REKAPITULASI LAPORAN PRESTASI MINGGUAN

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017
PERIODE LAPORAN :
MINGGU KE : 1 ( SATU )
TANGGAL : 14 - 20 Juni 2017

RENCANA PEKERJAAN REALISASI PEKERJAAN


NO. URAIAN PEKERJAAN JUMLAH BIAYA BOBOT PRESTASI JUMLAH BIAYA BOBOT PRESTASI
(Rp.) (%) (Rp.) (%)

A. PEKERJAAN TANAH 8,117,125.68 2.07 582,673,818.00 #NAME?


B. PEKERJAAN PASANGAN DAN PLESTERA 44,918,451.81 11.48 - #NAME?
C. PEKERJAAN BETON 262,879,327.60 40.83 1,845,537,512.00 #NAME?
D. PEKERJAAN PINTU DAN JENDELA 340,848,000.00 6.37 - #NAME?
II. PEKERJAAN NON KONSTRUKSI 30,000,000.00 7.67 - #NAME?
III. PERENCANAAN DAN PENGAWASAN 17,040,000.00 4.35 - #NAME?
IV. BIAYA PENGELOLAAN 3,408,000.00 0.87 - #NAME?
### #NAME? #NAME? #NAME? #NAME? #NAME?
### #NAME? #NAME? #NAME? #NAME? #NAME?
### #NAME? #NAME? #NAME? #NAME? #NAME?
### #NAME? #NAME? #NAME? #NAME? #NAME?
### #NAME? #NAME? #NAME? #NAME? #NAME?

TOTAL #NAME? #NAME? #NAME? #NAME?


JUMLAH TOTAL #NAME? #NAME?
DIBULATKAN #NAME? #NAME?

PRESTASI PEKERJAAN MINGGU LALU #REF! %


PRESTASI PEKERJAAN MINGGU INI #REF! %
PRESTASI PEKERJAAN S/D MINGGU INI #REF! %
RENCANA PEKERJAAN S/D MINGGU INI 2.61 %
#REF! #REF! %

#NAME?
Mengetahui / Menyetujui, Dibuat Oleh :
TIM PENGAWAS Konsultan Pengawas

BAYU ESKA KURNIAWAN, ST BAYU ESKA KURNIAWAN, ST


LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 1 ( SATU )
TANGGAL : 14 - 20 Juni 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 0 -
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.49
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 0 -
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 0 -
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 0 -
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 -
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 0 -
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 0 -
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 0 -
~ Besi Beton kg 263.760 0.82 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 0 -
~ Besi Beton kg 589.095 1.82 0 -
~ Beton Cor K-225 m3 3.807 0.94 0 -
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 0 -
~ Besi Beton kg 1582.039 4.90 0 -
~ Beton Cor K-225 m3 9.180 2.27 0 -
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 0 -
~ Besi Beton kg 154.227 0.48 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 0 -
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 0 -
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 0 -
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 0 -
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 5.03
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 6.52
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 6.52

Batang, 21 Juni 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 1 ( SATU )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 14 - 20 Juni 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52
DEVISIASI 3.91
KETERANGAN Mendahului

Batang, 21 Juni 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 2 ( DUA )
TANGGAL : 21 - 27 Juni 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 0 -
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.49
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 0 -
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 0 -
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 0 -
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 -
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 0 -
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 70 1.25
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 0 -
~ Besi Beton kg 263.760 0.82 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 0 -
~ Besi Beton kg 589.095 1.82 0 -
~ Beton Cor K-225 m3 3.807 0.94 0 -
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 0 -
~ Besi Beton kg 1582.039 4.90 0 -
~ Beton Cor K-225 m3 9.180 2.27 0 -
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 0 -
~ Besi Beton kg 154.227 0.48 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 0 -
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 0 -
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 0 -
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 0 -
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 6.28
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 7.77
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 7.77

Batang, 28 Juni 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 2 ( DUA )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 21 - 27 Juni 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77
DEVISIASI 3.91 5.16
KETERANGAN Mendahului Mendahului

