JADWAL PELAKSANAAN (KURVA S) BULAN XIV

Proyek : Pengerukan Kolam dan Alur Pelayaran Pelabuhan Belawan


Lokasi : Belawan, Sumatera Utara
Durasi : 504 Hari
Waktu (minggu)
NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
BOBOT KET.
VOLUME Bobot VOLUME Bobot SISA VOLUME
URAIAN SAT SISA ADD 01 Agus - 02 03 Agus - 09 10 Agus - 16 17 Agus - 23 24 Agus - 30 31 Agus - 06 07 Sept - 13 14 Sept - 20 21 Sept - 27 28 Sept - 04 05 Okt - 11 Okt 12 Okt - 18 Okt 19 Okt - 25 Okt 26 Okt - 01 Nov 02 Nov - 08 Nov 09 Nov - 15 Nov 16 Nov - 22 Nov 23 Nov - 29 Nov 30 Nov - 06 Des 07 Des - 13 Des 14 Des - 20 Des 21 Des - 27 Des 28 Des'20 - 03 04 Jan - 10 Jan 11 Jan - 17 Jan 18 Jan - 24 Jan 25 Jan - 31 Jan 01 Feb - 07 Feb 08 Feb - 14 Feb 15 Feb - 21 Feb 22 Feb - 28 Feb 01 Mar - 07 Mar 08 Mar - 14 Mar 15 Mar - 21 Mar 22 Mar - 28 Mar 29 Mar - 04 Apr 05 Apr - 11 Apr 12 Apr - 18 Apr 119 Apr - 25 26 Apr - 02 Mei 03 Mei - 9 Mei 10 Mei - 16 Mei 17 Mei - 23 Mei 24 Mei - 30 Mei 31 Mei - 06 Jun 07 Jun - 13 Jun 14 Jun - 20 Jun 21 Jun - 27 Jun 28 Jun - 04 Jul 05 Juli - 11 Juli 12 Juli - 18 19 Juli - 25 Juli 26 Juli - 01 02 Agus - 08 09 Agus - 15 16 Agus - 22 23 Agus - 29 30 Agus - 05 06 Sept - 12 13 Sept - 19 20 Sept - 26 27 Sept - 03 04 Okt - 10 Okt 11 Okt - 17 Okt 18 Okt - 24 Okt 25 Okt - 31 Okt 01 Nov - 07 Nov 08 Nov - 14 Nov 15 Nov - 21 Nov 22 Nov - 28 Nov 29 Nov - 04 Des 05 Des - 11 Des 12 Des - 18 Des
KONTRAK (%) ADENDUM (%) ADD III
III (%) Agus 2020 Agus 2020 Agus 2020 Agus 2023 Agus 2020 Sept 2020 Sept 2020 Sept 2020 Sept 2020 Okt 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 Jan 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 Apr 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 Juli 2021 2021 Agus 2021 Agus 2021 Agus 2021 Agus 2021 Agus 2021 Sept 2021 Sept 2021 Sept 2021 Sept 2021 Okt 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
I PEKERJAAN PERSIAPAN
1 Mobilisasi dari Bojonegara-Belawan = 863 Nm
- 1 unit TSHD Nm 863 0,86 863 0,76 0,38 0,38
- 1 Set Clamshell Dredger Nm 863 0,95 863 0,84 0,84
- Predredge Sounding Kali 1 1
II PELAKSANAAN PEKERJAAN 0
Pengerukan alur pelayaran Belawan
m³ 1.307.931,80 67,93 1.454.829,35 66,64 593.399,00 27,18 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01
dengan menggunakan TSHD

Pengerukan alur pelabuhan citra


dengan menggunakan: m³ 161.504,85 134.072,75
A A A
- TSHD m³ 8,39 66.002,65 6,14 2.844,00 0,13 0,05 0,35 0,45 0,89 1,09 1,09 0,99 0,89 0,33 -
D D D
0,13

m³ 68.070,98
- Clamshell Dredger
D D D
Kolam Pelabuhan Belawan
REALISASI S.D 30 Mei 2021
- Kolam Dermaga IKD 1 m³ 21.484,10 1,17 12.400,30 0,60 0,04 0,55 E E E
- Kolam Dermaga IKD 2 m³ 58.980,90 3,21 55.240,90 2,65 0,29 0,79 0,83 0,04 0,35 0,35
N N N
- Kolam Dermaga IKD 3 m³ 67.577,40 3,68 63.365,50 3,04 0,41 - 0,91 1,24 0,47

- Kolam Dermaga Citra (201 - 203) m³ 63.021,20 3,43 56.815,00 2,73 0,61 0,26 1,37 0,49 D KURVA S RENCANA KONTRAK D D
- Kolam Dermaga 101 - 103 m³ 34.843,60 1,90 32.030,90 1,54 0,12 0,71 0,71
U U U
- Kolam Dermaga BICT m³ 26.263,60 1,43 20.847,20 1,00 1,00

- Kolam Dermaga TPKDB m³ 41.252,20 2,24 34.435,50 1,65 M 0,83 0,83


KURVA S RENCANA M KURVA S RENCANA ADDENDUM II M KURVA S RENCANA ADDENDUM III
- Kolam Dermaga Ex. Rukindo m³ 20.515,00 1,12 15.606,80 0,75 0,12 0,41 - 0,17 0,04
- Kolam Dermaga Belawan Lama
m³ 7.119,20 0,39 5.861,90 0,28 0,14 0,14
(Gudang 002 - 006)
- Kolam Dermaga 200 (Ex. Dermaga I 2 3
Ferry) m³ 9.378,60 0,51 3.240,60 0,16 0,16

