RENCANA ANGGARAN BIAYA ( RAB )

PEKERJAAN : RUMAH 2 LANTAI


LOKASI : PALOPO. SUL-SEL
TAHUN ANGGARAN : 2018
HARGA
JUMLAH HARGA
SATUA SATUAN
NO. JENIS PEKERJAAN VOLUME
N ( Rp ) ( Rp )
I PEKERJAAN PERSIAPAN
1 Luas bangunan m2 191.00 0.00 0.00
2 Pengukuran & Bouwplank m1 115.00 79,742.76 9,170,417.40
JUMLAH 9,170,417.40
II PEKERJAAN TANAH DAN PONDASI
1 Pek.Galian Tanah Pondasi m3 96.00 36,400.00 3,494,400.00
2 Urugan Tanah Kembali m 3
38.40 17,450.00 670,080.00
3 Pasir Urug Tanah Pondasi m3 9.60 17,450.00 167,520.00
4 Pondasi Batu Gunung m3 76.80 605,580.00 46,508,544.00
5 Pek.Pasangan Batu Kosong m3 19.20 310,590.00 5,963,328.00
JUMLAH 56,803,872.00
III PEK. STRUKTUR BETON
1 Pondasi Poer m3 8.53 5,943,351.93 50,690,848.65
2 Sloof 30/20 m 3
9.00 3,919,768.47 35,277,916.20
3 Kolom Praktis 10/10 m 3
1.17 6,043,442.46 7,070,827.68
4 Kolom Utama 15/40 m 3
2.52 6,281,979.20 15,830,587.59
5 Pekerjaan Balok utama 25/30 m 3
4.31 7,380,010.01 31,826,293.16
6 Ring Balok 25/15 m 3
1.46 4,395,628.09 6,428,606.08
7 Pek. Meja Beton m 3
0.22 6,626,998.50 1,431,431.68
8 Pek. Tangga Beton m3 4.00 4,996,485.33 19,985,941.30
9 Pek. Plat Lantai Beton m3 9.12 5,043,688.66 45,998,440.56
JUMLAH 214,540,892.89
IV PEK. PASANGAN DINDING BATA
1 Pasangan Dinding Batu Bata m2 854.75 101,094.00 86,410,096.50
2 Plesteran Dinding m 2
### 42,061.00 71,903,279.50
3 Acian Tembok m 2
### 21,182.70 36,211,825.65
4 Pek. Pasangan keramik Batu Alam 30 X 30 m 2
1.10 283,572.00 311,929.20
JUMLAH 194,837,130.85

RUMAH
HARGA
JUMLAH HARGA
SATUA SATUAN
NO. JENIS PEKERJAAN VOLUME
N ( Rp ) ( Rp )
V PEKERJAAN LANTAI DAN KERAMIK DINDING
1 Pek. Urugan Tanah lantai m3 28.65 139,100.00 3,985,215.00
2 Pek.Urugan pasir Lantai m3 38.20 94,100.00 3,594,620.00
3 Pek.rabat beton lantai k100 tebal 7 cm m3
22.31 634,730.00 14,162,413.13
4 Pas. Lantai Keramik tangga 60 x 60 m2
4.00 313,711.00 1,254,844.00
5 Pas. Lantai Keramik 60 x 60 m2
179.00 313,711.00 56,154,269.00
6 Pas Lantai Keramik Teras 60 x 60 m2
165.27 313,711.00 51,847,016.97
7 Pas. Lantai Keramik 20/ 20 KM/WC m2
12.00 174,586.00 2,095,032.00
8 Pas. Dinding Keramik 20/25 KM/WC m2
50.00 145,075.00 7,253,750.00
9 Pas. Dinding Keramik 20/25 DAPUR m2
3.20 145,075.00 464,240.00
10 Pek. Plint Lantai m' 170.95 52,285.17 8,938,149.24
JUMLAH 149,749,549.34
VI PEK. KOSEN PINTU/JENDELA
1 Pas. Kosen Pintu & Jendela+ventilasi Kayu Kelas m' 310.81 99,000.00 30,770,190.00
2 Daun Pintu panil kayu kelas 1 bh 8.00 3,393,300.00 27,146,400.00
3 Daun JENDELA kayu kelas 1 m2
16.00 1,132,900.00 18,126,400.00
3 Pintu KM PVC bh 3.00 252,000.00 756,000.00
4 Kaca Mati BENING 5 mm m2
8.00 136,084.30 1,088,674.40
6 Engsel Pintu psng 16.00 41,032.50 656,520.00
7 Engsel Jendela psng 32.00 32,782.50 1,049,040.00
8 Hak Angin bh 16.00 37,282.50 596,520.00
9 Kunci Pintu 2 x Putar bh 8.00 255,175.00 2,041,400.00
10 Grendel kodok untuk jendela bh 16.00 36,633.50 586,136.00
JUMLAH 82,817,280.40
VII PEKERJAAN KUDA - KUDA ATAP
1 Pek.Kuda-Kuda BAJA RINGAN m2 77.50 190,000.00 14,725,000.00
2 Pekerjaan List Plank m' 19.00 47,095.98 894,823.62
3 Pasangan Atap spandek 0.4 mm m2
77.50 83,220.00 6,449,550.00
4 Pasangan Nok Atap spandek m' 6.50 116,650.00 758,225.00
JUMLAH 22,827,598.62
VIII PEKERJAAN PLAFOND DAN RANGKA
1 Pek. Plafond & rangka m2 191.00 210,331.20 40,173,259.20
3 List Profil sudut Plafond m' 170.95 14,458.30 2,471,646.39
JUMLAH 42,644,905.59
IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan Tembok Dinding dalam m2 ### 25,835.00 30,164,946.00
2 Pek. Pengecatan Tembok Dinding Luar m2
182.25 33,375.00 6,082,593.75
3 Pek. Pengecatan Plafond m2
191.00 23,459.08 4,480,684.28
4 Pek. Pengecatan Kusen & Pintu m2
48.00 39,540.00 1,897,920.00
5 Cat Lisplank m' 19.00 39,540.00 751,260.00
JUMLAH 43,377,404.03

RUMAH
HARGA
JUMLAH HARGA
SATUA SATUAN
NO. JENIS PEKERJAAN VOLUME
N ( Rp ) ( Rp )
X PEKERJAAN INSTALASI LISTRIK
1 Titik Instalasi Lampu ttk 18.00 154,525.00 2,781,450.00
2 Titik Instalasi Stop Kontak ttk 9.00 143,965.00 1,295,685.00
3 Saklar Tunggal bh 8.00 19,000.00 152,000.00
4 Saklar Ganda bh 5.00 25,000.00 125,000.00
5 Stop Kontak bh 9.00 16,500.00 148,500.00
6 Lampu TL.RM 2 x 40 watt bh 0.00 189,000.00 0.00
7 Lampu TL.RM 2 x 20 watt bh 0.00 310,000.00 0.00
8 Lampu pijar 25 watt bh 18.00 8,800.00 158,400.00
9 Fitting Lampu bh 18.00 20,000.00 360,000.00
10 MCB 6 Ampere bh 2.00 85,000.00 170,000.00
11 Box MCB 4 group bh 1.00 75,000.00 75,000.00
JUMLAH 5,266,035.00
XI PEKERJAAN INSTALASI AIR BERSIH/KOTOR
1 Pekerjaan Pemipaan Pipa PVC Type AW Ø.4" m1 21.00 130,931.00 2,749,551.00
2 Pekerjaan Pipa PVC Type AW Ø.3" m1 26.00 95,181.00 2,474,706.00
3 Pekerjaan Pipa PVC Type AW Ø.3/4" m1 30.00 37,331.00 1,119,930.00
4 Pas. Kran Air bh 5.00 56,450.00 282,250.00
5 Pek. Pas. Klosed Duduk bh 3.00 2,564,300.00 7,692,900.00
9 Pas. Floor Drain bh 5.00 151,350.00 756,750.00
10 Pek. Septicktank bh 1.00 2,010,693.38 2,010,693.38
JUMLAH 17,086,780.38
XII PEKERJAAN RAILING TANGGA DAN PEMBERSIHAN
1 Pek. Railing stainles steel m1 10.60 850,000.00 9,010,000.00
2 Pembersihan Lapangan ls 1.00 2,000,000.00 2,000,000.00
JUMLAH 11,010,000.00

