Anda di halaman 1dari 4

No ITEM PEKERJAAN TOTAL

1 RAB SERVIS 45,280,000.00


2 RAB PH 17,896,000.00
3 RAB MEP 474,040,000.00
TOTAL 537,216,000.00
RENCANA ANGGARAN BIAYA ( RAB )

NO URAIAN PEKERJAAN VOLUME KODE HARGA SATUAN JUMLAH HARGA


01 02 03 04 05 06

III PEKERJAAN MEKANIKAL ELEKTRIKAL & PLUMBING


PEKERJAAN TATA UDARA
Pengadaan dan pemasangan unit AC, Indoor + Outdoor dengan asesories
termasuk pondasi, penyangga, pipa refrigent, pipa drain, peredam suara
sesuai standar pabrik
AC SPLIT WALL
1 AC split 1/2 PK + Remote 8.00 8.00 Unit 4,530,000.00 36,240,000.00
2 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 8.00 8.00 Unit 550,000.00 4,400,000.00
3 Pemasangan Dudukan Outdoor & Ongkos Pasang 8.00 8.00 Unit 90,000.00 720,000.00
4 Instalasi listrik, NYM 3x2.5 mm2 + Pipa Conduit 8.00 8.00 Titik 300,000.00 2,400,000.00
5 Stop Kontak 8.00 8.00 Unit 65,000.00 520,000.00
6 Material Bantu & Testing Commissioning 1.00 1.00 Ls 1,000,000.00 1,000,000.00
Sub Jumlah 45,280,000.00
RENCANA ANGGARAN BIAYA ( RAB )

NO URAIAN PEKERJAAN VOLUME KODE HARGA SATUAN JUMLAH HARGA


01 02 03 04 05 06

II PEKERJAAN MEKANIKAL ELEKTRIKAL & PLUMBING


PEKERJAAN TATA UDARA
Pengadaan dan pemasangan unit AC, Indoor + Outdoor dengan asesories
termasuk pondasi, penyangga, pipa refrigent, pipa drain, peredam suara
sesuai standar pabrik
AC SPLIT WALL
1 AC split 1/2 PK + Remote 1.00 Unit 4,530,000.00 4,530,000.00
2 AC split 3/4 PK + Remote 1.00 Unit 4,720,000.00 4,720,000.00
3 AC split 1 PK + Remote 1.00 Unit 4,631,000.00 4,631,000.00
5 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 3.00 Unit 550,000.00 1,650,000.00
6 Pemasangan Dudukan Outdoor & Ongkos Pasang 3.00 Unit 90,000.00 270,000.00
7 Instalasi listrik, NYM 3x2.5 mm2 + Pipa Conduit 3.00 Titik 300,000.00 900,000.00
8 Stop Kontak 3.00 Unit 65,000.00 195,000.00
9 Material Bantu & Testing Commissioning 1.00 Ls 1,000,000.00 1,000,000.00
Sub Jumlah 17,896,000.00
RENCANA ANGGARAN BIAYA ( RAB )

NO URAIAN PEKERJAAN VOLUME KODE HARGA SATUAN JUMLAH HARGA


01 02 03 04 05 06

III PEKERJAAN TATA UDARA


Pengadaan dan pemasangan unit AC, Indoor + Outdoor dengan asesories
termasuk pondasi, penyangga, pipa refrigent, pipa drain, peredam suara
sesuai standar pabrik
LANTAI 03
AC SPLIT WALL
1 AC split 1/2 PK + Remote 6.00 Unit Taksir 4,530,000.00 27,180,000.00
2 AC split 3/4 PK + Remote 4.00 Unit Taksir 4,720,000.00 18,880,000.00
3 AC split 1 1/2 PK + Remote 18.00 Unit Taksir 5,764,000.00 103,752,000.00
4 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 28.00 Unit Taksir 550,000.00 15,400,000.00
5 Pemasangan Dudukan Outdoor & Ongkos Pasang 28.00 Unit Taksir 125,000.00 3,500,000.00
6 Instalasi listrik, NYM 3x2.5 mm2 + Pipa Conduit 28.00 Titik Taksir 450,000.00 12,600,000.00
7 Stop Kontak 28.00 Unit Taksir 95,000.00 2,660,000.00
8 Material Bantu & Testing Commissioning 1.00 Ls Taksir 1,500,000.00 1,500,000.00
-
AC CASSETE -
1 AC Cassete 2 1/2PK + Remote 4.00 Unit Taksir 23,044,000.00 92,176,000.00
2 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 4.00 Unit Taksir 5,500,000.00 22,000,000.00
3 Pemasangan Dudukan Outdoor & Ongkos Pasang 4.00 Unit Taksir 550,000.00 2,200,000.00
4 Instalasi listrik, NYM 4 x 4 mm2 + Pipa Conduit 4.00 Titik Taksir 1,700,000.00 6,800,000.00
5 Material Bantu & Testing Commissioning 1.00 Ls Taksir 1,500,000.00 1,500,000.00
-
LANTAI ATAP -
AC SPLIT WALL -
1 AC split 3/4 PK + Remote 1.00 Unit 4,720,000.00 4,720,000.00
2 AC split 1 PK + Remote 2.00 Unit 4,631,000.00 9,262,000.00
3 Pekerjaan Instalasi Pipa Refrigerant & Pipa Drain 3.00 Unit 550,000.00 1,650,000.00
4 Pemasangan Dudukan Outdoor & Ongkos Pasang 3.00 Unit 125,000.00 375,000.00
5 Instalasi listrik, NYM 3x2.5 mm2 + Pipa Conduit 3.00 Titik 450,000.00 1,350,000.00
6 Stop Kontak 3.00 Unit 95,000.00 285,000.00
7 Material Bantu & Testing Commissioning 1.00 Ls 1,500,000.00 1,500,000.00

5 Water Heater Kapasitas 15 Liter Terpasang Lengkap dengan Asesories 4.00 Unit 11,250,000.00 45,000,000.00
6 Water Heater Kapasitas 30 Liter Terpasang Lengkap dengan Asesories 7.00 Unit 14,250,000.00 99,750,000.00
Sub Jumlah 144,750,000.00

Jumlah Total 474,040,000.00