shower set setara Toto tipe THX 118SE Lengkap 5.00 unit 619,000.00 3,095,000.00
5 Kitchen Zink Lengkap 1.00 unit 704,000.00 704,000.00
6 Meja Beton lapis Homogenius tlle 2.40 m2 550,000.00 1,320,000.00
7 Clean Out dia 100 Toto 2.00 bh 374,600.00 749,200.00
JUMLAH E : 33,423,072.00
F PEKERJAAN PENGECATAN
F.1 LANTAI 1
1 Pengecatan Dinding Bagian Dalam 502.73 m2 26,930.00 13,538,518.90
2 Pengecatan Dinding Bagian Luar 126.51 m2 47,900.00 6,059,829.00
3 Pengecatan Plafon 241.35 m2 25,400.00 6,130,290.00
F.2 LANTAI 2
1 Pengecatan Dinding Bagian Dalam 57.77 m2 26,930.00 1,555,746.10
2 Pengecatan Dinding Bagian Luar 126.51 m2 47,900.00 6,059,829.00
3 Pengecatan Plafon 144.00 m2 25,400.00 3,657,600.00
JUMLAH F : 37,001,813.00
G PEKERJAAN RAILING DAN ATAP
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

G.1 PEKERJAAN RAILING


1 Railing Tangga Hollow 50 x 50 mm 16.50 m1 501,200.00 8,269,800.00
2 Railing Kantin Hollow 20x40 dan 40x40 /jarak hollow 20/40 As-AS = 12cm 34.00 m1 501,200.00 17,040,800.00
G.2 PEKERJAAN ATAP + PENUTUPNYA
1 Rangka Atap Baja Ringan 252.00 m2 180,000.00 45,360,000.00
2 Insulation Alluminium Foil foam T=6,5mm 252.00 m2 58,900.00 14,842,800.00
3 Pasang atap Zinc - Allumunium Prepainted TCT 0.45mm 252.00 m2 200,300.00 50,475,600.00
4 Nok 21.00 m1 136,400.00 2,864,400.00
5 Talang Horisontal Pipa AW dia 4" 42.00 m1 74,500.00 3,129,000.00
JUMLAH G : 141,982,400.00
JUMLAH PEKERJAAN ARSITEKTUR : 851,896,923.73
II PEKERJAAN MEKANIKAL ELEKTRIKAL
A PEKERJAAN PANEL, INSTALASI DAN ARMATURE
A.1 LANTAI 1
1 a. Panel Listrik
- Panel - BP1 1.00 unit 10,444,665.00 10,444,665.00
- Panel Mesin TNKB 1.00 unit 6,565,020.00 6,565,020.00
- Panel Kantin 1.00 unit 4,405,170.00 4,405,170.00
b. Kabel Feeder
- Kabel feeder dari panel Utama ke panel BP1, NYFGbY 4x50mm 70.00 m' 334,950.00 23,446,500.00
- Kabel dari PB1 ke panel CF ( Cek Fisik1), NYY 4 x 6mm 70.00 m' 84,000.00 5,880,000.00
- Kabel dari panel BP1 ke panel FK (Kantin) NYY 4 x 6mm 25.00 m' 84,000.00 2,100,000.00
- Kabel dari panel BP1 ke panel TNKB, NYY 4 x 16mm 20.00 m' 127,050.00 2,541,000.00
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

2 Titik Instalasi
- Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 38.00 ttk 274,739.85 10,440,114.30
- Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 19.00 ttk 288,599.85 5,483,397.15
- Instalasi stop kontak 3 phase, NYM 4 x 4 mm2 dalam conduit PVC 4.00 ttk 432,899.78 1,731,599.10
- Instalasi AC, NYM 3 x 2,5 mm2 dalam conduit PVC 3.00 ttk 346,319.82 1,038,959.46
- Instalasi Exhaust Fan, NYM 3 x 2,5 mm2 dalam conduit PVC 3.00 ttk 274,739.85 824,219.55
3 Saklar Dan Stop Kontak
- Saklar Tunggal 4.00 bh 42,735.00 170,940.00
- Saklar Ganda 8.00 bh 65,835.00 526,680.00
- Stop Kontak 1 phase 19.00 bh 42,735.00 811,965.00
- Stop Kontak 3 phase 4.00 bh 85,470.00 341,880.00
4 Fikstures Lampu Lengkap Dengan Armature
- Recessed Mounted (RM) TLED 2 x 14 Watt @ 2100 Lumen 18.00 bh 433,125.00 7,796,250.00
- Slim square Down Light LED panel 15 Watt 2.00 bh 196,350.00 392,700.00
- Slim square Down Light LED panel 7 Watt 4.00 bh 155,925.00 623,700.00
- Slim Round cabinet Down Light LED panel 5 Watt (outdoor) 14.00 bh 161,700.00 2,263,800.00
5 Exhaust Fan Panasonik FV20TGU ukuran 8 inch 2.00 bh 340,400.00 680,800.00
Exhaust Fan Panasonik FV-30RUN5 ukuran 12 inch 1.00 bh 425,000.00 425,000.00
A.2 LANTAI 2
1 Panel Listrik
- Panel BP2 1.00 Unit 6,796,020.00 6,796,020.00
2 Titik Instalasi
- Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 50.00 ttk 274,739.85 13,736,992.50
- Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 19.00 ttk 288,599.85 5,483,397.15
- Instalasi AC, NYM 3 x 2,5 mm2 dalam conduit PVC 5.00 ttk 346,319.82 1,731,599.10
- Instalasi Exhaust Fan, NYM 3 x 2,5 mm2 dalam conduit PVC 5.00 ttk 274,739.85 1,373,699.25
3 Saklar Dan Stop Kontak
- Saklar Tunggal 8.00 bh 42,735.00 341,880.00
- Saklar Ganda 13.00 bh 65,835.00 855,855.00
- Stop Kontak 19.00 bh 42,735.00 811,965.00
4 Fikstures Lampu Lengkap Dengan Armature
- Recessed Mounted (RM) TLED 2 x 14 Watt @ 2100 Lumen 4.00 bh 433,125.00 1,732,500.00
- Slim square Down Light LED panel 15 Watt 15.00 bh 196,350.00 2,945,250.00
- Slim square Down Light LED panel 7 Watt 14.00 bh 155,925.00 2,182,950.00
- Slim Round cabinet Down Light LED panel 5 Watt (outdoor) 17.00 bh 161,700.00 2,748,900.00
5 Exhaust Fan Panasonik FV20TGU ukuran 8 inch 5.00 bh 340,400.00 1,702,000.00
JUMLAH A : 131,377,367.56
B PEKERJAAN AIR BERSIH, AIR BEKAS ADAN AIR KOTOR
B.1 LANTAI 1
1 Air Bersih
Instasi pemipaan dengan pipa Pipa PPR80 PN10 termasuk hanger/support,
Fitting dan Accessories
- Pipa PP-R PN 10 Ø 40 dari ruang pompa ke roof tank 40.00 m1 48,813.77 1,952,550.60
- Pipa PP-R PN 10 Ø 32 20.00 m1 36,053.16 721,063.20
- Pipa PP-R PN 10 Ø 25 20.00 m1 22,770.00 455,400.00
- Pipa PP-R PN 10 Ø 20 37.50 m1 17,078.16 640,431.00
2 Air Bekas dan Air Kotor
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

Instasi pemipaan air bekas dan air kotor dengan pipa Pipa AW termasuk
hanger/support, Fitting dan Accessories
- Pipa PVC Klas AW Ø 50 8.00 m1 44,300.00 354,400.00
- Pipa PVC Klas AW Ø 80 30.00 m1 98,300.00 2,949,000.00
- Pipa PVC Klas AW Ø 100 12.00 m1 146,000.00 1,752,000.00
- Gate Valve PP-R : dia 32 2.00 bh 326,700.00 653,400.00
- Gate Valve PP-R : dia 25 6.00 bh 242,000.00 1,452,000.00
- Roof Drain dia 4 inch 5.00 bh 374,600.00 1,873,000.00
- STP Biotech System Type BC-4 1.00 unit 18,000,000.00 18,000,000.00
Sumur Resapan Box Culvert Precast 1,5 x1,5 X 3m + diisi koral 2/3 T=50cm
1.00 unit 8,261,500.00 8,261,500.00
termasuk tutup box culvert 150x150 T=10cm
B.2 LANTAI 2
Pompa booster Grundfos CB 5-28 termasuk Pipa Header dia 80, Water level
1 1.00 set 8,200,000.00 8,200,000.00
Control, cabeling, dan gate valve
Roof tank Penguin Kav. 1Mᶾ termasuk dudukan tangki T= 100cm dari besi Siku
1.00 set 4,389,000.00 4,389,000.00
40x40 dan 60x60
Instasi pemipaan dengan pipa Pipa PPR - PN10 termasuk hanger/support,
2
Fitting dan Accessories
- Pipa PP-R PN 10 Ø 32 25.00 m' 36,053.16 901,329.00
- Pipa PP-R PN 10 Ø 25 16.00 m1 22,770.00 364,320.00
- Pipa PP-R PN 10 Ø 20 20.00 m1 17,078.16 341,563.20
- Gate Valve PP-R : dia 40 1.00 bh 489,500.00 489,500.00
- Gate Valve PP-R : dia 32 1.00 bh 326,700.00 326,700.00
- Gate Valve PP-R : dia 25 6.00 bh 242,000.00 1,452,000.00
NO URAIAN PEKERJAAN VOLUME SATUAN HARGA SATUAN JUMLAH HARGA

3 Air Bekas, air hujan dan Air Kotor


Instasi pemipaan air bekas dan air kotor dengan pipa Pipa AW termasuk
hanger/support, Fitting dan Accessories
- Pipa PVC Klas AW Ø 50 2.00 m1 44,300.00 88,600.00
- Pipa PVC Klas AW Ø 80 31.33 m1 98,300.00 3,079,739.00
- Pipa PVC Klas AW Ø 100 37.00 m1 146,000.00 5,402,000.00
- Pipa PVC Klas AW Ø 150
- Box Kontrol Drainase 600 x 600 x 800
- Roof Drain dia 4 inch 8.00 bh 374,600.00 2,996,800.00
JUMLAH B : 67,096,296.00
C PEKERJAAN AIR CONDITIONING, FAN DAN AFAR
C.1 LANTAI 1
1 AC Split Wall Mounted 18.000 BTU/h lengkap dengan Stop kontak AC 1.00 unit 7,177,275.00 7,177,275.00
2 AC Split Wall Mounted 12.000 BTU/h lengkap dengan Stop kontak AC 2.00 unit 5,899,477.50 11,798,955.00
3 Pipa Refrigrant Berisolasi 15.00 m1 195,888.00 2,938,320.00
4 Pipa Drain Berisolasi 15.00 m1 58,905.00 883,575.00
5 PANASONIC Exhaust Fan Ceiling Plafon 10 Inch FV-25TGU 2.00 unit 404,250.00 808,500.00
Exhaust Fan fanasonic Industrial 16 Inch FV - 40AFU, 220v - 50Hz, 58,1 - 73,9
6 2.00 unit 880,015.50 1,760,031.00
Watt
7 Kipas Angin Dinding Panasonic F-400MI Plus Remote Control 5.00 unit 1,790,250.00 8,951,250.00
8 Fire Extinguisher @ 6 Kg (Dry Chemical Multy Purpose) 3.00 bh 1,400,000.00 4,200,000.00
C.1 LANTAI 2
1 AC Split Wall Mounted 18.000 BTU/h lengkap dengan Stop kontak AC 1.00 unit 7,177,275.00 7,177,275.00
2 AC Split Wall Mounted 7.000 BTU/h lengkap dengan Stop kontak AC 5.00 unit 4,000,000.00 20,000,000.00
3 Pipa Refrigrant Berisolasi 30.00 m1 195,888.00 5,876,640.00
4 Pipa Drain Berisolasi 30.00 m1 58,905.00 1,767,150.00
5 PANASONIC Exhaust Fan Ceiling Plafon 10 Inch FV-25TGU 6.00 unit 404,250.00 2,425,500.00
6 Fire Extinguisher @ 6 Kg (Dry Chemical Multy Purpose) 2.00 bh 1,400,000.00 2,800,000.00
JUMLAH C : 78,564,471.00
JUMLAH PEKERJAAN MEKANIKAL ELEKTRIKAL : 277,038,134.56
JUMLAH PEKERJAAN BANGUNAN PENUNJANG : 1,684,879,343.29
BILL OF QUANTITY
PEKERJAAN : PEKERJAAN PEMBANGUNAN GEDUNG KANTOR PPPD WILAYAH KOTA BANJAR TAHAP.II
LOKASI : KOTA BANJAR
TAHUN ANGGARAN : 2019

RENCANA REALISASI
NO URAIAN PEKERJAAN SATUAN HARGA SATUAN
VOLUME JUMLAH HARGA VOLUME JUMLAH HARGA

BANGUNAN UTAMA

PEKERJAAN ELEKTRIKAL DAN MEKANIKAL

I PEKERJAAN ELEKTRIKAL
Pekerjaan RUNNING TEKS Ukuran 48 X 356 cm, 1 warna dengan 4 baris hurup bisa di ganti-ganti,
1 set 17,000,000.00 1.00 17,000,000.00 1.00 17,000,000.00
termasuk biaya instalasi/ kabel, braket dan pemasangan
Pekerjaan Mesin Antrian lengkap software untuk 8 loket termasuk biaya instalasi cabeling sehingga
2 Set 45,000,000.00 1.00 45,000,000.00 1.00 45,000,000.00
system bisa berjalan dengan baik.
- Program Software Antrian
- Router Wifi
- Display LED Matrix + Controler untuk 8 loket
- Loket tombol antrian Wifi untuk 8 loket
- Printer Thermal + Standing (1 set)
- Speker + Power Supply (1 set)
- PC I5 RAM 4, Hardisk 500GB + VGA Dual Monitor (1 set)
- Panasonic TV LED 32 Inch + Braket (2 Set)
- Power Supply 5V - 10Amper (9 unit)
- Test Commisioning dan Training

JUMLAH I : - - 62,000,000.00 - 62,000,000.00

II PEKERJAAN HIDRANT

1 Sistem Utama
2 Electric Fire Pump (Kap : 500 USGPM, Tek : 70 M, Put : 2900 RPM, Motor : 75 KW) unit 140,000,000.00 1.00 140,000,000.00 1.00 140,000,000.00
3 Diesel Fire Pump (Kap : 500 USGPM, Tek : 70 M, Put : 2900 RPM, Motor : 100 KW) unit 225,000,000.00 1.00 225,000,000.00 1.00 225,000,000.00
4 Jockey Fire Pump (Kap : 10 USGPM, Tek : 77 M, Put : 1450 RPM, Motor : 1,5 KW) unit 37,500,000.00 1.00 37,500,000.00 1.00 37,500,000.00
5 Header Ø 200 m1 875,000.00 4.00 3,500,000.00 4.00 3,500,000.00
6 Check Valve Ø 150 bh 4,200,000.00 4.00 16,800,000.00 2.00 8,400,000.00
Check Valve Ø 50 bh 1,750,000.00 - - 1.00 1,750,000.00
Gate Valve Ø 150 bh 4,200,000.00 - - 1.00 4,200,000.00
Gate Valve Ø 50 bh 1,750,000.00 - - 1.00 1,750,000.00
Y Strainer Ø 150 bh 4,200,000.00 - - 1.00 4,200,000.00
Y Strainer Ø 50 bh 1,750,000.00 - - 1.00 1,750,000.00
Flexible Rabber Joint Ø 150 bh 2,375,000.00 - - 4.00 9,500,000.00
Flexible Rabber Joint Ø 50 bh 1,125,000.00 - - 2.00 2,250,000.00
RENCANA REALISASI
NO URAIAN PEKERJAAN SATUAN HARGA SATUAN
VOLUME JUMLAH HARGA VOLUME JUMLAH HARGA

Pressure Guage bh 327,500.00 - - 2.00 655,000.00


Pressure Switch bh 415,300.00 - - 3.00 1,245,900.00
Kbael kontrol ls 750,000.00 - - 1.00 750,000.00
Kabel Feeder NYFGBY 4 X 70 mm dari panel MDP ke panel SDP Pompa R.Pompa mtr 527,300.00 - - 82.00 43,238,600.00
Kabel Feeder NYFGBY 4 X 50 mm dari panel SDP Pompa ke panel Elektrik Fire Pump mtr 359,700.00 - - 17.00 6,114,900.00
Kabel Feeder NYY 4 X 35 mm (x2) dari panel Kontrol ke elektrik fire pump mtr 287,600.00 - - 30.00 8,628,000.00
Kabel Feeder NYFGBY 4 X 16 mm dari panel SDP Pompa ke panel Joykey Fire Pump mtr 198,600.00 - - 17.00 3,376,200.00
Kabel Feeder NYY 4 X 10 mm dari panel Kontrol ke Jockey fire pump mtr 175,300.00 - - 15.00 2,629,500.00
Panel SDP Pompa unit 28,750,000.00 - - 1.00 28,750,000.00
7 Pipa BSP Sch 40 Ø 150 m1 700,000.00 19.00 13,300,000.00 8.00 5,600,000.00

JUMLAH II : 436,100,000.00 540,788,100.00


JUMLAH PEKERJAAN ELEKTRIKAL DAN MEKANIKAL : 498,100,000.00 602,788,100.00

Kelebihan Volume
Tidak ada di BOQ

Jumlah yang Tidak ada dalam BOQ

Rp 120,788,100.00
ANALISA HARGA SATUAN PEKERJAAN
TAHUN ANGGARAN 2020
TAHUN ANGGARAN 2020

KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

I PEKERJAAN PERSIAPAN
A-01 1M' PAGAR SEMENTARA DARI KAYU TINGGI 2 M
A. TENAGA
Pekerja 0.4000 OH 85,000.00 34,000.00
Tukang Kayu 0.2000 OH 105,000.00 21,000.00
Kepala Tukang 0.0200 OH 110,000.00 2,200.00
Mandor 0.0200 OH 120,000.00 2,400.00
B. BAHAN
Semen Portland 2.5000 kg 1,200.00 3,000.00
Pasir Beton 0.0050 m3 195,000.00 975.00
Koral Beton 0.0090 m3 220,000.00 1,980.00
Kayu 5/7 0.0720 m3 1,800,000.00 129,600.00
Paku biasa 2"-5" 0.0600 Kg 18,000.00 1,080.00
Residu 0.4000 Lt 5,000.00 2,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 198,235.00
Overhead + Profit 15.0000 % 29,735.25
Harga Satuan Pekerjaan 227,970.25
A-02 1M' PAGAR SEMENTARA DARI SENG GELOMBANG 2 M
A. TENAGA
Pekerja 0.4000 OH 85,000.00 34,000.00
Tukang Kayu 0.2000 OH 105,000.00 21,000.00
Kepala Tukang 0.0200 OH 110,000.00 2,200.00
Mandor 0.0200 OH 120,000.00 2,400.00
B. BAHAN
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 29,700.00 37,125.00
Semen Portland 2.5000 kg 1,200.00 3,000.00
Seng gelombang 3"-5" 1.2000 lbr 74,400.00
Pasir Beton 0.0050 m3 195,000.00 975.00
Koral Beton 0.0090 m3 220,000.00 1,980.00
Kayu 5/7 0.0720 m3 1,800,000.00 129,600.00
Paku biasa 2"-5" 0.0600 Kg 18,000.00 1,080.00
Meni Besi 0.4500 Lt 5,000.00 2,250.00
Jumlah Harga Tenaga, Bahan dan Peralatan 235,610.00
Overhead + Profit 15.0000 % 35,341.50
Harga Satuan Pekerjaan 270,951.50
A-03 1 M PAGAR SEMENTARA DARI KAWAT DURI TINGGI 1,8 METER
A. TENAGA
Pekerja 0.3000 OH 85,000.00 25,500.00
Tukang Kayu 0.2000 OH 105,000.00 21,000.00
Kepala Tukang 0.0200 OH 110,000.00 2,200.00
Mandor 0.0200 OH 120,000.00 2,400.00
B. BAHAN
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 29,700.00 37,125.00
Semen Portland 2.0000 kg 1,200.00 2,400.00
Kawat Duri 25.0000 kg 5,000.00 125,000.00
Pasir Beton 0.0050 m3 195,000.00 975.00
Koral Beton 0.0090 m3 220,000.00 1,980.00
Paku biasa 2"-5" 0.0600 Kg 18,000.00 1,080.00
Jumlah Harga Tenaga, Bahan dan Peralatan 219,660.00
Overhead + Profit 15.0000 % 32,949.00
Harga Satuan Pekerjaan 252,609.00
A.2.2.1.4. 1 M' PENGUKURAN DAN PEMASANGAN BOUPLANK
A. TENAGA
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pekerja 0.1000 OH 85,000.00 8,500.00


Tukang Kayu 0.1000 OH 105,000.00 10,500.00
Kepala Tukang 0.0100 OH 110,000.00 1,100.00
Mandor 0.0050 OH 120,000.00 600.00
B. BAHAN
Kayu 5/7 0.0120 m3 1,800,000.00 21,600.00
Paku biasa 2"-5" 0.0200 Kg 18,000.00 360.00
Kayu Papan 3/20 0.0070 m3 1,800,000.00 12,600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 55,260.00
Overhead + Profit 15.0000 % 8,289.00
Harga Satuan Pekerjaan 63,549.00
A-05 1 M2 PEMBUATAN KANTOR SEMENTARA
A. TENAGA
Pekerja 1.0000 OH 85,000.00 85,000.00
Tukang Kayu 2.0000 OH 105,000.00 210,000.00
Kepala Tukang 0.3000 OH 110,000.00 33,000.00
Mandor 0.0500 OH 120,000.00 6,000.00
B. BAHAN
Dolken kayu diameter 8-10/400 cm 1.2500 Btg 29,700.00 37,125.00
Kayu 5/7 0.1800 m3 1,800,000.00 324,000.00
Paku biasa 2"-5" 0.8500 Kg 18,000.00 15,300.00
Besi Strip 1.1000 Kg 9,500.00 10,450.00
Semen Portland 35.0000 kg 1,200.00 42,000.00
Pasir Pasang 0.1500 m3 125,000.00 18,750.00
Pasir Beton 0.1000 m3 195,000.00 19,500.00
Koral Beton 0.1500 m3 220,000.00 33,000.00
Bata Merah 30.0000 Bh 800.00 24,000.00
Seng Plat 0.2500 Lbr 50,000.00 12,500.00
Jendela Nako 2.0000 Bh 50,000.00 100,000.00
Kaca Polos 0.0800 m2 52,000.00 4,160.00
Kunci Tanam 0.1500 Bh 135,000.00 20,250.00
Plywood 4 mm 0.0600 lbr 35,000.00 2,100.00
Jumlah Harga Tenaga, Bahan dan Peralatan 997,135.00
Overhead + Profit 15.0000 % 149,570.25
Harga Satuan Pekerjaan 1,146,705.25
A-06 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT
A. TENAGA
Pekerja 1.0000 OH 85,000.00 85,000.00
Tukang Kayu 2.0000 OH 105,000.00 210,000.00
Kepala Tukang 0.3000 OH 110,000.00 33,000.00
Mandor 0.0500 OH 120,000.00 6,000.00
B. BAHAN
Dolken kayu diameter 8-10/400 cm 1.7000 Btg 29,700.00 50,490.00
Kayu 5/7 0.2100 m3 1,800,000.00 378,000.00
Paku biasa 2"-5" 0.3000 Kg 18,000.00 5,400.00
Semen Portland 10.5000 kg 1,200.00 12,600.00
Pasir Beton 0.0300 m3 195,000.00 5,850.00
Koral Beton 0.0500 m3 220,000.00 11,000.00
Seng gelombang BJLS 32 1.5000 lbr 74,400.00 111,600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 908,940.00
Overhead + Profit 15.0000 % 136,341.00
Harga Satuan Pekerjaan 1,045,281.00
A-07 1 M2 PEMBUATAN RUMAH JAGA / KOSTRUKSI KAYU
A. TENAGA
Pekerja 1.0000 OH 85,000.00 85,000.00
Tukang kayu 1.5000 OH 105,000.00 157,500.00
Kepala tukang 0.1500 OH 110,000.00 16,500.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Mandor 0.0500 OH 120,000.00 6,000.00


B. BAHAN
Dolken Kayu D 8-10/400 Cm 3.0000 Btg 29,700.00 89,100.00
Kayu 0.2760 m3 1,800,000.00 496,800.00
Paku biasa 0.7000 Kg 18,000.00 12,600.00
Seng gelombang BJLS 32 1.5000 Lbr 50,000.00 75,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 938,500.00
Overhead + Profit 15.0000 % 140,775.00
Harga Satuan Pekerjaan 1,079,275.00
A.2.2.1.8. 1 M2 PEKERJAAN MEMBERSIHKAN LAPANGAN DAN PERATAAN
A. TENAGA
Pekerja 0.1000 OH 85,000.00 8,500.00
Mandor 0.0500 OH 120,000.00 6,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 14,500.00
Overhead + Profit 15.0000 % 2,175.00
Harga Satuan Pekerjaan 16,675.00
A-09 1 M2 PEMBUATAN BEDENG BURUH
A. TENAGA
Pekerja 1.0000 OH 85,000.00 85,000.00
Tukang kayu 2.0000 OH 105,000.00 210,000.00
Kepala tukang 0.2000 OH 110,000.00 22,000.00
Mandor 0.0500 OH 120,000.00 6,000.00
B. BAHAN
Dolken Kayu D 8-10/400 Cm 1.2500 Btg 29,700.00 37,125.00
Kayu 0.1860 m3 1,800,000.00 334,800.00
Paku biasa 0.3000 Kg 18,000.00 5,400.00
Semen Portland 18.0000 Kg 1,200.00 21,600.00
Pasir Beton 0.0300 m3 195,000.00 5,850.00
Koral Beton 0.0500 m3 220,000.00 11,000.00
Seng gelombang BJLS 32 1.5000 Lbr 50,000.00 75,000.00
Plywood 4mm 1.3500 Lbr 35,000.00 47,250.00
Jumlah Harga Tenaga, Bahan dan Peralatan 861,025.00
Overhead + Profit 15.0000 % 129,153.75
Harga Satuan Pekerjaan 990,178.75
A.2.2.1.10. 1 BUAH PEMBUATAN BAK ADUKAN, UKURAN (40 x 50 x 25) cm
A. TENAGA
Tukang kayu 0.3000 OH 105,000.00 31,500.00
Kepala Tukang 0.0300 OH 110,000.00 3,300.00
B. BAHAN
Kayu papan kelas III 0.0360 m3 1,800,000.00 64,800.00
Paku biasa 0.0800 Kg 18,000.00 1,440.00
Kaso 5/7 1.0000 Btg 18,000.00 18,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 119,040.00
Overhead + Profit 15.0000 % 17,856.00
Harga Satuan Pekerjaan 136,896.00
A.2.2.1.11. 1 M2 PEMBUATAN STEGGER DARI BAMBU
A. TENAGA
Pekerja 0.2500 OH 85,000.00 21,250.00
Tukang kayu 0.0170 OH 105,000.00 1,785.00
Kepala tukang 0.0020 OH 110,000.00 220.00
Mandor 0.0130 OH 120,000.00 1,560.00
B. BAHAN
Bambu Ø 6-8/600 cm 1.0000 Btg 7,000.00 7,000.00
Tali ijuk 0.2500 Kg 8,000.00 2,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 33,815.00
Overhead + Profit 15.0000 % 5,072.25
Harga Satuan Pekerjaan 38,887.25
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A.2.2.1.12. 1 M2 PEMBUATAN JALAN SEMENTARA


A. TENAGA
Pekerja 1.0000 OH 85,000.00 85,000.00
Mandor 0.0500 OH 120,000.00 6,000.00
B. BAHAN
Batu belah 15/20 0.1500 m3 130,000.00 19,500.00
Batu Pecah 5/7 0.0900 m3 210,000.00 18,900.00
Pasir pasang 1.0100 m3 125,000.00 126,250.00
Jumlah Harga Tenaga, Bahan dan Peralatan 255,650.00
Overhead + Profit 15.0000 % 38,347.50
Harga Satuan Pekerjaan 293,997.50
A.2.2.1.13. 1 M3 BONGKARAN BETON BERTULANG
A. TENAGA
Pekerja 13.3340 OH 85,000.00 1,133,390.00
Mandor 0.6660 OH 120,000.00 79,920.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,213,310.00
Overhead + Profit 15.0000 % 181,996.50
Harga Satuan Pekerjaan 1,395,306.50
A.2.2.1.14. 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH
A. TENAGA
Pekerja 0.6667 OH 85,000.00 56,669.50
Mandor 0.0333 OH 120,000.00 3,996.00
Jumlah Harga Tenaga, Bahan dan Peralatan 60,665.50
Overhead + Profit 15.0000 % 9,099.83
Harga Satuan Pekerjaan 69,765.33
A-15 1 M' PASANG PAGAR KAWAT JARING GALVANIS, PANJANG 240CM
A. TENAGA
Pekerja 0.0420 OH 85,000.00 3,570.00
Tukang Besi 0.0420 OH 105,000.00 4,410.00
Kepala tukang Besi 0.0040 OH 110,000.00 440.00
Mandor 0.0020 OH 120,000.00 240.00
B. BAHAN
Pagar Kawat Jaring 0.4340 LBR 100,000.00 43,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 52,060.00
Overhead + Profit 15.0000 % 7,809.00
Harga Satuan Pekerjaan 59,869.00
A-16 1 M2 PASANG PAGAR BETON PRACETAK (5X50X213)CM
A. TENAGA
Pekerja 0.3750 OH 85,000.00 31,875.00
Tukang Batu 0.1250 OH 100,000.00 12,500.00
Kepala tukang Batu 0.0120 OH 110,000.00 1,320.00
Mandor 0.0190 OH 120,000.00 2,280.00
B. BAHAN
Panel Beton Pracetak 0.9860 LBR 150,000.00 147,900.00
Kolom Beton Pracetak 0.5250 BTG 150,000.00 78,750.00
Pasir Beton 0.0740 M3 195,000.00 14,430.00
Koral 2/3 0.1460 M3 235,000.00 34,310.00
Semen Portland 45.0000 KG 1,200.00 54,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 377,365.00
Overhead + Profit 15.0000 % 56,604.75
Harga Satuan Pekerjaan 433,969.75
A.2.2.1.17. 1 M2 BONGKARAN PLESTERAN DINDING
A. TENAGA
Pekerja 0.0500 HOK 85,000.00 4,250.00
Mandor 0.0250 HOK 120,000.00 3,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 7,250.00
Overhead + Profit 15.0000 % 1,087.50
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Harga Satuan Pekerjaan 8,337.50


A.2.2.1.18. 1 M2 BONGKARAN GENTENG
A. TENAGA
Pekerja 0.1600 HOK 85,000.00 13,600.00
Mandor 0.0200 HOK 120,000.00 2,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 16,000.00
Overhead + Profit 15.0000 % 2,400.00
Harga Satuan Pekerjaan 18,400.00
A.2.2.1.19. 1 M2 BONGKARAN RANGKA ATAP /RENG+KASO
A. TENAGA
Pekerja 0.1000 HOK 85,000.00 8,500.00
Tukang kayu 0.0250 HOK 105,000.00 2,625.00
Kepala tukang kayu 0.0025 HOK 110,000.00 275.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 12,000.00
Overhead + Profit 15.0000 % 1,800.00
Harga Satuan Pekerjaan 13,800.00
A.2.2.1.20. 1 M3 BONGKARAN KUDA-KUDA, GORDING /BALOK
A. TENAGA
Pekerja 4.0000 HOK 85,000.00 340,000.00
Tukang kayu 3.0000 HOK 105,000.00 315,000.00
Mandor 0.2000 HOK 120,000.00 24,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 679,000.00
Overhead + Profit 15.0000 % 101,850.00
Harga Satuan Pekerjaan 780,850.00
A.2.2.1.21. 1 m2 BONGKARAN PLAFOND
A. TENAGA
Pekerja 0.1250 HOK 85,000.00 10,625.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 11,225.00
Overhead + Profit 15.0000 % 1,683.75
Harga Satuan Pekerjaan 12,908.75

II PEKERJAAN PELAKSANAAN
A PEKERJAAN TANAH
A.2.3.1.1. PENGGALIAN 1M3 TANAH BIASA SEDALAM 1 M'
A. TENAGA
Pekerja 0.7500 OH 85,000.00 63,750.00
Mandor 0.0250 OH 120,000.00 3,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 66,750.00
Overhead + Profit 15.0000 % 10,012.50
Harga Satuan Pekerjaan 76,762.50
A.2.3.1.2. PENGGALIAN 1M3 TANAH BIASA SEDALAM 2 M'
A. TENAGA
Pekerja 0.9000 OH 85,000.00 76,500.00
Mandor 0.0450 OH 120,000.00 5,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 81,900.00
Overhead + Profit 15.0000 % 12,285.00
Harga Satuan Pekerjaan 94,185.00
A.2.3.1.3. PENGGALIAN 1M3 TANAH BIASA SEDALAM 3 M'
A. TENAGA
Pekerja 1.0500 OH 85,000.00 89,250.00
Mandor 0.0670 OH 120,000.00 8,040.00
Jumlah Harga Tenaga, Bahan dan Peralatan 97,290.00
Overhead + Profit 15.0000 % 14,593.50
Harga Satuan Pekerjaan 111,883.50
A.2.3.1.4. PENGGALIAN 1M3 TANAH KERAS SEDALAM 1 M'
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A. TENAGA
Pekerja 1.0000 OH 85,000.00 85,000.00
Mandor 0.0320 OH 120,000.00 3,840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 88,840.00
Overhead + Profit 15.0000 % 13,326.00
Harga Satuan Pekerjaan 102,166.00
A.2.3.1.5. PENGGALIAN 1M3 TANAH CADAS SEDALAM 1 M'
A. TENAGA
Pekerja 1.5000 OH 85,000.00 127,500.00
Mandor 0.0600 OH 120,000.00 7,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 134,700.00
Overhead + Profit 15.0000 % 20,205.00
Harga Satuan Pekerjaan 154,905.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A.2.3.1.6. PENGGALIAN 1M3 TANAH LUMPUR SEDALAM 1 M'


A. TENAGA
Pekerja 1.2000 OH 85,000.00 102,000.00
Mandor 0.0450 OH 120,000.00 5,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 107,400.00
Overhead + Profit 15.0000 % 16,110.00
Harga Satuan Pekerjaan 123,510.00
A.2.3.1.7. MENGERJAKAN 1M2 STRIPPING TEBING SETINGGI 1 M
A. TENAGA
Pekerja 0.0500 OH 85,000.00 4,250.00
Mandor 0.0050 OH 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 4,850.00
Overhead + Profit 15.0000 % 727.50
Harga Satuan Pekerjaan 5,577.50
A.2.3.1.8. PEMBUANGAN 1 M3 TANAH SEJAUH 30 M
A. TENAGA
Pekerja 0.3300 OH 85,000.00 28,050.00
Mandor 0.0100 OH 120,000.00 1,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 29,250.00
Overhead + Profit 15.0000 % 4,387.50
Harga Satuan Pekerjaan 33,637.50
A.2.3.1.8.1 1 M3 PEMBUANGAN TANAH SEJAUH 100 METER
Pekerja 0.6000 HOK 85,000.00 51,000.00
Mandor 0.0300 HOK 120,000.00 3,600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 54,600.00
Overhead + Profit 15.0000 % 8,190.00
Harga Satuan Pekerjaan 62,790.00
A.2.3.1.9. PENGURUGAN KEMBALI 1 M3 GALIAN
A. TENAGA
Pekerja 0.5000 OH 85,000.00 42,500.00
Mandor 0.0500 OH 120,000.00 6,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 48,500.00
Overhead + Profit 15.0000 % 7,275.00
Harga Satuan Pekerjaan 55,775.00
A.2.3.1.10. PEMADATAN TANAH 1 M3 TANAH (PER 20 CM)
A. TENAGA
Pekerja 0.5000 OH 85,000.00 42,500.00
Mandor 0.0500 OH 120,000.00 6,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 48,500.00
Overhead + Profit 15.0000 % 7,275.00
Harga Satuan Pekerjaan 55,775.00
A.2.3.1.11. PENGURUGAN 1 M3 PASIR URUG
A. TENAGA
Pekerja 0.3000 OH 85,000.00 25,500.00
Mandor 0.0100 OH 120,000.00 1,200.00
B. BAHAN
Pasir Urug 1.2000 OH 85,000.00 102,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 128,700.00
Overhead + Profit 15.0000 % 19,305.00
Harga Satuan Pekerjaan 148,005.00
B-12 MEMASANG 1 M3 LAPISAN PUDEL CAMPURAN 1 KP : 3 PP : 7 TL UNTUK STABILISASI TANAH
A. TENAGA
Pekerja 0.8000 OH 85,000.00 68,000.00
Tukang Batu 0.4000 OH 100,000.00 40,000.00
Kepala Tukang 0.0400 OH 110,000.00 4,400.00
Mandor 0.0800 OH 120,000.00 9,600.00
B. BAHAN
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Kapur Padam 0.1350 m3 50,000.00 6,750.00


Pasir Pasang 0.4000 m3 125,000.00 50,000.00
Tanah Liat 0.9480 m3 50,000.00 47,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 226,150.00
Overhead + Profit 15.0000 % 33,922.50
Harga Satuan Pekerjaan 260,072.50
B-13 MEMASANG 1 M3 LAPISAN PUDEL CAMPURAN 1 KP : 5 TL UNTUK STABILISASI TANAH
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A. TENAGA
Pekerja 0.8000 OH 85,000.00 68,000.00
Tukang Batu 0.4000 OH 100,000.00 40,000.00
Kepala Tukang 0.0400 OH 110,000.00 4,400.00
Mandor 0.0800 OH 120,000.00 9,600.00
B. BAHAN
Kapur Padam 0.2480 m3 50,000.00 12,400.00
Tanah Liat 1.2400 m3 50,000.00 62,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 196,400.00
Overhead + Profit 15.0000 % 29,460.00
Harga Satuan Pekerjaan 225,860.00
B-14 MEMASANG 1 M2 LAPISAN IJUK TEBAL 10 CM, UNTUK BIDANG RESAPAN
A. TENAGA
Pekerja 0.1500 OH 85,000.00 12,750.00
Mandor 0.0150 OH 120,000.00 1,800.00
B. BAHAN
Ijuk 6.0000 kg 8,000.00 48,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 62,550.00
Overhead + Profit 15.0000 % 9,382.50
Harga Satuan Pekerjaan 71,932.50
A.2.3.1.14. PENGURUGAN 1M3 SIRTU PADAT
A. TENAGA
Pekerja 0.2500 OH 85,000.00 21,250.00
Mandor 0.0250 OH 120,000.00 3,000.00
B. BAHAN
Sirtu 1.2000 kg 100,000.00 120,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 144,250.00
Overhead + Profit 15.0000 % 21,637.50
Harga Satuan Pekerjaan 165,887.50
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

DIHITUNG 1 M2 HAMPARAN ABU BATU


Abu Batu 0.0050 m3 185,000.00 925.00
Pekerja 0.0015 HOK 85,000.00 127.50
Mandor 0.0005 HOK 120,000.00 60.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,112.50
Overhead + Profit 15.0000 % 166.88
Harga Satuan Pekerjaan 1,279.38

B PEKERJAAN PONDASI
A.3.2.1.1. PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP : 3 PP
A. TENAGA
Pekerja 1.5000 OH 85,000.00 127,500.00
Tukang Batu 0.7500 OH 100,000.00 75,000.00
Kepala Tukang 0.0750 OH 110,000.00 8,250.00
Mandor 0.0750 OH 120,000.00 9,000.00
B. BAHAN
Batu Belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Semen PC Type 1 202.0000 kg 1,200.00 242,400.00
Pasir Pasang 0.4850 m3 125,000.00 60,625.00
Jumlah Harga Tenaga, Bahan dan Peralatan 678,775.00
Overhead + Profit 15.0000 % 101,816.25
Harga Satuan Pekerjaan 780,591.25
A.3.2.1.2. PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP : 4 PP
A. TENAGA
Pekerja 1.5000 HOK 85,000.00 127,500.00
Tukang batu 0.7500 HOK 100,000.00 75,000.00
Kepala tukang 0.0750 HOK 110,000.00 8,250.00
Mandor 0.0750 HOK 120,000.00 9,000.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Semen Portland 163.0000 Kg 1,200.00 195,600.00
Pasir pasang 0.5200 m3 125,000.00 65,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 636,350.00
Overhead + Profit 15.0000 % 95,452.50
Harga Satuan Pekerjaan 731,802.50
A.3.2.1.2.1 PEMASANGAN 1 M3 PONDASI BATU BELAH CAMPURAN 1 SP : 4 PP
A. TENAGA
Pekerja 1.5000 HOK 85,000.00 127,500.00
Tukang batu 0.7500 HOK 100,000.00 75,000.00
Kepala tukang 0.0750 HOK 110,000.00 8,250.00
Mandor 0.0750 HOK 120,000.00 9,000.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Semen Portland 163.0000 Kg 1,200.00 195,600.00
Pasir beton 0.5200 m3 195,000.00 101,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 672,750.00
Overhead + Profit 15.0000 % 100,912.50
Harga Satuan Pekerjaan 773,662.50
C-03 MEMASANG 1 M3 PONDASI BATU BELAH CAMPURAN 1 PC : 5 PP
A. TENAGA
Pekerja 1.5000 HOK 85,000.00 127,500.00
Tukang batu 0.7500 HOK 100,000.00 75,000.00
Kepala tukang 0.0750 HOK 110,000.00 8,250.00
Mandor 0.0750 HOK 120,000.00 9,000.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Semen Portland 136.0000 Kg 1,200.00 163,200.00


Pasir pasang 0.5440 m3 125,000.00 68,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 606,950.00
Overhead + Profit 15.0000 % 91,042.50
Harga Satuan Pekerjaan 697,992.50
C-04 MEMASANG 1 M3 PONDASI BATU BELAH CAMPURAN 1 PC : 6 PP
A. TENAGA
Pekerja 1.5000 HOK 85,000.00 127,500.00
Tukang batu 0.7500 HOK 100,000.00 75,000.00
Kepala tukang 0.0750 HOK 110,000.00 8,250.00
Mandor 0.0750 HOK 120,000.00 9,000.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Semen Portland 117.0000 Kg 1,200.00 140,400.00
Pasir pasang 0.5610 m3 125,000.00 70,125.00
Jumlah Harga Tenaga, Bahan dan Peralatan 586,275.00
Overhead + Profit 15.0000 % 87,941.25
Harga Satuan Pekerjaan 674,216.25
C-05 MEMASANG 1 M3 PONDASI BATU BELAH CAMPURAN 1 PC : 8 PP
A. TENAGA
Pekerja 1.5000 HOK 85,000.00 127,500.00
Tukang batu 0.7500 HOK 100,000.00 75,000.00
Kepala tukang 0.0750 HOK 110,000.00 8,250.00
Mandor 0.0750 HOK 120,000.00 9,000.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Semen Portland 91.0000 Kg 1,200.00 109,200.00
Pasir pasang 0.5840 m3 125,000.00 73,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 557,950.00
Overhead + Profit 15.0000 % 83,692.50
Harga Satuan Pekerjaan 641,642.50
C-06 MEMASANG 1 M3 PONDASI BATU BELAH CAMPURAN 1 KP : 1 SM : 2 PP
A. TENAGA
Pekerja 1.5000 HOK 85,000.00 127,500.00
Tukang batu 0.7500 HOK 100,000.00 75,000.00
Kepala tukang 0.0750 HOK 110,000.00 8,250.00
Mandor 0.0750 HOK 120,000.00 9,000.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Kapur Padam 0.1700 m3 50,000.00 8,500.00
Semen Merah 0.1700 m3 1,200.00 204.00
Pasir pasang 0.3400 m3 125,000.00 42,500.00
Jumlah Harga Tenaga, Bahan dan Peralatan 426,954.00
Overhead + Profit 15.0000 % 64,043.10
Harga Satuan Pekerjaan 490,997.10
C-07 MEMASANG 1 M3 PONDASI BATU BELAH CAMPURAN 1 PC : 3 KP : 10 PP
A. TENAGA
Pekerja 1.5000 HOK 85,000.00 127,500.00
Tukang batu 0.7500 HOK 100,000.00 75,000.00
Kepala tukang 0.0750 HOK 110,000.00 8,250.00
Mandor 0.0750 HOK 120,000.00 9,000.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Semen Portland 61.0000 Kg 1,200.00 73,200.00
Kapur Padam 0.1470 m3 50,000.00 7,350.00
Pasir pasang 0.4920 m3 125,000.00 61,500.00
Jumlah Harga Tenaga, Bahan dan Peralatan 517,800.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Overhead + Profit 15.0000 % 77,670.00