RUMAH
4
DAFTAR HARGA BAHAN DAN
DAN UPAH KERJA 2016
HARGA EE
No. JENIS BAHAN SATUAN
( Rp. )

1 Batu Gunung m3 147,000.00


2 Sirtu m3 150,000.00
3 Batu Kali m3 250,000.00
4 Batu pecah (splijt) 2-3 cm m3 250,000.00
5 Pasir Timbunan m3 57,500.00
6 Pasir Pasangan m3 115,000.00
7 Pasir Beton m3 135,000.00
8 Pasir urug m3 95,000.00
9 Kerikil beton m3 182,000.00
10 Batu Bata bh 600.00
11 Paving Blok 8 mm bh 5,000.00
11 Semen Tonasa kg 1,200.00
12 Semen Tonasa @ 50 kg zak 60,900.00
13 Kapur Ayak zak 105,000.00
14 Lem beton zak 41,000.00
15 Semen warna zak 16,000.00
16 Buis Beton 1/2 m' 32,000.00
16 Seng gelombang BWG 28" lbr 39,300.00
17 Spandek /Essar deck 76cm x 0.40mm m2 60,000.00
18 Nok Spandek 0.4mm m1 79,000.00
19 Paku Spandek ( Warna ) bh 500.00
20 Paku Biasa kg 17,233.00
21 Karet pelapis l= 110 cm m' 190,000.00
22 Kayu Klas I (Balok) senso m3 14,600,000.00
23 Kayu Klas II (balok) ex Samarindah m3 4,500,000.00
24 Kayu Klas II (papan) ex Samarindah m3 4,550,000.00
kayu klas I (balok ) m1 49,000.00
25 Kayu Klas I (Balok) bayam m3 12,100,000.00
26 Kayu Klas I (papan) bayam m3 13,300,000.00
27 Kayu Klas III balok m3 3,116,800.00
28 Kayu Klas III papan m3 3,349,500.00
29 Kayu Dolken 4 mm btng 30,000.00
30 Kusen Ventilasi bh 50,000.00
31 Teakwood 4 mm lbr 165,000.00
32 Tripleks 3 mm lbr 52,250.00
33 Multiplex 6 mm lbr 98,200.00
34 Multiplex 9 mm Lbr 120,000.00
35 Multiplex 10 mm Lbr 136,400.00
36 Kawat beton kg 25,000.00
37 Besi Beton kg 13,000.00
38 Besi propil SIKU kg 15,000.00
43 Pipa GIP - MED."A" dia. 6 " btg 1,366,200.00
44 Granite P. graha Type EGYPT RED m2 191,544.73
45 Granite P. graha Type PINK PORINO CN m2 147,729.73
46 Granite P. graha Type CRYSTAL WHITE m2 416,829.73
47 Granite P. graha Type PURE Black m2 0.00
42 Pipa PVC 2" btg 85,000.00
43 Pipa PVC 3" btg 115,000.00
44 Pipa PVC 4" btg 170,000.00
45 Pipa PVC 3/4" EX MASPION btg 26,000.00
46 Coating anti gores lt 0.00
5
HARGA EE
No. JENIS BAHAN SATUAN
( Rp. )
47 Keramik 20/25 m2 58,900.00
48 Keramik 10/20 m2 57,800.00
48 Keramik 20/20 m2 60,000.00
50 Keramik 30/30 m2 60,690.00
51 Keramik 30/30 motif m2 70,000.00
52 Keramik 40/40 warna m2 66,000.00
53 Keramik 60/60 PUTIH m2 192,500.00
Cat tembok MOWILEX INTERIOR kg 56,000.00
Cat tembok MOWILEX EKSTERIOR kg 85,000.00
Cat tembok METROLITE kg 30,708.00
Cat tembok Avitek kg 19,947.00
Cat kayu avian kg 60,500.00
Cat Kayu glotex kg 60,500.00
Politur/teal oil kg 52,800.00
Minyak bekisting ltr 14,500.00
Minyak cat ltr 17,600.00
Cat meni kayu kg 22,000.00
Dempul kayu kg 27,300.00
Plamur kg 4,000.00
Kertas Gosok Lbr 2,700.00
Kaca bening 3 mm m2 88,000.00
Kaca bening 5 mm m2 107,433.00
Kaca rayband 3 mm m2 106,333.00
Kaca rayband 5 mm m2 126,500.00
Kran wastafel set 100,000.00
Stop kran bh 50,000.00
Kran dinding bh 44,000.00
Kloset duduk ex kia set 2,060,000.00
Kitchen Sinc + Kran Leher Angsa set 200,000.00
Wastafel LW 237 Toto + Kran putar lengkap set 250,000.00
Cermin + Rak handuk set 225,000.00
Urinoar Muslim + Kran tekan set 190,000.00
Floor Drain bh 140,000.00
Kabel NYK 2 1/2mm m 2,945.00
pipa 5/8" btg 8,800.00
lampu pijar 25 watt bh 8,800.00
Stop kontak bh 16,500.00
Saklar triple set 45,000.00
Saklar ganda set 25,000.00
Saklar tunggal set 19,000.00
lampu TL 2x20 watt (pakai kap) bh 189,000.00
lampu TL 2x40 watt (pakai kap) bh 310,000.00
fitting bh 20,000.00
MCB 2 group bh 21,000.00
Box MCB 4 group bh 75,000.00
MCB 6 ampere bh 85,000.00
Sekring Box + Arde bh 495,000.00
Engsel pintu bh 24,750.00
Engsel jendela bh 16,500.00
Grendel besar bh 20,350.00
Grendel Jendela bh 20,351.00
Hak angin bh 21,000.00
Expanoglet bh 52,200.00
Kunci Tanam 2 slag SES bh 209,000.00
Kunci Tanam 2 slag bh 68,200.00
Cisa Master key bh 25,000.00
6
HARGA EE
No. JENIS BAHAN SATUAN
( Rp. )
Alluminium holow 1" x 2" warna m' 38,250.00
Kosen All. m' 120,000.00
Bingkai pintu / jendela All. m' 324,000.00
Handle Pintu Kaca bh 22,500.00
List propil Gypsum btg /3 m 25,300.00
List propil kayu 5 cm m' 17,500.00
Wall paper ( merk Baravo ) Rol (100 x 0,50) 22,500.00
Suspension clip PN 223 bh 5,850.00
Suspension rod PN 225 btg 11,250.00
Siku tembak / angle bracket bh 2,700.00
Wall Studs PN 162 M' 58,500.00
Wall Track PN 150 M' 49,500.00
Paper tape 75 m roll 31,500.00
Ramset bh 385.00
Coumpond zak 125,000.00
cotton plaster bh 12,000.00
Gypsum board 9 mm lbr 83,550.00
Mesiu & paku tembak set 13,500.00
7
HARGA EE
No. JENIS BAHAN SATUAN
( Rp. )
Paku beton 1,5 inci bh 2,250.00
Amplas lbr 2,700.00
Screw gypsum 25 mm bh 2,250.00
Hollow steel 4 x 4 btg 43,200.00
Hollow steel 2 x 4 btg 30,000.00
Lisplank Uk.20x2.44x0.9cm lbr 56,000.00
Spandrel Alluminium 10 cm merk Indal, Super x, alex m2 26,250.00
ijuk m2 93,500.00
Pintu kamar mandi pvc bh 252,000.00
Railing stainsteel m1 850,000.00
pintu plat baja ls 8,500,000.00
Rangka baja untuk atap spandek m2 190,000.00

