WEEKLY

REPORT
PEKERJAAN JASA KONSULTAN UNTUK
PENDAMPINGAN PENYELESAIAN
CME – CONSTRUCTION, MECHANICAL, ELECTRICAL
PEMBANGUNAN KONSTRUKSI MEDIA PILAR
ADVERTISING MRT JAKARTA
OUR TIMELINE MAIN PILLAR
LED 8 LED 1 LED 2 LED 9
PILLAR LED SUDAH SELESAI
KONSTRUKSI 8 KONSTRUKSI 25 KONSTRUKSI 23 KONSTRUKSI 36
WEEK 3
WEEK 1 WEEK 2 WEEK 2 1-39
1,2,3,4,5,6,7,8 1-29 1-29

SP MP AP HP CP FP LP DP

Ikut minggu 3
4S, 4N,
5S, 5N
WEEK 1 WEEK 2 WEEK 3 WEEK 3
1,2,3,8,9, 1-28 1-40 1-4
LED 5 LED 2 LED 9 LED 9
PILLAR LED SUDAH SELESAI PILLAR LED SUDAH SELESAI
KONSTRUKSI 12 KONSTRUKSI 25 KONSTRUKSI 36 KONSTRUKSI 36
PROGRESS MAIN PILLAR

100%
LED
47 TITIK TOTAL 47

67%
KONSTRUKSI
114 TITIK TERHADAP 170

54% 0 25 50 75 100 125 150 170

NON LED
67 TITIK TERHADAP 123
RESUME DOKUMENTASI HASIL SURVEY

Hasil Survey Mayoritas


Base Plate 36x36 berbeda
dengan As Built Drawing
RESUME DOKUMENTASI HASIL SURVEY

???

Pada daftar gambar


Hasil Survey Mayoritas hollow 4x4
As Built Drawing
tidak ada di As Built Drawing
tidak ada notasi
Dilapangan dimensi hollow 4x4
Hollow 4x4
adalah 3,5 - 3,75
THANKS!