- Kolam Dermaga Shore Base m³ 18.482,20 1,01 21.629,30 1,04 0,04 0,95 0,04

- Kolam Dermaga Phase I 96.258,80 4,41 96.258,80 4,41 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88

- Kolam Dermaga Phase II 87.400,50 4,19 870,50 0,04 0,84 0,84 0,84 0,84 0,84 0,04

Progress / Prefinal Sounding Kali 5 - - Final Sounding

III PEKERJAAN FINAL


Mobilisasi dari Bojonegara-Belawan = 863 Nm
- 1 unit TSHD Nm 863 0,86 863 0,76 0,76
- 1 Set Clamshell Dredger Nm 863 0,95 863 0,84 0,84
Bobot Rencana Kontrak 100,00 100,00 1,33 0,47 2,06 2,34 4,68 3,64 3,96 3,49 3,49 3,54 3,54 3,54 3,54 3,51 3,52 3,52 3,52 3,51 3,51 3,34 3,55 3,56 3,59 2,82 2,82 2,34 2,34 2,34 2,34 2,34 2,34 2,34 2,34 0,86 -
Bobot Rencana Akumulatif 0 1,33 1,81 3,87 6,21 10,89 14,53 18,49 21,97 25,46 29,00 32,54 36,08 39,62 43,13 46,65 50,18 53,70 57,21 60,72 64,07 67,62 71,18 74,77 77,59 80,40 82,74 85,09 87,43 89,77 92,11 94,46 96,80 99,14 100
Realisasi Berdasarkan Bobot Kontrak 1,58 2,63 4,22 5,89 7,13 9,40 12,27 15,40 17,59 19,92
Realisasi Berdasarkan Bobot Addendum 1 0 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 3,11 3,01 3,63 3,73 1,04 5,89 4,25 3,90 7,77 9,03 7,45 6,13 6,81 7,86 8,06
Akumulasi realisai berdasarkan Adendum 1 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 18,90 20,52 22,45 24,64 27,51 29,48 32,03 35,21 38,14 41,04 43,61 45,50 47,45 49,41 51,37 52,72 53,80 54,09 56,41 59,51 62,52 66,14 69,87 70,92 76,80 81,06 84,95 92,73 101,76 109,21 115,34 122,16 130,01 138,1
(0,97) 2,91 5,15 7,04 12,80 18,94 23,50 26,74 30,67 35,63 41,68
Rencana Addendum 1 3,80 3,73 3,60 3,60 2,98 3,04 3,04 3,72 3,72 4,28 2,90 2,90 3,78 3,78 3,78 3,78 3,78 3,74 3,74 3,74 3,74 3,74 3,32
Rencana Akumulatif Addendum 1 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 20,41 24,15 27,75 31,35 34,34 37,37 40,41 44,14 47,86 52,14 55,03 57,93 61,71 65,49 69,27 73,05 76,83 80,56 84,30 88,03 91,77 95,51 98,82 100,0
Deviasi (1,51) (3,63) (5,30) (6,71) (6,83) (7,89) (8,38) (8,92) (9,71) (11,10) (11,42) (12,43) (14,26) (16,08) (17,90) (20,32) (23,02) (26,48) (27,89) (28,90) (29,25) (29,36) (28,95) (100,0)

Bobot Rencana Addendum II 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 2,73 3,01 3,63 3,73 2,01 2,01 2,01 2,01 2,01 2,89 2,89 2,89 2,89 2,89 2,01 2,01 0,42 1,18
Bobot Rencana Akumulatif Addendum II 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 18,90 20,52 22,45 24,64 27,51 29,48 32,03 35,21 38,14 41,04 43,61 45,50 47,45 49,41 51,37 52,72 53,80 54,09 56,41 59,13 62,52 66,15 69,87 71,88 73,89 75,90 77,91 79,92 82,82 85,71 88,60 91,49 94,38 96,39 98,40 98,82 100,0
Realisasi Berdasarkan Bobot Addendum II 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 2,73 3,01 3,63 3,73 70,92 76,80 81,06 84,95 92,73 101,76 109,21 115,34 122,16 130,01 138,1
(0,97) 2,91 5,15 7,04 12,80 18,94 23,50 26,74 30,67 35,63 41,68

Bobot Rencana Addendum III 1,01 1,01 1,01 1,89 2,02 1,89 1,89 1,89 1,05 1,01 1,01 1,01 1,84 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 - 0,76 -
Bobot Rencana Akumulatif Addendum III 66,64 67,65 68,66 69,66 71,55 73,57 75,46 77,35 79,24 80,28 81,29 82,30 83,30 85,15 86,15 87,16 88,17 89,17 90,18 91,19 92,19 93,20 94,21 95,21 96,22 97,23 98,23 99,24 99,24 100,00 100,00
Realisasi Berdasarkan Bobot Addendum II 66,64 71,12 78,73 85,99 93,66 101,67 108,76 114,55 121,45 121,45 124,60 125,25 125,95 126,83 129,43 129,78 129,78 129,78
Deviasi 3,47 10,07 16,33 22,11 28,10 33,30 37,20 42,21 41,16 43,31 42,95 42,65 41,68 43,27 42,62 41,61 40,61

Belawan, 27 September 2021

Disetujui oleh Diperiksa oleh Dibuat oleh


Pengawas Pekerjaan Konsultan Pengawas Kontraktor Pelaksana
PT Pelabuhan Indonesia (persero) PT Muara Consult PT Bina Mitra IndoSejahtera

Mhd. Zulpan Kalam Sambiring Sundra


Project Manager Fasilitas Direktur Project Manager
JADWAL PELAKSANAAN (KURVA S) BULAN XVII

