PEKERJAAN : REHAB ATAP RUANG VIP
LOKASI : RSUD AHMAD RIPIN KABUPATEN MUARO JAMBI
PERENCANA : CV. PASIFIC NUSA CONSULTINDO
TAHUN ANGGARAN : 2019
A PEKERJAAN PENDAHULUAN
JUMLAH A 9,926,000.00
B PEKERJAAN ATAP
1 Pek. Perbaikan Kuda-kuda dan Rangka Atap (Eksisting) 600.12 M2 20,000.00 12,002,400.00
2 Pek. Atap Metal Baja Ringan (Terpasang) 600.12 M2 106,990.40 64,207,078.85
3 Pek. Bubungan Atap Genteng Metal 77.98 M1 89,010.90 6,941,069.98
4 Pek. Lisplank GRC 30 Cm 76.18 M1 52,881.40 4,028,505.05
JUMLAH B 87,179,053.88
C PEKERJAAN LANGIT - LANGIT
1 Pek. Rangka Plafond Hollow 40x40x 3mm Modul 60x60cm 435.20 M2 122,999.80 53,529,512.96
2 Pek. Plafond Gypsum t. 9mm 308.00 M2 46,712.60 14,387,480.80
3 Pek. Plafond GRC t. 4mm Teras/ Luar 127.20 M2 42,148.04 5,361,230.69
JUMLAH C 73,278,224.45
D PEKERJAAN PENGECATAN DAN FINISHING
JUMLAH D 11,414,246.50
Page 4
Keterangan :
- Bongkar Atap + Rangka 100%
- Bongkar Plafond + Rangka Selasar Saja 82%
Page 5
PEKERJAAN : REHAB ATAP RUANG VIP
LOKASI : RSUD AHMAD RIPIN KABUPATEN MUARO JAMBI
PEMBERI KERJA : 0.00
PERENCANA : CV. PASIFIC NUSA CONSULTINDO
TAHUN ANGGARAN : 2019
BACKUP DATA
URAIAN PERHITUNGAN :
PANJANG JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN LEBAR (M) TINGGI (M) Sisi Keliling Jarak (M) Diameter Luas (M2) UNIT KET
(M) (BH)
1 Pek. Cat Dinding Tembok Luar weather shield, Kolom & Balok Timbul
DINDING LUAR TEPI 302.48 M2 95.12 3.18
DIKURANGI JENDELA - 36.56 M2 - 1.58 1.78 13.00
Page 6
PANJANG JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN LEBAR (M) TINGGI (M) Sisi Keliling Jarak (M) Diameter Luas (M2) UNIT KET
(M) (BH)
JUMLAH TOTAL - M2
1 Pek. Cat Papan Lisplank M2
JUMLAH TOTAL - M2
Page 7
PANJANG JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN LEBAR (M) TINGGI (M) Sisi Keliling Jarak (M) Diameter Luas (M2) UNIT KET
(M) (BH)
Page 8
PANJANG JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN LEBAR (M) TINGGI (M) Sisi Keliling Jarak (M) Diameter Luas (M2) UNIT KET
(M) (BH)
Page 9
PANJANG JUMLAH
No. URAIAN PEKERJAAN VOLUME SATUAN LEBAR (M) TINGGI (M) Sisi Keliling Jarak (M) Diameter Luas (M2) UNIT KET
(M) (BH)
Page 10
JUMLAH
NO NAMA ANALISA
HARGA
12 A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87 902,170.37
A.A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),
13 slump (3-6) cm, w/c = 0,87
828,667.62
13 A. A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66 1,151,883.55
14 A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58 1,219,278.39
14 A.4.1.1.8. Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56 1,235,716.56
15 A.4.1.1.17. Pembesian 10 kg dengan besi polos atau besi ulir 163,936.74
15 A.4.1.1.18. Pemasangan 10 kg kabel presstressed polos/strands 158,726.70
16 A.4.1.1.20. Pemasangan 1 m2 bekisting untuk pondasi 185,104.92
16 A.4.1.1.21. Pemasangan 1 m2 bekisting untuk sloof 197,204.92
17 A.4.1.1.22. Pemasangan 1 m2 bekisting untuk kolom 322,803.36
17 A.4.1.1.23. Pemasangan 1 m2 bekisting untuk balok 333,528.36
18 A.4.1.1.24. Pemasangan 1 m2 bekisting untuk lantai 344,803.36
18 A.4.1.1.25. Pemasangan 1 m2 bekisting untuk dinding 335,178.36
19 A.4.1.1.26. Pemasangan 1 m2 bekisting untuk tangga 298,053.36
19 A.4.1.1.27. Pemasangan 1 m2 jembatan untuk pengecoran beton 98,881.20
20 A.4.1.1.28. Membuat 1 m3 pondasi beton bertulang (150 kg besi + bekisting) 4,498,301.94
20 A.4.1.1.29. Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting) 4,597,047.40
21 A.4.1.1.30. Membuat 1 m3 kolom beton bertulang (300 kg besi + bekisting) 8,743,450.76
21 A.4.1.1.31. Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting) 6,737,299.36
22 A.4.1.1.32. Membuat 1 m3 kolom beton bertulang (150 kg besi + bekisting) 5,824,980.70
22 A.4.1.1.33. Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting) 5,730,026.94
23 A.4.1.1.34. Membuat 1 m3 dinding beton bertulang (200 kg besi + bekisting) 6,302,260.36
23 A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm 92,086.17
24 A.4.1.1.36. Membuat 1 m’ ring balok beton bertulang (10 x 15) cm 110,466.29
Page 11
JUMLAH
NO NAMA ANALISA
HARGA
24 A.4.1.1.28.a. Membuat 1 M3 Pondasi Plat Type PT Uk. 40 x 40 Beton K-225; Besi 83 Kg 2,888,461.54
26 A.4.1.1.29.a. Membuat 1 M3 Beton Sloof Uk. 15/20 // Beton K-225 ; Besi 176 Kg 5,090,589.62
27 A.4.1.1.30.a. Membuat 1 M3 Beton Kolom K1 Uk. 30x30 cm // Beton K-225 ; Besi 93 Kg 4,895,912.48
29 A.4.1.1.31.a. Membuat 1 M3 Balok Beton B1 Uk. 20x20 cm // Beton K-225 ; Besi 139 Kg 4,460,712.90
30 A.4.1.1.31.b. Membuat 1 M3 Balok Beton // Beton K-225; Besi 159 Kg 6,494,099.44
30 A.4.1.1.31.c. Membuat 1 M3 Balok Beton BP Uk 13/15 // Beton K-225 ; Besi 252 Kg 12,705,212.18
31 A.4.1.1.31.d. Membuat 1 M3 Balok Beton BG Uk. 13/15 // Beton K-225 ; Besi 252 Kg 12,705,212.18
A.4.1.1.31.e. Membuat 1 M3 Balok Beton RB Uk. 13/20 // Beton K-225 ; Besi 199 Kg 9,013,731.16
A.4.1.1.31.f. Membuat 1 M3 Balok Beton // Beton K-225 ; Besi 223 Kg 7,098,590.10
A.4.1.1.31.G. Membuat 1 M3 Balok Beton // Beton K-225 ; Besi 116 Kg 5,091,793.98
A. 4.4.1.1. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1PC : 2PP 226,511.18
37 A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1PC : 3PP 211,658.62
38 A. 4.4.1.7. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1PC : 2PP 108,786.07
38 A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1PC : 3PP 102,040.57
39 A.4.4.1.9. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1PC :4PP 98,000.93
39 A. 4.4.1.23. Pemasangan 1 m2 dinding terawang (rooster) 12x11x24 campuran 1PC :4PP 391,733.10
Page 12
JUMLAH
NO NAMA ANALISA
HARGA
49 A.4.4.3.54. Pemasangan 1 m2 dinding keramik 20cm x 20cm 230,160.65
49 A.4.4.3.54.a. Pemasangan 1 m2 dinding keramik 20cm x 25cm 253,480.65
50 A.4.4.3.54.b. Pemasangan 1 m2 dinding keramik 20cm x 40cm 241,820.65
50 A.4.4.3.58. Pemasangan 1 m2 dinding batu alam tempel 282,476.84
51 A.4.4.3.63. Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm 56,972.74
Page 13
JUMLAH
NO NAMA ANALISA
HARGA
71 A.4.6.2.18. Pemasangan 1 m2 kaca tebal 8 mm 325,939.68
A.4.6.2.20. Pemasangan 1 m2 kaca cermin tebal 5 mm 231,281.60
71 A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 51,242.40
A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur 108,058.72
72 A.4.7.1.10.a. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 25,468.26
72 A.4.7.1.10.a. Pengecatan 1 m2 tembok baru ANTI LUMUT ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 42,656.86
73 A.4.7.1.11. Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup) 18,982.74
73 A.4.7.1.13. 1 m2 Pengecatan menggunakan water profing 23,182.54
74 A.4.7.1.16. Pengecatan 1 m2 permukaan baja dengan menie besi 28,996.00
74 A.4.7.1.18. Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis 65,962.16
75 A.4.7.1.19. Pengecatan 1 m2 Plafond 23,536.66
Page 14
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
Page 15
A. 2.2.1.4. Pengukuran dan pemasangan 1 m’ Bouwplank
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1000 84,800.00 8,480.00
Tukang Kayu L.02 OH 0.1000 93,200.00 9,320.00
Kepala Tukang L.03 OH 0.0100 107,200.00 1,072.00
Mandor L.04 OH 0.0050 112,000.00 560.00
JUMLAH HARGA TENAGA -------------------- 19,432.00
B BAHAN
Kayu balok 5/7 m3 0.0120 2,200,000.00 26,400.00
Paku 2”-3” Kg 0.0200 17,500.00 350.00
Kayu papan 3/20 m3 0.0070 2,200,000.00 15,400.00
JUMLAH HARGA BAHAN -------------------- 42,150.00
C PERALATAN
-