Harga Satuan Pekerjaan 595,470.00
C-08 MEMASANG 1 M3 PONDASI BATU BELAH CAMPURAN 1/2 PC : 1 KP : 4 PP
A. TENAGA
Pekerja 1.5000 HOK 85,000.00 127,500.00
Tukang batu 0.7500 HOK 100,000.00 75,000.00
Kepala tukang 0.0750 HOK 110,000.00 8,250.00
Mandor 0.0750 HOK 120,000.00 9,000.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Semen Portland 41.0000 Kg 1,200.00 49,200.00
Kapur Padam 0.1310 m3 50,000.00 6,550.00
Pasir pasang 0.5230 m3 125,000.00 65,375.00
Jumlah Harga Tenaga, Bahan dan Peralatan 496,875.00
Overhead + Profit 15.0000 % 74,531.25
Harga Satuan Pekerjaan 571,406.25
A.3.2.1.9. 1 M3 PASANGAN PONDASI BATU KOSONG (ANSTAMPING)
A. TENAGA
Pekerja 0.7800 HOK 85,000.00 66,300.00
Tukang batu 0.3900 HOK 100,000.00 39,000.00
Kepala tukang 0.0390 HOK 110,000.00 4,290.00
Mandor 0.0390 HOK 120,000.00 4,680.00
B. BAHAN
Batu belah 15/20 cm 1.2000 m3 130,000.00 156,000.00
Pasir urug 0.4320 m3 85,000.00 36,720.00
Jumlah Harga Tenaga, Bahan dan Peralatan 306,990.00
Overhead + Profit 15.0000 % 46,048.50
Harga Satuan Pekerjaan 353,038.50
C-10 1 M3 PONDASI SIKLOP, 60% BETON CAMPURAN 1 PC : 2 PB : 3 KR DAN 40% BT BELAH
A. TENAGA
Pekerja 3.4000 HOK 85,000.00 289,000.00
Tukang batu 0.8500 HOK 100,000.00 85,000.00
Kepala tukang 0.0850 HOK 110,000.00 9,350.00
Mandor 0.1700 HOK 120,000.00 20,400.00
B. BAHAN
Batu belah 15/20 cm 0.4800 m3 130,000.00 62,400.00
Semen Portland 194.0000 Kg 1,200.00 232,800.00
Pasir beton 0.3120 m3 195,000.00 60,840.00
Koral beton 0.4680 m3 220,000.00 102,960.00
Besi beton 126.0000 Kg 12,000.00 1,512,000.00
Kawat beton 1.8000 Kg 17,500.00 31,500.00
Jumlah Harga Tenaga, Bahan dan Peralatan 2,406,250.00
Overhead + Profit 15.0000 % 360,937.50
Harga Satuan Pekerjaan 2,767,187.50
C-11 1 M3 PASANGAN PONDASI SUMURAN DIAMETER 100 cm
A. TENAGA
Pekerja 2.4000 HOK 85,000.00 204,000.00
Tukang batu 0.8000 HOK 100,000.00 80,000.00
Kepala tukang 0.0800 HOK 110,000.00 8,800.00
Mandor 0.1190 HOK 120,000.00 14,280.00
B. BAHAN
Batu belah 15/20 cm 0.4500 m3 130,000.00 58,500.00
Semen Portland 194.0000 Kg 1,200.00 232,800.00
Pasir beton 0.3120 m3 195,000.00 60,840.00
Koral beton 0.4680 m3 220,000.00 102,960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 762,180.00
Overhead + Profit 15.0000 % 114,327.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Harga Satuan Pekerjaan 876,507.00

C PEKERJAAN BETON
A.4.1.1.1. 1 M3 BETON UNTUK LANTAI KERJA ( BEDDING)
A. TENAGA
Pekerja 1.2000 HOK 85,000.00 102,000.00
Tukang batu 0.2000 HOK 100,000.00 20,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 230.0000 kg 1,200.00 276,000.00
Pasir beton 0.6379 m3 195,000.00 124,382.14
Koral beton 0.7607 m3 235,000.00 178,774.07
Air 200.0000 L 50.00 10,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 720,556.22
Overhead + Profit 15.0000 % 108,083.43
Harga Satuan Pekerjaan 828,639.65
D.02 1 M3 BETON 1 PC : 2 PB : 3KR MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 232.0000 kg 1,200.00 278,400.00
Pasir beton 0.5200 m3 195,000.00 101,400.00
Koral beton 0.7800 m3 235,000.00 183,300.00
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 754,640.00
Overhead + Profit 15.0000 % 113,196.00
Harga Satuan Pekerjaan 867,836.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

D-03 1 M3 BETON 1 PC : 2 PB : 3 KR MOLEN


A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 232.0000 kg 1,200.00 278,400.00
Pasir beton 0.5200 m3 195,000.00 101,400.00
Koral beton 0.7800 m3 235,000.00 183,300.00
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 775,950.00
Overhead + Profit 15.0000 % 116,392.50
Harga Satuan Pekerjaan 892,342.50
D-04 1 M3 BETON 1 PC : 3 PB : 5 KR MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 218.0000 kg 1,200.00 261,600.00
Pasir beton 0.5200 m3 195,000.00 101,400.00
Koral beton 0.8700 m3 235,000.00 204,450.00
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 758,990.00
Overhead + Profit 15.0000 % 113,848.50
Harga Satuan Pekerjaan 872,838.50
D-05 1 M3 BETON 1 PC : 3 PB : 5 KR MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 218.0000 kg 1,200.00 261,600.00
Pasir beton 0.5200 m3 195,000.00 101,400.00
Koral beton 0.8700 m3 235,000.00 204,450.00
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 780,300.00
Overhead + Profit 15.0000 % 117,045.00
Harga Satuan Pekerjaan 897,345.00
D-06 1 M3 BETON F'c = 7,4 Mpa (K100), SLUMP (12±2), W/C=0,87 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 247.0000 kg 1,200.00 296,400.00
Pasir beton 0.6207 m3 195,000.00 121,039.29
Koral beton 0.7400 m3 235,000.00 173,900.00
Air 215.0000 L 50.00 10,750.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Jumlah Harga Tenaga, Bahan dan Peralatan 782,879.29


Overhead + Profit 15.0000 % 117,431.89
Harga Satuan Pekerjaan 900,311.18
A.4.1.1.7. 1 M3 BETON F'c = 7,4 Mpa (K100), SLUMP (12±2), W/C=0,87 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 247.0000 kg 1,200.00 296,400.00
Pasir beton 0.6207 m3 195,000.00 121,039.29
Koral beton 0.7400 m3 235,000.00 173,900.00
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 804,189.29
Overhead + Profit 15.0000 % 120,628.39
Harga Satuan Pekerjaan 924,817.68
D-08 1 M3 BETON F'c = 9,8 Mpa (K125), SLUMP (12±2), W/C=0,78 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 276.0000 kg 1,200.00 331,200.00
Pasir beton 0.5914 m3 195,000.00 115,328.57
Koral beton 0.7496 m3 235,000.00 176,162.96
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 814,231.53
Overhead + Profit 15.0000 % 122,134.73
Harga Satuan Pekerjaan 936,366.26
A.4.1.1.9. 1 M3 BETON F'c = 9,8 Mpa (K125), SLUMP (12±2), W/C=0,78 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 276.0000 kg 1,200.00 331,200.00
Pasir beton 0.5914 m3 195,000.00 115,328.57
Koral beton 0.7496 m3 235,000.00 176,162.96
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 835,541.53
Overhead + Profit 15.0000 % 125,331.23
Harga Satuan Pekerjaan 960,872.76
D-10 1 M3 BETON F'c = 12,2 Mpa (K150), SLUMP (12±2), W/C=0,72 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 299.0000 kg 1,200.00 358,800.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pasir beton 0.5707 m3 195,000.00 111,289.29


Koral beton 0.7533 m3 235,000.00 177,033.33
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 838,662.62
Overhead + Profit 15.0000 % 125,799.39
Harga Satuan Pekerjaan 964,462.01
A.4.1.1.11. 1 M3 BETON F'c = 12,2 Mpa (K150), SLUMP (12±2), W/C=0,72 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 299.0000 kg 1,200.00 358,800.00
Pasir beton 0.5707 m3 195,000.00 111,289.29
Koral beton 0.7533 m3 235,000.00 177,033.33
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 859,972.62
Overhead + Profit 15.0000 % 128,995.89
Harga Satuan Pekerjaan 988,968.51
D-12 1 M3 BETON F'c = 14,5 Mpa (K175), SLUMP (12±2), W/C=0,66 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 326.0000 kg 1,200.00 391,200.00
Pasir beton 0.5429 m3 195,000.00 105,857.14
Koral beton 0.7622 m3 235,000.00 179,122.22
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 867,719.37
Overhead + Profit 15.0000 % 130,157.90
Harga Satuan Pekerjaan 997,877.27
A.4.1.1.13. 1 M3 BETON F'c = 14,5 Mpa (K175), SLUMP (12±2), W/C=0,66 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 326.0000 kg 1,200.00 391,200.00
Pasir beton 0.5429 m3 195,000.00 105,857.14
Koral beton 0.7622 m3 235,000.00 179,122.22
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 889,029.37
Overhead + Profit 15.0000 % 133,354.40
Harga Satuan Pekerjaan 1,022,383.77
A.4.1.1.14. 1 M3 BETON F'c = 14,5 Mpa (K175), SLUMP (12±2), W/C=0,66 READIMIX + POMPA
A. TENAGA
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 0.1380 HOK 100,000.00 13,800.00
Kepala tukang 0.0180 HOK 110,000.00 1,980.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Mandor 0.0500 HOK 120,000.00 6,000.00


B. BAHAN
Beton Readymix K-175 1.0500 M3 800,000.00 840,000.00
C. PERALATAN
Pompa Beton 0.1200 hari 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,276,780.00
Overhead + Profit 15.0000 % 191,517.00
Harga Satuan Pekerjaan 1,468,297.00
D-15 1 M3 BETON F'c = 16,9 Mpa (K200), SLUMP (12±2), W/C=0,61 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 352.0000 kg 1,200.00 422,400.00
Pasir beton 0.5221 m3 195,000.00 101,817.86
Koral beton 0.7637 m3 235,000.00 179,470.37
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 895,228.23
Overhead + Profit 15.0000 % 134,284.23
Harga Satuan Pekerjaan 1,029,512.46
A.4.1.1.16. 1 M3 BETON F'c = 16,9 Mpa (K200), SLUMP (12±2), W/C=0,61 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 352.0000 kg 1,200.00 422,400.00
Pasir beton 0.5221 m3 195,000.00 101,817.86
Koral beton 0.7637 m3 235,000.00 179,470.37
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 916,538.23
Overhead + Profit 15.0000 % 137,480.73
Harga Satuan Pekerjaan 1,054,018.96
A.4.1.1.17. 1 M3 BETON F'c = 16,9 Mpa (K200), SLUMP (12±2), W/C=0,61 READYMIX+POMPA
A. TENAGA
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 0.1380 HOK 100,000.00 13,800.00
Kepala tukang 0.0180 HOK 110,000.00 1,980.00
Mandor 0.0500 HOK 120,000.00 6,000.00
B. BAHAN
Beton Readymix K-200 1.0500 M3 840,000.00 882,000.00
C. PERALATAN
Pompa Beton 0.1200 hari 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,318,780.00
Overhead + Profit 15.0000 % 197,817.00
Harga Satuan Pekerjaan 1,516,597.00
D-18 1 M3 BETON F'c = 19,3 Mpa (K225), SLUMP (12±2), W/C=0,58 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

B. BAHAN
Semen portland 371.0000 kg 1,200.00 445,200.00
Pasir beton 0.4986 m3 195,000.00 97,221.43
Koral beton 0.7756 m3 235,000.00 182,255.56
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 916,216.98
Overhead + Profit 15.0000 % 137,432.55
Harga Satuan Pekerjaan 1,053,649.53
A.4.1.1.19. 1 M3 BETON F'c = 19,3 Mpa (K225), SLUMP (12±2), W/C=0,58 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 371.0000 kg 1,200.00 445,200.00
Pasir beton 0.4986 m3 195,000.00 97,221.43
Koral beton 0.7756 m3 235,000.00 182,255.56
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 937,526.98
Overhead + Profit 15.0000 % 140,629.05
Harga Satuan Pekerjaan 1,078,156.03
A.4.1.1.20. 1 M3 BETON F'c = 19,3 Mpa (K225), SLUMP (12±2), W/C=0,58 READYMIX+POMPA
A. TENAGA
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 0.1380 HOK 100,000.00 13,800.00
Kepala tukang 0.0180 HOK 110,000.00 1,980.00
Mandor 0.0500 HOK 120,000.00 6,000.00
B. BAHAN
Beton Readymix K-225 1.0500 M3 900,000.00 945,000.00
C. PERALATAN
Pompa Beton 0.1200 hari 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,381,780.00
Overhead + Profit 15.0000 % 207,267.00
Harga Satuan Pekerjaan 1,589,047.00
D-21 1 M3 BETON F'c = 21,7 Mpa (K250), SLUMP (12±2), W/C=0,56 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 384.0000 kg 1,200.00 460,800.00
Pasir beton 0.4943 m3 195,000.00 96,385.71
Koral beton 0.7696 m3 235,000.00 180,862.96
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 929,588.68
Overhead + Profit 15.0000 % 139,438.30
Harga Satuan Pekerjaan 1,069,026.98
A.4.1.1.22. 1 M3 BETON F'c = 21,7 Mpa (K250), SLUMP (12±2), W/C=0,56 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

B. BAHAN
Semen portland 384.0000 kg 1,200.00 460,800.00
Pasir beton 0.4943 m3 195,000.00 96,385.71
Koral beton 0.7696 m3 235,000.00 180,862.96
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 950,898.68
Overhead + Profit 15.0000 % 142,634.80
Harga Satuan Pekerjaan 1,093,533.48
A.4.1.1.23. 1 M3 BETON F'c = 21,7 Mpa (K250), SLUMP (12±2), W/C=0,56 READYMIX+POMPA
A. TENAGA
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 0.1380 HOK 100,000.00 13,800.00
Kepala tukang 0.0180 HOK 110,000.00 1,980.00
Mandor 0.0500 HOK 120,000.00 6,000.00
B. BAHAN
Beton Readymix K-250 1.0500 M3 900,000.00 945,000.00
C. PERALATAN
Pompa Beton 0.1200 hari 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,381,780.00
Overhead + Profit 15.0000 % 207,267.00
Harga Satuan Pekerjaan 1,589,047.00
D-24 1 M3 BETON F'c = 24 Mpa (K275), SLUMP (12±2), W/C=0,53 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 406.0000 kg 1,200.00 487,200.00
Pasir beton 0.4886 m3 195,000.00 95,271.43
Koral beton 0.7600 m3 235,000.00 178,600.00
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 952,611.43
Overhead + Profit 15.0000 % 142,891.71
Harga Satuan Pekerjaan 1,095,503.14
A.4.1.1.25. 1 M3 BETON F'c = 24 Mpa (K275), SLUMP (12±2), W/C=0,53 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 406.0000 kg 1,200.00 487,200.00
Pasir beton 0.4886 m3 195,000.00 95,271.43
Koral beton 0.7600 m3 235,000.00 178,600.00
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 973,921.43
Overhead + Profit 15.0000 % 146,088.21
Harga Satuan Pekerjaan 1,120,009.64
A.4.1.1.26. 1 M3 BETON F'c = 24 Mpa (K275), SLUMP (12±2), W/C=0,53 READYMIX+POMPA
A. TENAGA
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 0.1380 HOK 100,000.00 13,800.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Kepala tukang 0.0180 HOK 110,000.00 1,980.00


Mandor 0.0500 HOK 120,000.00 6,000.00
B. BAHAN
Beton Readymix K-275 1.0500 M3 950,000.00 997,500.00
C. PERALATAN
Pompa Beton 0.1200 hari 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,434,280.00
Overhead + Profit 15.0000 % 215,142.00
Harga Satuan Pekerjaan 1,649,422.00
D-27 1 M3 BETON F'c = 26,4 Mpa (K300), SLUMP (12±2), W/C=0,52 MANUAL
A. TENAGA
Pekerja 1.6500 HOK 85,000.00 140,250.00
Tukang batu 0.2750 HOK 100,000.00 27,500.00
Kepala tukang 0.0280 HOK 110,000.00 3,080.00
Mandor 0.0830 HOK 120,000.00 9,960.00
B. BAHAN
Semen portland 413.0000 kg 1,200.00 495,600.00
Pasir beton 0.4864 m3 195,000.00 94,853.57
Koral beton 0.7563 m3 235,000.00 177,729.63
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 959,723.20
Overhead + Profit 15.0000 % 143,958.48
Harga Satuan Pekerjaan 1,103,681.68
A.4.1.1.28. 1 M3 BETON F'c = 26,4 Mpa (K300), SLUMP (12±2), W/C=0,52 MOLEN
A. TENAGA
Pekerja 1.3200 HOK 85,000.00 112,200.00
Tukang batu 0.2050 HOK 100,000.00 20,500.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0600 HOK 120,000.00 7,200.00
B. BAHAN
Semen portland 413.0000 kg 1,200.00 495,600.00
Pasir beton 0.4864 m3 195,000.00 94,853.57
Koral beton 0.7563 m3 235,000.00 177,729.63
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 981,033.20
Overhead + Profit 15.0000 % 147,154.98
Harga Satuan Pekerjaan 1,128,188.18
A.4.1.1.29. 1 M3 BETON F'c = 26,4 Mpa (K300), SLUMP (12±2), W/C=0,52 READYMIX+POMPA
A. TENAGA
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 0.1380 HOK 100,000.00 13,800.00
Kepala tukang 0.0180 HOK 110,000.00 1,980.00
Mandor 0.0500 HOK 120,000.00 6,000.00
B. BAHAN
Beton Readymix K-300 1.0500 M3 950,000.00 997,500.00
C. PERALATAN
Pompa Beton 0.1200 hari 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,434,280.00
Overhead + Profit 15.0000 % 215,142.00
Harga Satuan Pekerjaan 1,649,422.00
D-30 1 M3 BETON F'c = 28,8 Mpa (K325), SLUMP (12±2), W/C=0,49 MANUAL
A. TENAGA
Pekerja 2.1000 HOK 85,000.00 178,500.00
Tukang batu 0.3500 HOK 100,000.00 35,000.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Mandor 0.1050 HOK 120,000.00 12,600.00


B. BAHAN
Semen portland 439.0000 kg 1,200.00 526,800.00
Pasir beton 0.4786 m3 195,000.00 93,321.43
Koral beton 0.7452 m3 235,000.00 175,118.52
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,035,939.95
Overhead + Profit 15.0000 % 155,390.99
Harga Satuan Pekerjaan 1,191,330.94
A.4.1.1.31. 1 M3 BETON F'c = 28,8 Mpa (K325), SLUMP (12±2), W/C=0,49 MOLEN
A. TENAGA
Pekerja 1.6800 HOK 85,000.00 142,800.00
Tukang batu 0.2630 HOK 100,000.00 26,300.00
Kepala tukang 0.0250 HOK 110,000.00 2,750.00
Mandor 0.0740 HOK 120,000.00 8,880.00
B. BAHAN
Semen portland 439.0000 kg 1,200.00 526,800.00
Pasir beton 0.4786 m3 195,000.00 93,321.43
Koral beton 0.7452 m3 235,000.00 175,118.52
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,046,719.95
Overhead + Profit 15.0000 % 157,007.99
Harga Satuan Pekerjaan 1,203,727.94
A.4.1.1.32. 1 M3 BETON F'c = 28,8 Mpa (K325), SLUMP (12±2), W/C=0,49 READYMIX+POMPA
A. TENAGA
Pekerja 1.2600 HOK 85,000.00 107,100.00
Tukang batu 0.1750 HOK 100,000.00 17,500.00
Kepala tukang 0.0210 HOK 110,000.00 2,310.00
Mandor 0.0630 HOK 120,000.00 7,560.00
B. BAHAN
Beton Readymix K-325 1.0500 M3 990,000.00 1,039,500.00
C. PERALATAN
Pompa Beton 0.1200 hari 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,503,970.00
Overhead + Profit 15.0000 % 225,595.50
Harga Satuan Pekerjaan 1,729,565.50
D-33 1 M3 BETON F'c = 31,2 Mpa (K350), SLUMP (12±2), W/C=0,48 MANUAL
A. TENAGA
Pekerja 2.1000 HOK 85,000.00 178,500.00
Tukang batu 0.3500 HOK 100,000.00 35,000.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.1050 HOK 120,000.00 12,600.00
B. BAHAN
Semen portland 448.0000 kg 1,200.00 537,600.00
Pasir beton 0.4764 m3 195,000.00 92,903.57
Koral beton 0.7407 m3 235,000.00 174,074.07
Air 215.0000 L 50.00 10,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,045,277.65
Overhead + Profit 15.0000 % 156,791.65
Harga Satuan Pekerjaan 1,202,069.29
A.4.1.1.34. 1 M3 BETON F'c = 31,2 Mpa (K350), SLUMP (12±2), W/C=0,48 MOLEN
A. TENAGA
Pekerja 1.6800 HOK 85,000.00 142,800.00
Tukang batu 0.2630 HOK 100,000.00 26,300.00
Kepala tukang 0.0250 HOK 110,000.00 2,750.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Mandor 0.0740 HOK 120,000.00 8,880.00


B. BAHAN
Semen portland 448.0000 kg 1,200.00 537,600.00
Pasir beton 0.4764 m3 195,000.00 92,903.57
Koral beton 0.7407 m3 235,000.00 174,074.07
Air 215.0000 L 50.00 10,750.00
C. PERALATAN
Molen 0,35 m3 0.2000 hari 300,000.00 60,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,056,057.65
Overhead + Profit 15.0000 % 158,408.65
Harga Satuan Pekerjaan 1,214,466.29
A.4.1.1.35. 1 M3 BETON F'c = 31,2 Mpa (K350), SLUMP (12±2), W/C=0,48 READYMIX+POMPA
A. TENAGA
Pekerja 1.2600 HOK 85,000.00 107,100.00
Tukang batu 0.1750 HOK 100,000.00 17,500.00
Kepala tukang 0.0210 HOK 110,000.00 2,310.00
Mandor 0.0630 HOK 120,000.00 7,560.00
B. BAHAN
Beton Readymix K-325 1.0500 M3 1,030,000.00 1,081,500.00
C. PERALATAN
Pompa Beton 0.1200 hari 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,545,970.00
Overhead + Profit 15.0000 % 231,895.50
Harga Satuan Pekerjaan 1,777,865.50
D.II. TENAGA DAN ALAT ANGKUT CAMPURAN BETON TIAP KENAIKAN 4M VERTIKAL DAN TIAP JARAK 25 M HORIZONTAL
D-36 PENGECORAN 1 M3 BETON JARAK <25 M, TINGGI/DALAM <1M
A. TENAGA
Pekerja 0.4100 HOK 85,000.00 34,850.00
Mandor 0.0200 HOK 120,000.00 2,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 37,250.00
Overhead + Profit 15.0000 % 5,587.50
Harga Satuan Pekerjaan 42,837.50
D-37 PENGECORAN 1 M3 BETON JARAK <25 M, TINGGI/DALAM <1M + VIBRATOR
A. TENAGA
Pekerja 0.5000 HOK 85,000.00 42,500.00
Mandor 0.0250 HOK 120,000.00 3,000.00
B. BAHAN
Vibrator 0.1000 HOK 250,000.00 25,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 70,500.00
Overhead + Profit 15.0000 % 10,575.00
Harga Satuan Pekerjaan 81,075.00
A.4.1.1.38. PEMAKAIAN VIBRATOR PADA PENGECORAN BETON/M3
A. TENAGA
Pekerja 0.2500 HOK 85,000.00 21,250.00
B. BAHAN
Vibrator 0.1000 HOK 250,000.00 25,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 46,250.00
Overhead + Profit 15.0000 % 6,937.50
Harga Satuan Pekerjaan 53,187.50
D-39 PENGECORAN 1 M3 BETON SETIAP TAMBAHAN JARAK 25 M (HORIZONTAL)
A. TENAGA
Pekerja 0.5000 HOK 85,000.00 42,500.00
Mandor 0.0250 HOK 120,000.00 3,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 45,500.00
Overhead + Profit 15.0000 % 6,825.00
Harga Satuan Pekerjaan 52,325.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

D-40 PENGECORAN 1 M3 BETON SETIAP KENAIKAN 3-4 M (VERTIKAL)


A. TENAGA
Pekerja 0.2500 HOK 85,000.00 21,250.00
Mandor 0.0100 HOK 120,000.00 1,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,450.00
Overhead + Profit 15.0000 % 3,367.50
Harga Satuan Pekerjaan 25,817.50
D-41 PENGECORAN 1 M3 BETON MENGGUNAKAN POMPA BETON
A. TENAGA
Pekerja 0.2000 HOK 85,000.00 17,000.00
Mandor 0.0100 HOK 120,000.00 1,200.00
B. BAHAN
Pompa Beton 0.1200 HOK 2,750,000.00 330,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 348,200.00
Overhead + Profit 15.0000 % 52,230.00
Harga Satuan Pekerjaan 400,430.00
D.III. PEKERJAAN PEMBESIAN BETON
A.4.1.1.17.1 PEMBESIAN 1 KG BESI POLOS ATAU ULIR
A. TENAGA
Pekerja 0.0070 OH 85,000.00 595.00
Tukang Besi 0.0070 OH 105,000.00 735.00
Kepala Tukang Besi 0.0007 OH 110,000.00 77.00
Mandor 0.0004 OH 120,000.00 48.00
B. BAHAN
Besi Beton (Polos / Ulir) 1.0500 kg 12,000.00 12,600.00
Kawat Beton 0.0150 kg 17,500.00 262.50
Jumlah Harga Tenaga, Bahan dan Peralatan 14,317.50
Overhead + Profit 15.0000 % 2,147.63
Harga Satuan Pekerjaan 16,465.13
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A.4.1.1.18.1 PEMBESIAN 1 KG JARING KAWAT BAJA (WIREMESH)


A. TENAGA
Pekerja 0.0025 OH 85,000.00 212.50
Tukang Besi 0.0025 OH 105,000.00 262.50
Kepala Tukang Besi 0.0002 OH 110,000.00 22.00
Mandor 0.0001 OH 120,000.00 12.00
B. BAHAN
Jaring Kawat Baja di las 1.0200 kg 15,000.00 15,300.00
Kawat Beton 0.0050 kg 17,500.00 87.50
C. PERALATAN
Mesin Potong Besi 0.0500 hari 50,000.00 2,500.00
Jumlah Harga Tenaga, Bahan dan Peralatan 18,396.50
Overhead + Profit 15.0000 % 2,759.48
Harga Satuan Pekerjaan 21,155.98

D-44 1 Kg KABEL PRESSTRESSED POLOS /STRANDS


A. TENAGA
Pekerja 0.0050 OH 85,000.00 425.00
Tukang Besi 0.0050 OH 105,000.00 525.00
Kepala Tukang Besi 0.0005 OH 110,000.00 55.00
Mandor 0.0003 OH 120,000.00 36.00
B. BAHAN
Kabel Prestres 1.0500 kg -
Besi Beton 0.1250 kg 12,000.00 1,500.00
Kawat Beton 0.0100 kg 17,500.00 175.00
C. PERALATAN
Jack Tension 0.1500 hari -
Jumlah Harga Tenaga, Bahan dan Peralatan 2,716.00
Overhead + Profit 15.0000 % 407.40
Harga Satuan Pekerjaan 3,123.40

A.4.1.1.20.1 1 m2 PASANG BEKISTING UNTUK PONDASI


A. TENAGA
Pekerja 0.5200 OH 85,000.00 44,200.00
Tukang Besi 0.2600 OH 105,000.00 27,300.00
Kepala Tukang Besi 0.0260 OH 110,000.00 2,860.00
Mandor 0.0260 OH 120,000.00 3,120.00
B. BAHAN
Kayu Kelas III 0.0400 m3 1,800,000.00 72,000.00
Paku biasa 2'-5" 0.3000 Kg 18,000.00 5,400.00
Minyak bekisting 0.1000 Ltr -
Jumlah Harga Tenaga, Bahan dan Peralatan 154,880.00
Overhead + Profit 15.0000 % 23,232.00
Harga Satuan Pekerjaan 178,112.00

DIHITUNG 1 m2 PASANG BEKISTING UNTUK PONDASI (2x PAKAI)


A. TENAGA
Pekerja 0.5200 OH 85,000.00 44,200.00
Tukang Besi 0.2600 OH 105,000.00 27,300.00
Kepala Tukang Besi 0.0260 OH 110,000.00 2,860.00
Mandor 0.0260 OH 120,000.00 3,120.00
B. BAHAN
Kayu Kelas III 0.0200 m3 1,800,000.00 36,000.00
Paku biasa 2'-5" 0.1500 Kg 18,000.00 2,700.00
Minyak bekisting 0.0500 Ltr -
Jumlah Harga Tenaga, Bahan dan Peralatan 116,180.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Overhead + Profit 15.0000 % 17,427.00


Harga Satuan Pekerjaan 133,607.00

A.4.1.1.21.1 1 m2 PASANG BEKISTING UNTUK SLOOF


A. TENAGA
Pekerja 0.5200 OH 85,000.00 44,200.00
Tukang Besi 0.2600 OH 105,000.00 27,300.00
Kepala Tukang Besi 0.0260 OH 110,000.00 2,860.00
Mandor 0.0260 OH 120,000.00 3,120.00
B. BAHAN
Kayu Kelas III 0.0450 m3 1,800,000.00 81,000.00
Paku biasa 2'-5" 0.3000 Kg 18,000.00 5,400.00
Minyak bekisting 0.1000 Ltr 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 163,880.00
Overhead + Profit 15.0000 % 24,582.00
Harga Satuan Pekerjaan 188,462.00

DIHITUNG 1 m2 PASANG BEKISTING UNTUK SLOOF (2x PAKAI)


A. TENAGA
Pekerja 0.5200 OH 85,000.00 44,200.00
Tukang Besi 0.2600 OH 105,000.00 27,300.00
Kepala Tukang Besi 0.0260 OH 110,000.00 2,860.00
Mandor 0.0260 OH 120,000.00 3,120.00
B. BAHAN
Kayu Kelas III (Papan) 0.0225 m3 2,000,000.00 45,000.00
Paku biasa 2'-5" 0.3000 Kg 18,000.00 5,400.00
Minyak bekisting 0.0500 Ltr 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 127,880.00
Overhead + Profit 15.0000 % 19,182.00
Harga Satuan Pekerjaan 147,062.00

A.4.1.1.22.1 1 m2 PASANG BEKISTING UNTUK KOLOM


A. TENAGA
Pekerja 0.6600 HOK 85,000.00 56,100.00
Tukang kayu 0.3300 HOK 105,000.00 34,650.00
Kepala tukang 0.0330 HOK 110,000.00 3,630.00
Mandor 0.0330 HOK 120,000.00 3,960.00
B. BAHAN
Kayu kelas III 0.0400 m3 1,800,000.00 72,000.00
Paku biasa 2'-5" 0.4000 Kg 18,000.00 7,200.00
Minyak bekisting 0.2000 Ltr 0.00 -
Balok kayu Kelas III 0.0150 m3 1,800,000.00 27,000.00
Papan Kayu Kelas III 0.0202 m3 1,800,000.00 36,288.00
bambu 2.0000 Btg 7,000.00 14,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 254,828.00
Overhead + Profit 15.0000 % 38,224.20
Harga Satuan Pekerjaan 293,052.20

DIHITUNG 1 m2 PASANG BEKISTING UNTUK KOLOM (2X PAKAI)


A. TENAGA
Pekerja 0.6600 HOK 85,000.00 56,100.00
Tukang kayu 0.3300 HOK 105,000.00 34,650.00
Kepala tukang 0.0330 HOK 110,000.00 3,630.00
Mandor 0.0330 HOK 120,000.00 3,960.00
B. BAHAN
Kayu kelas III 0.0200 m3 2,000,000.00 40,000.00
Paku biasa 2'-5" 0.4000 Kg 18,000.00 7,200.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Minyak bekisting 0.1000 Ltr 0.00 -


Balok kayu Kelas III 0.0075 m3 2,000,000.00 15,000.00
Papan Kayu Kelas III 0.0101 m3 2,000,000.00 20,160.00
bambu 1.0000 Btg 7,000.00 7,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 187,700.00
Overhead + Profit 15.0000 % 28,155.00
Harga Satuan Pekerjaan 215,855.00

A.4.1.1.23.1 1 m2 PASANG BEKISTING UNTUK BALOK


A. TENAGA
Pekerja 0.6600 HOK 85,000.00 56,100.00
Tukang kayu 0.3300 HOK 105,000.00 34,650.00
Kepala tukang 0.0330 HOK 110,000.00 3,630.00
Mandor 0.0330 HOK 120,000.00 3,960.00
B. BAHAN
Kayu kelas III 0.0400 m3 1,800,000.00 72,000.00
Paku biasa 2'-5" 0.4000 Kg 18,000.00 7,200.00
Minyak bekisting 0.2000 Ltr 0.00 -
Balok kayu Kelas III 0.0180 m3 1,800,000.00 32,400.00
Papan Kayu Kelas III 0.0202 M3 1,800,000.00 36,288.00
Bambu 2.0000 Btg 7,000.00 14,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 260,228.00
Overhead + Profit 15.0000 % 39,034.20
Harga Satuan Pekerjaan 299,262.20

DIHITUNG 1 m2 PASANG BEKISTING UNTUK BALOK (2X PAKAI)


A. TENAGA
Pekerja 0.6600 HOK 85,000.00 56,100.00
Tukang kayu 0.3300 HOK 105,000.00 34,650.00
Kepala tukang 0.0330 HOK 110,000.00 3,630.00
Mandor 0.0330 HOK 120,000.00 3,960.00
B. BAHAN
Kayu kelas III 0.0200 m3 2,000,000.00 40,000.00
Paku biasa 2'-5" 0.4000 Kg 18,000.00 7,200.00
Minyak bekisting 0.2000 Ltr 0.00 -
Balok kayu Kelas III 0.0090 m3 2,000,000.00 18,000.00
Papan Kayu Kelas III 0.0101 M3 2,000,000.00 20,160.00
Bambu 1.0000 Btg 7,000.00 7,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 190,700.00
Overhead + Profit 15.0000 % 28,605.00
Harga Satuan Pekerjaan 219,305.00
A.4.1.1.24.1 1 m2 PASANG BEKISTING PLAT LANTAI
A. TENAGA
Pekerja 0.6600 HOK 85,000.00 56,100.00
Tukang kayu 0.3300 HOK 105,000.00 34,650.00
Kepala tukang 0.0330 HOK 110,000.00 3,630.00
Mandor 0.0330 HOK 120,000.00 3,960.00
B. BAHAN
Kayu kelas III 0.0400 m3 1,800,000.00 72,000.00
Paku biasa 2'-5" 0.4000 Kg 18,000.00 7,200.00
Minyak bekisting 0.2000 Ltr 0.00 -
Balok kayu Kelas III 0.0150 m3 1,800,000.00 27,000.00
Papan Kayu Kelas III 0.0202 M3 2,000,000.00 40,320.00
Bambu* 6.0000 Btg 7,000.00 42,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 286,860.00
Overhead + Profit 15.0000 % 43,029.00
Harga Satuan Pekerjaan 329,889.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

DIHITUNG 1 m2 PASANG BEKISTING PLAT LANTAI (2X PAKAI)


A. TENAGA
Pekerja 0.6600 HOK 85,000.00 56,100.00
Tukang kayu 0.3300 HOK 105,000.00 34,650.00
Kepala tukang 0.0330 HOK 110,000.00 3,630.00
Mandor 0.0330 HOK 120,000.00 3,960.00
B. BAHAN
Kayu kelas III 0.0200 m3 2,000,000.00 40,000.00
Paku biasa 2'-5" 0.4000 Kg 18,000.00 7,200.00
Minyak bekisting 0.1000 Ltr 0.00 -
Balok kayu Kelas III 0.0075 m3 2,000,000.00 15,000.00
Papan Kayu Kelas III 0.0101 M3 2,000,000.00 20,160.00
Bambu* 3.0000 Btg 7,000.00 21,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 201,700.00
Overhead + Profit 15.0000 % 30,255.00
Harga Satuan Pekerjaan 231,955.00
A.4.1.1.25.1 1 m2 PASANG BEKISTING PLAT TANGGA
A. TENAGA
Pekerja 0.6600 HOK 85,000.00 56,100.00
Tukang kayu 0.3300 HOK 105,000.00 34,650.00
Kepala tukang 0.0330 HOK 110,000.00 3,630.00
Mandor 0.0330 HOK 120,000.00 3,960.00
B. BAHAN
Kayu kelas III 0.0300 m3 1,800,000.00 54,000.00
Paku biasa 2'-5" 0.4000 Kg 18,000.00 7,200.00
Minyak bekisting 0.2000 Ltr 0.00 -
Balok kayu Kelas III 0.0150 m3 1,800,000.00 27,000.00
Papan Kayu Kelas III 0.0202 M3 2,000,000.00 40,320.00
Bambu* 2.0000 Btg 7,000.00 14,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 240,860.00
Overhead + Profit 15.0000 % 36,129.00
Harga Satuan Pekerjaan 276,989.00
D-50 1 m2 PASANG JEMBATAN UNTUK PENGECORAN
A. TENAGA
Pekerja 0.1500 HOK 85,000.00 12,750.00
Tukang kayu 0.0500 HOK 105,000.00 5,250.00
Kepala tukang 0.0050 HOK 110,000.00 550.00
Mandor 0.0080 HOK 120,000.00 960.00
B. BAHAN
Kayu kelas III (papan) 0.0264 m3 2,000,000.00 52,800.00
Paku biasa 2"-5" 0.6000 Kg 18,000.00 10,800.00
Bambu 0.5000 Btg 7,000.00 3,500.00
Jumlah Harga Tenaga, Bahan dan Peralatan 86,610.00
Overhead + Profit 15.0000 % 12,991.50
Harga Satuan Pekerjaan 99,601.50

DIHITUNG 1 m3 MEMBUAT PLAT BETON T = 7 CM


Pas. Beton 1pc : 2pb : 3krl 1.0000 m3 754,640.00 754,640.00
Pas. Besi 201.5074 Kg 14,317.50 2,885,082.61
Pas. Bekisting 2x Pakai 8.2129 m2 201,700.00 1,656,533.29
Total 5,296,255.89
Total Harga 5,296,255.89
Keuntungan 794,438.38
Jumlah Total 6,090,694.28

DIHITUNG 1 m3 MEMBUAT PLAT BETON T = 7 CM


KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pas. Beton Site Mix 1pc : 2ps : 3kr 1.0000 m3 754,640.00 754,640.00
Pas. Besi 165.2361 Kg 14,317.50 2,365,767.74
Pas. Bekisting 2x Pakai 8.2129 m2 201,700.00 1,656,533.29
Total 4,776,941.02
Total Harga 4,776,941.02
Keuntungan 716,541.15
Jumlah Total 5,493,482.18

DIHITUNG 1 m3 MEMBUAT PLAT BETON T = 10 CM


Pas. Beton Site Mix 1pc : 2ps : 3kr 1.0000 m3 754,640.00 754,640.00
Pas. Besi 124.6284 Kg 14,317.50 1,784,366.43
Pas. Bekisting 2x Pakai 8.3000 m2 201,700.00 1,674,110.00
Total 4,213,116.43
Total Harga 4,213,116.43
Keuntungan 631,967.46
Jumlah Total 4,845,083.89
DIHITUNG 1 m3 MEMBUAT PLAT BETON T = 15 CM
Pas. Beton Site Mix 1pc : 2ps : 3kr 1.0000 m3 754,640.00 754,640.00
Pas. Besi 223.9342 Kg 14,317.50 3,206,177.51
Pas. Bekisting 2x Pakai 8.9667 m2 201,700.00 1,808,576.67
Total 5,769,394.17
Total Harga 5,769,394.17
Keuntungan 865,409.13
Jumlah Total 6,634,803.30
DIHITUNG 1 m3 MEMBUAT BALOK BETON BERTULANG 20/30
Pas. Beton Site Mix 1pc : 2ps : 3kr 1.0000 m3 754,640.00 754,640.00
Pas. Besi 82.0781 Kg 14,317.50 1,175,153.68
Pas. Bekisting 3.3333 m2 219,305.00 731,016.67
Total 2,660,810.34
Total Harga 2,660,810.34
Keuntungan 399,121.55
Jumlah Total 3,059,931.90

DIHITUNG 1 m3 MEMBUAT BALOK BETON BERTULANG 25/60


Pas. Beton Site Mix 1pc : 2ps : 3kr 1.0000 m3 754,640.00 754,640.00
Pas. Besi 77.3739 Kg 14,317.50 1,107,801.19
Pas. Bekisting 8.0667 m2 219,305.00 1,769,060.33
Total 3,631,501.52
Total Harga 3,631,501.52
Keuntungan 544,725.23
Jumlah Total 4,176,226.75

DIHITUNG 1 m3 MEMBUAT KOLOM BETON BERTULANG 15/15


Pas. Beton Site Mix 1pc : 2ps : 3kr 1.0000 m3 754,640.00 754,640.00
Pas. Besi 134.9599 Kg 14,317.50 1,932,288.70
Pas. Bekisting 13.3333 m2 215,855.00 2,878,066.67
Total 5,564,995.37
Total Harga 5,564,995.37
Keuntungan 834,749.30
Jumlah Total 6,399,744.67

DIHITUNG 1 m3 MEMBUAT KOLOM BETON BERTULANG 20/20


Pas. Beton Site Mix 1pc : 2ps : 3kr 1.0000 m3 754,640.00 754,640.00
Pas. Besi 126.3147 Kg 14,317.50 1,808,510.36
Pas. Bekisting 20.0000 m2 72,000.00 1,440,000.00
Total 4,003,150.36
Total Harga 4,003,150.36
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Keuntungan 600,472.55
Jumlah Total 4,603,622.92

D PEKERJAAN DINDING
E-01 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 2 Ps
A. TENAGA
Pekerja 0.6000 HOK 85,000.00 51,000.00
Tukang Batu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0300 HOK 120,000.00 3,600.00
B. BAHAN
Bata merah ( 5x11x22 ) cm 140.0000 bh 800.00 112,000.00
Semen Portland 43.5000 Kg 1,200.00 52,200.00
Pasir pasang 0.0800 m3 125,000.00 10,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 252,000.00
Overhead + Profit 15.0000 % 37,800.00
Harga Satuan Pekerjaan 289,800.00

A.4.4.1.2. 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 3 Ps


A. TENAGA
Pekerja 0.6000 HOK 85,000.00 51,000.00
Tukang Batu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0300 HOK 120,000.00 3,600.00
B. BAHAN
Bata merah ( 5x11x22 ) cm 140.0000 Bh 800.00 112,000.00
Semen Portland 32.9500 Kg 1,200.00 39,540.00
Pasir pasang 0.0910 m3 125,000.00 11,375.00
Jumlah Harga Tenaga, Bahan dan Peralatan 240,715.00
Overhead + Profit 15.0000 % 36,107.25
Harga Satuan Pekerjaan 276,822.25

A.4.4.1.3. 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 4 Ps


A. TENAGA
Pekerja 0.6000 HOK 85,000.00 51,000.00
Tukang Batu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0300 HOK 120,000.00 3,600.00
B. BAHAN
Bata merah ( 5x11x22 ) cm 140.0000 Bh 800.00 112,000.00
Semen Portland 26.5500 Kg 1,200.00 31,860.00
Pasir pasang 0.0930 m3 125,000.00 11,625.00
Jumlah Harga Tenaga, Bahan dan Peralatan 233,285.00
Overhead + Profit 15.0000 % 34,992.75
Harga Satuan Pekerjaan 268,277.75

A.4.4.1.4. 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 5 Ps


A. TENAGA
Pekerja 0.6000 HOK 85,000.00 51,000.00
Tukang Batu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0300 HOK 120,000.00 3,600.00
B. BAHAN
Bata merah ( 5x11x22 ) cm 140.0000 Bh 800.00 112,000.00
Semen Portland 22.2000 Kg 1,200.00 26,640.00
Pasir pasang 0.1020 m3 125,000.00 12,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 229,190.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Overhead + Profit 15.0000 % 34,378.50


Harga Satuan Pekerjaan 263,568.50

E-05 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 6 Ps

E-06 1 m2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 3 Kp : 10 Ps

E-07 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 2 Ps


A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Bata merah ( 5x11x22 ) cm 70.0000 Bh 800.00 56,000.00
Semen Portland 18.9500 Kg 1,200.00 22,740.00
Pasir pasang 0.0380 m3 125,000.00 4,750.00
Jumlah Harga Tenaga, Bahan dan Peralatan 122,390.00
Overhead + Profit 15.0000 % 18,358.50
Harga Satuan Pekerjaan 140,748.50

A.4.4.1.8. 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 Ps


A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Bata merah ( 5x11x22 ) cm 70.0000 Bh 800.00 56,000.00
Semen Portland 14.3700 Kg 1,200.00 17,244.00
Pasir pasang 0.0400 m3 125,000.00 5,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 117,144.00
Overhead + Profit 15.0000 % 17,571.60
Harga Satuan Pekerjaan 134,715.60

A.4.4.1.9. 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 4 Ps


A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Bata merah ( 5x11x22 ) cm 70.0000 Bh 800.00 56,000.00
Semen Portland 11.5000 Kg 1,200.00 13,800.00
Pasir pasang 0.0430 m3 125,000.00 5,375.00
Jumlah Harga Tenaga, Bahan dan Peralatan 114,075.00
Overhead + Profit 15.0000 % 17,111.25
Harga Satuan Pekerjaan 131,186.25

A.4.4.1.10. 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 Ps


A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Bata merah ( 5x11x22 ) cm 70.0000 Bh 800.00 56,000.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Semen Portland 9.6800 Kg 1,200.00 11,616.00


Pasir pasang 0.0450 m3 125,000.00 5,625.00
Jumlah Harga Tenaga, Bahan dan Peralatan 112,141.00
Overhead + Profit 15.0000 % 16,821.15
Harga Satuan Pekerjaan 128,962.15

