Anda di halaman 1dari 1

Analisa EI-633a

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

NAMA PAKET : Pembangunan Jembatan Kamp. Muri - Kwatisore (Bts. Provinsi Papua) I

PROP / KAB / KODYA : Papua Barat / Kab. Teluk Wondama


ITEM PEMBAYARAN NO. : 6.3(3)
JENIS PEKERJAAN : Lataston Lapis Aus (HRS-WC)
SATUAN PEMBAYARAN : Ton

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.2410 20,571.43 4,956.97


2. Mandor (L03) Jam 0.0402 26,285.71 1,055.65

JUMLAH HARGA TENAGA 6,012.62

B. BAHAN

1. Agr Pch Mesin 5-10 & 10-15 (M92) M3 0.2704 160,000.00 43,266.67
2. Agr Pch Mesin 0 - 5 (M91) M3 0.1856 163,000.00 30,258.27
3 Pasir Halus (M01c) M3 0.2957 50,000.00 14,786.13
4 Semen (M12) Kg 18.7680 1,822.50 34,204.68
5 Aspal (M10) Kg 66.3000 14,300.00 948,090.00

JUMLAH HARGA BAHAN 1,070,605.75

C. PERALATAN
1. Wheel Loader E15 Jam 0.0047 540,826.58 2,553.79
2. AMP E01 Jam 0.0201 9,167,372.58 184,083.79
3. Genset E12 Jam 0.0201 432,522.25 8,685.19
4. Dump Truck E09 Jam 0.3718 489,457.24 182,003.13
5. Asphalt Finisher E02 Jam 0.0103 294,728.64 3,033.05
6. Tandem Roller E17a Jam 0.0105 468,218.25 4,906.70
7 P. Tyre Roller E18 Jam 0.0115 565,274.65 6,507.88
8 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 391,773.52

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 1,468,391.90


E. OVERHEAD & PROFIT 10.0 % x D 146,839.19
F. HARGA SATUAN PEKERJAAN ( D + E ) 1,615,231.09