Anda di halaman 1dari 3

RENCANA ANGGARAN BIAYA

NO. ITEM VOLUME SATUAN HARGA SATUAN HARGA TOTAL


1 Balok kayu 1/2 10.00 Btg 45,000.00 450,000.00
2 Balok kayu 2/2 29.50 Btg 60,000.00 1,770,000.00
3 Batu Kali 29.78 M3 300,000.00 8,933,400.00
4 Batu Kosong / Anstamping 6.81 M3 300,000.00 2,041,920.00
5 Besi 12 mm 28.00 Btg 100,000.00 2,800,000.00
6 Besi 8 mm 16.00 Btg 90,000.00 1,440,000.00
7 Besi 6 mm 16.00 Btg 40,000.00 640,000.00
8 Kawat Ikat 5.00 Kg 15,000.00 75,000.00
9 Kerikil 4.34 M3 300,000.00 1,301,158.82
10 Paku 5/12 cm 7.00 Kg 15,000.00 105,000.00
11 Pasir Pasang 15.11 M3 250,000.00 3,777,608.84
12 Pasir Urug 3.70 M3 200,000.00 740,640.00
13 Plywood 6 mm 11.00 Lbr 100,000.00 1,100,000.00
14 Semen 177.00 Zak 55,000.00 9,735,000.00
15
TOTAL HARGA MATERIAL 34,909,727.66
3
1 m beton mutu, f’c = 16,9 MPa (K200), slump (12±2) cm, w/c = 0,61
Manual
Jumlah
No Uraian Kode Satuan Koefisien Volume
(Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja OH OH 1.323 5.89 7.79
2 Tukang batu OH OH 0.189 5.89 1.11
3 Kepala tukang OH OH 0.019 5.89 0.11
4 Mandor OH OH 0.132 5.89 0.78
Jumlah Harga Tenaga Kerja 9.79
B Bahan
1 PC / Portland Cement zak kg 352 5.89 51.83
2 PB / Pasir Beton m3 kg 731 5.89 3.08
3 Kr / Krikil m3 kg 1031 5.89 4.34
4 Air m3 L 215 5.89 1.27
Jumlah Harga Bahan

3
Pasangan Batu Kosong (1 m )

Jumlah
No Uraian Kode Satuan Koefisien Volume
(Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja OH OH 1.000 5.67 5.67
2 Tukang batu OH OH 0.500 5.67 2.84
3 Kepala Tukang OH OH 0.050 5.67 0.28
4 Mandor OH OH 0.100 5.67 0.57
Jumlah Harga Tenaga Kerja 9.36
B Bahan
3
1 Batu/batu belah m3 m 1.200 5.67 6.81
Jumlah Harga Bahan 6.81

Pasangan Batu Kali (1 m3)


Jumlah
No Uraian Kode Satuan Koefisien Volume
(Rp)

1 2 3 4 5 6 7
A Tenaga Kerja
1 Pekerja OH OH 1.000 24.82 24.82
2 Tukang batu OH OH 0.500 24.82 12.41
3 Kepala Tukang OH OH 0.050 24.82 1.24
4 Mandor OH OH 0.100 24.82 2.48
Jumlah Harga Tenaga Kerja 40.94
B Bahan
1 PC / Portland Cement zak kg 202 24.82 125.32
3 3
2 PB / Pasir Beton m m 0.485 24.82 12.04
3 3
3 Batu/batu belah m m 1.200 24.82 29.78
Jumlah Harga Bahan 167.13
BACK UP DATA

NO. ITEM P x L x T x Koef x Jumlah = Jumlah Satuan


1 Pekerjaan Galian Tanah Pondasi Tapak 1.00 x 1.00 x 1.00 x 0.00 x 4.00 = 4.00 M3
Jumlah = 4.00 M3

2 Pekerjaan Galian Tanah Pondasi Menerus 34.00 x 0.80 x 0.31 x 0.00 x 1.00 = 8.43 M3
36.90 x 0.80 x 0.31 x 0.00 x 1.00 = 9.15 M3
Jumlah = 17.58 M3

3 Pekerjaan Pasangan Batu Anstamping 70.90 x 0.80 x 0.10 x 0.00 x 1.00 = 5.67 M3
Jumlah = 5.67 M3

4 Pekerjaan Urugan Pasir Bawah Pondasi 70.90 x 0.80 x 0.05 x 0.00 x 1.00 = 2.84 M3
1.00 x 1.00 x 0.05 x 0.00 x 5.00 = 0.25 M3
Jumlah = 3.09 M3

5 Paasangan Pondasi Batu Kali 70.90 x 1.00 x 0.35 x 0.00 x 1.00 = 24.82 M3
Jumlah = 24.82 M3

6 Pondasi Tapak 1.00 x 1.00 x 0.35 x 0.00 x 5.00 = 1.75 M3


Jumlah = 1.75 M3

7 Kolom pedestal 30/30 0.30 x 0.30 x 2.45 x 0.00 x 5.00 = 1.10 M3


Jumlah = 1.10 M3

8 Sloof 15/20 77.90 x 0.15 x 0.20 x 0.00 x 1.00 = 2.34 M3


Sloof 25/30 8.00 x 0.25 x 0.35 x 0.00 x 1.00 = 0.70 M3
Jumlah = 3.04 M3

9 Besi Sloof 10 mm 78.10 x 0.00 x 0.00 x 0.00 x 4.00 = 312.40 M'


Jumlah = 312.40 M3
1 batang = 12 meter = 27.00 Btg

10 Besi Kolom pedestal 12 mm 3.45 x 0.00 x 0.00 x 6.00 x 5.00 = 103.50 M'
Besi Pondasi Tapak 12 mm 2.45 x 0.00 x 0.00 x 14.00 x 5.00 = 171.500 m'
Besi Sloof 12 mm 8.20 x 0.00 x 0.00 x 6.00 x 1.00 = 49.20 M'
Jumlah = 324.20 M'
1 batang = 12 meter = 28.00 Btg

11 Besi Beugel Sloof 8 mm 0.89 x 0.00 x 0.00 x 0.00 x 54.67 = 49.00 M'
Besi Beugel Kolom 8 mm 1.10 x 0.00 x 0.00 x 0.00 x 122.50 = 135.00 M'
Jumlah = 184.00 M'
1 batang = 12 meter = 16.00 Btg

12 Besi Beugel Sloof 6 mm 0.35 x 0.00 x 0.00 x 0.00 x 520.67 = 183.000 M'
Jumlah = 183.00 M'
1 batang = 12 meter = 16.00 Btg

13 Bekisting Sloof 77.90 x 0.00 x 0.20 x 0.00 x 2.00 = 31.16 M2


8.00 x 0.00 x 0.30 x 0.00 x 2.00 = 4.80 M2
Jumlah = 31.16 M2
Plywood 122 x 244 cm = 11.00 Lbr

Anda mungkin juga menyukai