UPAH KERJA

NO. U R A I A N SATUAN JUMLAH

1 Pekerja Hari 80,000.00

2 Mandor Hari 110,000.00

3 Tukang Hari 90,000.00

4 Kepala Tukang Hari 100,000.00


RINGKASAN SPESIFIKASI MATERIAL
BANGUNAN TOWER & BANG. PENGHUBUNG / PERPUSTAKAAN
GEDUNG DPRD PROPINSI SUL SEL

A PEKERJAAN SIPIL / ARSITEKTUR

NO U R A I A N SPESIFIKASI

1 Keramik Lantai K I A , ASIA TILE, IKAD


2 Keramik Dinding K I A , ASIA TILE, IKAD
3 Granit Lantai PERMATA GRAHA PRIMA GEMILANG
4 Granit Dinding PERMATA GRAHA PRIMA GEMILANG
5 Cat Tembok Luar I C I WEATHERSHIELD
6 Cat Tembok Dalam MOWILEX
7 Cat Kayu AVIAN
8 Cat Melamine IMPRA
9 Master key eks. KENARI JAYA
10 Kunci tanam 2 slag SES / YALE
11 Expanoglet MILANO
12 Engsel pintu / Jendela MILANO
13 Daun Pintu NYATOH TULUS DOOR
14 Kuzen Pintu / Jendela INDAL ALL.
15 Bingkai Pintu / Jendela INDAL ALL.
16 Floor hinges DORMA
17 Door closer DORMA
18 Kaca Polos 12 mm & 10 mm TEMPERED (khusus pintu)
19 Kaca Polos 5 mm KACA BIASA
20 Plapon Gypsum + rangka JAYA BOARD
21 Plapon Aqustik + rangka JAYA BOARD
22 Plapon spandril INDAL ALL.
23 Rangka spandril BESI HOLOW
24 Dinding Partisi GYPSUM + WALL PAPER ( BRAVO)
25 Dinding Partisi MULTIPLEKS 9 mm + MELAMINE
26 Railing tangga STAINLESS STELL
27 Railing Outdoor AC STAINLESS STELL
28 Pipa talang GIP MED. A
29 Kuda - kuda, Gording dll RANGKA BAJA RINGAN
30 Rangka atap RANGKA BAJA RINGAN
31 Atap & Bubungan SENG SPANDEK
32 Anjong FIBER + RANGKA BESI
33 Sanitair K I A / TOTO
34 Armatur Lamp ARTOLITE + PHILIPS
35 Water proofing Eks. S I K A

B PEKERJAAN MECANICAL ELECTRICAL

NO U R A I A N SPESIFIKASI

1 LVMDP MERLIN GERIN


2 Kabel - kabel Instalasi TRANGKA , SUPPREME DLL (4 BESAR)
3 Kompenen - komponen Panel MERLIN GERIN
4 Panel Panel SUILITE 1,5 mm
13 Plambing
- Pompa KSB - TORISIMA, GAE
- Valve & Fitting KITAZAWA, TOYO, NBC
- Pipa GIP MEDIUM A
- Pipa MASPION, PVC AW
ERIAL
NG / PERPUSTAKAAN
UL SEL

SPESIFIKASI ALTER.

SES, Tanpa MK

KACA BIASA

BSP + DUCO
ALLUMINIUM HOLOW
TOTO

KETERANGAN

( 4 BESAR )
ANALISA HARGA SATUAN PEKERJAAN

1. ANALISA UNTUK PEKERJAAN PERSIAPAN

1.00 M' PENGUKURAN DAN PEMASANGAN BOUWPLANK


0.012 M3 Kayu kls III @ Rp 3,116,800.00 Rp 37,401.60
0.02 Kg Paku Biasa 2'-5" @ Rp 17,233.00 Rp 344.66
0.007 M3 Kayu Papan kls III @ Rp 3,349,500.00 Rp 23,446.50
0.100 Oh Tukang Kayu @ Rp 90,000.00 Rp 9,000.00
0.100 Oh Pekerja @ Rp 80,000.00 Rp 8,000.00
0.010 Oh Kepala Tukang @ Rp 100,000.00 Rp 1,000.00
0.005 Oh Mandor @ Rp 110,000.00 Rp 550.00
Rp 79,742.76

1.00 M2 PEKERJAAN KANTOR DIREKSI


0.100 M3 Kayu Kls II @ Rp 4,500,000.00 Rp 450,000.00
0.250 Kg Paku @ Rp 17,233.00 Rp 4,308.25
1.100 Lbr Seng Gelombang BJLS 28 (80x180 cm) @ Rp 39,300.00 Rp 43,230.00
1.440 Lbr Triplks 3 mm @ Rp 52,250.00 Rp 75,240.00
5.000 Kg semen PC @ Rp 1,200.00 Rp 6,000.00
0.250 M3 Pasir Pasang @ Rp 115,000.00 Rp 28,750.00
70.000 Bh Bata Merah @ Rp 600.00 Rp 42,000.00
0.020 Ls Peralatan @ Rp 97000 Rp 1,940.00
0.150 Ls Ongkos Pasang @ Rp 105000 Rp 15,750.00
Rp 667,218.25

2. ANALISA UNTUK PEKERJAAN TANAH DAN PONDASI

1.00 M3 GALIAN TANAH


0.400 Oh Pekerja @ Rp 80,000.00 Rp 32,000.00
0.040 Oh Mandor @ Rp 110,000.00 Rp 4,400.00
Rp 36,400.00

1.00 M3 URUGAN KEMBALI


0.192 Oh Pekerja @ Rp 80,000.00 Rp 15,360.00
0.019 Oh Mandor @ Rp 110,000.00 Rp 2,090.00
Rp 17,450.00

1.00 M3 URUGAN
1.200 m3 Pasir urug a Rp. 57,500.00 Rp. 69,000.00
1.200 m3 Sirtu alam " 150,000.00 " 180,000.00
1.200 m3 Tanah urug " 95,000.00 " 114,000.00
0.300 Pekerja " 80,000.00 " 24,000.00
0.010 Mandor " 110,000.00 " 1,100.00
Pasir Timbunan Rp. 94,100.00
Sirtu Rp. 205,100.00
Tanah urug Rp. 139,100.00

