TOTAL ANGGARAN OPERASIONAL DAN JADWAL PELAKSANAAN PENAMBANGAN NIKEL PER 10.

000 WMT/BULAN
LOKASI PROJEC KEC. LANGGIKIMA KAB. KONAWE UTARA

1. TENAGA AHLI & HARIAN TEKNIS PERBULAN


No. Tenaga Kerja Jumlah Satuan Standart Gaji Total Keterangan
1 Produksi & Quality 1 Orang Rp 12,000,000 Rp 12,000,000 Tenaga Ahli
2 Grade Controll 2 Orang Rp 8,000,000 Rp 16,000,000 Tenaga Ahli
3 Support/logistic 1 Orang Rp 3,500,000 Rp 3,500,000 Tenaga Ahli
4 Administrasi 1 Orang Rp 4,000,000 Rp 4,000,000 Tenaga Ahli
5 Spv. External 1 Orang Rp 6,000,000 Rp 6,000,000 Tenaga Ahli
6 Humas 1 Orang Rp 4,000,000 Rp 4,000,000 Tenaga Lokal
7 Sampler & Preparasi 6 Orang Rp 3,000,000 Rp 18,000,000 Tenaga Lokal
8 Security/Wakar 2 Orang Rp 2,500,000 Rp 5,000,000 Tenaga Lokal
9 Driver Operasional 2 Orang Rp 3,000,000 Rp 6,000,000 Tenaga Lokal
10 Koki 2 Orang Rp 2,000,000 Rp 4,000,000 Tenaga Lokal
11 Laundry 2 Orang Rp 2,000,000 Rp 4,000,000 Tenaga Lokal
TOTAL Rp 82,500,000

2. OPERATION PER BULAN


No. Jenis Alat Jumlah Harga Satuan Waktu Operasi Tot Harga Keterangan
1 Excavator PC 200 4 Unit Rp. 275,000/Jam 800 Jam Rp 220,000,000 200 Jam/unit/Bulan
2 BBM Excavator PC 200_4 unit 600Ltr/Shift Rp. 21,000/ Ltr 30 Hari Rp 378,000,000 600 Ltr/hari(8Jam)/4 unit
3 Dump Truck 10 Roda 4 Unit Rp. 55,000,000/Unit 30 Hari Rp 220,000,000 Rp.55,000,000/Unit
4 BBM DT 10 Roda_4 Unit 240Ltr/Shift Rp. 21,000/ Ltr 30 Hari Rp 151,200,000 240 Ltr/hari(8Jam)/4 unit
5 Mobilisasi Ecavator 4 Unit 4 Unit Rp. 10,000,000/ Unit 3 Hari Rp 40,000,000 Rp.10,000,000/Unit
6 Mobilisasi DT 10 Roda_4 Unit 4 Unit Rp. 2,500,000/ Unit 3 Hari Rp 10,000,000 Rp.2,500,000/Unit
7 Mobil LV 4 WD 2 Unit Rp. 25,000,000/Unit 30 Hari Rp 40,000,000 Operasional Lapangan
8 Mobil Avanza 1 Unit Rp. 7,500,000 30 Hari Rp 7,500,000 Operasional & Pengurusan
9 BBM Mobil Operasional 40 Liter/Hari Rp. 9,000/ Ltr 30 Hari Rp 10,800,000 30 Ltr/hari/3 unit
10 Logistik LS Rp. 1,000,000/Hari 30 Hari Rp 30,000,000 Rp.1,000,000/Hari
11 Biaya Tak Terduga LS Rp. - 30 Hari Rp 15,000,000 Rp.500,000/Hari
TOTAL Rp 1,122,500,000
TOTAL ANGGARAN OPERASIONAL
No. Jenis Anggaran Total Anggaran
1. Tenaga Ahli dan Harian Rp 82,500,000
2. Operation Rp 1,122,500,000
Total Rp 1,205,000,000

JADWAL PELAKSANAAN
M1 M2 M3 M4 M5
NO AKTIFITAS
H2 H3 H4 H5 H6 H7 H2 H3 H4 H5 H6 H7 H2 H3 H4 H5 H6 H7 H2 H3 H4 H5 H6 H7 H2 H3
H1 H1 H1 H1 H1
1 Persiapan
2 Mobilisasi
3 Produksi/Hauling Ore
4 Barging

Ket :
M = Minggu
H = Hari