JUMLAH HARGA PERALATAN -------------------- -
Page 16
A. 2.2.1.14. Pembongkaran 1 m3 dinding tembok bata
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 6.6670 84,800.00 565,361.60
Mandor L.04 0.3330 112,000.00 37,296.00
JUMLAH HARGA TENAGA -------------------- 602,657.60
B BAHAN
-
JUMLAH HARGA BAHAN -------------------- -
C PERALATAN
-
JUMLAH HARGA PERALATAN -------------------- -
Page 17
A.2.3.1.3. Menggali 1 m3 tanah biasa sedalam 3 m
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.0500 84,800.00 89,040.00
Mandor L.04 OH 0.0670 112,000.00 7,504.00
JUMLAH HARGA TENAGA -------------------- 96,544.00
B BAHAN
-
JUMLAH HARGA BAHAN -------------------- -
C PERALATAN
-
JUMLAH HARGA PERALATAN -------------------- -
Page 18
A.2.3.1.6. Menggali 1 m3 tanah lumpur sedalam 1 m
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.2000 84,800.00 101,760.00
Mandor L.04 OH 0.0450 112,000.00 5,040.00
JUMLAH HARGA TENAGA -------------------- 106,800.00
B BAHAN
-
JUMLAH HARGA BAHAN -------------------- -
C PERALATAN
-
JUMLAH HARGA PERALATAN -------------------- -
Page 19
A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah
Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.5000 84,800.00 42,400.00
Mandor L.04 OH 0.0500 112,000.00 5,600.00
JUMLAH HARGA TENAGA -------------------- 48,000.00
B BAHAN
-
JUMLAH HARGA BAHAN -------------------- -
C PERALATAN
-
JUMLAH HARGA PERALATAN -------------------- -
Page 20
A.2.3.1.14. Pengurugan 1 m3 sirtu padat
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2500 84,800.00 21,200.00
Mandor L.04 OH 0.0250 112,000.00 2,800.00
JUMLAH HARGA TENAGA -------------------- 24,000.00
B BAHAN
Sirtu m3 1.2000 90,000.00 108,000.00
JUMLAH HARGA BAHAN -------------------- 108,000.00
C PERALATAN
-
JUMLAH HARGA PERALATAN -------------------- -
Page 21
A.3.2.1. Analisa Harga Satuan Pekerjaan - PONDASI
A.3.2.1.10. Pemasangan 1 m3 pondasi siklop, 60% beton campuran 1SP : 2 PB : 3 Kr dan 40% batu belah
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.4000 84,800.00 288,320.00
Tukang Batu L.02 OH 0.8500 93,200.00 79,220.00
Kepala Tukang L.03 OH 0.0850 107,200.00 9,112.00
Mandor L.04 OH 0.1700 112,000.00 19,040.00
JUMLAH HARGA TENAGA -------------------- 395,692.00
B BAHAN
Batu belah m3 0.4800 350,000.00 168,000.00
Portland Cement (PC) Kg 194.0000 1,381.50 268,011.00
Pasir Beton m3 0.3120 142,500.00 44,460.00
Kerikil (Maks 30 mm) m3 0.4680 325,000.00 152,100.00
Besi beton Kg 126.0000 12,650.00 1,593,900.00
Kawat beton Kg 1.8000 17,000.00 30,600.00
JUMLAH HARGA BAHAN -------------------- 2,257,071.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 22
A.3.2.1.11. Pemasangan 1 m3 pondasi sumuran, diameter 100 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.4000 84,800.00 203,520.00
Tukang Batu L.02 OH 0.8000 93,200.00 74,560.00
Kepala Tukang L.03 OH 0.0800 107,200.00 8,576.00
Mandor L.04 OH 0.1190 112,000.00 13,328.00
JUMLAH HARGA TENAGA -------------------- 299,984.00
B BAHAN
Batu belah m3 0.4500 350,000.00 157,500.00
Portland Cement (PC) Kg 194.0000 1,381.50 268,011.00
Pasir Beton m3 0.3120 142,500.00 44,460.00
Kerikil (Maks 30 mm) m3 0.4680 325,000.00 152,100.00
JUMLAH HARGA BAHAN -------------------- 622,071.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.3.2.1.12. Memasang Cerucuk Kayu Bulat Dia. 8 s/d 15 cm Panjang 3 s/d 4 M/Btg
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0450 84,800.00 3,816.00
Tukang kayu L.03 OH 0.1500 93,200.00 13,980.00
Kepala tukang L.03 OH 0.0120 107,200.00 1,286.40
Mandor L.04 OH 0.0060 112,000.00 672.00
JUMLAH HARGA TENAGA -------------------- 19,754.40
B BAHAN
Kayu Bulat dia. 12 s/d 15 cm Panjang 3 s/d 4 Btg 1.0000 40,000.00 40,000.00
M
Alat Bantu kg 0.1200 20,000.00 2,400.00
JUMLAH HARGA BAHAN -------------------- 42,400.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 23
A.4.1.1. Analisa Harga Satuan Pekerjaan - BETON
A.4.1.1.1. Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.6500 84,800.00 139,920.00
Tukang Batu L.02 OH 0.2750 93,200.00 25,630.00
Kepala Tukang L.03 OH 0.0280 107,200.00 3,001.60
Mandor L.04 OH 0.0830 112,000.00 9,296.00
JUMLAH HARGA TENAGA -------------------- 177,847.60
B BAHAN
Portland Cement (PC) kg 247.0000 1,381.50 341,230.50
Pasir Beton kg 869.0000 101.79 88,451.79
Kerikil (Maks 30 mm) kg 999.0000 180.56 180,375.00
Air Liter 215.0000 150.00 32,250.00
JUMLAH HARGA BAHAN -------------------- 642,307.29
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.A.4.1.1.4. Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100),
slump (3-6) cm, w/c = 0,87
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.2000 84,800.00 101,760.00
Tukang Batu L.02 OH 0.2000 93,200.00 18,640.00
Kepala Tukang L.03 OH 0.0200 107,200.00 2,144.00
Mandor L.04 OH 0.0600 112,000.00 6,720.00
JUMLAH HARGA TENAGA -------------------- 129,264.00
B BAHAN
Portland Cement (PC) kg 230.0000 1,381.50 317,745.00
Pasir Beton kg 893.0000 101.79 90,894.64
Kerikil (Maks 30 mm) kg 1,027.0000 180.56 185,430.56
Air Liter 200.0000 150.00 30,000.00
JUMLAH HARGA BAHAN -------------------- 624,070.20
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 24
A. A.4.1.1.5. Membuat 1 m3 beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.6500 84,800.00 139,920.00
Tukang Batu L.02 OH 0.2750 93,200.00 25,630.00
Kepala Tukang L.03 OH 0.0280 107,200.00 3,001.60
Mandor L.04 OH 0.0830 112,000.00 9,296.00
JUMLAH HARGA TENAGA -------------------- 177,847.60
B BAHAN
Portland Cement (PC) kg 326.0000 1,381.50 450,369.00
Pasir Beton kg 760.0000 101.79 77,357.14
Batu Pecah uk. 2-3 cm ( Split ) kg 1,029.0000 300.63 309,343.13
Air Liter 215.0000 150.00 32,250.00
JUMLAH HARGA BAHAN -------------------- 869,319.27
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.4.1.1.7. Membuat 1 m3 beton mutu f’c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.6500 84,800.00 139,920.00
Tukang Batu L.02 OH 0.2750 93,200.00 25,630.00
Kepala Tukang L.03 OH 0.0280 107,200.00 3,001.60
Mandor L.04 OH 0.0830 112,000.00 9,296.00
JUMLAH HARGA TENAGA -------------------- 177,847.60
B BAHAN
Portland Cement (PC) kg 371.0000 1,381.50 512,536.50
Pasir Beton kg 698.0000 101.79 71,046.43
Batu Pecah uk. 2-3 cm ( Split ) kg 1,047.0000 300.63 314,754.38
Air Liter 215.0000 150.00 32,250.00
JUMLAH HARGA BAHAN -------------------- 930,587.30
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 25
A.4.1.1.8. Membuat 1 m3 beton mutu f’c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.6500 84,800.00 139,920.00
Tukang Batu L.02 OH 0.2750 93,200.00 25,630.00
Kepala Tukang L.03 OH 0.0280 107,200.00 3,001.60
Mandor L.04 OH 0.0830 112,000.00 9,296.00
JUMLAH HARGA TENAGA -------------------- 177,847.60
B BAHAN
Portland Cement (PC) kg 384.0000 1,381.50 530,496.00
Pasir Beton kg 692.0000 101.79 70,435.71
Batu Pecah uk. 2-3 cm ( Split ) kg 1,039.0000 300.63 312,349.38
Air Liter 215.0000 150.00 32,250.00
JUMLAH HARGA BAHAN -------------------- 945,531.09
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 26
E Overhead 10 % x D 14,429.70
F Harga satuan pekerjaan ( D + E ) 158,726.70
Page 27
D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 293,457.60
E Overhead 10 % x D 29,345.76
F Harga satuan pekerjaan ( D + E ) 322,803.36
Page 28
A.4.1.1.23. Pemasangan 1 m2 bekisting untuk balok
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.6600 84,800.00 55,968.00