1.00 M3 PASANG PONDASI batu gunung 1PC : 4PSR


1.100 m3 Batu Gunung @ Rp 147,000.00 Rp 161,700.00
163.000 kg Semen PC @ Rp 1,200.00 Rp 195,600.00
0.522 m3 Pasir Pasangan @ Rp 115,000.00 Rp 60,030.00
1.500 oh Pekerja @ Rp 80,000.00 Rp 120,000.00
0.075 oh Mandor @ Rp 110,000.00 Rp 8,250.00
0.600 oh Tukang @ Rp 90,000.00 Rp 54,000.00
0.060 oh Kepala Tukang @ Rp 100,000.00 Rp 6,000.00
Rp 605,580.00
1.00 M3 TIMBUNAN
1.200 m3 Pasir urug @ Rp 95,000.00 Rp 114,000.00
0.500 oh Pekerja @ Rp 80,000.00 Rp 40,000.00
0.050 oh Mandor @ Rp 110,000.00 Rp 5,500.00
Rp 159,500.00

1.00 M3 PASANG BATU KOSONG


1.200 m3 Batu Gunung @ Rp 147,000.00 Rp 176,400.00
0.300 m3 Pasir urug @ Rp 95,000.00 Rp 28,500.00
0.780 oh Pekerja @ Rp 80,000.00 Rp 62,400.00
0.039 oh Mandor @ Rp 110,000.00 Rp 4,290.00
0.390 oh Tukang @ Rp 90,000.00 Rp 35,100.00
0.039 oh Kepala Tukang @ Rp 100,000.00 Rp 3,900.00
Rp 310,590.00

3. ANALISA UNTUK PEKERJAAN BETON

1.00 M2 PASANG BEKISTING UNTUK KOLOM


0.040 M3 Kayu Balok Kelas II @ Rp 4,500,000.00 Rp 180,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp 17,233.00 Rp 6,893.20
0.200 Lt Minyak bekisting @ Rp 14,500.00 Rp 2,900.00
0.015 M3 Kayu Balok Kelas III @ Rp 3,116,800.00 Rp 46,752.00
0.350 Lbr Multipleks 9 mm @ Rp 120,000.00 Rp 42,000.00
2.000 Btg Kayu Dolken @ Rp 30,000.00 Rp 60,000.00
0.300 Oh Pekerja @ Rp 80,000.00 Rp 24,000.00
0.330 Oh Tukang @ Rp 90,000.00 Rp 29,700.00
0.033 Oh Kepala tukang @ Rp 100,000.00 Rp 3,300.00
0.006 Oh Mandor @ Rp 110,000.00 Rp 660.00
Rp 396,205.20
1.00 M2 PASANG BEKISTING UNTUK BALOK
0.040 M3 Kayu Balok Kelas II @ Rp 4,500,000.00 Rp 180,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp 17,233.00 Rp 6,893.20
0.200 Lt Minyak bekisting @ Rp 14,500.00 Rp 2,900.00
0.015 M3 Kayu Balok Kelas III @ Rp 3,116,800.00 Rp 46,752.00
0.350 Lbr Multipleks 9 mm @ Rp 120,000.00 Rp 42,000.00
2.000 Btg Kayu Dolken @ Rp 30,000.00 Rp 60,000.00
0.320 Oh Pekerja @ Rp 80,000.00 Rp 25,600.00
0.330 Oh Tukang @ Rp 90,000.00 Rp 29,700.00
0.033 Oh Kepala tukang @ Rp 100,000.00 Rp 3,300.00
0.006 Oh Mandor @ Rp 110,000.00 Rp 660.00
Rp 397,805.20
1.00 M' PASANG BEKISTING UNTUK RING BALOK
0.003 M3 Kayu Papan Kelas III @ Rp 3,349,500.00 Rp 10,048.50
0.020 Kg Paku biasa 2" - 5" @ Rp 17,233.00 Rp 344.66
0.050 Lt Minyak bekisting @ Rp 14,500.00 Rp 725.00
0.100 Oh Pekerja @ Rp 80,000.00 Rp 8,000.00
0.033 Oh Tukang @ Rp 90,000.00 Rp 2,970.00
0.010 Oh Kepala tukang @ Rp 100,000.00 Rp 1,000.00
0.005 Oh Mandor @ Rp 110,000.00 Rp 550.00
Rp 23,638.16
1.00 M2 PASANG BEKISTING UNTUK LANTAI
0.040 M3 Kayu Kelas II (Balok) @ Rp 4,500,000.00 Rp 180,000.00
0.400 Kg Paku biasa 2" - 5" @ Rp 17,233.00 Rp 6,893.20
0.200 Lt Minyak bekisting @ Rp 14,500.00 Rp 2,900.00
0.015 M3 Kayu Kelas III (Balok) @ Rp 3,116,800.00 Rp 46,752.00
0.350 Lbr Multipleks 9 mm @ Rp 120,000.00 Rp 42,000.00
6.000 Btg Kayu Dolken @ Rp 30,000.00 Rp 180,000.00
0.320 Oh Pekerja @ Rp 80,000.00 Rp 25,600.00
0.330 Oh Tukang @ Rp 90,000.00 Rp 29,700.00
0.033 Oh Kepala tukang @ Rp 100,000.00 Rp 3,300.00
0.006 Oh Mandor @ Rp 110,000.00 Rp 660.00
Rp 517,805.20
1.00 M2 Bekisting Tangga
1. Bahan
0.030 m3 Kayu kls II eff. 50 % @ Rp 4,500,000.00 Rp. 67,500.00
0.400 kg Paku 2" - 5" @ Rp 17,233.00 " 6,893.20
0.150 Lt Minyak bekisting @ Rp 14,500.00 " 2,175.00
0.015 m3 Balok kayu eff. 7 @ Rp 4,500,000.00 " 50,625.00
0.350 lbr multipleks 9 mm eff. @ Rp 120,000.00 " 21,000.00
2.000 btg Dolken kayu 0 8 - 10 L= 4 m @ Rp 30,000.00 " 60,000.00
2. Tenaga
0.320 Pekerja @ Rp 80,000.00 " 25,600.00
0.006 Mandor @ Rp 110,000.00 " 660.00
0.330 Tukang kayu @ Rp 90,000.00 " 29,700.00
0.033 Kepala tukang @ Rp 100,000.00 " 3,300.00
Rp. 267,453.20

