REKAPITULASI RINCIAN ANGGARAN & BIAYA (RAB)

PEKERJAAN : PEMBANGUNAN PAGAR KELILING GEDUNG LECTURER & WORK SHOP


LOKASI : POLITEKNIK ENERGI DAN MINERAL (PEM) AKAMIGAS
NGLAJO - CEPU
PEMILIK : PPT. MIGAS CEPU
TA : 2020

JUMLAH HARGA PPN 10% JUMLAH SEMUA


NO. URAIAN PEKERJAAN
(Rp) (Rp) (Rp)

A. PEKERJAAN PERSIAPAN - #NAME? 8,849,306.38

B. PAGAR SAMPING KIRI (PANJANG = 89,90M)


I Pekerjaan Tanah & Urugan - #NAME? 6,160,227.22
II Pekerjaan Beton - #NAME? 31,403,793.21
III Pekerjaan Pasangan - #NAME? 92,123,233.15

Jumlah A+B+C - #NAME? 138,536,559.97


Dibulatkan 138,536,000.00

TERBILANG : SERATUS TUJUH PULUH DUA JUTA EMPAT RATUS SEMBILAN PULUH DELAPAN RIBU RUPIAH

Blora, …… ……………… 2020


Konsultan Perencana :
CV. DUTA CAHAYA DESIGN

……………………
Direktur
DAFTAR HARGA SATUAN PEKERJAAN
TAHUN 2020
( PERMEN PU NO. 11/PRT/M/2013 & SE MENTERI PU NO. 02/SE/M/2013 )

KODE HARGA SATUAN


No. JENIS PEKERJAAN
ANALIS PEKERJAAN

A A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


1 A.2.2.1.4a Pengukuran dan Pemasangan Bouwplank m' 63,952.24

B A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 69,025.00
2 A.2.3.1.9 Pengurugan Kembali m3 16,683.33
Pengurugan Kembali di hitung dari 1/3 kali koefisien Pekerjaan galian
3 A.2.3.1.11 Urugan Pasir m3 227,458.00
4 A.2.3.1.11a Urugan Tanah Biasa (tersedia) m3 27,610.00

C A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 846,044.43
2 A.3.2.1.9 Pemasangan Batu Kosong/Anstamping m3 486,788.28

D A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.17.a Pembesian dg Besi Polos atau Besi Ulir Kg 14,997.40
2 A.4.1.1.20.a Memasang Bekisting untuk Pondasi 3x pakai m2 106,051.00
3 A.4.1.1.21.a Memasang Bekisting untuk Sloof 3x pakai m2 109,351.00
4 A.4.1.1.22.a Memasang Bekisting untuk Kolom 3x pakai m2 197,793.20
5 A.4.1.1.23.a Memasang Bekisting untuk Balok 3x pakai m2 204,993.14
6 A.4.1.1.4 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 m3 919,281.40
7 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 m3 1,085,547.99
8 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61 m3 1,118,463.47

E A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


1 A.4.4.1.11 Pas. Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 103,184.07
2 A.4.4.1.21 Pas. Dinding Bata Ringan / Hebel m2 160,435.00

F A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 58,498.77
2 A.4.4.2.20.a Pemasangan Skoning Sudutan 1 Pc : 2Pp, (0,1 x indeks skoning l=10cm) m' 5,574.57
3 A.4.4.2.20.b Pembuatan Tali Air (2 x indeks skoningan) m' 11,149.14
4 A.4.4.2.27 Pemasangan Acian m2 34,636.25

G A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


1 A.4.4.3.58 Pemasangan Dinding Batu Paros / Batu Tempel Hitam m2 276,350.80
2 A.4.4.3.34.c Pemasangan Lantai/Dinding granit cina Sandimas Cream 60x60cm m2 274,290.50

H A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


1 A.4.7.1.10a Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat Penutup) - Dinding Luar m2 40,458.00

J. DIHITUNG HARGA SATUAN PEKERJAAN BERDASARKAN PERHITUNGAN


1 ARS 01 PASANG PAGAR KISI2 BESI HOLLOW m2 890,016.88
2 ARS 02 PASANG PINTU PAGAR KISI2 BESI HOLLOW m2 1,377,621.71
3 ARS 03 PASANG TULISAN ACRYLIC set #REF!
4 ME. 01 PEMASANGAN INSTALASI PENERANGAN titik 207,200.00
5 ME. 02 PEMASANGAN SAKLAR GANDA bh 22,725.00
6 ME. 03 PEMASANGAN LAMPU PCB LED 9 WATT bh 16,500.00
7 ME. 04 PEMBUATAN PENUTUP LAMPU ACRYLIC 20x25 cm bh 52,052.00
DAFTAR HARGA SATUAN UPAH
TAHUN 2020
( PERMEN PU NO. 11/PRT/M/2013 & SE MENTERI PU NO. 02/SE/M/2013 )

NO. TENAGA KERJA KODE SAT. UPAH KET.