Batang, 28 Juni 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 3 ( TIGA )
TANGGAL : 28 Juni - 4 Juli 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 0 -
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.49
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 0 -
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 0 -
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 0 -
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 -
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 0 -
~ Besi Beton kg 263.760 0.82 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 0 -
~ Besi Beton kg 589.095 1.82 0 -
~ Beton Cor K-225 m3 3.807 0.94 0 -
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 0 -
~ Besi Beton kg 1582.039 4.90 0 -
~ Beton Cor K-225 m3 9.180 2.27 0 -
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 0 -
~ Besi Beton kg 154.227 0.48 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 0 -
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 0 -
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 0 -
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 0 -
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 7.75
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 9.24
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 9.24

Batang, 5 Juli 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 3 ( TIGA )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 28 Juni - 4 Juli 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24
DEVISIASI 3.91 5.16 3.29
KETERANGAN Mendahului Mendahului Mendahului

Batang, 5 Juli 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 4 ( EMPAT )
TANGGAL : 5 - 11 Juli 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 0 -
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.49
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 0 -
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 0 -
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 0 -
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 -
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 0 -
~ Besi Beton kg 589.095 1.82 0 -
~ Beton Cor K-225 m3 3.807 0.94 0 -
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 0 -
~ Besi Beton kg 1582.039 4.90 0 -
~ Beton Cor K-225 m3 9.180 2.27 0 -
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 0 -
~ Besi Beton kg 154.227 0.48 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 0 -
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 0 -
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 0 -
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 0 -
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 9.06
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 10.55
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 10.55

Batang, 12 Juli 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 4 ( EMPAT )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 5 - 11 Juli 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55
DEVISIASI 3.91 5.16 3.29 1.27
KETERANGAN Mendahului Mendahului Mendahului Mendahului

Batang, 12 Juli 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 5 ( LIMA )
TANGGAL : 12 - 18 Juli 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.76
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 0 -
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 4.89
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 20 0.19
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 0 -
~ Besi Beton kg 1582.039 4.90 0 -
~ Beton Cor K-225 m3 9.180 2.27 0 -
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 0 -
~ Besi Beton kg 154.227 0.48 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 0 -
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 0 -
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 0 -
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 0 -
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 13.04
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 19.69
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 19.69

Batang, 18 Juli 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 5 ( LIMA )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 12 - 18 Juli 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69
DEVISIASI 3.91 5.16 3.29 1.27 2.01
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 18 Juli 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 6 ( ENAM )
TANGGAL : 19 - 25 Juli 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.76
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 0 -
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 4.89
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 60 2.89
~ Besi Beton kg 1582.039 4.90 60 2.94
~ Beton Cor K-225 m3 9.180 2.27 60 1.36
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 0 -
~ Besi Beton kg 154.227 0.48 0 -
~ Beton Cor K-225 m3 1.120 0.28 0 -
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 0 -
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 0 -
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 0 -
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 0 -
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 20.99
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 27.64
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 27.64

Batang, 26 Juli 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 6 ( ENAM )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 19 - 25 Juli 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 26 Juli 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 7 ( TUJUH )
TANGGAL : 26 Juli - 1 Agustus 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.76
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 0 -
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 4.89
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 50 1.00
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 0 -
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 0 -
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 30.41
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 37.06
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 37.06

Batang, 2 Agustus 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 7 ( TUJUH )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 26 Juli - 1 Agustus 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 2 Agustus 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 8 ( DELAPAN )
TANGGAL : 2 - 8 Agustus 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.76
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 40 1.84
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 6.73
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 30 3.04
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 36.63
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 45.12
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 45.12

Batang, 9 Agustus 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 8 ( DELAPAN )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 2 - 8 Agustus 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 9 Agustus 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 9 ( SEMBILAN )
TANGGAL : 9 - 15 Agustus 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.76
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 40 1.84
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 6.73
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 0 -
~ Beton Cor K-225 m3 5.760 1.43 0 -
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 0 -
~ Beton Cor K-225 m3 1.104 0.27 0 -
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 0 -
~ Beton Cor K-225 m3 0.855 0.21 0 -
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 0 -
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 43.72
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 52.21
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 52.21

