RENCANA ANGGARAN BIAYA ( RAB )

NO URAIAN PEKERJAAN VOLUME KODE HARGA SATUAN JUMLAH HARGA


01 02 03 04 05 06

III PEKERJAAN MEKANIKAL ELEKTRIKAL & PLUMBING


PEKERJAAN TATA UDARA
Pengadaan dan pemasangan unit AC, Indoor + Outdoor dengan asesories
termasuk pondasi, penyangga, pipa refrigent, pipa drain, peredam suara
sesuai standar pabrik
AC SPLIT WALL
1 AC split 1/2 PK + Remote 8,00 Unit 4.335.500,00 34.684.000,00
2 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 8,00 Unit 1.380.000,00 11.040.000,00
3 Pemasangan Dudukan Outdoor & Ongkos Pasang 8,00 Unit 287.500,00 2.300.000,00
4 Instalasi listrik, NYM 3x2.5 mm2 + Pipa Conduit 8,00 Titik 431.250,00 3.450.000,00
5 Stop Kontak 8,00 Unit 143.750,00 1.150.000,00
6 Material Bantu & Testing Commissioning 1,00 Ls 2.760.000,00 2.760.000,00
Sub Jumlah 55.384.000,00
RENCANA ANGGARAN BIAYA ( RAB )

NO URAIAN PEKERJAAN VOLUME KODE HARGA SATUAN JUMLAH HARGA


01 02 03 04 05 06

II PEKERJAAN MEKANIKAL ELEKTRIKAL & PLUMBING


PEKERJAAN TATA UDARA
Pengadaan dan pemasangan unit AC, Indoor + Outdoor dengan asesories
termasuk pondasi, penyangga, pipa refrigent, pipa drain, peredam suara
sesuai standar pabrik
AC SPLIT WALL
1 AC split 1/2 PK + Remote 1,00 Unit 4.335.500,00 4.335.500,00
2 AC split 3/4 PK + Remote 1,00 Unit 4.623.000,00 4.623.000,00
3 AC split 1 PK + Remote 1,00 Unit 5.060.000,00 5.060.000,00
5 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 3,00 Unit 1.380.000,00 4.140.000,00
6 Pemasangan Dudukan Outdoor & Ongkos Pasang 3,00 Unit 287.500,00 862.500,00
7 Instalasi listrik, NYM 3x2.5 mm2 + Pipa Conduit 3,00 Titik 431.250,00 1.293.750,00
8 Stop Kontak 3,00 Unit 143.750,00 431.250,00
9 Material Bantu & Testing Commissioning 1,00 Ls 1.035.000,00 1.035.000,00
Sub Jumlah 21.781.000,00
RENCANA ANGGARAN BIAYA ( RAB )

NO URAIAN PEKERJAAN VOLUME KODE HARGA SATUAN JUMLAH HARGA


01 02 03 04 05 06

III PEKERJAAN TATA UDARA


Pengadaan dan pemasangan unit AC, Indoor + Outdoor dengan asesories
termasuk pondasi, penyangga, pipa refrigent, pipa drain, peredam suara
sesuai standar pabrik
LANTAI 03
AC SPLIT WALL
1 AC split 1/2 PK + Remote 6,00 Unit Taksir 4.335.500,00 26.013.000,00
2 AC split 3/4 PK + Remote 4,00 Unit Taksir 4.623.000,00 18.492.000,00
3 AC split 1 1/2 PK + Remote 18,00 Unit Taksir 6.555.000,00 117.990.000,00
4 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 28,00 Unit Taksir 1.380.000,00 38.640.000,00
5 Pemasangan Dudukan Outdoor & Ongkos Pasang 28,00 Unit Taksir 287.500,00 8.050.000,00
6 Instalasi listrik, NYM 3x2.5 mm2 + Pipa Conduit 28,00 Titik Taksir 431.250,00 12.075.000,00
7 Stop Kontak 28,00 Unit Taksir 143.750,00 4.025.000,00
8 Material Bantu & Testing Commissioning 1,00 Ls Taksir 8.050.000,00 8.050.000,00
-
AC CASSETE -
1 AC Cassete 2 1/2PK + Remote 4,00 Unit Taksir 22.885.000,00 91.540.000,00
2 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 4,00 Unit Taksir 3.162.500,00 12.650.000,00
3 Pemasangan Dudukan Outdoor & Ongkos Pasang 4,00 Unit Taksir 862.500,00 3.450.000,00
4 Instalasi listrik, NYM 4 x 4 mm2 + Pipa Conduit 4,00 Titik Taksir 747.500,00 2.990.000,00
5 Material Bantu & Testing Commissioning 1,00 Ls Taksir 2.530.000,00 2.530.000,00
-
LANTAI ATAP -
AC SPLIT WALL -
1 AC split 3/4 PK + Remote 1,00 Unit 4.623.000,00 4.623.000,00
2 AC split 1 PK + Remote 2,00 Unit 4.692.000,00 9.384.000,00
3 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 3,00 Unit 1.380.000,00 4.140.000,00
4 Pemasangan Dudukan Outdoor & Ongkos Pasang 3,00 Unit 287.500,00 862.500,00
5 Instalasi listrik, NYM 3x2.5 mm2 + Pipa Conduit 3,00 Titik 431.250,00 1.293.750,00
6 Stop Kontak 3,00 Unit 143.750,00 431.250,00
7 Material Bantu & Testing Commissioning 1,00 Ls 1.035.000,00 1.035.000,00

5 Water Heater Kapasitas 15 Liter Terpasang Lengkap dengan Asesories 4,00 Unit 9.250.000,00 37.000.000,00
6 Water Heater Kapasitas 30 Liter Terpasang Lengkap dengan Asesories 7,00 Unit 13.216.500,00 92.515.500,00
Sub Jumlah 497.780.000,00

Jumlah Total 574.945.000,00