1 Kepala Tukang L.01 OH 100,000.00


2 Kepala Tukang Batu L.02 OH 100,000.00
3 Kepala Tukang Besi L.03 OH 100,000.00
4 Kepala Tukang Cat L.04 OH 100,000.00
5 Kepala Tukang Gali L.05 OH 100,000.00
6 Kepala Tukang Kayu L.06 OH 100,000.00
7 Kepala Tukang Ledeng L.07 OH 100,000.00
8 Kepala Tukang Plitur L.08 OH 100,000.00
9 Mandor L.09 OH 110,000.00
10 Operator L.10 OH 120,000.00
11 Operator Pembantu L.11 OH 85,000.00
12 Pekerja L.12 OH 80,000.00
13 Penjaga Malam L.13 OH 80,000.00
14 Tukang L.14 OH 90,000.00
15 Tukang Batu L.15 OH 90,000.00
16 Tukang Besi L.16 OH 90,000.00
17 Tukang Cat L.17 OH 90,000.00
18 Tukang Gali L.18 OH 90,000.00
19 Tukang Kayu L.19 OH 90,000.00
20 Tukang Las L.20 OH 90,000.00
21 Tukang Ledeng L.21 OH 90,000.00
22 Tukang Plitur L.22 OH 90,000.00
DAFTAR HARGA SATUAN BAHAN
TAHUN 2020
( PERMEN PU NO. 11/PRT/M/2013 & SE MENTERI PU NO. 02/SE/M/2013 )

NO. NAMA BAHAN / MATERIAL SATUAN HARGA (Rp.)

1 Air bersih ltr 50.00


2 Alat bantu (set @ 3 alat) lot 10,000.00
3 Ampelas / Ambril lbr 3,500.00
4 Acrylic warna putih susu tebal 3mm (uk. 100x200 cm) lbr 496,000.00
m2 248,000.00
5 Bambu diameter 3-4" (panjang 600-800 cm) btg 26,000.00
6 Bata merah lokal bh 500.00
7 Bata ringan / Hebel 40x20x10 cm m3 850,000.00
8 Batu Belah Putih m3 226,200.00
9 Batu Pecah 1/2 (kerikil tersaring max 30mm) m3 289,200.00
10 Batu Alam (candi) - alur lurus m2 120,000.00
11 Besi Beton Polos kg 11,500.00
12 Cat Besi (cukup) kg 46,000.00
13 Cat Dasar kg 37,500.00
14 Cat Tembok Luar (baik) kg 90,000.00
15 Granit Cina Sandimas Cream 60x60cm (warna gelap) m2 125,000.00
16 Kabel NYM 3x2,5 mm2 m' 8,500.00
17 Kawat Beton kg 17,000.00
18 Kayu Dolken Sengon ø 8-10 cm, 4 m btg 54,500.00
19 Kayu Dolken Perancah m3 1,800,000.00
20 Kayu 5/7x 4m Kayu Kruing m3 6,545,400.00
21 Kayu Balok Klas 3 (Kruing) m3 6,545,400.00
22 Kayu Papan Kelas III (kruing) m3 7,200,000.00
23 Kayu Perancah m3 1,800,000.00
24 Kuas 3" bh 9,800.00
25 Pcb Led DC (9w) - Lampu Led SE Almunium bh 15,000.00
26 Minyak Beton & Bekisting ltr 11,100.00
27 Mortar MU (perekat hebel) @40 kg sak 150,000.00
28 Multipleks 120 x 240 tebal 9mm lbr 115,500.00
29 Paku - ukuran 1" s/d 4" kg 17,000.00
30 Paku - ukuran 1/4" s/d 1" kg 17,000.00
31 Paku Biasa ukuran 2"s/d5" & 5"s/d10" kg 15,800.00
32 Pasir Beton (ex. Bengawan Solo) m3 270,600.00
33 Pasir Pasang (ex. Bengawan Solo) m3 243,300.00
34 Pasir Urug (ada unsur lempung) m3 151,400.00
35 Pasir urug (tanah timbunan) m3 80,000.00
36 Paving Block K-300 (tebal 6cm) m2 65,000.00
37 Plamur Tembok kg 14,000.00
38 Pipa Medium B Galvanis DN 63 ( 2" ) m' 42,000.00
39 Portland Cement / PC kg 1,350.00
40 Saklar ganda standard bh 22,500.00
41 Tanah Biasa m3 70,000.00
42 Thinner liter 22,000.00
ANALISA HARGA SATUAN PEKERJAAN

PEKERJAAN : KONSTRUKSI PAGAR SISI SELATAN GEDUNG LECTURE ROOM & WORKSHOP
LOKASI : Jalan Dumai
TAHUN ANGGARAN : 2020

HARGA
JUMLAH
No. SNI KOEF SAT. URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp

I A.2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN


1 A.2.2.1.4a 1 m' Pengukuran dan Pemasangan Bouwplank 63,952.24
A Tenaga 18,550.00
0.1 OH Pekerja 80,000.00 8,000.00
0.1 OH Tukang Kayu 90,000.00 9,000.00
0.01 OH Kepala Tukang 100,000.00 1,000.00
0.005 OH Mandor 110,000.00 550.00
B Bahan 39,588.40
0.006 m3 Kayu 5/7x 4m Kayu Kruing 6,545,400.00 39,272.40
0.02 Kg Paku Biasa 2" - 5" 15,800.00 316.00
0.004 m3 Kayu Papan 3/20 Kruing 0.00 -
C PERALATAN
D Jumlah A + B + C 58,138.40
E Over Head & Provit 10% 5,813.84
F Harga Satuan Pekerjaan (D+E) 63,952.24

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 69,025.00
A TENAGA 62,750.00
0.75 OH Pekerja 80,000.00 60,000.00
0.025 OH Mandor 110,000.00 2,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 62,750.00
E Over Head & Provit 10% 6,275.00
F Harga Satuan Pekerjaan (D+E) 69,025.00

2 A.2.3.1.9 1 m3 Pengurugan Kembali


Pengurugan Kembali di hitung dari 1/3 kali koefisien Pekerjaan galian 16,683.33
A TENAGA 45,500.00
0.50 OH Pekerja 80,000.00 40,000.00
0.050 OH Mandor 110,000.00 5,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 45,500.00
E Over Head & Provit 10% 4,550.00
F Harga Satuan Pekerjaan (D+E) 50,050.00

3 A.2.3.1.11 1 m3 Urugan Pasir 227,458.00


A Pengurugan Kembali di hitung dari 1/3 kali koefisien Pekerjaan galian 25,100.00
0.30 OH Pekerja 80,000.00 24,000.00
0.01 OH Mandor 110,000.00 1,100.00
B BAHAN 181,680.00
1.200 m3 Pasir Urug (ada unsur lempung) 151,400.00 181,680.00
C PERALATAN
D Jumlah A + B + C 206,780.00
E Over Head & Provit 10% 20,678.00
F Harga Satuan Pekerjaan (D+E) 227,458.00

4 A.2.3.1.11a 1 m3 Urugan Tanah Biasa (tersedia) 27,610.00


A TENAGA 25,100.00
0.30 OH Pekerja 80,000.00 24,000.00
0.01 OH Mandor 110,000.00 1,100.00
B BAHAN -
1.200 m3 Tanah Biasa - -
C PERALATAN
D Jumlah A + B + C 25,100.00
E Over Head & Provit 10% 2,510.00
HARGA
JUMLAH
No. SNI KOEF SAT. URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
F Harga Satuan Pekerjaan (D+E) 27,610.00

IV A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 846,044.43
A TENAGA 203,250.00
1.5 OH Pekerja 80,000.00 120,000.00
0.750 OH Tukang Batu 90,000.00 67,500.00
0.075 OH Kepala Tukang 100,000.00 7,500.00
0.075 OH Mandor 110,000.00 8,250.00
B BAHAN 565,881.30
1.200 m3 Batu Belah Putih 226,200.00 271,440.00
117.000 Kg Portland Cement / PC 1,350.00 157,950.00
0.561 m3 Pasir Pasang (ex. Bengawan Solo) 243,300.00 136,491.30
C PERALATAN
D Jumlah A + B + C 769,131.30
E Over Head & Provit 10% 76,913.13
F Harga Satuan Pekerjaan (D+E) 846,044.43

2 A.3.2.1.9 1 m3 Pemasangan Batu Kosong/Anstamping 486,788.28


A TENAGA 105,690.00
0.78 OH Pekerja 80,000.00 62,400.00
0.39 OH Tukang Batu 90,000.00 35,100.00
0.039 OH Kepala Tukang 100,000.00 3,900.00
0.039 OH Mandor 110,000.00 4,290.00
B BAHAN 336,844.80
1.2 m3 Batu Belah 226,200.00 271,440.00
0.432 m3 Pasir Urug 151,400.00 65,404.80
C PERALATAN
D Jumlah A + B + C 442,534.80
E Over Head & Provit 10% 44,253.48
F Harga Satuan Pekerjaan (D+E) 486,788.28

III A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.17.a 1 Kg Pembesian dg Besi Polos atau Besi Ulir 14,997.40
A TENAGA 1,304.00
0.0070 OH Pekerja 80,000.00 560.00
0.0070 OH Tukang Besi 90,000.00 630.00
0.0007 OH Kepala Tukang 100,000.00 70.00
0.0004 OH Mandor 110,000.00 44.00
B BAHAN 12,330.00
1.050 Kg Besi Beton Polos 11,500.00 12,075.00
0.015 Kg Kawat Beton 17,000.00 255.00
C PERALATAN
D Jumlah A + B + C 13,634.00
E Over Head & Provit 10% 1,363.40
F Harga Satuan Pekerjaan (D+E) 14,997.40