Batang, 16 Agustus 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 9 ( SEMBILAN )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 9 - 15 Agustus 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 16 Agustus 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 10 ( SEPULUH )
TANGGAL : 16 - 22 Agustus 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.76
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 40 1.84
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 6.73
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 100 2.21
~ Beton Cor K-225 m3 5.760 1.43 100 1.43
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 100 1.72
~ Beton Cor K-225 m3 1.104 0.27 100 0.27
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 100 1.70
~ Beton Cor K-225 m3 0.855 0.21 100 0.21
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 50 4.65
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 55.92
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 64.41
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 64.41

Batang, 23 Agustus 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 10 ( SEPULUH )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 16 - 22 Agustus 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09 12.20
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21 64.41
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95 4.75
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 23 Agustus 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 11 ( SEBELAS )
TANGGAL : 23 - 29 Agustus 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 0 -
Sub Total 2.07 1.76
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 40 1.84
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 6.73
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 100 2.21
~ Beton Cor K-225 m3 5.760 1.43 100 1.43
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 100 1.72
~ Beton Cor K-225 m3 1.104 0.27 100 0.27
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 100 1.70
~ Beton Cor K-225 m3 0.855 0.21 100 0.21
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 100 9.31
~ Beton Cor K-225 m3 21.600 5.35 0 -
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 20 0.31
Sub Total 67.18 60.57
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 0 -
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 -
TOTAL I 87.11 69.06
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 69.06

Batang, 30 Agustus 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 11 ( SEBELAS )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 23 - 29 Agustus 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09 12.20 4.65
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21 64.41 69.06
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95 4.75 1.00
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 30 Agustus 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 12 ( DUA BELAS )
TANGGAL : 30 Agustus - 5 September 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 100 0.32
Sub Total 2.07 2.07
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 100 4.60
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 0 -
Sub Total 11.48 9.49
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 100 2.21
~ Beton Cor K-225 m3 5.760 1.43 100 1.43
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 100 1.72
~ Beton Cor K-225 m3 1.104 0.27 100 0.27
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 100 1.70
~ Beton Cor K-225 m3 0.855 0.21 100 0.21
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 100 9.31
~ Beton Cor K-225 m3 21.600 5.35 100 5.35
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 100 1.57
Sub Total 67.18 67.18
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 100 2.66
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 0 -
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 0 -
4 Pek. Engsel Pintu set 2.000 0.02 0 -
5 Pek. Engsel Jendela set 20.000 0.14 0 -
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 0 -
7 Pek. Kait Angin Bh 20.000 0.14 0 -
8 Pek. Grendel Bh 20.000 0.11 0 -
9 Pek. Kaca T: 5 mm m2 49.280 1.70 0 -
Sub Total 6.37 2.66
TOTAL I 87.11 81.41
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 81.41

Batang, 6 September 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 12 ( DUA BELAS )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 30 Agustus - 5 September 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09 12.20 4.65 12.35
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21 64.41 69.06 81.41
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95 4.75 1.00 2.66
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 6 September 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 13 ( TIGA BELAS )
TANGGAL : 6 - 12 September 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 100 0.32
Sub Total 2.07 2.07
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 100 4.60
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 100 1.99
Sub Total 11.48 11.48
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 100 2.21
~ Beton Cor K-225 m3 5.760 1.43 100 1.43
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 100 1.72
~ Beton Cor K-225 m3 1.104 0.27 100 0.27
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 100 1.70
~ Beton Cor K-225 m3 0.855 0.21 100 0.21
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 100 9.31
~ Beton Cor K-225 m3 21.600 5.35 100 5.35
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 100 1.57
Sub Total 67.18 67.18
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 100 2.66
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 100 0.80
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 100 0.72
4 Pek. Engsel Pintu set 2.000 0.02 100 0.02
5 Pek. Engsel Jendela set 20.000 0.14 100 0.14
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 100 0.08
7 Pek. Kait Angin Bh 20.000 0.14 100 0.14
8 Pek. Grendel Bh 20.000 0.11 100 0.11
9 Pek. Kaca T: 5 mm m2 49.280 1.70 100 1.70
Sub Total 6.37 6.37
TOTAL I 87.11 87.11
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 0 -
TOTAL II 7.67 -
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 0 -
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 -
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 87.11

