RENCANA ANGGARAN BIAYA 013/RAB/INFRA/KAL/VII/2019

PEMINDAHAN AREA PARKIR GAMA


GAMA RESTO
BUKIT SEMARANG BARU

NO ITEM PEKERJAAN VOL HARSAT TOTAL HARGA

Pekerjaan Paving Gama Tahap 1


1 Bongkar Paving 295.5 m2 7,000 2,068,500.00
2 Bongkar kanstein nok 49.7 m1 5,000 248,500.00
3 Gelar LPB T.30 cm 88.65 m3 315,000 27,924,750.00
4 Gelar Abu batu 4+1 cm 14.775 m3 250,000 3,693,750.00
5 Pasang Paving 295.5 m2 10,000 2,955,000.00
6 Pasang Kanstein nok 49.7 m1 10,000 497,000.00
7 Galian Tanah 30.17 m3 40,000 1,206,800.00
8 Biaya Langsir 1 LS 1,000,000 1,000,000.00
TOTAL 39,594,300.00
DIBULATKAN 39,594,000.00

Semarang, ###
PT. KARYADEKA ALAM LESTARI
Diketahui : Dibuat Oleh :

Wawan Susilo Suwondo Garit Dani


Mngr. Proyek Asc. Mngr. Proyek Estimator
Disetujui :

Andy Iriawan M. Aryabhekti


Direktur Assc. Direktur
RENCANA ANGGARAN BIAYA 03/RAB/INFRA/KAL/VII/2019
PEKERJAAN PENAMBAHAN PAVING AREAL PARKIR
GAMA RESTO
BUKIT SEMARANG BARU

NO ITEM PEKERJAAN VOLUME HARGA SATUAN TOTAL HARGA

1 Bongkar paving +langsir dari Mall 198.9 m2 15,000 2,983,500.00


2 Bongkar paving area gama 160 m 2
7,000 1,120,000.00
3 Bongkar +pasang kembali kanstein nok 21.7 m 1
15,000 325,500.00
4 Pasang kanstein nok baru 48.3 m1 45,000 2,173,500.00
5 Gelar LPB Tebal 30 cm 227.85 m 3
325,000 74,051,250.00
6 Gelar Abu batu Tebal 5cm 37.975 m 3
270,000 10,253,250.00
7 Pembelian Paving Tebal 6cm K -300 400.6 m2 85,000 34,051,000.00
8 Pasang Paving 759.5 m2 10,000 7,595,000.00
9 Perataan tanah /pembentukan jalan 379.75 m 3
35,000 13,291,250.00
10 Slooping tanah pinggir berm 1 LS 1,000,000 1,000,000.00
TOTAL 146,844,250.00
DIBULATKAN 146,844,000.00

Semarang, ###
PT. KARYADEKA ALAM LESTARI
Diketahui : Dibuat Oleh :

Wawan Susilo Suwondo Garit Dani


Mngr. Proyek Asc. Mngr. Proyek Estimator
Disetujui :

Andy Iriawan M. Aryabhekti


Direktur Assc. Direktur