2 A.4.1.1.20.a 1 m2 Memasang Bekisting untuk Pondasi 3x pakai 106,051.00


A TENAGA 70,460.00
0.5200 OH Pekerja 80,000.00 41,600.00
0.2600 OH Tukang Kayu 90,000.00 23,400.00
0.0260 OH Kepala Tukang 100,000.00 2,600.00
0.0260 OH Mandor 110,000.00 2,860.00
B BAHAN 25,950.00
0.0133 m3 Kayu Perancah 1,800,000.00 24,000.00
0.1000 Kg Paku Biasa ukuran 2"s/d5" & 5"s/d10" 15,800.00 1,580.00
0.0333 Ltr Minyak Beton & Bekisting 11,100.00 370.00
C PERALATAN
D Jumlah A + B + C 96,410.00
E Over Head & Provit 10% 9,641.00
F Harga Satuan Pekerjaan (D+E) 106,051.00

3 A.4.1.1.21.a 1 m2 Memasang Bekisting untuk Sloof 3x pakai 109,351.00


A TENAGA 70,460.00
0.5200 OH Pekerja 80,000.00 41,600.00
0.2600 OH Tukang Kayu 90,000.00 23,400.00
HARGA
JUMLAH
No. SNI KOEF SAT. URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
0.0260 OH Kepala Tukang 100,000.00 2,600.00
0.0260 OH Mandor 110,000.00 2,860.00
B BAHAN 28,950.00
0.0150 m3 Kayu Perancah 1,800,000.00 27,000.00
0.1000 Kg Paku Biasa ukuran 2"s/d5" & 5"s/d10" 15,800.00 1,580.00
0.0333 Ltr Minyak Beton & Bekisting 11,100.00 370.00
C PERALATAN
D Jumlah A + B + C 99,410.00
E Over Head & Provit 10% 9,941.00
F Harga Satuan Pekerjaan (D+E) 109,351.00

4 A.4.1.1.22.a 1 m2 Memasang Bekisting untuk Kolom 3x pakai 197,793.20


A TENAGA 89,430.00
0.660 OH Pekerja 80,000.00 52,800.00
0.330 OH Tukang Kayu 90,000.00 29,700.00
0.033 OH Kepala Tukang 100,000.00 3,300.00
0.033 OH Mandor 110,000.00 3,630.00
B BAHAN 90,382.00
0.013 m3 Kayu Perancah 1,800,000.00 24,000.00
0.133 Kg Paku Biasa ukuran 2"s/d5" & 5"s/d10" 15,800.00 2,106.67
0.067 Ltr Minyak Beton & Bekisting 11,100.00 740.00
0.005 m3 Kayu Balok Klas 3 (Kruing) 6,545,400.00 32,727.00
0.117 Lbr Multipleks 120 x 240 tebal 9mm 115,500.00 13,475.00
0.667 Btg Bambu diameter 3-4" (panjang 600-800 cm) 26,000.00 17,333.33
C PERALATAN
D Jumlah A + B + C 179,812.00
E Over Head & Provit 10% 17,981.20
F Harga Satuan Pekerjaan (D+E) 197,793.20

5 A.4.1.1.23.a 1 m2 Memasang Bekisting untuk Balok 3x pakai 204,993.14


A TENAGA 89,430.00
0.660 OH Pekerja 80,000.00 52,800.00
0.330 OH Tukang Kayu 90,000.00 29,700.00
0.033 OH Kepala Tukang 100,000.00 3,300.00
0.033 OH Mandor 110,000.00 3,630.00
B BAHAN 96,927.40
0.013 m3 Kayu Perancah 1,800,000.00 24,000.00
0.133 Kg Paku Biasa ukuran 2"s/d5" & 5"s/d10" 15,800.00 2,106.67
0.067 Ltr Minyak Beton & Bekisting 11,100.00 740.00
0.006 m3 Kayu Balok Klas 3 (Kruing) 6,545,400.00 39,272.40
0.117 Lbr Multipleks 120 x 240 tebal 9mm 115,500.00 13,475.00
0.667 Btg Bambu diameter 3-4" (panjang 600-800 cm) 26,000.00 17,333.33
C PERALATAN
D Jumlah A + B + C 186,357.40
E Over Head & Provit 10% 18,635.74
F Harga Satuan Pekerjaan (D+E) 204,993.14

6 A.4.1.1.4 1.00 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, 919,281.40
A TENAGA 122,600.00
1.200 OH Pekerja 80,000.00 96,000.00
0.200 OH Tukang Batu 90,000.00 18,000.00
0.020 OH Kepala Tukang 100,000.00 2,000.00
0.060 OH Mandor 110,000.00 6,600.00
B BAHAN 713,110.37
230 Kg Portland Cement / PC 1,350.00 310,500.00
893 kg Pasir Beton (ex. Bengawan Solo) 193.29 172,604.14
1,027 kg Batu Pecah 1/2 (kerikil tersaring max 30mm) 214.22 220,006.22
200 ltr Air 50.00 10,000.00
C PERALATAN
D Jumlah A + B + C 835,710.37
E Over Head & Provit 10% 83,571.04
F Harga Satuan Pekerjaan (D+E) 919,281.40