Batang, 13 September 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 13 ( TIGA BELAS )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 6 - 12 September 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09 12.20 4.65 12.35 5.69
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21 64.41 69.06 81.41 87.11
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95 4.75 1.00 2.66 0.31
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 13 September 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 14 ( EMPAT BELAS )
TANGGAL : 13 - 19 September 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 100 0.32
Sub Total 2.07 2.07
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 100 4.60
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 100 1.99
Sub Total 11.48 11.48
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 100 2.21
~ Beton Cor K-225 m3 5.760 1.43 100 1.43
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 100 1.72
~ Beton Cor K-225 m3 1.104 0.27 100 0.27
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 100 1.70
~ Beton Cor K-225 m3 0.855 0.21 100 0.21
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 100 9.31
~ Beton Cor K-225 m3 21.600 5.35 100 5.35
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 100 1.57
Sub Total 67.18 67.18
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 100 2.66
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 100 0.80
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 100 0.72
4 Pek. Engsel Pintu set 2.000 0.02 100 0.02
5 Pek. Engsel Jendela set 20.000 0.14 100 0.14
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 100 0.08
7 Pek. Kait Angin Bh 20.000 0.14 100 0.14
8 Pek. Grendel Bh 20.000 0.11 100 0.11
9 Pek. Kaca T: 5 mm m2 49.280 1.70 100 1.70
Sub Total 6.37 6.37
TOTAL I 87.11 87.11
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 100 7.67
TOTAL II 7.67 7.67
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 100 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 0 -
TOTAL III 4.35 2.61
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 97.39

Batang, 20 September 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 14 ( EMPAT BELAS )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 13 - 19 September 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09 12.20 4.65 12.35 5.69 10.28
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21 64.41 69.06 81.41 87.11 97.39
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95 4.75 1.00 2.66 0.31 2.34
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 20 September 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 15 ( LIMA BELAS )
TANGGAL : 20 - 26 September 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 100 0.32
Sub Total 2.07 2.07
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 100 4.60
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 100 1.99
Sub Total 11.48 11.48
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 100 2.21
~ Beton Cor K-225 m3 5.760 1.43 100 1.43
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 100 1.72
~ Beton Cor K-225 m3 1.104 0.27 100 0.27
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 100 1.70
~ Beton Cor K-225 m3 0.855 0.21 100 0.21
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 100 9.31
~ Beton Cor K-225 m3 21.600 5.35 100 5.35
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 100 1.57
Sub Total 67.18 67.18
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 100 2.66
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 100 0.80
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 100 0.72
4 Pek. Engsel Pintu set 2.000 0.02 100 0.02
5 Pek. Engsel Jendela set 20.000 0.14 100 0.14
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 100 0.08
7 Pek. Kait Angin Bh 20.000 0.14 100 0.14
8 Pek. Grendel Bh 20.000 0.11 100 0.11
9 Pek. Kaca T: 5 mm m2 49.280 1.70 100 1.70
Sub Total 6.37 6.37
TOTAL I 87.11 87.11
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 100 7.67
TOTAL II 7.67 7.67
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 100 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 100 1.74
TOTAL III 4.35 4.35
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 0 -
TOTAL IV 0.87 -