E-11 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 6 Ps


E-12 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 8 Ps
E-13 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 Kp : 10 Ps
E-14 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Kp : 1 Sm : 1 Ps
E-15 1 m2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 Kp : 1 Sm : 2 Ps
E-16 1 m2 PASANGAN DINDING HB/CB 20, 1 PC : 3 Ps
E-17 1 m2 PASANGAN DINDING HB/CB 20, 1 PC : 4 Ps
E-18 1 m2 PASANGAN DINDING HB/CB 15, 1 PC : 3 Ps
E-19 1 m2 PASANGAN DINDING HB/CB 15, 1 PC : 4 Ps
E-20 1 m2 PASANGAN DINDING HB/CB 10, 1 PC : 3 Ps
E-21 1 m2 PASANGAN DINDING HB/CB 10, 1 PC : 4 Ps
E-22 1 m2 PASANGAN DINDING ROSTER /TERAWANG (12X11X24) cm 1 PC : 3 Ps
E-23 1 m2 PASANGAN DINDING ROSTER /TERAWANG (12X11X24) cm 1 PC : 4 Ps
E-24 1 m2 PASANGAN DINDING BATA BERONGGA EKSPOSE (5X11X24) cm 1 PC : 3 Ps
A.4.4.1.25. 1 m2 PASANGAN DINDING BATA RINGAN TEBAL 7,5 CM DENGAN MORTAR SIAP PAKAI
A. TENAGA
Pekerja 0.6700 HOK 85,000.00 56,950.00
Tukang Batu 1.3000 HOK 105,000.00 136,500.00
Kepala tukang 0.1300 HOK 110,000.00 14,300.00
Mandor 0.0030 HOK 120,000.00 360.00
B. BAHAN
Bata ringan tebal 7,5 cm 8.4000 m3 44,800.00 376,320.00
Mortar siap pakai 0.4730 Kg 4,312.50 2,039.81
Jumlah Harga Tenaga, Bahan dan Peralatan 586,469.81
Overhead + Profit 15.0000 % 87,970.47
Harga Satuan Pekerjaan 674,440.28
A.4.4.1.26. 1 m2 PASANGAN DINDING BATA RINGAN TEBAL 10 CM DENGAN MORTAR SIAP PAKAI
A. TENAGA
Pekerja 0.6710 HOK 85,000.00 57,035.00
Tukang Batu 1.3000 HOK 105,000.00 136,500.00
Kepala tukang 0.1300 HOK 110,000.00 14,300.00
Mandor 0.0030 HOK 120,000.00 360.00
B. BAHAN
Bata ringan tebal 10 cm 8.4000 m3 44,800.00 376,320.00
Mortar siap pakai 0.0630 Kg 4,312.50 271.69
Jumlah Harga Tenaga, Bahan dan Peralatan 584,786.69
Overhead + Profit 15.0000 % 87,718.00
Harga Satuan Pekerjaan 672,504.69
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

E PEKERJAAN PLESTERAN
F-01 1 m2 PLESTERAN 1 PC : 1 Ps, TEBAL 15 mm
A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Semen Portland 15.5040 kg 1,200.00 18,604.80
Pasir pasang 0.0160 m3 125,000.00 2,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 65,304.80
Overhead + Profit 15.0000 % 9,795.72
Harga Satuan Pekerjaan 75,100.52
Jumlah Total

F-02 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 15 mm


A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Semen Portland 10.2240 kg 1,200.00 12,268.80
Pasir pasang 0.0200 m3 125,000.00 2,500.00
Jumlah Harga Tenaga, Bahan dan Peralatan 59,468.80
Overhead + Profit 15.0000 % 8,920.32
Harga Satuan Pekerjaan 68,389.12

A.4.4.2.3. PEMASANGAN 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 15 mm


A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Semen Portland 7.7760 kg 1,200.00 9,331.20
Pasir pasang 0.0230 m3 125,000.00 2,875.00
Jumlah Harga Tenaga, Bahan dan Peralatan 56,906.20
Overhead + Profit 15.0000 % 8,535.93
Harga Satuan Pekerjaan 65,442.13

A.4.4.2.4. PEMASANGAN 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 15 mm


A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Semen Portland 6.2400 kg 1,200.00 7,488.00
Pasir pasang 0.0240 m3 125,000.00 3,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 55,188.00
Overhead + Profit 15.0000 % 8,278.20
Harga Satuan Pekerjaan 63,466.20
A.4.4.2.5. PEMASANGAN 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 15 mm
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Semen Portland 5.1840 kg 1,200.00 6,220.80
Pasir pasang 0.0260 m3 125,000.00 3,250.00
Jumlah Harga Tenaga, Bahan dan Peralatan 54,170.80
Overhead + Profit 15.0000 % 8,125.62
Harga Satuan Pekerjaan 62,296.42

F-06 1 m2 PLESTERAN 1 PC : 6 Ps, TEBAL 15 mm


F-07 1 m2 PLESTERAN 1 PC : 7 Ps, TEBAL 15 mm
F-08 1 m2 PLESTERAN 1 PC : 8 Ps, TEBAL 15 mm
F-09 1 m2 PLESTERAN 1 PC : 1/2 Kp : 3 Ps, TEBAL 15 mm
F-10 1 m2 PLESTERAN 1 PC : 2 Kp : 8 Ps, TEBAL 15 mm
F-11 1 m2 PLESTERAN 1 SM : 1 Kp: 1 Ps, TEBAL 15 mm
F-12 1 m2 PLESTERAN 1 SM : 1 Kp: 2 Ps, TEBAL 15 mm
F-13 1 m2 PLESTERAN 1 PC : 2 Ps, TEBAL 20 mm
F-14 1 m2 PLESTERAN 1 PC : 3 Ps, TEBAL 20 mm
F-15 1 m2 PLESTERAN 1 PC : 4 Ps, TEBAL 20 mm
F-16 1 m2 PLESTERAN 1 PC : 5 Ps, TEBAL 20 mm
F-17 1 m2 PLESTERAN 1 PC : 6 Ps, TEBAL 20 mm
F-18 1 m2 PLESTERAN 1 SM : 1 Kp: 2 Ps, TEBAL 20 mm
F-19 1 m2 BERAPEN 1 PC : 5 Ps, TEBAL 15 mm
F-20 1 m2 PLESTERAN SKONING 1 PC : 2 Ps, Lebar 10 mm
F-21 1 m2 PLESTERAN GRANIT 1 PC : 2 Granit, TEBAL 10 mm
F-22 1 m2 PLESTERAN TERASO 1 PC : 2 Batu Teraso, TEBAL 10 mm
F-23 1 m2 PLESTERAN CIPRAT 1 PC : 2 Ps
F-24 1 m2 FINISHING SIAR PASANGAN DINDING BATA MERAH (=20 m')
F-25 1 m2 FINISHING SIAR PASANGAN DINDING CONBLOCK EKSPOSE (=8 m')

A.4.4.2.26. PEMASANGAN 1 m2 FINISHING SIAR PASANGAN BATU KALI, 1 PC : 2 Ps


A. TENAGA
Pekerja 0.3000 HOK 85,000.00 25,500.00
Tukang Batu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.0150 HOK 120,000.00 1,800.00
B. BAHAN
Semen Portland 6.3400 kg 1,200.00 7,608.00
Pasir pasang 0.0120 m3 125,000.00 1,500.00
Jumlah Harga Tenaga, Bahan dan Peralatan 53,808.00
Overhead + Profit 15.0000 % 8,071.20
Harga Satuan Pekerjaan 61,879.20
A.4.4.2.27. PEMASANGAN 1 m2 ACIAN
A. TENAGA
Pekerja 0.2000 HOK 85,000.00 17,000.00
Tukang Batu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0100 HOK 120,000.00 1,200.00
B. BAHAN
Semen Portland 3.2500 kg 1,200.00 3,900.00
Jumlah Harga Tenaga, Bahan dan Peralatan 33,700.00
Overhead + Profit 15.0000 % 5,055.00
Harga Satuan Pekerjaan 38,755.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

F PEKERJAAN KAYU
G-01 1 M3 MEMBUAT DAN MEMASANG KUSEN PINTU DAN KUSEN JENDELA, KAYU KELAS I
A.4.6.1.2. 1 M3 MEMBUAT DAN MEMASANG KUSEN PINTU DAN KUSEN JENDELA, KAYU KELAS II ATAU III
A. TENAGA
Pekerja 6.0000 HOK 85,000.00 510,000.00
Tukang kayu 18.0000 HOK 105,000.00 1,890,000.00
Kepala tukang 1.8000 HOK 110,000.00 198,000.00
Mandor 0.3000 HOK 120,000.00 36,000.00
B. BAHAN
Kayu Balok Gunung Kelas II 1.2000 m3 2,700,000.00 3,240,000.00
Paku 10 cm 1.2500 kg 18,000.00 22,500.00
Lem 1.0000 kg -
Jumlah Harga Tenaga, Bahan dan Peralatan 5,896,500.00
Overhead + Profit 15.0000 % 884,475.00
Harga Satuan Pekerjaan 6,780,975.00

G-03 1 M2 MEMBUAT DAN MEMASANG PINTU KLAMP STANDAR, KAYU KELAS II


G-04 1 M2 MEMBUAT DAN MEMASANG PINTU KLAMP SEDERHANA, KAYU KELAS III
A.4.6.1.5. 1 M2 MEMBUAT DAN MEMASANG DAUN PINTU PANEL, KAYU KELAS I ATAU II
A. TENAGA
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang kayu 3.0000 HOK 105,000.00 315,000.00
Kepala tukang 0.3000 HOK 110,000.00 33,000.00
Mandor 0.0500 HOK 120,000.00 6,000.00
B. BAHAN
Papan Kayu Gunung Kelas II 0.0400 m3 2,700,000.00 108,000.00
Lem 0.5000 kg 61,600.00 30,800.00
Jumlah Harga Tenaga, Bahan dan Peralatan 577,800.00
Overhead + Profit 15.0000 % 86,670.00
Harga Satuan Pekerjaan 664,470.00
A.4.6.1.6. 1 M2 MEMBUAT DAN MEMASANG PINTU DAN JENDELA KACA, KAYU KELAS I ATAU II
A. TENAGA
Pekerja 0.8000 HOK 85,000.00 68,000.00
Tukang kayu 2.4000 HOK 105,000.00 252,000.00
Kepala tukang 0.2400 HOK 110,000.00 26,400.00
Mandor 0.0400 HOK 120,000.00 4,800.00
B. BAHAN
Papan Kayu Gunung Kelas II 0.0240 m3 2,700,000.00 64,800.00
Lem 0.3000 kg 61,600.00 18,480.00
Jumlah Harga Tenaga, Bahan dan Peralatan 434,480.00
Overhead + Profit 15.0000 % 65,172.00
Harga Satuan Pekerjaan 499,652.00

G-07 1 M2 MEMBUAT DAN MEMASANG PINTU DAN JENDELA JALUSI, KAYU KELAS I ATAU II
G-08 1 M2 MEMBUAT DAUN PINTU KAYU LAPIS (PLYWOOD) RANGKAP, RANGKA TERTUTUP KAYU KELAS II (LEBAR SAMPAI 90 cm)
G-09 1 M2 MEMBUAT DAUN PINTU PLYWOOD RANGKAP, RANGKA EXPOSE KAYU KELAS I ATAU II
G-10 1 M2 MEMASANG JALUSI KUSEN, KAYU KELAS I ATAU II
G-11 1 M2 MEMASANG TEAKWOOD RANGKAP, RANGKA EKSPOSE KAYU KELAS I
G-12 1 M2 MEMASANG TEAKWOOD RANGKAP LAPIS FORMIKA, RANGKA EKSPOSE KAYU KELAS II
G-13 1 M3 MEMASANG KONSTRUKSI KUDA-KUDA KONVENSIONAL, KAYU KELAS I, II, DAN III
G-14 1 M3 MEMASANG KONSTRUKSI KUDA-KUDA EXPOSE, KAYU KELAS I
G-15 1 M3 MEMASANG KONSTRUKSI GORDENG, KAYU KELAS II
G-16 1 M2 MEMASANG RANGKA ATAP GENTENG KERAMIK, KAYU KELAS II
G-17 1 M2 MEMASANG RANGKA ATAP GENTENG BETON, KAYU KELAS II
G-18 1 M2 MEMASANG RANGKA ATAP SIRAP, KAYU KELAS II
G-19 1 M2 MEMASANG RANGKA LANGIT-LANGIT (50x100) CM, KAYU KELAS II ATAU III
G-20 1 M2 MEMASANG RANGKA LANGIT-LANGIT (60x60) CM, KAYU KELAS II ATAU III
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

A. TENAGA
Pekerja 0.2000 HOK 85,000.00 17,000.00
Tukang kayu 0.3000 HOK 105,000.00 31,500.00
Kepala tukang 0.0300 HOK 110,000.00 3,300.00
Mandor 0.0100 HOK 120,000.00 1,200.00
B. BAHAN
Kaso (5x7) cm 0.0163 m3 2,700,000.00 44,010.00
Paku 7-10 cm 0.2500 kg 18,000.00 4,500.00
Jumlah Harga Tenaga, Bahan dan Peralatan 101,510.00
Overhead + Profit 15.0000 % 15,226.50
Harga Satuan Pekerjaan 116,736.50

G-21 1 M' MEMASANG LISPLANK UKURAN (3x20) cm, KAYU KELAS I ATAU II
G-22 1 M' MEMASANG LISPLANK UKURAN (3x30) cm, KAYU KELAS I ATAU II
A.4.6.1.23. 1 M2 MEMASANG RANGKA DINDING PEMISAH (60x120) cm, KAYU KELAS II ATAU III
A. TENAGA
Pekerja 0.1500 HOK 85,000.00 12,750.00
Tukang kayu 0.4500 HOK 105,000.00 47,250.00
Kepala tukang 0.0450 HOK 110,000.00 4,950.00
Mandor 0.0080 HOK 120,000.00 960.00
B. BAHAN
Kaso (5x7) cm 0.0280 m3 2,700,000.00 75,600.00
Paku 7-10 cm 0.1500 kg 18,000.00 2,700.00
Jumlah Harga Tenaga, Bahan dan Peralatan 144,210.00
Overhead + Profit 15.0000 % 21,631.50
Harga Satuan Pekerjaan 165,841.50
G-24 1 M2 MEMASANG DINDING PEMISAH TEAKWOOD RANGKAP, RANGKA KAYU KELAS II
G-25 1 M2 MEMASANG DINDING PEMISAH PLYWOOD RANGKAP, RANGKA KAYU KELAS II
G-26 1 M2 MEMASANG DINDING LAMBRIZIRING DARI PAPAN KAYU KELAS I
G-27 1 M2 MEMASANG DINDING LAMBRIZIRING DARI PLYWOOD UKURAN (120x240)cm
G-28 1 M2 MEMASANG DINDING BILIK, RANGKA KAYU KELAS III ATAU IV

G PEKERJAAN PENUTUP ATAP


A.4.5.2.1. 1 m2 PASANG ATAP GENTENG PALENTONG KECIL
Genteng palentong 25.0000 Bh 2,400.00 60,000.00
Pekerja 0.1500 HOK 85,000.00 12,750.00
Tukang kayu 0.0750 HOK 105,000.00 7,875.00
Kepala tukang 0.0075 HOK 110,000.00 825.00
Mandor 0.0080 HOK 120,000.00 960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 82,410.00
Overhead + Profit 15.0000 % 12,361.50
Harga Satuan Pekerjaan 94,771.50

H-02 1 m2 PASANG ATAP GENTENG KODOK / GLAZZUR


Genteng kodok 25.0000 Bh -
Pekerja 0.1500 HOK 85,000.00 12,750.00
Tukang kayu 0.0750 HOK 105,000.00 7,875.00
Kepala tukang 0.0080 HOK 110,000.00 880.00
Mandor 0.0080 HOK 120,000.00 960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,465.00
Overhead + Profit 15.0000 % 3,369.75
Harga Satuan Pekerjaan 25,834.75

A.4.5.2.3. 1 m2 PASANG ATAP GENTENG PALENTONG SUPER / BESAR


Genteng palentong super 12.0000 Bh 0.00 -
Pekerja 0.1500 HOK 85,000.00 12,750.00
Tukang kayu 0.0600 HOK 105,000.00 6,300.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Kepala tukang 0.0060 HOK 110,000.00 660.00


Mandor 0.0080 HOK 120,000.00 960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 20,670.00
Overhead + Profit 15.0000 % 3,100.50
Harga Satuan Pekerjaan 23,770.50

A.4.5.2.4. 1 m1 PASANG GENTENG BUBUNG PALENTONG


Genteng bubung palentong 5.0000 Bh 19,100.00 95,500.00
Semen portland 8.0000 Kg 1,200.00 9,600.00
Pasir pasang 0.0320 m3 125,000.00 4,000.00
Pekerja 0.4000 HOK 85,000.00 34,000.00
Tukang kayu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0020 HOK 120,000.00 240.00
Jumlah Harga Tenaga, Bahan dan Peralatan 166,540.00
Overhead + Profit 15.0000 % 24,981.00
Harga Satuan Pekerjaan 191,521.00

H-05 1 m' PASANG BUBUNG GENTENG KODOK GLAZZUR


Genteng bubung kodok 5.0000 Bh 0.00 -
Semen portland 8.0000 Zak 1,200.00 9,600.00
Pasir pasang 0.0320 m3 125,000.00 4,000.00
Pekerja 0.4000 HOK 85,000.00 34,000.00
Tukang kayu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0020 HOK 120,000.00 240.00
Jumlah Harga Tenaga, Bahan dan Peralatan 71,040.00
Overhead + Profit 15.0000 % 10,656.00
Harga Satuan Pekerjaan 81,696.00

A.4.5.2.6. 1 m' PASANG BUBUNG GENTENG PALENTONG BESAR


Genteng bubung palentong 4.0000 Bh -
Semen portland 8.0000 Kg 1,200.00 9,600.00
Pasir pasang 0.0320 m3 125,000.00 4,000.00
Pekerja 0.4000 HOK 85,000.00 34,000.00
Tukang kayu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0020 HOK 120,000.00 240.00
Jumlah Harga Tenaga, Bahan dan Peralatan 71,040.00
Overhead + Profit 15.0000 % 10,656.00
Harga Satuan Pekerjaan 81,696.00

H-07 1 m2 PASANG ROOF LIGHT FIBREGLASS ( 180X90 ) cm


Roof light fibreglass 0.6000 Lbr 0.00 -
Paku biasa 1/2"-1" 0.0500 Kg 18,000.00 900.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 21,445.00
Overhead + Profit 15.0000 % 3,216.75
Harga Satuan Pekerjaan 24,661.75

H-08 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,50X0,920 m )X 5 mm


KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Asbes gelombang 0.5000 Lbr 68,600.00 34,300.00


Paku pancing 60x230 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0750 HOK 105,000.00 7,875.00
Kepala tukang 0.0080 HOK 110,000.00 880.00
Mandor 0.0080 HOK 120,000.00 960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 58,075.00
Overhead + Profit 15.0000 % 8,711.25
Harga Satuan Pekerjaan 66,786.25

H-09 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,25X0,920 m )X 5 mm


Asbes gelombang 0.6000 Lbr 68,600.00 41,160.00
Paku pancing 60x230 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0750 HOK 105,000.00 7,875.00
Kepala tukang 0.0080 HOK 110,000.00 880.00
Mandor 0.0080 HOK 120,000.00 960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 64,935.00
Overhead + Profit 15.0000 % 9,740.25
Harga Satuan Pekerjaan 74,675.25

H-10 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,00X0,920 m )X 5 mm


Asbes gelombang 0.0600 Lbr 68,600.00 4,116.00
Paku pancing 60x230 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0700 HOK 105,000.00 7,350.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 27,136.00
Overhead + Profit 15.0000 % 4,070.40
Harga Satuan Pekerjaan 31,206.40

H-11 1 m2 PASANG ATAP ASBES GELOMBANG ( 1,80X0,920 m )X 5 mm


Asbes gelombang 0.7500 Lbr 68,600.00 51,450.00
Paku pancing 60x230 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0700 HOK 105,000.00 7,350.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 74,470.00
Overhead + Profit 15.0000 % 11,170.50
Harga Satuan Pekerjaan 85,640.50

H-12 1 m2 PASANG ATAP ASBES GELOMBANG ( 3,00X1,50 m )X 4 mm


Asbes gelombang 0.3500 Lbr 27,600.00 9,660.00
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0700 HOK 105,000.00 7,350.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 32,680.00
Overhead + Profit 15.0000 % 4,902.00
Harga Satuan Pekerjaan 37,582.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

H-13 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,70X1,50 m )X 4 mm


Asbes gelombang 0.4200 Lbr 27,600.00 11,592.00
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0700 HOK 105,000.00 7,350.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 34,612.00
Overhead + Profit 15.0000 % 5,191.80
Harga Satuan Pekerjaan 39,803.80

H-14 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,40X1,50 m )X 4 mm


Asbes gelombang 0.4400 Lbr 27,600.00 12,144.00
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 34,849.00
Overhead + Profit 15.0000 % 5,227.35
Harga Satuan Pekerjaan 40,076.35

H-15 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,10X1,50 m )X 4 mm


Asbes gelombang 0.5100 Lbr 27,600.00 14,076.00
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 36,781.00
Overhead + Profit 15.0000 % 5,517.15
Harga Satuan Pekerjaan 42,298.15

H-16 1 m2 PASANG ATAP ASBES GELOMBANG ( 5,50X1,50 m )X 4 mm


Asbes gelombang 0.8000 Lbr 27,600.00 22,080.00
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 44,785.00
Overhead + Profit 15.0000 % 6,717.75
Harga Satuan Pekerjaan 51,502.75

H-17 1 m2 PASANG ATAP ASBES GELOMBANG ( 3,00x1,80 m ) x 6 mm


Asbes gelombang 0.3700 Lbr -
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,705.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Overhead + Profit 15.0000 % 3,405.75


Harga Satuan Pekerjaan 26,110.75

H-18 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,70x1,80 m ) x 6 mm


Asbes gelombang 0.3800 Lbr -
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,705.00
Overhead + Profit 15.0000 % 3,405.75
Harga Satuan Pekerjaan 26,110.75

H-19 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,40x1,80 m ) x 6 mm


Asbes gelombang 0.4600 Lbr -
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,705.00
Overhead + Profit 15.0000 % 3,405.75
Harga Satuan Pekerjaan 26,110.75

H-20 1 m2 PASANG ATAP ASBES GELOMBANG ( 2,10x1,80 m ) x 6 mm


Asbes gelombang 0.4900 Lbr -
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,705.00
Overhead + Profit 15.0000 % 3,405.75
Harga Satuan Pekerjaan 26,110.75

H-21 1 m2 PASANG ATAP ASBES GELOMBANG ( 1,80x1,80 m ) x 6 mm


Asbes gelombang 0.5700 Lbr -
Paku pancing 0.1200 Kg 18,000.00 2,160.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang kayu 0.0670 HOK 105,000.00 7,035.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,705.00
Overhead + Profit 15.0000 % 3,405.75
Harga Satuan Pekerjaan 26,110.75

H-22 1 m' PASANG BUBUNG STEL GELOMBANG 0.92 m


Bubung stel gelombang 2.4000 Lbr -
Paku skrup 3.5" 6.0000 Bh 18,000.00 108,000.00
Pekerja 0.0840 HOK 85,000.00 7,140.00
Tukang kayu 0.1250 HOK 105,000.00 13,125.00
Kepala tukang 0.0130 HOK 110,000.00 1,430.00
Mandor 0.0040 HOK 120,000.00 480.00
Jumlah Harga Tenaga, Bahan dan Peralatan 130,175.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Overhead + Profit 15.0000 % 19,526.25


Harga Satuan Pekerjaan 149,701.25

H-25 1 m' PASANG NOK PATEN 0.92 m


Nok paten 1.2000 Lbr -
Paku skrup 3.5" 6.0000 Kg 18,000.00 108,000.00
Pekerja 0.0840 HOK 85,000.00 7,140.00
Tukang kayu 0.1250 HOK 105,000.00 13,125.00
Kepala tukang 0.0130 HOK 110,000.00 1,430.00
Mandor 0.0040 HOK 120,000.00 480.00
Jumlah Harga Tenaga, Bahan dan Peralatan 130,175.00
Overhead + Profit 15.0000 % 19,526.25
Harga Satuan Pekerjaan 149,701.25

H-28 1 m' PASANG NOK STEL RATA 0.92 m


Nok stel rata 1.1000 Lbr -
Paku skrup 3.5" 6.0000 Kg 18,000.00 108,000.00
Pekerja 0.1000 HOK 85,000.00 8,500.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0130 HOK 110,000.00 1,430.00
Mandor 0.0040 HOK 120,000.00 480.00
Jumlah Harga Tenaga, Bahan dan Peralatan 134,160.00
Overhead + Profit 15.0000 % 20,124.00
Harga Satuan Pekerjaan 154,284.00

H-30 1 m2 PASANG ATAP GENTENG BETON


Genteng beton 11.0000 bh 6,800.00 74,800.00
Paku biasa 2"-5" 0.0300 Kg 18,000.00 540.00
Pekerja 0.2000 HOK 85,000.00 17,000.00
Tukang kayu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0100 HOK 120,000.00 1,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 105,140.00
Overhead + Profit 15.0000 % 15,771.00
Harga Satuan Pekerjaan 120,911.00

A.4.5.2.32. 1 m2 PASANG ATAP GENTENG METAL UKURAN 80 x 100 ATAP PELANA


Genteng metal 1.3000 Buah 137,500.00 178,750.00
Paku biasa 2"-5" 0.2000 Kg 18,000.00 3,600.00
Pekerja 0.2000 HOK 85,000.00 17,000.00
Tukang kayu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0010 HOK 120,000.00 120.00
Jumlah Harga Tenaga, Bahan dan Peralatan 211,070.00
Overhead + Profit 15.0000 % 31,660.50
Harga Satuan Pekerjaan 242,730.50

A.4.5.2.33. 1 m2 PASANG ATAP GENTENG METAL UKURAN 80 x 100 ATAP JURAI


Genteng metal 2.0000 Buah 137,500.00 275,000.00
Paku biasa 2"-5" 0.2000 Kg 18,000.00 3,600.00
Pekerja 0.2000 HOK 85,000.00 17,000.00
Tukang kayu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0010 HOK 120,000.00 120.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Jumlah Harga Tenaga, Bahan dan Peralatan 307,320.00


Overhead + Profit 15.0000 % 46,098.00
Harga Satuan Pekerjaan 353,418.00

H-33 1 m2 PASANG ATAP SIRAP


KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Genteng sirap 60.0000 bh -


Paku biasa 1/2"-1" 0.2000 Kg 18,000.00 3,600.00
Pekerja 0.1660 HOK 85,000.00 14,110.00
Tukang kayu 0.2500 HOK 105,000.00 26,250.00
Kepala tukang 0.0250 HOK 110,000.00 2,750.00
Mandor 0.0080 HOK 120,000.00 960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 47,670.00
Overhead + Profit 15.0000 % 7,150.50
Harga Satuan Pekerjaan 54,820.50

H-34 1 m' PASANG NOK GENTENG BETON


Nok genteng beton 3.5000 bh -
Paku biasa 2"-5" 0.0500 Kg 18,000.00 900.00
Semen PC (50 kg) 0.2160 Zak 1,200.00 259.20
Pasir pasang 0.0320 m3 125,000.00 4,000.00
Semen warna 1.0000 Kg 13,000.00 13,000.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pekerja 0.4000 HOK 85,000.00 34,000.00


Tukang kayu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0200 HOK 120,000.00 2,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 77,759.20
Overhead + Profit 15.0000 % 11,663.88
Harga Satuan Pekerjaan 89,423.08

A.4.5.2.33. 1 m' PASANG NOK GENTENG METAL


Nok Genteng Metal 1.1000 bh 83,300.00 91,630.00
Paku biasa 1/2"-1" 0.0500 Kg 18,000.00 900.00
Pekerja 0.2500 HOK 85,000.00 21,250.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.0130 HOK 120,000.00 1,560.00
Jumlah Harga Tenaga, Bahan dan Peralatan 132,740.00
Overhead + Profit 15.0000 % 19,911.00
Harga Satuan Pekerjaan 152,651.00

H-37 1 m' PASANG NOK SIRAP


Seng plat 3"x6" BJLS 28 0.4000 Lbr 74,400.00 29,760.00
Paku biasa 1/2"-1" 0.0600 Kg 18,000.00 1,080.00
Paku biasa 2"-5" 0.0500 Kg 18,000.00 900.00
Kayu papan 3 cm 0.0040 m3 #NAME? #NAME?
Pekerja 0.1250 HOK 85,000.00 10,625.00
Tukang kayu 0.2500 HOK 105,000.00 26,250.00
Kepala tukang 0.0250 HOK 110,000.00 2,750.00
Mandor 0.0060 HOK 120,000.00 720.00
Jumlah Harga Tenaga, Bahan dan Peralatan #NAME?
Overhead + Profit 15.0000 % #NAME?
Harga Satuan Pekerjaan #NAME?

H-38 1 m2 PASANG ATAP SENG GELOMBANG


Seng gelombang 3"x6" BJLS 28 0.7000 Lbr 74,400.00 52,080.00
Paku biasa 1/2"-1" 0.0200 Kg 18,000.00 360.00
Pekerja 0.1200 HOK 85,000.00 10,200.00
Tukang kayu 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0060 HOK 110,000.00 660.00
Mandor 0.0060 HOK 120,000.00 720.00
Jumlah Harga Tenaga, Bahan dan Peralatan 70,320.00
Overhead + Profit 15.0000 % 10,548.00
Harga Satuan Pekerjaan 80,868.00

H-39 1 m2 PASANG ATAP NOK SENG


Seng plat 3"x6" BJLS 28 0.3000 Lbr -
Paku biasa 1/2"-1" 0.0400 Kg 18,000.00 720.00
Pekerja 0.1500 HOK 85,000.00 12,750.00
Tukang kayu 0.0700 HOK 105,000.00 7,350.00
Kepala tukang 0.0080 HOK 110,000.00 880.00
Mandor 0.0060 HOK 120,000.00 720.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,420.00
Overhead + Profit 15.0000 % 3,363.00
Harga Satuan Pekerjaan 25,783.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

H-40 1 m2 PASANG ATAP ALUMINIUM


Atap alluminium gelombang tebal 0.55 1.0500 m2 0.00 -
Paku hak panjang 15cm 0.0200 Kg 18,000.00 360.00
Pekerja 0.1500 HOK 85,000.00 12,750.00
Tukang kayu 0.7500 HOK 105,000.00 78,750.00
Kepala tukang 0.0080 HOK 110,000.00 880.00
Mandor 0.0060 HOK 120,000.00 720.00
Jumlah Harga Tenaga, Bahan dan Peralatan 93,460.00
Overhead + Profit 15.0000 % 14,019.00
Harga Satuan Pekerjaan 107,479.00

H-41 1 m2 PASANG NOK ALLUMINIUM


Nok standar 40 cm18, swg 22 1.2000 m2 0.00 -
Paku hak panjang 15cm 0.0400 Kg 18,000.00 720.00
Pekerja 0.1000 HOK 85,000.00 8,500.00
Tukang kayu 1.0000 HOK 105,000.00 105,000.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0100 HOK 120,000.00 1,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 116,520.00
Overhead + Profit 15.0000 % 17,478.00
Harga Satuan Pekerjaan 133,998.00

H-42 1 m2 PASANG ALLUMINIUM FOIL /SISALATION


Alluminiumfoil /sisalation 1.0500 m2 0.00 -
Pekerja 0.1500 HOK 85,000.00 12,750.00
Tukang kayu 0.0500 HOK 105,000.00 5,250.00
Kepala tukang 0.0050 HOK 110,000.00 550.00
Mandor 0.0080 HOK 120,000.00 960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 19,510.00
Overhead + Profit 15.0000 % 2,926.50
Harga Satuan Pekerjaan 22,436.50

H PEKERJAAN LANGIT-LANGIT (PLAFOND)


I-01 1 M2 PASANG LANGIT-LANGIT ASBES SEMEN, TEBAL 4 mm, 5 mm dan 6 mm
Plat asbes 1.1000 Lbr 9,000.00 9,900.00
Paku 0.0100 Kg 18,000.00 180.00
Pekerja 0.0300 HOK 85,000.00 2,550.00
Tukang kayu 0.0700 HOK 105,000.00 7,350.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0040 HOK 120,000.00 480.00
Jumlah Harga Tenaga, Bahan dan Peralatan 21,230.00
Overhead + Profit 15.0000 % 3,184.50
Harga Satuan Pekerjaan 24,414.50

I-02 1 M2 PASANG LANGIT-LANGIT AKUSTIK (30x30)cm


I-03 1 M2 PASANG LANGIT-LANGIT AKUSTIK (30x60)cm
I-04 1 M2 PASANG LANGIT-LANGIT AKUSTIK (60x120)cm
I-05 1 M2 PASANG LANGIT-LANGIT TRIPLEK (120x240)cm, TEBAL 3 mm, 4 mm dan 6 mm
I-06 1 M2 PASANG LANGIT-LANGIT LAMBRIZIRING KAYU, TEBAL 9 mm
I-07 1 M2 PASANG LANGIT-LANGIT GYPSUM BOARD UKURAN (1200x2400x9) mm, TEBAL 9 mm
Gypsum Board 0.3640 Lbr 60,000.00 21,840.00
Paku skrup 0.1100 Kg 18,000.00 1,980.00
Pekerja 0.1000 HOK 85,000.00 8,500.00
Tukang kayu 0.0500 HOK 105,000.00 5,250.00
Kepala tukang 0.0050 HOK 110,000.00 550.00
Mandor 0.0050 HOK 120,000.00 600.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Jumlah Harga Tenaga, Bahan dan Peralatan 38,720.00


Overhead + Profit 15.0000 % 5,808.00
Harga Satuan Pekerjaan 44,528.00

I-08 1 M' PASANG LIST PLAFOND GYPSUM PROFIL


List Gypsum Profil 1.0500 m' 11,000.00 11,550.00
Tepung Gypsum 0.1500 Kg 4,000.00 600.00
Pekerja 0.0600 HOK 85,000.00 5,100.00
Tukang kayu 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0060 HOK 110,000.00 660.00
Mandor 0.0030 HOK 120,000.00 360.00
Jumlah Harga Tenaga, Bahan dan Peralatan 24,570.00
Overhead + Profit 15.0000 % 3,685.50
Harga Satuan Pekerjaan 28,255.50

I-09 1 M2 PASANG LANGIT-LANGIT AKUSTIK (60x120)cm + RANGKA ALLUMINIUM


I-10 1 M' PASANG LIST LANGIT-LANGIT KAYU PROFIL
List kayu Profil 1.0500 m' 7,500.00 7,875.00
Paku 0.0100 Kg 18,000.00 180.00
Pekerja 0.0500 HOK 85,000.00 4,250.00
Tukang kayu 0.0500 HOK 105,000.00 5,250.00
Kepala tukang 0.0050 HOK 110,000.00 550.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 18,405.00
Overhead + Profit 15.0000 % 2,760.75
Harga Satuan Pekerjaan 21,165.75

PEKERJAAN SANITASI
J-01 MEMASANG 1 BUAH KLOSET DUDUK /MONOBLOK
Kloset duduk /monoblok 1.0000 Unit *) 1,700,000.00 1,700,000.00
Perlengkapan 6.00% Harga Kloset 1,700,000.00 102,000.00
Pekerja 3.3000 HOK 85,000.00 280,500.00
Tukang batu 1.1000 HOK 100,000.00 110,000.00
Kepala tukang 0.0010 HOK 110,000.00 110.00
Mandor 0.1600 HOK 120,000.00 19,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 2,211,810.00
Overhead + Profit 15.0000 % 331,771.50
Harga Satuan Pekerjaan 2,543,581.50

J-02 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN


Kloset jongkok porselin 1.0000 Bh 210,000.00 210,000.00
Semen Portland 6.0000 Kg 1,200.00 7,200.00
Pasir pasang 0.0100 m3 125,000.00 1,250.00
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 1.5000 HOK 100,000.00 150,000.00
Kepala tukang 1.5000 HOK 110,000.00 165,000.00
Mandor 0.1600 HOK 120,000.00 19,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 637,650.00
Overhead + Profit 15.0000 % 95,647.50
Harga Satuan Pekerjaan 733,297.50

J-04 MEMASANG 1 BUAH URINOIR


Urinoir 1.0000 Bh 650,000.00 650,000.00
Perlengkapan 30.0% Urinoir 650,000.00 195,000.00
Semen Portland 6.0000 Kg 1,200.00 7,200.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pasir pasang 0.0100 m3 125,000.00 1,250.00


Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 1.0000 HOK 100,000.00 100,000.00
Kepala tukang 0.1000 HOK 110,000.00 11,000.00
Mandor 0.1000 HOK 120,000.00 12,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,061,450.00
Overhead + Profit 15.0000 % 159,217.50
Harga Satuan Pekerjaan 1,220,667.50

J-05 MEMASANG 1 BUAH WASTAFEL


Wastafel 1.0000 Bh 1,250,000.00 1,250,000.00
Perlengkapan 12.0% wastafel 1,250,000.00 150,000.00
Semen Abu-abu 6.0000 Kg 1,200.00 7,200.00
Pasir pasang 0.0100 m3 125,000.00 1,250.00
Pekerja 1.2000 HOK 85,000.00 102,000.00
Tukang batu 1.4500 HOK 100,000.00 145,000.00
Kepala tukang 0.1500 HOK 110,000.00 16,500.00
Mandor 0.1000 HOK 120,000.00 12,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,683,950.00
Overhead + Profit 15.0000 % 252,592.50
Harga Satuan Pekerjaan 1,936,542.50

J-07 MEMASANG 1 BUAH BAK MANDI FIBREGLASS 0,30M3


Bak fibreglass 1.0000 Bh 285,000.00 285,000.00
Perlengkapan 18.0% Hrg Bak 285,000.00 51,300.00
Pembantu tukang 1.8000 HOK 85,000.00 153,000.00
Tukang batu 2.7000 HOK 100,000.00 270,000.00
Kepala tukang 0.5400 HOK 110,000.00 59,400.00
Mandor 0.1100 HOK 120,000.00 13,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 831,900.00
Overhead + Profit 15.0000 % 124,785.00
Harga Satuan Pekerjaan 956,685.00

J-08 MEMASANG 1 BUAH BAK MANDI BATU BATA VOLUME 0,30 M3


Batu bata 0.4000 m3 800.00 320.00
Semen Portland 120.0000 Kg 1,200.00 144,000.00
Pasir pasang 0.3000 m3 125,000.00 37,500.00
Porselen (11x11) cm 360.0000 Bh -
Semen nat 6.0000 Kg 1,200.00 7,200.00
Pekerja 6.0000 HOK 85,000.00 510,000.00
Tukang batu 3.0000 HOK 100,000.00 300,000.00
Kepala tukang 0.3000 HOK 110,000.00 33,000.00
Mandor 0.3000 HOK 120,000.00 36,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 1,068,020.00
Overhead + Profit 15.0000 % 160,203.00
Harga Satuan Pekerjaan 1,228,223.00

J-09 MEMASANG 1 BUAH BADKIP PERSELEN


Badkip 1.0000 bh -
Perlengkapan 20.0% Badkip -
Tukang batu 0.0750 HOK 100,000.00 7,500.00
Kepala tukang 0.7500 HOK 110,000.00 82,500.00
Mandor 0.2500 HOK 120,000.00 30,000.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Jumlah Harga Tenaga, Bahan dan Peralatan 120,000.00


Overhead + Profit 15.0000 % 18,000.00
Harga Satuan Pekerjaan 138,000.00

J-10 MEMBUAT 1 BUAH BAK BETON 1 M3 AIR


Beton 1 : 1.5 : 2.5 0.9000 m3 -
Besi beton 180.0000 Kg -
Kayu cetakan 8.0000 m2 -
Ubin porselen 5.0000 m2 -
Perlengkapan 10.0% Tot bahan -
Pekerja 3.5000 HOK 85,000.00 297,500.00
Tukang batu 4.5000 HOK 100,000.00 450,000.00
Kepala tukang 0.9000 HOK 110,000.00 99,000.00
Mandor 0.9000 HOK 120,000.00 108,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 954,500.00
Overhead + Profit 15.0000 % 143,175.00
Harga Satuan Pekerjaan 1,097,675.00

J-11 MEMASANG 1 BUAH BAK FIBREGLASS VOLUME 1M3 AIR


Bak fibreglass 1.0000 bh -
Perlengkapan 12.0% Badkip -
Pekerja 3.0000 HOK 85,000.00 255,000.00
Tukang batu 4.5000 HOK 100,000.00 450,000.00
Kepala tukang 0.9000 HOK 110,000.00 99,000.00
Mandor 0.9000 HOK 120,000.00 108,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 912,000.00
Overhead + Profit 15.0000 % 136,800.00
Harga Satuan Pekerjaan 1,048,800.00

J-14 MEMASANG 1 METER PIPA BETON, Ø 15-20 CM


Pipa beton 1.1000 bh -
Batu bata 0.0270 m3 -
Semen Portland 3.9200 Kg 1,200.00 4,704.00
Pasir Pasang 0.0560 m3 125,000.00 7,000.00
Pasir Urug 0.2400 m3 85,000.00 20,400.00
Pekerja 0.1400 HOK 85,000.00 11,900.00
Tukang batu 0.0700 HOK 100,000.00 7,000.00
Kepala tukang 0.0070 HOK 110,000.00 770.00
Mandor 0.0070 HOK 120,000.00 840.00
Jumlah Harga Tenaga, Bahan dan Peralatan 52,614.00
Overhead + Profit 15.0000 % 7,892.10
Harga Satuan Pekerjaan 60,506.10

J-15 MEMASANG 1 METER PIPA BETON, Ø 30-100 CM


Pipa beton 1.1000 bh 0.00 -
Batu bata 0.0550 m3 -
Semen Portland 10.3000 Kg 1,200.00 12,360.00
Pasir Pasang 0.0610 m3 125,000.00 7,625.00
Pasir Urug 0.0690 m3 85,000.00 5,865.00
Pekerja 0.3800 HOK 85,000.00 32,300.00
Tukang batu 0.1900 HOK 100,000.00 19,000.00
Kepala tukang 0.0190 HOK 110,000.00 2,090.00
Mandor 0.0190 HOK 120,000.00 2,280.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Jumlah Harga Tenaga, Bahan dan Peralatan 81,520.00


Overhead + Profit 15.0000 % 12,228.00
Harga Satuan Pekerjaan 93,748.00

J-16 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (30X30) CM TINGGI 35 CM
Batu bata 0.1450 m3 -
Semen Portland 44.0000 Kg 1,200.00 52,800.00
Pasir Pasang 0.0700 m3 125,000.00 8,750.00
Batu kerikil 0.0700 m3 -
Besi beton 1.6000 Kg -
Pasir beton 0.0600 m3 -
Pekerja 3.2000 HOK 85,000.00 272,000.00
Tukang batu 1.0150 HOK 100,000.00 101,500.00
Kepala tukang 0.0015 HOK 110,000.00 165.00
Mandor 0.0160 HOK 120,000.00 1,920.00
Jumlah Harga Tenaga, Bahan dan Peralatan 437,135.00
Overhead + Profit 15.0000 % 65,570.25
Harga Satuan Pekerjaan 502,705.25

J-17 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (45X45) CM TINGGI 50 CM
Batu bata 0.2500 m3 0.00 -
Semen Portland 77.0000 Kg 1,200.00 92,400.00
Pasir Pasang 0.1300 m3 125,000.00 16,250.00
Batu kerikil 0.0200 m3 0.00 -
Besi beton 2.6000 Kg 0.00 -
Pasir beton 0.0900 m3 0.00 -
Pekerja 1.4200 HOK 85,000.00 120,700.00
Tukang batu 0.4730 HOK 100,000.00 47,300.00
Kepala tukang 0.0470 HOK 110,000.00 5,170.00
Mandor 0.0710 HOK 120,000.00 8,520.00
Jumlah Harga Tenaga, Bahan dan Peralatan 290,340.00
Overhead + Profit 15.0000 % 43,551.00
Harga Satuan Pekerjaan 333,891.00

J-18 MEMASANG 1 BUAH BAK KONTROL PASANGAN BATU BATA (60x60) CM TINGGI 65 CM
Batu bata 0.3710 m3
Semen Portland 114.0000 Kg 1,200.00 136,800.00
Pasir Pasang 0.1840 m3 125,000.00 23,000.00
Batu koral 0.0330 m3 0.00 -
Besi beton 4.8500 Kg 0.00 -
Pasir beton 0.1200 m3 0.00 -
Pekerja 2.1600 HOK 85,000.00 183,600.00
Tukang batu 0.7200 HOK 85,000.00 61,200.00
Tukang gali 0.1000 HOK 100,000.00 10,000.00
Kepala tukang 0.0720 HOK 110,000.00 7,920.00
Mandor 0.1080 HOK 120,000.00 12,960.00
Jumlah Harga Tenaga, Bahan dan Peralatan 435,480.00
Overhead + Profit 15.0000 % 65,322.00
Harga Satuan Pekerjaan 500,802.00

J-19 MEMASANG 1 METER PIPA GALVANIS Ø 1/2"