Tukang Kayu L.02 OH 0.3300 93,200.00 30,756.00
Kepala Tukang L.03 OH 0.0330 107,200.00 3,537.60
Mandor L.04 OH 0.0330 112,000.00 3,696.00
JUMLAH HARGA TENAGA -------------------- 93,957.60
B BAHAN
Kayu kelas III m3 0.0400 2,200,000.00 88,000.00
Paku 5 cm – 12 cm kg 0.4000 17,500.00 7,000.00
Minyak bekisting Liter 0.2000 10,000.00 2,000.00
Balok kayu kelas II m3 0.0180 3,250,000.00 58,500.00
Plywood tebal 9 mm Lbr 0.3500 125,000.00 43,750.00
Dolken kayu Ø 8-10cm –panj 4 m Batang 2.0000 5,000.00 10,000.00
JUMLAH HARGA BAHAN -------------------- 209,250.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 29
A.4.1.1.25. Pemasangan 1 m2 bekisting untuk dinding
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.6600 84,800.00 55,968.00
Tukang Kayu L.02 OH 0.3300 93,200.00 30,756.00
Kepala Tukang L.03 OH 0.0330 107,200.00 3,537.60
Mandor L.04 OH 0.0330 112,000.00 3,696.00
JUMLAH HARGA TENAGA -------------------- 93,957.60
B BAHAN
Kayu kelas III m3 0.0300 2,200,000.00 66,000.00
Paku 5 cm – 12 cm kg 0.4000 17,500.00 7,000.00
Minyak bekisting Liter 0.2000 10,000.00 2,000.00
Balok kayu kelas II m3 0.0200 3,250,000.00 65,000.00
Plywood tebal 9 mm Lbr 0.3500 125,000.00 43,750.00
Dolken kayu Ø 8-10cm –panj 4 m Batang 3.0000 5,000.00 15,000.00
Penjaga jarak bekisting/spacer Buah 4.0000 3,000.00 12,000.00
JUMLAH HARGA BAHAN -------------------- 210,750.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 30
A.4.1.1.27. Pemasangan 1 m2 jembatan untuk pengecoran beton
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1500 84,800.00 12,720.00
Tukang Kayu L.02 OH 0.0500 93,200.00 4,660.00
Kepala Tukang L.03 OH 0.0050 107,200.00 536.00
Mandor L.04 OH 0.0080 112,000.00 896.00
JUMLAH HARGA TENAGA -------------------- 18,812.00
B BAHAN
Kayu kelas III (papan) m3 0.0264 2,200,000.00 58,080.00
Paku 5 cm – 12 cm kg 0.6000 17,500.00 10,500.00
Dolken kayu Ø 8-10cm –panj 4 m Batang 0.5000 5,000.00 2,500.00
JUMLAH HARGA BAHAN -------------------- 71,080.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 31
A.4.1.1.29. Membuat 1 m3 sloof beton bertulang (200 kg besi + bekisting)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 5.6500 84,800.00 479,120.00
Tukang batu L.02 OH 0.2750 93,200.00 25,630.00
Tukang kayu L.02 OH 1.5600 93,200.00 145,392.00
Tukang besi L.02 OH 1.4000 93,200.00 130,480.00
Kepala tukang L.03 OH 0.3230 107,200.00 34,625.60
Mandor L.04 OH 0.2830 112,000.00 31,696.00
JUMLAH HARGA TENAGA --------------------
B BAHAN
Kayu kelas III m3 0.2700 2,200,000.00 594,000.00
Paku 5 cm – 12 cm kg 2.0000 17,500.00 35,000.00
Minyak bekisting Liter 0.6000 10,000.00 6,000.00
Besi beton polos kg 210.0000 12,650.00 2,656,500.00
Kawat beton kg 3.0000 17,000.00 51,000.00
Portland Cement (PC) kg 336.0000 1,381.50 464,184.00
Pasir Beton m3 0.5400 142,500.00 76,950.00
Kerikil (Maks 30 mm) m3 0.8100 325,000.00 263,250.00
Air Liter 215.0000 150.00 32,250.00
JUMLAH HARGA BAHAN -------------------- 4,179,134.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 32
A.4.1.1.31. Membuat 1 m3 balok beton bertulang (200 kg besi + bekisting)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 6.3500 84,800.00 538,480.00
Tukang batu L.02 OH 0.2750 93,200.00 25,630.00
Tukang kayu L.02 OH 1.6500 93,200.00 153,780.00
Tukang besi L.02 OH 1.4000 93,200.00 130,480.00
Kepala tukang L.03 OH 0.3330 107,200.00 35,697.60
Mandor L.04 OH 0.3180 112,000.00 35,616.00
JUMLAH HARGA TENAGA -------------------- 919,683.60
B BAHAN
Kayu kelas III m3 0.3200 2,200,000.00 704,000.00
Paku 5 cm – 12 cm kg 3.2000 17,500.00 56,000.00
Minyak bekisting Liter 1.6000 10,000.00 16,000.00
Besi beton polos kg 210.0000 12,650.00 2,656,500.00
Kawat beton kg 3.0000 17,000.00 51,000.00
Portland Cement (PC) kg 336.0000 1,381.50 464,184.00
Pasir Beton m3 0.5400 142,500.00 76,950.00
Kerikil (Maks 30 mm) m3 0.8100 325,000.00 263,250.00
Kayu kelas II balok m3 0.1400 3,250,000.00 455,000.00
Plywood tebal 9 mm Lembar 2.8000 125,000.00 350,000.00
Dolken kayu Ø 8-10cm –panj 4 m Batang 16.0000 5,000.00 80,000.00
Air Liter 215.0000 150.00 32,250.00
JUMLAH HARGA BAHAN -------------------- 5,205,134.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 33
A.4.1.1.33. Membuat 1 m3 dinding beton bertulang (150 kg besi + bekisting)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 5.3000 84,800.00 449,440.00
Tukang batu L.02 OH 0.2750 93,200.00 25,630.00
Tukang kayu L.02 OH 1.3000 93,200.00 121,160.00
Tukang besi L.02 OH 1.0500 93,200.00 97,860.00
Kepala tukang L.03 OH 0.2620 107,200.00 28,086.40
Mandor L.04 OH 0.2650 112,000.00 29,680.00
JUMLAH HARGA TENAGA -------------------- 751,856.40
B BAHAN
Kayu kelas III m3 0.2400 2,200,000.00 528,000.00
Paku 5 cm – 12 cm kg 3.2000 17,500.00 56,000.00
Minyak bekisting Liter 1.6000 10,000.00 16,000.00
Besi beton polos kg 157.5000 12,650.00 1,992,375.00
Kawat beton kg 2.2500 17,000.00 38,250.00
Portland Cement (PC) kg 336.0000 1,381.50 464,184.00
Pasir Beton m3 0.5400 142,500.00 76,950.00
Kerikil (Maks 30 mm) m3 0.8100 325,000.00 263,250.00
Kayu kelas II balok m3 0.1600 3,250,000.00 520,000.00
Plywood tebal 9 mm Lembar 2.8000 125,000.00 350,000.00
Dolken kayu Ø 8-10cm –panj 4 m Batang 24.0000 5,000.00 120,000.00
Air Liter 215.0000 150.00 32,250.00
JUMLAH HARGA BAHAN -------------------- 4,457,259.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 34
A.4.1.1.35. Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1800 84,800.00 15,264.00
Tukang batu L.02 OH 0.0200 93,200.00 1,864.00
Tukang kayu L.02 OH 0.0200 93,200.00 1,864.00
Tukang besi L.02 OH 0.0200 93,200.00 1,864.00
Kepala tukang L.03 OH 0.0060 107,200.00 643.20
Mandor L.04 OH 0.0090 112,000.00 1,008.00
JUMLAH HARGA TENAGA -------------------- 22,507.20
B BAHAN
Kayu kelas III m3 0.0020 2,200,000.00 4,400.00
Paku 5 cm – 12 cm kg 0.0100 17,500.00 175.00
Besi beton polos kg 3.0000 12,650.00 37,950.00
Kawat beton kg 0.4500 17,000.00 7,650.00
Portland Cement (PC) kg 4.0000 1,381.50 5,526.00
Pasir Beton m3 0.0060 142,500.00 855.00
Batu Pecah uk. 2-3 cm ( Split ) m3 0.0090 481,000.00 4,329.00
Air Liter 2.1500 150.00 322.50
JUMLAH HARGA BAHAN -------------------- 61,207.50
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 35
A.4.1.1.28.a. Membuat 1 M3 Pondasi Plat Type PT Uk. 40 x 40 Beton K-225; Besi 83 Kg
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
- Beton Site Mix (K-225) A. A.4.1.1.6. M3 1.0000 1,219,278.39 1,219,278.39
- Pembesian Tulangan A.4.1.1.17. Kg 83.0000 16,393.67 1,360,674.94
- Begesting Untuk Pondasi A.4.1.1.20. M2 1.6667 185,104.92 308,508.20
Harga satuan pekerjaan 2,888,461.54
A.4.1.1.29.a. Membuat 1 M3 Beton Sloof Uk. 15/20 // Beton K-225 ; Besi 176 Kg
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
- Beton Site Mix (K-225) A. A.4.1.1.6. M3 1.0000 1,219,278.39 1,219,278.39
- Pembesian Tulangan A.4.1.1.17. Kg 176.0000 16,393.67 2,885,286.62
- Begesting Untuk Sloof A.4.1.1.21. M2 5.0000 197,204.92 986,024.60
Harga satuan pekerjaan 5,090,589.62
A.4.1.1.31.a. Membuat 1 M3 Balok Beton B1 Uk. 20x20 cm // Beton K-225 ; Besi 139 Kg
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
- Beton Site Mix (K-225) A. A.4.1.1.6. M3 1.0000 1,219,278.39 1,219,278.39
- Pembesian Tulangan A.4.1.1.17. Kg 96.0000 16,393.67 1,573,792.70
- Begesting Untuk Balok A.4.1.1.23. M2 5.0000 333,528.36 1,667,641.80
Harga satuan pekerjaan 4,460,712.90