TOTAL 100.00 99.13

Batang, 27 September 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 15 ( LIMA BELAS )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 20 - 26 September 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09 12.20 4.65 12.35 5.69 10.28 1.74
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21 64.41 69.06 81.41 87.11 97.39 99.13
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95 4.75 1.00 2.66 0.31 2.34 0.44
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 27 September 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 16 ( ENAM BELAS )
TANGGAL : 27 September - 3 Oktober 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 100 0.32
Sub Total 2.07 2.07
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 100 4.60
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 100 1.99
Sub Total 11.48 11.48
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 100 2.21
~ Beton Cor K-225 m3 5.760 1.43 100 1.43
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 100 1.72
~ Beton Cor K-225 m3 1.104 0.27 100 0.27
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 100 1.70
~ Beton Cor K-225 m3 0.855 0.21 100 0.21
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 100 9.31
~ Beton Cor K-225 m3 21.600 5.35 100 5.35
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 100 1.57
Sub Total 67.18 67.18
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 100 2.66
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 100 0.80
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 100 0.72
4 Pek. Engsel Pintu set 2.000 0.02 100 0.02
5 Pek. Engsel Jendela set 20.000 0.14 100 0.14
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 100 0.08
7 Pek. Kait Angin Bh 20.000 0.14 100 0.14
8 Pek. Grendel Bh 20.000 0.11 100 0.11
9 Pek. Kaca T: 5 mm m2 49.280 1.70 100 1.70
Sub Total 6.37 6.37
TOTAL I 87.11 87.11
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 100 7.67
TOTAL II 7.67 7.67
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 100 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 100 1.74
TOTAL III 4.35 4.35
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 80 0.70
TOTAL IV 0.87 0.70

TOTAL 100.00 99.83

Batang, 4 Oktober 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 16 ( ENAM BELAS )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 27 September - 3 Oktober 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09 12.20 4.65 12.35 5.69 10.28 1.74 0.70
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21 64.41 69.06 81.41 87.11 97.39 99.13 99.83
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95 4.75 1.00 2.66 0.31 2.34 0.44 0.04
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului

Batang, 4 Oktober 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
LAPORAN KEMAJUAN PEKERJAAN
KEGIATAN : PEMBANGUNAN RUANG KELAS BARU
PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2
LOKASI : KEC. BATANG KAB. BATANG
TAHUN ANGGARAN : 2017

WAKTU PELAKSANAAN PEKERJAAN : 120 (Seratus Dua Puluh) Hari Kalender


MINGGU KE : 17 ( TUJUH BELAS )
TANGGAL : 4 - 11 Oktober 2017

PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

I. PEKERJAAN KONSTRUKSI
PEMBANGUNAN RUANG KELAS BARU 2 RUANG
A. PEKERJAAN TANAH
1 Pek. Galian tanah m3 97.470 1.21 100 1.21
2 Pek. Urugan tanah kembali m3 32.490 0.27 100 0.27
3 Pek. Urugan Pasir Bawah pondasi m3 4.214 0.27 100 0.27
4 Pek. Urugan Tanah Baru m3 18.000 0.32 100 0.32
Sub Total 2.07 2.07
B. PEKERJAAN PASANGAN DAN PLESTERAN
1 Pek. Aanstamping/Batu kosong m3 9.216 0.86 100 0.86
2 Pek. Pas. Batu kali 1 : 6 (batu belah 70% : batu blonos 30%) m3 22.626 4.03 100 4.03
3 Pek. Pas. Batu bata 1 : 6 tebal 1/2 bata m2 164.777 4.60 100 4.60
4 Pek. Plesteran 1 : 6 tebal 15 mm ( dalam kelas ) m2 169.277 1.99 100 1.99
Sub Total 11.48 11.48
C. PEKERJAAN BETON
1 Pek. Footplat 120 x 120 cm
~ Bekisting 2 x pakai m2 24.000 0.93 100 0.93
~ Besi Beton kg 1523.947 4.72 100 4.72
~ Beton Cor K-225 m3 7.200 1.78 100 1.78
2 Pek. Footplat 80 x 80 cm
~ Bekisting 2 x pakai m2 5.600 0.22 100 0.22
~ Besi Beton kg 263.760 0.82 100 0.82
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
3 Pek. Sloof 15 x 30 cm
~ Bekisting 2 x pakai m2 50.760 1.97 100 1.97
~ Besi Beton kg 589.095 1.82 100 1.82
~ Beton Cor K-225 m3 3.807 0.94 100 0.94
4 Pek. Beton Kolom Struktur 30 x 30 cm
~ Bekisting 2 x pakai m2 123.960 4.82 100 4.82
~ Besi Beton kg 1582.039 4.90 100 4.90
~ Beton Cor K-225 m3 9.180 2.27 100 2.27
5 Pek. Beton Kolom Teras 20 x 20 cm
~ Bekisting 2 x pakai m2 23.440 0.91 100 0.91
~ Besi Beton kg 154.227 0.48 100 0.48
~ Beton Cor K-225 m3 1.120 0.28 100 0.28
6 Pek. Beton Balok Induk 30 x 60 cm
~ Bekisting 2 x pakai m2 50.400 1.96 100 1.96
~ Besi Beton kg 713.522 2.21 100 2.21
~ Beton Cor K-225 m3 5.760 1.43 100 1.43
7 Pek. Beton Balok Anak 20 x 30 cm
~ Bekisting 2 x pakai m2 51.520 2.00 100 2.00
~ Besi Beton kg 555.754 1.72 100 1.72
~ Beton Cor K-225 m3 1.104 0.27 100 0.27
PRESTASI
TAHAP
TERHADAP
NO. JENIS PEKERJAAN SATUAN VOLUME NILAI BOBOT (%) PENYELESAIAN
KESELURUHAN
(%)
PEKERJAAN (%)