Pipa galvanis 1.2000 m' 18,000.00 21,600.00
Perlengkapan 35.0% Hrg-pipa 18,000.00 6,300.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pekerja 0.0540 HOK 85,000.00 4,590.00


Tukang batu 0.0900 HOK 100,000.00 9,000.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0270 HOK 120,000.00 3,240.00
Jumlah Harga Tenaga, Bahan dan Peralatan 45,720.00
Overhead + Profit 15.0000 % 6,858.00
Harga Satuan Pekerjaan 52,578.00

J-20 MEMASANG 1 METER PIPA GALVANIS Ø 3/4"


Pipa galvanis 1.2000 m' 23,000.00 27,600.00
Perlengkapan 35.0% Hrg-pipa 23,000.00 8,050.00
Pekerja 0.0540 HOK 85,000.00 4,590.00
Tukang batu 0.0900 HOK 100,000.00 9,000.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0270 HOK 120,000.00 3,240.00
Jumlah Harga Tenaga, Bahan dan Peralatan 53,470.00
Overhead + Profit 15.0000 % 8,020.50
Harga Satuan Pekerjaan 61,490.50

A.5.1.1.21. PEMASANGAN 1 M' PIPA GALVANIS Ø 1"


A. TENAGA
Pekerja 0.0540 HOK 85,000.00 4,590.00
Tukang Batu 0.0900 HOK 105,000.00 9,450.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0270 HOK 120,000.00 3,240.00
B. BAHAN
Pipa galvanis 1" 1.2000 M' 0.00 -
Perlengkapan 0.3500 % 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 18,270.00
Overhead + Profit 15.0000 % 2,740.50
Harga Satuan Pekerjaan 21,010.50
A.5.1.1.22. PEMASANGAN 1 M' PIPA GALVANIS Ø 1 1/2"
A. TENAGA
Pekerja 0.1080 HOK 85,000.00 9,180.00
Tukang Batu 0.1800 HOK 105,000.00 18,900.00
Kepala tukang 0.0180 HOK 110,000.00 1,980.00
Mandor 0.0050 HOK 120,000.00 600.00
B. BAHAN
Pipa galvanis 1 1/2" 1.2000 M' 0.00 -
Perlengkapan 0.3500 % 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 30,660.00
Overhead + Profit 15.0000 % 4,599.00
Harga Satuan Pekerjaan 35,259.00
A.5.1.1.23. PEMASANGAN 1 M' PIPA GALVANIS Ø 3"
A. TENAGA
Pekerja 0.1350 HOK 85,000.00 11,475.00
Tukang Batu 0.2250 HOK 105,000.00 23,625.00
Kepala tukang 0.0230 HOK 110,000.00 2,530.00
Mandor 0.0070 HOK 120,000.00 840.00
B. BAHAN
Pipa galvanis 3" 1.2000 M' -
Perlengkapan 0.3500 % 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 38,470.00
Overhead + Profit 15.0000 % 5,770.50
Harga Satuan Pekerjaan 44,240.50
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

J-23 MEMASANG 1 METER PIPA GALVANIS Ø 3"


Pipa galvanis 1.2000 m' 0.00 -
Perlengkapan 35.0% Hrg-pipa 0.00 -
Pekerja 0.1080 HOK 85,000.00 9,180.00
Tukang batu 0.1800 HOK 100,000.00 18,000.00
Kepala tukang 0.0180 HOK 110,000.00 1,980.00
Mandor 0.0054 HOK 120,000.00 648.00
Jumlah Harga Tenaga, Bahan dan Peralatan 29,808.00
Overhead + Profit 15.0000 % 4,471.20
Harga Satuan Pekerjaan 34,279.20

J-24 MEMASANG 1 METER PIPA GALVANIS Ø 4"


Pipa galvanis 1.2000 m' 0.00 -
Perlengkapan 35.0% Hrg-pipa 0.00 -
Pekerja 0.1350 HOK 85,000.00 11,475.00
Tukang batu 0.2250 HOK 100,000.00 22,500.00
Kepala tukang 0.0225 HOK 110,000.00 2,475.00
Mandor 0.0068 HOK 120,000.00 816.00
Jumlah Harga Tenaga, Bahan dan Peralatan 37,266.00
Overhead + Profit 15.0000 % 5,589.90
Harga Satuan Pekerjaan 42,855.90

A.5.1.1.25. PEMASANGAN 1 M' PIPA PVC type AW Ø 1/2"


A. TENAGA
Pekerja 0.0360 HOK 85,000.00 3,060.00
Tukang Batu 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0060 HOK 110,000.00 660.00
Mandor 0.0020 HOK 120,000.00 240.00
B. BAHAN
Pipa PVC 1/2" 1.2000 M' 6,750.00 8,100.00
Perlengkapan 0.3500 % 6,750.00 2,362.50
Jumlah Harga Tenaga, Bahan dan Peralatan 20,722.50
Overhead + Profit 15.0000 % 3,108.38
Harga Satuan Pekerjaan 23,830.88

A.5.1.1.26. PEMASANGAN 1 M' PIPA PVC type AW Ø 3/4"


A. TENAGA
Pekerja 0.0360 HOK 85,000.00 3,060.00
Tukang Batu 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0060 HOK 110,000.00 660.00
Mandor 0.0020 HOK 120,000.00 240.00
B. BAHAN
Pipa PVC 3/4" 1.2000 M' 8,750.00 10,500.00
Perlengkapan 0.3500 % 8,750.00 3,062.50
Jumlah Harga Tenaga, Bahan dan Peralatan 23,822.50
Overhead + Profit 15.0000 % 3,573.38
Harga Satuan Pekerjaan 27,395.88
A.5.1.1.27. PEMASANGAN 1 M' PIPA PVC type AW Ø 1"
A. TENAGA
Pekerja 0.0360 HOK 85,000.00 3,060.00
Tukang Batu 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0060 HOK 110,000.00 660.00
Mandor 0.0020 HOK 120,000.00 240.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

B. BAHAN
Pipa PVC 1" 1.2000 M' 11,250.00 13,500.00
Perlengkapan 0.3500 % 11,250.00 3,937.50
Jumlah Harga Tenaga, Bahan dan Peralatan 27,697.50
Overhead + Profit 15.0000 % 4,154.63
Harga Satuan Pekerjaan 31,852.13
A.5.1.1.28. PEMASANGAN 1 M' PIPA PVC type AW Ø 1 1/2"
A. TENAGA
Pekerja 0.0540 HOK 85,000.00 4,590.00
Tukang Batu 0.0900 HOK 105,000.00 9,450.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0030 HOK 120,000.00 360.00
B. BAHAN
Pipa PVC 1 1/2" 1.2000 M' 18,750.00 22,500.00
Perlengkapan 0.3500 % 18,750.00 6,562.50
Jumlah Harga Tenaga, Bahan dan Peralatan 44,452.50
Overhead + Profit 15.0000 % 6,667.88
Harga Satuan Pekerjaan 51,120.38
A.5.1.1.33. PEMASANGAN 1 M' PIPA AIR LIMBAH JENIS PIPA TANAH Ø 20 CM
A. TENAGA
Pekerja 0.0800 HOK 85,000.00 6,800.00
Tukang Batu 0.0400 HOK 105,000.00 4,200.00
Kepala tukang 0.0040 HOK 110,000.00 440.00
Mandor 0.0040 HOK 120,000.00 480.00
B. BAHAN
Pipa tanah 1.6000 bh 208,333.33 333,333.33
Semen Portland 35.0000 kg 1,200.00 42,000.00
Pasir Pasang 0.0140 M3 125,000.00 1,750.00
Pasir Urug 0.0140 M3 85,000.00 1,190.00
Jumlah Harga Tenaga, Bahan dan Peralatan 390,193.33
Overhead + Profit 15.0000 % 58,529.00
Harga Satuan Pekerjaan 448,722.33
P.16 MEMASANG 1 METER PIPA SULING-SULING Ø 1 1/2"
A. TENAGA
Pekerja 0.1000 HOK 60,000.00 6,000.00
Mandor 0.0100 HOK 120,000.00 1,200.00
B. BAHAN
Pipa PVC dia.1,5" 1.0500 M' 18,750.00 19,687.50
Jumlah Harga Tenaga, Bahan dan Peralatan 26,887.50
Overhead + Profit 15.0000 % 4,033.13
Harga Satuan Pekerjaan 30,920.63

J-29 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2"


Pipa PVC 1.2000 m' 25,000.00 30,000.00
Perlengkapan 35.0% Hrg-pipa 25,000.00 8,750.00
Pekerja 0.0540 HOK 85,000.00 4,590.00
Tukang batu 0.0900 HOK 100,000.00 9,000.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0027 HOK 120,000.00 324.00
Jumlah Harga Tenaga, Bahan dan Peralatan 53,654.00
Overhead + Profit 15.0000 % 8,048.10
Harga Satuan Pekerjaan 61,702.10

J-30 MEMASANG 1 METER PIPA PVC TIPE AW Ø 2 1/2"


Pipa PVC 1.2000 m' 35,000.00 42,000.00
Perlengkapan 35.0% Hrg-pipa 35,000.00 12,250.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pekerja 0.0360 HOK 85,000.00 3,060.00


Tukang batu 0.0600 HOK 100,000.00 6,000.00
Kepala tukang 0.0060 HOK 110,000.00 660.00
Mandor 0.0018 HOK 120,000.00 216.00
Jumlah Harga Tenaga, Bahan dan Peralatan 64,186.00
Overhead + Profit 15.0000 % 9,627.90
Harga Satuan Pekerjaan 73,813.90

J-31 MEMASANG 1 METER PIPA PVC TIPE AW Ø 3"


Pipa PVC 1.2000 m' 50,000.00 60,000.00
Perlengkapan 35.0% Hrg-pipa 50,000.00 17,500.00
Pekerja 0.0810 HOK 85,000.00 6,885.00
Tukang batu 0.1350 HOK 100,000.00 13,500.00
Kepala tukang 0.0135 HOK 110,000.00 1,485.00
Mandor 0.0041 HOK 120,000.00 492.00
Jumlah Harga Tenaga, Bahan dan Peralatan 99,862.00
Overhead + Profit 15.0000 % 14,979.30
Harga Satuan Pekerjaan 114,841.30

A.5.1.1.32 PEMASANGAN 1 METER PIPA PVC Ø 4"


A. TENAGA
Pekerja 0.0810 HOK 85,000.00 6,885.00
Tukang Batu 0.1350 HOK 105,000.00 14,175.00
Kepala tukang 0.0135 HOK 110,000.00 1,485.00
Mandor 0.0040 HOK 120,000.00 480.00
B. BAHAN
Pipa PVC 4" 1.2000 M' 0.00 -
Perlengkapan 15.0000 % 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 23,025.00
Overhead + Profit 35.0000 % 8,058.75
Harga Satuan Pekerjaan 31,083.75

J-33 MEMASANG 1 BUAH BAK CUCI PIRING STAINLESS-STEEL


Bak cuci stainles steel 1.0000 Bh -
Water drain + asesories 1.0000 Set -
Pekerja 0.0300 HOK 85,000.00 2,550.00
Tukang batu 0.3000 HOK 100,000.00 30,000.00
Kepala tukang 0.0300 HOK 110,000.00 3,300.00
Mandor 0.0015 HOK 120,000.00 180.00
Jumlah Harga Tenaga, Bahan dan Peralatan 36,030.00
Overhead + Profit 15.0000 % 5,404.50
Harga Satuan Pekerjaan 41,434.50

J-35 MEMASANG 1 BUAH KRAN Ø 1/2" ATAU Ø 3/4"


Kran air 1.0000 Bh 15,000.00 15,000.00
Seal tape 0.0250 Set 1,500.00 37.50
Pekerja 0.0100 HOK 85,000.00 850.00
Tukang batu 0.1000 HOK 100,000.00 10,000.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 27,587.50
Overhead + Profit 15.0000 % 4,138.13
Harga Satuan Pekerjaan 31,725.63
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

J-36 MEMASANG 1 BUAH FLOOR DRAIN


Floor drain 1.0000 Bh 45,000.00 45,000.00
Pekerja 0.0100 HOK 85,000.00 850.00
Tukang batu 0.1000 HOK 100,000.00 10,000.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 57,550.00
Overhead + Profit 15.0000 % 8,632.50
Harga Satuan Pekerjaan 66,182.50

A.4.2.1.1. 1 Kg PASANG BESI PROFIL


A. TENAGA
Pekerja 0.0600 HOK 85,000.00 5,100.00
Tukang Las Konstruksi 0.0600 HOK 105,000.00 6,300.00
Kepala Tukang 0.0060 HOK 110,000.00 660.00
Mandor 0.0030 HOK 120,000.00 360.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

B. BAHAN
Besi Profil 1.1500 kg 15,000.00 17,250.00
Jumlah Harga Tenaga, Bahan dan Peralatan 29,670.00
Overhead + Profit 15.0000 % 4,450.50
Harga Satuan Pekerjaan 34,120.50

K-02 1 Kg PASANG RANGKA KUDA-KUDA BAJA IWF


K-03 100 Kg PEKERJAAN PERAKITAN
K-04 1 m2 MEMBUAT PINTU BESI PLAT BAJA TEBAL 2 mm RANGKAP, RANGKA BAJA SIKU
K-05 1 cm PEKERJAAN PENGELASAN DENGAN LAS LISTRIK
K-06 1 m2 MEMBUAT RANGKA JENDELA BESI SCUARE TUBE 25x5 cm
K-07 1 m2 PASANG PINTU ROLLING DOOR BESI
K-08 1 m2 PASANG PINTU LIPAT (FOLDING DOOR)
K-09 1 m2 PASANG SUNSCREEN ALLUMUNIUM
K-10 1 m2 PASANG ROLLING DOOR ALLUMUNIUM
K-11 1 M' PASANG KUSEN PINTU ALUMUNIUM
Profil Alumunium 1.1500 m' 0.00 -
Skrup Fixer 2.0000 bh 0.00 -
sealant 0.0600 Tube 0.00 -
Pekerja 0.0430 HOK 85,000.00 3,655.00
Tukang Khusus Alumunium 0.0430 HOK 105,000.00 4,515.00
Kepala tukang 0.0043 HOK 110,000.00 473.00
Mandor 0.0021 HOK 120,000.00 252.00
Jumlah Harga Tenaga, Bahan dan Peralatan 8,895.00
Overhead + Profit 15.0000 % 1,334.25
Harga Satuan Pekerjaan 10,229.25

K-12 1 M2 PASANG PINTU ALUMUNIUM STRIP LEBAR 8 CM


Profil Alumunium 4.4000 m' 0.00 -
Alumunium Strip 14.6000 m' 0.00 -
Pekerja 0.0850 HOK 85,000.00 7,225.00
Tukang Khusus Alumunium 0.0850 HOK 105,000.00 8,925.00
Kepala tukang 0.0085 HOK 110,000.00 935.00
Mandor 0.0042 HOK 120,000.00 504.00
Jumlah Harga Tenaga, Bahan dan Peralatan 17,589.00
Overhead + Profit 15.0000 % 2,638.35
Harga Satuan Pekerjaan 20,227.35

K-13 1 m2 PASANG PINTU KACA RANGKA ALLUMINIUM


K-14 1 m2 PASANG VENETIONS BLINDS DAN VERTICAL BLINDS
K-15 1 m2 PASANG TERALIS BESI STRIP 2x3 mm
K-16 1 m2 PASANG KAWAT NYAMUK
K-17 1 m2 PASANG JENDELA NAKO & TERALIS
K-18 1 m' PASANG TALANG DATAR/JURAI SENG BJLS 28 LEBAR 90 cm
K-19 1 m' PASANG TALANG 1/2 LINGKARAN D-15 cm SENG PLAT BJLS 30 LEBAR 45 cm

L PEKERJAAN KUNCI DAN KACA


L-01 1 BUAH PASANG KUNCI TANAM
Kunci tanam antik 1.0000 bh 35,000.00 35,000.00
Pekerja 0.0600 HOK 85,000.00 5,100.00
Tukang kayu 0.6000 HOK 105,000.00 63,000.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Kepala tukang 0.0600 HOK 110,000.00 6,600.00


Mandor 0.0030 HOK 120,000.00 360.00
Jumlah Harga Tenaga, Bahan dan Peralatan 110,060.00
Overhead + Profit 15.0000 % 16,509.00
Harga Satuan Pekerjaan 126,569.00

L-02 1 BUAH PASANG KUNCI TANAM BIASA


Kunci tanam biasa 1.0000 bh 135,000.00 135,000.00
Pekerja 0.0100 HOK 85,000.00 850.00
Tukang kayu 0.5000 HOK 105,000.00 52,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 190,050.00
Overhead + Profit 15.0000 % 28,507.50
Harga Satuan Pekerjaan 218,557.50

L-03 1 BUAH PASANG KUNCI TANAM KAMAR MANDI


Kunci tanam kamar mandi 1.0000 bh 135,000.00 135,000.00
Pekerja 0.0050 HOK 85,000.00 425.00
Tukang kayu 0.5000 HOK 105,000.00 52,500.00
Kepala tukang 0.0050 HOK 110,000.00 550.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 188,775.00
Overhead + Profit 15.0000 % 28,316.25
Harga Satuan Pekerjaan 217,091.25

L-04 1 BUAH PASANG KUNCI SILINDER


Kunci silinder 1.0000 bh 70,100.00 70,100.00
Pekerja 0.0050 HOK 85,000.00 425.00
Tukang kayu 0.5000 HOK 105,000.00 52,500.00
Kepala tukang 0.0050 HOK 110,000.00 550.00
Mandor 0.00025 HOK 120,000.00 30.00
Jumlah Harga Tenaga, Bahan dan Peralatan 123,605.00
Overhead + Profit 15.0000 % 18,540.75
Harga Satuan Pekerjaan 142,145.75

L-05 1 BUAH PASANG ENGSEL PINTU


Engsel pintu 1.0000 bh 18,500.00 18,500.00
Pekerja 0.0150 HOK 85,000.00 1,275.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.00075 HOK 120,000.00 90.00
Jumlah Harga Tenaga, Bahan dan Peralatan 37,265.00
Overhead + Profit 15.0000 % 5,589.75
Harga Satuan Pekerjaan 42,854.75

L-06 1 BUAH PASANG ENGSEL JENDELA KUPU-KUPU


Engsel jendela 1.0000 bh 10,000.00 10,000.00
Pekerja 0.0100 HOK 85,000.00 850.00
Tukang kayu 0.1000 HOK 105,000.00 10,500.00
Kepala tukang 0.0100 HOK 110,000.00 1,100.00
Mandor 0.0005 HOK 120,000.00 60.00
Jumlah Harga Tenaga, Bahan dan Peralatan 22,510.00
Overhead + Profit 15.0000 % 3,376.50
Harga Satuan Pekerjaan 25,886.50
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

L-07 1 BUAH PASANG ENGSEL ANGIN


Engsel angin 1.0000 bh 10,000.00 10,000.00
Pekerja 0.0200 HOK 85,000.00 1,700.00
Tukang kayu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.01000 HOK 120,000.00 1,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 36,100.00
Overhead + Profit 15.0000 % 5,415.00
Harga Satuan Pekerjaan 41,515.00

L-09 1 BUAH PASANG KAIT ANGIN


Kait angin 1.0000 bh 9,500.00 9,500.00
Pekerja 0.0150 HOK 85,000.00 1,275.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.00075 HOK 120,000.00 90.00
Jumlah Harga Tenaga, Bahan dan Peralatan 28,265.00
Overhead + Profit 15.0000 % 4,239.75
Harga Satuan Pekerjaan 32,504.75

L-11 1 BUAH PASANG KUNCI SELOT


Kunci selot 1.0000 bh 5,000.00 5,000.00
Pekerja 0.0200 HOK 85,000.00 1,700.00
Tukang kayu 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
Mandor 0.0010 HOK 120,000.00 120.00
Jumlah Harga Tenaga, Bahan dan Peralatan 30,020.00
Overhead + Profit 15.0000 % 4,503.00
Harga Satuan Pekerjaan 34,523.00

L-12 1 BUAH PASANG PEGANGAN PINTU / DOOR HOLDER


Door holder 1.0000 bh 0.00 -
Pekerja 0.0500 HOK 85,000.00 4,250.00
Tukang kayu 0.5000 HOK 105,000.00 52,500.00
Kepala tukang 0.0500 HOK 110,000.00 5,500.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 62,550.00
Overhead + Profit 15.0000 % 9,382.50
Harga Satuan Pekerjaan 71,932.50

L-14 1 BUAH PASANG REL PINTU DORONG


Rel pintu dorong 1.0000 bh 0.00 -
Pekerja 0.0600 HOK 85,000.00 5,100.00
Tukang kayu 0.6000 HOK 105,000.00 63,000.00
Kepala tukang 0.0600 HOK 110,000.00 6,600.00
Mandor 0.0030 HOK 120,000.00 360.00
Jumlah Harga Tenaga, Bahan dan Peralatan 75,060.00
Overhead + Profit 15.0000 % 11,259.00
Harga Satuan Pekerjaan 86,319.00

L-15 1 BUAH PASANG KUNCI LEMARI


Kunci lemari 1.0000 Bh 0.00 -
Pekerja 0.0250 HOK 85,000.00 2,125.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Tukang kayu 0.2500 HOK 105,000.00 26,250.00


Kepala tukang 0.0250 HOK 110,000.00 2,750.00
Mandor 0.00125 HOK 120,000.00 150.00
Jumlah Harga Tenaga, Bahan dan Peralatan 31,275.00
Overhead + Profit 15.0000 % 4,691.25
Harga Satuan Pekerjaan 35,966.25

L-16 1 m2 PASANG KACA TEBAL 3 mm


Kaca 1.1000 M2 52,000.00 57,200.00
Pekerja 0.0150 HOK 85,000.00 1,275.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.00075 HOK 120,000.00 90.00
Jumlah Harga Tenaga, Bahan dan Peralatan 75,965.00
Overhead + Profit 15.0000 % 11,394.75
Harga Satuan Pekerjaan 87,359.75

L-17 1 m2 BUAH PASANG KACA TEBAL 5 mm


Kaca 1.1000 bh 65,000.00 71,500.00
Pekerja 0.0150 HOK 85,000.00 1,275.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.00075 HOK 120,000.00 90.00
Jumlah Harga Tenaga, Bahan dan Peralatan 90,265.00
Overhead + Profit 15.0000 % 13,539.75
Harga Satuan Pekerjaan 103,804.75

L-18 1 m2 BUAH PASANG KACA TEBAL 8 mm


Kaca polos 1.1000 bh -
Pekerja 0.0165 HOK 85,000.00 1,402.50
Tukang kayu 0.1650 HOK 105,000.00 17,325.00
Kepala tukang 0.0165 HOK 110,000.00 1,815.00
Mandor 0.00080 HOK 120,000.00 96.00
Jumlah Harga Tenaga, Bahan dan Peralatan 20,638.50
Overhead + Profit 15.0000 % 3,095.78
Harga Satuan Pekerjaan 23,734.28

L-20 1 m2 BUAH PASANG KACA CERMIN TEBAL 3 mm


Kaca cermin 1.1000 bh -
Pekerja 0.0150 HOK 85,000.00 1,275.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.00075 HOK 120,000.00 90.00
Jumlah Harga Tenaga, Bahan dan Peralatan 18,765.00
Overhead + Profit 15.0000 % 2,814.75
Harga Satuan Pekerjaan 21,579.75

L-23 1 m2 BUAH PASANG KACA WIREGLASS TEBAL 5 mm


Kaca wireglass 1.1000 bh -
Pekerja 0.0150 HOK 85,000.00 1,275.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.00075 HOK 120,000.00 90.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Jumlah Harga Tenaga, Bahan dan Peralatan 18,765.00


Overhead + Profit 15.0000 % 2,814.75
Harga Satuan Pekerjaan 21,579.75

L-24 1 m2 BUAH PASANG KACA PATRI TEBAL 5 mm


Kaca wireglass 1.1000 bh -
Pekerja 0.0150 HOK 85,000.00 1,275.00
Tukang kayu 0.1500 HOK 105,000.00 15,750.00
Kepala tukang 0.0150 HOK 110,000.00 1,650.00
Mandor 0.00075 HOK 120,000.00 90.00
Jumlah Harga Tenaga, Bahan dan Peralatan 18,765.00
Overhead + Profit 15.0000 % 2,814.75
Harga Satuan Pekerjaan 21,579.75

PEKERJAAN PENUTUP LANTAI


A.4.4.3.64. PEMASANGAN 1 M2 PAVING BLOCK NATURAL TEBAL 6 CM
A. TENAGA
Pekerja 0.2500 HOK 85,000.00 21,250.00
Tukang Batu 0.5000 HOK 105,000.00 52,500.00
Kepala Tukang 0.0500 HOK 110,000.00 5,500.00
Mandor 0.0013 HOK 120,000.00 156.00
B. BAHAN
Paving Block 6 cm 1.0100 M2 75,000.00 75,750.00
Pasir Beton 0.0500 M3 195,000.00 9,750.00
C. PERALATAN
Peralatan 10%
Jumlah Harga Tenaga, Bahan dan Peralatan 164,906.00
Overhead + Profit 15.0000 % 24,735.90
Harga Satuan Pekerjaan 189,641.90
A.4.4.3.66. PEMASANGAN 1 M2 PAVING BLOCK BERWARNA TEBAL 6 CM
A. TENAGA
Pekerja 0.2500 Kg 85,000.00 21,250.00
Tukang Batu 0.5000 HOK 105,000.00 52,500.00
Kepala Tukang 0.0500 HOK 110,000.00 5,500.00
Mandor 0.0013 HOK 120,000.00 156.00
B. BAHAN
Paving Block 6 cm 1.0100 M2 -
Pasir Beton 0.0500 M3 195,000.00 9,750.00
C. PERALATAN
Peralatan 10%
Jumlah Harga Tenaga, Bahan dan Peralatan 89,156.00
Overhead + Profit 15.0000 % 13,373.40
Harga Satuan Pekerjaan 102,529.40
M-01 1 m2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 40X40 cm
M-02 1 m2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 30X30 cm
Ubin abu-abu 30x30 cm 11.8700 bh -
Semen Portland 10.0000 Kg 1,200.00 12,000.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Pekerja 0.2600 HOK 85,000.00 22,100.00
Tukang batu 0.1300 HOK 100,000.00 13,000.00
Kepala tukang 0.0130 HOK 110,000.00 1,430.00
Mandor 0.0130 HOK 120,000.00 1,560.00
Jumlah Harga Tenaga, Bahan dan Peralatan 55,715.00
Overhead + Profit 15.0000 % 8,357.25
Harga Satuan Pekerjaan 64,072.25
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

M-03 1 m2 PASANG LANTAI UBIN PC ABU-ABU UKURAN 20X20 cm


Ubin abu-abu 20x20 cm 26.5000 bh -
Semen Portland 10.4000 Kg 1,200.00 12,480.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Pekerja 0.2700 HOK 85,000.00 22,950.00
Tukang batu 0.1350 HOK 100,000.00 13,500.00
Kepala tukang 0.0140 HOK 110,000.00 1,540.00
Mandor 0.0140 HOK 120,000.00 1,680.00
Jumlah Harga Tenaga, Bahan dan Peralatan 57,775.00
Overhead + Profit 15.0000 % 8,666.25
Harga Satuan Pekerjaan 66,441.25

M-04 1 m2 PASANG LANTAI UBIN PC WARNA UKURAN 40X40 cm


M-05 1 m2 PASANG LANTAI UBIN PC WARNA UKURAN 30X30 cm
Ubin warna 30x30 cm 11.8700 bh -
Semen Portland 10.0000 Kg 1,200.00 12,000.00
Pasir pasang 0.4500 m3 125,000.00 56,250.00
Semen warna 1.5000 Kg 13,000.00 19,500.00
Pekerja 0.2600 HOK 85,000.00 22,100.00
Tukang batu 0.1300 HOK 100,000.00 13,000.00
Kepala tukang 0.0130 HOK 110,000.00 1,430.00
Mandor 0.0130 HOK 120,000.00 1,560.00
Jumlah Harga Tenaga, Bahan dan Peralatan 125,840.00
Overhead + Profit 15.0000 % 18,876.00
Harga Satuan Pekerjaan 144,716.00

M-06 1 m2 PASANG LANTAI UBIN PC WARNA UKURAN 20X20 cm


Ubin warna 20x20 cm 26.5000 bh -
Semen Portland 10.4000 Kg 1,200.00 12,480.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.6200 Kg 13,000.00 21,060.00
Pekerja 0.2700 HOK 85,000.00 22,950.00
Tukang batu 0.1350 HOK 100,000.00 13,500.00
Kepala tukang 0.0140 HOK 110,000.00 1,540.00
Mandor 0.0140 HOK 120,000.00 1,680.00
Jumlah Harga Tenaga, Bahan dan Peralatan 78,835.00
Overhead + Profit 15.0000 % 11,825.25
Harga Satuan Pekerjaan 90,660.25

M-07 1 m2 PASANG LANTAI UBIN TERASO UKURAN 40X40 cm


M-08 1 m2 PASANG LANTAI UBIN TERASO UKURAN 30X30 cm
M-09 1 m2 PASANG LANTAI UBIN GRANITO UKURAN 40X40 cm
Ubin granito 40x40 cm 6.9300 bh -
Semen Portland 9.8000 Kg 1,200.00 11,760.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.3000 Kg 13,000.00 16,900.00
Pekerja 0.2500 HOK 85,000.00 21,250.00
Tukang batu 0.1250 HOK 100,000.00 12,500.00
Kepala tukang 0.0130 HOK 110,000.00 1,430.00
Mandor 0.0130 HOK 120,000.00 1,560.00
Jumlah Harga Tenaga, Bahan dan Peralatan 71,025.00
Overhead + Profit 15.0000 % 10,653.75
Harga Satuan Pekerjaan 81,678.75
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

M-10 1 m2 PASANG LANTAI UBIN GRANITO UKURAN 30X30 cm


Ubin granito 30x30 cm 11.8700 bh -
Semen Portland 10.0000 Kg 1,200.00 12,000.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.5000 Kg 13,000.00 19,500.00
Pekerja 0.2600 HOK 85,000.00 22,100.00
Tukang batu 0.1300 HOK 100,000.00 13,000.00
Kepala tukang 0.0130 HOK 110,000.00 1,430.00
Mandor 0.0130 HOK 120,000.00 1,560.00
Jumlah Harga Tenaga, Bahan dan Peralatan 75,215.00
Overhead + Profit 15.0000 % 11,282.25
Harga Satuan Pekerjaan 86,497.25

M-11 1 m2 PASANG LANTAI UBIN TERALUX UKURAN 40X40 cm


M-12 1 m2 PASANG LANTAI UBIN TERALUX UKURAN 30X30 cm
M-13 1 m2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 60X60 cm
M-14 1 m2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 40X40 cm
M-15 1 m2 PASANG LANTAI UBIN TERALUX MARMER UKURAN 30X30 cm
M-16 1 m2 PASANG PLINT UBIN PC ABU-ABU UKURAN 15X20 cm
Plin ubint 15x20 cm 5.3000 bh -
Semen Portland 1.6500 Kg 1,200.00 1,980.00
Pasir pasang 0.0040 m3 125,000.00 500.00
Pekerja 0.0900 HOK 85,000.00 7,650.00
Tukang batu 0.0900 HOK 100,000.00 9,000.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 20,720.00
Overhead + Profit 15.0000 % 3,108.00
Harga Satuan Pekerjaan 23,828.00

M-17 1 m' PASANG PLINT UBIN PC ABU-ABU UKURAN 10X30 cm


Plint ubin 10x30 cm 3.5300 bh -
Semen Portland 1.2400 Kg 1,200.00 1,488.00
Pasir pasang 0.0030 m3 125,000.00 375.00
Pekerja 0.0900 HOK 85,000.00 7,650.00
Tukang batu 0.0900 HOK 100,000.00 9,000.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 20,103.00
Overhead + Profit 15.0000 % 3,015.45
Harga Satuan Pekerjaan 23,118.45

M-18 1 m' PASANG PLINT UBIN PC ABU-ABU UKURAN 10X40 cm


M-19 1 m' PASANG PLINT UBIN PC WARNA UKURAN 10X20 cm
Plin ubin pc warna 10x20 cm 5.3000 bh -
Semen Portland 1.1400 Kg 1,200.00 1,368.00
Pasir pasang 0.0030 m3 125,000.00 375.00
Semen warna 0.1000 Kg 13,000.00 1,300.00
Pekerja 0.0900 HOK 85,000.00 7,650.00
Tukang batu 0.0900 HOK 100,000.00 9,000.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 21,283.00
Overhead + Profit 15.0000 % 3,192.45
Harga Satuan Pekerjaan 24,475.45
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

M-20 1 m' PASANG PLINT UBIN PC WARNA UKURAN 10X30 cm


M-21 1 m' PASANG PLINT UBIN PC WARNA UKURAN 10X40 cm
M-22 1 m' PASANG PLINT UBIN TERASO UKURAN 10X30 cm
M-23 1 m' PASANG PLINT UBIN TERASO UKURAN 10X40 cm
M-24 1 m' PASANG PLINT UBIN GRANITO UKURAN 10X40 cm
M-25 1 m' PASANG PLINT UBIN GRANITO UKURAN 10X30 cm
Plin ubin granito 10x30 cm 3.5300 bh -
Semen Portland 1.1400 Kg 1,200.00 1,368.00
Pasir pasang 0.0030 m3 125,000.00 375.00
Semen warna 0.1000 Kg 13,000.00 1,300.00
Pekerja 0.0900 HOK 85,000.00 7,650.00
Tukang batu 0.0900 HOK 100,000.00 9,000.00
Kepala tukang 0.0090 HOK 110,000.00 990.00
Mandor 0.0050 HOK 120,000.00 600.00
Jumlah Harga Tenaga, Bahan dan Peralatan 21,283.00
Overhead + Profit 15.0000 % 3,192.45
Harga Satuan Pekerjaan 24,475.45

M-26 1 m' PASANG PLINT UBIN TERALUX KERANG UKURAN 10X40 cm


M-27 1 m' PASANG PLINT UBIN TERALUX KERANG UKURAN 10X30 cm
M-28 1 m' PASANG PLINT UBIN TERALUX MARMER UKURAN 10X60 cm
M-29 1 m' PASANG PLINT UBIN TERALUX MARMER UKURAN 10X40 cm
M-30 1 m' PASANG PLINT UBIN TERALUX MARMER UKURAN 10X30 cm
M-31 1 m2 PASANG LANTAI TERASO COR DITEMPAT, TEBAL 3 cm
M-32 1 m2 PASANG LANTAI KERAMIK ARTISTIK UKURAN 10X20 cm
Ubin Keramik Artistik (10x20)cm 53.0000 bh -
Semen Portland 8.1900 Kg 1,200.00 9,828.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 2.7500 Kg 13,000.00 35,750.00
Pekerja 0.7000 HOK 85,000.00 59,500.00
Tukang batu 0.3500 HOK 100,000.00 35,000.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0350 HOK 120,000.00 4,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 153,753.00
Overhead + Profit 15.0000 % 23,062.95
Harga Satuan Pekerjaan 176,815.95

M-33 1 m' PASANG PLINT KERAMIK ARTISTIK UKURAN 10X10 cm ATAU 5x20 cm
M-34 1 m2 PASANG LANTAI KERAMIK UKURAN 33X33 cm
M-35 1 M2 PASANG LANTAI KERAMIK UKURAN (30x30) cm (Putih Polos)
Keramik (30 x 30) polos 11.8700 bh 3,590.91 42,624.09
Semen Portland 10.0000 kg 1,200.00 12,000.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.5000 kg 13,000.00 19,500.00
Pekerja 0.7000 HOK 85,000.00 59,500.00
Tukang kayu 0.3500 HOK 105,000.00 36,750.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0350 HOK 120,000.00 4,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 184,049.09
Overhead + Profit 15.0000 % 27,607.36
Harga Satuan Pekerjaan 211,656.45

M-35A 1 M2 PASANG LANTAI KERAMIK UKURAN (30x30) cm (Warna)


Keramik (30 x 30) polos 11.8700 bh 4,090.91 48,559.09
Semen Portland 10.0000 kg 1,200.00 12,000.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.5000 kg 13,000.00 19,500.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pekerja 0.7000 HOK 85,000.00 59,500.00


Tukang kayu 0.3500 HOK 105,000.00 36,750.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0350 HOK 120,000.00 4,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 189,984.09
Overhead + Profit 15.0000 % 28,497.61
Harga Satuan Pekerjaan 218,481.70

M-35B 1 m2 PASANG LANTAI KERAMIK 30X30 cm WARNA ANTI SELIP


Ubin keramik 30x30 cm 11.8700 bh 7,272.73 86,327.27
Semen Portland 10.0000 Kg 1,200.00 12,000.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.5000 Kg 13,000.00 19,500.00
Pekerja 0.7000 HOK 85,000.00 59,500.00
Tukang batu 0.3500 HOK 100,000.00 35,000.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0350 HOK 120,000.00 4,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 226,002.27
Overhead + Profit 15.0000 % 33,900.34
Harga Satuan Pekerjaan 259,902.61

M-35C 1 M2 PASANG LANTAI KERAMIK UKURAN (40x40) cm (Putih Polos)


Keramik (40 x 40) polos 6.6300 bh 8,750.00 58,012.50
Semen Portland 10.0000 kg 1,200.00 12,000.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.5000 kg 13,000.00 19,500.00
Pekerja 0.7000 HOK 85,000.00 59,500.00
Tukang kayu 0.3500 HOK 105,000.00 36,750.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0350 HOK 120,000.00 4,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 199,437.50
Overhead + Profit 15.0000 % 29,915.63
Harga Satuan Pekerjaan 229,353.13

M-35D 1 M2 PASANG LANTAI KERAMIK UKURAN (40x40) cm (Warna)


Keramik (40 x 40) polos 6.6300 bh 9,450.00 62,653.50
Semen Portland 10.0000 kg 1,200.00 12,000.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.5000 kg 13,000.00 19,500.00
Pekerja 0.7000 HOK 85,000.00 59,500.00
Tukang kayu 0.3500 HOK 105,000.00 36,750.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0350 HOK 120,000.00 4,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 204,078.50
Overhead + Profit 15.0000 % 30,611.78
Harga Satuan Pekerjaan 234,690.28

M-35E 1 m2 PASANG LANTAI KERAMIK 60X60 cm


Ubin keramik 60x60 cm 2.7800 bh 33,333.33 92,666.67
Semen Portland 11.3800 Kg 1,200.00 13,656.00
Pasir pasang 0.0420 m3 125,000.00 5,250.00
Semen warna 1.5000 Kg 13,000.00 19,500.00
Pekerja 0.6200 HOK 85,000.00 52,700.00
Tukang batu 0.3500 HOK 105,000.00 36,750.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0300 HOK 120,000.00 3,600.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Jumlah Harga Tenaga, Bahan dan Peralatan 227,972.67


Overhead + Profit 15.0000 % 34,195.90
Harga Satuan Pekerjaan 262,168.57

M-36 1 M2 PASANG LANTAI KERAMIK UKURAN 20X20 cm Putih (Polos)


Ubin keramik 20x20 cm 26.5000 bh 1,460.00 38,690.00
Semen Portland 10.4000 Kg 1,200.00 12,480.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.6200 Kg 13,000.00 21,060.00
Pekerja 0.7000 HOK 85,000.00 59,500.00
Tukang batu 0.3500 HOK 105,000.00 36,750.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0350 HOK 120,000.00 4,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 182,155.00
Overhead + Profit 15.0000 % 27,323.25
Harga Satuan Pekerjaan 209,478.25

M-36A 1 M2 PASANG LANTAI KERAMIK UKURAN 20X20 cm WARNA ANTI SELIP


Ubin keramik 20x20 cm 26.5000 bh 1,700.00 45,050.00
Semen Portland 10.4000 Kg 1,200.00 12,480.00
Pasir pasang 0.0450 m3 125,000.00 5,625.00
Semen warna 1.6200 Kg 13,000.00 21,060.00
Pekerja 0.7000 HOK 85,000.00 59,500.00
Tukang batu 0.3500 HOK 105,000.00 36,750.00
Kepala tukang 0.0350 HOK 110,000.00 3,850.00
Mandor 0.0350 HOK 120,000.00 4,200.00
Jumlah Harga Tenaga, Bahan dan Peralatan 188,515.00
Overhead + Profit 15.0000 % 28,277.25
Harga Satuan Pekerjaan 216,792.25

M-37 1 m2 PASANG LANTAI KERAMIK UKURAN 10X33 cm, VARIASI/BORDER


M-38 1 m2 PASANG LANTAI MOSAIK 30X30 cm, ADUKAN 1 PC ; 3 Ps
M-39 1 m' PASANG PLINT KERAMIK 10X20 cm
M-40 1 m' PASANG PLINT KERAMIK 10X10 cm
M-41 1 m' PASANG PLINT KERAMIK 5X20 cm
M-42 1 m' PASANG PLINT INTERVAL COVE ARTISTIK (5x5x20) cm
M-43 1 m2 PASANG LANTAI MARMER 100X100 cm
M-44 1 m2 PASANG LANTAI KARPET
M-45 1 m2 PASANG UNDERLAYER
M-46 1 m2 PASANG LANTAI PARQUET
M-47 1 m2 PASANG LANTAI KAYU (GYMFLOOR)
M-48 1 m2 PASANG DINDING PORSELIN 11X11 cm
Porselin 11x11 cm, warna 86.0000 bh -
Semen Abu-abu 9.3000 Kg 1,200.00 11,160.00
Pasir pasang 0.0180 m3 125,000.00 2,250.00
Semen warna 1.5000 Kg 13,000.00 19,500.00
Pekerja 1.0000 HOK 85,000.00 85,000.00
Tukang batu 0.5000 HOK 105,000.00 52,500.00
Kepala tukang 0.0500 HOK 110,000.00 5,500.00
Mandor 0.0500 HOK 120,000.00 6,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 181,910.00
Overhead + Profit 15.0000 % 27,286.50
Harga Satuan Pekerjaan 209,196.50

M-49 1 m2 PASANG DINDING PORSELIN 10X20 cm


Porselin 10x20 cm warna 53.0000 bh -
Semen Abu-abu 9.3000 Kg 1,200.00 11,160.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pasir pasang 0.0180 m3 125,000.00 2,250.00


Semen warna 2.7500 Kg 13,000.00 35,750.00
Pekerja 0.9000 HOK 85,000.00 76,500.00
Tukang batu 0.4500 HOK 105,000.00 47,250.00
Kepala tukang 0.0450 HOK 110,000.00 4,950.00
Mandor 0.0450 HOK 120,000.00 5,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 183,260.00
Overhead + Profit 15.0000 % 27,489.00
Harga Satuan Pekerjaan 210,749.00

M-50 1 m2 PASANG DINDING PORSELIN 20X20 cm


M-51 1 m2 PASANG DINDING KERAMIK ARTISTIK 10X20 cm
M-52 1 m2 PASANG DINDING KERAMIK ARTISTIK 5X20 cm
M-53 1 m2 PASANG DINDING KERAMIK 10X20 cm
Keramik 10x20 cm warna 53.0000 bh -
Semen Abu-abu 9.3000 Kg 1,200.00 11,160.00
Pasir pasang 0.0180 m3 125,000.00 2,250.00
Semen warna 2.7500 Kg 13,000.00 35,750.00
Pekerja 0.9000 HOK 85,000.00 76,500.00
Tukang batu 0.4500 HOK 105,000.00 47,250.00
Kepala tukang 0.0450 HOK 110,000.00 4,950.00
Mandor 0.0450 HOK 120,000.00 5,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 183,260.00
Overhead + Profit 15.0000 % 27,489.00
Harga Satuan Pekerjaan 210,749.00

M-54 1 m2 PASANG DINDING KERAMIK 20X20 cm (putih polos)


Keramik 20x20 cm putih polos 26.5000 bh 1,460.00 38,690.00
Semen Abu-abu 9.3000 Kg 1,200.00 11,160.00
Pasir pasang 0.0180 m3 125,000.00 2,250.00
Semen warna 1.9400 Kg 13,000.00 25,220.00
Pekerja 0.9000 HOK 85,000.00 76,500.00
Tukang batu 0.4500 HOK 105,000.00 47,250.00
Kepala tukang 0.0450 HOK 110,000.00 4,950.00
Mandor 0.0450 HOK 120,000.00 5,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 211,420.00
Overhead + Profit 15.0000 % 31,713.00
Harga Satuan Pekerjaan 243,133.00

M-54A 1 m2 PASANG DINDING KERAMIK 20X20 cm (warna)


Keramik 20x20 cm warna 26.5000 bh 1,840.00 48,760.00
Semen Abu-abu 9.3000 Kg 1,200.00 11,160.00
Pasir pasang 0.0180 m3 125,000.00 2,250.00
Semen warna 1.9400 Kg 13,000.00 25,220.00
Pekerja 0.9000 HOK 85,000.00 76,500.00
Tukang batu 0.4500 HOK 105,000.00 47,250.00
Kepala tukang 0.0450 HOK 110,000.00 4,950.00
Mandor 0.0450 HOK 120,000.00 5,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 221,490.00
Overhead + Profit 15.0000 % 33,223.50
Harga Satuan Pekerjaan 254,713.50

M-54B 1 m2 PASANG DINDING KERAMIK 20X25 cm (warna)


