TERBILANG : SERATUS TUJUH PULUH DUA JUTA EMPAT RATUS SEMBILAN PULUH DELAPAN RIBU RUPIAH
……………………
Direktur
DAFTAR HARGA SATUAN PEKERJAAN
TAHUN 2020
( PERMEN PU NO. 11/PRT/M/2013 & SE MENTERI PU NO. 02/SE/M/2013 )
PEKERJAAN : KONSTRUKSI PAGAR SISI SELATAN GEDUNG LECTURE ROOM & WORKSHOP
LOKASI : Jalan Dumai
TAHUN ANGGARAN : 2020
HARGA
JUMLAH
No. SNI KOEF SAT. URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
6 A.4.1.1.4 1.00 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, 919,281.40
A TENAGA 122,600.00
1.200 OH Pekerja 80,000.00 96,000.00
0.200 OH Tukang Batu 90,000.00 18,000.00
0.020 OH Kepala Tukang 100,000.00 2,000.00
0.060 OH Mandor 110,000.00 6,600.00
B BAHAN 713,110.37
230 Kg Portland Cement / PC 1,350.00 310,500.00
893 kg Pasir Beton (ex. Bengawan Solo) 193.29 172,604.14
1,027 kg Batu Pecah 1/2 (kerikil tersaring max 30mm) 214.22 220,006.22
200 ltr Air 50.00 10,000.00
C PERALATAN
D Jumlah A + B + C 835,710.37
E Over Head & Provit 10% 83,571.04
F Harga Satuan Pekerjaan (D+E) 919,281.40
7 A.4.1.1.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,6 1,085,547.99
A TENAGA 168,680.00
1.650 OH Pekerja 80,000.00 132,000.00
HARGA
JUMLAH
No. SNI KOEF SAT. URAIAN PAKERJAAN BAHAN/UPAH
Rp Rp
0.275 OH Tukang Batu 90,000.00 24,750.00
0.028 OH Kepala Tukang 100,000.00 2,800.00
0.083 OH Mandor 110,000.00 9,130.00
B BAHAN 818,181.81
326 Kg Portland Cement / PC 1,350.00 440,100.00
760 Kg Pasir Beton (ex. Bengawan Solo) 193.29 146,897.14
1,029 Kg Batu Pecah 1/2 (kerikil tersaring max 30mm) 214.22 220,434.67
215 ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 986,861.81
E Over Head & Provit 10% 98,686.18
F Harga Satuan Pekerjaan (D+E) 1,085,547.99
8 A.4.1.1.6 1 m3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,6 1,118,463.47
A TENAGA 168,680.00
1.650 OH Pekerja 80,000.00 132,000.00
0.275 OH Tukang Batu 90,000.00 24,750.00
0.028 OH Kepala Tukang 100,000.00 2,800.00
0.083 OH Mandor 110,000.00 9,130.00
B BAHAN 848,104.97
352 Kg Portland Cement / PC 1,350.00 475,200.00
731 Kg Pasir Beton (ex. Bengawan Solo) 193.29 141,291.86
1,031 Kg Batu Pecah 1/2 (kerikil tersaring max 30mm) 214.22 220,863.11
215 ltr Air 50.00 10,750.00
C PERALATAN
D Jumlah A + B + C 1,016,784.97
E Over Head & Provit 10% 101,678.50
F Harga Satuan Pekerjaan (D+E) 1,118,463.47