( RAB )
I PEK. PERSIAPAN
1 Pek.Pembersihan M2 18.00 17,307.50 311,535.00
2 Pembuatan 1 m2 steger/perancah dari bambu M 4.80 416,805.43 2,000,666.04
2,312,201.04
II PEKERJAAN TANAH DAN PONDASI
1 Pek.Galian Tanah Biasa M3 9.89 69,825.00 690,639.08
2 Pek.Pondasi Batu Belah 1Sp:3PP M2 33.97 862,927.09 29,310,707.79
30,001,346.86
II PEK.PELINGGIH
1 Saka exsiting di ukir SET 3.00 500,000.00 1,500,000.00
2 Canggahwang cepaka diukir SET 3.00 600,000.00 1,800,000.00
3 Lambang mayeng 11/12 cepaka ukir gempong M 7.00 2,300,000.00 16,100,000.00
4 Lambang mayeng 11/12 cepaka kekupakan M 10.00 900,000.00 9,000,000.00
5 Sineb 6/10x400 finish politur BTG 5.00 260,000.00 1,300,000.00
6 Pemade-pemucu kamper 6/10x400 profil politur finish BTG 8.00 360,000.00 2,880,000.00
7 Iga-iga cepaka 5/7x300 profil politur finish BTG 48.00 100,000.00 4,800,000.00
8 Lambresering 1/9x400 cepaka politur finish BTG 10.00 70,000.00 700,000.00
9 Usuk grantang maling kamper 4/6300 BTG 24.00 85,000.00 2,040,000.00
10 Dedeleg kekupakan politur finish SET 1.00 500,000.00 500,000.00
11 Kolong ukir & prada (ring-ring, kolong,pepayasan) M 18.00 750,000.00 13,500,000.00
12 Ijuk geles M² 18.00 2,650,000.00 47,700,000.00
13 Setel Kayu LS 1.00 6,000,000.00 6,000,000.00
14 Finishing prada dan politur LS 1.00 8,500,000.00 8,500,000.00
15 Restorasi bongkar-pasang bebaturan, luluh tanah,pengresek LS 1.00 72,000,000.00 72,000,000.00
16 Pas. patung naga + tatakan ukir Unit 2.00 12,000,000.00 24,000,000.00
212,320,000.00
III PEK.ARSITEKTUR
1 Pemasangan lantai ubin granit ukuran 60 cm x 60 cm M2 15.70 433,822.84 6,811,018.66
6,811,018.66
TERBILANG : DUA RATUS LIMA PULUH SATU JUTA EMPAT RATUS EMPAT PULUH EMPAT RIBU RUPIAH
Ketua Sekretaris
Mengetahui,
Kelihan Kelihan
Banjar Sima Banjar Tegalkuwalon