A.4.1.1.31.d. Membuat 1 M3 Balok Beton BG Uk. 13/15 // Beton K-225 ; Besi 252 Kg
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
- Beton Site Mix (K-225) A. A.4.1.1.6. M3 1.0000 1,219,278.39 1,219,278.39
- Pembesian Tulangan A.4.1.1.17. Kg 252.0000 16,393.67 4,131,205.85
- Begesting Untuk Balok A.4.1.1.23. M2 22.0513 333,528.36 7,354,727.94
Harga satuan pekerjaan 12,705,212.18
A.4.1.1.31.e. Membuat 1 M3 Balok Beton RB Uk. 13/20 // Beton K-225 ; Besi 199 Kg
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
- Beton Site Mix (K-225) A. A.4.1.1.6. M3 1.0000 1,219,278.39 1,219,278.39
- Pembesian Tulangan A.4.1.1.17. Kg 199.0000 16,393.67 3,262,341.13
- Begesting Untuk Balok A.4.1.1.23. M2 13.5884 333,528.36 4,532,111.64
Harga satuan pekerjaan 9,013,731.16
Page 36
A.4.1.1.31.f. Membuat 1 M3 Balok Beton // Beton K-225 ; Besi 223 Kg
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
- Beton Site Mix (K-225) A. A.4.1.1.6. M3 1.0000 1,219,278.39 1,219,278.39
- Pembesian Tulangan A.4.1.1.17. Kg 223.0000 16,393.67 3,655,789.30
- Begesting Untuk Balok A.4.1.1.23. M2 6.6667 333,528.36 2,223,522.40
Harga satuan pekerjaan 7,098,590.10
Page 37
A.4.2.1.2. Pemasangan 1 M Pipa Besi Galvanis Ø3"
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0300 84,800.00 2,544.00
Tukang Las Konstruksi L.03 OH 0.0300 93,200.00 2,796.00
Kepala tukang L.03 OH 0.0030 107,200.00 321.60
Mandor L.04 OH 0.0015 112,000.00 168.00
JUMLAH HARGA TENAGA -------------------- 5,829.60
B BAHAN
Pipa Galvanis Ø3" M 1.1000 79,166.67 87,083.33
JUMLAH HARGA BAHAN -------------------- 87,083.33
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 38
A.4.2.1.11. Pemasangan 1 m kusen pintu alluminium
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0430 84,800.00 3,646.40
Tukang Khusus Alumunium L.03 OH 0.0430 93,200.00 4,007.60
Kepala tukang L.03 OH 0.0043 107,200.00 460.96
Mandor L.04 OH 0.0021 112,000.00 235.20
JUMLAH HARGA TENAGA -------------------- 8,350.16
B BAHAN
Profil alluminium m 1.1000 75,000.00 82,500.00
Skrup fixer buah 2.0000 250.00 500.00
Sealant Tube 0.0600 30,000.00 1,800.00
JUMLAH HARGA BAHAN -------------------- 84,800.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 39
A.4.2.1.20. Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 120 cm, dinding partisi
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2500 84,800.00 21,200.00
Tukang Besi L.02 OH 0.2500 93,200.00 23,300.00
Kepala Tukang L.03 OH 0.0250 107,200.00 2,680.00
Mandor L.04 OH 0.0130 112,000.00 1,456.00
JUMLAH HARGA TENAGA -------------------- 48,636.00
B BAHAN
Rangka metal hollow 40.40.2 mm M1 3.5000 8,750.00 30,625.00
Assesoris (perkuatan, las dll) Ls 25%xrangka 8,750.00 8,750.00
JUMLAH HARGA BAHAN -------------------- 39,375.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A. 4.4.1.1. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1PC : 2PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.6000 84,800.00 50,880.00
Tukang Batu L.02 OH 0.2000 93,200.00 18,640.00
Kepala Tukang L.03 OH 0.0200 107,200.00 2,144.00
Mandor L.04 OH 0.0300 112,000.00 3,360.00
JUMLAH HARGA TENAGA -------------------- 75,024.00
B BAHAN
Bata merah m3 140.0000 450.00 63,000.00
Portland Cement (PC) Kg 43.5000 1,381.50 60,095.25
Pasir Pasang m3 0.0800 97,500.00 7,800.00
JUMLAH HARGA BAHAN -------------------- 130,895.25
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 40
A. 4.4.1.2. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal 1 batu campuran 1PC : 3PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.6000 84,800.00 50,880.00
Tukang Batu L.02 OH 0.2000 93,200.00 18,640.00
Kepala Tukang L.03 OH 0.0200 107,200.00 2,144.00
Mandor L.04 OH 0.0300 112,000.00 3,360.00
JUMLAH HARGA TENAGA -------------------- 75,024.00
B BAHAN
Bata merah m3 140.0000 450.00 63,000.00
Portland Cement (PC) Kg 32.9500 1,381.50 45,520.43
Pasir Pasang m3 0.0910 97,500.00 8,872.50
JUMLAH HARGA BAHAN -------------------- 117,392.93
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A. 4.4.1.7. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1PC : 2PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 84,800.00 25,440.00
Tukang Batu L.02 OH 0.1000 93,200.00 9,320.00
Kepala Tukang L.03 OH 0.0100 107,200.00 1,072.00
Mandor L.04 OH 0.0150 112,000.00 1,680.00
JUMLAH HARGA TENAGA -------------------- 37,512.00
B BAHAN
Bata merah m3 70.0000 450.00 31,500.00
Portland Cement (PC) Kg 18.9500 1,381.50 26,179.43
Pasir Pasang m3 0.0380 97,500.00 3,705.00
JUMLAH HARGA BAHAN -------------------- 61,384.43
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A. 4.4.1.8. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1PC : 3PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 84,800.00 25,440.00
Tukang Batu L.02 OH 0.1000 93,200.00 9,320.00
Kepala Tukang L.03 OH 0.0100 107,200.00 1,072.00
Mandor L.04 OH 0.0150 112,000.00 1,680.00
JUMLAH HARGA TENAGA -------------------- 37,512.00
B BAHAN
Bata merah m3 70.0000 450.00 31,500.00
Portland Cement (PC) Kg 14.3700 1,381.50 19,852.16
Pasir Pasang m3 0.0400 97,500.00 3,900.00
JUMLAH HARGA BAHAN -------------------- 55,252.16
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 41
A.4.4.1.9. Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1PC :4PP
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 84,800.00 25,440.00
Tukang Batu L.02 OH 0.1000 93,200.00 9,320.00
Kepala Tukang L.03 OH 0.0100 107,200.00 1,072.00
Mandor L.04 OH 0.0150 112,000.00 1,680.00
JUMLAH HARGA TENAGA -------------------- 37,512.00
B BAHAN
Bata merah Bh 70.0000 450.00 31,500.00
Portland Cement (PC) Kg 11.5000 1,381.50 15,887.25
Pasir Pasang m3 0.0430 97,500.00 4,192.50
JUMLAH HARGA BAHAN -------------------- 51,579.75
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 42
F Harga satuan pekerjaan ( D + E ) 64,660.70
Page 43
A.4.4.2.3. Pemasangan 1 m2 plesteran 1PC : 3PP tebal 15mm.
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.3000 84,800.00 25,440.00
Tukang Batu L.03 OH 0.1500 93,200.00 13,980.00
Kepala Tukang L.03 OH 0.0150 107,200.00 1,608.00
Mandor L.04 OH 0.0150 112,000.00 1,680.00
JUMLAH HARGA TENAGA -------------------- 42,708.00
B BAHAN
Portland Cement (PC) Kg 7.7760 1,381.50 10,742.54
Pasir Pasang m3 0.0230 97,500.00 2,242.50
JUMLAH HARGA BAHAN -------------------- 12,985.04
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 44
A.4.4.2.20. Pemasangan 1 m’ plesteran skoning 1PC : 3PP lebar 10 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0800 84,800.00 6,784.00
Tukang Batu L.03 OH 0.4000 93,200.00 37,280.00
Kepala Tukang L.03 OH 0.0400 107,200.00 4,288.00
Mandor L.04 OH 0.0040 112,000.00 448.00
JUMLAH HARGA TENAGA -------------------- 48,800.00
B BAHAN
Portland Cement (PC) Kg 0.5000 1,381.50 690.75
Pasir pasang m3 0.0130 97,500.00 1,267.50
JUMLAH HARGA BAHAN -------------------- 1,958.25
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 45
A.4.4.2.27. Pemasangan 1 m2 acian
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2000 84,800.00 16,960.00
Tukang Batu L.03 OH 0.1000 93,200.00 9,320.00
Kepala Tukang L.03 OH 0.0100 107,200.00 1,072.00
Mandor L.04 OH 0.0100 112,000.00 1,120.00
JUMLAH HARGA TENAGA -------------------- 28,472.00
B BAHAN
Portland Cement (PC) Kg 3.2500 1,381.50 4,489.88
JUMLAH HARGA BAHAN --------------------
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.4.4.3. Analisa Harga Satuan Pekerjaan - PENUTUP LANTAI DAN PENUTUP DINDING