Keramik 20x25 cm warna 21.2000 bh 2,450.00 51,940.00
Semen Abu-abu 9.3000 Kg 1,200.00 11,160.00
Pasir pasang 0.0180 m3 125,000.00 2,250.00
Semen warna 1.9400 Kg 13,000.00 25,220.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pekerja 0.9000 HOK 85,000.00 76,500.00


Tukang batu 0.4500 HOK 105,000.00 47,250.00
Kepala tukang 0.0450 HOK 110,000.00 4,950.00
Mandor 0.0450 HOK 120,000.00 5,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 224,670.00
Overhead + Profit 15.0000 % 33,700.50
Harga Satuan Pekerjaan 258,370.50

M-54C 1 m2 PASANG DINDING KERAMIK 20X40 cm (warna)


Keramik 20x40 cm warna Roman 13.2500 bh 7,916.67 104,895.83
Semen Abu-abu 9.3000 Kg 1,200.00 11,160.00
Pasir pasang 0.0180 m3 125,000.00 2,250.00
Semen warna 1.9400 Kg 13,000.00 25,220.00
Pekerja 0.9000 HOK 85,000.00 76,500.00
Tukang batu 0.4500 HOK 105,000.00 47,250.00
Kepala tukang 0.0450 HOK 110,000.00 4,950.00
Mandor 0.0450 HOK 120,000.00 5,400.00
Jumlah Harga Tenaga, Bahan dan Peralatan 277,625.83
Overhead + Profit 15.0000 % 41,643.88
Harga Satuan Pekerjaan 319,269.71

M-55 1 m2 PASANG DINDING MARMER 100X100 cm


M-56 1 m2 PASANG DINDING BATA PELAPIS 3x7x24 cm
M-57 1 m2 PASANG DINDING BATU PARAS
M-58 1 m2 PASANG DINDING BATU TEMPEL HITAM
M-59 1 m2 PASANG LANTAI VINYL 30x30 cm
M-60 1 m2 WALL PAPER, LEBAR 50 cm
M-61 1 m2 FLOOR HARDENER
M-62 1 m' PLINT VIVYIL KARET 30x30 cm DENGAN PEREKAT
M-63 1 m' PLINT KAYU KELAS II 2x10 cm

PEKERJAAN PENGECATAN
N-01 1 m2 MENGIKIS / MENGEROK PERMUKAAN CAT TEMBOK LAMA
Soda api 0.0500 Kg 0.00 -
Pekerja 0.1500 HOK 85,000.00 12,750.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 13,050.00
Overhead + Profit 15.0000 % 1,957.50
Harga Satuan Pekerjaan 15,007.50

N-02 1 m2 MENCUCI BIDANG PERMUKAAN TEMBOK YANG PERNAH DI CAT


Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 85,000.00 12,750.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 13,125.00
Overhead + Profit 15.0000 % 1,968.75
Harga Satuan Pekerjaan 15,093.75

N-03 1 m2 MENGEROK KARAT CAT LAMA PERMUKAAN BAJA DENGAN CARA MANUAL
Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 85,000.00 12,750.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 13,125.00
Overhead + Profit 15.0000 % 1,968.75
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Harga Satuan Pekerjaan 15,093.75

N-04 1 m2 MENYABUN PERMUKAAN TEMBOK LAMA


Sabun 0.0500 Kg 1,500.00 75.00
Pekerja 0.1500 HOK 85,000.00 12,750.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 13,125.00
Overhead + Profit 15.0000 % 1,968.75
Harga Satuan Pekerjaan 15,093.75

N-06 1 m2 MENDEMPUL DAN MENGGOSOK KAYU


Dempul jadi 0.0800 Kg 37,000.00 2,960.00
Minyak cat 0.0200 Kg 0.00 -
Batu apung 0.0100 Kg 1,500.00 15.00
Pekerja 0.0400 HOK 85,000.00 3,400.00
Tukang cat 0.0400 HOK 105,000.00 4,200.00
Kepala tukang 0.0040 HOK 110,000.00 440.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 11,315.00
Overhead + Profit 15.0000 % 1,697.25
Harga Satuan Pekerjaan 13,012.25

N-07 1 m2 PENGECATAN BIDANG KAYU LAMA


Plamir 0.1500 Kg 15,000.00 2,250.00
Cat dasar 0.1700 Kg 55,000.00 9,350.00
Cat Penutup 0.1700 Kg 55,000.00 9,350.00
Pekerja 0.0700 HOK 85,000.00 5,950.00
Tukang cat 0.0750 HOK 105,000.00 7,875.00
Kepala tukang 0.0075 HOK 110,000.00 825.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 35,900.00
Overhead + Profit 15.0000 % 5,385.00
Harga Satuan Pekerjaan 41,285.00

N-08 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
Cat meni 0.2000 Kg 23,600.00 4,720.00
Plamir 0.1500 Kg 15,000.00 2,250.00
Cat dasar 0.1700 Kg 55,000.00 9,350.00
Cat Penutup ( 2 kali ) 0.2600 Kg 55,000.00 14,300.00
Pekerja 0.0700 HOK 85,000.00 5,950.00
Tukang cat 0.0090 HOK 105,000.00 945.00
Kepala tukang 0.0060 HOK 110,000.00 660.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 38,475.00
Overhead + Profit 15.0000 % 5,771.25
Harga Satuan Pekerjaan 44,246.25

N-09 1 m2 PENGECATAN BIDANG KAYU BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 3 Lapis Cat Penutup)
Cat meni 0.2000 Kg 23,600.00 4,720.00
Plamir 0.1500 Kg 15,000.00 2,250.00
Cat dasar 0.1700 Kg 55,000.00 9,350.00
Cat Penutup ( 3 kali ) 0.3500 Kg 55,000.00 19,250.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Pekerja 0.0700 HOK 85,000.00 5,950.00


Tukang cat 0.1050 HOK 105,000.00 11,025.00
Kepala tukang 0.0040 HOK 110,000.00 440.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 53,285.00
Overhead + Profit 15.0000 % 7,992.75
Harga Satuan Pekerjaan 61,277.75

N-11 1 m2 PELABURAN BIDANG KAYU DENGAN POLITUR


Politur 0.1500 Ltr 12,600.00 1,890.00
Politur jadi 0.3720 Ltr 27,000.00 10,044.00
Ampelas 2.0000 Lbr 5,000.00 10,000.00
Tukang cat 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0160 HOK 110,000.00 1,760.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 30,294.00
Overhead + Profit 15.0000 % 4,544.10
Harga Satuan Pekerjaan 34,838.10

N-12 1 m2 PELABURAN BIDANG KAYU DENGAN CAT RESIDU DAN TER


Residu atau ter 0.3500 Ltr 5,000.00 1,750.00
Pekerja 0.1000 HOK 85,000.00 8,500.00
Mandor 0.0060 HOK 120,000.00 720.00
Jumlah Harga Tenaga, Bahan dan Peralatan 10,970.00
Overhead + Profit 15.0000 % 1,645.50
Harga Satuan Pekerjaan 12,615.50

N-13 1 m2 PELABURAN BIDANG KAYU DENGAN VERNIS


Vernis 0.1500 Ltr 18,000.00 2,700.00
Dempul 0.0500 Kg 16,500.00 825.00
Ampelas 0.1000 Lbr 5,000.00 500.00
Kuas 0.0100 Bh 13,000.00 130.00
Pekerja 0.1600 HOK 85,000.00 13,600.00
Tukang cat 0.1600 HOK 105,000.00 16,800.00
Kepala tukang 0.0160 HOK 110,000.00 1,760.00
Mandor 0.0025 HOK 120,000.00 300.00
Jumlah Harga Tenaga, Bahan dan Peralatan 36,615.00
Overhead + Profit 15.0000 % 5,492.25
Harga Satuan Pekerjaan 42,107.25

A.4.7.1.10. PENGECATAN 1 m2 TEMBOK BARU (1 Lapis Plamir; 1 Lapis Cat dasar; 2 Lapis Cat Penutup)
A. TENAGA
Pekerja 0.0200 HOK 70,000.00 1,400.00
Tukang cat 0.0630 HOK 105,000.00 6,615.00
Kepala tukang 0.0063 HOK 110,000.00 693.00
Mandor 0.0030 HOK 120,000.00
B. BAHAN
Plamuur 0.1000 kg 25,000.00 2,500.00
Cat dasar 0.1000 kg 25,000.00 2,500.00
Cat Penutup 0.2600 kg 25,000.00 6,500.00

Jumlah Harga Tenaga, Bahan dan Peralatan 20,208.00


Overhead + Profit 15.0000 % 3,031.20
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Harga Satuan Pekerjaan 23,239.20

N-14A 1 m2 PENGECATAN BIDANG TEMBOK BARU EKSTERIOR


Cat dasar 0.1000 Kg 74,000.00 7,400.00
Cat Penutup ( 2 kali ) Mowilex 0.2600 Kg 74,000.00 19,240.00
Pekerja 0.0200 HOK 25,000.00 500.00
Tukang cat 0.0630 HOK 25,000.00 1,575.00
Kepala tukang 0.0063 HOK 25,000.00 157.50
Mandor 0.0025 HOK 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 28,872.50
Overhead + Profit 15.0000 % 4,330.88
Harga Satuan Pekerjaan 33,203.38

N-14B 1 m2 PENGECATAN BIDANG TEMBOK BARU INTERIOR


Cat dasar 0.1000 Kg 50,000.00 5,000.00
Cat Penutup ( 2 kali ) Mowilex 0.2600 Kg 50,000.00 13,000.00
Pekerja 0.0200 HOK 25,000.00 500.00
Tukang cat 0.0630 HOK 25,000.00 1,575.00
Kepala tukang 0.0063 HOK 25,000.00 157.50
Mandor 0.0025 HOK 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 20,232.50
Overhead + Profit 15.0000 % 3,034.88
Harga Satuan Pekerjaan 23,267.38

N-15 1 m2 PENGECATAN BIDANG TEMBOK LAMA ( 1 Lapis Cat dasar; 2 Lapis Cat Penutup )
Cat dasar 0.1200 Kg 25,000.00 3,000.00
Cat Penutup ( 2 kali ) Sanlex 0.1800 Kg 25,000.00 4,500.00
Pekerja 0.0280 HOK 25,000.00 700.00
Tukang cat 0.0420 HOK 25,000.00 1,050.00
Kepala tukang 0.0042 HOK 25,000.00 105.00
Mandor 0.0025 HOK 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 9,355.00
Overhead + Profit 15.0000 % 1,403.25
Harga Satuan Pekerjaan 10,758.25

N-19 1 m2 PEMASANGAN WALL PAPER


Wall paper 1.2000 m3 -
Perekat 0.2000 Kg -
Pekerja 0.0200 HOK 25,000.00 500.00
Tukang cat 0.2000 HOK 25,000.00 5,000.00
Kepala tukang 0.0020 HOK 25,000.00 50.00
Mandor 0.0025 HOK 0.00 -
Jumlah Harga Tenaga, Bahan dan Peralatan 5,550.00
Overhead + Profit 15.0000 % 832.50
Harga Satuan Pekerjaan 6,382.50

N-20 1 m2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI


Meni besi 0.1000 Kg 23,600.00 2,360.00
Kuas 0.0100 Bh 13,000.00 130.00
Pekerja 0.0200 HOK 25,000.00 500.00
Tukang cat 0.2000 HOK 105,000.00 21,000.00
Kepala tukang 0.0200 HOK 110,000.00 2,200.00
KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Mandor 0.0100 HOK 120,000.00 1,200.00


Jumlah Harga Tenaga, Bahan dan Peralatan 27,390.00
Overhead + Profit 15.0000 % 4,108.50
Harga Satuan Pekerjaan 31,498.50

N-21 1 m2 PENGECATAN PERMUKAAN BAJA DENGAN MENI BESI DAN PERANCAH


Meni besi 0.1000 Kg 23,600.00 2,360.00
Kuas 0.0100 Bh 13,000.00 130.00
Perancah kayu 0.0020 m3 1,800,000.00 3,600.00
Pekerja 0.2500 HOK 25,000.00 6,250.00
Tukang cat 0.2250 HOK 105,000.00 23,625.00
Kepala tukang 0.0225 HOK 110,000.00 2,475.00
Mandor 0.0075 HOK 120,000.00 900.00
Jumlah Harga Tenaga, Bahan dan Peralatan 39,340.00
Overhead + Profit 15.0000 % 5,901.00
Harga Satuan Pekerjaan 45,241.00

N-22 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS SENG GALBANI SECARA MANUAL (4 lapis cat konvensional, tebal 200 um)
Cat dasar 0.1100 Kg -
Cat antara 0.1700 Kg -
Cat penutup 0.0800 Kg -
Pekerja 0.5000 HOK 25,000.00 12,500.00
Tukang cat 0.8000 HOK 105,000.00 84,000.00
Kepala tukang 0.3000 HOK 110,000.00 33,000.00
Mandor 0.2000 HOK 120,000.00 24,000.00
Jumlah Harga Tenaga, Bahan dan Peralatan 153,500.00
Overhead + Profit 15.0000 % 23,025.00
Harga Satuan Pekerjaan 176,525.00

N-23 1 m2 PENGECATAN PERMUKAAN BAJA LAPIS GALBANI SECARA MANUAL (1 lapis cat mutakhir, tebal 200 um)
Cat 0.3000 Kg -
Pekerja 0.0060 HOK 25,000.00 150.00
Tukang cat 0.0600 HOK 105,000.00 6,300.00
Kepala tukang 0.0120 HOK 110,000.00 1,320.00
Mandor 0.0060 HOK 120,000.00 720.00
Jumlah Harga Tenaga, Bahan dan Peralatan 8,490.00
Overhead + Profit 15.0000 % 1,273.50
Harga Satuan Pekerjaan 9,763.50

O. PEKERJAAN JALAN
O-01 1 M2 HOTMIX TANGAN T=3 CM (JADI) UNTUK HALAMAN & JALAN KLS 6 TON KE BAWAH
Screen 0.0144 M3 200,000.00 2,880.00
Abu Batu 0.0216 M3 185,000.00 3,996.00
Aspal Penetrasi 5.0000 Kg 10,580.65 52,903.23
Kayu Bakar 0.0080 M3 175,000.00 1,400.00
Pekerja setengah terampil 0.0800 M3 70,000.00 5,600.00
Pekerja Terampil 0.0300 Ls 85,000.00 2,550.00
Mandor 0.0100 HOK 120,000.00 1,200.00
Peralatan 0.0980 Lot 70,529.23 6,911.86
Jumlah Harga Tenaga, Bahan dan Peralatan 77,441.09
Overhead + Profit 15.0000 % 11,616.16
Harga Satuan Pekerjaan 89,057.25

O-01.1 1 M2 HOTMIX TANGAN T=2 CM (JADI) UNTUK JALAN GANG


KODE PEK URAIAN KOEF SATUAN HARGA (Rp) HARGA SATUAN(Rp)

Screen 0.0096 M3 200,000.00 1,920.00


Abu Batu 0.0144 M3 185,000.00 2,664.00
Aspal Penetrasi 3.3333 Kg 10,580.65 35,268.82
Kayu Bakar 0.0053 M3 175,000.00 933.33
Pekerja setengah terampil 0.0533 M3 70,000.00 3,733.33
Pekerja Terampil 0.0200 Ls 85,000.00 1,700.00
Mandor 0.0067 HOK 120,000.00 800.00
Peralatan 0.0653 Lot 47,019.48 3,071.94
Jumlah Harga Tenaga, Bahan dan Peralatan 50,091.42
Overhead + Profit 15.0000 % 7,513.71
Harga Satuan Pekerjaan 57,605.14
DAFTAR HARGA SATUAN BAHAN DAN UPAH

UPAH
NO KEAHLIAN SAT
Rp.
I. PEKERJA (UMK 2018). Proy
1 Tenaga/ Pekerja 72,000.00 /Org/Hr
2 Tukang Aspal 85,000.00 /Org/Hr
3 Tukang Batu 85,000.00 /Org/Hr
4 Tukang Besi 85,000.00 /Org/Hr
5 Tukang Cat 85,000.00 /Org/Hr
6 Tukang Gypsum 85,000.00 /Org/Hr
7 Tukang Kayu 85,000.00 /Org/Hr
8 Tukang Las 85,000.00 /Org/Hr
9 Tukang Listrik 85,000.00 /Org/Hr
10 Tukang Taman 85,000.00 /Org/Hr
11 Tukang Cat Melamik 85,000.00 /Org/Hr
12 Tukang Pipa 85,000.00 /Org/Hr
13 Tukang Aluminium 85,000.00 /Org/Hr
14 Kepala Tukang 90,000.00 /Org/Hr
15 Operator 85,000.00 /Org/Hr
16 Mandor 90,000.00 /Org/Hr
###
II. BAHAN. ###
HARGA
NO JENIS MATERIAL SAT
Rp.
A BAHAN DASAR ###

1 Pasir Beton 200,000.00 m3


2 Pasir Pasang 160,000.00 m3
3 Pasir Urug 130,000.00 m3
4 Batu Belah / Batu Kali / Batu Gunung 160,000.00 m3
5 Batu Split 1/2 260,000.00 m3
6 Batu Split 2/3 250,000.00 m3
7 Batu Split 3/5 230,000.00 m3
8 Batu Krop 59,000.00 m3
9 Sirtu (Pasir Batu) 120,000.00 m3
10 Tanah Urug merah 35,000.00 m3
11 Tanah Subur 39,000.00 m3
12 Tanah Urug pilihan 40,000.00 m3
13 Bata Merah Kelas 1 600.00 bh
14 Batako 2,000.00 bh
15 Bata ringan ( Ukuran 7,5 / 10 / 12,5 / 20 cm ) 750,000.00 m3
16 Glass block Lokal 20 x 20 cm ex. Mulya 18,000.00 bh
17 Semen PC type I @ 50 kg Product Tiga Roda 55,000.00 Zak
18 Semen Warna untuk nat kemasan plastik 13,000.00 kg
19 Semen Mortar Instant ( PM – 210  ) - Plester 1,000.00 kg
20 Semen Mortar Instant ( PM – 310  ) - Acian 2,000.00 kg
21 Semen Mortar Instant ( MU-100 ) - Plester Premium 2,000.00 kg
22 Semen Mortar Instant ( PM 110 –Thin Bed Mortar ) - Perekat bata ringan 2,000.00 kg
23 Semen Mortar Instant ( MU-400 ) - Perekat Keramik Dinding 6,000.00 kg
24 Semen Mortar Instant ( MU-410 ) - Self Leveling Floor 13,000.00 kg
25 Semen Mortar Instant ( MU-420 ) - Perekat Keramik Lantai 4,000.00 kg
26 Semen Mortar Instant ( MU-700 ) - Floor Hardener 6,000.00 kg
27 Semen Grouting t=25mm 269,000.00 m2
28 Roster beton 12 x 11 x 24 cm 5,000.00 bh
B BETON
B.1 BETON READY MIX
1 Beton K - 250 892,000.00 m3
2 Beton K - 300 952,000.00 m3
3 Sewa pompa beton 66,000.00 m3
4 Sewa vibrator 10,000.00 m3
B.2 PRECAST AND PRESTRESS CONCRETE
1 Kansteen
- K.03.1 ( 15.18.40 ) Beton elemendo 34,000.00 bh
- K.05.1 ( 15.30.60 ) ex. Csangkan 68,000.00 bh
C BAHAN BESI ###
1 Besi beton polos 8,500.00 kg
2 Besi beton ulir 8,500.00 kg
3 Kawat beton 14,000.00 kg
4 Paku 14,000.00 kg
5 Sekruf 11,000.00 gross
6 Paku hak panjang 23,000.00 kg
7 Skruf gyp 33,000.00 kg
8 WM - M6-150 2,1 x 5,4 m 25,000.00 m2
9 WM - M7-150 2,1 x 5,4 m 35,000.00 m2
10 WM - M8-150 2,1 x 5,4 m 46,000.00 m2
11 WM - M9-150 2,1 x 5,4 m 60,000.00 m2
12 WM - M10-150 2,1 x 5,4 m 74,000.00 m2
13 Skruf + fiser untuk kusen alumunium 1,000.00 bh
14 Baja HB & IWF 12,000.00 kg
15 Siku 12,000.00 kg
16 Jenis CNP 12,000.00 kg
17 Jenis UNP 12,000.00 kg
HARGA
NO JENIS MATERIAL SAT
Rp.
18 Jenis Lips Canal 12,000.00 kg
19 Jenis plat ukuran 4' x 8' berlaku untuk semua ketebalan 12,000.00 kg
20 Besi hollow kotak 40/40 mm t.2mm pj=6m 108,000.00 btg
21 Besi kotak hollow 40/20 mm t.2mm pj=6m 89,000.00 btg
22 Besi hollow kotak 30/30 mm t.2mm pj=6m 85,000.00 btg
23 Besi kotak 20/20 mm (untuk rangka plafond) pj=4m 31,000.00 btg
24 Besi kotak 20/40 mm (untuk rangka plafond) pj=4m 40,000.00 btg
25 Besi kotak 40/40 mm (untuk rangka plafond) pj=6m 102,000.00 btg
26 Besi hollow kotak 40/40 mm t.0.40mm pj=4m ( untuk rangka plafond ) 22,000.00 btg
27 Besi kotak hollow 40/20 mm t.0.40mm pj=4m ( Untuk rangka plafond ) 17,000.00 btg
28 Besi hollow galvanis 40/40 mm t= 0.35mm 23,000.00 m2
29 Besi hollow galvanis 20/40 mm t= 0.35mm 14,000.00 m2
30 Kawat las 25,000.00 kg
31 Angker dia 12 13,000.00 bh
32 Angker dia 16 17,000.00 bh
33 Angker dia 19 20,000.00 bh
34 Angker dia 20 21,000.00 bh
35 Angker dia 22 A 327 24,000.00 bh
36 Angker dia 32 35,000.00 bh
37 Baut HTB M12 - panjang 60 mm 2,000.00 bh
38 Baut HTB M16 - panjang 60 mm 4,000.00 bh
39 Baut HTB M20 - panjang 60 mm 7,000.00 bh
40 Baut HTB M22 - panjang 70 mm 13,000.00 bh
41 Baut HTB M27 - panjang 70 mm 31,000.00 bh
42 Walter mur 16 39,000.00 bh
43 Kawat harmonika 18,000.00 bh
44 Kawat nyamuk 18,000.00 bh
45 Kawat kassa 31,000.00 bh
46 Kawat burung 9,000.00 bh
47 Jaring pengaman plastik 6,000.00 bh
D TIANG PANCANG - K 500 ###
1 Pancang PC. SQ pile 25x25 - P. 6-12 m1
2 Pancang PC. SQ pile 30x30 - P. 6-12 m1
2 Pancang Pancang PC. SQ pile 40x40 - P. 6-12 m1
3 Joint plate 40x40 joint
4 Joint plate 25x25 ( Sudah termasuk pada tiang pancang ) - joint
5 Mob/Demob pemancangan
- Crane pancang + Diesel hammer 50 Ton ( 1 unit ) ###
- Crane service ###
4.1 Biaya lain - lain untuk pemancangan : -
- Keamanan alat LS
- Perlengkapan safety LS
- Akomodasi & transfortasi Crew LS
- Asuransi Jamsostek LS
6 Biaya pemotongan tiang pancang tiang pancang 40x40cm joint
7 Biaya pemotongan tiang pancang tiang pancang 25x25cm joint
Biaya pemotongan tiang pancang tiang pancang 30x30cm joint
8 Biaya penyambungan tiang pancang 40x40cm ( Las AWS E6013 ) joint
9 Biaya penyambungan tiang pancang 25x25cm ( Las AWS E6013 ) joint
Biaya penyambungan tiang pancang 30x30cm ( Las AWS E6013 ) joint
10 Biaya pemancangan tiang pancang 40x40cm m1
11 Biaya pemancangan tiang pancang 25x25cm m1
12 Handling tiang pancang m1
E KAYU
1 Kayu Kamper Samarinda :
- Jenis Papan 8,137,000.00 m3
- Jenis Balok 7,157,000.00 m3
2 Kayu Borneo Super -
- Jenis Papan 3,000,000.00 m3
HARGA
NO JENIS MATERIAL SAT
Rp.
- Jenis Balok 3,000,000.00 m3
3 Kayu bekisting / kayu sembarang / kayu lokal / terentang - Kelas III -
- Jenis Papan 1,500,000.00 m3
- Jenis Balok 1,500,000.00 m3
4 Dolken Ø 8-10cm panjang 4m - 5m 22,000.00 bt
5 Multiplek 18 mm 248,000.00 lbr
6 Multiplek 15 mm 202,000.00 lbr
7 Multiplek 12 mm 198,000.00 lbr
6 Multiplek 9 mm 151,000.00 lbr
8 Multiplek 6 mm 99,000.00 lbr
9 Multiplek 4 mm 56,000.00 lbr
10 Multiplek 3 mm 44,000.00 lbr
11 Teak wood ukuran 1.2 x 2.4 ( Jati ) 3mm 116,000.00 lbr
11 Plywood ukuran Pintu 900 x 2200 4mm 79,000.00 lbr
12 Teak wood ukuran 1.2 x 2.4 ( Jati ) 4mm 124,000.00 lbr
13 Formika uk. Besar 120 x 240 warna putih 151,000.00 lbr
14 Formika uk. Besar 120 x 240 warna 156,000.00 lbr
15 Melaminto uk. 120 x 240 ( Triplek lapis ) 79,000.00 lbr
16 Profil kayu jati Jabar 24,000.00 m1
F BAHAN LANGIT - LANGIT
F.1 Bahan Penutup Langit-Langit
1 Silicate uk. 120 x 240 t=4mm ex. GRC 81,000.00 lbr
2 Silicate uk. 120 x 240 t=6mm ex. GRC 102,000.00 lbr
3 Silicate uk. 120 x 240 t=8mm ex. GRC 168,000.00 lbr
4 Gypsum 2.4 x 1.2 t= 9 mm Jayaboard 63,000.00 lbr
5 Gypsum 2.4 x 1.2 t= 12 mm Jayaboard 90,000.00 lbr
6 Gypsum water prof 2.4 x 1.2 t= 9 mm Jayaboard 181,000.00 lbr
7 List Gypsum T. 8 - 10 cm 11,000.00 m1
8 List Plafond Gypsum T, 5 - 7 cm 9,000.00 m1
9 Tepung Gypsum @ 20 kg 74,000.00 zak
10 Plafond Akustik 25,000.00 lbr
11 Ceiling Panel 9mm (600mmx1200mm) 25,000.00 lbr
12 Textile tape 19,000.00 bh
Plafond gyfsum t=9mm ex. Jayaboard rangka hollow galvanis 20/40 & 40/40 mm t= 0.30mm
13 86,000.00 m2
( Harga terpasang )
Plafond gyfsum t=9mm ex. Jayaboard rangka hollow galvanis 40/40 mm, 20/40 mm t=
14 89,000.00 m2
0.35mm ( Harga terpasang )
Plafond GRC t=5mm rangka hollow galvanis 20/40mm & 40/40 mm t= 0.35mm ( Harga
15 99,000.00 m2
terpasang )
Plafond GRC t=6mm rangka hollow galvanis 20/40mm & 40/40 mm t= 0.40mm ( Harga
16 142,000.00 m2
terpasang )
17 Kalsiplank uk. 8 x 300 x 3000 setara ex. Kalsiboard 50,000.00 lbr
F.2 Rangka Plafond Metal ( Galvanis / Zincalume tebal 0.45mm ) - ###
- Kohler top Cros 35,000.00 batang
- Kohler ceiling Batten 36,000.00 batang
- Kohler furring chanel U Clamp Channel 36,000.00 batang
- Kohler Batten to top cross rail 1,000.00 pcs
- Kohlerfurring channel to top cross rail 1,000.00 pcs
- Kohler wall angle panjang 3m, tebal 0.43 mm 16,000.00 batang
- Kohler top cross rail spring adjuster rod 1,000.00 pcs
- U-champ 3,000.00 pcs
- 5mm Soft Suspension rod 1,000.00 pcs
- Angle clips - pcs
F.3 Rangka Metal BMSys ( untuk plafond gyfsum tile ) - ###
- Bracket PN-220 / PN-221 - pc(s)
- Suspension Rod 2400mm PN-409 3,000.00 pc(s)
- Suspension Clip Adjuster PN-410 3,000.00 pc(s)
- Wall Angel 3000mm PN-408 19,000.00 pc(s)
- Main Tee 3600mm PN-400 34,000.00 pc(s)
HARGA
NO JENIS MATERIAL SAT
Rp.
- Cross Tee 600mm PN-401 5,000.00 pc(s)
- Cross Tee 1200mm PN-402 10,000.00 pc(s)
-
HARGA
NO JENIS MATERIAL SAT
Rp.
F.3 Rangka Metal BMSys ( untuk partisi gyfsum ) -
- Wall Track 45,000.00 pc(s)
- Wall Stud 50,000.00 pc(s)
- Jointing Compound UB-10/20/888/CCL 20kg/bag(s) 82,000.00 bag(s)
- UB Tape 75m/roll(s) 22,000.00 roll(s)
- Drywall Screw 25mmX083 - pc(s)
- Jaya Sealant 580ml - pc(s)
G BAHAN FINISHING LANTAI & DINDING
G.1 Keramik dan Homogenius Tile
1 Keramik lantai 30 x 30 type Polised Setara Roman Gol. B 107,000.00 m2
2 Keramik lantai 30 x 30 type Unpolised Setara Roman Gol. C 113,000.00 m2
3 Homogenius Tile 60 x 60 type Polised Setara Indogress / Niro Granit 189,000.00 m2
4 Homogenius Tile 60 x 60 type Unpolised Setara Indogrees / Niro Granit 193,000.00 m2
5 Plint Homogenius Tile 10 x 60 cm polised setara Indogreess / Niro Granit 31,000.00 bh
6 Homogenius Tile 30 x 60 setara Indogreess / Niro Granit 189,000.00 m2
Stair nozing Homogeneus 10 x 60 unpolised Indogrees / Niro Granit 58,000.00 ###
G.2 Homogenius Tile - ###
1 Homogenius Tile 60 x 60 type Polised Setara Indogress / Niro Granit 189,000.00 m2
2 Plint Homogenius Tile 10 x 60 cm polised setara Indogreess / Niro Granit 31,000.00 bh
3 Stair nozing Homogeneus 10 x 60 unpolised Indogrees / Niro Granit 58,000.00 bh
G.3 Marmer, Garnit & batu alam berikut material jalan -
1 Batu andesit bakar macam ukuran 241,000.00 m2
2 Batu sikat 14,000.00 kg
3 Batu paras 250,000.00 m2
4 Batu candi 250,000.00 m2
G.4 Paving block ex. Cisangkan - ###
1 Paving block press 6 cm natural 2,000.00 bh
2 Paving block press 6 cm warna 2,000.00 bh
3 Paving block press 8 cm natural 2,000.00 bh
4 Paving block press 8 cm warna 3,000.00 bh
5 Grassblock 30x45 6 cm 15,000.00 bh
6 Grassblock 30x45 8 cm 21,000.00 bh
H BAHAN PENUTUP ATAP ###
1 Genteng Morando natural 2,000.00 bh
2 Genteng bubung morando ex jatiwangi 4,000.00 bh
3 Genteng samping penutup lisplang morando ex jatiwangi 5,000.00 bh
4 Genteng beton 6,000.00 bh
5 Nok genteng beton 8,000.00 bh
6 Seng gelombang 3" x 6" bkls 28 33,000.00 lbr
7 Nok seng Seng plat 3" x 6" bjls 28 44,000.00 lbr
8 Atap alumunium gelombang tebal 0,55 73,000.00 m2
9 Nok strandar 40 cm 18, swg 22 alumunium 60,000.00 m1
10 Talang alumunium 114,000.00 m1
11 Zincalume Hi- Tensile G 550 Union : - ###
- Union Pesona TCT 0.50mm lebar 990mm Colorbond 153,000.00 m2
- Union Pesona TCT 0.45mm lebar 990mm Colorbond 144,000.00 m2
- Ridge capping - 0.45 TCT Zincalume 940 width 82,000.00 m1
- Nok Standar untuk sudut atap kurang dari 5⁰ 49,000.00 m1
- Penutup atap arah memanjang ( Longitudinal fascia Capping - 0.45 TCT colorbond 470 width ) 64,000.00 m1
- Penutup atap arah melintang 64,000.00 m1
- Penutup pinggir dinding dan atap arah memanjang 64,000.00 m1
- Penutup pinggir dinding dan atap arah melintang 64,000.00 m1
- Penutup sudut 24,000.00 m1
- Standing seam TCT 0.50 mm 449,000.00 m2
- Talang U 1230 Zincalume t=0.50mm 184,000.00 m1
- Trimdek Hi-ten Zincalume t=0.40mm 99,000.00 m1
HARGA
NO JENIS MATERIAL SAT
Rp.
12 Alumunium foil Setara Primary Smart - Foam 6,5 mm 39,000.00 m2
13 Rangka atap baja ringan ( Harga terpasang ) setara GIGA Steel 180,000.00 m2
14 Alumunium Composite Panel ex Alucomp type 03 380,000.00 m2
15 Alumunium Composite Panel 235,000.00 m2
Rangka alumunium hollow 33x38x1mm, MF, bracket besi hollow 40x40x4 zincromate + silicone
16 316,000.00 m2
sealant dan accessories
J ALLUMUNIUM & KACA
1 Bahan kusen Alluminium ex. Alexindo 4 " ( silver / natural ) 90,000.00 m1
2 Bahan kusen Alluminium ex. Alexindo 4 " ( warna / coklat, hitam ) 141,000.00 m1
3 Bahan kusen Alluminium ex. Alexindo 3 " ( silver / natural ) 80,000.00 m1
4 Bahan kusen Alluminium ex. Alexindo 3 " ( warna / coklat, hitam ) 103,000.00 m1
5 Aneka pintu dan jendela : 365,000.00 m2
6 Jendela casement silver (60 x 120) + kaca polos 5 mm 401,000.00 Unit
7 Jendela casement coklat (60 x 120) + kaca polos 5 mm 449,000.00 Unit
8 Jendela sliding silver (60 x 120) + kaca polos 5 mm 425,000.00 Unit
9 Jendela sliding coklat (60 x 120) + kaca polos 5 mm 472,000.00 Unit
10 Pintu swing + kaca polos 5 mm 850,000.00 Unit
11 Pintu swing silver + kaca polos 8 mm tempered, floor hinge dorma BTS 84 1,701,000.00 Unit
12 Pintu swing coklat + kaca polos 8 mm tempered, foor hinge dorma BTS 84 1,890,000.00 Unit
13 Pintu frameless (tempered 12 mm polos) floor hinge dorma BTS 84 2,836,000.00 Unit
14 Pintu frameless (tempered 12 mm rayban) floor hinge dorma BTS 84 3,072,000.00 Unit
15 Pintu fitting (tempered 12 mm polos) floor hinge dorma BTS 84 3,308,000.00 Unit
16 Pintu fitting (tempered 12 mm rayban) floor hinge dorma BTS 84 3,545,000.00 Unit
17 Pintu swing blackboard, foor hinge dorma 1,302,000.00 m1
18 List Kaca karet L 1 cm - m'
19 List aluminium L 1 cm 3,000.00 m'
20 List aluminium L 1 x 2 cm 9,000.00 m'
21 Folding Gate t=0.8mm 519,000.00 m2
22 Rolling Door t=0.8mm + Motor penggerak ( Harga terpasang ) 1,039,000.00 m2
23 Kaca polos 3mm 66,000.00 m2
24 Ukuran 5 mm (kaca polos) 101,000.00 m2
25 Ukuran 5 mm (kaca rayban) 113,000.00 m2
26 Ukuran 5 mm (kaca dark blue) 170,000.00 m2
27 Ukuran 5 mm (kaca dark green) 170,000.00 m2
28 Ukuran 5 mm (kaca cermin) 330,000.00 m2
29 Ukuran 6 mm (kaca polos) 141,000.00 m2
30 Ukuran 6 mm (kaca buram) 174,000.00 m2
31 Ukuran 6 mm (kaca dark blue) 207,000.00 m2
32 Ukuran 6 mm (kaca dark green) 207,000.00 m2
33 Ukuran 6 mm (kaca cermin) 373,000.00 m2
34 Ukuran 8 mm (kaca polos) 199,000.00 m2
35 Ukuran 8 mm (kaca rayban) 283,000.00 m2
36 Ukuran 8 mm (kaca dark blue) 283,000.00 m2
37 Ukuran 8 mm (kaca dark green) 283,000.00 m2
38 Ukuran 10 mm (kaca polos) 330,000.00 m2
39 Ukuran 10 mm (kaca dark blue) 444,000.00 m2
40 Ukuran 10 mm (kaca dark green) 444,000.00 m2
41 Ukuran 12 mm (kaca polos) 425,000.00 m2
42 Ukuran 12 mm (kaca dark blue) 472,000.00 m2
43 Ukuran 12 mm (kaca dark green) 472,000.00 m2
44 Kaca clear tempered 5 mm 192,000.00 m2
45 Kaca clear tempered 6 mm 257,000.00 m2
46 Kaca clear tempered 8 mm 336,000.00 m2
47 Kaca clear tempered 10 mm 414,000.00 m2
48 Kaca clear tempered 12 mm 484,000.00 m2
49 Kaca Anti radiasi 15 mm (terpasang sebelum Jasa keuntungan ) 1,545,000.00 m2
HARGA
NO JENIS MATERIAL SAT
Rp.
50 Kaca clear tempered 19 mm 2,316,000.00 m2
51 Kaca Reflective Stopsol On Line 12 mm 612,000.00 m2
52 Plat alumunium t = 2mm 215,000.00 m2
53 Plat alumunium t = 3mm 375,000.00 m2
53 Plat alumunium L = 80cm 19,000.00 m1
54 Partisi cubical toilet lengkap daun pintu berikut accessories : 4,905,000.00 unit
- Partisi Phenolic resin Board ex. D'CUBICS tebal 12mm, (100% kedap air )
- Pintu Phenolic resin Board ex. D'CUBICS uk. 800x1800x12 mm,(100% kedap air )
- Door hardware stainless steel accessories
- Rangka frame alumunium N/A
- Kaki pedestal dan Screw conection stainless steel
57 Pintu baja tahan api, anti gores finish cat anti karat, Ukuran 900 x 2200 Ex. Bostinco 10,343,000.00 unit
56 Pintu baja tahan api, anti gores finish cat anti karat, Ukuran 1000 x 2200 Ex. Bostinco 11,492,000.00 unit
58 Pintu baja tahan api, anti gores finish cat anti karat, Ukuran 1600 x 2200 Ex. Bostinco 11,657,000.00 unit
55 Pintu baja tahan api, anti gores finish cat anti karat, Ukuran 2000 x 2200 Ex. Bostinco 11,869,000.00 unit
K STAINLESS STEEL
1 Stainless steel t=1mm Hair lineukuran 4' x 12' 201,000.00 m2
2 Stainless steel t=2mm Hair lineukuran 4' x 12' 402,000.00 m2
3 Plat stainless steel 1,2 x 1200 x 2400 413,000.00 lbr
4 Pipa stainless steel Ø 1/2" 226,000.00 btg
5 Pipa stainless steel Ø 1" 362,000.00 btg
6 Pipa stainless steel Ø 1 1/2" 543,000.00 btg
7 Pipa stainless steel Ø 2" 714,000.00 btg
8 Pipa stainless steel Ø 2 1/4" 355,000.00 m1
9 Pipa stainless steel Ø 2 1/2" 780,000.00 btg
10 Pipa stainless steel Ø 4" 992,000.00 btg
11 Stainless steel t=1.2mm Hair lineukuran 4' x 12' 241,000.00 m2
12 "U" Channel Stenliss Steel Uk 2x2cm ( untuk dudukan kaca fremless ) 47,000.00 m1
L JENIS CAT
1 Cat Tembok interior 35,000.00 Kg
2 Weathershield Pro Exterior warna standar 79,000.00 Liter
5 Cat Dasar setara mutu tinggi 79,000.00 Liter
6 Cat epoxi gloos ex Propant 74,000.00 ltr
7 Cat Kayu dan Besi setara mutu Seiv 61,000.00 kg
9 Cat Alkali 51,000.00 ltr
10 Cat jenis termoplastic 117,000.00 m2
11 Minyak cat standard biasa 14,000.00 Lt
12 Thiner ( minyak cat A spesial ) 19,000.00 Lt
13 Wood filer setara mutu tinggi 25,000.00 kg
14 Wood stand setara Impra 40,000.00 kg
15 Sanding Sealer setara Impra 33,000.00 Itr
16 Clear Melamic Setara Impra 37,000.00 kg
17 Meni kayu setara mutu menengah 16,000.00 kg
18 Meni besi setara mutu menengah 25,000.00 kg
19 Plitur jadi ( teak Oil ) 25,000.00 kg
20 Dempul kayu setara mutu menengah 18,000.00 kg
21 Dempul duko setara mutu tinggi 43,000.00 kg
22 Kwas setara Makita 11,000.00 bh
23 Rool cat 17,000.00 bh
24 Ampelas tembok 3,000.00 bh
25 Ampelas kayu & besi 3,000.00 bh
26 Plamur tembok setara mutu ICI. Dulux 19,000.00 kg
27 Minyak bekisting 20,000.00 Lt
28 Ram kawat ayam 9,000.00 m2
29 Coating Primer 17,000.00 m2
30 Water Proofing Produck Sika : -
- Sika rain Tite ( Untuk atap beton ) 49,000.00 kg
- Sika top 107 Seal ( Untuk toilet, balkon & area basah ) 16,000.00 kg
- Sikafloor Epolem Module ( Water cistern & rain water tank ) 90,000.00 kg
HARGA
NO JENIS MATERIAL SAT
Rp.
- Sikagard 81 Epolem ( Water cistern & rain water tank ) 24,000.00 kg
- Sikagard 720 Epolem ( Water cistern & rain water tank ) 23,000.00 kg
- Sikagard 62 ( Water cistern & rain water tank ) 341,000.00 kg
- Sika Chapdur ( Floor hardener ) Natural 4,000.00 kg
- Sika Chapdur ( Floor hardener ) warna 5,000.00 kg
31 Seal Bound 7,000.00 ltr
33 Anti rayap 15,000.00 m2
34 Epoxy Floor Coating Ex. Dongyang t=2mm 198,000.00 m2
35 Epoxy Floor Coating Ex. Dongyang t=3mm 236,000.00 m2
36 Cat anti bacteri setara Propant 85,000.00 Liter
M JENIS PELEKAT / LEM & IJUK
1 Sealent (penjepit kaca) dari karet 1,000.00 m1
2 Sealent setara mutu menengah 23,000.00 tube
3 Lem kuning setara mutu menengah 16,000.00 kg
4 Lem Kayu putih setara mutu menengah 11,000.00 kg
5 Ijuk 70,000.00 kg
6 Water stop lebar 150 mm 20,000.00 m1
7 Water stop lebar 200 mm 27,000.00 m1
8 Water stop lebar 250 mm 34,000.00 m1
9 Water stop lebar 300 mm 41,000.00 m1
10 Timbal tebal 2mm 1,465,000.00 m1
N MATERIAL JALAN -
1 Aspal curah 9,000.00 kg
2 Asphalt emulsi 10,000.00 kg
3 Asphalt minyak 13,000.00 kg
4 Material LPA Base Coarse A 276,000.00 m3
5 Material LPA Base Coarse B 230,000.00 m3
6 Material LPA Base Coarse C 220,000.00 m3
7 ATB 1,039,000.00 m3
8 Material Laston (AC-WC) 1,075,000.00 ton
9 Material Laston (AC-BC) 1,039,000.00 ton
10 Aspal Bitumen 10,000.00 kg
11 Prime Coat ( Asphalt Emulsi ) 10,000.00 lt
O SALURAN AIR
O.1 Saluran pipa air kotor -
1 Buis beton 1/2 Ø 20 cm 51,000.00 bh
2 Buis beton 1/2 Ø 30 cm 56,000.00 bh
3 Buis beton Ø 20 cm panjang 1M 66,000.00 bh
4 Buis beton Ø 30 cm panjang 1M 89,000.00 bh
5 Buis beton Ø 40 cm panjang 1M 94,000.00 bh
6 Buis beton Ø 50 cm panjang 1M 103,000.00 bh
7 Buis beton Ø 60 cm panjang 1M 141,000.00 bh
8 Buis beton Ø 80 cm panjang 1M 359,000.00 bh
9 Buis beton Ø 100 cm panjang 1M 368,000.00 bh
10 Pipa tanah Ø 15 cm panjang 1 M 85,000.00 bh
11 Pipa tanah Ø 20 cm panjang 1 M 66,000.00 bh
O.2 Precast and Prestress Concrete ( Product Beton Elemendo Perkasa ) -
12 Saluran air kotor ( U-DITCH ) : -
- 200x300mm 242,000.00 bh
- 300x400mm 242,000.00 bh
- 400x600mm 383,000.00 bh
- 500x600mm 474,000.00 bh
- 600x800mm 620,000.00 bh
- 800x1000mm 1,032,000.00 bh
- 1000x1000mm 1,403,000.00 bh
- 1200x1200mm 1,659,000.00 bh
P PLUMBING
P.1 PVC
1 Pipa PVC Ø 1/2" setara standard AW 17,000.00 Meter
HARGA
NO JENIS MATERIAL SAT
Rp.
2 Pipa PVC Ø 3/4" setara standard AW 24,000.00 Meter
3 Pipa PVC Ø 1" setara standard AW 37,000.00 Meter
4 Pipa PVC Ø 1 1/4" setara standard AW 55,000.00 Meter
5 Pipa PVC Ø 1 1/2" setara standard AW 65,000.00 Meter
6 Pipa PVC Ø 2" setara standard AW 82,000.00 Meter
7 Pipa PVC Ø 2 1/2" setara standard AW 122,000.00 Meter
8 Pipa PVC Ø 3" setara standard AW 174,000.00 Meter
9 Pipa PVC Ø 4" setara standard AW 281,000.00 Meter
10 Pipa PVC Ø 5" setara standard AW 449,000.00 Meter
11 Pipa PVC Ø 6" setara standard AW 638,000.00 Meter
12 Pipa PVC Ø 8" setara standard AW 1,132,000.00 Meter
13 Pipa PVC Ø 10" setara standard AW 1,699,000.00 Meter
P.2 PIPA - galvanize ( KELAS MEDIUM ) -
1 Galvanize Medium Ø 1/2” - Meter
2 Galvanize Medium Ø 3/4” - Meter
3 Galvanize Medium Ø 1” - Meter
4 Galvanize Medium Ø 1 1/4” - Meter
5 Galvanize Medium Ø 1 1/2” - Meter
6 Galvanize Medium Ø 2 ” - Meter
7 Galvanize Medium Ø 2 1/2” - Meter
8 Galvanize Medium Ø 3” - Meter
9 Galvanize Medium Ø 4” - Meter
10 Galvanize Medium Ø 5” - Meter
11 Galvanize Medium Ø 6” - Meter
12 Galvanize Medium Ø 8” - Meter
P.3 PIPA - GSP - SCHEDULE .40 -
1 GSP SCH.40 Ø 1/2” - Meter
2 GSP SCH.40 Ø 3/4” - Meter
3 GSP SCH.40 Ø 1” - Meter
4 GSP SCH. Ø 1 1/4” - Meter
5 GSP SCH. Ø 1 1/2” - Meter
6 GSP SCH. Ø 2” - Meter
7 GSP SCH. 40 Ø 2 1/2” - Meter
8 GSP SCH. 40 Ø 3” - Meter
9 GSP SCH. Ø 4” - Meter
10 GSP SCH. Ø 5” - Meter
11 GSP SCH. Ø 6” - Meter
12 GSP SCH.40 Ø 8” - Meter
P.4 PIPA BSP SCHEDULE 40 - hitam
1 Pipa besi BSP Ø 1" hitam 47,000.00 Meter
2 Pipa besi BSP Ø 1 1/4" hitam 62,000.00 Meter
3 Pipa besi BSP Ø 1 1/2" hitam 72,000.00 Meter
4 Pipa besi BSP Ø 2" hitam standar BOS 98,000.00 Meter
5 Pipa besi BSP Ø 2.5" hitam standar BOS 126,000.00 Meter
6 Pipa besi BSP Ø 3" hitam standar BOS 162,000.00 Meter
7 BSP SCH. Ø 4” 318,000.00 Meter
8 BSP SCH. Ø 5” 438,000.00 Meter
9 BSP SCH. Ø 6” 566,000.00 Meter
10 BSP SCH.40 Ø 8” 939,000.00 Meter
11 BSP SCH.40 Ø 10” 1,174,000.00 Meter
12 Lem PVC ASAHI 22,000.00 kg
13 Gergaji besi 11,000.00 bh
Q SANITARY ACCESSORIES
1 1 Unit Closet duduk setara TOTO Type CW 421 J / SW420JP 2,448,000.00 unit
2 Closet duduk TOTO Type C 704 L/SW 784 JP ( Difable ) 4,150,000.00 unit
3 Closet jongkok - unit
- CE 7 264,000.00 bh
- CE 9 + perlengkapan instalasi 3,346,000.00 bh
HARGA
NO JENIS MATERIAL SAT
Rp.
- CE 6 433,000.00 bh
5 Urinal U 57 M 2,363,000.00 unit
- Urinal U57M Muslim type urinal 1,403,000.00 ###
- T60P 893,000.00 ###
6 Urinal partition - unit
- Urinal partition w/fittings tipe A100 786,000.00 ###
- Urinal partition w/fittings tipe AW 115J 786,000.00 ###
8 Wastafel setara TOTO tipe LW103JT1 Complete set 1,661,000.00 unit
10 Wastafel Lengkap Standard setara Toto tipe L 521 VIA + TS 126AR + TX III L2YR 1,669,000.00 unit
11 Eye Shower 18,670,000.00 unit
12 Wastafel Lengkap setara Toto type LW 241 CJ + TX101LB 2,549,000.00 unit
LW 241 CJ - bh
13 Wastafel Lengkap setara Toto type LW 811 CJ + TX115LQBR 4,426,000.00 set
14 Wastafel dinding ex. TOTO Tipe LW 825 J komplit 3,836,000.00 unit
15 Bak mandi teraso volume air 0.30 m3 266,000.00 unit
16 Bak mandi fiberglass volume air 0.30 m3 173,000.00 unit
17 Bak mandi fiberglass volume air 1 m3 1,247,000.00 unit
18 Bath tube ex. Toto 3,545,000.00 unit
19 Kitchen zink setara Royal 1 lobang stainless lengkap 704,000.00 unit
20 Zink laboratorium setara TOTO type SK 508 3,431,000.00 unit
21 Zink setara TOTO tipe SK322E SPOEL HOOK 8,498,000.00 unit
22 Sloop Sink Toto tipe SK 33 ( spoel hook ) 6,239,000.00 unit
22 Kran TX 603 KM 509,000.00 unit
23 Kran TX 603 KCS 588,000.00 unit
23 Shower Spray setara Toto tipe THX 20 MCRB 322,000.00 unit
24 Floor drain TX 1 B 330,000.00 unit
26 Kran air setara Toto tipe T 23 B 13 V7N 228,000.00 unit
28 Kran Air Angsa setara Toto tipe TX 609 K 302,000.00 unit
29 Kran dinding T 30 ARQ 13N 474,000.00 unit
30 Kran dinding Toto tipe T 26-13 ( kran taman ) 685,000.00 unit
31 Kran dinding ex SUN-EI Type TY 20 JNR 184,000.00 unit
32 Hand shower set setara Toto tipe THX 118SE Lengkap 619,000.00 bh
39 Fixed shower head setara Toto tipe TX 465 SEN + TX 452 SE 1,679,000.00 unit
43 Paper Holder ex. Toto : -
Tempat Tissue setara Toto tipe TX 720 ACRB 501,000.00 bh
44 Soap holder/Tempat sabun ex. Toto tipe : -
- S 156N colour 61,000.00 unit
45 Grab Bar ex. Toto tipe : -
- TX3A1 Grab Bar (Panjang 350 mm) 484,000.00 bh
- TX3A2 Grab Bar (Panjang 500 mm) 587,000.00 bh
- TX3A3 Grab Bar (Panjang 800 mm) 717,000.00 bh
46 Double Robe Hook TOTO Type TS 118 WS 156,000.00 bh
47 Kran dinding panas dingin setara Toto tipe TX432SHV1BR 1,247,000.00 bh
R ACCESSORIES PINTU -
Setara WILKA & DORMA -
1 Lockcase : -
- Lockcase tipe Art 1492.55 ( untuk pintu kayu dobel ) 785,000.00 set
- Lockcase tipe Art 1492.55 ( untuk pintu kayu engkel ) 302,000.00 bh
- Lockcase tipe Art 1452.30 ( untuk pintu alumunium dobel ) 1,617,000.00 bh
- Lockcase tipe Art 1438.30 ( untuk pintualumunium engkel ) 597,000.00 bh
- Lockcase tipe Art 1450.55 ( untuk pintu geser ) 728,000.00 bh
- Alumunium lockcase ex. Griff 2110 536,000.00 bh
2 Lever Handle : - ###
- Lever Handle ART 312 SS setara WILKA 310,000.00 psg
3 Double Cylinder : - ###
- Double Cylinder WC Type Art 1477.60 (untuk toilet) 136,000.00 bh
- Double Cylinder Type Art 1400.60 245,000.00 bh
4 Tubular Pull Handle : - ###
- Tubular Pull Handle Griff 2342-SS -C300-D32-H70 ( pintu kaca & alumunium ) 401,000.00 psg
HARGA
NO JENIS MATERIAL SAT
Rp.
- Pull Handle tipe ART PH 2296 G-600 setara WILKA 1,245,000.00 psg
- Pull Handle tipe ART GD 9330-350 setara WILKA 236,000.00 psg
- Pull Handle tipe ART PH 260 - L 600 setara WILKA 996,000.00 psg
- Fush Handle Griff FP 4207 - F1/F2 83,000.00 psg
5 Engsel pintu : - ###
-Hinges Gracia Art 2302 tipe 4"x3"x2mm SS 86,000.00 psg
- Hinges Gracia Art 2201 tipe BB 4"x3"x3mm SS 117,000.00 psg
6 Floor hinge BTS 60 Comolete Dorma 931,000.00 set
7 Sliding track huskey 100 ex. Griff ( untuk pintu geser ) panjang 3 m 1,432,000.00 set
8 Engsel jendela : -
- Frictionstay top hung tipe 8"/MM2 73,000.00 psg
- Friction stay top hung tipe 12"/2mm 89,000.00 psg
- Friction stay top hung tipe 20"/2mm 162,000.00 psg
- Friction stay top hung tipe 24"/2,5mm 233,000.00 psg
9 Slot tarikan jendela alumunium : - ###
- Window lock Gracia Locking tipe Art 120 ( untuk jendela alumunium ) 33,000.00 bh
10 Fush Plate ( untuk pintu geser ) tipe : - ###
- Fush Plate FH 216 212,000.00 set
11 Door stop : - ###
- Door stop Gracia tipe Art 604/40mm SS. ( Floor ) 84,000.00 bh
- Door stop Gracia tipe Art 713 ( Wall ) Silver 142,000.00 bh
12 Door closer : - ###
- Door closer tipe TS 1M RA Dorma 316,000.00 set
13 Fushbolt : 119,000.00 bh
- Fluslr Bolt Gracia tanam atas bawah 8+12" 260,000.00 psg
- Dust Proof Art 1150 setara WILKA 33,000.00 bh
15 Floor hinge BTS 65 Complete setara WILKA 1,843,000.00 bh
16 Top Fact fitting PT-20 + Bottom Fact fitting PT-10 + Corner Lock PS - 10 LCK Dorma 3,083,000.00 bh
17 Over & side Top Fact fitting Pt-30 setara Drma 995,000.00 bh
18 Top Pipot PT.24 Dorma 442,000.00 bh
19 Bottom Fact fitting PT-10 Dorma - bh
20 Corner Lock PT - 10 LCK - bh
21 Escutcheon tipe Art 901 DR setara WILKA 72,000.00 set
- Door closer tipe 300 EN-4 complete 709,000.00 set
22 Shaft door tipe Art 542 + Anak kunci shaft door tipe Art 543 + Handle shaft door tipe Art RH 8-3 267,000.00 set
24 Rel pintu Henderson J-3, Panjang 1.475mm untuk pintu lebar 750 - 900 mm 263,000.00 bh
25 Rel pintu Henderson J-4, Panjang 1.700mm untuk pintu lebar 950- 1050 mm 321,000.00 bh
26 Rel pintu Henderson J-5, Panjang 1.980mm untuk pintu lebar 1050- 1200 mm 352,000.00 bh
27 Rel pintu Henderson J-6, Panjang 2.440mm untuk pintu lebar 1200- 1500 mm 447,000.00 bh
S TANAMAN - ###
Pohon Pelindung - ###
1 Pohon Bintaro t=300 cm 240,000.00 btg
2 Pohon Akasia mangium t=3m 112,000.00 btg
3 Dadap Merah t=2 - 4 m 330,000.00 btg
4 Pohon trembesi t = 3,00 m 259,000.00 btg
5 Angsana Tinggi 100 cm 6,000.00 btg
6 Pohon Cabefuya Caraiba `t=3m 156,000.00 btg
7 Pohon plamboyan t=300cm 283,000.00 btg
8 Pohon bungur t=1,5 -3 m 32,000.00 btg
9 Pohon kiara payung t=300cm 223,000.00 btg
10 Pohon Kupu-kupu t=300cm 236,000.00 btg
11 Pohon Mahoni t= 2,5 - 3 m 245,000.00 btg
12 Pohon Angsana T=300cm 70,000.00 btg
13 Pohon Ketapang laut t= 2 - 4 m 236,000.00 btg
14 Pohon Ketapang kencana tinggi 200 236,000.00 btg
15 Pohon Tanjung t= 2,5 - 3 m 251,000.00 btg
16 Pohon Kiara payung T= 1 - 2 m 27,000.00 btg
Pohon Pagar : - ###
17 Bambu Jepang (2 s/d 3m) 22,000.00 btg
HARGA
NO JENIS MATERIAL SAT
Rp.
18 Bambu Kuning (2 s/d 3m) 14,000.00 btg
Pohon Berbuah : - ###
19 Pohon Nangka tinggi 100cm 13,000.00 btg
20 Pohon Sukun t=1,5 - 2 m 30,000.00 btg
21 Pohon Kelengkeng t=1 m 141,000.00 btg
Tananaman hias : - ###
22 Bunga sepatu t = 30 - 50 cm 5,000.00 btg
23 Hanjuang merah t = 50 - 60 cm 8,000.00 btg
24 Kemuning t = 30 - 35 cm 4,000.00 btg
25 Anturium GC t = 40 - 50 cm 55,000.00 btg
26 Pohon semak ekor tupai tinggi 200cm 61,000.00 btg
27 Pohon kaca piring tinggi 40cm 27,000.00 btg
28 Palem botol t=100cm 55,000.00 btg
29 Palem ekor tupai Øbatang 10cm, tinggi 200cm 210,000.00 btg
30 Pohon semak mahkota duri 13,000.00 btg
31 Pohon pisang - pisangan 11,000.00 btg
32 Pohon semak hias taiwan beuty 11,000.00 btg
33 Teh-Tehan ( Duranta) 3,000.00 btg
34 Pohon Biola cantik t=1 - 2 m 212,000.00 btg
35 Pohon Jabon t= 70 cm - 80 cm 3,000.00 btg
36 Pohon Kasia kuning t=1 m 47,000.00 btg
37 Aires polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 1,000.00 btg
38 Lantana polybeg t=30cm ( 1 polibag ---25 pohon ) 3,000.00 btg
39 Soka Jepang/ground cover, tinggi 30cm ( 1 polibag=1m2 ---25 pohon ) 3,000.00 btg
40 Pohon hias bougenville tunggal t = 50 cm 33,000.00 btg
41 Pohon hias bougenville campur 3 warna t = 100 cm 82,000.00 btg
42 Pohon hias bougenville sambung t = 50 cm 44,000.00 btg
43 Perdu Oleander 22,000.00 btg
44 Azalea Ungu Polybag t=60cm ( 1 rumpun ---5 pohon ) 6,000.00 btg
45 Heliconia/perdu, tinggi 80cm ( 1 rumpun ---5 pohon ) 9,000.00 btg
46 Bayam Merah Polybag 30 2,000.00 btg
Rumput : - ###
47 Rumput Gajah 7,000.00 m2
48 Rumput jepang 17,000.00 m2
49 Rumput peking 6,000.00 m2
50 Rumput bermuda ( terpasang belum PPN + keuntungan ) 87,000.00 m2
51 Pohon Kamboja t=300 189,000.00 btg
52 Pohon YangLiu t= 200-400 108,000.00 btg
53 Pohon semak T agape Polybag 35 cm 47,000.00 btg
54 Pohon Kemuning t=150 236,000.00 btg
55 Pohon Terong muda t=150 203,000.00 btg
56 Pohon sikat botol t=150 189,000.00 btg
57 Pohon Cemara angin 236,000.00 btg
HARGA
NO JENIS MATERIAL SAT
Rp.