Proyek : Pengerukan Kolam dan Alur Pelayaran Pelabuhan Belawan


Lokasi : Belawan, Sumatera Utara
Durasi : 504 Hari

Waktu (minggu)
NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
BOBOT KET.
VOLUME Bobot VOLUME Bobot SISA VOLUME
URAIAN SAT SISA ADD 01 Agus - 02 03 Agus - 09 10 Agus - 16 17 Agus - 23 24 Agus - 30 31 Agus - 06 07 Sept - 13 14 Sept - 20 21 Sept - 27 28 Sept - 04 05 Okt - 11 Okt 12 Okt - 18 Okt 19 Okt - 25 Okt 26 Okt - 01 Nov 02 Nov - 08 Nov 09 Nov - 15 Nov 16 Nov - 22 Nov 23 Nov - 29 Nov 30 Nov - 06 Des 07 Des - 13 Des 14 Des - 20 Des 21 Des - 27 Des 28 Des'20 - 03 04 Jan - 10 Jan 11 Jan - 17 Jan 18 Jan - 24 Jan 25 Jan - 31 Jan 01 Feb - 07 Feb 08 Feb - 14 Feb 15 Feb - 21 Feb 22 Feb - 28 Feb 01 Mar - 07 Mar 08 Mar - 14 Mar 15 Mar - 21 Mar 22 Mar - 28 Mar 29 Mar - 04 Apr 05 Apr - 11 Apr 12 Apr - 18 Apr 119 Apr - 25 26 Apr - 02 Mei 03 Mei - 9 Mei 10 Mei - 16 Mei 17 Mei - 23 Mei 24 Mei - 30 Mei 31 Mei - 06 Jun 07 Jun - 13 Jun 14 Jun - 20 Jun 21 Jun - 27 Jun 28 Jun - 04 Jul 05 Juli - 11 Juli 12 Juli - 18 19 Juli - 25 Juli 26 Juli - 01 02 Agus - 08 09 Agus - 15 16 Agus - 22 23 Agus - 29 30 Agus - 05 06 Sept - 12 13 Sept - 19 20 Sept - 26 27 Sept - 03 04 Okt - 10 Okt 11 Okt - 17 Okt 18 Okt - 24 Okt 25 Okt - 31 Okt 01 Nov - 07 Nov 08 Nov - 14 Nov 15 Nov - 21 Nov 22 Nov - 28 Nov 29 Nov - 04 Des 05 Des - 11 Des 12 Des - 18 Des
KONTRAK (%) ADENDUM (%) ADD III
III (%) Agus 2020 Agus 2020 Agus 2020 Agus 2023 Agus 2020 Sept 2020 Sept 2020 Sept 2020 Sept 2020 Okt 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 Jan 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 Apr 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 Juli 2021 2021 Agus 2021 Agus 2021 Agus 2021 Agus 2021 Agus 2021 Sept 2021 Sept 2021 Sept 2021 Sept 2021 Okt 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
I PEKERJAAN PERSIAPAN
1 Mobilisasi dari Bojonegara-Belawan = 863 Nm
- 1 unit TSHD Nm 863 0,86 863 0,76 0,38 0,38
- 1 Set Clamshell Dredger Nm 863 0,95 863 0,84 0,84
- Predredge Sounding Kali 1 1
II PELAKSANAAN PEKERJAAN 0
Pengerukan alur pelayaran Belawan
m³ 1.307.931,80 67,93 1.454.829,35 66,64 593.399,00 27,18 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01
dengan menggunakan TSHD

Pengerukan alur pelabuhan citra


dengan menggunakan: m³ 161.504,85 134.072,75
A A A
- TSHD m³ 8,39 66.002,65 6,14 2.844,00 0,13 0,05 0,35 0,45 0,89 1,09 1,09 0,99 0,89 0,33 -
D D D
0,13

m³ 68.070,98
- Clamshell Dredger
D D D
Kolam Pelabuhan Belawan
REALISASI S.D 30 Mei 2021
- Kolam Dermaga IKD 1 m³ 21.484,10 1,17 12.400,30 0,60 0,04 0,55 E E E
- Kolam Dermaga IKD 2 m³ 58.980,90 3,21 55.240,90 2,65 0,29 0,79 0,83 0,04 0,35 0,35
N N N
- Kolam Dermaga IKD 3 m³ 67.577,40 3,68 63.365,50 3,04 0,41 - 0,91 1,24 0,47

- Kolam Dermaga Citra (201 - 203) m³ 63.021,20 3,43 56.815,00 2,73 0,61 0,26 1,37 0,49 D KURVA S RENCANA KONTRAK D D
- Kolam Dermaga 101 - 103 m³ 34.843,60 1,90 32.030,90 1,54 0,12 0,71 0,71
U U U
- Kolam Dermaga BICT m³ 26.263,60 1,43 20.847,20 1,00 1,00
M KURVA S RENCANA M KURVA S RENCANA ADDENDUM II M KURVA S RENCANA ADDENDUM III
- Kolam Dermaga TPKDB m³ 41.252,20 2,24 34.435,50 1,65 0,83 0,83

- Kolam Dermaga Ex. Rukindo m³ 20.515,00 1,12 15.606,80 0,75 0,12 0,41 - 0,17 0,04
- Kolam Dermaga Belawan Lama
m³ 7.119,20 0,39 5.861,90 0,28 0,14 0,14
(Gudang 002 - 006)
- Kolam Dermaga 200 (Ex. Dermaga I 2 3
Ferry) m³ 9.378,60 0,51 3.240,60 0,16 0,16

- Kolam Dermaga Shore Base m³ 18.482,20 1,01 21.629,30 1,04 0,04 0,95 0,04

- Kolam Dermaga Phase I 96.258,80 4,41 96.258,80 4,41 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88