7 A.4.1.1.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,6 1,085,547.99
A TENAGA 168,680.00
1.650 OH Pekerja 80,000.00 132,000.00
HARGA
JUMLAH
No. SNI KOEF SAT. URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
0.275 OH Tukang Batu 90,000.00 24,750.00
0.028 OH Kepala Tukang 100,000.00 2,800.00
0.083 OH Mandor 110,000.00 9,130.00
B BAHAN 818,181.81
326 Kg Portland Cement / PC 1,350.00 440,100.00
760 Kg Pasir Beton (ex. Bengawan Solo) 193.29 146,897.14
1,029 Kg Batu Pecah 1/2 (kerikil tersaring max 30mm) 214.22 220,434.67
215 ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 986,861.81
E Over Head & Provit 10% 98,686.18
F Harga Satuan Pekerjaan (D+E) 1,085,547.99

8 A.4.1.1.6 1 m3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,6 1,118,463.47
A TENAGA 168,680.00
1.650 OH Pekerja 80,000.00 132,000.00
0.275 OH Tukang Batu 90,000.00 24,750.00
0.028 OH Kepala Tukang 100,000.00 2,800.00
0.083 OH Mandor 110,000.00 9,130.00
B BAHAN 848,104.97
352 Kg Portland Cement / PC 1,350.00 475,200.00
731 Kg Pasir Beton (ex. Bengawan Solo) 193.29 141,291.86
1,031 Kg Batu Pecah 1/2 (kerikil tersaring max 30mm) 214.22 220,863.11
215 ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,016,784.97
E Over Head & Provit 10% 101,678.50
F Harga Satuan Pekerjaan (D+E) 1,118,463.47

V A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


1 A.4.4.1.11 1 m2 Pas. Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP 103,184.07
A TENAGA 35,650.00
0.30 OH Pekerja 80,000.00 24,000.00
0.1 OH Tukang Batu 90,000.00 9,000.00
0.01 OH Kepala Tukang 100,000.00 1,000.00
0.015 OH Mandor 110,000.00 1,650.00
B BAHAN 58,153.70
70 Buah Bata merah lokal 500.00 35,000.00
8.32 Kg Portland Cement / PC 1,350.00 11,232.00
0.049 m3 Pasir Pasang (ex. Bengawan Solo) 243,300.00 11,921.70
C PERALATAN
D Jumlah A + B + C 93,803.70
E Over Head & Provit 10% 9,380.37
F Harga Satuan Pekerjaan (D+E) 103,184.07

2 A.4.4.1.21 1 m2 Pas. Dinding Bata Ringan / Hebel 160,435.00


A TENAGA 35,100.00
0.30 OH Pekerja 80,000.00 24,000.00
0.1 OH Tukang Batu 90,000.00 9,000.00
0.01 OH Kepala Tukang 100,000.00 1,000.00
0.010 OH Mandor 110,000.00 1,100.00
B BAHAN 110,750.00
0.10 m3 Bata ringan / Hebel 850,000.00 85,000.00
0.105 sak Mortar MU 150,000.00 15,750.00
1.000 ls Alat Bantu 10,000.00 10,000.00
C PERALATAN
D Over Head & Provit 145,850.00
E Harga Satuan Pekerjaan (D+E) 10% 14,585.00
F $ - 160,435.00

VI A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.4.2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 58,498.77
A TENAGA 40,650.00
0.3 OH Pekerja 80,000.00 24,000.00
0.15 OH Tukang batu 90,000.00 13,500.00
0.015 OH Kepala Tukang 100,000.00 1,500.00
HARGA
JUMLAH
No. SNI KOEF SAT. URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
0.015 OH Mandor 110,000.00 1,650.00
B BAHAN 12,530.70
4.416 Kg Portland Cement / PC 1,350.00 5,961.60
0.027 m3 Pasir Pasang (ex. Bengawan Solo) 243,300.00 6,569.10
C PERALATAN
D Jumlah A + B + C 53,180.70
E Over Head & Provit 10% 5,318.07
F Harga Satuan Pekerjaan (D+E) 58,498.77

2 A.4.4.2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 cm 55,745.69


A Tenaga 46,840.00
0.0800 OH Pekerja 80,000.00 6,400.00
0.4000 OH Tukang batu 90,000.00 36,000.00
0.0400 OH Kepala Tukang 100,000.00 4,000.00
0.0040 OH Mandor 110,000.00 440.00
B Bahan 3,837.90
0.5000 Kg Portland Semen 1,350.00 675.00
0.0130 m3 Pasir Pasang 243,300.00 3,162.90
C PERALATAN
D Jumlah A + B + C 50,677.90
E Over Head & Provit 10% 5,067.79
F Harga Satuan Pekerjaan (D+E) 55,745.69