R ACCESSORIES PINTU-Terusan -
Panic Device (Cross Bar) + Handle tipe Art 8378 /MMP4 SE HF setara WILKA 2,975,000.00 set
Panlc Devlce Vertlcal tipe Art 8376 E setara WILKA 4,110,000.00 set
Terpasang -
Box Culvert Tipe 1 Uk. 800 x 800 2,319,000.00
Steel Greting Uk. 50 x 50 651,000.00 m1
Bak Kontrol 1,674,000.00 unit
Pipa Dalam Tanah Kedalaman 6 m ex. Drain Belt Atau Setara 2,046,000.00 unit
Sumur Resapan Diameter 800 816,000.00 ttk
- ttk
Wastafel Lengkap setara Toto type LW 811 CJ + TX115LQBR 4,426,000.00 set
Terpasang -
Biaya Pengurusan Dan Penyambungan Listrik PLN 197 KVA 239,962,000.00
1. Genset Tipe Silent 399,993,000.00
a. Diesel
- Kapasitas : 200 KVA
- Putaran : 1500 Rpm
- Pendingin : Air
- Langkah : 4
b. Alternator
- Kapasitas : 200 KVA
- Putaran : 1500 Rpm
- Tegangan : 220 V / 380 V
- Frekuensi : 50 Hz
c. Tanki Bulanan Kapasitas 5000 L 41,850,000.00
d. Tanki Harian Kapasitas 200 L 13,020,000.00
e. Pondasi Dan Rumah Genset 32,550,000.00
f. Test Dan Commisioning 1,395,000.00
2. Pengadaan Dan Pemasangan Kabel Listrik -
- Pekerjaan Pengadaan & Pemasangan Kabel Tufur NYFGBY 4 x 120 mm 694,000.00
3. Pengadaan Dan Pemasangan PJU -
- Lampu OSRAM PJU STREET LED ST-90W/757 AC, IP66-Rate, 4000 Lm, lifetime 50.000 jam 3,255,000.00
- Tiang Lampu Oktagonal Single Arm Ornamen T atau Siku PJU H-07M, Hot Dip Galvanized,
4,000,000.00
tebal 2 - 2,8 mm T= 7M termasuk Pondasi, base Plate dan angkur bolt
- Tiang Lampu Oktagonal Double Arm Ornamen T atau Siku PJU H-07M, Hot Dip Galvanized,
4,200,000.00
tebal 2 - 2,8 mm T= 7M termasuk pondasi, Base Plate dan angkur Bolt
- Instalasi Penerangan Jalan Umum 139,000.00
4. Pekerjaan Sumur Dalam (Deep Well) 353,400,000.00
- Jasa Survey Geolistrik -
- Jasa Well Loging -
- Pengeboran, Cashing, Screen +/- 60 m -
- Pompa Deep Well -
- Pemipaan Dan Accesories -
5. Distribusi Air Bersih -
a. Pompa Suplay GWT Ke Roof Tank -
- Pompa Transfer ( Transsfer Pump), ex. Raddyant, Equal, Ebara atau setara 51,615,000.00
- T y p e : Centrifugal End Suction -
- Capacity : 300 Lpm -
- Total Head : 30 m -
- Elec. Power : ± 3 KW/ 4 Hp/ 2900Rpm/ 380 V / 3 Ph / 50 Hz -
- Pompa Sudah Lengkap Terkopel Dengan Motor -
- Diameter Suction & Discharge : 2" / 2" -
b. Rumah Pompa Dan Pondasi 18,600,000.00
c. Pemipaan Dan Aksesoris Pompa -
- Pipa PPR PN-10 Dia. 50 mm ex. Wavin Tigris, Paralon Maspion Atau Setara 104,000.00
- Fitting Pipe (Elbow, Tee, Tee Reducer, etc) 3,906,000.00
- Support Dan Hanger 2,232,000.00
HARGA
NO JENIS MATERIAL SAT
Rp.
- Header diameter 100 mm (Lengkap dengan Flange etc) 1,990,000.00
- Gate valve Ø 50 mm, ex. Ecoval, Arita, Kitz atau setara 767,000.00
- Strainer Ø 50 mm 767,000.00
- Flexible Joint Ø 50 mm 1,581,000.00
- Check Valve Ø 50 mm 1,069,000.00
- Pressure Gauge 0-8 bar 688,000.00
- Accesories flange dan fitting-fitting 5,068,000.00
6. Jaringan Air Untuk Taman -
- Pipa PPR PN-10 Dia. 32 mm ex. Wavin Tigris, Paralon Maspion Atau Setara 52,000.00
- Fitting Pipe (Elbow, Tee Y, Reducer, etc) 2,822,000.00
- Galian Dan Urugan Kembali 1,668,000.00
- Test Dan Commisioning 930,000.00
DAFTAR HARGA SATUAN PEKERJAAN

NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
A PEKERJAAN PERSIAPAN
6.1.a 1 m2 Pembersihan Lapangan/ Pemerataan Tanah 12,868.00
6.1.b 1m2 Pembuatan Pagar Pengaman Proyek (dinding seng tbl 0.2 mm.t=1.8 m') Pondasi beton cor 1:3:5, 30x30x30
131,932.00
cm dari tiang kayu lokal
1 1 m' Pengukuran Dan Pemasangan Bouwplank 42,491.00
6.1.d 1 m2 Pembuatan Direksikeet 754,675.00
6.1.e 1 m2 Pembuatan Gudang/los bahan & bedeng tenaga kerja 704,823.00
6.1.f 1 Bulan Sarana dan prasarana fasilitas kerja sementara
1 Penyediaan listrik kerja sementara 38,705,288.00
2 Penyediaan air kerja sementara ( Selama proyek berjalan ) 2,535,499.80
3 Penyediaan lift barang sementara 22,633,598.00
Jumlah Sarana dan prasarana fasilitas kerja sementara 1 + 2 + 3 63,874,385.80
6.1.g 1 bulan Sewa alat tower Crane 191,622,255.00
6.1.h 1 unit Mob demob alat pemancangan ( Sub Cont ) 98,999,998.00
6.1.i 1 Hari Mobilisasi dan Demobilisasi Alat material (Asumsi mobil Colt Diesel) 904,198.00
6.1.j 1 orang Mobilisasi tenaga kerja jarak tempuh 200km kebawah 202,123.00
6.1.k 1 Set DOKUMENTASI / POTO PROGRES 4,253,918.00
6.1.l 1 Set Asbuilt dwg.(1 asli + 2 copy) Err:509
6.1.m 1 m2 Jalan sementara 44,328.00
6.1.n 1 set Pondasi tower crane ukuran 5x5x1,5m 98,116,300.00
6.1.o 1 m' Pekerjaan Pagar Kawat duri (tinggi pagar = 1.8 m pondasi cor beton 1:3:5) 260,000.00
6.1.p 1 m' Pekerjaan Pagar BRC T= 1.2 m Pondasi (Batukali + Sloof) Dihitung setiap 2.4 m 1,042,600.00
6.1.q 1 m² 1 m2 1,047,400.00
6.1.s 1 m² Pasang jaring pengaman proyek 11,000.00
B HARGA SATUAN PEKERJAAN TANAH
1 1 m³ Galian Tanah Dalam s/d 1 m manual 61,880.00
2 1 m³ Galian Tanah Dalam s/d 2 m manual 75,700.00
3 1 m³ Galian Tanah Dalam s/d 3 m manual 67,700.00
4 1 m³ Galian Tanah keras Dalam 1 m manual 82,400.00
5 1 m³ Galian Tanah Cadas Dalam 1 m manual 124,700.00
6 1 m³ Galian Tanah Lumpur Dalam 1 m manual 99,500.00
7 1 m² Pekerjaan Stripping Tebing 1 m 4,460.00
8 1 m³ Buang Tanah Sejauh 30 m 27,100.00
3 1 m³ Mengurug Kembali Galian
Mengurug Kembali Galian Dihitung dari 1/3 Kali Dari Indeks Pekerjaan Galian 29,400.00
4 1 m³ Memadatkan Tanah Per 20 cm 44,600.00
5 1 m³ Urugan pasir 196,400.00
6 1 m³ Pasang Lapisan Pudel Campuran 1 KP : 3 PP : 7 TL 281,900.00
7 1 m³ Pasang Lapisan Pudel Campuran 1 KP : 5 TL 284,000.00
8 1 m² Lapisan Ijuk Tebal 10 cm, untuk bidang resapan 475,400.00
9 1 m³ Urug Sirtu Padat Untuk Peniggian Lantai Bangunan 180,700.00
6 1 Bh Cerucuk Kayu Ø 8-10 Cm Panjang 4 m' 35,600.00
7 1 m² Penyemprotan anti rayap untuk pondasi 29,500.00
8 1 m² Styrofoam untuk peredam getaran mesin 20,100.00
6 1 m³ Buangan tanah kearea site dengan jarak 100 m 50,500.00
7 1 m³ Galian tanah sumuran rata-rata 93,700.00
A.3.2.1a NON SNI HARGA SATUAN PEKERJAAN TANAH
1 1 m2 Pekerjaan land Clearing dibuang pada jarak sampai dengan 3 KM dihitung setiap 100 m2 29,200.00
2 1 m³ Galian Tanah 47,800.00
7 1 m³ Timbunan tanah berikut Pemadatan tanah tiap 20 cm (tanah setempat bekas galian sumber bahan) 18,800.00
8 1 m³ Timbunan tanah berikut Pemadatan tanah tiap 20 cm dengan alat berat (Tanah dari luar) 65,000.00
Timbunan tanah berikut Pemadatan tanah tiap 20 cm secara manual (tanah setempat bekas galian sumber
9 1 m³ 56,200.00
bahan)
10 1 m³ Urugan Sirtu + pemadatan dengan alat berat 179,529.00
11 1 m³ Cut and fill dg jarak rata-rata maks 200 m 70,660.00
12 1 m³ Pengerukan saluran dengan alat berat 31,100.00
9 1 m³ Buangan tanah atau hasil Pengerukan saluran dengan alat berat keluar site radius sampai 10 km 61,600.00
10 1 m' Pengeboran tanah Ø 30cm ( Pakai mesin ) 84,200.00
11 1 m' Pengeboran tanah Ø 40cm ( Pakai mesin ) 108,400.00
12 1 m' Pengeboran tanah Ø 50cm ( Pakai mesin ) 132,500.00
13 1 m' Pengeboran tanah Ø 60cm ( Pakai mesin ) 156,800.00
14 1 m2 Pekerjaan Geotextile -
15 1 m³ Pekerjaan Soil Cement (Clean Set) 235,300.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
16 1 m³ Pekerjaan Soil Cement Tanah Laterit (Clean Set) 346,100.00
17 1 m³ Pemadatan sampai dengan CBR 5% 68,810.00
C HARGA SATUAN PEKERJAAN PONDASI
1 1 m³ Pasang Pondasi Batu Belah 1PC : 3PP 744,800.00
1 1 m³ Pasang Pondasi Batu Belah 1PC : 4PP 703,700.00
2 1 m³ Pasang Pondasi Batu Belah 1PC : 5PP 675,300.00
3 1 m³ Pasang Pondasi Batu Belah 1PC : 6PP 655,300.00
4 1 m³ Pasang Pondasi Batu Belah 1PC : 8PP 627,900.00
5 1 m³ Pasang Pondasi Batu Belah 1 KP : 1PC : 2 PP -
6 1 m³ Pasang Pondasi Batu Belah 1 PC : 3KP : 10 PP -
7 1 m³ Pasang Pondasi Batu Belah 1/4 PC : 1KP : 4 PP -
3 1 m³ Pasang Batu Kosong ( Aanstamping ) 378,900.00
4 1 m³ Pasang Bronjong Kawat Batu Kali 643,900.00
5 1 m³ Pasang Pondasi Siklop. 60 % Beton Campuran 1 : 2 : 3 2,096,400.00
6 1 m³ Pasang Pondasi Sumuran. Dia 100 cm 795,900.00
4 1 m³ Pasangan Pondasi Rollag Bata 1PC : 4PP 934,200.00
D Non SNI - PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PONDASI
1 1 Joint Potong/pecah kepala tiang pancang 45 x 45 -
2 1 Joint Potong/pecah kepala tiang pancang 25 x 25 -
3 1 Joint Sambungan tiang pancang 45 X 45 ( Joint plate Sq. 450 ) -
4 1 Joint Sambungan tiang pancang 25 X 25 ( Joint plate Sq. 250 ) -
5 1 m1 Pemancang 40x40cm ( HSPD CNT 300 Ton ) -
6 1 m1 Pemancang 25x25cm ( Hidrolik Hammer ) -
7 1 m1 Pengadaan tiang pancang 40x40 cm ( Tiang pancang pabrikasi ) -
8 1 m1 Pengadaan tiang pancang 25x25 cm ( Tiang pancang pabrikasi ) -
9 1 Joint Sambungan tiang pancang 30 X 30 ( Joint plate Sq. 300 ) 165,000.00
E SNI-2837-2008 PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PLESTERAN
1 1 m² Plesteran 1PC : 1PP Tebal 15 mm 62,300.00
1 1 m² Plesteran 1PC : 2PP Tebal 15 mm 56,600.00
1 1 m² Plesteran 1PC : 3PP Tebal 15 mm 54,200.00
4 1 m² Plesteran 1PC : 4PP Tebal 15 mm 52,500.00
2 1 m² Plesteran 1PC : 5PP Tebal 15 mm 51,600.00
2 1 m² Plesteran 1PC : 6PP Tebal 15 mm 50,900.00
3 1 m² Plesteran 1PC : 7PP Tebal 15 mm 50,400.00
4 1 m² Plesteran 1PC : 8PP Tebal 15 mm 50,000.00
5 1 m² Plesteran 1PC : 1/2KP : 3PP Tebal 15 mm 52,000.00
6 1 m² Plesteran 1PC : 2KP : 8PP Tebal 15 mm 49,900.00
7 1 m² Plesteran 1SM : 1KP : 1PP Tebal 15 mm 44,300.00
8 1 m² Plesteran 1SM : 1KP : 2PP Tebal 15 mm 45,300.00
9 1 m² Plesteran 1PC : 2PP Tebal 20 mm 75,800.00
10 1 m² Plesteran 1PC : 3PP Tebal 20 mm 72,500.00
11 1 m² Plesteran 1PC : 4PP Tebal 20 mm 70,200.00
12 1 m² Plesteran 1PC : 5PP Tebal 20 mm 69,100.00
13 1 m² Plesteran 1PC : 6PP Tebal 20 mm 68,000.00
14 1 m² Plesteran 1SM : 1KP : 2PP Tebal 20 mm 62,900.00
15 1 m² Berapen 1PC : 5PP Tebal 15 mm 31,300.00
16 1 m' Plesteran skoneng 1PC : 2PP Lebar 10 mm 51,000.00
17 1 m' Plesteran Granit 1PC : 2Granit Tebal 10 mm 73,300.00
18 1 m' Plesteran Granit 1PC : 2Teraso Tebal 10 mm 73,300.00
3 1 m² Plesteran Ciprat 1PC : 2PP 41,900.00
4 1 m' Finishing Siar Pasangan Dinding Bata Merah 24,200.00
5 1 m' Finishing Siar nat / tali air 11,500.00
5 1 m² Finishing Siar Pasangan Batu Kali Adukan 1PC : 2PP 50,500.00
6 1 m² Finishing Acian 31,100.00
7 1 m² Flesteran + Acian (Pakai perekat jenis mortar) 60,500.00
F HARGA SATUAN PEKERJAAN LANGIT-LANGIT(PLAFOND)
A.4.5.1.1 1 m² Pasang Langit-langit Asbes Semen Tebal 4 mm, 5mm dan 6mm -
A.4.5.1.2 1 m² Pasang Langit-langit Akustik 30 x 30 cm -
A.4.5.1.3 1 m² Pasang Langit-langit Akustik 30 x 60 cm -
A.4.5.1.4 1 m² Pasang Langit-langit Akustik 60 x 120 cm -
A.4.5.1.5 1 m² Pasang Langit-langit Tripleks 120 x 240 cm. Tebal 3. 4. 6 mm -
1 1 m² Pasang Langit-langit Gypsum Board 120 x 240 x 9 mm. Tebal 9 mm 38,800.00
A.4.5.1.7a 1 m² Pasang Langit-langit calcium cilicate Board 120 x 240 Tebal 6 mm 56,500.00
2 1 m² Pasang Langit-langit Gypsum water prof 120 x 240 Tebal 9 mm 88,200.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
3 1 m² Pasang Ceiling Panel tile 9mm (600mmx1200mm) 54,800.00
4 1 m' Pasang List plafon gyfsum profil 22,300.00
A.4.5.1.9 1 m' Pasang List Langit-langit Kayu Profil 37,100.00
5 1 m² Pasang rangka hollow galvanises uk. gypsum / calcium cilicate 55,300.00
6 1 m² Pasang rangka hollow uk. gypsum / calcium cilicate 65,000.00
7 1 m² Pasang rangka metal furing BMSys ( Untuk ceilling panel 600 x 1200 ) 68,700.00
8 1 m² Pasang plafond gyfsum board t=9mm berikut rangka metal furing 139,000.00
9 1 m² Pasang plafond gyfsum board t=9mm berikut rangka hollow t=0.40mm 103,800.00
0 1 m² Pasang plafond calcium cilicate GRC t=6mm berikut rangka hollow galvanises 111,800.00
10 1 m² Pasang plafond calcium cilicate GRC t=6mm berikut rangka hollow t=0.40mm 121,500.00
11 1 m² Pasang plafond gyfsum tile 600 x 1200 t=6mm berikut rangka metal furing BMSys 123,600.00
12 1 m² Pasang plafond gyfsum board t=9mm berikut rangka metal furing 188,400.00
13 1 m² Dinding Partisi dobel Gypsum 12 mm + Rangka Metal BMSys 176,791.00
14 1 m² Dinding Partisi Double Kalsiboard 6 mm + + Rangka Metal BMSys 186,000.00
15 1 m² Pasang plafond gyfsum water prof t=9mm berikut rangka hollow galvanises 143,500.00
6.F SNI-3434-2008 PENETAPAN INDEKS HARGA SATUAN PEKERJAAN KAYU
2 1 m³ Membuat & memasang Kusen Pintu dan Kusen Jendela.Kayu Jati Kelas II 11,844,700.00
3 1 m² Membuat & memasang Pintu Klamp Standart. Kayu Kelas II 496,900.00
4 1 m² Membuat & memasang Pintu Klamp sederhana. Kayu Kelas III gudang sementara 270,800.00
5a 1 m² Membuat & memasang Daun Pintu Panel.Kayu Kamper Samarinda Kelas II 758,400.00
6.a 1 m² Membuat & memasang Pintu dan Jendela Kaca.Kayu Kamper Samarinda Kelas II 533,900.00
7.a 1 m² Membuat & memasang Pintu dan Jendela Jalusi. Kayu Kelas II 973,200.00
Membuat & memasang Daun Pintu Kayu Lapis (Plywood) Rangkap.Rangka Tertutup Kayu Kelas II (lebar
8 1 m² 593,200.00
Sampai 90 cm)
9 1 m² Membuat & memasang Pintu Plywood Rangkap.Rangka Expose Kayu Kelas I Jati 638,000.00
10 1 m² Pasang Jalusi Kusen. Kayu Kamper Samarinda 832,400.00
11 1 m² Pasang Daun pintu teakwood rangkap, rangka kayu Kamper Samarinda 679,700.00
12 1 m² Pasang daun pintu Teakwood Rangkap bagian dalapis Lapis Formika. Rangka Expose Kayu Kamper Samarinda 791,400.00
13 1 m³ Pasang Kuda-kuda Expose. Kayu Kamper Samarinda 13,667,200.00
14 1 m² Pasang Rangka Atap Sirap. Kayu Kamper Samarinda 135,800.00
15 1 m² Pasang Rangka Langit-Langit (50x100)cm. Kayu Borneo super 97,500.00
16 1 m² Pasang Rangka Langit-Langit (60x60)cm. Kayu Borneo super 105,500.00
17 1 m' Pasang Lisplank (3x20)cm. Kayu Kamper Samarinda 127,300.00
18 1 m' Pasang Lisplank (3x30)cm. Kayu Kamper Samarinda 128,300.00
19 1 m² Pasang Rangka Dinding Pemisah/partisi (60x120) cm. Kayu Kamper Samarinda 312,100.00
20 1 m² Pasang Dinding Pemisah/partisi Teakwood Rangkap. Rangka Kayu Kamper Samarinda 341,700.00
21 1 m² Pasang Dinding Pemisah/partisi Plywood Rangkap. Rangka Kayu Kamper Samarinda 361,400.00
22 1 m² Pasang Dinding Lambriziring dari Plywood Ukuran (120x240)cm 35,300.00
23 1 m² Pasang Dinding Bilik . Rangka Kayu Kelas III Borneo 111,100.00
24 1 m' Cope Lampu kayu Kamper Samarinda Finish cat Duco 183,700.00
25 1 m' Plin kayu Kamper Samarinda 10 x 100mm finish melamik 79,000.00

G HARGA SATUAN PEKERJAAN DINDING


1 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 2PP 230,300.00
1 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 3PP 219,500.00
3 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 4PP 212,100.00
2 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 5PP 208,400.00
3 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC : 6PP 207,400.00
4 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1 Bata. Campuran Spesi 1PC:3KP:10PP 194,000.00
5 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 1PC : 2PP 111,400.00
3 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 1PC : 3PP 106,200.00
4 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 1PC : 4PP 103,300.00
4 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 1PC : 5PP 101,400.00
5 1 m² Pasangan Dinding Bata Merah kelas 1 Uk.(5x11x22)cm Tebal 1/2 Bata. Campuran Spesi 1PC : 6PP 100,500.00
5 1 m² Pasangan Dinding Batako. Campuran Spesi 1PC : 5PP 48,200.00
6 1 m³ Pasangan Pondasi Rollag Bata 1:4 859,000.00
16 1 m² Pasangan Dinding HB/CB 20.Campuran Spesi 1PC : 3PP -
17 1 m² Pasangan Dinding HB/CB 20.Campuran Spesi 1PC :4PP -
18 1 m² Pasangan Dinding HB/CB 15.Campuran Spesi 1PC :3PP -
19 1 m² Pasangan Dinding HB/CB 15.Campuran Spesi 1PC :4PP -
20 1 m² Pasangan Dinding HB/CB 10.Campuran Spesi 1PC :3PP -
21 1 m² Pasangan Dinding HB 10.Campuran Spesi 1PC 4PP -
22 1 m² Pasangan Dinding Terawang (Roster beton) Uk.(12x11x24)cm.Campuran Spesi 1PC : 3PP 220,100.00
23 1 m² Pasangan Dinding Terawang (Roster beton) Uk.(12x11x24)cm.Campuran Spesi 1PC : 4PP 220,100.00
24 1 m² Pasangan Dinding Bata Berongga Ekspose Uk.(5x11x24)cm.Campuran Spesi 1PC : 3PP -
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
7 1 m² Pasangan Dinding Bata ringan tebal 7.5cm 110,300.00
8 1 m² Pasangan Dinding Bata ringan tebal 10cm 120,300.00
9 1 m² Pasangan Dinding Bata ringan tebal 15cm 163,500.00
10 1 m² Pasangan Dinding panel fasade beton ringan super panel ex. Hebel tebal 100 mm 480,300.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
H HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM
1 1 kg Memasang besi profil 26,400.00
2 1 kg Memasang rangka kuda-kuda Baja IWF 26,400.00
3 1 kg Memasang Rangka Kuda - Kuda Baja L dan Canal 26,400.00
4 1 kg Memasang Plat Baja t=…… 26,400.00
5 1 kg Mengerjakan Pekerjaan Perakitan 1,650.00
6 1 m² Membuat Pintu Besi Plat Baja Tebal 2 mm Rangkap. Rangka Baja Siku 829,200.00
7 10 cm Mengerjakan Pengelasan Dengan Las Listrik 50,200.00
8 1 kg Memasang rangka kuda-kuda Baja IWF ( Termasuk pengelasan dan perakitan ) 33,100.00
9 1 kg Memasang rangka kuda-kuda Baja C, UNP dan L ( Termasuk pengelasan dan perakitan ) 31,400.00
10 1 kg Memasang baja plat semua ukuran ( Termasuk pengelasan dan perakitan ) 31,190.00
11 1 kg Angkur baut M12mm 16,200.00
12 1 kg Angkur baut M16mm 20,600.00
5.f. 1 kg Angkur baut M20mm 25,000.00
5.g. 1 kg Angkur baut M32mm 40,400.00
5.h. 1 kg Mur baut M12mm 4,100.00
5.i. 1 kg Mur baut M16mm 6,300.00
5.j. 1 kg Mur baut M19/20mm 9,600.00
5.k. 1 kg Mur baut M22mm 28,300.00
5.l. 1 kg Mur baut M32mm 36,000.00
5.m. 1 kg Walter moor 45,900.00
13 1 m² Membuat Rangka Jendela Besi Scuare Tube (25 x 5) cm 1,563,100.00
14 1 m² Memasang Pintu Rolling Door Besi ( Manual ) 577,200.00
15 1 m² Memasang Pintu Lipat (Folding Door) bahan plastik/PVC 653,400.00
16 1 m² Memasang Jalusi Alumunium 326,000.00
17 1 m² Memasang Rolling Door t=0.8mm + Motor penggerak 1,142,900.00
16 1 m1 Memasang Kusen Pintu Alumunium 4" tebal 1.2mm ex. YKK ( silver / natural ) #REF!
17 1 m1 Memasang Kusen Pintu Alumunium 3" tebal 1.2mm ex. YKK ( silver / natural ) #REF!
18 1 m² Memasang Pintu Alumunium Strip Lebar 8 cm #REF!
19 1 m² Memasang Pintu Kaca Rangka Alumunium #REF!
20 1 m² Memasang Jendela Kaca Rangka Alumunium 291,700.00
20 1 m² Memasang Venetions Blinds dan Vertical Blinds 1,402,600.00
21 1 m² Memasang Teralis Besi Strip (2 x 3) mm 530,600.00
22 1 m² Memasang Kawat Nyamuk 112,300.00
23 1 m² Memasang Jendela Nako & tralis 343,200.00
24 1 m1 Memasang Talang Datar / Jurai alumunium Lebar 90 cm 121,800.00
25 1 m1 Memasang Talang 1/2 Lingkaran D-15 cm. Alumunium plat Lebar 90 cm 78,400.00
25 1 m1 Railling tangga dari Stainless dan kaca 981,800.00
26 1 m1 Railling tangga dari pipa Stainless 893,300.00
27 1 m1 Railling tangga dari pipa BSP 822,900.00
28 1 m² Pekerjaan Alumunium Composite Panel 636,400.00
29 1 m² Curtain Wall + kaca + Jendela + accessories ( Dihitung uk. 2.750 x 15.750m ) #REF!
29 1 unit Partisi cubical toilet lengkap daun pintu berikut Accessories ( terpasang ) 5,395,500.00
30 1 m2 Pasang dinding Zinc - Allumunium colorbond TCT 0.45mm 276,900.00
31 1 m2 Pintu baja tahan api, anti gores finish cat anti karat, Ukuran 2000 x 2200 Ex. Bostinco 13,649,350.00
32 1 m2 Pintu baja tahan api, anti gores finish cat anti karat, Ukuran 1000 x 2200 Ex. Bostinco 13,215,800.00
33 1 m2 Pintu baja tahan api, anti gores finish cat anti karat, Ukuran 900 x 2200 Ex. Bostinco 11,894,450.00
34 1 m2 Pintu baja tahan api, anti gores finish cat anti karat, Ukuran 1600 x 2200 Ex. Bostinco 13,405,550.00
35 1 m2 Buffer plate / Kicking plate Stainless stell Hairline #REF!