8 Pek. Beton Balok Anak 15 x 25 cm


~ Bekisting 2 x pakai m2 56.340 2.19 100 2.19
~ Besi Beton kg 550.870 1.70 100 1.70
~ Beton Cor K-225 m3 0.855 0.21 100 0.21
9 Pek. Beton Plat Lantai
~ Bekisting m2 136.100 10.13 100 10.13
~ Besi Beton kg 3006.629 9.31 100 9.31
~ Beton Cor K-225 m3 21.600 5.35 100 5.35
10 Pek. Beton Lantai Kerja ( Bawah footplat, lantai ruang kelas & selasar)
~ Beton Cor (Mutu beton K-100) m3 7.142 1.57 100 1.57
Sub Total 67.18 67.18
D. PEKERJAAN PINTU DAN JENDELA
1 Pek. Kusen Pintu Dan Jendela Kayu Kampas m3 1.174 2.66 100 2.66
2 Pek. Daun Pintu Panil Kayu Kampas m2 5.040 0.80 100 0.80
3 Pek. Daun Jendela Kaca Kayu Kampas m2 6.400 0.72 100 0.72
4 Pek. Engsel Pintu set 2.000 0.02 100 0.02
5 Pek. Engsel Jendela set 20.000 0.14 100 0.14
6 Pek. Kunci Tanam 2x Putar Bh 2.000 0.08 100 0.08
7 Pek. Kait Angin Bh 20.000 0.14 100 0.14
8 Pek. Grendel Bh 20.000 0.11 100 0.11
9 Pek. Kaca T: 5 mm m2 49.280 1.70 100 1.70
Sub Total 6.37 6.37
TOTAL I 87.11 87.11
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT
1 Perabot Ruang Kelas paket 2.000 7.67 100 7.67
TOTAL II 7.67 7.67
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) Ls 1.000 2.61 100 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) Ls 1.000 1.74 100 1.74
TOTAL III 4.35 4.35
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) Ls 1.000 0.87 100 0.87
TOTAL IV 0.87 0.87

TOTAL 100.00 100.00

Batang, 12 Oktober 2017


Menyetujui / Mengetahui :
KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
TIME SCHEDULE

