Rencana Anggaran Biaya (Rab) : I Pekerjaan Persiapan
Rencana Anggaran Biaya (Rab) : I Pekerjaan Persiapan
RUMAH
HARGA
JUMLAH HARGA
SATUA SATUAN
NO. JENIS PEKERJAAN VOLUME
N ( Rp ) ( Rp )
V PEKERJAAN LANTAI DAN KERAMIK DINDING
1 Pek. Urugan Tanah lantai m3 28.65 139,100.00 3,985,215.00
2 Pek.Urugan pasir Lantai m3 38.20 94,100.00 3,594,620.00
3 Pek.rabat beton lantai k100 tebal 7 cm m3
22.31 634,730.00 14,162,413.13
4 Pas. Lantai Keramik tangga 60 x 60 m2
4.00 313,711.00 1,254,844.00
5 Pas. Lantai Keramik 60 x 60 m2
179.00 313,711.00 56,154,269.00
6 Pas Lantai Keramik Teras 60 x 60 m2
165.27 313,711.00 51,847,016.97
7 Pas. Lantai Keramik 20/ 20 KM/WC m2
12.00 174,586.00 2,095,032.00
8 Pas. Dinding Keramik 20/25 KM/WC m2
50.00 145,075.00 7,253,750.00
9 Pas. Dinding Keramik 20/25 DAPUR m2
3.20 145,075.00 464,240.00
10 Pek. Plint Lantai m' 170.95 52,285.17 8,938,149.24
JUMLAH 149,749,549.34
VI PEK. KOSEN PINTU/JENDELA
1 Pas. Kosen Pintu & Jendela+ventilasi Kayu Kelas m' 310.81 99,000.00 30,770,190.00
2 Daun Pintu panil kayu kelas 1 bh 8.00 3,393,300.00 27,146,400.00
3 Daun JENDELA kayu kelas 1 m2
16.00 1,132,900.00 18,126,400.00
3 Pintu KM PVC bh 3.00 252,000.00 756,000.00
4 Kaca Mati BENING 5 mm m2
8.00 136,084.30 1,088,674.40
6 Engsel Pintu psng 16.00 41,032.50 656,520.00
7 Engsel Jendela psng 32.00 32,782.50 1,049,040.00
8 Hak Angin bh 16.00 37,282.50 596,520.00
9 Kunci Pintu 2 x Putar bh 8.00 255,175.00 2,041,400.00
10 Grendel kodok untuk jendela bh 16.00 36,633.50 586,136.00
JUMLAH 82,817,280.40
VII PEKERJAAN KUDA - KUDA ATAP
1 Pek.Kuda-Kuda BAJA RINGAN m2 77.50 190,000.00 14,725,000.00
2 Pekerjaan List Plank m' 19.00 47,095.98 894,823.62
3 Pasangan Atap spandek 0.4 mm m2
77.50 83,220.00 6,449,550.00
4 Pasangan Nok Atap spandek m' 6.50 116,650.00 758,225.00
JUMLAH 22,827,598.62
VIII PEKERJAAN PLAFOND DAN RANGKA
1 Pek. Plafond & rangka m2 191.00 210,331.20 40,173,259.20
3 List Profil sudut Plafond m' 170.95 14,458.30 2,471,646.39
JUMLAH 42,644,905.59
IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan Tembok Dinding dalam m2 ### 25,835.00 30,164,946.00
2 Pek. Pengecatan Tembok Dinding Luar m2
182.25 33,375.00 6,082,593.75
3 Pek. Pengecatan Plafond m2
191.00 23,459.08 4,480,684.28
4 Pek. Pengecatan Kusen & Pintu m2
48.00 39,540.00 1,897,920.00
5 Cat Lisplank m' 19.00 39,540.00 751,260.00
JUMLAH 43,377,404.03
RUMAH
HARGA
JUMLAH HARGA
SATUA SATUAN
NO. JENIS PEKERJAAN VOLUME
N ( Rp ) ( Rp )
X PEKERJAAN INSTALASI LISTRIK
1 Titik Instalasi Lampu ttk 18.00 154,525.00 2,781,450.00
2 Titik Instalasi Stop Kontak ttk 9.00 143,965.00 1,295,685.00
3 Saklar Tunggal bh 8.00 19,000.00 152,000.00
4 Saklar Ganda bh 5.00 25,000.00 125,000.00
5 Stop Kontak bh 9.00 16,500.00 148,500.00
6 Lampu TL.RM 2 x 40 watt bh 0.00 189,000.00 0.00
7 Lampu TL.RM 2 x 20 watt bh 0.00 310,000.00 0.00
8 Lampu pijar 25 watt bh 18.00 8,800.00 158,400.00
9 Fitting Lampu bh 18.00 20,000.00 360,000.00
10 MCB 6 Ampere bh 2.00 85,000.00 170,000.00
11 Box MCB 4 group bh 1.00 75,000.00 75,000.00
JUMLAH 5,266,035.00
XI PEKERJAAN INSTALASI AIR BERSIH/KOTOR
1 Pekerjaan Pemipaan Pipa PVC Type AW Ø.4" m1 21.00 130,931.00 2,749,551.00
2 Pekerjaan Pipa PVC Type AW Ø.3" m1 26.00 95,181.00 2,474,706.00
3 Pekerjaan Pipa PVC Type AW Ø.3/4" m1 30.00 37,331.00 1,119,930.00
4 Pas. Kran Air bh 5.00 56,450.00 282,250.00
5 Pek. Pas. Klosed Duduk bh 3.00 2,564,300.00 7,692,900.00
9 Pas. Floor Drain bh 5.00 151,350.00 756,750.00
10 Pek. Septicktank bh 1.00 2,010,693.38 2,010,693.38
JUMLAH 17,086,780.38
XII PEKERJAAN RAILING TANGGA DAN PEMBERSIHAN
1 Pek. Railing stainles steel m1 10.60 850,000.00 9,010,000.00
2 Pembersihan Lapangan ls 1.00 2,000,000.00 2,000,000.00
JUMLAH 11,010,000.00
RUMAH
4
DAFTAR HARGA BAHAN DAN
DAN UPAH KERJA 2016
HARGA EE
No. JENIS BAHAN SATUAN
( Rp. )
UPAH KERJA
NO U R A I A N SPESIFIKASI
NO U R A I A N SPESIFIKASI
SPESIFIKASI ALTER.
SES, Tanpa MK
KACA BIASA
BSP + DUCO
ALLUMINIUM HOLOW
TOTO
KETERANGAN
( 4 BESAR )
ANALISA HARGA SATUAN PEKERJAAN
1.00 M3 URUGAN
1.200 m3 Pasir urug a Rp. 57,500.00 Rp. 69,000.00
1.200 m3 Sirtu alam " 150,000.00 " 180,000.00
1.200 m3 Tanah urug " 95,000.00 " 114,000.00
0.300 Pekerja " 80,000.00 " 24,000.00
0.010 Mandor " 110,000.00 " 1,100.00
Pasir Timbunan Rp. 94,100.00
Sirtu Rp. 205,100.00
Tanah urug Rp. 139,100.00
Pek. Penebalan
Beton K. 175 Rp 782,730.00
Bekisting(M2 13.33 ( x Analisa )----------(2 x Pakai) 50% Rp 2,641,103.86
Rp 3,423,833.86