I HARGA SATUAN PEKERJAAN BETON


1 1 m³ Membuat beton tumbuk/Lantai kerja 1:3:5 808,900.00
2 1 m³ Membuat beton 1:2:3 801,100.00
3 1 m³ Membuat beton mutu fc=7,4 Mpa (K 100), slum (12 ± 2) cm, w/c = 0.87 790,900.00
4 1 m³ Membuat beton mutu fc=9.8 Mpa (K 125), slum (12 ± 2) cm, w/c = 0.76 821,500.00
5 1 m³ Membuat beton mutu fc=12.2 Mpa (K 150), slum (12 ± 2) cm, w/c = 0.72 845,600.00
6 1 m³ Membuat beton mutu fc=7,4 Mpa (K 100), slum (3-6) cm, w/c 730,200.00
7 1 m³ Membuat beton mutu fc=14.5 Mpa (K 175), slum (12 ± 2) cm, w/c = 0.66 874,000.00
8 1 m³ Membuat beton mutu fc=16.9 Mpa (K 200), slum (12 ± 2) cm, w/c = 0.61 901,200.00
9 1 m³ Membuat beton mutu fc=19.3 Mpa (K 225), slum (12 ± 2) cm, w/c = 0.58 921,400.00
10 1 m³ Membuat beton mutu fc=21.7 Mpa (K 250), slum (12 ± 2) cm, w/c = 0.56 935,000.00
11 1 m³ Membuat beton mutu fc=24.0 Mpa (K 275), slum (12 ± 2) cm, w/c = 0.53 958,400.00
12 1 m³ Membuat beton mutu fc=26.4 Mpa (K 300), slum (12 ± 2) cm, w/c = 0.52 1,211,500.00
13 1 m³ Membuat beton mutu fc=28.8 Mpa (K 325), slum (12 ± 2) cm, w/c = 0.49 1,038,600.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
14 1 m³ Membuat beton mutu fc=31.2 Mpa (K 350), slum (12 ± 2) cm, w/c = 0.48 1,198,600.00
3 1 m³ Beton B0 ( ready mix ) 683,600.00
4 1 m³ Beton K - 175 ( ready mix ) 1,182,500.00
4 1 m³ Beton K - 250 ( ready mix ) 1,144,400.00
5 1 m³ Beton K 300 (ready mix) 1,211,500.00
7 1 m³ Beton K - 375 ( ready mix ) 1,198,600.00
15 1 m³ Membuat beton kedap air dengan strorox - 100 1,029,600.00
16 1 m³ Memasang PVC waterstop L=150 mm 31,300.00
17 1 m³ Memasang PVC waterstop L=200 mm 41,100.00
18 1 m³ Memasang PVC waterstop L=230 mm 50,100.00
Pembesian
6 Dengan Besi polos/Ulir :
Tiap 10 kg 113,700.00
Tiap 1 kg 11,370.00
7 1 m² Pekerjaan Wire Mesh M - 6 46,600.00
8 1 m² Pekerjaan Wire Mesh M - 7 57,700.00
9 1 m² Pekerjaan Wire Mesh M - 8 69,900.00
10 1 m² Pekerjaan Wire Mesh M - 10 101,000.00
11 10 kg Kabel Presstressed Polos/Strands 10,900.00
12 10 kg Jaring Kawat Baja / Wire Mesh 10,300.00
13 1 m² Memasang Bekisting Untuk Pondasi ( 1 x pakai ) 143,400.00
14 1 m² Memasang Bekisting sloof ( 1 x pakai ) 151,700.00
15 1 m² Memasang Bekisting Untuk Kolom ( 2 x pakai ) 221,000.00
16 1 m² Memasang Bekisting Untuk Balok ( 2 x pakai ) H < 800 210,300.00
25.a 1 m² Memasang Bekisting Untuk Balok ( 2 x pakai ) H > 800 211,100.00
17 1 m² Memasang Bekisting Untuk plat lantai ( 2 x pakai ) 268,600.00
18 1 m² Memasang Bekisting Untuk Dinding ( 2 x pakai ) 299,100.00
19 1 m² Memasang Bekisting Untuk Tangga ( 2 x pakai ) 211,700.00
11 1 m² Memasang bekisting Bata Merah Uk.(5x11x22)cm Tebal 1/4 Bata. Campuran Spesi 1PC : 5PP 50,700.00
20 1 m² Memasang jembatan untuk pengecoran beton 82,700.00
12 1 m³ Pondasi Beton Bertulang (150 kg Besi + Bekisting) 3,334,700.00
13 1 m³ Sloof Beton Bertulang (200 kg Besi + Bekisting) 4,057,300.00
14 1 m³ Kolom Beton Bertulang (300 kg Besi + Bekisting) 7,294,500.00
15 1 m³ Balok Beton Bertulang (200 kg Besi + Bekisting) 5,719,900.00
16 1 m³ Plat Beton Bertulang (150 kg Besi + Bekisting) 4,880,300.00
17 1 m³ Tangga Beton Bertulang (150 kg Besi + Bekisting) 5,184,200.00
18 1 m³ Dinding Beton Bertulang (200 kg Besi + Bekisting) 5,293,700.00
19 1 m' Kolom Praktis Beton Bertulang (11 x 11) cm 94,800.00
20 1 m' Ring Balok Beton Bertulang (10 x 15) cm 114,100.00
21 1 m' Joint Sealant 24,200.00
22 1 Bh Pekerjaan Dowel Ø 1" 14,500.00
21 1 m1 Gutter Lebar 20 cm dalam 10 cm 34,600.00
22 1 m1 Gutter Lebar 25 cm dalam 10 cm 51,300.00
23 1 m2 Grouting tebal 25 mm 385,500.00
24 1 m2 Pagar panel precast 247,700.00
25 1 bt Kolom ( H-BEAM - 260 ) pagar panel precast tinggi 2.60m 411,500.00
26 1 bt Kolom ( H-BEAM - 300 ) pagar panel precast tinggi 3.00m 473,400.00
27 1 bt Kolom ( H-BEAM - 340 ) pagar panel precast tinggi 3.40m 631,200.00
28 1 bt Kolom ( H-BEAM - 360 ) pagar panel precast tinggi 3.60m 667,500.00
29 1 bt Kolom ( H-BEAM - 380 ) pagar panel precast tinggi 3.80m 705,500.00
30 1m2 Dinding panel fasade beton precast tebal 120 mm 275,600.00
J PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PENUTUP ATAP
1 1 m² Atap Polycarbonat 313,300.00
2 1 m² Glass wool WM6 51,200.00
3 1 m² Pasang atap genteng morando 58,500.00
4 1 m' Pasang genteng bubung morando 89,900.00
5 1 m' Pasang genteng samping penutup lisplang morando 95,400.00
6 1 m' Pasang atap genteng beton 99,800.00
7 1 m' Pasang nok genteng beton 106,100.00
8 1 m² Pasang atap seng gelombang 42,200.00
9 1 m² Pasang atap nok seng 34,900.00
1 1 m² Pasang atap Zinc - Allumunium Prepainted TCT 0.45mm 200,300.00
2 1 m² Pasang atap Zinc - Allumunium Standing seam TCT 0.50 mm 602,300.00
3 1 m' Pasang nok Zinc - Allumunium 136,400.00
4 1 m' Pasang penutup atap arah memanjang ( Longtudinat pascia capping ) TCT 0.45mm 114,700.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
5 1 m' Pasang atap arah melintang ( Transvarsa pascia capping ) TCT 0.45mm 114,700.00
4 1 m² Pasang Alumunium foil Setara Primary Smart - Foam 6.5 mm 58,900.00
5 1 m' Pasang Talang Gantung 145,600.00
6 1 m' Talang Jurai atau datar Zincalume 138,200.00
7 1 m' Talang Vertikal Pralon D 1 1/2" 28,900.00
8 1 m' Talang Vertikal Pralon D 2" 34,200.00
9 1 m' Talang Vertikal Pralon D 2 1/2" 46,700.00
10 1 m' Talang Vertikal Pralon D 3" 63,000.00
5 1 m' Talang Vertikal Pralon d 4" 96,600.00
6 1 m' Sparing Pralon d 1 1/2" 6,600.00
7 1 m' Sparing Pralon d 2" 8,000.00
8 1 m' Sparing Pralon d 2 1/2" 11,300.00
9 1 m' Sparing Pralon d 3" 15,600.00
6 1 m' Sparing Pralon d 4" 24,400.00
7 1 m' Talang jurai atau datar BJLS 74,500.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
K HARGA SATUAN PEKERJAAN PENUTUP DINDING & LANTAI
1 1 m² Pasang Lantai keramaik Ukuran (33 x 33)cm polished setara Roman Gol. A 277,400.00
A.4.4.3.34A 1 m² Pasang Lantai keramaik Ukuran (33 x 33)cm unpolished setara Roman Gol. C 312,200.00
1 1 m² Pasang Lantai Keramik Ukuran (30 x 30)cm polished setara Roman Gol. A 262,300.00
2 1 m² Pasang Lantai Keramik Ukuran (30 x 30) cm polished setara Roman Gol. B 269,400.00
A.4.4.3.35B 1 m² Pasang Lantai Homogenous Ukuran (30 x 30) cm Setara Niro granit 358,700.00
3 1 m² Pasang Lantai Keramik Ukuran (20 x 20) cm polished setara Roman Gol. A 273,100.00
A.4.4.3.36 1 m² Pasang Lantai Keramik Ukuran (10 x 33) cm. polished setara Roman Gol. A 370,200.00
A.4.4.3.38 1 m² Pasang Lantai Mosaik Ukuran (30 x 30) cm. Campuran Spesi 1 PC : 3 PP 1,739,000.00
A.4.4.3.39 1 m' Pasang Plint Keramik Ukuran (10 x 20) cm polished setara Roman Gol. A 34,500.00
39.a 1 m' Pasang Plint Keramik Ukuran (10 x 30) cm polished setara Roman Gol. A 36,400.00
4 1 m' Pasang Plint Keramik Ukuran (10 x 40) cm polished setara Roman Gol. A 46,500.00
5 1 m' Pasang Plint Homogenius Tile Ukuran (10 x 60) cm polished setara Indo Gress 78,600.00
39.d 1 m' Pasang Plint Homogeneus Ukuran (10 x 30) cm 95,100.00
39.e 1 m' Pasang Plint Homogeneus Ukuran (10 x 40) cm 96,000.00
3 1 m' Pasang Plint Homogeneus Ukuran (10 x 60) cm polished setara Niro Granit 47,300.00
39.g 1 m' Pasang Border Keramik Ukuran (8 x 20) cm setara Roman 85,200.00
39.h 1 m' Pasang Border Keramik Ukuran (8 x 25) cm setara Roman 92,200.00
39.i 1 m' Pasang Border Keramik Ukuran (8 x 30) cm setara Roman 98,800.00
39.j 1 m' Pasang Stair nozing Keramik Ukuran (10 x 20) cm setara Roman 126,300.00
39.k 1 m' Pasang Stair nozing Homogenius Tile Ukuran (10 x 60) cm setara Indogress / Niro Granit 128,100.00
39.l 1 m' Pasang Stair nozing Homogenous Ukuran (10 x 60) cm setara Niro granit 138,700.00
#VALUE! 1 m' Pasang Plint Keramik Ukuran (10 x 10) cm -
#VALUE! 1 m' Pasang Plint Keramik Ukuran (5 x 20) cm -
A.4.4.42 1 m' Pasang Plint Internal Cove Artistik Ukuran (5 x 5 x 20) cm 262,600.00
A.4.4.43 1 m2 Pasang lantai Marmer slab cream Malaga Premium C1 Setara ex. Ujung Pandang 672,600.00
A.4.4.43A 1 m2 Pasang lantai Marmer slab cream Malaga Premium Setara ex. Citatah 672,600.00
A.4.4.43B 1 m2 Pasang lantai Marmer slab kawi Setara ex. Tulung agung 86,450.00
A.4.4.43C 1 m2 Pasang lantai Marmer Ukuran (60x60) cm Polised Setara ex. Ujung Pandang 672,600.00
A.4.4.43D 1 m2 Pasang lantai Marmer Ukuran (60x60) cm Polised Setara ex. Citatah 589,800.00
A.4.4.43E 1 m2 Pasang lantai Marmer Ukuran (60x60) cm Polised Setara ex. Tulung Agung 650,400.00
A.4.4.43F 1 m2 Pasang lantai Granit macam-macam corak slab setara Cina 1,086,500.00
A.4.4.43G 1 m2 Pasang lantai Granit macam-macam corakslab setara India 1,060,800.00
A.4.4.43H 1 m2 Pasang lantai Granit macam-macam corakslab setara Tulung Agung Indonesia 751,900.00
A.4.4.44 1 m² Pasang Lantai Karpet 110,500.00
A.4.4.45 1 m² Pasang underlayer / Pelapis bawah karpet Karpet 71,000.00
6 1 m² Pasang Lantai Parquet kayu Jati 509,900.00
A.4.4.47 1 m² Pasang Lantai kayu ( Gym floor ) 591,900.00
A.4.4.48 1 m² Pasang Dinding Porselin Ukuran (11 x 11) cm -
A.4.4.49 1 m² Pasang Dinding Porselin Ukuran (10 x 20) cm -
A.4.4.50 1 m² Pasang Dinding Porselin Ukuran (20 x 20) cm -
A.4.4.51 1 m² Pasang Dinding Keramik artistik Ukuran (10 x 20) cm -
A.4.4.52 1 m² Pasang Dinding Keramik artistik Ukuran (5 x 20) cm -
A.4.4.53 1 m² Pasang Dinding Keramik Ukuran (10 x 20) cm -
A.4.4.54 1 m² Pasang Dinding Keramik Ukuran (20 x 20) cm polished setara Roman Gol. A 206,500.00
A.4.4.54A 1 m² Pasang Dinding Keramik Ukuran (20 x 25) cm polished setara Roman Gol. A 198,300.00
A.4.4.54B 1 m² Pasang Dinding Keramik Ukuran (25 x 45) cm polished setara Roman Gol. A 189,100.00
A.4.4.54C 1 m² Pasang Dinding Keramik Ukuran (25 x 45 ) cm polished setara Roman Gol. B 195,500.00
7 1 m² Pasang Homogenius Tile Ukuran (30 x 60 ) cm setara Setara Indogress/ Niro Granit 303,900.00
8 1 m² Pasang Dinding Homogenous Ukuran (60 x 60 ) cm setara Niro Granit 550,500.00
A.4.4.54F 1 m² Pasang Dinding Homogenous Ukuran (60 x 60 ) cm setara Niro Granit 393,700.00
A.4.4.55 1 m' Pasang dinding Marmer Ukuran (slab ) setara Ujung Pandang 756,900.00
A.4.4.55A 1 m' Pasang dinding Marmer Ukuran (slab ) setara Citatah 756,900.00
A.4.4.55B 1 m' Pasang dinding Marmer Ukuran (slab ) setara Tulung Agung 734,800.00
A.4.4.55C 1 m' Pasang dinding Marmer Ukuran (60x60) cm setara Ujung Pandang 756,900.00
A.4.4.55D 1 m' Pasang dinding Marmer Ukuran (60x60) cm setara Citatah 674,100.00
A.4.4.55E 1 m' Pasang dinding Marmer Ukuran (60x60) cm setara Tulung Agung 734,800.00
A.4.4.55F 1 m' Pasang dinding Granit alam slab setara Cina 1,170,900.00
A.4.4.55G 1 m' Pasang dinding Granit alam slab setara India 1,145,200.00
A.4.4.55H 1 m' Pasang dinding Granit alam slab setara Tulung Agung 836,200.00
A.4.4.56 1 m2 Pasang dinding bata pelapis ukuran (3x7x24) cm 367,900.00

9 1 m2 Pasang dinding batu paras 355,300.00


NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
10 1 m2 Pasang dinding batu paras 407,100.00
11 1 m2 Pasang dinding batu Candi 418,000.00
A.4.4.3.59A 1 m2 Pasang lantai vinyl Anti Bacterial 408,300.00
A.4.4.3.59B 1 m2 Pasang lantai vinyl Heavy Duty 463,300.00
A.4.4.3.59C 1 m2 Pasang lantai vinyl HD + Backfoam #REF!
A.4.4.60 1 m2 Pasang wall paper, lebar 100cm 146,100.00
12 1 m2 Pasang Floor hardener natural ex. Sika Chapdur 68,200.00
13 1 m2 Pasang Floor hardener warna ex. Sika Chapdur 83,100.00
A.4.4.62 1 m' Pasang Plint dan instalasinya degan Cove Former dan Capping 168,600.00
A.4.4.63 1 m' Pasang plin plin kayu Kamper Samarinda ukuran ( t=2cm x l=10 ) 51,200.00
14 1 m² Pasang Lantai keramaik Ukuran (40 x 40) cm Polised Setara Roman Gol. A 265,000.00
15 1 m² Pasang Lantai keramaik Ukuran (40 x 40) cm Unpolised Setara Roman Gol. B 271,900.00
16 1 m² Pasang Lantai Homogenous Ukuran (40 x 40) cm Setara Niro granit 347,400.00
14 1 m² Pasang Homogenius Tile Ukuran (60 x 60) cm Polised Setara Indo Grees 295,400.00
15 1 m² Pasang Homogenius Tile Ukuran (60 x 60) cm Unpolised Setara Indo Gress Gol. B 362,700.00
16 1 m² Pasang Lantai Homogenous Ukuran (60 x 60) cm setara Nito Granit 358,000.00
17 1 M² Screeding tebal 3 cm 53,200.00
18 1 M² Water profing ex. Sika Top 107 Seal (untuk Toilet dan Area basah) 89,400.00
19 1 M² Water profing ex. Sika Rain Tile untuk atap dak beton 206,700.00
20 1 M² Pekerjaan meja beton wastafel finish. Batu granit alam 1,743,900.00
21 1 M² Pekerjaan meja beton pantry finish. Keramik 20 x 20 cm berikut dinding 1,050,100.00
6 1 m2 Lantai beton sikat ( Pearl stone ) 362,500.00
7 1 m2 Epoxy floor lining 2000 um ( 2mm ) 212,500.00
8 1 m2 Epoxy floor lining 3000 um ( 3mm ) 266,800.00
1 1 M² Timbal ( BA ) ketebalan 2mm 1,810,900.00
2 1 Unit Pasang Credenza TV + kaca dengan lapisan film motif kawung ( Ruang VVIP ) #REF!
A.4.4.3.62.A 1 m1 Hospital Plint Conwood 72,800.00
39.d 1 m' Pasang Hospital Plint Keramik Ukuran (10 x 40) cm 129,200.00

L HARGA SATUAN PEKERJAAN PENGECATAN


1 1 m² Mengikis/mengerok permukaan cat tembok lama 13,400.00
2 1 m² Mencuci bidang permukaan tembok yang pernah dicat 12,500.00
3 1 m² Mengerok karat cat lama permukaan baja dengan cara manual 13,100.00
4 1 m² Menyabun permukaan tembok lama 12,500.00
Mengerok karat atau cat lama permukaan baja dengan pancar pasir (sandblasting) dengan tingkat kebersihan
5 1 m² 348,500.00
Sa 2 1/2 %
6 1 m² Mendempul dan menggosok kayu 9,800.00
7 1 m² Pengecatan bidang kayu lama 39,300.00
8 1 m² Pengecatan bidang kayu baru ( 1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup 43,900.00
9 1 m² Pengecatan bidang kayu baru ( 1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup 44,000.00
10 1 m² Pelaburan bidang kayu dengan teak oil 25,500.00
11 1 m² Pelaburan bidang kayu dengan politur 35,900.00
12 1 m² Pelaburan bidang kayu dengan politur 35,900.00
12.a 1 m² Pengecatan melamik kayu baru ( 1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup 102,300.00

1 1 m² Pengecatan Duco bidang kayu baru/besi ( 1 lapis Dempul plastik), 1 lapis cat dasar, 3 lapis cat penutup 89,700.00

13 1 m² Pelaburan bidang kayu dengan vernis 37,100.00

2 1 m² Pengecatan tembok baru Interior ex. Catilax AEP (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) 26,930.00

Pengecatan tembok baru Exterior ex ICI Dulux Type exterior warna standar jenis Weathershield Pro ( 1 lapis
3 1 m² 47,900.00
cat dasar, 2 lapis cat penutup )
14.b 1 m² Cat epoxi gloos setara Propant ( 1 x cat dasar, 2 x cat penutup ) 59,900.00

4 1 m² Pengecatan plafon/dak beton baru ex. Catilax AEP (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) 25,400.00

5 1 m² Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup) 18,400.00
6 1 m² Melabur tembok dengan kalkarium 7,500.00
7 1 m² Melabur tembok dengan kapur sirih 13,800.00
8 1 m² Melabur tembok lama dengan kapur sirih (pemeliharaan) 6,500.00
5 1 m² Pengecatan permukaan baja dengan meni besi 26,100.00
6 1 m² Pengecatan permukaan baja dengan meni besi dan perancah 50,000.00
7 Pengecatan permukaan baja lapis seng (galpanis) secara manual sistem 4 lapis cat konvensional dengan tebal
1 m² 21,800.00
200 um
8 Pengecatan permukaan baja lapis seng (galpanis) secara manual sistem 4 lapis cat mutakhir dengan tebal 200
1 m² 28,800.00
um
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
9 Pengecatan permukaan baja lapis seng (galvanis) secara manual sistem 3 lapis cat konvensional dengan tebal
1 m² 193,600.00
200 um
10 Pengecatan permukaan baja lapis seng (galvani) secara semprot (airless spray) dengan sistem 1 lapis cat
1 m² 161,500.00
mutakhir dengan tebal 200 um
7 1 m² Pengecatan marka jalan/garis parkir 151,400.00
1m Lebar 5 cm 7,570.00
1m Lebar 10 cm 15,140.00
1m Lebar 15 cm 22,710.00
8 1 m² Finishing Lapisan HPL 127,800.00
9 1 m² Pengecatan tembok baru Interior jenis cat anti bakteri setara Propant ( 1 lapis cat dasar, 2 lapis cat penutup ) 40,900.00
6.M PENETAPAN INDEKS HARGA SATUAN PEKERJAAN BONGKARAN
1 1m2 Pekerjaan Bongkaran Dinding Tembok Plesteran 22,300.00
2 1m2 Pekerjaan Bongkaran Lantai Ubin / Keramik 4,200.00
3 1m2 Pekerjaan Bongkaran Atap Genteng / Sirap 2,600.00
4 1m2 Pekerjaan Bongkaran Atap Seng 5,000.00
5 1m2 Pekerjaan Bongkaran Rangka Atap Kayu 84,200.00
6 1m3 Pekerjaan Bongkaran Rangka Badan Kayu 638,000.00
7 1m3 Pekerjaan Bongkaran Beton Bertulang 561,000.00

M HARGA SATUAN PEKERJAAN SANITAIR


1 1 unit Closet duduk ex. TOTO Type CW 421 J / SW420JP 3,102,600.00
2 1 unit Closet duduk ex. CW 867 4,776,800.00
3 1 unit Closet duduk TOTO Type C 704 L/SW 784 JP ( Difable ) 4,974,800.00
4 1 unit Closet duduk ex. TOTO Type CW 661 JT1/SW 661 JP 3,226,900.00
5 1 unit Closet jongkok ex Toto type CE 9 / TV 150 NWV 12 3,950,300.00
2 1 unit Closet jongkok ex. Toto type CE 7 542,400.00
3 1 unit Urnal ex. TOTO tipe U 370 M 3,366,600.00
3 1 unit Urinal ex. Toto tipe U57M Muslim type urinal 2,713,200.00
4 1 unit Urinal partition ex. Toto tipe A100 1,052,200.00
5 1 unit Urinal partition ex. Toto tipe AW 115J 1,052,200.00
6 1 unit Wastafel ex. Toto tipe L 521 V1A 1,636,300.00
7 1 unit Wastafel setara TOTO type L 237 V1B komplit 2,078,500.00
8 1 unit Wastafel setara TOTO type LW 535 J SHEET 2,934,300.00
9 1 unit Wastafel Lengkap Standard setara Toto tipe L 521 VIA + TS 126AR + TX III L2YR 2,087,300.00
4 1 unit Wastafel Lengkap setara Toto type LW 241 CJ + TX101LB 3,055,300.00
5 1 unit Wastafel Lengkap setara Toto type LW 811 CJ + TX115LQBR 5,120,000.00
6 1 unit Wastafel setara TOTO type Tipe LW 825 J komplit 4,471,000.00
7 1 bh Bak mandi teraso volume air 0.30 m3 597,500.00
8 1 unit Wastafel setara TOTO type L 237 V1B komplit 2,078,500.00
9 1 bh Bak mandi fibreglass volume air 0.30 m3 495,200.00
10 1 bh Memasang bak mandi batu bata volume 0.3 m3 1,065,100.00
11 1 bh Memasang Bath tub ex. Toto 4,425,400.00
12 1 bh Membuat bak beton volume 1 m3 air 5,185,100.00
13 1 bh Memasang fibreglass volume 1 m3 air 2,288,700.00
14 1 unit Kitchen zink setara Royal 1 lobang stainless lengkap 809,300.00
15 1 unit Zink ex. TOTO tipe T30ARQ13N/ SK 508 laboratorium 4,365,000.00
16 1 unit Zink spoel hook ex. TOTO tipe SK33 6,893,900.00
5 1 bh Kran dinding ex. Toto tipe T 23B 13V7NB 293,400.00
6 1 bh Kran dinding ex. Toto tipe T 23BQ 13N 429,800.00
6 1 bh Kran Air Angsa setara Toto tipe TX 609 K 374,800.00
7 1 bh Kran dinding ex. Toto tipe T 26-13 ( kran taman ) 796,100.00
7 1 bh Kran dinding ex. Toto tipe T 30 ARQ 13N 564,000.00
8 1 bh Kran zink ex. Toto tipe TX 603 KM 602,500.00
8 1 bh Kran zink ex. Toto tipe TX 603 KCS 689,400.00
9 1 bh Kran dinding ex SUN-EI Type TY 20 JNR 245,000.00
6 1 unit Shower Spray setara Toto tipe THX 20 MCRB 396,800.00
10 1 unit Hand shower set setara Toto tipe THX 118SE Lengkap 723,500.00
11 1 unit Hand shower set set ex. Toto tipe THX 18ZB/ TX 402 XZ 297,800.00
12 1 unit Hand shower set ex. Toto tipe THX 19ZB/ TX 402 XZ 917,100.00
13 1 unit Hand shower set ex. Toto tipe TX 423 SZ/sink tap 656,400.00
14 1 unit Hand shower set ex. Toto tipe B250 105,300.00
15 1 unit Fixed head Shower set ex. Toto tipe TX 422 S `- Valve: TX452SF + TGB 9 MZN 1,331,800.00
16 1 unit Fixed head Shower set ex. Toto tipe TB 18 D (Luxury shower head) 2,870,700.00
17 1 unit Fixed shower head setara Toto tipe TX 465 SEN + TX 452 SE 1,889,500.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
18 1 unit Fixed head Shower ex. Toto tipe TX435SZ (3S Massage) 667,400.00
19 1 unit Fixed head Shower ex. Toto tipe TX439SZ (3S Massage) 667,400.00
20 1 unit Shower Hed ex. TOTO tipe TX422S + TX452SF + TGB 9 MZN 283,500.00
7 1 unit Floor drain Ex TOTO Type TX 1 BN 374,600.00
8 1 unit Tempat Tissue setara Toto tipe TX 720 ACRB 559,900.00
9 1 unit Paper Holder TOT 703 AC 264,000.00
10 1 unit Paper Holder TOTO TX11B 225,500.00
11 1 unit Soap holder ( Tempat sabun ) ex. Toto tipe S 6N colour 71,500.00
12 1 unit Soap holder ( Tempat sabun ) ex. Toto tipe S 11N colour 57,200.00
13 1 unit Soap holder ( Tempat sabun ) ex. Toto tipe S 156N colour 75,900.00
14 1 unit Soap holder ( Tempat sabun ) ex. Toto tipe S 160V1 colour 221,100.00
15 1 unit Tempat sabun setara Toto tipe S 156N colour 313,500.00
16 1 unit Soap Dispencer ex. Toto tipe TS 125 R 249,700.00
17 1 unit Soap Basket ex TOTO Type TX 2 BV1B 251,900.00
18 1 unit Tissue Dispencer ex. Toto tipe TX 8 403,100.00
19 1 unit Grab Bar tipe TX3A1 (Panjang 350 mm) ex. Toto 547,200.00
20 1 unit Grab Bar tipe TX3A2 (Panjang 500 mm) ex. Toto 660,500.00
21 1 unit Grab Bar tipe TX3A3 (Panjang 800 mm) ex. Toto 803,500.00
22 1 unit Double Robe Hook ex. TOTO Type TS 118 WS 186,400.00
23 1 unit Towel bar tipe TX 5 B (L=660 mm) ex. Toto 481,200.00
24 1 unit Towel bar tipe TX 5A2 (L=660 mm) ex. Toto 451,500.00
25 1 unit Towel bar tipe TX 5A1 (L=558 mm) ex. Toto 413,000.00
26 1 unit Towel Ring tipe TS 115 S ex. Toto 174,300.00
27 1 unit Double Robe Hook ex. TOTO Type TS 118 WS 186,400.00
9 1 m' Memasang Pipa PVC Tipe AW Ø 1/2" 16,800.00
10 1 m' Memasang Pipa PVC Tipe AW Ø 3/4" 19,900.00
11 1 m' Memasang Pipa PVC Tipe AW Ø 1" 25,700.00
12 1 m' Memasang Pipa PVC Tipe AW Ø 1 1/4" 33,800.00
13 1 m' Memasang Pipa PVC Tipe AW Ø 1 1/2" 42,800.00
14 1 m' Memasang Pipa PVC Tipe AW Ø 2" 44,300.00
15 1 m' Memasang Pipa PVC Tipe AW Ø 2 1/2" 75,100.00
16 1 m' Memasang Pipa PVC Tipe AW Ø 3" 98,300.00
17 1 m' Memasang Pipa PVC Tipe AW Ø 4" 146,000.00
18 1 m' Memasang Pipa PVC Tipe AW Ø 5" 222,700.00
19 1 m' Memasang Pipa PVC Tipe AW Ø 6" 309,200.00
20 1 m' Memasang Pipa PVC Tipe AW Ø 8" 531,800.00
21 1 m' Memasang Pipa PVC Tipe AW Ø 10" 724,100.00
N HARGA SATUAN PEKERJAAN KUNCI & KACA
1 1 set Pasang kunci tanam antik setara mutu menengah -
2 1 set Pasang kunci tanam biasa setara mutu menengah 217,344.00
3 1 set Pasang kunci pintu toilet bulat (Kenobset WC Griff 6656 - SS) 915,844.00
4 1 set Lockcase tipe Art 1492.55 + Double Cylinder Type Art 1400.60 setara WILKA 2,100,544.00
5 1 set Lockcase tipe Art 1492.55 + Double Cylinder Type Art 1400.60 setara WILKA 653,821.00
6 1 set Lockcase tipe Art 1450.55 + Double Cylinder Type Art 1400.60 setara WILKA 978,544.00
7 1 set Pasang kunci tanam Alumunium lockcase 2110 (Untuk pintu alumunium) 637,266.00
8 1 set Pasang kunci pintu toilet terpisah 2,646,589.00
9 1 psg Lever Handle ART 312 SS setara WILKA 364,254.00
10 1 bh Engsel pintu tipe 1901 (4"x3"x2,5) washer ( Berikut setel pintu ): 64,072.00
11 1 bh Hinges Gracia Art 2201 tipe BB 4"x3"x3mm SS setara WILKA 81,122.00
12 1 bh Engsel jendela tipe ES-S/S-3x3x2-2BB ( Berikut setel jendela ) 57,988.00
13 1 psg Friction stay jendela tipe 1909-SS-8" ( untuk boven jungkit ) 108,950.00
14 1 psg Friction stay top hung tipe 12"/2mm setara WILKA 126,550.00
15 1 psg Friction stay top hung tipe 20"/2mm setara WILKA 206,850.00
16 1 psg Friction stay top hung tipe 24"/2mm setara WILKA 275,050.00
17 1 psg Pasang spring knip -
18 1 psg Pasang hak angin tipe -
19 1 psg Door closer tipe TS 1M RA Dorma 403,557.00
20 1 Psg Fush Bolt Gracia tanam atas bawah 8+12" setara WILKA 330,726.00
21 1 Psg Pasang selot 1619 - NC ( untuk pintu rangka ) 212,663.00
22 1 bh Dust Proof Art 1150 setara WILKA 59,554.00
23 1 bh Pasang slot jendela rambucis 1607 59,554.00
24 1 bh Window lock Gracia Locking tipe Art 120 setara WILKA 122,254.00
25 1 Psg Pull Handle tipe ART GD 9330-350 setara WILKA 315,508.00
26 1 Psg Pull Handle tipe ART PH 260 - L 600 setara WILKA 1,151,508.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
27 1 Psg Pull Handle tipe ART PH 2296 G-600 setara WILKA 1,425,408.00
28 1 Psg Tubular Pull Handle Griff 2342-SS -C300-D32-H70 ( pintu kaca frame alumunium ) 497,008.00
29 1 Psg Fush Handle FP 4207 - F1/F2 147,208.00
30 1 Psg Door stop Gracia tipe Art 604/40mm SS. ( Floor ) 103,582.00
31 1 Psg Door stop Gracia tipe Art 713 ( Wall ) Silver 167,382.00
32 1 set Rel pintu Henderson J-3, Panjang 1.475mm untuk pintu lebar 750 - 900 mm 359,062.00
33 1 set Rel pintu Henderson J-4, Panjang 1.700mm untuk pintu lebar 950- 1050 mm 422,862.00
34 1 set Floor hinge BTS 60 Comolete Dorma 1,093,862.00
35 1 Set Top Fact fitting PT-20 + Bottom Fact fitting PT-10 + Corner Lock PS - 10 LCK Dorma 3,449,435.00
36 1 Set Over & side Top Fact fitting Pt-30 setara Drma 1,146,002.00
37 1 Set Top Pipot PT.24 Dorma 537,702.00
38 1 Set Bottom Patch Griff 9711 ( untuk pintu kaca engsel bawah ) 51,502.00
39 1 Set Corner Lock Griff 9721 ( untuk kunci bawah pintu kaca ) 51,502.00
40 1 bh Escutcheon tipe Art 901 DR setara WILKA 102,454.00
Shaft door tipe Art 542 + Anak kunci shaft door tipe Art 543 + Handle shaft door tipe Art RH 8-3 ( untuk
41 1 bh 345,202.00
pintu shapt )
1 1 m² Pasang kaca polos 3 mm 96,637.00
2 1 m² Pasang kaca polos 5 mm 138,982.00
3 1 m² Pasang kaca buram 5 mm -
4 1 m² Pasang kaca warna 5 mm 153,502.00
5 1 m² Pasang kaca cermin 5 mm 416,072.00
6 1 m² Pasang kaca polos 6 mm 187,382.00
7 1 m² Pasang kaca buram 6 mm 227,312.00
8 1 m² Pasang kaca warna 6 mm 227,312.00
9 1 m² Pasang kaca cermin 6 mm 468,102.00
10 1 m² Pasang kaca polos 8 mm 259,804.00
11 1 m² Pasang kaca warna 8 mm 361,444.00
12 1 m² Pasang kaca polos 10 mm 418,314.00
13 1 m² Pasang kaca warna 10 mm 556,254.00
14 1 m² Pasang kaca polos 12 mm 542,209.00
15 1 m² Pasang kaca warna 12 mm 599,079.00
16 1 m² Pasang kaca tempered 12 mm 613,599.00
17 1 m² Pasang kaca clear tempered t= 5 mm 249,092.00
18 1 m² Pasang kaca clear tempered t= 6 mm 327,742.00
19 1 m² Pasang kaca clear tempered t= 8 mm 425,007.00
20 1 m² Pasang kaca clear tempered t= 10 mm 519,954.00
21 1 m² Pasang kaca clear tempered t= 12 mm 613,599.00
22 1 m² Pasang kaca Reflective Stopsol On Line 12 mm 768,479.00
23 1 m² Pasang kaca clear tempered t= 15 mm 1,904,392.00
24 1 m² Pasang kaca clear tempered t= 19 mm 2,846,620.00
25 1 m² Pasang kaca patry 9 mm -
26 1 m² Upah bevel l=2cm 25,146.00
27 1 m² Upah bevel l=2,5cm 30,712.00
28 1 m² Upah bevel l=3cm 34,608.00
O PENETAPAN INDEKS HARGA SATUAN PEKERJAAN JALAN/PERKERASAN
1 1m Pemasangan Paving 6 Cm 162,800.00
2 1 m² Pemasangan Paving 8 Cm 155,800.00
3 1 m' Pekerjaan Kansteen K.03.1 ( 15.18.40 ) 140,500.00
4 1 m' Pekerjaan Kansteen 176,000.00
5 1 m2 Lantai grass block - T. 6 cm 211,200.00
6 1 m2 Lantai grass block - T. 8 cm 237,100.00
5 1 Hr Pekerjaan Menggilas 1,253,086.57
>>>>>>>>>>> Biaya menggilas macadam /m² = 1,989.03
>>>>>>>>>>> Biaya menggilas amparan / m² = 994.51
6 1 m² Pekerjaan Macadam T=20 cm 90,600.00
7 1 m² Pekerjaan Macadam T=25 cm 108,300.00
8 1 m² Pekerjaan Macadam T=30 cm 118,900.00
9 1 m² Pekerjaan Onderlag Telford 15/20 1 lapis 40,000.00
10 1 m² Pekerjaan Steenslag 5/7 1 Lapis 16,100.00
11 1 m² Pekerjaan Spleet 3/4 1 Lapis 19,800.00
12 1 m² Pekerjaan Amparan Batu Pecah 2/3 T=5 cm 33,000.00
13 1 m² Pekerjaan Lapisan Pengisi / Penutup 18,500.00
7 1 m² Pekerjaan Pengaspalan Manual 66,200.00
8 1 m³ Pekerjaan Base Course A t=15 cm 387,900.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
9 1 m³ Pekerjaan Sub base course kelas B t=20 cm 327,100.00
10 1 m³ Pekerjaan Sub base course kelas C t=30 cm 313,900.00
11 1 m² Pekerjaan ATB / Binder Coarse tebal 6 cm 87,300.00
12 1 m² Pekerjaan AC tebal 4 cm 157,700.00
13 1 m² Pekerjaan HRS tebal 3 cm 126,200.00
14 1 m² Pekerjaan Sand Sheet 2cm -
15 1 m² Pekerjaan Lapisan Penetrasi 85,800.00
16 1 m² Pekerjaan Teak Coating 13,200.00
17 1 m² Pekerjaan Prime Coat 15,100.00
10 1 m³ Pekerjaan Lime stone CBR 7 - 8% 100,100.00
11 1 m³ Sub base course kelas B t=15 cm batu crop ( CBR 60% ) 123,200.00
12 1 m³ Urug Sirtu Padat Untuk jalan ( CBR 75% ) t=40 cm 203,600.00
P PENETAPAN INDEKS HARGA SATUAN PEKERJAAN SALURAN
1 1m' Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm 162,400.00
2 1m' Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm 132,800.00
3 1m' Memasang pipa penyalur air limbah jenis pipa beton, diameter 1/2 20 cm 78,400.00
4 1m' Memasang pipa penyalur air limbah jenis pipa beton, diameter 1/2 30 cm 88,800.00
5 1m' Memasang pipa beton, diameter 15 cm - 20 cm 129,400.00
6 1m' Memasang pipa beton, diameter 30 cm SNI - Edisi -2007 182,000.00
7 1m' Memasang pipa beton, diameter 40 cm 225,200.00
8 1m' Memasang pipa beton, diameter 50 cm 291,800.00
9 1m' Memasang pipa beton, diameter 60 cm 371,200.00
10 1m' Memasang pipa beton, diameter 70 cm 374,200.00
11 1m' Memasang pipa beton, diameter 80 cm 701,800.00
12 1m' Memasang pipa beton, diameter 100 cm 779,600.00
13 1m' Memasang Pemasangan Precast U- 200 x 300 cm ( Beton Elemindo ) 266,900.00
14 1m' Memasang saluran U- 200 x 300 cm ( Cor ditempat ) 344,000.00
3 1m' Memasang Pemasangan Precast U- 300 x 400 cm ( Beton Elemindo ) 369,100.00
2 1m' Memasang saluran U- 300 x 400 cm ( Cor ditempat ) 460,200.00
4 1m' Memasang Pemasangan Precast U- 400 x 600 cm ( Beton Elemindo ) 549,800.00
5 1m' Memasang saluran U- 400 x 600 cm ( Cor ditempat ) 573,400.00
6 1m' Memasang Pemasangan Precast U- 500 x 700 cm ( Beton Elemindo ) 670,500.00
7 1m' Memasang saluran U- 500 x 700 cm ( Cor ditempat ) 671,200.00
3 1m' Memasang Pemasangan Precast U- 600 x 800 cm ( Beton Elemindo ) 858,400.00
4 1m' Memasang saluran U- 600 x 800 cm ( Cor ditempat ) 768,900.00
5 1m' Memasang Pemasangan Precast U- 700 x 900 cm ( Beton Elemindo ) 995,200.00
6 1m' Memasang saluran U- 700 x 900 cm ( Cor ditempat ) 918,800.00
7 1m' Memasang Pemasangan Precast U- 800 x 1000 cm ( Beton Elemindo ) 1,373,600.00
8 1m' Memasang saluran U- 800 x 1000 cm ( Cor ditempat ) 1,022,400.00
9 1m' Memasang Pemasangan Precast U- 1000 x 1000 cm ( Beton Elemindo ) 1,840,000.00
10 1m' Memasang saluran U-1000 x 1000 cm ( Cor ditempat ) 1,166,100.00
11 1m' Memasang Pemasangan Precast U- 1200 x 1200 cm ( Beton Elemindo ) 2,167,900.00
12 1m' Memasang saluran U-1200 x 1200 cm ( Cor ditempat ) 1,454,400.00
5 1m' Memasang tutup saluran untuk U-300 185,000.00
6 1m' Memasang tutup saluran untuk U-400 275,000.00
7 1m' Memasang tutup saluran untuk U-500 319,500.00
8 1m' Memasang tutup saluran untuk U-600 439,800.00
9 1m' Memasang tutup saluran untuk U-700 439,600.00
10 1m' Memasang tutup saluran untuk U-800 546,800.00
11 1m' Memasang tutup saluran untuk U-1000 711,800.00
12 1m' Memasang tutup saluran untuk U-1200 828,400.00
7 1bh Memasang bak kontrol pas. Bata ukuran (30x30) cm t 35 cm 251,500.00
8 1bh Memasang bak kontrol pas. Bata ukuran (50x50) cm T. 50 cm 482,800.00
9 1bh Memasang bak kontrol pas. Bata ukuran (60x60) cm T. 65 cm 728,100.00
10 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 50x50x100cm termasuk tutup 3,361,400.00
11 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 60x60x100cm termasuk tutup 3,994,200.00
12 1bh Pembuatan bak kontrol dari beton bertulang t= 100mm uk. 70x70x120cm termasuk tutup 5,630,700.00
13 1bh Pembuatan bak kontrol dari beton bertulang t= 120mm uk. 80x80x130cm termasuk tutup 6,226,900.00
14 1bh Pembuatan bak kontrol dari beton bertulang t= 120mm uk. 90x90x150cm termasuk tutup 8,698,400.00
15 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 100x100x200cm termasuk tutup 14,623,700.00
16 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 120x120x200cm termasuk tutup 16,427,300.00
17 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 140x140x200cm termasuk tutup 19,998,200.00
18 1bh Pembuatan bak kontrol dari beton bertulang t= 150mm uk. 200x200x300cm termasuk tutup 37,366,500.00
19 1bh Pembuatan sumur bidang resapan Ø100 kedalaman 2.50m 10,576,300.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3

6.R PENETAPAN INDEKS HARGA SATUAN PEKERJAAN TANAMAN


1 1 m³ Pek. Galian lubang tanam pada tanah biasa maks kedalaman 1 M' 60,600.00
2 1 m³ Urugan Tanah Humus / Timbunan 69,500.00
3 1 m³ Pek. Pemadatan dan pengolahan Tanah urugan 44,600.00
4 1 m³ Buangan sisa Pekerjaan keluar Lokasi Max 30 M 27,100.00
5 1 lbg Lubang Tanam dan pengolahan untuk Pohon 17,800.00
6 1 m² Penyiraman Tanaman 2,900.00
7 1 m² Pemupukan dan Pendangiran 8,600.00
a. Penanaman pohon peneduh
8 1 pohon Penanaman pohon bintaro t=3m 287,800.00
9 1 pohon Pohon Akasia mangium t=3m 147,000.00
10 1 pohon Dadap Merah t=2 - 4 m 386,800.00
11 1 pohon Pohon trembesi t = 3,00 m 308,700.00
12 1 pohon Angsana Tinggi 100 cm 14,600.00
13 1 pohon Pohon Cabefuya Caraiba `t=3m Jenis pohon peneduh 195,400.00
14 1 Pohon Pohon plamboyan t=300cm 335,100.00
15 1 Pohon Pohon bungur t=1,5 -3 m 59,000.00
16 1 Pohon Pohon kiara payung t=300cm 269,100.00
17 1 Pohon Pohon Kupu-kupu t=300cm 283,400.00
18 1 Pohon Pohon Mahoni t= 2,5 - 3 m 293,300.00
19 1 Pohon Pohon Angsana T=300cm 100,800.00
20 1 Pohon Pohon Ketapang laut t= 2 - 4 m 283,400.00
21 1 Pohon Pohon Ketapang kencana tinggi 200 283,400.00
22 1 Pohon Pohon Tanjung t= 2,5 - 3 m 299,900.00
23 1 Pohon Pohon Kiara payung T= 1 - 2 m 39,900.00
b. Penanaman pohon pagar
24 1 m'. Bambu Jepang (2 s/d 3m) 178,200.00
25 1 m'. Bambu Kuning (2 s/d 3m) 134,200.00
c. Penanaman pohon berbuah
26 1 pohon Pohon Nangka tinggi 100cm 27,600.00
27 1 Pohon Pohon Sukun t=1,5 - 2 m 52,300.00
d. Penanaman tanaman hias
28 1 pohon Bunga sepatu t = 30 - 50 cm 15,100.00
29 1 pohon Hanjuang merah t = 50 - 60 cm 18,600.00
30 1 pohon Kemuning t = 30 - 35 cm 14,000.00
31 1 pohon Anturium GC t = 40 - 50 cm 70,300.00
32 1 pohon Pohon kaca piring tinggi 40cm 39,500.00
33 1 pohon Palem botol t=100cm 73,800.00
34 1 pohon Palem ekor tupai Øbatang 10cm, tinggi 200cm 244,300.00
35 1 pohon Pohon semak mahkota duri 24,100.00
36 1 pohon Pohon pisang - pisangan 21,900.00
37 1 rumpun Pohon semak hias taiwan beuty 83,300.00
38 1 M' Teh-Tehan ( Duranta) 39,300.00
39 1 pohon Pohon Biola cantik t=1 - 2 m 247,200.00
40 1 pohon Pohon Jabon t= 70 cm - 80 cm 15,700.00
41 1 pohon Pohon Kasia kuning t=1 m 65,700.00
42 1 rumpun Aires polybeg 20 ( 1 Rumpun=1m2 ---25 pohon ) 50,300.00
43 1 rumpun Lantana polybeg t=30cm ( 1 polibag ---25 pohon ) 105,300.00
44 1 rumpun Soka Jepang/ground cover, tinggi 30cm ( 1 polibag=1m2 ---25 pohon ) 105,300.00
45 1 pohon Pohon hias bougenville tunggal t = 50 cm 43,200.00
46 1 pohon Pohon hias bougenville campur 3 warna t = 100 cm 97,100.00
47 1 pohon Pohon hias bougenville sambung t = 50 cm 55,300.00
48 1 pohon Perdu Oleander 31,100.00
49 1 Rumpun Azalea Ungu Polybag t=60cm ( 1 rumpun ---5 pohon ) 83,600.00
50 1 Rumpun Heliconia/perdu, tinggi 80cm ( 1 rumpun ---5 pohon ) 116,600.00
51 1 Rumpun Bayam Merah Polybag 30 77,600.00
52 1M2. Rumput Gajah 37,400.00
53 1M2. Rumput jepang 53,000.00
54 1M2. Rumput peking 40,300.00
55 1M2. Rumput bermuda ( terpasang belum PPN + keuntungan ) 100,500.00
56 1 pohon Pohon kamboja 227,200.00
57 1 pohon Pohon Yengliu 138,100.00
58 1 pohon Pohon T agave 71,000.00
NO. KOEF/SATUAN/URAIAN HARGA STUAN