KEGIATAN : PEMBANGUNAN RUANG KELAS BARU


PEKERJAAAN : PEMBANGUNAN RUANG KELAS BARU SMK BHAKTI PRAJA 2 MINGGU KE : 17 ( TUJUH BELAS )
LOKASI : KEC. BATANG KAB. BATANG TANGGAL : 4 - 11 Oktober 2017
TAHUN ANGGARAN : 2017
BULAN I BULAN II BULAN III BULAN IV BULAN V
MINGGU KE
BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
NO. URAIAN PEKERJAAN PRESTASI
(%) 14-Jun-17 21-Jun-17 28-Jun-17 5-Jul-17 12-Jul-17 19-Jul-17 26-Jul-17 2-Aug-17 9-Aug-17 16-Aug-17 23-Aug-17 30-Aug-17 6-Sep-17 13-Sep-17 20-Sep-17 27-Sep-17 4-Oct-17 BOBOT PEK. WAKTU
s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d s/d (%) PELAKS.
20-Jun-17 27-Jun-17 4-Jul-17 11-Jul-17 18-Jul-17 25-Jul-17 1-Aug-17 8-Aug-17 15-Aug-17 22-Aug-17 29-Aug-17 5-Sep-17 12-Sep-17 19-Sep-17 26-Sep-17 3-Oct-17 11-Oct-17

I. PEKERJAAN KONSTRUKSI -
PEMBANGUNAN RUANG KELAS BARU 2 RUANG 100%
A. PEKERJAAN TANAH 2.07 1.04 1.04

Jangka Waktu 120 hari kalender


B. PEKERJAAN PASANGAN DAN PLESTERAN 11.48 2.30 2.30 2.30 2.30 2.30
C. PEKERJAAN BETON 67.18 8.40 8.40 8.40 8.40 8.40 8.40 8.40 8.40
D. PEKERJAAN PINTU DAN JENDELA 6.37 3.19 3.19
II. PEKERJAAN NON KONSTRUKSI
A. MEUBELAIR/PERABOT 7.67 2.56 2.56 2.56
III. PERENCANAAN DAN PENGAWASAN
A. BIAYA PERENCANAAN ( 3% x Sub Total I ) 2.61 2.61
B. BIAYA PENGAWASAN ( 2% x Sub Total I ) 1.74 0.87 0.87
IV. BIAYA PENGELOLAAN
A. BIAYA PENGELOLAAN ADMINISTRASI ( 1% x Sub Total I ) 0.87 0.22 0.22 0.22 0.22 0%

TOTAL 100.00

RENCANA PEKERJAAN PER-MINGGU 2.61 - 3.33 3.33 8.40 8.40 8.40 8.40 8.40 8.40 8.40 10.69 8.04 8.26 3.64 1.09 0.22
RENCANA PEKERJAAN PER-MINGGU KOMULATIF - 2.61 2.61 5.95 9.28 17.68 26.07 34.47 42.87 51.27 59.67 68.06 78.76 86.79 95.05 98.69 99.78 100.00
PRESTASI PEKERJAAN PER-MINGGU 6.52 1.25 1.47 1.31 9.14 7.95 9.42 8.07 7.09 12.20 4.65 12.35 5.69 10.28 1.74 0.70 0.17
PRESTASI PEKERJAAN PER-MINGGU KOMULATIF - 6.52 7.77 9.24 10.55 19.69 27.64 37.06 45.12 52.21 64.41 69.06 81.41 87.11 97.39 99.13 99.83 100.00
DEVISIASI 3.91 5.16 3.29 1.27 2.01 1.56 2.58 2.25 0.95 4.75 1.00 2.66 0.31 2.34 0.44 0.04 -
KETERANGAN Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Mendahului Sesuai Schedule

Batang, 12 Oktober 2017

Menyetujui / Mengetahui : Direncanakan Oleh:


