Anda di halaman 1dari 4

REKAPITULASI PEKERJAAN ME

PROYEK: : GUDANG DEPO HARKAN DIV. TIK. POLRI


Lokasi : : JLN. BEKASI TIMUR RAYA N0. 86 CIPINANG KEC. PULO GADUNG
Owner : : TIK POLRI

NO. URAIAN PEKERJAAN BOBOT TOTAL JUMLAH KETERANGAN


%

V. PEKERJAAN MEKANIKAL ###


A PEKERJAAN INSTALASI AIR KOTOR + AIR SISA 8% 16,360,000.00

B PEKERJAAN INSTALASI AIR BERSIH 1% 1,500,000.00

C PEKERJAAN SEPTICTANK 2% 3,837,500.00

VI. PEKERJAAN ELEKTRIKAL ###


A PEKERJAAN INSTALASI PENERANGAN 3% 6,120,000.00

B PEKERJAAN INSTALASI STOP KONTAK 6% 12,600,000.00

C PERALATAN UTAMA 25% 53,508,000.00

VII. PEKERJAAN TATA UDARA ###


A PEKERJAAN INSTALASI TATA UDARA 2% 3,500,000.00

B PEKERJAAN INSTALASI AIR BUANGAN AC 4% 8,400,000.00

C PERALATAN UTAMA 51% 109,400,000.00

TOTAL PEKERJAAN MEKANIKAL 100% 215,225,500.00 ###


I. RAB MEKANIKAL

VOLUME HARGA SAT JUMLAH KETERANGAN


NO. NAMA MATERIAL
Jumlah Sat

###
A PEKERJAAN INSTALASI AIR KOTOR + AIR SISA
SPEK PIPA WAVIN AW
1 Pekerjaan Instalasi air kotor pipa pvc Ø 1/2 " 40.00 m1 25,000.00 1,000,000.00

2 Pekerjaan Instalasi air kotor pipa pvc Ø 4 " DARI KLOSET 40.00 m1 85,000.00 3,400,000.00
PIPA HORISONTAL

3 Pekerjaan Instalasi air SISA pipa pvc Ø 3 " DARI TOILET 40.00 m1 65,000.00 2,600,000.00

4 Pekerjaan Instalasi air HUJAN pipa pvc Ø 3 " 144.00 m1 65,000.00 9,360,000.00

16,360,000.00
JUMLAH A

B PEKERJAAN INSTALASI AIR BERSIH .

1 Pekerjaan Instalasi air bersih pipa PVC Ø 3/4 " 60.00 m1 25,000.00 1,500,000.00

1,500,000.00
JUMLAH B

C PEKERJAAN SEPTICTANK

1 Pekerjaan galian septicank 4.50 m1 75,000.00 337,500.00

2 biofil 1000 liter 1.00 unit 3,500,000.00 3,500,000.00

3,837,500.00
JUMLAH C

TOTAL A,B,C 21,697,500.00


II. RAB ELEKTRIKAL

VOLUME HARGA SAT JUMLAH KETERANGAN


NO. NAMA MATERIAL
Jumlah Sat

###
A PEKERJAAN INSTALASI PENERANGAN
1 LANTAI 1 + LANTAI MEZANINE
1 Pekerjaan Instalasi Penerangan 34.00 ttk 180,000.00 6,120,000.00

6,120,000.00
JUMLAH A

B PEKERJAAN INSTALASI STOP KONTAK


1 LANTAI 1 + LANTAI MEZANINE
1 Pekerjaan Instalasi Stop Kontak 30.00 ttk 180,000.00 5,400,000.00
2 Pekerjaan Instalasi Power Ac 10.00 ttk 180,000.00 1,800,000.00

2 LANTAI 1 + LANTAI MEZANINE


1 Pekerjaan Instalasi Stop Kontak 20.00 ttk 180,000.00 3,600,000.00
2 Pekerjaan Instalasi Power Ac 10.00 ttk 180,000.00 1,800,000.00

12,600,000.00
JUMLAH B

C PERALATAN UTAMA
1 ARMATURE
1 Lampu RM2X36 watt OUTBOW 32.00 bh 350,000.00 11,200,000.00
2 Fitting lampu + bolam 9watt 2.00 bh 55,000.00 110,000.00
3 EMERGENCY LAMP 10.00 bh 150,000.00 1,500,000.00

4 Saklar Tunggal ex. Panasonic setara 2.00 bh 35,000.00 70,000.00


5 Saklar Ganda ex. Pansonic setara 16.00 bh 38,000.00 608,000.00

6 Stop Kontak ex. Panasonic setara 20.00 bh 32,000.00 640,000.00


7 Stop Kontak AC ex. Panasonic setara 10.00 bh 38,000.00 380,000.00

8 Bongkar Pasang Box Panel 1.00 ls 600,000.00 600,000.00


9 Bongkar Pasang Box MCB 1.00 ls 400,000.00 400,000.00
10 Instalasi MCB dan Panel Listrik 1.00 ls 2,500,000.00 2,500,000.00
11 Kabel Tray 112.00 m1 250,000.00 28,000,000.00

12 Penangkal Petir 1.00 lot 7,500,000.00 7,500,000.00

53,508,000.00
JUMLAH C

TOTAL A,B,C 72,228,000.00


.
III. RAB TATA UDARA

VOLUME HARGA SAT JUMLAH


NO. NAMA MATERIAL KETERANGAN
Jumlah Sat

###
A PEKERJAAN INSTALASI TATA UDARA

1 Pekerjaan Instalasi REFRIGENT AC lantai 1 10.00 ttk 350,000.00 3,500,000.00

3,500,000.00
JUMLAH A

B PEKERJAAN INSTALASI AIR BUANGAN AC

1 Pekerjaan Instalasi air buangan AC


1 Pekerjaan Instalasi air buangan pipa pvc Ø 1 " 60.00 m1 65,000.00 3,900,000.00
2 ARMAFLEK 60.00 m1 75,000.00 4,500,000.00

8,400,000.00
JUMLAH B

C PERALATAN UTAMA

1 PENGADAAN UNIT AC 1 PK ex. Daikin 1.00 unit 7,200,000.00 7,200,000.00


2 PENGADAAN UNIT AC 2 PK ex. Daikin 9.00 unit 11,000,000.00 99,000,000.00
3 PENGADAAN FAN GANTUNG 2.00 unit 1,600,000.00 3,200,000.00

109,400,000.00
JUMLAH C

TOTAL A,B,C 121,300,000.00

Anda mungkin juga menyukai