- Kolam Dermaga Phase II 87.400,50 4,19 870,50 0,04 0,84 0,84 0,84 0,84 0,84 0,04

Progress / Prefinal Sounding Kali 5 - - Final Sounding

III PEKERJAAN FINAL


Mobilisasi dari Bojonegara-Belawan = 863 Nm
- 1 unit TSHD Nm 863 0,86 863 0,76 0,76
- 1 Set Clamshell Dredger Nm 863 0,95 863 0,84 0,84
Bobot Rencana Kontrak 100,00 100,00 1,33 0,47 2,06 2,34 4,68 3,64 3,96 3,49 3,49 3,54 3,54 3,54 3,54 3,51 3,52 3,52 3,52 3,51 3,51 3,34 3,55 3,56 3,59 2,82 2,82 2,34 2,34 2,34 2,34 2,34 2,34 2,34 2,34 0,86 -
Bobot Rencana Akumulatif 0 1,33 1,81 3,87 6,21 10,89 14,53 18,49 21,97 25,46 29,00 32,54 36,08 39,62 43,13 46,65 50,18 53,70 57,21 60,72 64,07 67,62 71,18 74,77 77,59 80,40 82,74 85,09 87,43 89,77 92,11 94,46 96,80 99,14 100
Realisasi Berdasarkan Bobot Kontrak 1,58 2,63 4,22 5,89 7,13 9,40 12,27 15,40 17,59 19,92
Realisasi Berdasarkan Bobot Addendum 1 0 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 3,11 3,01 3,63 3,73 1,04 5,89 4,25 3,90 7,77 9,03 7,45 6,13 6,81 7,86 8,06
Akumulasi realisai berdasarkan Adendum 1 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 18,90 20,52 22,45 24,64 27,51 29,48 32,03 35,21 38,14 41,04 43,61 45,50 47,45 49,41 51,37 52,72 53,80 54,09 56,41 59,51 62,52 66,14 69,87 70,92 76,80 81,06 84,95 92,73 101,76 109,21 115,34 122,16 130,01 138,1
(0,97) 2,91 5,15 7,04 12,80 18,94 23,50 26,74 30,67 35,63 41,68
Rencana Addendum 1 3,80 3,73 3,60 3,60 2,98 3,04 3,04 3,72 3,72 4,28 2,90 2,90 3,78 3,78 3,78 3,78 3,78 3,74 3,74 3,74 3,74 3,74 3,32
Rencana Akumulatif Addendum 1 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 20,41 24,15 27,75 31,35 34,34 37,37 40,41 44,14 47,86 52,14 55,03 57,93 61,71 65,49 69,27 73,05 76,83 80,56 84,30 88,03 91,77 95,51 98,82 100,0
Deviasi (1,51) (3,63) (5,30) (6,71) (6,83) (7,89) (8,38) (8,92) (9,71) (11,10) (11,42) (12,43) (14,26) (16,08) (17,90) (20,32) (23,02) (26,48) (27,89) (28,90) (29,25) (29,36) (28,95) (100,0)

Bobot Rencana Addendum II 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 2,73 3,01 3,63 3,73 2,01 2,01 2,01 2,01 2,01 2,89 2,89 2,89 2,89 2,89 2,01 2,01 0,42 1,18
Bobot Rencana Akumulatif Addendum II 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 18,90 20,52 22,45 24,64 27,51 29,48 32,03 35,21 38,14 41,04 43,61 45,50 47,45 49,41 51,37 52,72 53,80 54,09 56,41 59,13 62,52 66,15 69,87 71,88 73,89 75,90 77,91 79,92 82,82 85,71 88,60 91,49 94,38 96,39 98,40 98,82 100,0
Realisasi Berdasarkan Bobot Addendum II 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 2,73 3,01 3,63 3,73 70,92 76,80 81,06 84,95 92,73 101,76 109,21 115,34 122,16 130,01 138,1
(0,97) 2,91 5,15 7,04 12,80 18,94 23,50 26,74 30,67 35,63 41,68

Bobot Rencana Addendum III 1,01 1,01 1,01 1,89 2,02 1,89 1,89 1,89 1,05 1,01 1,01 1,01 1,84 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 - 0,76 -
Bobot Rencana Akumulatif Addendum III 66,64 67,65 68,66 69,66 71,55 73,57 75,46 77,35 79,24 80,28 81,29 82,30 83,30 85,15 86,15 87,16 88,17 89,17 90,18 91,19 92,19 93,20 94,21 95,21 96,22 97,23 98,23 99,24 99,24 100,00 100,00
Realisasi Berdasarkan Bobot Addendum II 66,64 71,12 78,73 85,99 93,66 101,67 108,76 114,55 121,45 121,45 124,60 125,25 125,95 126,83 129,43 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78 130,62 130,62 130,62 130,62
Deviasi 3,47 10,07 16,33 22,11 28,10 33,30 37,20 42,21 41,16 43,31 42,95 42,65 41,68 43,27 42,62 41,61 40,61 39,60 38,59 37,59 36,58 35,57 34,57 33,56 32,55 32,38 31,38 31,38 30,62

Belawan, 18 Desember 2021

Disetujui oleh Diperiksa oleh Dibuat oleh


Pengawas Pekerjaan Konsultan Pengawas Kontraktor Pelaksana
PT Pelabuhan Indonesi I (persero) PT Muara Consult PT Bina Mitra IndoSejahtera

Mhd. Zulpan Kalam Sambiring Sundra


Project Manager Fasilitas Direktur Project Manager
JADWAL PELAKSANAAN (KURVA S) BULAN XVI