1. Bahan beton K. 300


0.720 m3 Batu pecah @ Rp 250,000.00 Rp 180,000.00
0.470 m3 Pasir beton @ Rp 135,000.00 Rp 63,450.00
400.000 kg Semen PC @ Rp 1,200.00 Rp 480,000.00
Rp 723,450.00
2. Bahan beton K. 225
0.650 m3 kerikil beton @ Rp 182,000.00 Rp 118,300.00
0.650 m3 Pasir beton @ Rp 135,000.00 Rp 87,750.00
388.000 kg Semen PC @ Rp 1,200.00 Rp 465,600.00
Rp 671,650.00
3. Bahan beton K. 175
0.650 m3 Kerikil beton @ Rp 182,000.00 Rp 118,300.00
0.650 m3 Pasir beton @ Rp 135,000.00 Rp 87,750.00
340.000 kg Semen PC @ Rp 1,200.00 Rp 408,000.00
Rp 614,050.00
4. Bahan beton K. 100
0.450 m3 Kerikil beton @ Rp 182,000.00 Rp 81,900.00
0.650 m3 Pasir beton @ Rp 135,000.00 Rp 87,750.00
247.000 kg Semen PC @ Rp 1,200.00 Rp 296,400.00
Rp 466,050.00
Upah Pengecoran
1.650 Pekerja @ Rp 80,000.00 Rp 132,000.00
0.083 Mandor @ Rp 110,000.00 Rp 9,130.00
0.275 Tukang batu @ Rp 90,000.00 Rp 24,750.00
0.028 Kepala tukang @ Rp 100,000.00 Rp 2,800.00
Rp 168,680.00
1 m3 Beton K300 Rp 892,130.00
1 m3 Beton K225 Rp 840,330.00
1 m3 Beton K175 Rp 782,730.00
1 m3 Beton K100 Rp 634,730.00
C. Pekerjaan Besi U-32/100 Kg
Bahan
110.000 kg Besi Beton @ Rp 13,000.00 Rp 1,430,000.00
2.000 kg Kawat Beton @ Rp 25,000.00 Rp 50,000.00
Rp 1,480,000.00
D. Upah Kerja
2.2500 hr Tukang Besi @ Rp 90,000.00 Rp 202,500.00
3.0000 hr Pekerja @ Rp 80,000.00 Rp 240,000.00
0.2200 hr Mandor @ Rp 110,000.00 Rp 24,200.00
1.0000 hr Kepala Tukang @ Rp 100,000.00 Rp 100,000.00
Rp 566,700.00
Rp
HARGA PEMBESIAN UNTUK MUTU BAJA U32 (C+D) Rp 2,046,700.00
Untuk 1 Kg Besi Rp 20,467.00

E. Alat Bantu / Mollen/Vibrator/Air Bersih @ Rp 10,000 Rp 10,000.00

H. 1 m3 Pekerjaan Stut-werk 10 m2 untuk 1 m3 ( Plat/Kolom/Balok Lantai )


0.550 hr Tukang Kayu @ Rp 90,000.00 Rp 49,500.00
1.000 hr Pekerja @ Rp 80,000.00 Rp 80,000.00
0.100 hr Mandor @ Rp 110,000.00 Rp 11,000.00
0.500 hr Kepala Tukang @ Rp 100,000.00 Rp 50,000.00
0.200 m3 Kayu Klas II @ Rp 4,500,000.00 Rp 900,000.00
5.000 btng Kayu Dolken @ Rp 30,000.00 Rp 150,000.00
1.000 kg Paku @ Rp 17,233.00 Rp 17,233.00
Rp 1,257,733.00
1.00 M2 PASANG BEKISTING UNTUK SLOOF
0.045 M3 Kayu Papan Kelas III @ Rp 3,349,500.00 Rp 150,727.50
0.300 Kg Paku biasa 2" - 5" @ Rp 17,233.00 Rp 5,169.90
0.100 Lt Minyak bekisting @ Rp 14,500.00 Rp 1,450.00
0.300 Oh Pekerja @ Rp 80,000.00 Rp 24,000.00
0.260 Oh Tukang batu @ Rp 90,000.00 Rp 23,400.00
0.026 Oh Kepala tukang @ Rp 100,000.00 Rp 2,600.00
0.005 Oh Mandor @ Rp 110,000.00 Rp 550.00
Rp 207,897.40
1.00 M3 PEKERJAAN PONDASI POER
Beton K. 225 Rp 840,330.00
Besi Beton (1 Kg) 138.75 Kg Rp 2,839,897.83
Bekisting(M2 11.42 ( x Analisa )----------(2 x Pakai) 50% Rp 2,263,124.10
Rp 5,943,351.93

1.00 M3 PEKERJAAN SLOFF 50/30


1.000 m3 Beton K225 @ Rp 840,330.00 Rp 840,330.00
163.870 Pembesian @ Rp 20,467.00 Rp 3,353,927.29
1.000 Peralatan Bantu @ Rp 10,000 Rp 10,000.00
13.330 Cetakan/Mal @ Rp 207,897.40 Rp 1,385,636.17
Rp 5,589,893.46

1.00 M3 PEKERJAAN SLOFF 30/20


Beton K. 225 Rp 840,330.00
Besi Beton (1 Kg) 99.66 Kg Rp 2,039,743.57
Bekisting(M2 10.00 ( x Analisa )----------(2 x Pakai) 50% Rp 1,039,694.90
Rp 3,919,768.47
1.00 M3 PEKERJAAN KOLOM 20/10
1.000 m3 Beton K175 @ Rp 782,730.00 Rp 782,730.00
124.450 Pembesian @ Rp 20,467.00 Rp 2,547,118.15
1.000 Peralatan Bantu @ Rp 10,000 Rp 10,000.00
13.330 Cetakan/Mal @ Rp 396,205.20 Rp 2,640,707.66
0.050 Pekerjaan Stut-Verk @ Rp 1,257,733.00 Rp 62,886.65
Rp 6,043,442.46

1.00 M3 PEKERJAAN KOLOM 35/35


Beton K. 225 Rp 840,330.00
Besi Beton (1 Kg) 155.30 Kg Rp 3,178,525.10
Bekisting(M2 11.42 ( x Analisa )----------(2 x Pakai) 50% Rp 2,263,124.10
Rp 6,281,979.20

1.00 M3 PEKERJAAN BALOK 60/30


Beton K. 225 Rp 840,330.00
Besi Beton (1 Kg) 241.00 Kg Rp 4,932,547.00
Bekisting(M2 8.08 ( x Analisa )----------(2 x Pakai) 50% Rp 1,607,133.01
Rp 7,380,010.01

1.00 M3 PEKERJAAN RINGBALK 35/20


Beton K. 175 Rp 782,730.00
Besi Beton (1 Kg) 166.90 Kg Rp 3,415,874.02
Bekisting(M1 16.67 ( x Analisa )----------(2 x Pakai) 50% Rp 197,024.06
Rp 4,395,628.09

1.00 M3 PEKERJAAN MEJA BETON


Beton K. 175 Rp 782,730.00
Besi Beton (1 Kg) 137.94 Kg Rp 2,823,134.07
Bekisting(M2 11.67 ( x Analisa )----------(2 x Pakai) 50% Rp 3,021,134.44
Rp 6,626,998.50

1.00 M3 PEKERJAAN TANGGA


Beton K. 225 Rp 840,330.00
Besi Beton (1 Kg) 155.24 Kg Rp 3,177,276.61
Bekisting(M2 7.32 ( x Analisa )----------(2 x Pakai) 50% Rp 978,878.71
Rp 4,996,485.33

1.00 M3 PEKERJAAN PLAT LANTAI


Beton K. 225 Rp 840,330.00
Besi Beton (1 Kg) 100.00 Kg Rp 2,046,700.00
Bekisting(M2 8.33 ( x Analisa )----------(2 x Pakai) 50% Rp 2,156,658.66
Rp 5,043,688.66
4. ANALISA UNTUK PEKERJAAN PAS. DINDING BATA

1.00 M2 PASANGAN TEMBOK 1/2 BATA; 1PC : 3PSR


70.000 bh Batu Bata @ Rp 600.00 Rp 42,000.00
14.370 kg Semen PC @ Rp 1,200.00 Rp 17,244.00
0.040 m3 Pasir Pasangan @ Rp 115,000.00 Rp 4,600.00
0.320 Pekerja @ Rp 80,000.00 Rp 25,600.00
0.015 Mandor @ Rp 110,000.00 Rp 1,650.00
0.100 Tukang @ Rp 90,000.00 Rp 9,000.00
0.010 Kepala Tukang @ Rp 100,000.00 Rp 1,000.00
Rp 101,094.00