Page 46
D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 185,206.30
E Overhead 10 % x D 18,520.63
F Harga satuan pekerjaan ( D + E ) 203,726.93
Page 47
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 48
JUMLAH HARGA BAHAN -------------------- 15,262.41
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 49
Pasir Pasang M3 0.0180 97,500.00 1,755.00
Semen warna Kg 0.1940 15,000.00 2,910.00
JUMLAH HARGA BAHAN -------------------- 81,112.95
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 50
Batu alam tempel M2 1.1000 125,000.00 137,500.00
Portland Cement (PC) Kg 11.7500 1,381.50 16,232.63
Pasir Pasang M3 0.0350 97,500.00 3,412.50
JUMLAH HARGA BAHAN -------------------- 157,145.13
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 51
A.4.4.3.63. Pemasangan 1 m’ plint kayu tebal 2 cm lebar 10 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1200 84,800.00 10,176.00
Tukang Batu L.02 OH 0.1200 93,200.00 11,184.00
Kepala tukang L.03 OH 0.0120 107,200.00 1,286.40
Mandor L.04 OH 0.0060 112,000.00 672.00
JUMLAH HARGA TENAGA -------------------- 23,318.40
B BAHAN
Papan kayu kelas 1 M3 0.0030 9,200,000.00 27,600.00
Paku/skrup 5cm Kg 0.0500 17,500.00 875.00
JUMLAH HARGA BAHAN -------------------- 28,475.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 52
A.4.5.1.9. Pemasangan 1 m’ list langit-langit kayu profil
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0500 84,800.00 4,240.00
Tukang Kayu L.02 OH 0.0500 93,200.00 4,660.00
Kepala tukang L.03 OH 0.0050 107,200.00 536.00
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 9,772.00
B BAHAN
List kayu profil m 1.0500 10,000.00 10,500.00
Paku kg 0.0100 17,500.00 175.00
JUMLAH HARGA BAHAN -------------------- 10,675.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 53
A.4.5.2. Analisa Harga Satuan Pekerjaan - PENUTUP ATAP
Page 54
A.4.5.2.38. Pemasangan 1 m2 atap seng gelombang
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1200 84,800.00 10,176.00
Tukang Kayu L.03 OH 0.0600 93,200.00 5,592.00
Kepala tukang L.11 OH 0.0060 107,200.00 643.20
Mandor L.15 OH 0.0060 112,000.00 672.00
JUMLAH HARGA TENAGA -------------------- 17,083.20
B BAHAN
Seng gel 3”x6” Lbr 0.7000 30,000.00 21,000.00
Paku Seng Kg 0.0200 20,000.00 400.00
JUMLAH HARGA BAHAN -------------------- 21,400.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 55
A.4.5.2.43. Pemasangan 1 m2 atap spandek (GALVALUME) warna
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1200 84,800.00 10,176.00
Tukang Kayu L.03 OH 0.0600 93,200.00 5,592.00
Kepala tukang L.11 OH 0.0060 107,200.00 643.20
Mandor L.15 OH 0.0060 112,000.00 672.00
JUMLAH HARGA TENAGA -------------------- 17,083.20
B BAHAN
Atap Galvalume Warna Lbr 0.8130 46,000.00 37,398.37
Skrup Ulir Bh 10.0000 250.00 2,500.00
JUMLAH HARGA BAHAN -------------------- 39,898.37
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 7.0000 84,800.00 593,600.00
Tukang kayu L.03 OH 21.0000 93,200.00 1,957,200.00
Kepala tukang L.03 OH 2.1000 107,200.00 225,120.00
Mandor L.04 OH 0.3500 112,000.00 39,200.00
JUMLAH HARGA TENAGA -------------------- 2,815,120.00
B BAHAN
Balok kayu Klas. I m3 1.1000 8,750,000.00 9,625,000.00
Paku 10 cm Kg 1.2500 17,500.00 21,875.00
Lem kayu Kg 1.0000 17,500.00 17,500.00
JUMLAH HARGA BAHAN -------------------- 9,664,375.00
C PERALATAN - -
Page 56
A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.0000 84,800.00 84,800.00
Tukang kayu L.03 OH 3.0000 93,200.00 279,600.00
Kepala tukang L.03 OH 0.3000 107,200.00 32,160.00
Mandor L.04 OH 0.0500 112,000.00 5,600.00
JUMLAH HARGA TENAGA -------------------- 402,160.00
B BAHAN
Papan kayu Klas. 1 m3 0.0400 9,200,000.00 368,000.00
Lem kayu Kg 0.5000 17,500.00 8,750.00
JUMLAH HARGA BAHAN -------------------- 376,750.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.4.6.1.6. Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.8000 84,800.00 67,840.00
Tukang kayu L.03 OH 2.4000 93,200.00 223,680.00
Kepala tukang L.03 OH 0.2400 107,200.00 25,728.00
Mandor L.04 OH 0.0400 112,000.00 4,480.00
JUMLAH HARGA TENAGA -------------------- 321,728.00
B BAHAN
Papan kayu Klas. I m3 0.0240 9,200,000.00 220,800.00
Lem kayu Kg 0.3000 17,500.00 5,250.00
JUMLAH HARGA BAHAN -------------------- 226,050.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 57
A.4.6.1.13. Pemasangan 1 m3 konstruksi kuda-kuda konvensional, kayu kelas II bentang 6 meter
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 4.0000 84,800.00 339,200.00
Tukang kayu L.03 OH 12.0000 93,200.00 1,118,400.00
Kepala tukang L.03 OH 1.2000 107,200.00 128,640.00
Mandor L.04 OH 0.2000 112,000.00 22,400.00
JUMLAH HARGA TENAGA -------------------- 1,608,640.00
B BAHAN
Balok kayu Klas. II m3 1.1000 3,250,000.00 3,575,000.00
Besi strip tebal 5mm kg 15.0000 12,500.00 187,500.00
Paku 12 cm kg 5.6000 17,500.00 98,000.00
JUMLAH HARGA BAHAN -------------------- 3,860,500.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.4.6.1.20. Pemasangan 1 m2 rangka langit-langit (60 x 60) cm, kayu kelas II atau III
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2000 84,800.00 16,960.00
Tukang kayu L.03 OH 0.3000 93,200.00 27,960.00
Kepala tukang L.03 OH 0.0300 107,200.00 3,216.00
Mandor L.04 OH 0.0100 112,000.00 1,120.00
JUMLAH HARGA TENAGA -------------------- 49,256.00
B BAHAN
Kaso-kaso 5 x 7 cm m3 0.0163 3,250,000.00 52,975.00
Paku 7 – 10 cm kg 0.2500 17,500.00 4,375.00
JUMLAH HARGA BAHAN -------------------- 57,350.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 58
A.4.6.1.22. Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.1000 84,800.00 8,480.00
Tukang kayu L.03 OH 0.2000 93,200.00 18,640.00
Kepala tukang L.03 OH 0.0200 107,200.00 2,144.00
Mandor L.04 OH 0.0050 112,000.00 560.00
JUMLAH HARGA TENAGA -------------------- 29,824.00
B BAHAN
Papan kayu Klas. I m3 0.0110 9,200,000.00 101,200.00
Paku 5 dan 7 cm kg 0.0500 17,500.00 875.00
JUMLAH HARGA BAHAN -------------------- 102,075.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 59
A.4.6.1.25. Pemasangan 1 m2 dinding pemisah plywood rangkap, rangka kayu kelas II
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2000 84,800.00 16,960.00
Tukang kayu L.03 OH 0.6000 93,200.00 55,920.00
Kepala tukang L.03 OH 0.0600 107,200.00 6,432.00
Mandor L.04 OH 0.0100 112,000.00 1,120.00
JUMLAH HARGA TENAGA -------------------- 80,432.00
B BAHAN
Balok kayu, 6 x 12 Klas. II m3 0.0280 3,250,000.00 91,000.00
Paku 5 dan 10 kg 0.1500 17,500.00 2,625.00
Teakwood 4 mm, 120 x 240 Lembar 0.8600 85,000.00 73,100.00
Lem kayu kg 0.5600 17,500.00 9,800.00
JUMLAH HARGA BAHAN -------------------- 176,525.00
C PERALATAN - -
Page 60
A.4.6.2.3. Pemasangan 1 buah kunci kamar mandi
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0050 84,800.00 424.00
Tukang kayu L.02 OH 0.5000 93,200.00 46,600.00
Kepala tukang L.03 OH 0.0500 107,200.00 5,360.00
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 52,720.00
B BAHAN
Kunci tanam KM Bh 1.0000 80,000.00 80,000.00
JUMLAH HARGA BAHAN -------------------- 80,000.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 61
A.4.6.2.6. Pemasangan 1 buah engsel jendela
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0100 84,800.00 848.00
Tukang kayu L.02 OH 0.1000 93,200.00 9,320.00
Kepala tukang L.03 OH 0.0100 107,200.00 1,072.00
Mandor L.04 OH 0.0005 112,000.00 56.00