Pemasangan Skoning Sudutan 1 Pc : 2Pp, (0,1 x indeks skoning


3 A.4.4.2.20.a 1 m' 5,574.57
l=10cm)
4 A.4.4.2.20.b 1 m' Pembuatan Tali Air (2 x indeks skoningan) 11,149.14

5 A.4.4.2.27 1 m2 Pemasangan Acian 34,636.25


A TENAGA 27,100.00
0.20 OH Pekerja 80,000.00 16,000.00
0.10 OH Tukang batu 90,000.00 9,000.00
0.010 OH Kepala Tukang 100,000.00 1,000.00
0.010 OH Mandor 110,000.00 1,100.00
B BAHAN 4,387.50
3.25 Kg Portland Cement / PC 1,350.00 4,387.50
C PERALATAN
D Jumlah A + B + C 31,487.50
E Over Head & Provit 10% 3,148.75
F Harga Satuan Pekerjaan (D+E) 34,636.25

VII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


1 A.4.4.3.34.c 1 m2 Pemasangan Lantai/Dinding granit cina Sandimas Cream 60x60cm 274,290.50
A Tenaga 94,850.00
0.7000 OH Pekerja 80,000.00 56,000.00
0.3500 OH Tukang Batu 90,000.00 31,500.00
0.0350 OH Kepala Tukang 100,000.00 3,500.00
0.0350 OH Mandor 110,000.00 3,850.00
B Bahan 154,505.00
1.0600 m2 Granit Cina Sandimas Cream 60x60cm 125,000.00 132,500.00
8.1900 Kg Portland Semen 1,350.00 11,056.50
0.0450 m3 Pasir Pasang 243,300.00 10,948.50
0.6500 Kg Semen Warna - -
C PERALATAN
D Jumlah A + B + C 249,355.00
E Over Head & Provit 10% 24,935.50
F Harga Satuan Pekerjaan (D+E) 274,290.50

2 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 276,350.80


A Tenaga 94,850.00
0.70 OH Pekerja 80,000.00 56,000.00
0.35 OH Tukang Batu 90,000.00 31,500.00
0.035 OH Kepala Tukang 100,000.00 3,500.00
0.035 OH Mandor 110,000.00 3,850.00
B Bahan 156,378.00
1.10 m2 Batu Alam (candi) - alur lurus 120,000.00 132,000.00
11.75 Kg Portland Semen 1,350.00 15,862.50
HARGA
JUMLAH
No. SNI KOEF SAT. URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
0.035 m3 Pasir Pasang 243,300.00 8,515.50
C PERALATAN
D Jumlah A + B + C 251,228.00
E Over Head & Provit 10% 25,122.80
F Harga Satuan Pekerjaan (D+E) 276,350.80

VIII A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN


Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 2 lap. Cat
1 A.4.7.1.10a 1 m2 40,458.00
Penutup) - Dinding Luar
A TENAGA 8,230.00
0.02 OH Pekerja 80,000.00 1,600.00
0.063 OH Tukang Cat 90,000.00 5,670.00
0.0063 OH Kepala Tukang 100,000.00 630.00
0.0030 OH Mandor 110,000.00 330.00
B BAHAN 28,550.00
0.1 Kg Plamir 14,000.00 1,400.00
0.1 Kg Cat Dasar 37,500.00 3,750.00
0.26 Kg Cat Penutup 2 kali 90,000.00 23,400.00
C PERALATAN
D Jumlah A + B + C 36,780.00
E Over Head & Provit 10% 3,678.00
F Harga Satuan Pekerjaan (D+E) 40,458.00
NO. KODE VOL. SAT. URAIAN HARGA SAT. JUMLAH HARGA

1 ARS 01 1 m2 PASANG PAGAR KISI2 BESI HOLLOW 890,016.88


A BAHAN 586,375.00
4.250 m' Besi Hollow 40x40x0,5-0,7mm 94,000.00 399,500.00
3.250 m' Besi Hollow 40x20x0,5-0,7mm 57,500.00 186,875.00
0.10 kg Cat Besi (cukup) -
0.01 liter Thinner -
0.005 bh Kuas 3" -
B TENAGA 17,500.00
L.14 0.150 OH Tukang 90,000.00 13,500.00
L.12 0.050 OH Pekerja 80,000.00 4,000.00
C PERALATAN 205,231.25
1.000 ls Diambil 35% x harga bahan (u/ pengelasan dll) 205,231.25 205,231.25
C Jumlah A + B + C 809,106.25
D Overhead & Profit 10% 80,910.63
E Harga Satuan Pekerjaan (D+E) 890,016.88