1.00 M2 PLESTERAN 1 PC : 3 PSR (t=15 mm)


6.480 kg Semen PC @ Rp 1,200.00 Rp 7,776.00
0.019 m3 Pasir Pasangan @ Rp 115,000.00 Rp 2,185.00
0.200 Pekerja @ Rp 80,000.00 Rp 16,000.00
0.010 Mandor @ Rp 110,000.00 Rp 1,100.00
0.150 Tukang @ Rp 90,000.00 Rp 13,500.00
0.015 Kepala Tukang @ Rp 100,000.00 Rp 1,500.00
Rp 42,061.00

1.00 M2 ACIAN TEMBOK / BETON


5.346 kg Semen PC @ Rp 1,200.00 Rp 6,415.20
0.085 Pekerja @ Rp 80,000.00 Rp 6,800.00
0.0043 Mandor @ Rp 110,000.00 Rp 467.50
0.050 Tukang @ Rp 90,000.00 Rp 4,500.00
0.0050 Kepala Tukang @ Rp 100,000.00 Rp 500.00
1.0000 ls Alat Bantu @ Rp 1,500.00 Rp 1,500.00
1.0000 ls langsir Material @ Rp 1,000.00 Rp 1,000.00
Rp 21,182.70

Pek. Penebalan
Beton K. 175 Rp 782,730.00
Bekisting(M2 13.33 ( x Analisa )----------(2 x Pakai) 50% Rp 2,641,103.86
Rp 3,423,833.86

1.00 M2 PASANG KERAMIK BATU ALAM 30 X 30


1.000 M2 KERAMIK 30x 30 Batu Alam @ Rp 70,000.00 Rp 70,000.00
20.000 kg Semen @ Rp 1,200.00 Rp 24,000.00
1.050 Oh Pekerja @ Rp 80,000.00 Rp 84,000.00
1.050 Oh Tukang @ Rp 90,000.00 Rp 94,500.00
0.105 Oh Kepala tukang @ Rp 100,000.00 Rp 10,500.00
0.00520 Oh Mandor @ Rp 110,000.00 Rp 572.00
Rp 283,572.00
5. ANALISA UNTUK PEKERJAAN LANTAI DAN KERAMIK DINDING

1.00 M2 LANTAI KERAMIK


1.050 m2 Keramik 60/60 PUTIH @ Rp 192,500.00 Rp 202,125.00
1.050 m2 Keramik 30/30 @ Rp 60,690.00 Rp 63,724.50
1.050 m2 Keramik 20/20 @ Rp 60,000.00 Rp 63,000.00
1.050 m2 Keramik 40/40 warna @ Rp 66,000.00 Rp 69,300.00
1.050 m2 Keramik kasar 40/40 @ Rp 0.00 Rp 0.00
11.380 kg Semen PC @ Rp 1,200.00 Rp 13,656.00
0.042 m3 Pasir pasang @ Rp 115,000.00 Rp 4,830.00
1.500 kg Semen warna @ Rp 400.00 Rp 600.00

0.620 Pekerja @ Rp 80,000.00 Rp 49,600.00


0.030 Mandor @ Rp 110,000.00 Rp 3,300.00
0.350 Tukang @ Rp 90,000.00 Rp 31,500.00
0.035 Kepala Tukang @ Rp 100,000.00 Rp 3,500.00
0.100 zak AM Grout @ Rp 16,000.00 Rp 1,600.00
1.000 ls Alat Bantu @ Rp 1,000.00 Rp 1,000.00
1.000 ls Langsir Material @ Rp 2,000.00 Rp 2,000.00
Keramik 60/60 PUT Rp 313,711.00
Keramik 30/30 Rp 175,310.50
Keramik 20/20 Rp 174,586.00
Keramik 40/40 war Rp 180,886.00
Plin lantai Rp 52,285.17

1.00 M2 DINDING KERAMIK


1.050 m2 Keramik 20/25 @ Rp 58,900.00 Rp 61,845.00
1.050 m2 Keramik 20/20 @ Rp 60,000.00 Rp 63,000.00
9.300 kg Semen PC @ Rp 1,200.00 Rp 11,160.00
0.018 m3 Pasir pasang @ Rp 115,000.00 Rp 2,070.00
1.500 kg Semen warna @ Rp 400.00 Rp 600.00
0.600 Pekerja @ Rp 80,000.00 Rp 48,000.00
0.030 Mandor @ Rp 110,000.00 Rp 3,300.00
0.100 Tukang @ Rp 90,000.00 Rp 9,000.00
0.045 Kepala Tukang @ Rp 100,000.00 Rp 4,500.00
0.100 zak AM Grout @ Rp 16,000.00 Rp 1,600.00
1.000 ls Alat Bantu @ Rp 1,000.00 Rp 1,000.00
1.000 ls Langsir Material @ Rp 2,000.00 Rp 2,000.00
Keramik 20/25 Rp 145,075.00
Keramik 20/20 Rp 146,230.00

6. ANALISA UNTUK PEKERJAAN KUSEN PINTU & JENDELA

1.00 M' KUZEN PINTU / JENDELA


1.000 m' Kuzen bayam kls 1 @ Rp 49,000.00 Rp 49,000.00
1.000 m' Upah kerja & alat bantu @ Rp 50,000.00 Rp 50,000.00
Rp 99,000.00

1.00 BH PASANG PINTU PANEL KAYU KELAS I


0.400 M3 Kayu Kelas I (Papan) @ Rp 13,300,000.00 Rp 5,320,000.00
1.000 Oh Pekerja @ Rp 80,000.00 Rp 80,000.00
2.500 Oh Tukang kayu @ Rp 90,000.00 Rp 225,000.00
0.250 Oh Kepala tukang @ Rp 100,000.00 Rp 25,000.00
0.050 Oh Mandor @ Rp 110,000.00 Rp 5,500.00
Rp 5,655,500.00
Pintu panel Rp 3,393,300.00
1.00 M2 JENDELA KACA
0.065 m3 Kayu kelas I " 13,300,000.00 " 864,500.00
0.800 Pekerja " 80,000.00 " 64,000.00
0.040 Mandor " 110,000.00 " 4,400.00
2.000 Tukang Kayu " 90,000.00 " 180,000.00
0.200 Kepala Tukang " 100,000.00 " 20,000.00
Rp. 1,132,900.00

1.00 M2 PAS. KACA POLOS


1.100 m2 Kaca 3 mm a Rp. Rp. 0.00
1.100 m2 Kaca 5 mm " 107,433.00 " 118,176.30
0.0165 Pekerja " 80,000.00 " 1,320.00
0.0008 Mandor " 110,000.00 " 88.00
0.165 Tukang " 90,000.00 " 14,850.00
0.0165 Kepala Tukang " 100,000.00 " 1,650.00
1 m2 Kaca 3 mm Rp. 17,908.00
1 m2 Kaca 5 mm Rp. 136,084.30