JUMLAH HARGA TENAGA -------------------- 11,296.00
B BAHAN
Engsel kupu-kupu Bh 1.0000 12,500.00 12,500.00
JUMLAH HARGA BAHAN -------------------- 12,500.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 62
A.4.6.2.9. Pemasangan 1 buah kait angin
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0150 84,800.00 1,272.00
Tukang kayu L.02 OH 0.1500 93,200.00 13,980.00
Kepala tukang L.03 OH 0.0150 107,200.00 1,608.00
Mandor L.04 OH 0.0080 112,000.00 896.00
JUMLAH HARGA TENAGA -------------------- 17,756.00
B BAHAN
Kait angin Bh 1.0000 17,500.00 17,500.00
JUMLAH HARGA BAHAN -------------------- 17,500.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 63
A.4.6.2.12. Pemasangan 1 buah Door holder
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0500 84,800.00 4,240.00
Tukang kayu L.02 OH 0.5000 93,200.00 46,600.00
Kepala tukang L.03 OH 0.0500 107,200.00 5,360.00
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 56,536.00
B BAHAN
Door holder Bh 1.0000 100,000.00 100,000.00
JUMLAH HARGA BAHAN -------------------- 100,000.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 64
A.4.6.2.16. Pemasangan 1 m2 kaca tebal 3 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0150 84,800.00 1,272.00
Tukang kayu L.02 OH 0.1500 93,200.00 13,980.00
Kepala tukang L.03 OH 0.0150 107,200.00 1,608.00
Mandor L.04 OH 0.0008 112,000.00 89.60
JUMLAH HARGA TENAGA -------------------- 16,949.60
B BAHAN
Kaca tebal 3mm m2 1.1000 85,000.00 93,500.00
SEalant Tube 0.0500 30,000.00 1,500.00
JUMLAH HARGA BAHAN -------------------- 95,000.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 65
A.4.6.2.20. Pemasangan 1 m2 kaca cermin tebal 5 mm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0150 84,800.00 1,272.00
Tukang kayu L.02 OH 0.1500 93,200.00 13,980.00
Kepala tukang L.03 OH 0.0150 107,200.00 1,608.00
Mandor L.04 OH 0.0080 112,000.00 896.00
JUMLAH HARGA TENAGA -------------------- 17,756.00
B BAHAN
Kaca Cermin 5 mm m2 1.1000 175,000.00 192,500.00
JUMLAH HARGA BAHAN -------------------- 192,500.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.4.7.1.4. 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0700 84,800.00 5,936.00
Tukang cat L.02 OH 0.0090 93,200.00 838.80
Kepala tukang L.03 OH 0.0060 107,200.00 643.20
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 7,754.00
B BAHAN
Cat menie Kg 0.2000 35,000.00 7,000.00
Plamuur Kg 0.1500 17,000.00 2,550.00
Cat kilat dasar Kg 0.1700 60,000.00 10,200.00
Cat kilat penutup Kg 0.2600 68,000.00 17,680.00
Kuas Bh 0.0100 10,000.00 100.00
Minyak Cat Kg 0.0300 10,000.00 300.00
Ampelas Lbr 0.2000 5,000.00 1,000.00
JUMLAH HARGA BAHAN -------------------- 38,830.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 66
A.4.7.1.7. Pelaburan 1 m2 bidang kayu dengan politur
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0400 84,800.00 3,392.00
Tukang cat L.02 OH 0.0600 93,200.00 5,592.00
Kepala tukang L.03 OH 0.0160 107,200.00 1,715.20
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 11,035.20
B BAHAN
Politur Ltr 0.1500 100,000.00 15,000.00
Politur Jadi Ltr 0.3720 100,000.00 37,200.00
Ampelas Lbr 2.0000 17,500.00 35,000.00
JUMLAH HARGA BAHAN -------------------- 87,200.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.4.7.1.10.a. Pengecatan 1 m2 tembok baru ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0200 84,800.00 1,696.00
Tukang cat L.02 OH 0.0630 93,200.00 5,871.60
Kepala tukang L.03 OH 0.0063 107,200.00 675.36
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 8,578.96
B BAHAN
Plamuur Kg 0.1000 17,000.00 1,700.00
Cat tembok dasar Kg 0.1000 25,000.00 2,500.00
Cat tembok penutup Kg 0.2600 39,900.00 10,374.00
JUMLAH HARGA BAHAN -------------------- 14,574.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.4.7.1.10.a. Pengecatan 1 m2 tembok baru ANTI LUMUT ( 1lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0200 84,800.00 1,696.00
Tukang cat L.02 OH 0.0630 93,200.00 5,871.60
Kepala tukang L.03 OH 0.0063 107,200.00 675.36
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 8,578.96
B BAHAN
Plamuur Kg 0.1000 17,000.00 1,700.00
Cat tembok dasar Kg 0.1000 25,000.00 2,500.00
Cat tembok penutup (watersield) Kg 0.2600 100,000.00 26,000.00
JUMLAH HARGA BAHAN -------------------- 30,200.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 67
A.4.7.1.11. Pengecatan 1 m2 tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup)
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0280 84,800.00 2,374.40
Tukang cat L.02 OH 0.0420 93,200.00 3,914.40
Kepala tukang L.03 OH 0.0042 107,200.00 450.24
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 7,075.04
B BAHAN
Cat tembok dasar Kg 0.1200 25,000.00 3,000.00
Cat tembok penutup Kg 0.1800 39,900.00 7,182.00
JUMLAH HARGA BAHAN -------------------- 10,182.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 68
A.4.7.1.18. Pengecatan 1 m2 permukaan baja galvanis secara manual 4 lapis
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.2500 84,800.00 21,200.00
Tukang cat L.02 OH 0.2500 93,200.00 23,300.00
Kepala tukang L.03 OH 0.0250 107,200.00 2,680.00
Mandor L.04 OH 0.0013 112,000.00 145.60
JUMLAH HARGA TENAGA -------------------- 47,325.60
B BAHAN
Menie A Kg 0.1000 35,000.00 3,500.00
Menie B Kg 0.1000 35,000.00 3,500.00
Cat Kg 0.0800 68,000.00 5,440.00
Kwas Bh 0.0100 10,000.00 100.00
Minyak Cat L 0.0100 10,000.00 100.00
JUMLAH HARGA BAHAN -------------------- 12,640.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 69
E Overhead 10 % x D 138,185.20
F Harga satuan pekerjaan ( D + E ) 1,520,037.20
Page 70
A.5.1.1 2. Pemasangan 1 buah closet jongkok porslen
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 1.0000 84,800.00 84,800.00
Tukang batu L.02 1.5000 93,200.00 139,800.00
Kepala tukang L.03 0.1500 107,200.00 16,080.00
Mandor L.04 OH 0.1600 112,000.00 17,920.00
JUMLAH TENAGA KERJA 258,600.00
B BAHAN
Closet jongkok Unit 1.0000 300,000.00 300,000.00
Semen Portland Kg 6.0000 1,440.00 8,640.00
Pasir pasang M3 0.0100 97,500.00 975.00
JUMLAH HARGA BAHAN 309,615.00
C PERALATAN
Page 71
F Harga satuan pekerjaan ( D + E )
Page 72
A.5.1.1 6. Pemasangan 1 buah bathcuip porselen
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0,075
Tukang batu L.02 0,75
Kepala tukang L.03 0,075
Mandor L.04 OH 0,003
JUMLAH TENAGA KERJA
B BAHAN
Bathcuip Unit 1,00
Perlengkapan % 20,00
JUMLAH HARGA BAHAN
C PERALATAN
Page 73
A.5.1.1 9. Pemasangan 1 buah bak mandi teraso vol 0,30 m3
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3,00
Tukang batu L.02 4,50
Kepala tukang L.03 0,05
Mandor L.04 OH 0,90
JUMLAH TENAGA KERJA
B BAHAN
Bak fibreglass Unit 1,00
Perlengkapan Ls 12%xbak
JUMLAH HARGA BAHAN
C PERALATAN
Page 74
A.5.1.1 14. Pemasangan 1 buah floor/roof drain
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0100 84,800.00 848.00
Tukang batu L.02 OH 0.1000 93,200.00 9,320.00
Kepala tukang L.03 OH 0.0100 107,200.00 1,072.00
Mandor L.04 OH 0.0050 112,000.00 560.00
JUMLAH HARGA TENAGA -------------------- 11,800.00
B BAHAN
Floor drain Unit 1.0000 15,000.00 15,000.00
JUMLAH HARGA BAHAN -------------------- 15,000.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.5.1.1 15. Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 2.1600 84,800.00 183,168.00
Tukang batu L.02 OH 0.7200 93,200.00 67,104.00
Kepala tukang L.03 OH 0.0720 107,200.00 7,718.40
Mandor L.04 OH 0.0110 112,000.00 1,232.00