2 ARS 02 1 m2 PASANG PINTU PAGAR KISI2 BESI HOLLOW 1,377,621.71


1.100 m2 Pagar Profil Besi Kisi2 Hollow 890,016.88 979,018.56
3.000 m' Pipa Medium B Galvanis DN 63 ( 2" ) 42,000.00 126,000.00
0.500 kg Finish Cat Besi - -
0.050 m3 Rabbat Beton 919,281.40 45,964.07
1.100 m' Rel 50,000.00 55,000.00
0.200 x Bhn Upah Tenaga & Alat Bantu 232,003.71 46,400.74
C Jumlah 1,252,383.38
D Overhead & Profit 10% 125,238.34
E Harga Satuan Pekerjaan (D+E) 1,377,621.71

3 ARS 03 1 set PASANG TULISAN ACRYLIC #REF!


#REF! m2 Ketinggian 30cm 248,000.00 #REF!
1.000 ls Pemasangan & alat bantu 1,700,000.00 1,700,000.00
C Jumlah #REF!
D Overhead & Profit 10% #REF!
E Harga Satuan Pekerjaan (D+E) #REF!

4 ME. 01 1 titik PEMASANGAN INSTALASI PENERANGAN 207,200.00


Overhead (0%) - -
1 Titik pemasangan instalasi penerangan 207,200.00
12.00 m Bahan Kabel NYM 3x2,5 mm2 8,500.00 102,000.00
10% x Bahan Alat Bantu & Aksesoris 102,000.00 10,200.00
1.00 ls Upah Tenaga 95,000.00 95,000.00

5 ME. 02 1 bh PEMASANGAN SAKLAR GANDA 22,725.00


Overhead (0%) - -
1 Titik pemasangan saklar ganda 22,725.00
1.0000 bh saklar ganda 22,500.00 22,500.00
10% x Bahan Upah Tenaga 2,250.00 225.00

6 ME. 03 1 bh PEMASANGAN LAMPU PCB LED 9 WATT 16,500.00


Overhead (0%) - -
1 Titik pemasangan lampu LED 9 watt 16,500.00
1.0000 bh Pcb Led DC (9w) - Lampu Led SE Almunium 15,000.00 15,000.00
10% x Bahan Upah Tenaga 15,000.00 1,500.00

7 ME. 04 1 bh PEMBUATAN PENUTUP LAMPU ACRYLIC 20x25 cm 52,052.00


Overhead 10% 0.10 4,732.00
1 bh Pembuatan penutup lampu bahan acrylic putih susu tebal 3mm 47,320.00
0.0750 m2 Acrylic tebal 3mm 248,000.00 18,600.00
20% x Bahan Alat bantu & aksesories 18,600.00 3,720.00
1.0000 ls Upah tenaga 25,000.00 25,000.00
RINCIAN ANGGARAN BIAYA
PEKERJAAN : KONSTRUKSI PAGAR SISI SELATAN GEDUNG LECTURE ROOM & WORKSHOP
LOKASI : Jalan Dumai
TAHUN ANGGARAN : 2020

KODE HARGA JUMLAH TOTAL


NO. URAIAN PEKERJAAN VOLUME SAT SATUAN HARGA HARGA
ANALISA (Rp) (Rp) (Rp)
1 2 3 4 5 6 7 8
A PEKERJAAN PERSIAPAN
1 Pengukuran & pemasangan bouwplank 89.90 m' A.2.2.1.4a 63,952.24 5,749,306.38
2 Pembersihan 1.00 ls Taksir 01 2,300,000.00 2,300,000.00
3 Kesehatan Keselamatan Kerja (K3) 1.00 ls Taksir 02 600,000.00 600,000.00
4 Papan Pekerjaan 1.00 ls Taksir 03 200,000.00 200,000.00
SUB TOTAL A 8,849,306.38
B PAGAR SAMPING KIRI (PANJANG = 89,90M)
I Pekerjaan Tanah & Urugan
1 Galian tanah pondasi 63.40 m3 A.2.3.1.1 69,025.00 4,376,254.03
2 Urugan pasir di bawah pondasi 6.29 m3 A.2.3.1.11 227,458.00 1,431,393.19
3 Urugan tanah kembali 21.13 m3 A.2.3.1.9 16,683.33 352,580.01
SUB TOTAL B 6,160,227.22
C Pekerjaan Beton
1 Strauspall Ø 20cm :
a. Beton K-200 1.41 m3 A.4.1.1.6 1,118,463.47 1,580,388.88
b. Pembesian 215.26 kg A.4.1.1.17.a 14,997.40 3,228,314.89
2 Sloof 15/20 :
a. Beton K-200 2.70 m3 A.4.1.1.6 1,118,463.47 3,016,495.97
b. Pembesian 35.96 kg A.4.1.1.17.a 14,997.40 539,306.50
c. Bekisting 35.96 m2 A.4.1.1.21.a 109,351.00 3,932,261.96
3 Kolom 15/20 :
a. Beton K-200 1.40 m3 A.4.1.1.6 1,118,463.47 1,560,256.53
b. Pembesian 16.28 kg A.4.1.1.17.a 14,997.40 244,082.69
c. Bekisting 16.28 m2 A.4.1.1.22.a 197,793.20 3,219,084.33
4 Ring Balok 12/15 :
a. Beton K-200 1.62 m3 A.4.1.1.6 1,118,463.47 1,809,897.58
b. Pembesian 449.75 kg A.4.1.1.17.a 14,997.40 6,745,038.91
c. Bekisting 26.97 m2 A.4.1.1.23.a 204,993.14 5,528,664.99
SUB TOTAL C 31,403,793.21
D Pekerjaan Pasangan
1 Pasangan batu kosong setebal 20cm 12.59 m3 A.3.2.1.9 486,788.28 6,126,717.29
2 Pasangan pondasi batu belah 1:6 31.47 m3 A.3.2.1.4 846,044.43 26,620,787.99
3 Pasangan bata ringan dinding pagar 130.05 m2 A.4.4.1.21 160,435.00 20,863,769.58
4 Plester 1:6 260.09 m2 A.4.4.2.6 58,498.77 15,214,945.09
5 Aci 260.09 m2 A.4.4.2.27 34,636.25 9,008,542.26
6 Pengecatan 353.17 m2 A.4.7.1.10a 40,458.00 14,288,470.94
SUB TOTAL D 92,123,233.15
JUMLAH 138,536,559.97
PPN 10 % 13,853,656.00
JUMLAH TOTAL 152,390,215.97
DIBULATKAN 152,390,000.00
Terbilang : #NAME?