1.00 BUAH MEMASANG ENGSEL, GRENDEL PINTU / JENDELA


1.000 Bh Engsel Pintu a Rp. 24,750.00 Rp. 24,750.00
1.000 Bh Engsel Jendela Besar " 16,500.00 " 16,500.00
1.000 Bh Engsel Jendela Kecil " 0.00 " 0.00
1.000 Bh Expanoglet " 52,200.00 " 52,200.00
1.000 Bh Grendel Jendela " 20,351.00 " 20,351.00
1.000 Bh Grendel Ventilasi " 20,351.00 " 20,351.00
1.000 Bh Hak Angin (kuningan) " 0.00 " 0.00
0.015 Pekerja " 80,000.00 " 1,200.00
0.00075 Mandor " 110,000.00 " 82.50
0.150 Tukang " 90,000.00 " 13,500.00
0.015 Kepala Tukang " 100,000.00 " 1,500.00
E. Pintu Rp. 41,032.50
E. Jendela besar Rp. 32,782.50
E. Jendela kecil Rp. 16,282.50
Expanoglet Rp. 68,482.50
G. Jendela Rp. 36,633.50
G. Ventilasi Rp. 36,633.50

1.00 BH PASANG KAIT ANGIN


1.000 Bh Kait Angin @ Rp 21,000.00 Rp 21,000.00
0.0150 Oh Pekerja @ Rp 80,000.00 Rp 1,200.00
0.1500 Oh Tukang Kayu @ Rp 90,000.00 Rp 13,500.00
0.0150 Oh Kepala tukang @ Rp 100,000.00 Rp 1,500.00
0.00075 Oh Mandor @ Rp 110,000.00 Rp 82.50
Rp 37,282.50

1.00 BH PASANG KUNCI PINTU


1.000 Bh Kunci Pintu 2x Putar ex ses @ Rp 209,000.00 Rp 209,000.00
1.000 Bh Kunci Bundar Kamar Mandi @ Rp 0.00 Rp 0.00
0.0050 Oh Pekerja @ Rp 80,000.00 Rp 400.00
0.5000 Oh Tukang Kayu @ Rp 90,000.00 Rp 45,000.00
0.0050 Oh Kepala tukang @ Rp 100,000.00 Rp 500.00
0.00250 Oh Mandor @ Rp 110,000.00 Rp 275.00
Jum : A Rp 255,175.00
Jum : B Rp 46,175.00

7. ANALISA UNTUK PEKERJAAN ATAP


1.00 M' PASANG LISPLANK UKURAN 2 x(20 x 2.44) CM, PAPAN SEMEN
0.0145 M3 Lisplank Uk.2x(20x2.44)cm papan semen @ Rp 56,000.00 Rp 812.00
0.060 Kg Paku biasa 2" - 5" @ Rp 17,233.00 Rp 1,033.98
0.150 Oh Pekerja @ Rp 80,000.00 Rp 12,000.00
0.250 Oh Tukang kayu @ Rp 90,000.00 Rp 22,500.00
0.025 Oh Kepala tukang @ Rp 100,000.00 Rp 2,500.00
0.075 Oh Mandor @ Rp 110,000.00 Rp 8,250.00
Rp 47,095.98
1.00 M2 PASANG ATAP SPANDEK
1.050 m2 Atap Spandek @ Rp 60,000.00 " 63,000.00
0.020 bh Paku Spandek (warna) @ Rp 500.00 " 10.00
0.150 Pekerja @ Rp 80,000.00 " 12,000.00
0.006 Mandor @ Rp 110,000.00 " 660.00
0.075 Tukang @ Rp 90,000.00 " 6,750.00
0.008 Kepala Tukang @ Rp 100,000.00 " 800.00
Rp. 83,220.00

1.00 M' PASANG NOK ATAP SPANDEK


1.200 m' Nok Standar @ Rp 79,000.00 " 94,800.00
10.000 bh Paku Spandek (warna) @ Rp 500.00 " 5,000.00
0.100 Pekerja @ Rp 80,000.00 " 8,000.00
0.010 Mandor @ Rp 110,000.00 " 1,100.00
0.075 Tukang @ Rp 90,000.00 " 6,750.00
0.010 Kepala Tukang @ Rp 100,000.00 " 1,000.00
Rp. 116,650.00

8. ANALISA UNTUK PEKERJAAN PLAFOND DAN RANGKA

1.00 M2 PASANG PLAFOND DAN RANGKA


1.4 Btg Hollow 4/4Galvanize @ Rp 43,200.00 Rp 60,480.00
2.1 Btg Hollow 2/4 Galvanize @ Rp 30,000.00 Rp 63,000.00
0.364 Lbr Gypsumboard 9mm @ Rp 83,550.00 Rp 30,412.20
0.11 Kg Paku gypsum @ Rp 100,000.00 Rp 11,000.00
40 Bh Ramset / dynabolt @ Rp 385.00 Rp 15,400.00
0.072 BH Cotton plaster @ Rp 12,000.00 Rp 864.00
0.125 Zak Compoun @ Rp 125,000.00 Rp 15,625.00
0.1 Oh Pekerja @ Rp 80,000.00 Rp 8,000.00
0.05 Oh Tukang @ Rp 90,000.00 Rp 4,500.00
0.005 Oh Kepala Tukang @ Rp 100,000.00 Rp 500.00
0.005 Oh mandor @ Rp 110,000.00 Rp 550.00
Rp 210,331.20

1.00 M' LIST PLAPON


1.050 m' List propil @ Rp 0.00 Rp 0.00
1.050 m' Profil Gypsum @ Rp 8,433.33 Rp 8,855.00
0.100 kg Paku biasa 2 " - 5" @ Rp 17,233.00 Rp 1,723.30
0.021 Pekerja @ Rp 80,000.00 Rp 1,680.00
0.001 Mandor @ Rp 110,000.00 Rp 110.00
0.021 Tukang Kayu @ Rp 90,000.00 Rp 1,890.00
0.002 Kepala Tukang @ Rp 100,000.00 Rp 200.00
Kayu kls.I Rp 5,603.30
Gypsum Rp 14,458.30

9. ANALISA UNTUK PEKERJAAN PENGECATAN

1.00 M2 MENGECAT TEMBOK


0.260 kg Cat tembok MOWILEX INTERIOR @ Rp 56,000.00 Rp 14,560.00
0.260 kg Cat tembok MOWILEX EKSTERIOR @ Rp 85,000.00 Rp 22,100.00
0.260 kg anti lumut/bocor NO DROP @ Rp 150,000.00 Rp 39,000.00
0.100 kg Plamur @ Rp 4,000.00 Rp 400.00
0.100 kg Cat dasar @ Rp 0.00 Rp 0.00
1.000 lbr Kertas Gosok @ Rp 2,700.00 Rp 2,700.00
0.020 Pekerja @ Rp 80,000.00 Rp 1,600.00
0.0025 Mandor @ Rp 110,000.00 Rp 275.00
0.063 Tukang @ Rp 90,000.00 Rp 5,670.00
0.0063 Kepala Tukang @ Rp 100,000.00 Rp 630.00
MOWILEX INTERIOR Rp 25,835.00
MOWILEX EKSTERIOR Rp 33,375.00
anti lumut 75,710.00
1.00 M2 MENGECAT PLAFOND
0.260 kg Cat METROLITE @ Rp 30,708.00 Rp 7,984.08
0.150 kg Plamur @ Rp 4,000.00 Rp 600.00
0.170 kg Cat dasar @ Rp 0.00 Rp 0.00
0.070 Pekerja @ Rp 80,000.00 Rp 5,600.00
0.0025 Mandor @ Rp 110,000.00 Rp 275.00
0.090 Tukang @ Rp 90,000.00 Rp 8,100.00
0.0090 Kepala Tukang @ Rp 100,000.00 Rp 900.00
1 M2 Cat METROLITE Rp 23,459.08