JUMLAH HARGA TENAGA -------------------- 259,222.40
B BAHAN
Bata merah bh 40.0000 450.00 18,000.00
Portland Cement (PC) Kg 44.0000 1,381.50 60,786.00
Pasir Pasang (PP) M3 0.0700 97,500.00 6,825.00
Pasir Beton (BB) M3 0.0600 142,500.00 8,550.00
Kerikil (Maks 30 mm) M3 0.0700 325,000.00 22,750.00
Baja tulangan Kg 1.6000 12,650.00 20,240.00
JUMLAH HARGA BAHAN -------------------- 137,151.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
A.5.1.1 16. Pemasangan 1 buah bak kontrol pasangan bata 45cm x45cm tinggi 50 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.2000 84,800.00 271,360.00
Tukang batu L.02 OH 1.1500 93,200.00 107,180.00
Kepala tukang L.03 OH 0.0110 107,200.00 1,179.20
Mandor L.04 OH 0.0160 112,000.00 1,792.00
JUMLAH HARGA TENAGA -------------------- 381,511.20
B BAHAN
Bata merah bh 70.0000 450.00 31,500.00
Portland Cement (PC) Kg 77.0000 1,381.50 106,375.50
Pasir Pasang (PP) M3 0.1300 97,500.00 12,675.00
Pasir Beton (BB) M3 0.0900 142,500.00 12,825.00
Kerikil (Maks 30 mm) M3 0.0200 325,000.00 6,500.00
Baja tulangan Kg 2.6000 12,650.00 32,890.00
JUMLAH HARGA BAHAN -------------------- 202,765.50
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 75
D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 215,590.50
E Overhead 10 % x D 21,559.05
F Harga satuan pekerjaan ( D + E ) 237,149.55
A.5.1.1 17. Pemasangan 1 buah bak kontrol pasangan bata 60cm x60cm tinggi 65 cm
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 3.2000 84,800.00 271,360.00
Tukang batu L.02 OH 1.1500 93,200.00 107,180.00
Kepala tukang L.03 OH 0.0110 107,200.00 1,179.20
Mandor L.04 OH 0.0160 112,000.00 1,792.00
JUMLAH HARGA TENAGA -------------------- 381,511.20
B BAHAN
Bata merah bh 123.0000 450.00 55,350.00
Portland Cement (PC) Kg 114.0000 1,381.50 157,491.00
Pasir Pasang (PP) M3 0.1840 97,500.00 17,940.00
Pasir Beton (BB) M3 0.1200 142,500.00 17,100.00
Kerikil (Maks 30 mm) M3 0.0330 325,000.00 10,725.00
Baja tulangan Kg 4.8500 12,650.00 61,352.50
JUMLAH HARGA BAHAN -------------------- 319,958.50
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 76
D Jumlah harga tenaga, bahan dan peralatan ( A + B + C ) 182,917.60
E Overhead 10 % x D 18,291.76
F Harga satuan pekerjaan ( D + E ) 201,209.36
Page 77
A.5.1.1 25. Pemasangan 1 m’ pipa PVC tipe AW diameter 1/2”
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0360 84,800.00 3,052.80
Tukang batu L.02 OH 0.0600 93,200.00 5,592.00
Kepala tukang L.03 OH 0.0060 107,200.00 643.20
Mandor L.04 OH 0.0020 112,000.00 224.00
JUMLAH HARGA TENAGA -------------------- 9,512.00
B BAHAN
Pipa PVC 1/2” M 1.2000 3,400.00 4,080.00
Perlengkapan % 35.0000 3,400.00 1,190.00
JUMLAH HARGA BAHAN -------------------- 5,270.00
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 78
A.5.1.1 28. Pemasangan 1 m’ pipa PVC tipe AW diameter 11/2”
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0540 84,800.00 4,579.20
Tukang batu L.02 OH 0.0900 93,200.00 8,388.00
Kepala tukang L.03 OH 0.0090 107,200.00 964.80
Mandor L.04 OH 0.0030 112,000.00 336.00
JUMLAH HARGA TENAGA -------------------- 14,268.00
B BAHAN
Pipa PVC 11/2” M 1.2000 8,750.00 10,500.00
Perlengkapan % 35.0000 8,750.00 3,062.50
JUMLAH HARGA BAHAN -------------------- 13,562.50
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 79
A.5.1.1 31. Pemasangan 1 m’ pipa PVC tipe AW diameter 3”
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0810 84,800.00 6,868.80
Tukang batu L.02 OH 0.1350 93,200.00 12,582.00
Kepala tukang L.03 OH 0.0135 107,200.00 1,447.20
Mandor L.04 OH 0.0040 112,000.00 448.00
JUMLAH HARGA TENAGA -------------------- 21,346.00
B BAHAN
Pipa PVC 3” M 1.2000 25,156.25 30,187.50
Perlengkapan % 35.0000 25,156.25 8,804.69
JUMLAH HARGA BAHAN -------------------- 38,992.19
C PERALATAN
- -
JUMLAH HARGA PERALATAN -------------------- -
Page 80
A.6.2.1.1b. Memasang 1 Bh Titik lampu LC 20 Watt
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0125 84,800.00 1,060.00
Tukang Listrik / Teknisi L.02 OH 0.1250 93,200.00 11,650.00
Mandor L.04 OH 0.0025 112,000.00 280.00
JUMLAH HARGA TENAGA -------------------- 12,990.00
B BAHAN
Lampu LC 20 Watt Bh 1.0000 55,000.00 55,000.00
JUMLAH HARGA BAHAN -------------------- 55,000.00
C PERALATAN
Perlengkapan / Alat Bantu % 25.0000 55,000.00 13,750.00
JUMLAH HARGA PERALATAN -------------------- 13,750.00
Page 81
A.6.2.1.2b. Memasang 1 Bh Titik Lampu Down Ligt 20 Watt
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0250 84,800.00 2,120.00
Tukang Listrik / Teknisi L.02 OH 0.2500 93,200.00 23,300.00
Mandor L.04 OH 0.0050 112,000.00 560.00
JUMLAH HARGA TENAGA -------------------- 25,980.00
B BAHAN
Lampu Down Light 20 Watt Bh 1.0000 100,000.00 100,000.00
JUMLAH HARGA BAHAN -------------------- 100,000.00
C PERALATAN
Perlengkapan / Alat Bantu % 25.0000 100,000.00 25,000.00
JUMLAH HARGA PERALATAN -------------------- 25,000.00
Page 82
A.6.2.1.3. Memasang 1 Bh Titik Lampu Down Lampu Hollogen
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0250 84,800.00 2,120.00
Tukang Listrik / Teknisi L.02 OH 0.2500 93,200.00 23,300.00
Mandor L.04 OH 0.0050 112,000.00 560.00
JUMLAH HARGA TENAGA -------------------- 25,980.00
B BAHAN
Lampu Down Light Lampu Hollogen Bh 1.0000 165,000.00 165,000.00
JUMLAH HARGA BAHAN -------------------- 165,000.00
C PERALATAN
Perlengkapan / Alat Bantu % 25.0000 165,000.00 41,250.00
JUMLAH HARGA PERALATAN -------------------- 41,250.00
Page 83
A.6.2.1.5b. Memasang 1 Bh Titik Lampu TL. 1 x 20 Watt
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0125 84,800.00 1,060.00
Tukang Listrik / Teknisi L.02 OH 0.1250 93,200.00 11,650.00
Mandor L.04 OH 0.0025 112,000.00 280.00
JUMLAH HARGA TENAGA -------------------- 12,990.00
B BAHAN
Lampu TL 1 x 20 Watt Bh 1.0000 115,000.00 115,000.00
JUMLAH HARGA BAHAN -------------------- 115,000.00
C PERALATAN
Perlengkapan / Alat Bantu % 25.0000 115,000.00 28,750.00
JUMLAH HARGA PERALATAN -------------------- 28,750.00
Page 84
A.6.2.1.8. Memasang 1 Bh Memasang 1 Bh Saklar Tunggal
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0250 84,800.00 2,120.00
Tukang Listrik / Teknisi L.02 OH 0.2500 93,200.00 23,300.00
Mandor L.04 OH 0.0050 112,000.00 560.00
JUMLAH HARGA TENAGA -------------------- 25,980.00
B BAHAN
Saklar tunggal Bh 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN -------------------- 25,000.00
C PERALATAN
Perlengkapan / Alat Bantu % 25.0000 25,000.00 6,250.00
JUMLAH HARGA PERALATAN -------------------- 6,250.00
Page 85
A.6.2.1.11. Memasang 1 Bh Memasang 1 Bh Stop Kontak AC
Harga Satuan Jumlah Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)
A TENAGA
Pekerja L.01 OH 0.0250 84,800.00 2,120.00
Tukang Listrik / Teknisi L.02 OH 0.2500 93,200.00 23,300.00
Mandor L.04 OH 0.0050 112,000.00 560.00
JUMLAH HARGA TENAGA -------------------- 25,980.00
B BAHAN
Stop Kontak AC Bh 1.0000 45,000.00 45,000.00
JUMLAH HARGA BAHAN -------------------- 45,000.00
C PERALATAN
Perlengkapan / Alat Bantu % 25.0000 45,000.00 11,250.00
JUMLAH HARGA PERALATAN -------------------- 11,250.00
Page 87
DAFTAR HARGA SATUAN UPAH
HARGA SATUAN
NO URAIAN SATUAN
( Rp. )
A. AGREGAT
1 Pasir Pasangan Rp. 97,500.00 / M3
2 Pasir Beton Rp. 142,500.00 / M3
3 Pasir Beton ( dalam Kg ) Rp. 101.79 / Kg
4 Pasir Urug Rp. 90,000.00 / M3
5 Batu Kali / Batu Belah Rp. 350,000.00 / M3
6 Kerikil (2 Cm/3 Cm ) Rp. 325,000.00 / M3