Cepu, September 2020


Menyetujui,
Ka. Bag. Umum dan Keuangan Ka. Sub. Bag. Umum

Prasudjyana Gamarlap Seputra, ST., MT. Anwar Su'udi, S.E.


NIP. 196803031987031001 NIP. 196505011986031002
NAMA PEKERJAAN PANJANG LEBAR TINGGI BANYAK JUMLAH SAT
I. PEKERJAN TANAH
Pengukuran & pemasangan bouwplank 89.9 1 1 1 89.9 m1

Galian Pondasi Batu Belah


Pagar C 89.9 0.7 1 1.0 62.93 m3
Strous pile 0.5 0.0314 1 30.0 0.47 m3
total = 63.40 m3

Urugan pasir bawah pondasi


Pagar C 89.9 0.7 0.1 1.0 6.29 m3

Urugan tanah kembali 62.93 0.33333333 1 1 20.98 m3

II. PEKERJAAN PASANGAN PANJANG LEBAR TINGGI BANYAK JUMLAH SAT

Pasangan batu kosong setebal 20cm


Pagar C 89.9 0.7 0.2 1.0 12.59 m3

Pasangan pondasi batu belah 1:6


Pagar C 89.9 0.5 0.7 1.0 31.47 m3

Pasangan bata ringan dinding pagar

Pagar C 89.9 1 1.55 1 139.35 m2


Kolom 30 0.2 1.55 1 9.30 m2
total = 130.05 m2

Plester 1:6 130.05 1.0 1 2 = 260.09 m2


Aci 130.045 1.00 1 2 = 260.09 m2
=
III. PEKERJAAN BETON PANJANG LEBAR TINGGI BANYAK JUMLAH SAT

Strauspall Ø 20cm : 0.0314 1 1.5 30.0 = 1.41 m3


1.41 m3

Sloof 15/20 89.9 0.15 0.2 1 = 2.70 m3


2.70 m3

Kolom 15/20 0.2 0.15 1.55 30.0 = 1.40 m3


1.40 m3

Ringbalk 12/15 89.9 0.12 0.15 1 = 1.62 m3


1.62 m3

IV. PEKERJAAN BEGISTING PANJANG LEBAR TINGGI BANYAK JUMLAH SAT

Sloof 15/20 89.9 1 0.2 2 = 35.96 m2


35.96 m2

Kolom 15/20 1.55 0.35 1 30.0 = 16.28 m2


16.28 m2

Ringbalk 12/15 89.9 1 0.15 2 = 26.97 m2


26.97 m2

V. PEKERJAAN PEMBESIAN PANJANG jmlh besi koef BANYAK JUMLAH SAT

Strauspall Ø 20cm : 1.57 4.00 0.888 30.0 = 167.30 kg


0.628 11.47 0.222 30.0 = 47.96 kg
215.26 kg

Sloof 15/20 89.9 4 0.888 1 = 319.32 kg


0.65 600.33 0.395 1 = 154.14 kg
473.46 kg

Kolom 15/20 1.55 4 0.888 30.0 = 165.17 kg


0.55 11.33 0.395 30.0 = 73.87 kg
239.03 kg

Ringbalk 12/15 89.9 4 0.888 1 = 319.32 kg


0.55 600.33 0.395 1 = 130.42 kg
449.75 kg

VI. PEKERJAAN CAT PANJANG LEBAR TINGGI BANYAK JUMLAH SAT


cat pagar 89.9 1 1.9 2 341.62 m2
89.9 1 0.12 1 10.79 m2
0.2 1 1.9 2 0.76 m2
353.17 m2