Uraian Total Swaday Dana Satuan Satuan Swdy + ... Pajak(Rp)
(
a Desa (Rp ) (Rp) Rp )
BAHAN
1 Batu Gunung 45.0 45.0 m3 250,000 1,176,300 11,250,000
2 Pasir Pasang 24.0 24.0 m3 165,000 414,000 3,960,000
3 Semen (PC)-40 kg 147.0 147.0 zak 47,000 722,400 6,909,000
PERALATAN Sub Total 1) 0 2,312,700 22,119,000
Disetujui/Mengesahkan
KEPALA DESA PELAKSANA KEGIATAN
( H.ISBANDI ) ( M.ULYAH )
RENCANA
Disetuju
KEPALA DESA TAJINAN
ANGGARAN BIAYA
No. RAB :
Sumber Dana : Dana Desa
Jenis Kegiatan : TPT
Ukuran/Dimensi : 83 X 0,5 X 0,3 M
Jumlah
5,040,000 - - - 5,040,000
7,740,000 - - - - 7,740,000
750,000 - - - 750,000
250,000 - - - 250,000
1,000,000 - - - - 1,000,000
31,595,500 20,777,400 2,010,900 301,800 - 33,908,200
-
-
-
-
-
-
-
-
-
-
-
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 08 ( TPS Sawah )
Sketsa Perhitungan
RT .04 k
a
l
a
S
.
l
J
JL.Klengkeng
Ke
Puwroeskar
Lokasi TPT Rumah Warga
RT.04
Link ke RAB
Batu 15/20 = 44.77 45.00 -0.23
Pasir Pasang = 23.89 24.00 -0.11
Semen (40 Kg) = 146.97 147.00 -0.03
Pekerja = 84.36 84.00 0.36
Tukang = 36.35 36.00 0.35
RENCANA ANGGARAN BIAYA
Uraian Total Swaday Dana Satuan Satuan Swdy + ... Pajak Dana Desa
a Desa (Rp) (Rp) (Rp) (Rp)
BAHAN
1 Batu Gunung 7.0 7.0 m3 250,000 159,100 1,750,000
2 Pasir Pasang 4.0 4.0 m3 165,000 0 660,000
3 Semen (PC)-40 kg 22.0 22.0 zak 47,000 0 1,034,000
Sub Total 1) 0 159,100 3,444,000
PERALATAN
1 Selang Timbang 20.0 20.0 m 3,500 70,000
2 Benang 2.0 2.0 Roll 7,500 15,000
3 Cangkul 1.0 1.0 bh 60,000 60,000
4 Sekop 2.0 2.0 bh 60,000 120,000
5 Ember 10.0 10.0 bh 10,000 100,000
6 Papan Proyek 1.0 1.0 Ls 150,000 150,000
Sub Total 2) 0 0 515,000
UPAH
1 Pekerja 13.0 13.0 OH 60,000 780,000
2 Tukang 5.0 5.0 OH 75,000 375,000
0 0 1,155,000
OPERASIONAL PK
1 Transport TPK 3.0 0.0 3.0 Org 250,000 750,000
2 Transport Pengawas 1.0 0.0 1.0 Org 250,000 250,000
3 FC + Penggandaan 1.0 0.0 1.0 Ls 47,000 47,000
Sub Total 4) 0 0 1,047,000
TOTAL BIAYA 0 159,100 6,161,000
Sumber Dana dari Biaya 6,161,000
H. ISBANDI NGATENO
→ OK..!
→ OK..!
→ OK..!15,187,400 RAB Lama
8,867,300 Sisa
RENCANA ANGGARAN BIAYA
Propinsi : Jawa Timur No. RAB
Kabupaten : Malang Program
Kecamatan : Tajinan Kegiatan
Desa : Tajinan Volume
URAIAN VOLUME Satuan Harga Satuan Jumlah DPP PPN PPH Psl 22
Mengetahui / Menyetujui :
H. ISBANDI
:
: P3MD Kemendesa PDTT
: TPT RT 24
: 43 m
1,909,100 159,100
660,000 -
1,034,000 -
- 3,603,100 159,100
70,000 -
15,000 -
60,000 -
120,000 -
100,000 -
150,000 -
- 515,000 -
780,000 -
375,000 -
- 1,155,000 -
750,000 -
250,000 -
47,000 -
- 1,047,000 -
- 6,320,100 159,100
Dibuat Oleh :
m Penyusun RKP Desa
Ketua
NGATENO
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 08 ( TPS Sawah )
Sketsa Perhitungan
JL.NANGKA
Rumah Warga
s
i
g
g
n
a
M
.