7 Kerikil (2 Cm/3 Cm ) dalam Kg Rp. 180.56 / Kg
8 Batu Pecah uk. 2-3 cm ( Split ) Rp. 481,000.00 / M3
9 Batu Pecah uk. 2-3 cm ( Split ) dalam Kg Rp. 300.63 / Kg
10 Sirtu Rp. 300,000.00 / M3
11 Tanah Timbunan Biasa ( Didatangkan ) Rp. 45,000.00 / M3
12 Tanah Timbunan Pilihan ( Didatangkan ) Rp. 90,000.00 / M3
B. SEMEN
1 Semen PC Rp. 1,440.00 / Kg
2 Semen PC @ 40 Kg Rp. 57,600.00 / Zak
3 Semen PC @ 50 Kg Rp. 69,075.00 / Zak
4 Semen Warna Rp. 15,000.00 / Kg
5 Semen Putih Rp. 80,000.00 / Zak
C. BETON / MORTAR
1 Batu Bata Kecil uk. 5x11x22 cm Rp. 450.00 / Bh
2 Roster Batu Terawang Rp. 10,000.00 / Bh
3 Conblok Rp. 2,500.00 / Bh
Page 88
D. BAHAN BESI & ALLUMUNIUM
1 Besi Beton Rp. 12,650.00 / Kg
2 Besi Profil Rp. 20,500.00 / Kg
3 Besi hollow 40 x 40 mm Rp. 35,000.00 / Btg
4 Besi hollow 40 x 20 mm Rp. 30,000.00 / Btg
5 Pipa GLV Ø 4" x 6000 mm Rp. 570,000.00 / Btg
6 Pipa GLV Ø 3" x 6000 mm Rp. 475,000.00 / Btg
7 Pipa GLV Ø 2 1/2" x 6000 mm Rp. 420,000.00 / Btg
8 Pipa GLV Ø 2" x 6000 mm Rp. 370,000.00 / Btg
9 Pipa GLV Ø 1 1/2" x 6000 mm Rp. 275,000.00 / Btg
10 Pipa Stainlesstell Ø 2 1/2" x 6000 mm Rp. 650,000.00 / Btg
11 Pintu gulung besi Rp. 600,000.00 / M2
12 Pintu lipat (folding door) Rp. 750,000.00 / M2
13 Baut/Begel/Besi Rp. - / Kg
14 Besi strip tebal 5 mm Rp. 12,500.00 / Kg
15 Wire mesh Rp. 25,000.00 / Kg
16 Kawat Beton Rp. 17,000.00 / Kg
17 Kawat Nyamuk Rp. 17,500.00 / M2
18 Kawat Las Rp. 85,000.00 / Kg
19 Paku Biasa Rp. 17,500.00 / Kg
20 Paku Halus Rp. 20,000.00 / Kg
21 Paku Bulian Rp. 27,500.00 / Kg
22 Paku Seng Rp. 20,000.00 / Kg
23 Paku Skrup Rp. 25,000.00 / Kg
24 Paku GRC Rp. 25,000.00 / Ktk
25 Rooling door Alumunium Rp. 550,000.00 / M2
26 Kusen Alumunium Rp. 75,000.00 / M1
27 Profil Allumunium Rp. 165,000.00 / M1
28 Pintu allumunium Rp. 135,000.00 / M1
28 Pintu Fiber Rp. 300,000.00 / Unit
28 Sunscreen alluminium Rp. 195,000.00 / M2
28 Allumunium Panel Rp. 55,000.00 / M2
28 Skrup fixer Rp. 250.00 / Bh
28 Sealant Rp. 30,000.00 / Tube
28 Ramset Rp. 85,000.00 / Bh
28 Profil Kaca Rp. 35,000.00 / M1
E. BAHAN KAYU
1 Kayu Klas I Jenis Kulim Rp. 8,750,000.00 / M3
2 Kayu Klas II Rp. 3,250,000.00 / M3
3 Kayu Klas III Rp. 2,200,000.00 / M3
4 Papan Klas I Rp. 9,200,000.00 / M3
5 Papan klas II Rp. 3,450,000.00 / M3
6 Papan klas III Rp. 2,200,000.00 / M3
7 Papan Bekisting Rp. 1,750,000.00 / M3
8 Triplek 2,8 mm Rp. 37,000.00 / Lbr
9 Triplek 3,6 mm Rp. 53,000.00 Lbr
10 Teakwood/Plywood t. 4 mm Rp. 85,000.00 / Lbr
11 Multiplek tebal 6 mm Rp. 85,500.00 / Lbr
12 Multiplek tebal 9 mm Rp. 125,000.00 / Lbr
13 HPL Rp. 75,000.00 / Lbr
14 Formika Rp. 85,000.00 / Lbr
15 Kayu Bulat Cerucuk Ø 12 s/d 15 cm Panjang 3 s/d 4 M Rp. 40,000.00 / Btg
16 Dolken kayu biasa, Ø (8-10) cm, panjang 4m Rp. 5,000.00 / Btg
17 Kayu kelukup Panjang 5 m Rp. 20,000.00 / Btg
18 Kayu Cerucuk / Kelukup Panjang 2,5 M Rp. 20,000.00 / Btg
19 Kayu Bulian Belahan Rp. 4,500,000.00 / M3
Page 89
F. BAHAN PENUTUP ATAP
1 Seng Gelombang BJLS 20 Rp. 30,000.00 / Lbr
2 Seng Plat BJLS 20 Rp. 37,500.00 / M1
3 Genteng Metal Colour 2 Susun Rp. 65,000.00 / Lbr
4 Bubungan Genteng Metal Colour Panjang 1 M Rp. 38,000.00 / Bh
5 Super Plank GRC Board 9 x 200 mm Rp. 15,000.00 / M1
6 Lisplank Seng Plat BJLS 30 Pabrikasi Lebar 25 cm Rp. 30,000.00 / M1
7 Lisplank Seng Plat BJLS 30 Pabrikasi Lebar 30 cm Rp. 50,000.00 / M1
8 Atap Galvalume Warna ( Zyng Calum Ecotrim 0,03 ) Rp. 46,000.00 / M1
9 Rooflight 90x180 Rp. 150,000.00 / Lbr
10 Alumunium foil Rp. 25,000.00 / M2
11 Besi Baja Ringan Rangka Atap ( Pabrikasi ) Rp. 125,000.00 / M2
I. BAHAN KACA
1 Kaca Ryben 3 mm Rp. 85,000.00 / M2
2 Kaca Ryben 5 mm Rp. 115,000.00 / M2
3 Kaca Ryben 8 mm Rp. 250,000.00 / M2
4 Kaca Buram 5 mm Rp. 115,000.00 / M2
5 Kaca Cermin 5 mm Rp. 175,000.00 / M2
6 Glass Block Rp. 30,000.00 / Bh
Page 90
J. BAHAN INSTALASI LISTRIK
1 Instalasi Titik Lampu Rp. 175,000.00 / Ttk
2 Stop kontak Rp. 25,000.00 / Bh
3 Saklar tunggal Rp. 25,000.00 / Bh
4 Saklar ganda Rp. 30,000.00 / Bh
5 Stop kontak AC Rp. 45,000.00 / Bh
6 Lampu LC 35 Watt Rp. 90,000.00 / Bh
7 Lampu LC 20 Watt Rp. 55,000.00 / Bh
8 Lampu LC 18 Watt Rp. 45,000.00 / Bh
9 Lampu Down Light 35 Watt Rp. 140,000.00 / Bh
10 Lampu Down Light 20 Watt Rp. 100,000.00 / Bh
11 Lampu Down Light 18 Watt Rp. 90,000.00 / Bh
12 Lampu Down Light 10 Watt Rp. 65,000.00 / Bh
13 Lampu Down Light Lampu Hollogen Rp. 165,000.00 / Bh
14 Lampu Baret Bulat 20 Watt Rp. 135,000.00 / Bh
15 Lampu TL 2 x 20 Watt + Kaca Acrilic Rp. 325,000.00 / Bh
16 Lampu TL 1 x 20 Watt Rp. 115,000.00 / Bh
17 Lampu Pijar 40 watt Rp. 18,000.00 / Bh
18 Lampu Taman 35 Watt Rp. 225,000.00 / Bh
19 Box Panel Utama dan Kelengkapannya Rp. 3,750,000.00 / Unit
20 Box Zekring / Box MCB Rp. 125,000.00 / Unit
21 Kabel Listrik NYY 2x2,5 mm2 Rp. 6,500.00 / M1
22 Kabel Listrik NYY 3x2,5 mm2 Rp. 8,500.00 / M1
23 Panel Induk + Accesories Terpasang Rp. 750,000.00 / M1
K. BAHAN SANITER
1 Instalasi Air Bersih Rp. 85,000.00 / Ttk
2 Pipa PVC Tipe AW Ø 1/2" Rp. 3,400.00 / M1
3 Pipa PVC Tipe AW Ø 3/4" Rp. 4,550.00 / M1
4 Pipa PVC Tipe AW Ø 1" Rp. 6,062.50 / M1
5 Pipa PVC Tipe AW Ø 1 1/2" Rp. 8,750.00 / M1
6 Pipa PVC Tipe AW Ø 2" Rp. 14,875.00 / M1
7 Pipa PVC Tipe AW Ø 2 1/2" Rp. 22,500.00 / M1
8 Pipa PVC Tipe AW Ø 3" Rp. 25,156.25 / M1
9 Pipa PVC Tipe AW Ø 4" Rp. 51,500.00 / M1
10 Pipa Hitam Ø 3" Rp. 32,500.00 / M1
11 Pipa Hitam Ø 4" Rp. 35,000.00 / M1
12 Bak Fiber Glass Volume 0,3 M3 Rp. 175,000.00 / Bh
13 Bak Fiber Glass Volume 1 M3 Rp. 350,000.00 / Bh
14 Bak Cuci Stainless steel Rp. 250,000.00 / Bh
15 Closed Jongkok Keramik Standar Terpasang Rp. 300,000.00 / Unit
16 Closed Duduk Keramik Terpasang Rp. 925,000.00 / Unit
17 Urinoir Lengkap Rp. 850,000.00 / Bh
18 Wastafel lengkap Rp. 750,000.00 / Bh
19 Sower Air + Accesories Terpasang Rp. 125,000.00 / Bh
20 Kran Air 1/2" Rp. 20,000.00 / Bh
21 Floor Drain Rp. 15,000.00 / Bh
22 Sealtape Rp. 7,000.00 / Bh
23 Tedmond Air Kap. 1 M3 Rp. 1,800,000.00 / Bh
24 Sumur Bor + Acessories Rp. 15,000,000.00 / Unit
25 Mesin Air + Accesories terpasang Rp. 2,500,000.00 / Unit
Page 91
L. BAHAN FINISHING
1 Amplas Rp. 5,000.00 / Lbr
2 Cat Kilat Rp. 68,000.00 / Kg
3 Cat Kilat Dasar Rp. 60,000.00 / Kg
4 Cat Tembok SETARA VINILEX Rp. 39,900.00 / Kg
5 Cat Tembok ( Watersield) SETARA JOTUN / KEMTUN Rp. 100,000.00 / Kg
6 Cat Tembok Dasar Rp. 25,000.00 / Kg
7 Cat Meni Rp. 35,000.00 / Kg
8 Cat Melamik Rp. 65,000.00 / Kg
9 Water Profing Rp. 140,000.00 / Kg
10 Dempul Rp. 20,000.00 / Kg
11 Plamour Rp. 17,000.00 / Kg
12 Politur Rp. 100,000.00 / Ltr
13 Minyak Cat Rp. 10,000.00 / Ltr
14 Lem Kayu Rp. 17,500.00 / Kg
15 Lem Aibon Rp. 40,000.00 / Klg
16 Lem vinyl Rp. 25,000.00 / Kg
17 Spritus Rp. 9,000.00 / Btl
18 Minyak Bekisting Rp. 10,000.00 / Kg
19 Residu kap Rp. 1,500.00 / Ltr
20 Kuwas Rp. 10,000.00 / Bh
Page 92
N. PEKERJAAN PERPAKET / LUMPSUM
O. LAIN - LAIN
1 Air Rp. 150.00 / Liter
2 Minyak Solar Rp. 12,300.00 / Ltr
3 Minyak Pelumas Rp. 35,000.00 / Ltr
4 Aspal Semen Penetrasi Rp. 34,000.00 / Kg
5 Aspal Semen Emulsi Rp. 35,000.00 / Ltr
6 Alat bantu Rp. 20,000.00 / Ls
7 Sewa Mesin Las Rp. 75,000.00 / Jam
8 Lempengan Rumput Biasa Rp. 25,000.00 / M2
9 Pek. Design Mix Formula (DMF) Rp. 3,500,000.00 / Ls
10 Pembongkaran Atap Rp. 40,000.00 / M2
11 Pembongkaran Atap Rp. 10,000.00 / M2
12 Pembongkaran Plafond + Rangka Rp. 5,000.00 / M2
13 Pembongkaran Plafond Rp. 10,000.00 / M2
14 Pemasangan Kawat Duri Rp. 100,000.00 / M2