Proyek : Pengerukan Kolam dan Alur Pelayaran Pelabuhan Belawan


Lokasi : Belawan, Sumatera Utara
Durasi : 504 Hari
Waktu (minggu)
NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
BOBOT KET.
VOLUME Bobot VOLUME Bobot SISA VOLUME
URAIAN SAT SISA ADD 01 Agus - 02 03 Agus - 09 10 Agus - 16 17 Agus - 23 24 Agus - 30 31 Agus - 06 07 Sept - 13 14 Sept - 20 21 Sept - 27 28 Sept - 04 05 Okt - 11 Okt 12 Okt - 18 Okt 19 Okt - 25 Okt 26 Okt - 01 Nov 02 Nov - 08 Nov 09 Nov - 15 Nov 16 Nov - 22 Nov 23 Nov - 29 Nov 30 Nov - 06 Des 07 Des - 13 Des 14 Des - 20 Des 21 Des - 27 Des 28 Des'20 - 03 04 Jan - 10 Jan 11 Jan - 17 Jan 18 Jan - 24 Jan 25 Jan - 31 Jan 01 Feb - 07 Feb 08 Feb - 14 Feb 15 Feb - 21 Feb 22 Feb - 28 Feb 01 Mar - 07 Mar 08 Mar - 14 Mar 15 Mar - 21 Mar 22 Mar - 28 Mar 29 Mar - 04 Apr 05 Apr - 11 Apr 12 Apr - 18 Apr 119 Apr - 25 26 Apr - 02 Mei 03 Mei - 9 Mei 10 Mei - 16 Mei 17 Mei - 23 Mei 24 Mei - 30 Mei 31 Mei - 06 Jun 07 Jun - 13 Jun 14 Jun - 20 Jun 21 Jun - 27 Jun 28 Jun - 04 Jul 05 Juli - 11 Juli 12 Juli - 18 19 Juli - 25 Juli 26 Juli - 01 02 Agus - 08 09 Agus - 15 16 Agus - 22 23 Agus - 29 30 Agus - 05 06 Sept - 12 13 Sept - 19 20 Sept - 26 27 Sept - 03 04 Okt - 10 Okt 11 Okt - 17 Okt 18 Okt - 24 Okt 25 Okt - 31 Okt 01 Nov - 07 Nov 08 Nov - 14 Nov 15 Nov - 21 Nov 22 Nov - 28 Nov 29 Nov - 04 Des 05 Des - 11 Des 12 Des - 18 Des
KONTRAK (%) ADENDUM (%) ADD III
III (%) Agus 2020 Agus 2020 Agus 2020 Agus 2023 Agus 2020 Sept 2020 Sept 2020 Sept 2020 Sept 2020 Okt 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 Jan 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 Apr 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 Juli 2021 2021 Agus 2021 Agus 2021 Agus 2021 Agus 2021 Agus 2021 Sept 2021 Sept 2021 Sept 2021 Sept 2021 Okt 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
I PEKERJAAN PERSIAPAN
1 Mobilisasi dari Bojonegara-Belawan = 863 Nm
- 1 unit TSHD Nm 863 0,86 863 0,76 0,38 0,38
- 1 Set Clamshell Dredger Nm 863 0,95 863 0,84 0,84
- Predredge Sounding Kali 1 1
II PELAKSANAAN PEKERJAAN 0
Pengerukan alur pelayaran Belawan
m³ 1.307.931,80 67,93 1.454.829,35 66,64 593.399,00 27,18 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01
dengan menggunakan TSHD

Pengerukan alur pelabuhan citra


dengan menggunakan: m³ 161.504,85 134.072,75
A A A
- TSHD m³ 8,39 66.002,65 6,14 2.844,00 0,13 0,05 0,35 0,45 0,89 1,09 1,09 0,99 0,89 0,33 -
D D D
0,13

m³ 68.070,98
- Clamshell Dredger
D D D
Kolam Pelabuhan Belawan
REALISASI S.D 30 Mei 2021
- Kolam Dermaga IKD 1 m³ 21.484,10 1,17 12.400,30 0,60 0,04 0,55 E E E
- Kolam Dermaga IKD 2 m³ 58.980,90 3,21 55.240,90 2,65 0,29 0,79 0,83 0,04 0,35 0,35
N N N
- Kolam Dermaga IKD 3 m³ 67.577,40 3,68 63.365,50 3,04 0,41 - 0,91 1,24 0,47

- Kolam Dermaga Citra (201 - 203) m³ 63.021,20 3,43 56.815,00 2,73 0,61 0,26 1,37 0,49 D KURVA S RENCANA KONTRAK D D
- Kolam Dermaga 101 - 103 m³ 34.843,60 1,90 32.030,90 1,54 0,12 0,71 0,71
U U U
- Kolam Dermaga BICT m³ 26.263,60 1,43 20.847,20 1,00 1,00

- Kolam Dermaga TPKDB m³ 41.252,20 2,24 34.435,50 1,65 M 0,83 0,83


KURVA S RENCANA M KURVA S RENCANA ADDENDUM II M KURVA S RENCANA ADDENDUM III
- Kolam Dermaga Ex. Rukindo m³ 20.515,00 1,12 15.606,80 0,75 0,12 0,41 - 0,17 0,04
- Kolam Dermaga Belawan Lama
m³ 7.119,20 0,39 5.861,90 0,28 0,14 0,14
(Gudang 002 - 006)
- Kolam Dermaga 200 (Ex. Dermaga I 2 3
Ferry) m³ 9.378,60 0,51 3.240,60 0,16 0,16

- Kolam Dermaga Shore Base m³ 18.482,20 1,01 21.629,30 1,04 0,04 0,95 0,04

- Kolam Dermaga Phase I 96.258,80 4,41 96.258,80 4,41 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88

- Kolam Dermaga Phase II 87.400,50 4,19 870,50 0,04 0,84 0,84 0,84 0,84 0,84 0,04