1.00 M2 MENGECAT KAYU


0.260 kg Cat kayu avian @ Rp 60,500.00 Rp 15,730.00
0.150 kg dempul kayu @ Rp 27,300.00 Rp 4,095.00
0.170 kg Cat dasar @ Rp 0.00 Rp 0.00
0.200 kg Cat meni @ Rp 22,000.00 Rp 4,400.00
0.025 ltr Minyak Cat @ Rp 17,600.00 Rp 440.00
0.070 Pekerja @ Rp 80,000.00 Rp 5,600.00
0.0025 Mandor @ Rp 110,000.00 Rp 275.00
0.090 Tukang @ Rp 90,000.00 Rp 8,100.00
0.0090 Kepala Tukang @ Rp 100,000.00 Rp 900.00
1 M2 Cat ICI Rp 39,540.00

10. ANALISA UNTUK PEKERJAAN INSTALASI LISTRIK

Pemasangan Titik Lampu


20.000 Meter Kabel NYK(2x2,5) mm @ Rp 2,945.00 Rp 58,900.00
40.000 Bh Klem Kabel No. 10 @ Rp 75.00 Rp 3,000.00
1.000 Btg Pipa Pvc 5/8" @ Rp 1,400.00 Rp 1,400.00
1.000 Bh Inbow Dos @ Rp 3,000.00 Rp 3,000.00
4.000 Bh Las Dop @ Rp 50.00 Rp 200.00
4.000 Roll Isolasi @ Rp 600.00 Rp 2,400.00
1.000 Bh T - Dos 5/8" @ Rp 125.00 Rp 125.00
1.000 Ls Alat Bantu @ Rp 500.00 Rp 500.00
0.500 Tukang Instalatur @ Rp 90,000.00 Rp 45,000.00
0.500 Pembantu Tukang @ Rp 80,000.00 Rp 40,000.00
Rp 154,525.00

Pemasangan Stop Kontak


12.000 Meter Kabel NYK (2x2,5) mm @ Rp 2,945.00 Rp 35,340.00
20.000 Bh Klem Kabel No. 12 @ Rp 75.00 Rp 1,500.00
2.000 Btg Pipa Pvc 5/8" @ Rp 8,800.00 Rp 17,600.00
1.000 Bh Inbow Dos @ Rp 3,000.00 Rp 3,000.00
6.000 Bh Las Dop @ Rp 50.00 Rp 300.00
1.000 Roll Isolasi @ Rp 600.00 Rp 600.00
1.000 Bh T - Dos 5/8" @ Rp 125.00 Rp 125.00
1.000 Ls Alat Bantu @ Rp 500.00 Rp 500.00
0.500 Tukang Instalatur @ Rp 90,000.00 Rp 45,000.00
0.500 Pembantu Tukang @ Rp 80,000.00 Rp 40,000.00
Rp 143,965.00
11. ANALISA UNTUK PEKERJAAN INSTALASI AIR BERSIH & AIR KOTOR

1.00 BH MEMASANG PIPA PVC


1.200 M' PVC Dia 3" (D) @ Rp 115,000.00 Rp 34,500.00
0.3500 Perlengkapan @ Rp 115,000.00 Rp 40,250.00
1.200 M' PVC Dia 4" (D) @ Rp 170,000.00 Rp 51,000.00
0.3500 Perlengkapan @ Rp 170,000.00 Rp 59,500.00
1.200 M' PVC Dia 3/4" @ Rp 26,000.00 Rp 7,800.00
0.3500 Perlengkapan @ Rp 26,000.00 Rp 9,100.00
1.200 M' PVC Dia 2" @ Rp 85,000.00 Rp 25,500.00
0.3500 Perlengkapan @ Rp 85,000.00 Rp 29,750.00
0.0810 Oh Pekerja @ Rp 80,000.00 Rp 6,480.00
0.1350 Oh Tukang @ Rp 90,000.00 Rp 12,150.00
0.0135 Oh Kepala tukang @ Rp 100,000.00 Rp 1,350.00
0.00410 Oh Mandor @ Rp 110,000.00 Rp 451.00
Jum : PVC 3" Rp 95,181.00
Jum : PVC 4" Rp 130,931.00
Jum : PVC 3/4" Rp 37,331.00
Jum : PVC 2" Rp 75,681.00

1.00 BH MEMASANG KRAN AIR


1.000 Bh Kran Air @ Rp 44,000.00 Rp 44,000.00
0.0250 Set Seal Tape @ Rp 44,000.00 Rp 1,100.00
1.0000 Bh Stop Kran @ Rp 50,000.00 Rp 50,000.00
0.0250 Set Seal Tape @ Rp 50,000.00 Rp 1,250.00
0.0100 Oh Pekerja @ Rp 80,000.00 Rp 800.00
0.1000 Oh Tukang @ Rp 90,000.00 Rp 9,000.00
0.0100 Oh Kepala tukang @ Rp 100,000.00 Rp 1,000.00
0.00500 Oh Mandor @ Rp 110,000.00 Rp 550.00
Jum : A Rp 56,450.00
Jum : B Rp 63,700.00

1.00 BH MEMASANG 1 BUAH KLOSET DUDUK


1.000 bh Kloset Duduk @ Rp 2,060,000.00 Rp 2,060,000.00
0.060 Perlengkapan (6% Harga Kloset) @ Rp Rp 123,600.00
3.300 Pekerja @ Rp 80,000.00 Rp 264,000.00
0.160 Mandor @ Rp 110,000.00 Rp 17,600.00
1.100 Tukang @ Rp 90,000.00 Rp 99,000.00
0.001 Kepala Tukang @ Rp 100,000.00 Rp 100.00
Rp 2,564,300.00

1.00 BH MEMASANG 1 BUAH FLOOR DRAIN


1.000 bh Floor Drain @ Rp 140,000.00 Rp 140,000.00
0.010 Pekerja @ Rp 80,000.00 Rp 800.00
0.005 Mandor @ Rp 110,000.00 Rp 550.00
0.100 Tukang @ Rp 90,000.00 Rp 9,000.00
0.010 Kepala Tukang @ Rp 100,000.00 Rp 1,000.00
Rp 151,350.00

1.00 UNIT SEPTICKTANK DAN PERESAPAN


0.263 M3 Galian Tanah @ Rp 36,400.00 Rp 9,555.00
0.090 M3 Pas. Batu bata @ Rp 101,094.00 Rp 9,098.46
0.065 M3 Pasir Urug @ Rp 95,000.00 Rp 6,175.00
0.050 M3 Urugan Kembali @ Rp 17,450.00 Rp 872.50
0.520 M2 Plester @ Rp 42,061.00 Rp 21,871.72
0.120 M2 Ijuk @ Rp 93,500.00 Rp 11,220.00
0.300 M3 Plat Beton @ Rp 517,805.20 Rp 155,341.56
0.050 M2 Acian Semen Licin @ Rp 21,182.70 Rp 1,059.14
5.000 M1 Pipa Penghawaan @ Rp Ls Rp 50,000.00
0.250 M3 Krikil @ Rp 182,000.00 Rp 45,500.00
10.000 M' PVC Dia 4" (D) + By Pasang + Sambungan @ Rp 170,000.00 Rp 1,700,000.00
Rp 2,010,693.38