KEPALA SMK BHAKTI PRAJA 02 TIM PENGAWAS
KAB. BATANG

MOCH. SODIKIN, S.Pd BAYU ESKA KURNIAWAN, ST


Ketua
120 Hari kalender, SPMK 1 Agustus 2016 Keterangan

Rabu 14-Jun-17 1
Kamis 15-Jun-17 2
Jumat 16-Jun-17 3
Sabtu 17-Jun-17 4 1
Minggu 18-Jun-17 5
Senin 19-Jun-17 6
Selasa 20-Jun-17 7
Rabu 21-Jun-17 8
Kamis 22-Jun-17 9
Jumat 23-Jun-17 10
Sabtu 24-Jun-17 11 2
Minggu 25-Jun-17 12
Senin 26-Jun-17 13
Selasa 27-Jun-17 14
Rabu 28-Jun-17 15
Kamis 29-Jun-17 16
Jumat 30-Jun-17 17
Sabtu 1-Jul-17 18 3
Minggu 2-Jul-17 19
Senin 3-Jul-17 20
Selasa 4-Jul-17 21
Rabu 5-Jul-17 22
Kamis 6-Jul-17 23
Jumat 7-Jul-17 24
Sabtu 8-Jul-17 25 4
Minggu 9-Jul-17 26
Senin 10-Jul-17 27
Selasa 11-Jul-17 28
Rabu 12-Jul-17 29
Kamis 13-Jul-17 30
Jumat 14-Jul-17 31
Sabtu 15-Jul-17 32 5
Minggu 16-Jul-17 33
Senin 17-Jul-17 34
Selasa 18-Jul-17 35
Rabu 19-Jul-17 36
Kamis 20-Jul-17 37
Jumat 21-Jul-17 38
Sabtu 22-Jul-17 39 6
Minggu 23-Jul-17 40
Senin 24-Jul-17 41
Selasa 25-Jul-17 42
Rabu 26-Jul-17 43
Kamis 27-Jul-17 44
Jumat 28-Jul-17 45
Sabtu 29-Jul-17 46 7
Minggu 30-Jul-17 47
Senin 31-Jul-17 48
Selasa 1-Aug-17 49
Rabu 2-Aug-17 50
Kamis 3-Aug-17 51
Jumat 4-Aug-17 52
Sabtu 5-Aug-17 53 8
Minggu 6-Aug-17 54
Senin 7-Aug-17 55
8

Selasa 8-Aug-17 56
Rabu 9-Aug-17 57
Kamis 10-Aug-17 58
Jumat 11-Aug-17 59
Sabtu 12-Aug-17 60 9
Minggu 13-Aug-17 61
Senin 14-Aug-17 62
Selasa 15-Aug-17 63
Rabu 16-Aug-17 64
Kamis 17-Aug-17 65
Jumat 18-Aug-17 66
Sabtu 19-Aug-17 67 10
Minggu 20-Aug-17 68
Senin 21-Aug-17 69
Selasa 22-Aug-17 70
Rabu 23-Aug-17 71
Kamis 24-Aug-17 72
Jumat 25-Aug-17 73
Sabtu 26-Aug-17 74 11
Minggu 27-Aug-17 75
Senin 28-Aug-17 76
Selasa 29-Aug-17 77
Rabu 30-Aug-17 78
Kamis 31-Aug-17 79
Jumat 1-Sep-17 80
Sabtu 2-Sep-17 81 12
Minggu 3-Sep-17 82
Senin 4-Sep-17 83
Selasa 5-Sep-17 84
Rabu 6-Sep-17 85
Kamis 7-Sep-17 86
Jumat 8-Sep-17 87
Sabtu 9-Sep-17 88 13
Minggu 10-Sep-17 89
Senin 11-Sep-17 90
Selasa 12-Sep-17 91
Rabu 13-Sep-17 92
Kamis 14-Sep-17 93
Jumat 15-Sep-17 94
Sabtu 16-Sep-17 95 14
Minggu 17-Sep-17 96
Senin 18-Sep-17 97
Selasa 19-Sep-17 98
Rabu 20-Sep-17 99
Kamis 21-Sep-17 100
Jumat 22-Sep-17 101
Sabtu 23-Sep-17 102 15
Minggu 24-Sep-17 103
Senin 25-Sep-17 104
Selasa 26-Sep-17 105
Rabu 27-Sep-17 106
Kamis 28-Sep-17 107
Jumat 29-Sep-17 108
Sabtu 30-Sep-17 109 16
Minggu 1-Oct-17 110
Senin 2-Oct-17 111
Selasa 3-Oct-17 112
Rabu 4-Oct-17 113
Kamis 5-Oct-17 114
Jumat 6-Oct-17 115
Sabtu 7-Oct-17 116
17
Minggu 8-Oct-17 117
Senin 9-Oct-17 118
Selasa 10-Oct-17 119
Rabu 11-Oct-17 120