Progress / Prefinal Sounding Kali 5 - - Final Sounding

III PEKERJAAN FINAL


Mobilisasi dari Bojonegara-Belawan = 863 Nm
- 1 unit TSHD Nm 863 0,86 863 0,76 0,76
- 1 Set Clamshell Dredger Nm 863 0,95 863 0,84 0,84
Bobot Rencana Kontrak 100,00 100,00 1,33 0,47 2,06 2,34 4,68 3,64 3,96 3,49 3,49 3,54 3,54 3,54 3,54 3,51 3,52 3,52 3,52 3,51 3,51 3,34 3,55 3,56 3,59 2,82 2,82 2,34 2,34 2,34 2,34 2,34 2,34 2,34 2,34 0,86 -
Bobot Rencana Akumulatif 0 1,33 1,81 3,87 6,21 10,89 14,53 18,49 21,97 25,46 29,00 32,54 36,08 39,62 43,13 46,65 50,18 53,70 57,21 60,72 64,07 67,62 71,18 74,77 77,59 80,40 82,74 85,09 87,43 89,77 92,11 94,46 96,80 99,14 100
Realisasi Berdasarkan Bobot Kontrak 1,58 2,63 4,22 5,89 7,13 9,40 12,27 15,40 17,59 19,92
Realisasi Berdasarkan Bobot Addendum 1 0 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 3,11 3,01 3,63 3,73 1,04 5,89 4,25 3,90 7,77 9,03 7,45 6,13 6,81 7,86 8,06
Akumulasi realisai berdasarkan Adendum 1 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 18,90 20,52 22,45 24,64 27,51 29,48 32,03 35,21 38,14 41,04 43,61 45,50 47,45 49,41 51,37 52,72 53,80 54,09 56,41 59,51 62,52 66,14 69,87 70,92 76,80 81,06 84,95 92,73 101,76 109,21 115,34 122,16 130,01 138,1
(0,97) 2,91 5,15 7,04 12,80 18,94 23,50 26,74 30,67 35,63 41,68
Rencana Addendum 1 3,80 3,73 3,60 3,60 2,98 3,04 3,04 3,72 3,72 4,28 2,90 2,90 3,78 3,78 3,78 3,78 3,78 3,74 3,74 3,74 3,74 3,74 3,32
Rencana Akumulatif Addendum 1 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 20,41 24,15 27,75 31,35 34,34 37,37 40,41 44,14 47,86 52,14 55,03 57,93 61,71 65,49 69,27 73,05 76,83 80,56 84,30 88,03 91,77 95,51 98,82 100,0
Deviasi (1,51) (3,63) (5,30) (6,71) (6,83) (7,89) (8,38) (8,92) (9,71) (11,10) (11,42) (12,43) (14,26) (16,08) (17,90) (20,32) (23,02) (26,48) (27,89) (28,90) (29,25) (29,36) (28,95) (100,0)

Bobot Rencana Addendum II 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 2,73 3,01 3,63 3,73 2,01 2,01 2,01 2,01 2,01 2,89 2,89 2,89 2,89 2,89 2,01 2,01 0,42 1,18
Bobot Rencana Akumulatif Addendum II 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 18,90 20,52 22,45 24,64 27,51 29,48 32,03 35,21 38,14 41,04 43,61 45,50 47,45 49,41 51,37 52,72 53,80 54,09 56,41 59,13 62,52 66,15 69,87 71,88 73,89 75,90 77,91 79,92 82,82 85,71 88,60 91,49 94,38 96,39 98,40 98,82 100,0
Realisasi Berdasarkan Bobot Addendum II 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 2,73 3,01 3,63 3,73 70,92 76,80 81,06 84,95 92,73 101,76 109,21 115,34 122,16 130,01 138,1
(0,97) 2,91 5,15 7,04 12,80 18,94 23,50 26,74 30,67 35,63 41,68

Bobot Rencana Addendum III 1,01 1,01 1,01 1,89 2,02 1,89 1,89 1,89 1,05 1,01 1,01 1,01 1,84 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 - 0,76 -
Bobot Rencana Akumulatif Addendum III 66,64 67,65 68,66 69,66 71,55 73,57 75,46 77,35 79,24 80,28 81,29 82,30 83,30 85,15 86,15 87,16 88,17 89,17 90,18 91,19 92,19 93,20 94,21 95,21 96,22 97,23 98,23 99,24 99,24 100,00 100,00
Realisasi Berdasarkan Bobot Addendum II 66,64 71,12 78,73 85,99 93,66 101,67 108,76 114,55 121,45 121,45 124,60 125,25 125,95 126,83 129,43 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78 130,62
Deviasi 3,47 10,07 16,33 22,11 28,10 33,30 37,20 42,21 41,16 43,31 42,95 42,65 41,68 43,27 42,62 41,61 40,61 39,60 38,59 37,59 36,58 35,57 34,57 33,56 32,55 32,38

Belawan, 29 November 2021

Disetujui oleh Diperiksa oleh Dibuat oleh


Pengawas Pekerjaan Konsultan Pengawas Kontraktor Pelaksana
PT Pelabuhan Indonesi I (persero) PT Muara Consult PT Bina Mitra IndoSejahtera

Mhd. Zulpan Kalam Sambiring Sundra


Project Manager Fasilitas Direktur Project Manager
JADWAL PELAKSANAAN (KURVA) BULAN XV