1 2 3
59 1 pohon Pohon kemuning 273,600.00
60 1 pohon Pohon terong muda 237,300.00
61 1 pohon Pohon sikat botol 221,900.00
62 1 pohon Pohon cemara angin 273,600.00

Terusan Pekerjaan Sanitair


1 UNIT Bak mandi bayi 2,561,400.00

N HARGA SATUAN PEKERJAAN KUNCI & KACA


42.a 1 set Panic Device (Cross Bar) + Handle tipe Art 8378 /MMP4 SE HF setara WILKA 3,494,425.00
#VALUE! 1 set Panlc Device Vertical tipe Art 8376 E setara WILKA 4,668,950.00

19.A 1 unit Kran dinding panas dingin setara Toto tipe TX432SHV1BR 1,414,300.00
19.B 1 unit Eye Shower 20,598,300.00
A.4.4.1.22c 1 m2 1 m² Pasangan Dinding Glass Block Uk.(20x20)cm.Campuran Spesi 1PC : 3PP 550,100.00
A.4.2.1.31 1 m2 Pagar pengaman lapangan olah raga terbuka 600,300.00

Q SNI - PENETAPAN INDEKS HARGA SATUAN PEKERJAAN PONDASI


Bidang Sumber Daya Air
1 1M' Tiang pancang beton 40cm x 40cm 116,400.00
(Pengadaan berikut pemancangan)
2 1M' Tiang pancang beton 25cm x 25cm 64,400.00
(Pengadaan berikut pemancangan)

17 1bh Pembuatan Manhole dari plat baja chekered t=3mm + rangka siku uk. 80x80cm 1,275,800.00
potong pecah kepala tiang 30x30 91,300.00
3 1M' Tiang pancang beton 30cm x 30cm 421,300.00
(Pengadaan berikut pemancangan)
RENCANA ANGGARAN BIAYA

Nama Paket Pekerjaan : DED WISATA KULINER KP. SIDAMULYA DESA


LANGENSARI - KOTA BANJAR
Lokasi : Langensari - Kota Banjar

Tahun Anggaran : 2021

No Uraian Pekerjaan Volume Satuan Harga Satuan (Rp) Jumlah Harga (Rp) Total (Rp)

1 2 4 5 6 7 8

I PEKERJAAN PERSIAPAN

1 Survey Lapangan Untuk Peninjauan Kembali 1.00 Ls Rp 2,000,000 Rp 2,000,000


2 Pembersihan Lahan 4467.32 m2 Rp 12,868 Rp 57,485,474
3 Pembuatan Kantor Lapangan 20.00 m2 Rp 754,675 Rp 15,093,500
4 Pembuatan Gudang/los bahan & bedeng tenaga kerja 32.00 m2 Rp 704,823 Rp 22,554,336
5 Pembuatan Pagar Pengaman Proyek 286.70 m Rp 131,932 Rp 37,824,904
6 Pemasangan Bouwplank 455.00 m Rp 80,306 Rp 36,539,003
7 Penyediaan air kerja sementara ( Selama proyek berjalan ) 1.00 Ls Rp 2,535,500 Rp 2,535,500
8 Mobilisasi dan Demobilisasi Alat material (Asumsi mobil Colt Diesel) 1.00 Ls Rp 6,329,386 Rp 6,329,386

Rp 180,362,102 Rp 180,362,102
II PEKERJAAN TAMAN & LANDSCAPING

Area Lahan Parkir


1 Galian Tanah Untuk Perataan 67.33 m3 Rp 61,880 Rp 13,187,711
2 Urugan Pasir 13.47 m3 Rp 196,400 Rp 5,012,914
3 Beton Sitemix 1 : 2 : 3 40.40 m3 Rp 801,100 Rp 20,447,276
4 Asphalt Concrete t=5cm 13.47 m3 Rp 157,700 Rp 25,730,490

Jalur Pejalan Kaki


1 Galian Tanah Untuk Perataan 99.41 m3 Rp 61,880 Rp 6,151,646
2 Urugan Tanah 118.79 m3 Rp 29,400 Rp 3,492,538
3 Urugan Pasir 10.18 m3 Rp 196,400 Rp 1,999,809
4 Rolaag Pasangan Bata 2.92 m3 Rp 859,000 Rp 2,508,280
5 Pasangan Batu Kali 1pc:4ps 112.00 m3 Rp 744,800 Rp 83,421,138
6 Plester 192.20 m2 Rp 54,200 Rp 10,417,105
7 Paving Block Natural 6cm 339.41 m2 Rp 162,800 Rp 55,256,098
8 Beton Sitemix 1 : 2 : 3 10.50 m3 Rp 801,100 Rp 8,409,916
9 Kawat Ram Harmonika 249.36 m2 Rp 29,500 Rp 7,356,212

Area Playground
1 Galian Tanah Untuk Perataan 1.42 m3 Rp 61,880 Rp 88,055
2 Urugan Tanah 39.50 m3 Rp 29,400 Rp 1,161,300
3 Urugan Pasir Putih Bangka 31.60 m3 Rp 312,000 Rp 9,859,200
4 Urugan Tanah Humus / Timbunan 11.93 m3 Rp 69,500 Rp 828,788
5 Pengadaan 1 Set Playground Anak Outdoor 1.00 dihitung Rp 18,700,000 Rp 18,700,000

Area Tempat Duduk


1 Urugan Tanah Humus / Timbunan 64.79 m3 Rp 69,500 Rp 4,502,585
2 Pas. Pondasi Bata Rolaag 1 : 4 29.94 m3 Rp 859,000 Rp 25,721,209
3 Plesteran 1PC : 3PP Tebal 15 mm 180.94 m2 Rp 54,200 Rp 9,806,731
4 Urugan Tanah 6.78 m3 Rp 29,400 Rp 199,214
5 Urugan Pasir 0.58 m3 Rp 196,400 Rp 114,069
6 Paving Block Natural 6cm 19.36 m2 Rp 162,800 Rp 3,151,808
7 Rangka Atap Galvanis + Penutup Atap Membrane (By Vendor) 84.64 m2 Rp 750,000 Rp 63,480,000

Spot Selfie dan Jembatan


1 Galian Tanah 0.72 m3 Rp 61,880 Rp 44,670
2 Beton Sitemix 1 : 2 : 3 2.06 m3 Rp 801,100 Rp 1,652,269
3 Tiang Kayu Kelas II - 15/15 0.36 m3 Rp 6,780,975 Rp 2,470,445
4 Balok Kayu Kelas II - 18/12 1.99 m3 Rp 6,780,975 Rp 13,491,428
5 Papan Kayu Kelas II - 3/20 3.22 m3 Rp 6,780,975 Rp 21,806,598
6 Kawat Ram Harmonika 42.18 m2 Rp 29,500 Rp 1,244,310
7 Pemasangan Pipa Galvanis 2" 302.80 m Rp 229,800 Rp 69,583,440
8 Pengecatan Pipa Galvanis 47.54 Rp 28,800 Rp 1,369,140
9 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 33.00 titik Rp 274,740 Rp 9,066,415
10 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 1.00 titik Rp 288,600 Rp 288,600
11 Lampu Bohlam LED 12 Watt 33.00 unit Rp 196,350 Rp 6,479,550
12 Saklar Tunggal 1.00 unit Rp 42,735 Rp 42,735

Taman Bunga
1 Galian Tanah 6.96 m3 Rp 61,880 Rp 430,754
2 Urugan Tanah 80.50 m3 Rp 29,400 Rp 2,366,700
3 Urugan Tanah Humus / Timbunan 78.91 m3 Rp 69,500 Rp 5,483,932
4 Urugan Pasir 6.90 m3 Rp 196,400 Rp 1,355,160
5 Paving Block Natural 6cm 230.00 m2 Rp 162,800 Rp 37,444,000
6 Pas. Pondasi Bata Rolaag 1 : 4 22.29 m3 Rp 859,000 Rp 19,147,819
7 Plesteran 1PC : 3PP Tebal 15 mm 201.05 m2 Rp 54,200 Rp 10,897,154
8 Finishing Acian 201.05 m2 Rp 31,100 Rp 6,252,795

Pagar
1 Galian Tanah 126.15 m3 Rp 61,880 Rp 7,806,038
2 Urugan Tanah 17.20 m3 Rp 29,400 Rp 505,739
3 Pas. Batu Kali 86.01 m3 Rp 744,800 Rp 64,060,248
4 Pasangan Bata 454.16 m2 Rp 219,500 Rp 99,687,023
5 Sloof Beton Bertulang (200 kg Besi + Bekisting) 8.60 m3 Rp 4,057,300 Rp 34,896,837
6 Kolom Beton Bertulang (300 kg Besi + Bekisting) 3.60 m3 Rp 7,294,500 Rp 26,260,200
7 Plesteran 1PC : 3PP Tebal 15 mm 644.31 m2 Rp 54,200 Rp 34,921,602
8 Finishing Acian 644.31 m2 Rp 31,100 Rp 20,038,041
9 Pengecatan Dinding Pagar 644.31 m2 Rp 47,900 Rp 30,862,449
10 Pengecatan Rangka Besi Hollow 198.49 m2 Rp 28,800 Rp 5,716,385
11 Besi Hollow Galvanis 4x4 (tebal 1,6mm) 1240.54 m Rp 248,000 Rp 307,652,680

Pergola Jalan Lingkungan


1 Pemasangan Pipa Galvanis 2" 555.20 m Rp 229,800 Rp 127,584,960
2 Pengecatan Pipa Galvanis 88.56 m2 Rp 28,800 Rp 2,550,559
3 Kawat Ram Harmonika 141.16 m2 Rp 29,500 Rp 4,164,073

Gapura / Gerbang Masuk


1 Galian Tanah 1.17 m3 Rp 61,880 Rp 72,400
2 Pas. Batu Kali 1.17 m3 Rp 744,800 Rp 871,416
3 Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.30 m3 Rp 7,294,500 Rp 2,188,350
4 Pasangan Bata 31.00 m2 Rp 219,500 Rp 6,804,500
5 Plesteran 1PC : 3PP Tebal 15 mm 62.00 m2 Rp 54,200 Rp 3,360,400
6 Finishing Acian 62.00 m2 Rp 31,100 Rp 1,928,200
7 Pengecatan 62.00 m2 Rp 47,900 Rp 2,969,800

Paving Block
1 Urugan Tanah 54.06 m3 Rp 29,400 Rp 1,589,496
2 Urugan Pasir 4.63 m3 Rp 196,400 Rp 910,137
3 Paving Block Natural 6cm 154.47 m2 Rp 162,800 Rp 25,147,716

Kolam Pemancingan
1 Galian Tanah 45.74 m3 Rp 61,880 Rp 2,830,267
2 Urugan Tanah 162.37 m3 Rp 29,400 Rp 4,773,678
3 Urugan Pasir 7.49 m3 Rp 196,400 Rp 1,471,822
4 Urugan Tanah Humus / Timbunan 10.43 m3 Rp 69,500 Rp 724,538
5 Paving Block Natural 6cm 249.80 m2 Rp 162,800 Rp 40,667,440
6 Pas. Batu Kali 31.44 m3 Rp 744,800 Rp 23,416,512
7 Pas. Pondasi Bata Rolaag 1 : 4 0.86 m3 Rp 859,000 Rp 734,445
8 Sloof Beton Bertulang (200 kg Besi + Bekisting) 1.58 m3 Rp 4,057,300 Rp 6,426,763
9 Pasangan Bata 47.52 m2 Rp 219,500 Rp 10,430,640
10 Plesteran 1PC : 3PP Tebal 15 mm 199.20 m2 Rp 54,200 Rp 10,796,640
11 Finishing Acian 199.20 m2 Rp 31,100 Rp 6,195,120
12 Pengecatan 8.55 m2 Rp 47,900 Rp 409,545

Lampu Taman
1 Pengadaan dan Pemasangan Lampu Taman (By Vendor) 41.00 unit Rp 1,890,000 Rp 77,490,000
2 Lampu Bohlam LED 12 Watt 41.00 unit Rp 196,350 Rp 8,050,350

Rp 1,598,889,013 Rp 1,598,889,013
III PEKERJAAN GEDUNG PAMERAN DAN PERTEMUAN

Pekerjaan Tanah & Struktur


1 Pengukuran dan Pemasangan Bouwplank 78.00 m Rp 42,491.00 Rp 3,314,298
2 Galian Tanah 41.80 m3 Rp 61,880.00 Rp 2,586,754
3 Pas Batu Kosong 11.40 m3 Rp 378,900.00 Rp 4,319,744
4 Pas. Batu Kali Pondasi 25.34 m3 Rp 744,800.00 Rp 18,869,508
5 Urugan Tanah 118.80 m3 Rp 29,400.00 Rp 3,492,720
6 Pemadatan Tanah 198.00 m2 Rp 44,600.00 Rp 8,830,800
7 Urugan Pasir 5.94 m3 Rp 196,400.00 Rp 1,166,616
8 Sloof Beton Bertulang (200 kg Besi + Bekisting) 2.53 m3 Rp 4,057,300.00 Rp 10,279,170
9 Kolom Beton Bertulang (300 kg Besi + Bekisting) 4.43 m3 Rp 7,294,500.00 Rp 32,349,284
10 Balok Beton Bertulang (200 kg Besi + Bekisting) 7.60 m3 Rp 5,719,900.00 Rp 43,474,100
11 Plat Beton Bertulang (150 kg Besi + Bekisting) 8.58 m3 Rp 4,880,300.00 Rp 41,872,974

Pekerjaan Finishing
1 Pasangan Bata Ekspos 228.02 m2 Rp 219,500.00 Rp 50,049,293
2 Finishing Siaran Pas. Bata Ekspos 456.03 m2 Rp 24,200.00 Rp 11,035,926
3 Pengecatan 179.40 m2 Rp 47,900.00 Rp 8,593,260
4 Pas. Keramik Lantai 30x30 145.59 m2 Rp 262,300.00 Rp 38,188,257
5 Pas. Batu Sikat 37.50 m2 Rp 278,000.00 Rp 10,425,000
6 Pemasangan Rangka Kusen Aluminium 13.36 m2 Rp 141,000.00 Rp 1,883,760
7 Kusen dan Daun Pintu Megatek (By Vendor) 2.00 Unit Rp 2,500,000.00 Rp 5,000,000
8 Pemasangan Rangka Besi Hollow Anti karat 4x4 33.00 m2 Rp 500,000.00 Rp 16,500,000
9 Pemasangan Kaca Tempered 8mm 141.78 m2 Rp 336,000.00 Rp 47,638,080
10 Pemasangan Kaca Rayban 5mm 1.00 m2 Rp 113,000.00 Rp 113,000
11 Pemasangan Loster Keramik 688.00 bh Rp 30,000.00 Rp 20,640,000

Pekerjaan Langit-langit
1 Plafon Gypsum Tile Tb. 9 mm Berikut Rangka Hollow Galvanized 140.79 m2 Rp 103,800.00 Rp 14,614,002
2 Pengecatan Plafond 140.79 m2 Rp 25,400.00 Rp 3,576,066

Pekerjaan Atap
1 Pas. Rangka Atap Baja Ringan 99.85 m2 Rp 180,000.00 Rp 17,973,000
2 Penutup Atap Genteng Keramik 286.00 m2 Rp 157,000.00 Rp 44,902,000
3 Pas. Listplank Kayu 2/20 78.00 m Rp 31,700.00 Rp 2,472,600
4 Genteng Nok Keramik 64.00 m Rp 88,000.00 Rp 5,632,000

Pekerjaan Elektrikal
1 Pemasangan Panel 1.00 titik Rp 6,796,020.00 Rp 6,796,020
2 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 60.00 titik Rp 274,739.85 Rp 16,484,391
3 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 28.00 titik Rp 288,599.85 Rp 8,080,796
4 Lampu Bohlam LED 12 Watt 24.00 titik Rp 196,350.00 Rp 4,712,400
5 Slim Round Downlight LED Panel 15 Watt 36.00 titik Rp 49,800.00 Rp 1,792,800
6 Saklar Ganda 10.00 titik Rp 65,835.00 Rp 658,350
7 Saklar Tunggal 2.00 titik Rp 42,735.00 Rp 85,470
8 Stop Kontak 16.00 titik Rp 42,735.00 Rp 683,760

Rp 509,086,198 Rp 509,086,198
III PEKERJAAN KAMAR MANDI ( 2 Unit )
Pekerjaan Tanah & Struktur
1 Pengukuran dan Pemasangan Bouwplank 22.38 m Rp 42,491 Rp 950,736
2 Galian Tanah 11.19 m3 Rp 61,880 Rp 692,283
3 Pas Batu Kosong 3.02 m3 Rp 378,900 Rp 1,144,515
4 Pas. Batu Kali Pondasi 6.71 m3 Rp 744,800 Rp 4,999,470
5 Urugan Tanah 22.18 m3 Rp 29,400 Rp 652,156
6 Pemadatan Tanah 24.65 m2 Rp 44,600 Rp 1,099,251
7 Urugan Pasir 1.48 m3 Rp 196,400 Rp 290,439
8 Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.67 m3 Rp 4,057,300 Rp 2,723,463
9 Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.45 m3 Rp 7,294,500 Rp 3,249,700
10 Balok Beton Bertulang (200 kg Besi + Bekisting) 0.67 m3 Rp 5,719,900 Rp 3,839,483
11 Plat Beton Bertulang (150 kg Besi + Bekisting) 1.56 m3 Rp 4,880,300 Rp 7,636,449

Pekerjaan Finishing
1 Pasangan Bata 60.41 m2 Rp 219,500 Rp 13,260,544
2 Plesteran 1PC : 3PP Tebal 15 mm 120.83 m2 Rp 54,200 Rp 6,548,715
3 Finishing Acian 120.83 m2 Rp 31,100 Rp 3,757,658
4 Pengecatan 120.83 m2 Rp 47,900 Rp 5,787,518
5 Pas. Keramik Lantai 30x30 Anti Slip 24.65 m2 Rp 262,300 Rp 6,464,875
6 Pas. Keramik Dinding 20x30 18.05 m2 Rp 262,300 Rp 4,734,515
7 Kusen dan Pintu PVC 70x200 3.00 Unit Rp 321,000 Rp 963,000
8 Kusen dan Daun Pintu Megatek (By Vendor) 1.00 Unit Rp 2,500,000 Rp 2,500,000
9 Pemasangan Glassbox 20x20 18.00 bh Rp 30,000 Rp 540,000

Pekerjaan Langit-langit
1 Pasang Langit-langit Gypsum water prof 120 x 240 Tebal 9 mm 24.65 m2 Rp 88,200 Rp 2,173,854
2 Pengecatan Plafond 24.65 m2 Rp 25,400 Rp 626,031

Pekerjaan Atap
1 Plat Beton Bertulang (150 kg Besi + Bekisting) 2.46 m3 Rp 4,880,300 Rp 12,028,414
2 Water profing ex. Sika Rain Tile untuk atap dak beton 24.65 m2 Rp 157,000 Rp 3,869,559

Pekerjaan Elektrikal
1 Pemasangan Panel 1.00 titik Rp 6,796,020 Rp 6,796,020
2 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 7.00 titik Rp 274,740 Rp 1,923,179
3 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 2.00 titik Rp 288,600 Rp 577,200
4 Lampu Bohlam LED 12 Watt 2.00 titik Rp 196,350 Rp 392,700
5 Slim Round Downlight LED Panel 15 Watt 5.00 titik Rp 49,800 Rp 249,000
6 Saklar Ganda 1.00 titik Rp 65,835 Rp 65,835
7 Saklar Tunggal 1.00 titik Rp 42,735 Rp 42,735

Pekerjaan Plumbing & Sanitary


1 Memasang Pipa PVC Tipe AW Ø 1" 10.00 m Rp 25,700 Rp 257,000
2 Memasang Pipa PVC Tipe AW Ø 2" 3.00 m Rp 44,300 Rp 132,900
3 Memasang Pipa PVC Tipe AW Ø 4" 8.00 m Rp 146,000 Rp 1,168,000
4 Floor drain Ex TOTO Type TX 1 BN 3.00 bh Rp 374,600 Rp 1,123,800
5 Kran dinding ex. Toto tipe T 23B 13V7NB 3.00 unit Rp 293,400 Rp 880,200
6 Closet duduk ex. TOTO Type CW 421 J / SW420JP 3.00 unit Rp 3,102,600 Rp 9,307,800
7 Wastafel Lengkap setara Toto type LW 241 CJ + TX101LB 3.00 unit Rp 3,055,300 Rp 9,165,900

Rp 122,614,895 Rp 245,229,791
PEKERJAAN GAZEBO ( 5 Unit )

Pekerjaan Tanah & Struktur


1 Pengukuran dan Pemasangan Bouwplank 21.50 m Rp 42,491 Rp 913,557
2 Galian Tanah 1.06 m3 Rp 61,880 Rp 65,283
3 Beton Sitemix 1 : 2 : 3 0.13 m3 Rp 801,100 Rp 100,138
4 Pas. Batu Kali Pondasi 1.40 m3 Rp 744,800 Rp 1,042,720
5 Pas. Pondasi Bata Rolaag 1 : 4 0.43 m3 Rp 859,000 Rp 369,370
6 Urugan Tanah 17.25 m3 Rp 29,400 Rp 507,150
7 Pemadatan Tanah 28.75 m2 Rp 44,600 Rp 1,282,250
8 Urugan Pasir 0.57 m3 Rp 196,400 Rp 111,948

Pekerjaan Kayu
1 Tiang Kayu Kelas II - 15/15 0.26 m3 Rp 6,780,975 Rp 1,769,834
2 Balok Kayu Kelas II - 18/12 0.13 m3 Rp 6,780,975 Rp 878,814
3 Kaso Kayu Kelas II - 5/7 0.28 m3 Rp 6,780,975 Rp 1,931,425
4 Papan Kayu Kelas II - 3/20 0.34 m3 Rp 6,780,975 Rp 2,301,802
5 Pelaburan Bidang Kayu dengan Vernis 17.87 m2 Rp 42,107 Rp 752,457

Pekerjaan Atap
1 Rangka Atap Kayu Kelas II 0.68 m3 Rp 6,780,975 Rp 4,580,074
2 Penutup Atap Kayu Sirap 16.00 m2 Rp 294,500 Rp 4,712,000
3 Listplank Kayu kelas II - 2/20 0.01 m3 Rp 6,780,975 Rp 43,398

Pekerjaan Elektrikal
1 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 1.00 titik Rp 274,740 Rp 274,740
2 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 2.00 titik Rp 288,600 Rp 577,200
3 Lampu Bohlam LED 12 Watt 1.00 titik Rp 196,350 Rp 196,350
4 Saklar Tunggal 1.00 titik Rp 42,735 Rp 42,735
5 Stop Kontak 1.00 titik Rp 42,735 Rp 42,735

Pekerjaan Plumbing & Sanitary


1 Kran dinding ex. Toto tipe T 23B 13V7NB 1.00 unit Rp 293,400 Rp 293,400

Rp 22,789,380 Rp 113,946,898
PEKERJAAN AULA ( 1 Unit )

Pekerjaan Tanah dan Struktur


1 Pengukuran dan Pemasangan Bouwplank 31.25 m Rp 42,491 Rp 1,327,844
2 Galian Tanah 3.47 m3 Rp 61,880 Rp 214,637
3 Beton Sitemix 1 : 2 : 3 1.54 m3 Rp 801,100 Rp 1,230,490
4 Pas. Batu Kali Pondasi 3.19 m3 Rp 744,800 Rp 2,375,447
5 Urugan Tanah 47.00 m3 Rp 29,400 Rp 1,381,800
6 Pemadatan Tanah 67.50 m2 Rp 44,600 Rp 3,010,500
7 Urugan Pasir 0.57 m3 Rp 196,400 Rp 111,948

Pekerjaan Kayu
1 Tiang Kayu Kelas II - 15/15 0.38 m3 Rp 6,780,975 Rp 2,608,980
2 Balok Kayu Kelas II - 18/12 0.50 m3 Rp 6,780,975 Rp 3,388,318
3 Kaso Kayu Kelas II - 5/7 1.32 m3 Rp 6,780,975 Rp 8,928,510
4 Pelaburan Bidang Kayu dengan Vernis 17.87 m2 Rp 42,107 Rp 752,457

Pekerjaan Atap
1 Penutup Atap Kayu Sirap 56.00 m2 Rp 294,500 Rp 16,492,000

Pekerjaan Elektrikal
1 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 8.00 titik Rp 274,740 Rp 2,197,919
2 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 2.00 titik Rp 288,600 Rp 577,200
3 Lampu Bohlam LED 12 Watt 8.00 titik Rp 196,350 Rp 1,570,800
4 Saklar Ganda 1.00 titik Rp 65,835 Rp 65,835
5 Stop Kontak 1.00 titik Rp 42,735 Rp 42,735

Rp 46,277,417 Rp 46,277,417
PEKERJAAN TRIBUN ( 1 Unit )

Pekerjaan Tanah dan Struktur


1 Pengukuran dan Pemasangan Bouwplank 29.00 m Rp 42,491 Rp 1,232,239
2 Galian Tanah 4.57 m3 Rp 61,880 Rp 282,637
3 Beton Tumbuk / Lantai Kerja ( 1:3:5 ) 1.16 m3 Rp 808,900 Rp 937,593
4 Pas. Batu Kali Pondasi 16.61 m3 Rp 744,800 Rp 12,369,266
5 Urugan Tanah 41.88 m3 Rp 29,400 Rp 1,231,329
6 Pemadatan Tanah 28.98 m2 Rp 44,600 Rp 1,292,392
7 Urugan Pasir 2.03 m3 Rp 196,400 Rp 397,710
8 Finishing Acian 28.98 m2 Rp 31,100 Rp 901,197

Pekerjaan Atap
1 Rangka Atap Galvanis + Penutup Atap Membrane (By Vendor) 50.00 m2 Rp 750,000 Rp 37,500,000
2 Handrailling Tangga pipa Galvanis 2" 35.20 m Rp 152,000 Rp 5,350,400
3 Kawat Ram Harmonika 8.80 m2 Rp 29,500 Rp 259,600

Rp 61,754,363 Rp 61,754,363
PEKERJAAN COFFEE SHOP ( 1 Unit )

Pekerjaan Tanah & Struktur


1 Pengukuran dan Pemasangan Bouwplank 48.75 m Rp 42,491 Rp 2,071,436
2 Galian Tanah 28.36 m3 Rp 61,880 Rp 1,754,855
3 Pas. Pondasi Bata Rolaag 1 : 4 10.36 m3 Rp 859,000 Rp 8,895,804
4 Pas Batu Kosong 3.70 m3 Rp 378,900 Rp 1,401,551
5 Pas. Batu Kali Pondasi 8.22 m3 Rp 744,800 Rp 6,122,256
6 Urugan Tanah 39.19 m3 Rp 29,400 Rp 1,152,113
7 Pemadatan Tanah 74.25 m2 Rp 44,600 Rp 3,311,550
8 Urugan Pasir 1.16 m3 Rp 196,400 Rp 226,842
9 Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.82 m3 Rp 4,057,300 Rp 3,335,101
10 Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.95 m3 Rp 7,294,500 Rp 6,942,540
11 Balok Beton Bertulang (200 kg Besi + Bekisting) 1.30 m3 Rp 5,719,900 Rp 7,438,730
12 Plat Beton Bertulang (150 kg Besi + Bekisting) 3.85 m3 Rp 4,880,300 Rp 18,789,155

Pekerjaan Finishing
1 Pasangan Bata 90.42 m2 Rp 219,500 Rp 19,847,190
2 Plesteran 1PC : 3PP Tebal 15 mm 180.84 m2 Rp 54,200 Rp 9,801,528
3 Finishing Acian 180.84 m2 Rp 31,100 Rp 5,624,124
4 Pengecatan 180.84 m2 Rp 47,900 Rp 8,662,236
5 Water profing ex. Sika Rain Tile untuk atap dak beton 38.50 m2 Rp 157,000 Rp 6,044,500
6 Pas. Keramik Lantai 30x30 38.50 m2 Rp 262,300 Rp 10,098,550
7 Pemasangan Rangka Kusen Aluminium 35.55 m Rp 141,000 Rp 5,012,550
8 Kusen dan Daun Pintu Megatek (By Vendor) 2.00 Unit Rp 2,500,000 Rp 5,000,000
9 Pemasangan Kaca Tempered 8mm 24.54 m2 Rp 336,000 Rp 8,243,760

Pekerjaan Langit-langit
1 Plafon Gypsum Tile Tb. 9 mm Berikut Rangka Hollow Galvanized 38.50 m2 Rp 103,800 Rp 3,996,300
2 Pengecatan Plafond 38.50 m2 Rp 25,400 Rp 977,900

Pekerjaan Elektrikal
1 Pemasangan Panel 1.00 titik Rp 6,796,020 Rp 6,796,020
2 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 14.00 titik Rp 274,740 Rp 3,846,358
3 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 13.00 titik Rp 288,600 Rp 3,751,798
4 Lampu Bohlam LED 12 Watt 4.00 titik Rp 196,350 Rp 785,400
5 Slim Round Downlight LED Panel 15 Watt 10.00 titik Rp 49,800 Rp 498,000
6 Saklar Ganda 6.00 titik Rp 65,835 Rp 395,010
7 Stop Kontak 7.00 titik Rp 42,735 Rp 299,145

Pekerjaan Plumbing dan Sanitary


1 Memasang Pipa PVC Tipe AW Ø 1" 9.00 m Rp 25,700 Rp 231,300
2 Memasang Pipa PVC Tipe AW Ø 2" 4.25 m Rp 44,300 Rp 188,275
3 Wastafel Lengkap setara Toto type LW 241 CJ + TX101LB 2.00 unit Rp 3,055,300 Rp 6,110,600
Rp 167,652,477 Rp 167,652,477

PEKERJAAN TERAPI IKAN ( 1 Unit )

Pekerjaan Tanah & Struktur


1 Pengukuran dan Pemasangan Bouwplank 16.00 m Rp 42,491 Rp 679,856
3 Beton Sitemix 1 : 2 : 3 0.43 m3 Rp 801,100 Rp 346,075
4 Pas. Pondasi Bata Rolaag 1 : 4 3.92 m3 Rp 859,000 Rp 3,367,280
5 Urugan Tanah 4.80 m3 Rp 29,400 Rp 141,028
6 Pemadatan Tanah 16.00 m2 Rp 44,600 Rp 713,600
7 Urugan Pasir 0.20 m3 Rp 196,400 Rp 39,830

Pekerjaan Kayu
1 Tiang Kayu Kelas II - 15/15 0.21 m3 Rp 6,780,975 Rp 1,403,662
2 Balok Kayu Kelas II - 18/12 0.18 m3 Rp 6,780,975 Rp 1,188,027
3 Kaso Kayu Kelas II - 5/7 0.18 m3 Rp 6,780,975 Rp 1,219,694
4 Papan Kayu Kelas II - 3/20 0.44 m3 Rp 6,780,975 Rp 3,016,178
5 Pelaburan Bidang Kayu dengan Vernis 9.70 m2 Rp 42,107 Rp 408,440

Pekerjaan Atap
1 Penutup Atap Kayu Sirap 23.50 m2 Rp 294,500 Rp 6,920,750
2 Nok Atap Kayu Sirap 13.00 m3 Rp 327,000 Rp 4,251,000

Pekerjaan Elektrikal
1 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 5.00 titik Rp 274,740 Rp 1,373,699
2 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 2.00 titik Rp 288,600 Rp 577,200
3 Lampu Bohlam LED 12 Watt 5.00 titik Rp 196,350 Rp 981,750
4 Saklar Tunggal 1.00 titik Rp 42,735 Rp 42,735
5 Stop Kontak 1.00 titik Rp 42,735 Rp 42,735

Pekerjaan Plumbing dan Sanitary


1 Memasang Pipa PVC Tipe AW Ø 1" 4.75 m Rp 25,700 Rp 122,075
2 Memasang Pipa PVC Tipe AW Ø 2" 9.50 m Rp 44,300 Rp 420,850
3 Kran dinding ex. Toto tipe T 23B 13V7NB 1.00 unit Rp 293,400 Rp 293,400

Rp 27,549,864 Rp 27,549,864

PEKERJAAN PEMANCINGAN ( 2 Unit )

Pekerjaan Tanah & Struktur


1 Pengukuran dan Pemasangan Bouwplank 34.00 m Rp 42,491 Rp 1,444,694
3 Beton Sitemix 1 : 2 : 3 0.30 m3 Rp 801,100 Rp 240,330
5 Urugan Tanah 23.81 m3 Rp 29,400 Rp 700,088

Pekerjaan Kayu
1 Tiang Kayu Kelas II - 15/15 0.30 m3 Rp 6,780,975 Rp 2,031,038
2 Balok Kayu Kelas II - 18/12 0.55 m3 Rp 6,780,975 Rp 3,749,608
3 Kaso Kayu Kelas II - 5/7 0.35 m3 Rp 6,780,975 Rp 2,345,539
4 Papan Kayu Kelas II - 3/20 0.90 m3 Rp 6,780,975 Rp 6,102,878
5 Pelaburan Bidang Kayu dengan Vernis 27.80 m2 Rp 42,107 Rp 1,170,582

Pekerjaan Atap
1 Penutup Atap Kayu Sirap 30.00 m2 Rp 294,500 Rp 8,835,000
2 Nok Atap Kayu Sirap 15.00 m3 Rp 327,000 Rp 4,905,000

Pekerjaan Elektrikal
1 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 5.00 titik Rp 274,740 Rp 1,373,699
2 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 9.00 titik Rp 288,600 Rp 2,597,399
3 Lampu Bohlam LED 12 Watt 5.00 titik Rp 196,350 Rp 981,750
4 Saklar Tunggal 5.00 titik Rp 42,735 Rp 213,675
5 Stop Kontak 4.00 titik Rp 42,735 Rp 170,940

Pekerjaan Plumbing dan Sanitary


1 Memasang Pipa PVC Tipe AW Ø 1" 15.00 m Rp 25,700 Rp 385,500
3 Kran dinding ex. Toto tipe T 23B 13V7NB 3.00 unit Rp 293,400 Rp 880,200

Rp 38,127,918 Rp 76,255,837

PEKERJAAN TOKO ( 1 Unit )

Pekerjaan Tanah & Struktur


1 Pengukuran dan Pemasangan Bouwplank 16.60 m Rp 42,491 Rp 705,351
3 Beton Sitemix 1 : 2 : 3 0.20 m3 Rp 801,100 Rp 160,220
5 Urugan Tanah 11.60 m3 Rp 29,400 Rp 341,114

Pekerjaan Finishing & Kusen


1 Pasangan Partisi GRC 2 Muka 50.00 m2 Rp 293,500 Rp 14,673,533
2 Pengecatan Partisi GRC 50.00 m2 Rp 47,900 Rp 2,394,761
3 Pemasangan Rangka Kusen Aluminium 36.57 m Rp 141,000 Rp 5,156,680
4 Pemasangan Kaca Rayban 5mm 2.43 m2 Rp 113,000 Rp 274,816
5 Pemasangan Engsel Pintu 2.00 unit Rp 64,072 Rp 128,144
6 Pemasangan Engsel Jendela 4.00 unit Rp 57,988 Rp 231,952
7 Pemasangan Handle Pintu 2.00 unit Rp 364,254 Rp 728,508
8 Pemasangan Kunci Tanam Pintu 1.00 unit Rp 217,344 Rp 217,344

Pekerjaan Kayu
1 Tiang Kayu Kelas II - 15/15 0.21 m3 Rp 6,780,975 Rp 1,432,142
2 Balok Kayu Kelas II - 18/12 0.16 m3 Rp 6,780,975 Rp 1,090,381
3 Kaso Kayu Kelas II - 5/7 0.12 m3 Rp 6,780,975 Rp 804,054
4 Papan Kayu Kelas II - 3/20 0.51 m3 Rp 6,780,975 Rp 3,471,012
5 Pelaburan Bidang Kayu dengan Vernis 12.70 m2 Rp 42,107 Rp 534,762

Pekerjaan Atap
1 Penutup Atap Kayu Sirap 17.06 m2 Rp 294,500 Rp 5,024,906
2 Listplank Kayu kelas II - 2/20 0.50 m3 Rp 6,780,975 Rp 3,376,926

Pekerjaan Elektrikal
2 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 2.00 titik Rp 274,740 Rp 549,480
3 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 2.00 titik Rp 288,600 Rp 577,200
4 Lampu Bohlam LED 12 Watt 1.00 titik Rp 196,350 Rp 196,350
5 Saklar Ganda 1.00 titik Rp 42,735 Rp 42,735

Pekerjaan Plumbing dan Sanitary


1 Memasang Pipa PVC Tipe AW Ø 1" 4.55 m Rp 25,700 Rp 116,935
3 Kran dinding ex. Toto tipe T 23B 13V7NB 2.00 unit Rp 293,400 Rp 586,800

Rp 42,816,103 Rp 42,816,103

III PEKERJAAN MUSHOLA (1 UNIT)

Pekerjaan Tanah & Struktur


1 Pengukuran dan Pemasangan Bouwplank 26.55 m Rp 42,491.00 Rp 1,128,136
2 Galian Tanah 10.76 m3 Rp 61,880.00 Rp 666,076
3 Pas Batu Kosong 2.48 m3 Rp 378,900.00 Rp 941,188
4 Pas. Batu Kali Pondasi 9.38 m3 Rp 744,800.00 Rp 6,989,203
5 Urugan Tanah 22.84 m3 Rp 29,400.00 Rp 671,423
6 Pemadatan Tanah 42.33 m2 Rp 44,600.00 Rp 1,888,085
7 Urugan Pasir 0.83 m3 Rp 196,400.00 Rp 162,619
8 Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.55 m3 Rp 4,057,300.00 Rp 2,239,630
9 Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.58 m3 Rp 7,294,500.00 Rp 4,250,870
10 Balok Beton Bertulang (200 kg Besi + Bekisting) 0.55 m3 Rp 5,719,900.00 Rp 3,157,385
11 Plat Beton Bertulang (150 kg Besi + Bekisting) 6.52 m3 Rp 4,880,300.00 Rp 31,807,355

Pekerjaan Finishing dan Kusen


1 Pasangan Bata 61.74 m2 Rp 219,500.00 Rp 13,551,930
2 Plesteran 1PC : 3PP Tebal 15 mm 123.48 m2 Rp 54,200.00 Rp 6,692,616
3 Finishing Acian 123.48 m2 Rp 31,100.00 Rp 3,840,228
4 Pengecatan 137.13 m2 Rp 47,900.00 Rp 6,568,527
5 Water profing ex. Sika Rain Tile untuk atap dak beton 36.45 m2 Rp 157,000.00 Rp 5,722,650
6 Pas. Keramik Lantai 30x30 36.45 m2 Rp 262,300.00 Rp 9,560,835
7 Pemasangan Rangka Kusen Aluminium 48.18 m2 Rp 141,000.00 Rp 6,792,675
8 Pemasangan Engsel Pintu 4.00 unit Rp 64,072.00 Rp 256,288
9 Pemasangan Engsel Jendela 4.00 unit Rp 57,988.00 Rp 231,952
10 Pemasangan Handle Pintu 2.00 unit Rp 364,254.00 Rp 728,508
11 Pemasangan Kunci Tanam Pintu 1.00 unit Rp 217,344.00 Rp 217,344
12 Pemasangan Kaca Tempered 8mm 9.00 m2 Rp 336,000.00 Rp 3,024,000
13 Pemasangan Kaca Rayban 5mm 1.13 m2 Rp 113,000.00 Rp 127,125
14 Pemasangan Loster Keramik 40.00 bh Rp 30,000.00 Rp 1,200,000
15 Pemasangan Glassbox 9.00 bh Rp 35,000.00 Rp 315,000

Pekerjaan Langit-langit
1 Plafon Gypsum Tile Tb. 9 mm Berikut Rangka Hollow Galvanized 36.45 m2 Rp 103,800.00 Rp 3,783,510
2 Pengecatan Plafond 36.45 m2 Rp 25,400.00 Rp 925,830

Pekerjaan Elektrikal
1 Pemasangan Panel 1.00 titik Rp 6,796,020.00 Rp 6,796,020
2 - Instalasi penerangan, NYM 3 x 2,5 mm2 dalam conduit PVC 11.00 titik Rp 274,739.85 Rp 3,022,138
3 - Instalasi stop kontak, NYM 3 x 2,5 mm2 dalam conduit PVC 6.00 titik Rp 288,599.85 Rp 1,731,599
4 Lampu Bohlam LED 12 Watt 5.00 titik Rp 196,350.00 Rp 981,750
5 Slim Round Downlight LED Panel 15 Watt 6.00 titik Rp 49,800.00 Rp 298,800
6 Saklar Tunggal 2.00 titik Rp 65,835.00 Rp 131,670
7 Stop Kontak 4.00 titik Rp 42,735.00 Rp 170,940

Pekerjaan Plumbing dan Sanitary


1 Memasang Pipa PVC Tipe AW Ø 1" 7.00 m Rp 25,700 Rp 179,900
2 Memasang Pipa PVC Tipe AW Ø 2" 10.00 m Rp 44,300 Rp 443,000
3 Kran dinding ex. Toto tipe T 23B 13V7NB 4.00 unit Rp 293,400 Rp 1,173,600

Rp 132,370,405 Rp 132,370,405
Jumlah Total Rp 3,202,190,468
PPn 10% Rp 320,219,047
Tiga Miliar Lima Ratus Dua Puluh Dua Juta Empat Ratus Sembilan Ribu Rupiah
Total Rp 3,522,409,515
Dibulatkan Rp 3,522,409,000

Banjar, Oktober 2021


Diperiksa : Dibuat Oleh :
Kepala Seksi Konsultan Perencana
Pengelolaan Perumahan Rakyat CV. DNA CONSULTANT
Dan Kawasan Permukiman
Kabupaten Ciamis

DODY KUSWANDI,S.T. DICKY NURMAYADI, S.T.,M.T


NIP. 19781008 200604 1 006 Direktur

Mengetahui : Menyetujui :
Kepala Dinas Kepala Bidang
Perumahan Rakyat, Kawasan Permukiman Perumahan Rakyat dan Kawasan Permukiman
Dan Lingkungan Hidup Kabupaten Ciamis
Kabupaten Ciamis

Dr. H. TAUFIK GUMELAR, ST,. MM ARIS TAUFIK ABADI, S.T.


NIP. 19700408 200212 1 006 NIP. 19800420 200501 1 007
BILL OF QUANTITY
REKAPITULASI
DED WISATA KULINER KP. SIDAMULYA DESA
PEKERJAAN :
LANGENSARI - KOTA BANJAR
LOKASI : Langensari - Kota Banjar
TAHUN ANGGARAN : 2021

NO URAIAN PEKERJAAN JUMLAH HARGA

A.
1 PEKERJAAN PERSIAPAN 180,362,102.46
2 PEKERJAAN TAMAN & LANDSCAPING 1,598,889,013.28
3 PEKERJAAN GEDUNG PAMERAN DAN PERTEMUAN 509,086,198.02
4 PEKERJAAN KAMAR MANDI ( 2 Unit ) 245,229,790.64
5 PEKERJAAN GAZEBO ( 5 Unit ) 113,946,898.00
6 PEKERJAAN AULA ( 1 Unit ) 46,277,417.38
7 PEKERJAAN TRIBUN ( 1 Unit ) 61,754,363.32
8 PEKERJAAN COFFEE SHOP ( 1 Unit ) 167,652,476.65
9 PEKERJAAN TERAPI IKAN ( 1 Unit ) 27,549,863.97
10 PEKERJAAN PEMANCINGAN ( 2 Unit ) 76,255,836.54
11 PEKERJAAN TOKO ( 1 Unit ) 42,816,102.96
12 PEKERJAAN MUSHOLA (1 UNIT) 132,370,405.10
JUMLAH : 3,202,190,468.30
PPN 10 % : 320,219,046.83
JUMLAH TOTAL : 3,522,409,515.13
DIBULATKAN : 3,522,409,000.00
Terbilang : "Tiga Miliar Lima Ratus Dua Puluh Dua Juta Empat Ratus Sembilan Ribu Rupiah "

Banjar, Oktober 2021


CV. DNA CONSULTANT
DICKY NURMAYADI, S.T.,M.T
Direktur

Anda mungkin juga menyukai