l
J
RT.24
Link ke RAB
Batu 15/20 = 6.74 7.00 -0.26
Pasir Pasang = 3.65 4.00 -0.35
Semen (40 Kg) = 22.37 22.00 0.37
Pekerja = 13.06 13.00 0.06
Tukang = 5.81 5.00 0.81
RENCANA ANGGARAN BIAYA
Tajinan, 2018
H. ISBANDI NGATENO
RENCANA ANGGARAN BIAYA
Propinsi : Jawa Timur No. RAB
Kabupaten : Malang Program
Kecamatan : Tajinan Kegiatan
Desa : Tajinan Volume
URAIAN VOLUME Satu Harga Satuan Jumlah DPP PPN PPH Psl 22
Total Swadya DD an (Rp) (Rp)
BAHAN
1 Batu Gunung 36.00 36.00 m3 250,000 9,000,000 8,181,800 818,200 122,800
2 Batu Pecah 2/3 1.00 1.00 m3 250,000 250,000 227,200 - -
3 Batako 588.00 588.00 bh 4,000 2,352,000 2,138,100 213,900 32,100
4 Pasir Pasang 21.00 21.00 m3 165,000 3,465,000 3,150,000 315,000 47,300
5 Semen (40 Kg) 134.00 134.00 zak 65,000 8,710,000 7,918,100 791,900 118,800
6 Besi Ø6 27.00 27.00 btg 29,000 783,000 711,800 - -
7 Besi Ø8 56.00 56.00 btg 49,000 2,744,000 2,494,500 249,500 37,500
8 Kawat bendrat 6.00 6.00 kg 47,000 282,000 256,300 - -
Sub Total 1) 27,586,000 25,077,800 2,388,500 358,500
ALAT
1 Selang Timbang 20.00 20.00 m 3,500 70,000 63,600 - -
2 Kereta Dorong 1.00 1.00 bh 500,000 500,000 454,500 - -
3 Benang 2.00 2.00 Roll 7,500 15,000 13,600 - -
4 Ganco 1.00 1.00 bh 75,000 75,000 68,100 - -
5 Cangkul 2.00 2.00 bh 60,000 120,000 109,000 - -
6 Sekop 2.00 2.00 bh 60,000 120,000 109,000 - -
7 Ember 10.00 10.00 bh 10,000 100,000 90,900 - -
8 Kuas 4" 1.00 1.00 bh 25,000 25,000 22,700 - -
9 Prasasti 1.00 1.00 Ls 350,000 350,000 318,100 - -
10 Papan Proyek 1.00 1.00 Ls 150,000 150,000 136,300 - -
UPAH Sub Total 2) 1,525,000 1,385,800 - -
Mengetahui / Menyetujui :
KEPALA DESA
H. ISBANDI
:
: P3MD Kemendesa PDTT
: TPT RT. 08 (TPS Sawah)
: 65 m
250,000 -
2,598,000 246,000
3,827,300 362,300
9,620,700 910,700
783,000 -
3,031,000 287,000
282,000 -
0 30,333,000 2,747,000
70,000 -
500,000 -
15,000 -
75,000 -
120,000 -
120,000 -
100,000 -
25,000 -
350,000 -
150,000 -
- 1,525,000 -
5,070,000 -
2,640,000 -
- 7,710,000 -
750,000 -
250,000 -
73,700 -
- 1,073,700 -
- 40,641,700 2,747,000
Tajinan, 2018
Dibuat Oleh :
Tim Penyusun RKP Desa
Ketua
NGATENO
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 08 ( TPS Sawah )
Sketsa Perhitungan
Purwos
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan Tembok Penahan Tanah ( TPT )
Sketsa Perhitungan
0.25 0.50 0.25 Panjang Saluran : 83 m
2 x 0.30 x 0.40 x 83 = 20 m3
V3 = (1) x 0.15 x 0.30 ) x 83.0
Sketsa Perhitungan
Perhitungan Strikan / Siaran
V 20
2 x 0.30 x 0.40 x 83 = m3
Analisa Kebutuhan Bahan, Alat dan Tenaga Kerja
Link dari
perhitungan selisih pembulatan
volume
di atas tot. volume
Batu 15/20 = 55.69 -0.31 56.00
Uraian Total Swada Dana Satuan Satuan Swdy+ ….. Uang(Rp) ……...
ya ……. (Rp ) (Rp) ( Rp )
BAHAN
1 Batu Gunung 56.0 56.0 m3
2 Pasir Pasang 8.0 8.0 m3
3 Semen (PC)-40 kg 47.0 47.0 zak
PERALATAN Sub Total 1) 0 0 0
Sub Total 4) - - -
TOTAL BIAYA -
Total Biaya (……….. dan Swadaya)
Dimensi / Ukuran (0,6 x 200 ) Bobot Dimensi / Ukuran Bobot JUMLAH TOTAL Bobot
NO URAIAN Jumlah 1 unit % Jumlah % %
No. RAB - No. RAB
……. SWADAYA ……. SWADAYA ……. SWADAYA
I BAHAN 6,426,000 - 6,426,000 -
750,000 750,000 -
250,000 250,000 -
Jumlah 10,121,000 - - 10,121,000 -
Jumlah Total (………..+SWADAYA) 10,121,000 - - 10,121,000 -
Disetujui/Mengesahkan
KEPALA DESA PELAKSANA KEGIATAN
( H.ISBANDI ) ( M.ULYAH )
RENCANA
Disetuju
KEPALA DESA TAJINAN
ANGGARAN BIAYA
No. RAB :
Sumber Dana : Dana Desa
Jenis Kegiatan : TPT
Ukuran/Dimensi : 83 X 0,5 X 0,3 M
Jumlah
540,000 - - - 540,000
840,000 - - - - 840,000
750,000 - - - 750,000
250,000 - - - 250,000
1,000,000 - - - - 1,000,000
9,002,500 6,511,000 400,500 44,400 - 9,447,400
Tajinan, 10 Pebruari 2018
ui / mengesahkan
KETUA PELAKSANA
339,900
105,000
-
444,900
-
-
-
-
-
-
-
-
-
-
-
TAKE OF SHEET
Desa : Tajinan
Kecamatan : Tajinan
Kabupaten : Malang
Sub Kegiatan : Pembangunan TPT RT 04 ( Punden )
Sketsa Perhitungan
Lokasi TPT
RT.06
PUNDEN
JL.KLENGKENG
KeWajak
Rumah Warga
RT.04
An. SNI 6.6.1
An. SNI 024
Link ke RAB
Batu 15/20 = 13.01 13.00 0.01
Pasir Pasang = 7.04 7.00 0.04
Semen (40 Kg) = 43.17 43.00 0.17
Pekerja = 25.21 25.00 0.21
Tukang = 11.21 11.00 0.21