Anda di halaman 1dari 4

RENCANA ANGGARAN BIAYA (RAB)

Kelurahan : Eka Jaya No. RAB : 1


Kecamatan : Paal Merah Nama Kegiatan : ...............
Kota : Jambi Jenis Prasarana : ...............
Propinsi : Jambi Ukuran/dimensi : 1,2 x 0,15 x 170 m'
Tahun : 2023

Volume
Jumlah Dana
URAIAN Harga Satuan Jumlah Biaya
dari Swadaya dari Dana Satuan Swadaya
Total
Masyarakat Biaya
(Rp) (Rp) (Rp)
a b c d=b-c e f g=cxf h=dxf

1. BAHAN
1 Pasir Urug 41.00 41.00 M3 230,000.00 - 9,430,000.00
2 Pasir pasang 60.00 60.00 M3 270,000.00 - 16,200,000.00
3 Split 76.00 76.00 M3 300,000.00 - 22,800,000.00
4 Semen (50 kg) 563.00 563.00 zak 75,000.00 - 42,225,000.00
5 Papan Bekisting 2/20 32.00 32.00 Lembar 30,000.00 - 960,000.00
6 Paku 15.00 15.00 Kg 18,000.00 - 270,000.00
7 Minyak Bekisting 5.00 5.00 Liter 32,400.00 - 162,000.00

Sub Total 1) - 92,047,000.00


2. ALAT
1 Cangkul 2.00 2.00 buah 80,000.00 - 160,000.00
2 Ember cor 15.00 15.00 buah 10,000.00 - 150,000.00
3 Benang nilon 1.00 1.00 Pack 30,000.00 - 30,000.00
4 Sewa Molen 18.00 18.00 Hari 150,000.00 - 2,700,000.00

Sub Total 2) - 3,040,000.00


3. UPAH
1 Pekerja 231.00 231.00 HOK 100,000.00 - 23,100,000.00
2 Tukang 41.00 41.00 HOK 150,000.00 - 6,150,000.00

Sub Total 3) - 29,250,000.00


4. BIAYA OPERASIONAL
1 Papan nama pekerjaan 1.00 1.00 unit 500,000 - 500,000.00
2 Solar non subsidi 108.00 108.00 Liter 14,500.00 - 1,566,000.00
3 Batu prasasti 1.00 1.00 Buah - -

Sub Total 4) - 2,066,000.00


Jumlah 1 + 2 + 3 + 4 - 126,403,000.00

Total Biaya Dari Developer 126,403,000.00


Sumber Dana
Total Dari Biaya Swadaya Masyarakat -
TOTAL BIAYA DIBULATKAN 126,403,000.00
Terbilang : SERATUS DUA PULUH ENAM JUTA EMPAT RATUS TIGA RIBU RUPIAH
Ekajaya, 2 Oktober 2023

Disetujui Oleh: Diajukan Oleh: Dibuat oleh :


Develover an. Warga RT 23 Pelaksana Kegiatan

_________________ __________________ ___________________


Jenis Prasarana : Jalan Rabat Beton
Take Of Sheet Lokasi : Jl. Posos II
Volume : 102 m3
Data ukuran prasarana :
Panjang Jalan = 170
Lebar Jalan rabat beton = 4m
Tebal = 0.15 m

Perhitungan Volume Rekapitulasi Kebutuhan


Luas jalan x tebal beton rabat
170 x 4 x 0.15 = 102.00 m3 A. Bahan
1 Minyak Begesting 5.00 liter
2 Papan ukuran 2/20 32.00 Btng
3 Pasir untuk cor 60.00 m3
4 Pasir Urug 41.00 m3
Perhitungan Analisa Harga Satuan Bahan dan Upah 5 Paku 15.00 kg
6 Semen PC 50 Kg 563.00 Zak
1. Galian tanah ( SNI 2835-2008 hal. 3 ) 7 Split 76.00 m3
170 x 4 x 0.05 = 34.00 m3
B. Upah
Analisa Volume 1 Pekerja 231 HOK
Pekerja = 0.75 x 34.00 = 26 HOK 2 Tukang 41 HOK

2. Perhitungan Volume Pasir urug, tebal 5 cm


170 x 4 x 0.05 = 34.00 m3

Lapisan Pasir Urug 5 cm ( SNI 2835-2008 hal. 4 )


Analisa Volume
Pasir Urug = 1.2 x 34.00 = 41 M3

Pekerja = 0.3 x 34.00 = 10 HOK

3. Beton K-125 ( SNI 7394-2008 hal. 3 )


Analisa Volume
Split = 0.750 x 102.00 = 76 m3
Pasir untuk cor = 0.591 x 102.00 = 60 m3
Semen PC 50 Kg = 5.520 x 102.00 = 563 Zak

Pekerja = 1.650 x 102.00 = 168 HOK


Tukang = 0.275 x 102.00 = 28 HOK

4. Begesting ( SNI 7394-2008 hal. 7 )


Panjang Lebar Jumlah sisi
170 x 0.15 x 2= 51.00 m2

Papan ukuran 2/20 = 0.40 m2


51.00 : 0.40 = 128.00 Btng (1x pakai)
4x pakai = 128.00 : 4 = 32.00 Btng

Hitungan Bekisting selain Papan Beksting


Analisa Volume
Paku = 0.3 x 51.00 = 15 kg
Minyak Begesting = 0.1 x 51.00 = 5 liter

Pekerja = 0.52 x 51.00 = 27 HOK


Tukang = 0.26 x 51.00 = 13 HOK

Dibuat oleh :
HASIL SURVEY HARGA BAHAN / MATERIAL / ALAT

Kelurahan : Eka Jaya No. RAB : 1


Kecamatan : Paal Merah Nama Kegiatan : ...............
Kota : Jambi Jenis Prasarana : ...............
Propinsi : Jambi Ukuran/dimensi : 1,2 x 0,15 x 170 m'
Tahun : 2023

No Nama /Jenis Bahan/Alat Satuan Harga (Rp) Spesifikasi/Keterangan

Bahan :
1 Pasir Urug M3 230,000.00 Tidak mengandung lempung
2 Pasir pasang M3 270,000.00 Kasar
3 Split M3 300,000.00 Kasar, Tajam
4 Semen (50 kg) zak 75,000.00 Padang /Merah Putih /Batu Raja/Tiga Roda
5 Papan Bekisting 2/20 Batang 30,000.00 papan cor
6 Paku Kg 18,000.00
7 Minyak Bekisting Liter 32,400.00

Alat :
8 Cangkul buah 80,000.00
9 Ember cor buah 10,000.00
10 Benang nilon Pack 30,000.00 1 Pack isi 8-10 Roll
11 Molen Hari 150,000.00 Sewa

Keterangan :

1. Harga diatas sudah termasuk PPN


2. Harga diatas sudah termasuk biaya pengiriman

Dibuat oleh :
Pelaksana Kegiatan

___________________
(
HASIL KESEPAKATAN UPAH KERJA

Nama Kegiatan : ........................................................


Desa : ........................................................

No Nama /Jenis Bahan/Alat Satuan Harga (Rp) Spesifikasi

1 Pekerja HOK 100,000.00


2 Tukang HOK 150,000.00

Keterangan :