RENCANA ANGGARAN BIAYA TENAGA KERJA PRODUKSI PER SHIPMENT

PT. ARYA ANUGERAH PRASETIA

JUMLAH BIAYA BIAYA TENAGA


NO BIAYA TENAGA KERJA SATUAN
ORANG TENAGA KERJA KERJA / BULAN
A. KANTOR
1 DIREKTUR UTAMA 1 Orang Rp 50,000,000 Rp 50,000,000
2 DIREKTUR UMUM 1 Orang Rp 30,000,000 Rp 30,000,000
3 ASISTEN DIREKTUR UMUM 1 Orang Rp 25,000,000 Rp 25,000,000
4 MANAGER KEUANGAN 1 Orang Rp 20,000,000 Rp 20,000,000
5 MANAGER OPERASIONAL 1 Orang Rp 20,000,000 Rp 20,000,000
6 ASISTEN MANAGER OPERASIONAL 1 Orang Rp 15,000,000 Rp 15,000,000
7 MANAGER MARKETING 1 Orang Rp 20,000,000 Rp 20,000,000
8 HRD 1 Orang Rp 15,000,000 Rp 15,000,000
9 HUMAS 1 Orang Rp 10,000,000 Rp 10,000,000
10 ADMIN KEUANGAN 1 Orang Rp 5,000,000 Rp 5,000,000
11 ADMIN PERKANTORAN 1 Orang Rp 5,000,000 Rp 5,000,000
12 DRIVER OFICE 2 Orang Rp 3,000,000 Rp 6,000,000
13 OFICE BOY 1 Orang Rp 2,000,000 Rp 2,000,000
B. Penambangan
1 KTT TEAM 13 1 TEAM $ 0.7 Rp 344,750,000
2 Operator Alat Berat 11 Orang Rp 7,000,000 Rp 77,000,000
3 Driver Dump Truck 18 Orang Rp 7,000,000 Rp 126,000,000
4 Terpal Man 6 Orang Rp 1,500,000 Rp 9,000,000
5 Checker 4 Orang Rp 2,000,000 Rp 8,000,000
6 Flag Man 4 Orang Rp 1,500,000 Rp 6,000,000
7 Kepala Peralatan 1 Orang Rp 6,000,000 Rp 6,000,000
8 A. Foreman Peralatan 2 Orang Rp 4,000,000 Rp 8,000,000
9 Genset 1 Orang Rp 2,500,000 Rp 2,500,000
10 Fuel/BBM 4 Orang Rp 2,500,000 Rp 10,000,000
11 ADM Project 1 Orang Rp 5,000,000 Rp 5,000,000
12 Logistic 1 Orang Rp 3,500,000 Rp 3,500,000
13 Captain Perahu (Jolloro) 2 Orang Rp 1,500,000 Rp 3,000,000

Sub Total 82 Rp 831,750,000