Proyek : Pengerukan Kolam dan Alur Pelayaran Pelabuhan Belawan


Lokasi : Belawan, Sumatera Utara
Durasi : 504 Hari
Waktu (minggu)
NO. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
BOBOT KET.
VOLUME Bobot VOLUME Bobot SISA VOLUME
URAIAN SAT SISA ADD 01 Agus - 02 03 Agus - 09 10 Agus - 16 17 Agus - 23 24 Agus - 30 31 Agus - 06 07 Sept - 13 14 Sept - 20 21 Sept - 27 28 Sept - 04 05 Okt - 11 Okt 12 Okt - 18 Okt 19 Okt - 25 Okt 26 Okt - 01 Nov 02 Nov - 08 Nov 09 Nov - 15 Nov 16 Nov - 22 Nov 23 Nov - 29 Nov 30 Nov - 06 Des 07 Des - 13 Des 14 Des - 20 Des 21 Des - 27 Des 28 Des'20 - 03 04 Jan - 10 Jan 11 Jan - 17 Jan 18 Jan - 24 Jan 25 Jan - 31 Jan 01 Feb - 07 Feb 08 Feb - 14 Feb 15 Feb - 21 Feb 22 Feb - 28 Feb 01 Mar - 07 Mar 08 Mar - 14 Mar 15 Mar - 21 Mar 22 Mar - 28 Mar 29 Mar - 04 Apr 05 Apr - 11 Apr 12 Apr - 18 Apr 119 Apr - 25 26 Apr - 02 Mei 03 Mei - 9 Mei 10 Mei - 16 Mei 17 Mei - 23 Mei 24 Mei - 30 Mei 31 Mei - 06 Jun 07 Jun - 13 Jun 14 Jun - 20 Jun 21 Jun - 27 Jun 28 Jun - 04 Jul 05 Juli - 11 Juli 12 Juli - 18 19 Juli - 25 Juli 26 Juli - 01 02 Agus - 08 09 Agus - 15 16 Agus - 22 23 Agus - 29 30 Agus - 05 06 Sept - 12 13 Sept - 19 20 Sept - 26 27 Sept - 03 04 Okt - 10 Okt 11 Okt - 17 Okt 18 Okt - 24 Okt 25 Okt - 31 Okt 01 Nov - 07 Nov 08 Nov - 14 Nov 15 Nov - 21 Nov 22 Nov - 28 Nov 29 Nov - 04 Des 05 Des - 11 Des 12 Des - 18 Des
KONTRAK (%) ADENDUM (%) ADD III
III (%) Agus 2020 Agus 2020 Agus 2020 Agus 2023 Agus 2020 Sept 2020 Sept 2020 Sept 2020 Sept 2020 Okt 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 2020 Jan 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 Apr 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 Juli 2021 2021 Agus 2021 Agus 2021 Agus 2021 Agus 2021 Agus 2021 Sept 2021 Sept 2021 Sept 2021 Sept 2021 Okt 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021 2021

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75
I PEKERJAAN PERSIAPAN
1 Mobilisasi dari Bojonegara-Belawan = 863 Nm
- 1 unit TSHD Nm 863 0,86 863 0,76 0,38 0,38
- 1 Set Clamshell Dredger Nm 863 0,95 863 0,84 0,84
- Predredge Sounding Kali 1 1
II PELAKSANAAN PEKERJAAN 0
Pengerukan alur pelayaran Belawan
m³ 1.307.931,80 67,93 1.454.829,35 66,64 593.399,00 27,18 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,90 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 2,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01
dengan menggunakan TSHD

Pengerukan alur pelabuhan citra


dengan menggunakan: m³ 161.504,85 134.072,75
A A A
- TSHD m³ 8,39 66.002,65 6,14 2.844,00 0,13 0,05 0,35 0,45 0,89 1,09 1,09 0,99 0,89 0,33 -
D D D
0,13

m³ 68.070,98
- Clamshell Dredger
D D D
Kolam Pelabuhan Belawan
REALISASI S.D 30 Mei 2021
- Kolam Dermaga IKD 1 m³ 21.484,10 1,17 12.400,30 0,60 0,04 0,55 E E E
- Kolam Dermaga IKD 2 m³ 58.980,90 3,21 55.240,90 2,65 0,29 0,79 0,83 0,04 0,35 0,35
N N N
- Kolam Dermaga IKD 3 m³ 67.577,40 3,68 63.365,50 3,04 0,41 - 0,91 1,24 0,47

- Kolam Dermaga Citra (201 - 203) m³ 63.021,20 3,43 56.815,00 2,73 0,61 0,26 1,37 0,49 D KURVA S RENCANA KONTRAK D D
- Kolam Dermaga 101 - 103 m³ 34.843,60 1,90 32.030,90 1,54 0,12 0,71 0,71
U U U
- Kolam Dermaga BICT m³ 26.263,60 1,43 20.847,20 1,00 1,00

- Kolam Dermaga TPKDB m³ 41.252,20 2,24 34.435,50 1,65 M 0,83 0,83


KURVA S RENCANA M KURVA S RENCANA ADDENDUM II M KURVA S RENCANA ADDENDUM III
- Kolam Dermaga Ex. Rukindo m³ 20.515,00 1,12 15.606,80 0,75 0,12 0,41 - 0,17 0,04
- Kolam Dermaga Belawan Lama
m³ 7.119,20 0,39 5.861,90 0,28 0,14 0,14
(Gudang 002 - 006)
- Kolam Dermaga 200 (Ex. Dermaga I 2 3
Ferry) m³ 9.378,60 0,51 3.240,60 0,16 0,16

- Kolam Dermaga Shore Base m³ 18.482,20 1,01 21.629,30 1,04 0,04 0,95 0,04

- Kolam Dermaga Phase I 96.258,80 4,41 96.258,80 4,41 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88 0,88

- Kolam Dermaga Phase II 87.400,50 4,19 870,50 0,04 0,84 0,84 0,84 0,84 0,84 0,04

