Anda di halaman 1dari 1

REALISASI VOLUME PEKERJAAN MINGGU KE-21 (TGL.

12 S/D 18 NOV 2021)


URAIAN

AC-BC LEVELING BETON KURUS BETON FS' 45


NO TANGGAL
LEBAR PANJANG VOLUME LEBAR PANJANG VOLUME LEBAR PANJANG VOLUME TIKET
KM KM KM
(M1) (M1) TIKET (TON) (M1) (M1) TIKET (M3) (M1) (M1) (M3)

1 12 NOVEMBER 2021 9+525 - 9+480 (KIRI-2) 3,75 45


9+135 - 9+120 (KIRI-2) 3,75 15 79
30+407 - 30+410 (KIRI-2) 3,75 3
(OPRIT AWAL)
30+410 - 30+525 (KIRI-2) 3,75 115 134,5

2 13 NOVEMBER 2021 30+525 - 30+590 (KIRI-2) 3,75 65 78

3 14 NOVEMBER 2021 17+070 - 17+250 (KANAN) 7,6 180 201,32 30+590 - 30+700 (KIRI-2) 3,75 110 130,5

4 15 NOVEMBER 2021 30+700 - 30+750 (KIRI-2) 3,75 50 61,5

5 16 NOVEMBER 2021 13+455 - 13+503 (KIRI-1) 4 48 23+215 - 23+311 (KANAN-1) 4 96 122


13+543 - 13+616 (KIRI-1) 4 73 50

6 17 NOVEMBER 2021 13+455 - 13+440 (KIRI-1) 4 15 6 23+175 - 23+215 (KANAN-1) 4 40 52


13+440 - 13+503 (KIRI-1) 3,75 63 67

7 18 NOVEMBER 2021 23+100 - 23+175 (KANAN-1) 3,85 - 4 75 91


13+555 - 13+655 (KIRI-1) 3,75 112 133,5

SAMPAI DENGAN MINGGU LALU 14.185 7.841,10 2.633 975,40 15.912 18.572,50
MINGGU INI 180 201,32 136 56,00 789 949,00
SAMPAI DENGAN MINGGU INI 14.365 8.042,42 2.769 1.031,40 16.701 19.521,50
TOTAL VOLUME ADENDUM-2 9.428,23 1.517,25 22.123,00
SISA VOLUME ADENDUM-2 - 1.385,81 - 485,85 - 2.601,50