Progress / Prefinal Sounding Kali 5 - - Final Sounding

III PEKERJAAN FINAL


Mobilisasi dari Bojonegara-Belawan = 863 Nm
- 1 unit TSHD Nm 863 0,86 863 0,76 0,76
- 1 Set Clamshell Dredger Nm 863 0,95 863 0,84 0,84
Bobot Rencana Kontrak 100,00 100,00 1,33 0,47 2,06 2,34 4,68 3,64 3,96 3,49 3,49 3,54 3,54 3,54 3,54 3,51 3,52 3,52 3,52 3,51 3,51 3,34 3,55 3,56 3,59 2,82 2,82 2,34 2,34 2,34 2,34 2,34 2,34 2,34 2,34 0,86 -
Bobot Rencana Akumulatif 0 1,33 1,81 3,87 6,21 10,89 14,53 18,49 21,97 25,46 29,00 32,54 36,08 39,62 43,13 46,65 50,18 53,70 57,21 60,72 64,07 67,62 71,18 74,77 77,59 80,40 82,74 85,09 87,43 89,77 92,11 94,46 96,80 99,14 100
Realisasi Berdasarkan Bobot Kontrak 1,58 2,63 4,22 5,89 7,13 9,40 12,27 15,40 17,59 19,92
Realisasi Berdasarkan Bobot Addendum 1 0 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 3,11 3,01 3,63 3,73 1,04 5,89 4,25 3,90 7,77 9,03 7,45 6,13 6,81 7,86 8,06
Akumulasi realisai berdasarkan Adendum 1 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 18,90 20,52 22,45 24,64 27,51 29,48 32,03 35,21 38,14 41,04 43,61 45,50 47,45 49,41 51,37 52,72 53,80 54,09 56,41 59,51 62,52 66,14 69,87 70,92 76,80 81,06 84,95 92,73 101,76 109,21 115,34 122,16 130,01 138,1
(0,97) 2,91 5,15 7,04 12,80 18,94 23,50 26,74 30,67 35,63 41,68
Rencana Addendum 1 3,80 3,73 3,60 3,60 2,98 3,04 3,04 3,72 3,72 4,28 2,90 2,90 3,78 3,78 3,78 3,78 3,78 3,74 3,74 3,74 3,74 3,74 3,32
Rencana Akumulatif Addendum 1 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 20,41 24,15 27,75 31,35 34,34 37,37 40,41 44,14 47,86 52,14 55,03 57,93 61,71 65,49 69,27 73,05 76,83 80,56 84,30 88,03 91,77 95,51 98,82 100,0
Deviasi (1,51) (3,63) (5,30) (6,71) (6,83) (7,89) (8,38) (8,92) (9,71) (11,10) (11,42) (12,43) (14,26) (16,08) (17,90) (20,32) (23,02) (26,48) (27,89) (28,90) (29,25) (29,36) (28,95) (100,0)

Bobot Rencana Addendum II 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 2,73 3,01 3,63 3,73 2,01 2,01 2,01 2,01 2,01 2,89 2,89 2,89 2,89 2,89 2,01 2,01 0,42 1,18
Bobot Rencana Akumulatif Addendum II 1,39 2,32 3,72 5,20 6,29 8,29 10,82 13,58 15,20 16,61 18,90 20,52 22,45 24,64 27,51 29,48 32,03 35,21 38,14 41,04 43,61 45,50 47,45 49,41 51,37 52,72 53,80 54,09 56,41 59,13 62,52 66,15 69,87 71,88 73,89 75,90 77,91 79,92 82,82 85,71 88,60 91,49 94,38 96,39 98,40 98,82 100,0
Realisasi Berdasarkan Bobot Addendum II 1,39 0,93 1,40 1,48 1,09 2,01 2,53 2,76 1,62 1,41 2,29 1,62 1,93 2,20 2,87 1,97 2,55 3,18 2,93 2,89 2,57 1,89 1,95 1,96 1,96 1,36 1,08 0,28 2,32 2,73 3,01 3,63 3,73 70,92 76,80 81,06 84,95 92,73 101,76 109,21 115,34 122,16 130,01 138,1
(0,97) 2,91 5,15 7,04 12,80 18,94 23,50 26,74 30,67 35,63 41,68

Bobot Rencana Addendum III 1,01 1,01 1,01 1,89 2,02 1,89 1,89 1,89 1,05 1,01 1,01 1,01 1,84 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 1,01 - 0,76 -
Bobot Rencana Akumulatif Addendum III 66,64 67,65 68,66 69,66 71,55 73,57 75,46 77,35 79,24 80,28 81,29 82,30 83,30 85,15 86,15 87,16 88,17 89,17 90,18 91,19 92,19 93,20 94,21 95,21 96,22 97,23 98,23 99,24 99,24 100,00 100,00
Realisasi Berdasarkan Bobot Addendum II 66,64 71,12 78,73 85,99 93,66 101,67 108,76 114,55 121,45 121,45 124,60 125,25 125,95 126,83 129,43 129,78 129,78 129,78 129,78 129,78 129,78 129,78 129,78
Deviasi 3,47 10,07 16,33 22,11 28,10 33,30 37,20 42,21 41,16 43,31 42,95 42,65 41,68 43,27 42,62 41,61 40,61 39,60 38,59 37,59 36,58 35,57

Belawan, 01 November 2021

Disetujui oleh Diperiksa oleh Dibuat oleh


Pengawas Pekerjaan Konsultan Pengawas Kontraktor Pelaksana
PT Pelabuhan Indonesi I (persero) PT Muara Consult PT Bina Mitra IndoSejahtera

Mhd. Zulpan Kalam Sambiring Sundra


Project Manager Fasilitas Direktur Project Manager